The Predictability Index
The Predictability Index
Construction
Industry Implementation Resource 291-3
Institute®
CII Member Companies
Abbott AMEC
Air Products and Chemicals AZCO
Ameren Corporation Alstom Power
American Transmission Company Audubon Engineering Company
Anglo American Baker Concrete Construction
Anheuser-Busch InBev Barton Malow Company
Aramco Services Company Bechtel Group
ArcelorMittal Bentley Systems
Architect of the Capitol Bilfinger Industrial Services
BP America Black & Veatch
CITGO Petroleum Corporation Burns & McDonnell
Cameco Corporation CB&I
Cargill CCC Group
Chevron CDI Engineering Solutions
ConocoPhillips CH2M HILL
Consolidated Edison Company of New York CSA Central
DTE Energy Coreworx
The Dow Chemical Company Day & Zimmermann
DuPont Dresser-Rand Company
Eastman Chemical Company eProject Management
Ecopetrol Emerson Process Management
Eskom Holdings SOC Faithful+Gould
ExxonMobil Corporation Fluor Corporation
General Electric Company Foster Wheeler USA Corporation
General Motors Corporation GS Engineering & Construction Corporation
GlaxoSmithKline Gross Mechanical Contractors
Global Infrastructure Partners Hargrove Engineers + Constructors
Huntsman Corporation Hatch
Intel Corporation Hilti Corporation
International Paper IHI E&C International Corporation
Irving Oil Limited IHS
Kaiser Permanente Industrial Contractors Skanska
Koch Industries International Rivers Consulting
Eli Lilly and Company JMJ Associates
Linde North America JV Driver Projects
LyondellBasell Jacobs
Marathon Oil Corporation KBR
National Aeronautics & Space Administration Kiewit Corporation
NOVA Chemicals Corporation Kvaerner North American Construction
Occidental Petroleum Corporation Lauren Engineers & Constructors
Ontario Power Generation Leidos Constructors, LLC
Petroleo Brasileiro S/A - Petrobras Matrix Service Company
Petroleos Mexicanos McCarthy Building Companies
Petroliam Nasional Berhad McDermott International
Phillips 66 Midwest Steel
Praxair Parsons
The Procter & Gamble Company Pathfinder
Public Service Electric & Gas Company POWER Engineers
Reliance Industries Limited (RIL) Quality Execution
SABIC - Saudi Basic Industries Corporation Richard Industrial Group
Sasol Technology The Robins & Morton Group
Shell Global Solutions US S&B Engineers and Constructors
Smithsonian Institution SKEC USA
Southern Company SNC-Lavalin
Statoil ASA Technip
SunCoke Energy Tenova
Teck Resources Limited TOYO-SETAL Engenharia
Tennessee Valley Authority URS Corporation
TransCanada Corporation Victaulic Company
U.S. Army Corps of Engineers WESCO International
U.S. Department of Commerce/NIST/ Walbridge
Engineering Laboratory Wanzek Construction
U.S. Department of Defense/Tricare Wilhelm Construction
Management Activity Willbros United States Holdings
U.S. Department of Energy Wood Group Mustang
U.S. Department of Health and Human Services WorleyParsons
U.S. Department of State Yates Construction
U.S. Department of Veterans Affairs Zachry Holdings
U.S. General Services Administration Zurich
Vale
The Williams Companies
The Predictability Index ―
Benchmarking Project Outcome Predictions
January 2014
© 2013 Construction Industry Institute™
CII members may reproduce and distribute this work internally in any medium at no cost to internal recipients. CII members
are permitted to revise and adapt this work for their internal use, provided an informational copy is furnished to CII.
Available to non-members by purchase; however, no copies may be made or distributed and no modifications may be
made without prior written permission from CII. Contact CII at http://construction-institute.org/catalog.htm to purchase
copies. Volume discounts may be available.
All CII members, current students, and faculty at a college or university are eligible to purchase CII products at member
prices. Faculty and students at a college or university may reproduce and distribute this work without modification for
educational use.
1. Introduction 1
CII established Research Team 291 to help project teams produce more reliable project
cost and schedule forecasts. To do this, the team worked to isolate the factors that
promote accurate, timely, and consistent project outcome predictions. Having such
reliable forecasts empowers project teams to adopt appropriate mitigation actions
sooner than they would with faulty predictions. This ability to be proactive, rather than
reactive, can significantly improve a team’s ability to minimize the deviations between
predicted and actual outcomes. For example, while the early recognition that the
baseline cost of a project has been significantly underestimated cannot guarantee
meeting cost targets at project completion, it can enable the project team to proactively
address and improve cost performance. Conversely, the early recognition that a
project’s baseline cost has been significantly overestimated enables organizations to
invest the overcommitted funds as early as possible in other financial endeavors in
order to fulfill the expected rate of return. A timely and proactive response to external
events leads to earlier and more accurate predictions of project outcomes. Indeed,
improved predictability enables project teams to address project performance in a
proactive and timely manner and, thus, increase value. While project teams should not
be expected to eliminate all surprises, they can actually mitigate the potential negative
effects of such surprises by recognizing them early and producing timely information
on them. Unexpected events, whatever their quantity or magnitude, can always be
properly managed with the right people, processes, and behaviors.
Because a project team’s response to such events can make such a difference, its
cost and schedule performance must be evaluated on the basis of its ability to mitigate
deviations through the timely prediction of cost and schedule outcomes—as opposed
to the prevalent practice of basing evaluations on the magnitude of the final deviations
alone. However, evaluating how effectively (i.e., how early and how accurately) a team
forecasts cost and schedule project outcomes is not a common industry practice.
Indeed, to date, the industry has not had a method or tool to measure a team’s ability
to make timely and accurate project outcome predictions.
To address this lack, RT 291 developed the Predictability Index (PI), a metric that enables
organizations to assess and benchmark their predictability efforts on completed projects.
For a given project, the lower the Predictability Index is, the better the predictability
performance. The Predictability Index is expressed as the sum of cost and schedule
predictability measures, as Chapter 2 explains.
1
1: Introduction
Chapter 2 also defines the Predictability Index and its components, while Chapter 3
provides guidance on making PI assessments and interpreting PI values. Chapter 4
provides step-by-step instructions for using the PI tool.
2
2
The Predictability Index
This chapter discusses the equations that underlie the Predictability Index (PI) measures
and their meaning. Equation 1 expresses the PI as the sum of cost and schedule
predictability measures.
These cost and schedule predictability measures distinctly assess the cost and
schedule forecasting errors along the project completion timeline as the product of the
normalized timeliness error times the absolute deviation error (expressed in percentage
of deviation). (See Equations 2 and 3.)
The computation of these two error components—deviation and timeliness—for cost and
time predictability is produced as follows. First, the absolute values for the percentage
of cost and time deviations are represented with the pair of equations immediately
below. (See Equations 4 and 5.) The percentage of deviation is measured in absolute
(positive) values and, hence, theoretically ranges from “0” to any percent deviation
value, eventually going beyond 100 percent.
Equation 4
Equation 5
3
2: The Predictability Index
The normal timeliness error accounts for how timely the cost and schedule predictions
were along the project completion timeline, regardless of the magnitude of the final
deviation. In short, getting to the correct outcome sooner, whatever that outcome
might actually be, is much better than being surprised later when no mitigation actions
are possible. The normal timeliness error is independently computed for cost and
schedule predictions based on the definition of a normalized or unitary (equal to 1)
deviation. This unitary deviation corresponds to the difference between baseline and
completion values. Based on the unitary deviation, the normal timeliness error is equal
to the area above and/or below the actual outcome value at project completion. In
Figure 1, the area chart for Project A conceptually illustrate the computation of the
normalized cost timeliness component for a situation in which all forecasted costs
had been underestimated. It shows that, in such a situation, the area of error is strictly
below the actual total installed cost.
In the figure, Project A is assumed to be an early and accurate predictor of the final
project cost, while Project B is assumed to recognize the actual project cost growth
very late in the project execution. Thus, Project B experiences large errors between
forecasted and actual performance until late in its project execution. As reflected in
the Cost Predictability expression, at equal percentages of cost deviations, Project A
is a much better predictor of cost performance than Project B, since its normal cost
timeliness error is much smaller. The same normal timeliness concept can be applied
to compute the schedule predictability performance. By using this calculation CII
members will be able to gauge and benchmark the predictability of their completed
projects.
4
2: The Predictability Index
Forecasted/Reported
Authorized Cost Total Installed Cost
(Cost at t0 = 0)
Project A
...
Forecasted/Reported
Authorized Cost Total Installed Cost
(Cost at t0 = 0)
Project B
Chapter 3 presents a detailed discussion of the PI assessment, its use, and the
interpretation of its components.
5
3
Assessment and Interpretation
This chapter provides guidance on the PI assessment and its interpretation. Specifically,
it discusses the tool’s metrics on overall predictability, cost and schedule predictability,
and their normal timeliness error components.
7
3: Assessment and Interpretation
Nonetheless, the research team acknowledges that a project can be driven by either
cost or schedule—or both—and, thus, a project team can emphasize a clear priority
to satisfy one of those performance measures. Tables 2 and 3 respectively present
the sets of cost and schedule predictability values that belong in the four quartiles
of predictability performance. The reader should note that the team independently
generated these values by sorting out the 135 projects in its dataset in terms of both
cost predictability and schedule predictability. Thus, values in Tables 2 and 3 respectively
prioritize cost and schedule predictability performance alone and, hence, when added,
are not necessarily consistent with the PI values presented in Table 1.
Range
Assessment
Minimum Maximum
0 3.5 Very good cost predictor
>3.5 7.5 Good cost predictor
>7.5 15 Poor cost predictor
>15 Very poor cost predictor
8
3: Assessment and Interpretation
Range
Assessment
Minimum Maximum
0 3.5 Very good schedule predictor
>3.5 8 Good schedule predictor
>8 18 Poor schedule predictor
>18 Very poor schedule predictor
Error Range
Assessment
Minimum Maximum
0 0.4 Very timely forecasting
>0.4 0.55 Timely forecasting
>0.55 0.75 Late forecasting
>0.75 Very late forecasting
9
4
The Predictability Index Tool
RT 291 designed the Predictability Index (PI) tool to evaluate the predictability of cost and
schedule outcomes for completed projects. The PI tool enables owner and contractor
organizations to quantitatively assess and benchmark the predictability performance
of their completed projects. This chapter explains how to use this Excel-based tool.
11
4: The Predictability Index Tool
Input
The user should take the following steps in Section 3:
1. Make sure that the records in ALL the input tabs are empty. Not doing so
can alter and hinder the computed values.
2. Fill the fields in the Project Data section, which asks for both project data
and evaluator information. Notice that the cost and schedule units defined
by the user in the tab must be consistently utilized throughout the tool for
accurate results. Thus, if installed cost and completion time are defined
in millions of dollars and months, the forecast data must be introduced in
these units for the results to be consistent. (See Figure 2 for an example of
input data.)
3. Enter cost forecast log data, up to a total of 200 forecast records.
Sequentially introduce each instance of generated cost forecast with two
parameters (i.e., time at which the forecast was generated/reported, and
forecasted installed cost). Make sure that, in the last record introduced
by the user, the time at which the forecast was generated/reported
is equal to the total completion time of the project as introduced in
the Project Data section. Failure to meet this requirement will result in the
incorrect measurement of predictability. (If either of these two conditions
is violated, the tool will display an error message to alert the user.) Figure 3
provides an example of input data that are consistent with the units
defined in the Project Data section (See Figure 3.)
4. Enter schedule forecast log data, up to a total of 200 forecast records.
Sequentially introduce each instance of the generated schedule forecast
with two parameters (i.e., time at which the forecast was generated/
reported, and forecasted project duration). Make sure that, in the last
record introduced by the user, the time at which the forecast was
generated/reported is equal to the total completion time of the
project as introduced in the Project Data section. Failure to meet this
requirement will result in the incorrect measurement of predictability. (If
either of these two conditions is violated, the tool will display an error
message to alert the user.) Figure 4 provides an example of input data that
are consistent with units defined in Project Data section. (See Figure 4.)
12
4: The Predictability Index Tool
Enter records in
time-sequential order
Enter records in
time-sequential order
13
4: The Predictability Index Tool
Output
The tool contains five output tabs, inclusive of two charts. The first two output tabs
determine the predictability of cost and schedule forecasts, as the product of their
deviation error times the normal timeliness error. Cost and schedule predictability
values are independently calculated based on corresponding input data. The third
output tab measures the Predictability Index as the sum of the cost and schedule
predictability measures. The fourth and fifth outputs present the cost and schedule
forecast error charts.
1. After introducing the cost and schedule forecast log data, review the
results under the “Cost Predictability Index,” “Schedule Predictability
Index,” and “Predictability Index” tabs. Figure 5 presents an example of
the PI output tab. Throughout these tabs, if any output value is labeled
“ERROR,” it implies that the user has not addressed erroneous data inputs
that the tool has announced in error messages. Until such errors have
been resolved the tool cannot generate accurate results.
2. Each of the numeric outcome tabs (Cost Predictability, Schedule
Predictability, and the Predictability Index) has two components that can
be independently assessed. For instance, the Cost Predictability measure
is generated on the basis of the project’s normal timeliness and deviation
errors. The assessment of such components is necessary to understand
cost predictability performance.
3. The performance for each of these three predictability metrics (Cost
Predictability, Schedule Predictability, and the Predictability Index) is
illustrated on a dashboard dial in quartiles corresponding to very good,
good, poor, and very poor. The team statistically determined and adjusted
the quartiles by comparing the accurate and early predictors to the
inaccurate and late predictors, among the projects in its dataset.
4. To complement the previous quantitative measures, the “Cost
Predictability” and “Schedule Predictability” tabs contain the timeliness
chart representation for both cost and schedule forecasts. The area
between the actual project outcome (i.e., installed costs for cost forecast
and completion time for schedule forecast) and the forecasted values
during the project timeline illustrates the timeliness error. In other words,
the cost timeliness chart illustrates how early and accurately the final value
of total installed costs was ascertained for a given project. Similarly, the
schedule timeliness chart illustrates how precise the schedule forecasts
were during the project delivery process. Figure 6 provides an example of
a cost forecast error chart.
14
4: The Predictability Index Tool
Printing
1. Go to the INPUT tabs and print.
2. Go to the OUTPUT tabs and print.
15
Research Team 291, Improving Predictability of Project Outcomes
Former Members
Chris Sorrell, Day and Zimmermann
Mark White, Faithful+Gould
* Principal authors