CHECKLIST FOR GRANULAR SUB BASE (GSB)

Format No: HBLLP/BAL/D03/FT-42


Project:

Location Date

Reference Drawing No:


Approximate qty
Initial Level: Final Level:

Sr.No Points to Check Action Req. REMARKS

1 Drawings & Details Finalised

2 Is the fill Material Approved .

3 Availability of Req. equipments


BEFORE FILLING

4 Approach to Work Site

5 Levels Before Backfilling Taken

6 Subgrade Compaction done

Underground utilities are located and adequate precautions are in


7
place to protect them

8 Protection to Existing Structure/Services

9 Adequate lighting arrangement provided

HBLLP CONSULTANT/CLIENT

1 Use of PPEs
DURING GSB FILLING

2 Check for GSB filling as per Drg.

3 GSB Layer Thickness

4 Is the density achieved (Compaction 98%) IS 2720