2 Load Under Head Wall Final 1000

Uploaded by

ravikiran226
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Live Load Calculations

Height of Banking = 5.990 m

Clear Span of Slab = 2.75 m

Maximum Axle Load = 11.4 tonnes

Load on each wheel = 11.4 / 2 = 5.7 tonnes

Ground Contact Area of each Wheels 250 x 500


Spacing of wheels in Longitudinal
1.2 m
direction =
Spacing of wheels in each Axle = 1.8 m
Load Dispersion on Longitudinal
250 + 2 H Tan 45 + 1.2
direction =
13.43 m
Load Dispersion on Transverse
500 + 2 H Tan 45 + 1.8
direction =
14.28 m

Load Dispersion each wheel = ( 250 + 2 H Tan 45+1.2 ) x ( 500 + 2 H Tan 45+1.8 )

13.43 x 14.28

= 152.630 m2

Live load on slab = (5.7) / (152.63) = 0.037 t/m2


Live Load on slab due to Over
0.037 t/m2
lapping longitudinal direction =
Live Load on slab due to Over
0.037 t/m2
lapping in transverse direction =
Total Live Load on slab = 0.112 t/m2
DESIGN OF BOX (EARTH BANK)

Width of Box = 2.75 mts.


Height of Box = 1.2 mts.
Total Width of Box = 6.7 mts.
no. of vents = 2
Height of Box including wc = 1.24 mts.
Thickness of wc in box = 0.04 mts.
Thickness of Hor. Member = 0.4 mts.
Thickness of cc lining = 0.04 mts.
Thickness of sealing coat in canal = 0 mts.
Thickness of Ver. Member(end) = 0.4 mts.
Thickness of inner. Member = 0.4 mts.
F S L of canal = 26.790 M
Sill level of box = 14.916 M
Live Load Surcharge = 0.112 t/m2
Avg. Ground Level/TBL = 27.790 M
Stress under headwall = 12.5 t/m2
Top level of box = 21.800 M
Height of earth over box = 5.990 mts.
Density of RCC = 2.5
Density of earth = 2.1
Density of concrete = 2.4
Density of water = 1
Levelling course thickness = 0.15 m
left offset of levelling course = 0.3 m
right offset of levelling course = 0.3 m
Coeft. = 0.361
CBL = 21.840 m
T.B.L 27.790

1.00 F.S.L. 26.790

5.950
4.950
0.4 0.04 Th CC Lining
C.B.L. 21.840
Ph2

0.4

150 X 150 1.2 3.150


2.04
2.75
0.040 TH W.C

0.3 0.3
Ph1

6.7
Loads on RCC box per mt.
Wt. of top member = 6.7 * 0.4 * 2.5 = 6.7 t/m
Wt. of bottom member = 6.7 * 0.4 * 2.5 = 6.7 t/m
Wt. of vertical walls(END) = 2 1.24 * 0.4 * 2.5 = 2.48 t/m
Wt. of vertical walls(middle) = 1 1.24 * 0.4 * 2.5 = 1.240 t/m
Wt. of water in box = 2x 1.2 * 2.75 * 1= 6.6 t/m

Wt. of wc = 5.5 * 0.04 * 2.4 = 0.528 t/m


Wt. of over burden = 6.7 * 5.990 * 2.1 = 84.279 t/m
Wt. of live load surcharge = 6.7 * 0.112 = 0.751 t/m
Wt. of haunches = 8 * 0.0113 * 2.5 = 0.225 t/m
Wt. of cc lining = 6.7 * 0.00 * 2.4 = 0.000 t/m
pcc mat = 7.3 * 0.150 * 2.4 = 2.628 t/m
TOTAL 112.131 t/m
CASE 1 (BOX EMPTY)
Total wt. of box(without water) = 112.131 - 6.600 = 105.531 t

net upward soil reaction B = 105.531 - 6.7 - 0.528 - 2.628 = 14.280 t/sqmt
6.7
load on top of slab A = 84.279 + 0.751 + 6.700 = 13.691 t/sqmt
due to earth bank 6.7
Wt. of head wall = = 6.7 x 12.5 = 83.75

load on top of slab = 83.750 + 0.751 + 6.700 = 13.612 t/sqmt


due to headwall 6.7
load on top of slab = Max( 13.691,13.612) = 13.691 t/sqmt i.e due to due to earth bank
water pressure C = 0
water load D = 0
side thrust( Earth pressure + 100% hydrostatic pressure)
1. 100% hydrostatic pressure(canal)
P1 = 5.19 * 1 = 5.19 t/sqmt
P2 = 6.83 * 1 = 6.83 t/sqmt
earth pr. At top = 0.361 * (2.1-1.0) * 6.19 = 2.458 t/sqmt
earth pr. At bottom = 0.361 * (2.1-1.0) * 7.83 = 3.109 t/sqmt

Net Horizontal pressure at top = 5.19 + 2.458 = 7.650 t/sqmt


Net Horizontal pressure at bottom = 6.83 + 3.109 = 9.939 t/sqmt

13.691 t/sqmt

7.650 t/sqmt 7.650 t/sqmt

1.640
3.150

9.939 t/sqmt 9.939 t/sqmt

14.280 t/sqmt

CASE 2 (BOX FULL)


Total wt. of box = = 112.131 t/m

net upward soil reaction = 112.131 - 2.628 - 6.700 - 0.528 = 15.265 t/sqmt
6.7
load on top of slab = 13.691 t/sqmt i.e due to due to earth bank

side thrust( Earth pressure + 100% hydrostatic pressure)


1. 100% hydrostatic pressure(Canal)
P1 = 5.19 * 1 = 5.19
P2 = 6.83 * 1 = 6.83
earth pr. At top = 0.361 * (2.1-1.0) * 6.19 2.458 t/sqmt
earth pr. At bottom = 0.361 * (2.1-1.0) * 7.83 3.109 t/sqmt

1. 100% hydrostatic pressure(Drain)


P1 = 0 * 1 = 0 t/sqmt
P2 = 1.64 * 1 = 1.64t/sqmt

Net Horizontal pressure at top = 5.19 + 2.458 - 0 = 7.648 t/sqmt


Net Horizontal pressure at bottom = 6.83 + 3.109 - 1.64 = 8.299 t/sqmt
13.691 t/sqmt

7.648 t/sqmt 7.648 t/sqmt

1.640

3.150

8.299 t/sqmt
8.299 t/sqmt

15.265 t/sqmt
DESIGN OF BOX (CANAL)
Width of Box = 2.75 mts.
Height of Box = 1.2 mts.
Total Width of Box = 6.7 mts.
Height of Box including wc = 1.24 mts.
Thickness of wc in box = 0.04 mts.
No. of Vents = 2
Thickness cc lining = 0.04 mts.
Thickness of sealing coat in canal = 0 mts.
Thickness of Hor. Member(top) = 0.4 mts.
Thickness of Ver. Member( end) = 0.4 mts.
Thickness of Ver. Member( middle= 0.4 mts.
F S L of canal = 26.79 M
Sill level of box = 14.916 M
Live Load Surcharge = 0 t/m2
Avg. Ground Level/TBL = 27.79 M
Stress under headwall = 12.50 t/m2
Height of earth over box = 0.000 mts.
Top level of box = 21.800 M
Density of RCC = 2.5
Density of earth = 2.1
Density of concrete = 2.4
Density of water = 1
Levelling course thickness = 0.15 m
left offset of levelling course = 0.3 m
right offset of levelling course = 0.3 m
Coeft. = 0.361
CBL = 21.84 m
TBL 27.790
1.000 FSL 26.790

5.950 4.950 0.04 THICK SEALING COAT


CBL 21.84
Ph2

0.4 0.4 1.2


2.04 150 X 150 3.150

0.075 TH W.C 2.75

0.3 0.3
Ph1

Loads on RCC box per mt. 6.7


Wt. of top member = 6.7 * 0.4 * 2.5 = 6.700 t/m
Wt. of bottom member = 6.7 * 0.4 * 2.5 = 6.700 t/m
Wt. of vertical walls( end) = 2* 1.24 * 0.4 * 2.5 = 2.480 t/m
Wt. of vertical walls(middle) = 1* 1.24 * 0.4 * 2.5 = 1.240 t/m
Wt. of water in box = 2* 1.2 * 2.75 * 1 = 6.600 t/m
Wt. of sealing coat in canal 6.7 * 0 * 2.4 = 0.000 t/m
Wt. of wearing coat in box = 2.75 * 0.04 * 2.4 = 0.264 t/m
Wt. of water in canal = 6.7 * 4.950 * 1 = 33.165 t/m
Wt. of earth over box = 6.7 * 0.000 * 2.1 = 0.000 t/m
Wt. of cc lining = 6.7 * 0.040 * 2.4 = 0.643 t/m
pcc mat = 7.3 * 0.150 * 2.4 = 2.628 t/m
Wt. of haunches = 8 * 0.01125 * 2.5 = 0.225 t/m
TOTAL 60.645 t/m
CASE 1 (BOX EMPTY CANAL EMPTY)
Total wt. of box = 60.645 - 6.6 - 33.165 = 20.880 t/sqmt
net upward soil reaction = 20.880 - 0.264 - 2.628 - 6.700 = 1.685 t/sqmt
6.700
load on top of slab = 6.700 + 0.000 + 0.643 + 0.000 = 1.096 t/sqmt
6.700
Earth pressure at top = 0.361 x 2.1 x 0.24 = 0.1819 t/sqmt
Earth pressure at bottom = 0.361 x 2.1 x 1.88 = 1.425 t/sqmt
1.096 t/sqmt

0.182 t/sqmt 0.182 t/sqmt

1.64

3.15 3.15 3.15

1.425 t/sqmt 1.425 t/sqmt

1.685 t/sqmt
CASE 2 (BOX FULL CANAL EMPTY)
Total wt. of box = 60.645 - 33.165 = 27.480 t/sqmt
net upward soil reaction = 27.480 - 2.628 - 6.700 - 0.264 = 2.670 t/sqmt
6.700
load on top of slab = 6.700 + 0.000 + 0.643 + 0.000 = 1.096 t/sqmt
6.700
Earth pressure at top = 0.361 x 2.1 x 0.24 = 0.182 t/sqmt
Earth pressure at bottom = 0.361 x 2.1 x 1.88 = 1.425 t/sqmt
1. 100% hydrostatic pressure(Drain)
P1 = 0 * 1 = 0 t/sqmt
P2 = 1.64 * 1 = 1.64 t/sqmt
Net Horizontal pressure at top = 0.182 - 0.000 = 0.182 t/sqmt
Net Horizontal pressure at bottom = 1.425 - 1.640 = -0.215 t/sqmt
1.096 t/sqmt

0.182 t/sqmt 0.182 t/sqmt

1.64

3.15 3.15 3.15

0.215 t/sqmt 0.215 t/sqmt

2.670 t/sqmt
CASE 3 (BOX EMPTY CANALFULL)
Total wt. of box = 60.645 - 6.600 = 54.045 t/sqmt

net upward soil reaction = 54.045 - 2.628 - 6.700 - 0.264 = 6.635 t/sqmt
6.700
load on top of slab = 6.700 + 0.000 + 0.643 + 0.000 + 33.165 = 6.046 t/sqmt
6.700
side thrust( Earth pressure + 100% hydrostatic pressure)
1. 100% hydrostatic pressure
P1 = 5.190 * 1 = 5.19 t/sqmt
P2 = 6.83 * 1 = 6.83 t/sqmt
earth pr. At top = 0.361 * (2.1-1.0) * 0.24 = 0.095 t/sqmt
earth pr. At bottom = 0.361 * (2.1-1.0) * 1.880 = 0.747 t/sqmt
Net Horizontal pressure at top = 5.19 + 0.095 = 5.285 t/sqmt
Net Horizontal pressure at bottom = 6.83 + 0.747 = 7.577 t/sqmt
6.046 t/sqmt

5.285 t/sqmt 5.285 t/sqmt

1.64

3.150 3.15 3.15

7.577 t/sqmt
7.577 t/sqmt

6.635 t/sqmt
CASE 4 (BOX FULL CANALFULL)
Total wt. of box = 60.645 = 60.645 t

net upward soil reaction = 60.645 - 2.628 - 6.700 - 0.264 = 7.620 t/sqmt
6.700
load on top of slab = 6.700 + 0.000 + 0.643 + 0.000 + 33.165 = 6.046 t
6.700
side thrust( Earth pressure + 100% hydrostatic pressure)
1. 100% hydrostatic pressure(Canal)
P1 = 5.190 * 1 = 5.19 t/sqmt
P2 = 6.83 * 1 = 6.83 t/sqmt
earth pr. At top = 0.361 * (2.1-1.0) * 0.24 = 0.095 t/sqmt
earth pr. At bottom = 0.361 * (2.1-1.0) * 1.880 = 0.747 t/sqmt
1. 100% hydrostatic pressure(Drain)
P1 = 0 * 1 = 0 t/sqmt
P2 = 1.64 * 1 = 1.64 t/sqmt
Net Horizontal pressure at top = 5.19 + 0.095 - 0 = 5.285 t/sqmt
Net Horizontal pressure at bottom = 6.83 + 0.747 - 1.64 = 5.937 t/sqmt
6.046 t/sqmt

5.285 t/sqmt 5.285 t/sqmt

1.64

3.150 3.150 3.150


5.937 t/sqmt 5.937 t/sqmt

7.620 t/sqmt
HEAD WALL (U/S & D/S)
`
DATA : 2.0
1
HEAD WALL TOP LEVEL :+ 489.324
TOP OF FOUDATION :+ 487.134 W4
489.324

TOP WIDTH : 0.500 W3


REAR BATTER : 0.900 2.190
W1
W2

UNIT WT. OF CONC. : 2.400 500


UNIT WT. OF SOIL : 2.100 900

SLOPE OF SOIL SURCHARGE 2 : 1 487.134


HOR. COEFFT. OF SOIL : 0.3005 A 1400

VER. COEFFT. OF SOIL : 0.0749

STRESS IN CONCRETE AT 'A'

FORCE PARTICULARS MAG. L.A. MOMENT


TONS. MTS TON.MT.

W1 2.190 * 0.500 * 2.400 2.628 1.150 3.022

W2 0.500 * 2.190 * 0.900 * 2.400 2.365 0.600 1.419

W3 0.500 * 2.190 * 0.900 * 2.100 2.070 0.300 0.621

W4 0.500 * 0.900 * 0.45 * 2.100 0.425 0.300 0.128

PV 0.0749 * 6.767 * 2.100 1.064 0.000 0.000

8.552

PH 0.3005 * 6.767 * 2.100 4.270 0.876 3.741

4.270 8.931

LEVER ARM = 1.044 mts.


ECCENTRICITY = 0.344 mts.
ALLOWABLE LIMIT = 0.233 mts.

MAX. STRESS = 15.121 t/sq.mt.


MIN. STRESS = -2.903 t/sq.mt.
DESIGN OF BOX (UNDER HEAD WALL)

Width of Box = 2.75 mts.


Height of Box = 1.2 mts.
Total Width of Box = 6.7 mts.
no. of vents = 2
Height of Box including wc = 1.24 mts.
Thickness of wc = 0.04 mts.
Thickness of Hor. Member = 0.4 mts.
Thickness of cc lining = 0.04 mts.
Thickness of sealing coat in canal = 0 mts.
Thickness of Ver. Member(end) = 0.4 mts.
Thickness of inner. Member = 0.4 mts.
F S L of canal = 26.790 M
Sill level of box = 14.916 M
Live Load Surcharge = 0.112 t/m2
Avg. Ground Level/TBL = 27.790 M
Stress under headwall = 8.20927 t/m2
Top level of box = 21.800 M
Height of earth over box = 5.990 mts.
Density of RCC = 2.5
Density of earth = 2.1
Density of concrete = 2.4
Density of water = 1
Levelling course thickness = 0.15 m
left offset of levelling course = 0.25 m
right offset of levelling course = 0.25 m
Coeft. = 0.361
CBL = 21.840 m
T.B.L 27.790

1.00 F.S.L. 26.790

5.950
4.950
0.4 0.04 Th CC Lining
C.B.L. 21.840
Ph2

0.4

150 X 150 1.2 3.150


2.04
2.75
0.040 TH W.C

0.25 0.25
Ph1

6.7
Loads on RCC box per mt.

Wt. of top member = 6.7 * 0.4 * 2.5 = 6.7 t/m


Wt. of bottom member = 6.7 * 0.4 * 2.5 = 6.7 t/m
Wt. of vertical walls(END) =2* 1.24 * 0.4 * 2.5 = 2.48 t/m
Wt. of vertical walls(middle) = 1 1.24 * 0.4 * 2.5 = 1.240 t/m
Wt. of water in box = 2x 1.2 * 2.75 * 1= 6.6 t/m
Wt. of wc = 5.5 * 0.04 * 2.4 = 0.528 t/m
Wt. of Head wall = 6.7 * 8.209 = 55.002 t/m
Wt. of live load surcharge = 6.7 * 0.112 = 0.751 t/m
Wt. of haunches = 8 * 0.0113 * 2.5 = 0.225 t/m
Wt. of cc lining = 6.7 * 0.00 * 2.4 = 0.000 t/m
pcc mat = 7.2 * 0.150 * 2.4 = 2.592 t/m
TOTAL 82.818 t/m
CASE 1 (BOX EMPTY)
Total wt. of box(without water) = 82.818 - 6.600 = 76.218 t

net upward soil reaction B = 76.218 - 6.700 - 0.528 - 2.592 = 9.910 t/sqmt
6.7
load on top of slab A = 55.002 + 0.751 + 6.700 = 9.321 t/sqmt
6.7
water pressure C = 0

water load D = 0

side thrust( Earth pressure + 100% hydrostatic pressure)


1. 100% hydrostatic pressure
P1 = 5.19 * 1 = 5.19 t/sqmt
P2 = 6.83 * 1 = 6.83 t/sqmt
earth pr. At top = 0.361 * (2.1-1.0) * 6.19 = 2.458 t/sqmt
earth pr. At bottom = 0.361 * (2.1-1.0) * 7.83 = 3.109 t/sqmt

Net Horizontal pressure at top = 5.19 + 2.458 = 7.648 t/sqmt

Net Horizontal pressure at bottom = 6.83 + 3.109 = 9.939 t/sqmt

9.321 t/sqmt

7.648 t/sqmt 7.648 t/sqmt

1.640
3.150

9.939 t/sqmt 9.939 t/sqmt

9.910 t/sqmt

CASE 2 (BOX FULL)


Total wt. of box = = 82.818 t/m

net upward soil reaction = 82.818 - 2.592 - 6.700 - 0.528 = 10.895 t/sqmt
6.7
load on top of slab = 55.002 + 0.751 + 6.700 = 9.321 t/sqmt
6.7

side thrust( Earth pressure + 100% hydrostatic pressure)


1. 100% hydrostatic pressure(Canal)
P1 = 5.19 * 1 = 5.19
P2 = 6.83 * 1 = 6.83
earth pr. At top = 0.361 * (2.1-1.0) * 6.19 2.458 t/sqmt
earth pr. At bottom = 0.361 * (2.1-1.0) * 7.83 3.109 t/sqmt

1. 100% hydrostatic pressure(Drain)


P1 = 0 * 1 = 0 t/sqmt
P2 = 1.64 * 1 = 1.64t/sqmt

Net Horizontal pressure at top = 5.19 + 2.458 - 0 = 7.648 t/sqmt

Net Horizontal pressure at bottom = 6.83 + 3.109 - 1.64 = 8.299 t/sqmt

9.321 t/sqmt

7.648 t/sqmt 7.648 t/sqmt

1.640

3.150

8.299 t/sqmt
8.299 t/sqmt
10.895 t/sqmt
STRAIGHT WING WALL

DATA :

WING WALL TOP LEVEL : 492.541


FIRST BATTER LEVEL : 492.541
TOP OF FOUDATION : 489.910 0.500 492.541
BOT. OF FOUNDATION : 489.560

TOP WIDTH : 0.500


REAR SIDE BATTER : 0.570 492.541
FRONT SIDE BATTER : 0.530 W4
OFFSET ON EITHER SIDE : 0.400 2631 W3
W5 W2
W1 400
UNIT WT. OF CONC. : 2.400 400 570 500 530 489.910
UNIT WT. OF SOIL : 2.100 350 W6 A
489.560
HOR. COEFFT. OF SOIL : 0.3005 1600 B
VER. COEFFT. OF SOIL : 0.0749 2400

STRESS IN CONCRETE :

FORCE PARTICULARS MAG. L.A. MOMENT


TONS. MTS TON.MT.

W1 0.500 x 2.631 x 0.570 x 2.400 1.800 1.220 2.196


W2 x 2.631 x 0.500 x 2.400 3.157 0.780 2.463
W3 0.500 x 0.530 x 2.631 x 2.400 1.673 0.353 0.591
W4 0.500 x 0.570 x 2.631 x 2.100 1.575 1.410 2.220

PV 0.0749 x 2.631 ² x 2.100 1.089

9.294 7.470

PH 0.3005 x 2.631 ² x 2.100 4.368 -1.052 -4.597

2.873
Lever arm =M/V = 2.873 / 9.294 = 0.309 m
Eccentricity = 0.309 - 1.600 /2 = 0.491 m
B/6 = 1.60 / 6 = 0.267 m< 0.491 m

Max. Stress = 9.294 / 1.600 ) x { 1 + ( 6 x 0.491 ) / 1.600 }


= 16.500 T/ Sqm ( Compression )

Min. Stress = 9.294 / 1.600 ) x { 1 - ( 6 x 0.491 ) / 1.600 }


= -4.890 T/ Sqm ( Tension )

STRESS ON SOIL :

FORCE PARTICULARS MAG. L.A. MOMENT


TONS. MTS TON.MT.

W1 0.500 x 2.631 x 0.570 x 2.400 1.800 1.620 2.915

W2 2.631 x 0.500 x 2.400 3.157 1.180 3.725

W3 0.500 x 2.631 x 0.530 x 2.400 1.673 0.753 1.261

W4 0.500 x 2.631 x 0.570 x 2.100 1.575 1.810 2.850

W5 2.631 x 0.400 x 2.100 2.210 2.200 4.862

W6 0.350 x 2.400 x 2.400 2.016 1.200 2.419

PV 0.0749 x 2.981 ² x 2.100 1.398

13.829 18.033

PH 0.3005 x 2.981 ² x 2.100 5.608 -1.192 -6.687

5.608 11.346

Lever arm =M/V = 11.346 / 13.829 = 0.82 m


Eccentricity = 0.82 - 2.400 /2 = 0.380 m
B/6 = 2.40 / 6 = 0.400 m> 0.380 m

Max. Stress = 13.829 / 2.400 ) x { 1 + ( 6 x 0.380 ) / 2.400 }


= 11.240 T/ Sqm ( Compression )

Min. Stress = 13.829 / 2.400 ) x { 1 - ( 6 x 0.380 ) / 2.400 }


= 0.290 T/ Sqm ( Compression )

OVER TURNING MOMENT : 6.687 T-M

CHECK FOR OVER TURNING : 18.033 = 2.69683 > 2 (IRC:78-2000.cl.706.3.4)


6.687

CHECK FOR SLIDING : 0.50 X 13.829 = 1.233 < 1.5


5.608 (IRC:78-2000.cl.706.3.4)

max min
on concrete 16.500 -4.890 t/sq.mt.
on soil 11.240 0.290 t/sq.mt.