0% found this document useful (0 votes)
4 views12 pages

Exercise

Uploaded by

Nam Thái Hoài
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views12 pages

Exercise

Uploaded by

Nam Thái Hoài
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

EX1

5 10 15 20 25 30 35 40
Brief 5 7 1 4
Release 6 11 6
Market 12 15 45 9
Launch 3 9 4 2
Total
Weekly 5 13 24 25 48 18 4 2
Cumul. 5 18 42 67 115 133 137 139

EX2
1 2 3 4 5 6 7 8
A
B
C
D
E
F

EX3

A B C D E F Total
PV 10 15 10 25 20 20 100
EV 10 15 10 10 20 0 65
AC 9 22 8 30 22 0 91
SV=EV-PV 0 0 0 -15 0 -20 -35 -35
CV=EV-AC 1 -7 2 -20 -2 0 -26 -26
SPI=EV/PV 0.65
CPI=EV/AC 0.71

EX4

You are required to:


Calculate estimated time to completion
Calculate estimated cost to completion
Assume the project is planned for a 12-month duration and a $250,000budget.

Activity Jan Feb Mar Apr May Jun Plan %Comp


Staffing 8 7 15 100
Blueprinting 4 6 10 100
Prototype
Development 2 8 10 70
Full Design 3 8 10 21 60
Construction 2 30 32 25
Transfer 10 10 0
Monthly Plan 8 11 8 11 10 50 98
Cumulative 8 19 27 38 48 98
Monthly Actual 10 15 6 14 9 40
Cumul. Sctual 10 25 31 45 54 94

EX5
EV, AC, and PV data from a project for a five-month period are in the table below

You are required to:


Complete the table.
Calculate SPIC and CPIC
Compare the cost and schedule performance for the project on a month-by-month basis and cumulatively. How wo
project? (All values are in thousands $)

EX6:
Consider the following project information. The total budget is $36,000 and is expected to last six months. After fou
you have calculated the following information about the project:
PV = $29,000
EV = $30,500
AC = $28,000
Based on this information, you are required to:
Calculate the SPI and CPI.
Calculate estimated time and cost to completion?
Indicate the project status?

36000 6
a. b.
PV 29000 Estimated time 5.70 (Time/SPI)
EV 30500 Estimated cost 33049 (Cost/CPI)
AC 28000
SPI=EV/PV 1.05 c.
CPI=EV/AC 1.09 The project is ahead schedule and under cost
45 Total 5 10 15 20 25
Cumul. 5 18 42 67 115

Cumul.
1
160

1 140

140
120

100

80

60

40

20

0
5 10 15 20 25 30 35

9 10 11 12 13 14 15 16 17
(EV)Value SPI=EV/PV 0.54
15 CPI=EV/AC 0.56
10
7
12.6 Estimated time to completion = Planned time/SPI 22.3574
8 Estimated cost to completion = Planned cost/CPI 446768
0
52.6

le below

EV Evc AC
April 8 8 10
May 17 25 18
June 25 50 27
July 15 65 18
August 7 72 9

d cumulatively. How would you assess the performance of the

ast six months. After four months,


d under cost
30 35 40 45
133 137 139 140

Cumul.

0 25 30 35 40 45
months
$

Acc PV PVc SPI SPIc CPI CPIc


10 7 7 1.14 1.14 0.80 0.80
28 16 23 1.06 1.09 0.94 0.89
55 23 46 1.09 1.09 0.93 0.91
73 15 61 1.00 1.07 0.83 0.89
82 8 69 0.88 1.04 0.78 0.88
1 2 3 4 5 6 7 8 9 10 11 12 13
A
B
C
D
E
F
G
H
I
J

A C G H J

A B E I J
14 15 16 17 18 19 20 21 22

You might also like