Daily Progress Report 24-02-24
Daily Progress Report 24-02-24
Block D:
1. Block masonry of 9th floor flats
2. Plaster work of 7th floor flats
3. Distemper work 6th floor flats
Block E:
1. No activity
2 Abid 02 02 38 Block J:
Construction
Company 1. Floor tiles grinding 7th floor
2. Bib cock & shower fitting 7th floor
3. Internal wall distemper 3rd & 4th floor
Block H:
1. Window cleaning & paint Ist floor
2. Internal wall distemper work Ist floor
3. Dewatering lower basement
4. Electrical finishing works GF
3 Malik 03 01 05 Block N:
Construction
Company 1. Granding work at top floor
Block P:
4 Gondal 04 01 03 Block T:
Construction 1. 5TH floor paint repairing work
Company 2. 6th floor window repairing work
3. 8th Skirting grinding
Block Q:
1. 5th floor window repairing work
Daily Progress Report, All Packages PHA-F, I-12, Date: 24-02-2024
5 Gondal 05 01 01 Block U:
Construction
Company 1. Paint repairing work
Block X:
1. No Activity.
Block Y:
1. No Activity.
Block C:
1. No activity
Block F:
1. No activity
8 Ismail 08 02 22 Block R:
Construction
Company 1. OHWT chips work
Block S:
1. No activity
BLOCK L:
Block W
1. No activity
Block Z:
10 Malik 10 1 00 UGWT:
Construction
Company 1. No activity