Method Statement for Earthing System
Method Statement for Earthing System
PROJECT
Wave 6&7
1 | P ag e
Contents
1. SCOPE..........................................................................................................................3
2. DEFINITIONS.............................................................................................................3
3. RESPONSIBILITIES...................................................................................................3
4. MANPOWER REQUIRED.........................................................................................5
5. MATERIALS REQUIREMENTS................................................................................5
6. EQUIPMENTS REQUIREMENTS.............................................................................5
7. WASTE MANAGEMENT...........................................................................................6
9. OPERATION................................................................................................................6
13. DISTRIBUTION......................................................................................................8
2 | P ag e
1. SCOPE
This procedure to clear the method of the supply, installations of Earthing System for the
project.
This document details the Earthing System Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control
Engineer. WIR : Inspection and Test Request
MIR : Material Verification Record.
3. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out according
to the Contract Specification and with the approved drawings.
2. To ensure that the progressing of works is carried out according to the planned
program and as per the approved method of statement.
3. To ensure that all the equipment and material required executing the work are
available according to the planned construction program.
4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a
safe and proper execution of the works.
QC Engineer
1. The QC Engineer is responsible for compliance of complete work as per the
approved method statement will offer consultants approvals
3 | P ag e
2. Ensure WIRs and MIRs are being raised for activities in timely manner and
inspected by the Consultant.
3. He will follow and carried out all the relevant tests as per project specifications.
4. Obtain the required clearance prior to any inspections.
5. Coordinates with other Dept and Should acquire any necessary works clearances.
SITE ENGINEER
1. To ensure that the works are carried out according to the Contract Specification,
approved method statement and the shop drawings.
2. To provide all necessary information and distribute responsibilities to his
construction.
3. To monitor the progress of work in relation with the work program and to report
to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are carried out
in safe practicing method.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination
with the site engineer on daily basis, and ensure proper distribution of the work
force on the required and planned locations.
2. To ensure that his assistant foreman/ charge hand is aware of the job requirements
and they have enough information to carry out their duties properly.
3. To ensure that the daily work is progressing as planned and advice the site
engineer of any requirement for additional resources.
4. To ensure in consultation with the site engineer that the manpower involved in the
works are moving as agreed and planned for the work.
5. To control disposal of waste materials according to the instructions received from
the site engineer.
6. To ensure full coordination with the safety officer to maintain safe working and
proper housekeeping of the site, following the proved safety measures and further
ensure that all his working team are aware of the same to prevent accident and
losses.
7. To inform the site engineer regarding areas ready for inspection.
8. Foreman and the storekeeper are responsible for the distribution and control of
materials.
4 | P ag e
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with the HSE
plan and everybody aware of it for its proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe
working on the site.
3. Inspect all the site activities and train the person to prevent accidents and its
proper implementation.
4. Ensure that the site is maintained clean and tidy.
STORE KEEPER
Responsible for overall Store operations in making sure to store the material delivery to
the site and keep it in suitable area that will keep the material in safe from rusty and
damage.
One who will acknowledge the receiving of materials at site in coordination with QA/QC
and concerned Engineer.
4. MANPOWER REQUIRED
Charge hand and Experienced Technicians
5. MATERIALS REQUIREMENTS
Earthing System Components and Accessories.
6. EQUIPMENTS REQUIREMENTS
The Equipment that will be engaged for Earthing System Installation will be as follows:
Hand Tools
Power Tools (if required)
Diagonal-Cutting Pliers
Wire Stripper/Cutter with Spring
Side-Cutting Pliers
Shank Screwdriver/Flat screw driver
Compression lug crimp tool
Necessary conduit for System Cabling
Knock out set (for conduit)
P.P.E. – Personal Protective Equipment (safety helmet, Boots, gloves & safety vest)
5 | P ag e
7. WASTE MANAGEMENT
The Rubbish which would be created from our scope of works will be disposed to
the designated dumping ground.
9. OPERATION
Material:
6 | P ag e
Compression type connectors may be used where approved by the Consultant.
Measure the resistance of the complete installation and submit for review to the
Consultant.
Concrete inspection pits with cover shall be installed flush with finished floor
level and be fully accessible.
The complete installation shall be tested and inspected to ensure that it complies
with the requirements of the Specification and the Local Authorities.
7 | P ag e
Lifting operation permit (using crane) where applicable.
Confined space permit where applicable.
Approved work method statement and risk assessment will be made available to
site.
All workers doing the work shall be briefed on this method statement and risk
assessment.
13.DISTRIBUTION
Copy of this method statement shall be issued to the following for information/
action/ comments:
Project Manager
Site Engineer
Foremen
Safety Engineer
Technician from Supplier
Store Keeper
Inspection and Test Plan (ITP) For Method of Statement for Earthing System.
ITP shall identify all relevant Inspection and Testing activities to be carried out by
SAC and Subcontractor.
1. Inspection for comply the Using Material with specification with approval.
The Subcontractor shall use the SAC ITP document or their own in accordance with
the Project Requirements and submit to the Project team for review and approval prior
to undertaking specific project activities.
8 | P ag e
All contract specific ITP’s and Field Inspection Checklists (FIC) shall be provided to
the Client and its representative and Consultant for review and approval prior to work
commencing.
ITP’s and FICs shall be progressively compiled with the Project Specification and
client recommendation nominated SAC Project Engineer shall progressively sign off
each ITP and FIC on completion of each designated activity and present the ITP’s and
FICs to the Client and its representative or Consultant progressive sign off.
Check Activities
All inspection and surveillance activities involving SAC Site Supervision, Consultant
and Client Project Representative shall be nominated on the ITP and signed off at the
appropriate stage when completed.
The activities shall be done under witness by SAC Site Supervision, Consultant and
Client Project Representative.
Request for Inspection (RFI) form shall be sent to Consultant and Client.
Occurs during the process function where the Client Representative and Consultant
(at least 12 hours) given to the Client Representative and Consultant, And failure to
A Hold Point defines a critical inspection point in the construction process whereby
work must not continue past this point until all relevant inspections have been
completed and signed off. Hold Points designate a stop in the process, different to
that of the
9 | P ag e
Witness Point where the process can continue. Following RFI (at least 24 hours) given
to the Client Representative and Consultant.
failure to attend, SAC shall regard the Client Representative and Consultant accept the
quality of the point and shall past to the next point.
Review (R)
Monitoring (M)
SAC inspector /the Client and it’s representative and consultant engineer(s) to ensure
compliance.
10 | P ag e
15. ITP FORM
INSPECTION & TEST PLAN
SAC REF. No.:
REV. No.:
Material
inspection Clause of
4 according to Specification H H
Project Material Submittal
Specification
Clause of
Specification
5 Installation W W
Approved Shop
Drawings
Bare copper
6 cable and Clause of Specification H H
ground rods
7 Connections Clause of Specification W W
MAIN MAIN
CONSULTANT APPROVAL
CONTRACTOR CONTRACTOR
NAME: NAME:
SIGNATURE: SIGNATURE:
DATE: DATE:
11 | P ag e
16. RISK ASSESSMENT
Current Risk
Activity Potential Hazards Existing control
L S Risk
Only certified operator to operate the lifting equipment.
Lifting gears to be use must be certified by approved
Use of lifting third party.
4 1 4
equipment Copy of certificates to be keep and made available in
the work area.
Unsafe lifting
Assign certified banks-man / rigger.
Loading/ unloading procedure.
Foreman to conduct daily crew talk prior to start the
of cable drums using Damage to
activity.
Boom Truck equipment, injury 3 2 6
Post appropriate warning signages.
to workers,
Barricade the work area to avoid unauthorized entry.
Danger to public
12 | P ag e
Obtain hot work permit prior to start work.
Open flame. Only competent person to do the cad welding activity.
Earthing cable Fire hazard Assign competent fire watchman equipped with
jointing (cad Explosion sufficient firefighting equipment. 3 1 3
welding) Property damage Follow necessary precautions written on the hot work
permit.
Only competent person to perform the testing.
Use only approved and calibrated certificate to keep
along with the equipment.
Testing of earthing
Electrocution Follow earthing system method statement and work 2 1 2
system
procedure.
Use proper PPEs
13 | P ag e
17. CHECK LIST
CHECK LIST FOR INSTALLATION OF EARTHING SYSTEM
Contractor : Form No:
Rev No:
Sub-Contractor : Page: 1 of 1
SECTION OF LOCATI
WORK: ON
LEVEL:
Checked by
Stage Item Date
Yes No N/A
Check if sizes of the earthing wires
are as per the approved shop
drawing.
Check cable trays, trunking, and
equipment Equipotential bonded
as per project specification.
Check if locations and sizes of earth
bar are as specification and
approved shop drawings.
Earthing Check if that earthing wire(s) is
System connected to equipment as per shop
drawing in proper way.
14 | P ag e