ch 5
ch 5
Institute of
Technology
School of civil engineering
and Architecture
Principles Of Construction
Management
BY: Mohammednur H.
Chapter Five
Project Constraints’ Management
Project Scope Management
• No matter how well a project has been planned, there
will always be changes in scope. The general rule is
that if the work performed is not in the contract it is a
change in scope. The best approach is to not perform
the work until proper authorization has been granted.
• Project scope Management Involves the processes
required to insure that the project includes all the
work required.
Chapter Five…
• Project Scope Management generally has three
major processes: Project Scope Definition,
developing scope management plan and Change
Monitoring
• Scope management begins with scope definition,
which refers to the client’s brief, essentially the
client’s objectives or the desired end product. Once
the scope definition of the project (or the client’s
objectives) is down in writing, scope management
planning can begin. Without a clear scope definition,
proper scope management is virtually impossible.
Chapter Five…
❖ Tools and processes of scope definition :
✓ Expert judgement
✓ Statutory requirement
✓ Stakeholder requirement
✓ Product analysis
✓ Alternative generation
✓ Design, Specification and Drawing
Chapter Five…
• The Scope management plan is developed during
the pre-construction conceptual phase and refined in
the development phase. Scope must be developed to
a point where a program and a budget can be fixed to
it
• In other words, it clearly outlines the extent of the
project, available budget, and times frames where
three fundamentals must be agreed and signed off by
the client:
• Extent defined by drawings and specifications
• A budget based on the drawings
• A program to identify the project time frame
Chapter Five…
• Determining reasonable scope changes, subdividing
the project into manageable components, creating
WBS, developing scope change approval methods
are main parts of scope management plan process.
• The agreed scope framework forms the construction
project baseline against which all design, cost and
program objectives are measured.
• The Change Monitoring Process of the Project
Scope is a estimate to scan the major deliverables or
outputs of the project and carryout change
management.
Chapter Five…
❖Tools and processes of change monitoring:
✓ process inspection
✓ variance analysis
✓ scope validation/ verification
Chapter Five…
Project time management
– Project Time Management includes the processes
required to manage the timely completion of the
project. The project time objective specifies the
project completion time.
– Most projects are not completed on estimated
time because of the absence of a project time
planning and scheduling.
Chapter Five…
• There are three fundamental stages to this
process:
◆ Planning stage
◆ Sequencing stage
◆ Scheduling stage
❑ Planning stage: This is where the construction
manager identifies all of the activities needed to
build the project. The number of activities and the
level of detail needed in the schedule will vary from
job to job. The more complex the project, the more
detailed the activity list will be.
Chapter Five…
• Tools processes of time planning:
✓ Project Document
✓ Decomposition
✓ Define Units of Measure
✓ Project Scope Baseline/WBS
✓ Environmental Factors
✓ Organizational Process Assets
Chapter Five…
❑ Sequencing stage: Once you have identified
all of the activities that need to be performed on your
project, it is time to develop the sequencing of those
activities, or network logic.
1. Activity on
arrow notation
2. Activity on
node notation.
Chapter Five…
Critical Path Method
• It is the most widely used scheduling technique. It
represents the set or sequence of predecessor/
successor activities which will take the longest time
to complete. It is defined as the longest possible path
through the "network" of project activities.
• The duration of the critical path represents the
minimum time required to complete a project. Any
delays along the critical path would imply that
additional time would be required to complete the
project.
Chapter Five…
Example:-
B(1) E(4)
F(1) H(3)
A(2) C(2)
D(1) G(3)
B 2 ----
C 5 A
D 4 A
E 6 B,C
F 2 B,C
G 3 D,E
H 2 D,E
I 7 F,G
J 5 H,I
Chapter Five…
b. Critical path
ISO 9000