0% found this document useful (0 votes)
25 views

Daily Progress Report 24-02-24

Uploaded by

Alam Xaib
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

Daily Progress Report 24-02-24

Uploaded by

Alam Xaib
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Daily Progress Report, All Packages PHA-F, I-12, Date: 24-02-2024

Sr Contractor Package Technical Labor Daily Activities


Staff
1 Rehman 01 08 60 Block A:
Construction 1. Glaze tile fixing of 7th floor bath + kitchen
Company 2. External plaster work for 9th floor flats
3. Plumbing work external
4. Installation of 6mm cable 9th floor flats
5. Electrical wiring 6th floor flats
6. Water proofing top roof
7. Paint work 8th floor flats

Block D:
1. Block masonry of 9th floor flats
2. Plaster work of 7th floor flats
3. Distemper work 6th floor flats

Block E:
1. No activity

2 Abid 02 02 38 Block J:
Construction
Company 1. Floor tiles grinding 7th floor
2. Bib cock & shower fitting 7th floor
3. Internal wall distemper 3rd & 4th floor

Block H:
1. Window cleaning & paint Ist floor
2. Internal wall distemper work Ist floor
3. Dewatering lower basement
4. Electrical finishing works GF

3 Malik 03 01 05 Block N:
Construction
Company 1. Granding work at top floor

Block P:

1. Washrooms tile fixing 5th floor

4 Gondal 04 01 03 Block T:
Construction 1. 5TH floor paint repairing work
Company 2. 6th floor window repairing work
3. 8th Skirting grinding

Block Q:
1. 5th floor window repairing work
Daily Progress Report, All Packages PHA-F, I-12, Date: 24-02-2024
5 Gondal 05 01 01 Block U:
Construction
Company 1. Paint repairing work

Block X:
1. No Activity.

Block Y:

1. No Activity.

6 Conpro PVT 06 02 08 Block B:


LTD 1. Maintenance at various floors
2. Cleaning of lift shaft & basements

Block C:
1. No activity

Block F:

1. No activity

7 Conpro PVT 07 03 11 Block G:


LTD
1. Material shifting for plaster at mumty & OHWT
2. Drain work
Block K:
1. Cleaning at various floors

8 Ismail 08 02 22 Block R:
Construction
Company 1. OHWT chips work

Block S:
1. No activity
BLOCK L:

1. Formwork of 4th floor


beams
2. GF plaster work
3. Material shifting 3rd floor
4. Door/window formwork
GF
Daily Progress Report, All Packages PHA-F, I-12, Date: 24-02-2024
9 Malik 9 2 11 Block V:
Construction 1. 2nd floor column steel fixing
Company

Block W
1. No activity

Block Z:

1. Plaster repair work at 2nd floor


2. Block work at 4th floor
3. Steel cutting for slab

10 Malik 10 1 00 UGWT:
Construction
Company 1. No activity

You might also like