Structure Installation Manual No.1
Structure Installation Manual No.1
The left side is T rail steel structure, the T rail will be fixed on
this steel structure strongly.
Bottom side is the feet board, which used to fix the bottom
side strongly with ground.
The T rail structure are separated into several pieces refer to
different lifting height size;
We had process hole for fixing the screw bolts before ex-work;
5. T rail
6. T rail shoe
7. Lifting frame
5
8. Cylinder big screw nut
9. Cylinder
6
10. Oil injecting hole of cylinder
7
11. Cylinder base pillar
12. Cylinder fixing clip
8
9
Before install the cylinder and lifting frame,
the T rail should be fixed strongly;
Cylinder should be fixed on the T rail
12 structure, but the cylinder body cannot be
welded even a point;
10
11
13
The chain is heavy loading leaf chain, every
chain can load 4 Ton capacity;
This kind of chain noise lower than normal
14 chain;
B
Fix the rail structure on the shaft wall
21 Platform L structure
Note:
After install the L structure, workers should make the first time
up and down testing using hoist or other lifting machine; If
there is small shake, workers should adjust some spare parts to
assure the platform up and down steady;
Different view of the fixed structure on the wall
23 Floor
Now, the floor steel board had been installed steady
before ex-work, no need make the extra installation
when workers make the installation work;
Now, the floor steel board had been installed steady
before ex-work, no need make the extra installation
when workers make the installation work;
Step 2. Cabin wall installation
26 Cabin roof
When fixing the cabin roof, directly fix the top roof
cover on the top side of "C" type cabin wall;
Bolt the edge of roof cover on the cabin wall using
screw bolts, and fix them steady strongly;
27 COP
When install COP, connect the controlling wires firslty;
28 Handle
29 Header stainless steel
The function of header stainless steel is decoration,
which can block the seal between roof and cabin walls;