Method statement for formwork erection and dismantling
Method statement for formwork erection and dismantling
Issued on 03/01/2021,FT/HSE/HABC/079/REV-00
TABLE OF CONTENTS
1. PURPOSE............................................................................................................................................................3
3. REFERENCES.....................................................................................................................................................3
3.1. Contract documents......................................................................................................................................3
3.2. Contractors Submittal....................................................................................................................................3
4. DEFINITIONS / ABBREVIATIONS......................................................................................................................4
4.1. Definition.........................................................................................................................................................4
4.2. Abbreviations.................................................................................................................................................4
5. RESPONSIBLE FOR QUALITY CONTROL........................................................................................................4
6. PROCUREMENT & FABRICATION....................................................................................................................5
6.1. Specification Requirements..........................................................................................................................5
6.2. Shop Drawings...............................................................................................................................................5
6.3. General............................................................................................................................................................5
6.4. System Form for Wall “W3” & “W4”.............................................................................................................5
6.5. System Form for Columns............................................................................................................................5
7. TEST & INSPECTION..........................................................................................................................................6
7.1. Site Inspection Plan.......................................................................................................................................6
7.2. Laboratory Testing Plan................................................................................................................................6
8. CONTINGENCY PLANS......................................................................................................................................6
8.1. Formwork Hoisting Equipment.....................................................................................................................6
8.2. Night Time Works...........................................................................................................................................6
8.3. Traceability of Products................................................................................................................................6
8.4. Control of Non-conforming Products..........................................................................................................6
9. HEALTH, SAFETY AND ENVIRONMENT......................................................................................................7
10. ATTACHMENTS..............................................................................................................................................7
10.1. Inspection Checklists................................................................................................................................7
10.2. Inspection Test Plan..................................................................................................................................7
10.3. Risk Assessment.......................................................................................................................................7
11. Method Statement Communication and Meeting……………………………………….............................7
1. PURPOSE
1. The following is a document of the Quality Control procedures for formwork work for the project.
The objective of this document is two folds:
1. To demonstrate our total quality commitment in implementing, managing and executing of the works for this
project,
2. To assure the client and their project managers and Engineer the confidence that the contract requirements
will be satisfied by the contractor every respect of the works.
2. SCOPE OF WORKS
This document summarizes the general details of the quality assurance plan for system forms as well as traditional
wooden forms including:
1. Management Responsibility
2. Shop Drawings
3. Procurement
4. Fabrication
5. Erection
6. Inspection
7. Striking
Regarding the above procedures, not only the quality aspect of concrete formwork but the work methods will be described
to a relevant extent so that the actual work process can be envisaged.
This document is the beginning, not the end. This document should be communicated reiterated, regularly reviewed and
developed to suit changing condition, standards and technology as the site situation requires
3. REFERENCES
3.1.Contract documents
1. Project Specification :- Division 3, Section 030100
2. Contract Drawings :-
3.2.Contractors Submittal
3. Project Quality Plan :-
4. Project Safety Plan :-
5. Material approvals
Sr. No. Description Material Sub. No. Rev No. Date Remarks
1
2
3
6. Shop Drawings
Sr. No. Description Shop Drawings Rev No. Date Remarks
1
2
3
4. DEFINITIONS / ABBREVIATIONS
4.1.Definition
1. Project - G+1P+8F+R Residential Building
6.2.Shop Drawings
1. Shop drawing showing location of construction joints as well as precise dimensions of the structure form design
and other details will be submitted to Engineer for approval.
2. Only after getting approval, shop drawings will be released to the subcontractors for form fabrication. Sufficient
numbers of copies will be prepared on the site to assure that actual works are undertaken in accordance with the
approved shop drawings.
6.3.General
1. System forms will be used for the larger portion of this project. Conventional plywood forms will be also used in
the sub-structure, stair, and other relatively small or odd parts of formwork. Subjected to the approval of the
Engineer.
2. System forms will be procured from the manufactures that are specialized in both design and fabrication of
custom-made forms for the specific projects.
8. CONTINGENCY PLANS
8.1.Formwork Hoisting Equipment
One mechanic will be on standby to service any breakdown of the tower cranes. Even if one tower crane is
completely out of operation due to mechanical troubles, another tower crane can serve for hoisting forms, allowing
that the productivity goes down considerably while repairing work takes place.
Adequate illumination will be provided at all work areas to assure safe and efficient operations during night
8.3.Traceability of Products
Formwork itself is a temporary work after all. Therefore, “traceability of products” will not be directly applicable here.
TOPICS
S.No. Name Designation Signature