Guideline_and_Technical_Basis_Draft_2__Clean_
Guideline_and_Technical_Basis_Draft_2__Clean_
Introduction
The document, “Power Plant and Transmission System Protection Coordination,” published by
the NERC System Protection and Control Subcommittee (SPCS) provides extensive general
discussion about the protective functions and generator performance addressed within this
standard. This document was last revised in July 2010.1
The term, “while maintaining reliable fault protection” in Requirement R1, describes that the
Generator Owner (“responsible entity”) is to comply with this standard while achieving its
desired protection goals. Load-responsive protective relays, as addressed within this standard,
may be intended to provide a variety of backup protection functions, both within the generation
unit or plant and on the Transmission system, and this standard is not intended to result in the
loss of these protection functions. Instead, it is suggested that the responsible entity consider both
the requirement within this standard and its desired protection goals, and perform modifications
to its protective relays or protection philosophies as necessary to achieve both.
For example, if the intended protection purpose is to provide backup protection for a failed
Transmission breaker, it may not be possible to achieve this purpose while complying with this
standard if a simple mho relay is being used. In this case, it may be necessary to replace the
legacy relay with a modern advanced-technology relay that can be set using functions such as
load encroachment. It may otherwise be necessary to reconsider whether this is an appropriate
method of achieving protection for the failed Transmission breaker, and whether this protection
can be better provided by, for example, applying a breaker failure relay with a transfer trip
system.
Requirement R1 establishes that the responsible entity must understand the applications of Table
1, Relay Loadability Evaluation Criteria (“Table 1”) in determining the settings that it must
apply to each of its load-responsive protective relays to prevent an unnecessary trip of its
generator during the system conditions anticipated by this standard.
Applicability
The drafting team recognizes that some Generator Owners own an interconnection facility (in
some cases labeled a “transmission Facility” or “generator leads”) between the generator and the
interface with the portion of the BES where Transmission Owners take over the ownership. In
these cases, the Generator Owners own sole-use Facilities that are connected to the boundary of
the interconnected system. Load-responsive protective relays applied by the Generator Owner at
the terminals of these Facilities to protect these interconnection Facilities are included in the
scope of this standard.
1
http://www.nerc.com/docs/pc/spctf/Gen%20Prot%20Coord%20Rev1%20Final%2007-30-2010.pdf
condition, known as “field-forcing,” results in the Reactive Power output exceeding the steady-
state capability of the generator and may result in operation of generation system load-responsive
protective relays if they are not set to consider this operating condition. The ability of the
generating unit to withstand the increased Reactive Power output during field-forcing is limited
by the field winding thermal withstand capability. The excitation limiter will respond to begin
reducing the level of field-forcing in as little as one second, but may take much longer,
depending on the level of field-forcing given the characteristics and application of the excitation
system. Since this time may be longer than the time-delay of the generator load-responsive
protective relay, it is important to evaluate the loadability to prevent its operation for this
condition.
The generator bus voltage during field-forcing will be higher than the high-side voltage due to
the voltage drop across the generator step-up transformer. When the relay voltage is supplied
from the generator bus, it is necessary to assess loadability using the generator bus voltage. The
criteria established within Table 1 are based on 0.85 per unit of Transmission system nominal
voltage. This voltage was widely observed during the events of August 14, 2003, and was
determined during the analysis of the events to represent a condition from which the System may
have recovered, had not other undesired behavior occurred.
The dynamic load levels specified in Table 1 under column “Pickup Setting Criteria” are
representative of the maximum expected apparent power during field-forcing with the
Transmission system voltage at 0.85 per unit, for example, at the high-side of the generator step-
up transformer. These values are based on records from the events leading to the August 14,
2003 blackout, other subsequent System events, and simulations of generating unit responses to
similar conditions. Based on these observations, the specified criteria represent conservative but
achievable levels of Reactive Power output of the generator with a 0.85 per unit high-side
voltage at the point of interconnection.
The dynamic load levels were validated by simulating the response of synchronous generating
units to depressed Transmission system voltages for 67 different generating units. The generating
units selected for the simulations represented a broad range of generating unit and excitation
system characteristics as well as a range of Transmission system interconnection characteristics.
The simulations confirmed, for units operating at or near the maximum Real Power output, that it
is possible to achieve a Reactive Power output of 1.5 times the rated Real Power output when the
Transmission system voltage is depressed to 0.85 per unit. While the simulations demonstrated
that all generating units may not be capable of this level of Reactive Power output, the
simulations confirmed that approximately 20 percent of the units modeled in the simulations
could achieve these levels. On the basis of these levels, Table 1, Options 1a (0.95 per unit) and
1b (0.85 per unit), for example, are based on relatively simple, but conservative calculations of
the high-side nominal voltage. In recognition that not all units are capable of achieving this level
of output Option 1c (simulation) was developed to allow the responsible entity to simulate the
output of a generating unit when the simple calculation is not adequate to achieve the desired
protective relay setting.
Phase Directional Time Overcurrent Relay – Directional Toward Transmission System (67)
See section 3.9.2 of the Power Plant and Transmission System Protection Coordination technical
reference document for a detailed discussion of the phase time overcurrent protection function.
The basis for setting directional and non-directional time overcurrent relays are similar. Note that
the setting criteria established within these options differ from section 3.9.2 of the Power Plant
and Transmission System Protection Coordination technical reference document. Rather than
establishing a uniform setting threshold of 200 percent of the generator MVA rating at rated
power factor for all applications, the setting criteria are based on the maximum expected
generator output based on whether the generator operates synchronous or asynchronous.
Unit Auxiliary Transformers Phase Time Overcurrent Relay (51) (Option 13a and 13b)
In FERC Order No. 733, paragraph 104, directs NERC to include in this standard a loadability
requirement for relays used for overload protection of unit auxiliary transformer(s) (“UAT”)that
supply normal station service for a generating unit. For the purposes of this standard, UATs
provide the overall station power to support the unit at its maximum gross operation.
The UATs supplying power to the unit or plant electrical auxiliaries are sized to accommodate
the maximum expected UAT load demand at the highest generator output. Although the MVA
size normally includes capacity for future loads as well as capacity for starting of large induction
motors on the original unit or plant design, the MVA capacity of the transformer may be near full
load.
Because of the various design and loading characteristics of UATs, two options (13a and 13b)
are provided to accommodate an entity’s protection philosophy while preventing the UAT
transformer time overcurrent relays from operating during the dynamic conditions anticipated by
this standard.
Options 13a and 13b calculate the transformer bus voltage corresponding to 1.0 per unit nominal
voltage on the high-side winding or each low-side winding of the UAT based on relay location.
Consideration of the voltage drop across the transformer is not necessary.
For Option 13a, the overcurrent element shall be set greater than 150 percent of the calculated
current derived from the UAT maximum nameplate MVA rating. This is a simple calculation
that approximates the stressed system conditions.
For Option 13b, the overcurrent element shall be set greater than 150 percent of the UAT
measured current at the generator maximum gross MW capability reported to the Planning
Coordinator or Transmission Planner. This allows for a reduced setting pickup compared to
Option 13a but does allow for an entity’s relay setting philosophy. Because loading
characteristics may be different from one load bus to another, the phase current measurement
will have to be verified at each relay location protecting the transformer. The phase time
overcurrent relay pickup setting criteria is established at 150 percent of the measured value for
each relay location. This is a more involved calculation that approximates the stressed system
conditions by allowing the entity to consider the actual load placed on the UAT based on the
generator’s maximum gross MW capability reported to the Planning Coordinator or
Transmission Planner.
The performance of the UAT loads during stressed system conditions (depressed voltages) is
very difficult to determine. Rather than requiring responsible entities to determine the response
Example Calculations.
0.85
22
Generator step-up transformer turns ratio: () *
346.5
25000
Current transformer ratio: +, *
5
200
Potential transformer ratio: , *
1
5000
Auxiliary current transformer: +,$
5
2000
Transformer High Voltage CT: +,-.
5
Option 1a represents the simplest calculation for synchronous generators applying a phase distance relay (21)
directional toward the Transmission system.
767.6 !
5 1.5 4 767.6 !
5 1151.3 123
Option 1a, Table 1 – Bus Voltage, calls for a 0.95 per unit of the high-side nominal voltage for the generator bus
voltage (Vgen):
22
0.95 4 345 4 7 8
346.5
20.81
( 1383.7∠56.3°
<
Eq. (5) "*
(=
>20.81 ?<
"*
1383.7∠ @ 56.3°
"* 0.3130∠56.3° Ω
+, *
"#0 "* 4
,
Eq. (6)
*
<ABBB
A
"#0 0.3130∠56.3° Ω 4 <BB
C
"#0 0.3130∠56.3° Ω 4 25
"#0 7.8238∠56.3° Ω
"#0
Eq. (7) "DEF **
115%
7.8238∠56.3° Ω
"DEF **
1.15
Assume a Mho distance impedance relay with a maximum torque angle (MTA) set at 85˚, and then the maximum
allowable impedance reach is:
|"DEF ** |
"G H
cosMNOPQ @ N #* R
Eq. (8)
6.8033 Ω
"G H
cos>85.0° @ 56.3°?
6.8033 Ω
"G H
0.8771
"G H 7.7561∠85.0° Ω
Option 1b represents a more complex, more precise calculation for synchronous generators applying a phase
distance (21) directional toward the Transmission system relay. This option requires calculating low-side voltage
taking into account voltage drop across the generator step-up transformer. Similarly these calculations may be
applied to Option 7b for generator step-up transformers applying a phase distance (21) directional toward the
Transmission system relay.
767.6 !
5 1.5 4 767.6 !
5 1151.3 123
Convert Real Power, Reactive Power, and transformer reactance to per unit values on 767.6 MVA base:
$
S#
Eq. (11)
767.6 !
$
767.6
$ 1.0 . 6.
5
5$
S#
Eq. (12)
1151.3 123
5$
767.6
5$ 1.5 . 6.
S#
T$ TUVW> ? 4 7 8
UVW
Eq. (13)
767.6
T$ 12.14% 4 7 8
903
T$ 0.1032 . 6.
Use the formula below; calculate the low-side generator step-up transformer voltage (Vlow-side) using 0.85 p.u. high-
side voltage (Vhigh-side). Estimate initial low-side voltage to be 0.95 p.u. Repeat the calculation if necessary until Vlow-
side converges:
5.92°
N XY#*
0.8075
N XY#* 7.3°
<
Eq. (15) \^*^Y#* \ 4 cos>N XY#* ? ` a\^*^Y#* \ 4 cos>N XY#* ?< 9 4 4 5$ 4 T$
| XY#* |
2
0.8430 ` 1.1532
| XY#* |
2
| XY#* | 0.9981 . 6.
Use the new estimated Vlow-side value of 0.9981 per unit for the second iteration:
5.92°
N XY#*
0.8484
N XY#* 7.0°
<
Eq. (17) \^*^Y#* \ 4 cos>N XY#* ? ` a\^*^Y#* \ 4 cos>N XY#* ?< 9 4 4 5$ 4 T$
| XY#* |
2
0.8437 ` 1.1532
| XY#* |
2
| XY#* | 0.9987 . 6.
To account for system high-side nominal voltage and the transformer tap ratio:
22
S$# 0.9987 . 6. 4 345 4 7 8
346.5
S$# 21.88
( 1383.7∠56.3°
<
Eq. (20) "*
(=
>21.88 ?<
"*
1383.7∠ @ 56.3°
"* 0.3458∠56.3° Ω
+, *
"#0 "* 4
,
Eq. (21)
*
<ABBB
A
"#0 0.3458∠56.3° Ω 4 <BB
C
"#0 0.3458∠56.3° Ω 4 25
"#0 8.6462∠56.3° Ω
"#0
Eq. (22) "DEF **
115%
8.6462∠56.3° Ω
"DEF **
1.15
Assume a Mho distance impedance relay with a maximum torque angle (MTA) set at 85˚, and then the maximum
allowable impedance reach is:
|"DEF ** |
"G H
cosMNOPQ @ N #* R
Eq. (23)
7.5185Ω
"G H
cos>85.0˚ @ 56.3°?
7.5185 Ω
"G H
0.8771
"G H 8.5715∠85.0° Ω
This option requires simulation. Refer to the Machine Data at the beginning of this section for inputs and the
Guidelines and Technical Basis for other pertinent information.
Option 2a represents the simplest calculation for synchronous generators applying a phase time overcurrent (51V-R)
voltage restrained relay:
767.6 !
5 1.5 4 767.6 !
5 1151.3 123
Option 2a, Table 1 – Bus Voltage, calls for a 0.95 per unit of the high-side nominal voltage for the generator bus
voltage (Vgen):
22
0.95 4 345 4 7 8
346.5
20.81
( 1383.7∠56.3°
(
d*
√3 4
Eq. (28)
1383.7
d*
1.73 4 20.81
d* 38389.9
d*
d#0
+, *
Eq. (29)
38389.9 A
d#0
25000
5
d#0 7.678 A
Option 2b represents a more complex calculation for synchronous generators applying a phase time overcurrent
(51V-R) voltage restrained relay:
767.6 !
5 1.5 4 767.6 !
5 1151 123
Convert Real Power, Reactive Power, and transformer reactance to per unit values on 767.6 MVA base.
$
S#
Eq. (33)
767.6 !
$
767.6
$ 1.0 . 6.
5
5$
S#
Eq. (34)
1151.3 123
5$
767.6
5$ 1.5 . 6.
Transformer impedance:
S#
T$ TUVW> ? 4 7 8
UVW
Eq. (35)
767.6
T$ 12.14% 4 7 8
903
T$ 0.1032 . 6.
Use the formula below; calculate the low-side generator step-up transformer voltage (Vlow-side) using 0.85 p.u. high-
side voltage (Vhigh-side). Estimate initial low-side voltage to be 0.95 p.u. Repeat the calculation if necessary until Vlow-
side converges:
5.92°
N XY#*
0.8075
N XY#* 7.3°
<
Eq. (37) \^*^Y#* \ 4 cos>N XY#* ? ` a\^*^Y#* \ 4 cos>N XY#* ?< 9 4 4 5$ 4 T$
| XY#* |
2
0.8430 ` 1.1532
| XY#* |
2
| XY#* | 0.9981 . 6.
Use the new estimated Vlow-side value of 0.9981 per unit for the second iteration:
5.92°
N XY#*
0.8484
N XY#* 7.0°
<
Eq. (39) \^*^Y#* \ 4 cos>N XY#* ? ` a\^*^Y#* \ 4 cos>N XY#* ?< 9 4 4 5$ 4 T$
| XY#* |
2
0.8437 ` 1.1532
| XY#* |
2
| XY#* | 0.9987 . 6.
To account for system high-side nominal voltage and the transformer tap ratio:
22
S$# 0.9987 . 6. 4 345 4 7 8
346.5
S$# 21.88
( 1383.7∠56.3° MVA
(
Eq. (42) d*
√3 4 S$#
1383.7
d*
1.73 4 21.88
d* 36519.8
d*
d#0
+, *
Eq. (43)
36519.8 A
d#0
25000
5
d#0 7.304 A
This option requires simulation. Refer to the Machine Data at the beginning of this section for inputs and the
Guidelines and Technical Basis for other pertinent information.
Option 3 represents the only calculation for synchronous generators applying a phase time overcurrent (51V-C) –
voltage controlled relay (Enabled to operate as a function of voltage). Similarly, Option 6 uses the same calculation
for asynchronous generators.
767.6 !
5 1.5 4 767.6 !
5 1151.3 123
Options 3 and 6, Table 1 – Bus Voltage, calls for a 1.0 per unit of the high-side nominal voltage for the generator
bus voltage (Vgen):
22
1.0 4 345 4 7 8
346.5
21.9
The voltage setting shall be set less than 75% of the generator bus voltage:
This represents the calculation for an asynchronous generator (including inverter-based installations) applying a
phase distance (21) – directional toward the Transmission system relay. Similarly, these calculations may also be
applied to other asynchronous applications, including Option 17 for generator step-up transformers and lines that
radially connect a generating plant to the Transmission system. In this application it was assumed 100Mvar of static
compensation was added.
767.6 !
5 575.7 123
Options 4, 10, and 17, Table 1 – Bus Voltage, calls for a 1.0 per unit of the high-side nominal voltage for the
generator bus voltage (Vgen):
22
1.0 4 345 4 7 8
346.5
21.9
( 959.5∠36.9°
<
Eq. (53) "*
(=
>21.9 ?<
"*
959.5∠ @ 36.9°
"* 0.5001∠36.9° Ω
+, *
"#0 "* 4
,
Eq. (54)
*
<ABBB
A
"#0 0.5001∠36.9 Ω 4 <BB
C
"#0 0.5001∠36.9° Ω 4 25
"#0 12.502∠36.9° Ω
"#0
Eq. (55) "DEF **
130%
12.502∠36.9° Ω
"DEF **
1.30
Assume a Mho distance impedance relay with a maximum torque angle (MTA) set at 85˚, and then the maximum
allowable impedance reach is:
|"DEF ** |
"G H
cosMNOPQ @ N #* R
Eq. (56)
9.617 Ω
"G H
cos>85.0° @ 36.9°?
9.617 Ω
"G H
0.6678
"G H 14.401∠85.0° Ω
This represents the calculation for asynchronous generators applying a phase time overcurrent (51V-R) – voltage
restrained relay. In this application it was assumed 100Mvar of static compensation was added. Similarly, Option 6
uses the same calculation for asynchronous generators.
767.6 !
5 575.7 123
Option 5, Table 1 – Bus Voltage, calls for a 1.0 per unit of the high-side nominal voltage for the generator bus
voltage (Vgen):
22
1.0 4 345 4 7 8
346.5
21.9
( 959.5∠36.9°
(
d*
√3 4
Eq. (61)
959.5
d*
1.73 4 21.9
d* 25295.3
d*
d#0
+, *
Eq. (62)
25295.3 A
d#0
25000
5
d#0 5.06 A
Example Calculations: Option 8a, 8b, 9a, 9b, 15a, and 16a
Option 8a represents the calculation for a generator step-up (GSU) transformer applying a phase time overcurrent
(51) relay connected to a synchronous generator. Similarly, these calculations can be applied to other synchronous
generator applications, including Option 9a for generator step-up transformers applying a phase directional time
overcurrent (67) directional toward the Transmission system relay, and Option 15a and 16a for lines that radially
connect a generating plant to the Transmission system using a phase time overcurrent (51) and phase directional
time overcurrent (67) directional toward the Transmission system relay, respectively. Options 8b and 9b use the
same process, except the bus voltage is 0.85 per unit is used instead of 0.95 and excludes the generator step-up
(GSU) impedance.
This example uses Option 8b as an example.
767.6 !
5 1.5 4 767.6 !
5 1151.3 123
Option 8b, Table 1 – Bus Voltage, calls for a 0.85 per unit of the high-side nominal voltage:
293.25
( 1383.7∠56.3°
(
Eq. (68) d*
√3 4 S$#
1383.7
d*
1.73 4 293.25
d* 2724.3
d*
d#0
+, *
Eq. (69)
2724.3 A
d#0
25000
5
d#0 0.545 A
These options require simulation. Refer to the Machine Data at the beginning of this section for inputs and the
Guidelines and Technical Basis for other pertinent information.
Option 11 represents the calculation for a generator step-up (GSU) transformer applying a phase time overcurrent
(51) relay connected to an asynchronous generator. Similarly, these calculations can be applied to Option 12 for a
phase directional time overcurrent (67) directional toward the Transmission system relay. In this application it was
assumed 100Mvar of static compensation was added.
767.6 !
5 575.7 123
Options 11 and 12, Table 1 – Bus Voltage, calls for a 1.0 per unit of the high-side nominal voltage for the generator
bus voltage (Vgen):
22
1.0 4 345 4 7 8
346.5
21.9
( 959.5∠36.9°
(
d*
√3 4
Eq. (75)
959.5
d*
1.73 4 21.9
d* 25295
d*
d#0
+, *
Eq. (76)
25295 A
d#0
25000
5
d#0 5.059 A
Option 13a of the unit auxiliary transformer (UAT) assumes that the maximum nameplate rating of the winding
utilized for the purposes of the calculations and the appropriate voltage. Similarly, Option 13b uses the measured
current while operating at the maximum gross MW capability reported to the Planning Coordinator or Transmission
Planner.
),
Eq. (78) d*
√3 4 $
60
d*
1.73 4 13.8
d* 2510.2
d*
d#0
+,$
Eq. (79)
2510.2 A
d#0
5000
5
d#0 2.51 A
Option 14a represents the calculation for lines that radially connect an asynchronous generating plant to the
Transmission system for a phase directional time overcurrent (67) directional toward the Transmission system relay.
767.6 !
5 1.5 4 767.6 !
5 1151.3 123
Option 14a, Table 1 – Bus Voltage, calls for a 0.85 per unit of the high-side nominal voltage for the generator step-
up (GSU) voltage (Vnom):
293.25
( 1383.7∠56.3°
S$#
<
Eq. (85) "*
(=
>293.25 ?<
"*
1383.7∠ @ 56.3°
"* 62.1481∠56.3° Ω
+, *
"#0 "* 4
,
Eq. (86)
*
<ABBB
A
"#0 62.1481∠56.3° Ω 4 <BB
C
"#0 62.1481∠56.3° Ω 4 25
"#0 1553.7∠56.3° Ω
"#0
Eq. (87) "DEF **
115%
1553.7∠56.3° Ω
"DEF **
1.15
Assume a Mho distance impedance relay with a maximum torque angle (MTA) set at 85˚, and then the maximum
allowable impedance reach is:
|"DEF ** |
"G H
cosMNOPQ @ N #* R
Eq. (88)
1351.0 Ω
"G H
cos>85.0° @ 56.3°?
1651.0 Ω
"G H
0.8771
"G H 1540.3∠85.0° Ω
Option 11b represents the calculation for a generator step-up (GSU) transformer applying a phase time overcurrent
(51) relay connected to an asynchronous generator. Similarly, Option 18 may also be applied here as well for
generation interconnection Facilities and Option 19 for the phase directional time overcurrent (67) directional
toward the Transmission system relays for generation interconnection Facilities. In this application it was assumed
100 Mvar of static compensation was added.
767.6 !
5 575.7 123
Options 11b, 18, and 19, Table 1 – Bus Voltage, calls for a 1.0 per unit of the high-side nominal voltage for the
generator bus voltage (Vgen):
345
( 959.5∠36.9°
(
d*
√3 4
Eq. (93)
959.5
d*
1.73 4 345
d* 1605
d*
d#0
+,-.
Eq. (94)
1605 A
d#0
2000
5
d#0 4.014 A
End of calculations