0% found this document useful (0 votes)
11 views

Method Statement for Crane and SPB Lifting

Swms

Uploaded by

BalaKrishna Goru
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views

Method Statement for Crane and SPB Lifting

Swms

Uploaded by

BalaKrishna Goru
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

CHAITANYA INFRA PRIVATE LIMITED

Method statement For Tower cranes and SPB Lifting & Jumping.

Implementing a clear tower crane and SPB lifting plan ensures safety and efficiency.
The plan includes:

. Strategic placement of SPB initials for lifting and jumping.

. Staggered height management between the crane and SPB.

. Real-time monitoring of operations.

1. Planning Phase

1.1. Engineering Study

• Conduct a detailed engineering analysis to determine:

• Tower crane / SPB height and load capacity.

• SPB specifications, including weight and dimensions.

• Ground conditions and foundation strength.

• Wind and weather conditions at the site.

1.2. Risk Assessment

• Identify potential hazards, such as:

• Instability of the crane or SPB during lifting.

• Ground settlement or uneven surfaces.

• Weather conditions (wind, rain, etc.).

• Develop mitigation measures.

1.3. Equipment Selection

• We Choose appropriate equipment based on:

• Required lifting height and load.

• Crane type (crawler, mobile, or hydraulic).

• Additional support systems like guy wires or outriggers.

Method statement For Tower cranes and SPB Lifting & Jumping 1
CHAITANYA INFRA PRIVATE LIMITED

2. Preparation Phase

2.1. Site Setup

• We already Ensured a level and stable ground for the tower crane.

• Installed a concrete foundation and base plate as per design requirements.

• Barricaded the lifting area to restrict access.

2.2. Inspection and Testing

• Inspect all lifting equipment:

• We Check crane’s structural integrity and mechanical systems.

• We Verify the load charts and calibration of the lifting mechanism.

• We can Conduct load testing for SPB components if needed.

3. Lifting Execution

3.1. Tower crane Lifting

• Erection:

• We already done the erection of tower crane in the lift cut out area.

• We Sequentially add mast sections using the tower crane’s climbing frame as mentioned in the
drawing which we submitted.

• We Monitor plumbness and secure each section with bolts.

• Safety Checks:

• We Perform checks after every mast section is added.

• We Ensure stability using guy wires or tie-ins to the structure.

Method statement For Tower cranes and SPB Lifting & Jumping 2
CHAITANYA INFRA PRIVATE LIMITED

3.2. SPB Lifting

• Lifting Process:

• We Secure the SPB with slings or lifting beams at designed points as per the submitted drawing.

• Slowly we raise the SPB while ensuring it remains level.

• We Use tag lines to control movement and prevent swinging.

• Alignment and Placement:

• P & M in charge can Guide the SPB into position using personnel on the ground.

• We Check alignment and adjust as needed before final placement.

4.Jumping Procedure for SPB:

4.1 Staggered Height Maintenance:

• Ensure a minimum staggered height of 6.0 meters between the crane and the SPB during operations.

. Jumping Sequence:

• Perform SPB jumping every two floors, alternating with girder changes.

4.2. Girder Usage:

• Use three girders at the initial stage.

• Remove one girder after the first slab is cast.

• One additional girder will be kept rotating for continued support and operation

5. Post-Lifting Activities:

5.1. Inspections

• Inspect the installed tower crane and SPB for stability and alignment.

• Check for damages to components or anchor points during lifting.

Method statement For Tower cranes and SPB Lifting & Jumping 3
CHAITANYA INFRA PRIVATE LIMITED

5.2. Safety Protocols

• TPI can Conduct a briefing to address issues encountered during lifting.

• Ensure compliance with safety standards and regulations.

5.3. Documentation

• Maintain records of:

• Lifting plan and execution.

• Inspection reports.

• Lessons learned for future operations.

6. Safety Considerations

• We have Appointed a qualified lifting supervisor.

• We also Monitor weather conditions throughout the operation.

• Will Ensure all personnel wear appropriate personal protective equipment (PPE).

• We Implement an emergency response plan in case of failure.

Detailed Drawing have been given in the submitted drawing.