WRONG QUESTION
WRONG QUESTION
Test 1
Q1.A project manager must submit various high-level performance reports to executive
managers throughout the organization. The project team broke down the work to align with
the reporting needs to integrate costs, resources, and scope. Which level of the WBS should the
project manager report?
Select one:
A. Control account
B. Activity list
C. Work package
D. Planning package
Your answer is incorrect.
Managers throughout the project manager's organization are requesting performance reports
at a high level. They are not seeking the detailed data for low-level operations and activities.
The control accounts integrate the costs, scope, and schedule points and compare their
performance using the earned value management metrics.
The correct answer is: Control account
Q2.A project has been in execution for several months, and project communications have been
sent out regularly. During a meeting with the customer, some of the stakeholders indicate they
have not received the most recent performance report, which is supposed to be sent out every
two weeks. What should the project manager do first?
Select one:
A. Update the lessons learned register
B. Review the communications management plan
C. Update the change log
D. Document the issue in the issue log
Your answer is incorrect. The issue log is a project document where all issues encountered
during a project are recorded and tracked. Having just become aware of the problem with the
receipt of the most recent performance reports, the project manager would first want to
update the issue log with the information so that the matter can be documented, tracked, and
eventually resolved.
The correct answer is: Document the issue in the issue log.
Q3. A project to build a new generation nuclear reactor to power a small city has just started.
The public is divided on the project. While many have no concerns, some are worried about
safety, and others think it will have cost overruns. How should the project manager deal with
communicating the potential risks and issues?
Select one:
A. Risks and issues are internal to the project and do not need to be communicated outside the
project
B. Make the risk register and issue log a public document for the sake of transparency
C. Describe the information sharing process with the public in the communications
management plan
D. Invite the public representatives to the daily standup meetings with the project team
Your answer is incorrect. The communications management plan should outline the process
of information sharing with both internal and external stakeholders.
The correct answer is: Describe the information sharing process with the public in the
communications management plan
Q4. During project planning, a project manager allocates a dedicated team member to develop
and distribute weekly project status reports to project stakeholders. What project document
should reflect this repetitive and time-consuming task?
Select one:
A. Quality report
B. Risk register
C. Project schedule
D. Communications log
Your answer is incorrect. The project schedule is a project document that presents linked
activities with planned dates, duration, milestones, and resources. The project manager has
assigned a dedicated team member to develop and issue status reports. The project manager
should update the project schedule to reflect these communication activities.
The correct answer is: Project schedule
Q5. The sponsor asked the project manager to share the project progress and recommunicate
project objectives to the stakeholders. After reviewing the communications management plan
and the stakeholder engagement plan, the project manager decides that a presentation at the
upcoming project status meeting would be the best way to share the information. The
presentation is well received with a lot of positive feedback.
Which of the following should the project manager update?
Select one:
A. Communications management plan
B. Project communications log
C. Organizational process assets
D. Stakeholder engagement plan
Your answer is incorrect. Organizational process assets (OPAs) can be grouped into two
categories; processes, policies, and procedures, and organizational knowledge bases. The OPAs
that fall into the corporate knowledge bases are updated throughout the project with project
information. The presentation that the project manager gave is an example of the type of
information that would be added to the knowledge base aspect of the OPAs. Therefore, the
next thing the project manager should do is update the OPAs with his presentation.
The correct answer is: Organizational process assets
Q6. The updated version of the product is to be at the customer's location by the end of the
week, but the deliverable, despite the team's best efforts will not be complete by then. The
deployment team who is supposed to install the product at the customer site is under a lot of
stress to meet the deadline and will be furious that the update will not be there at the end of
the week. What is the project manager's best action?
Select one:
A. Send the status report to the customer
B. Cancel the installation at the customer site
C. Wait until the deadline hoping the team eventually makes it
D. Make the phone call to the customer to inform them of the delay
Your answer is incorrect. Communicating the status and the details to all affected stakeholders
is more important than worrying about disappointing them. The customer needs to know this
information to make accommodations and plan accordingly.
The correct answer is: Make the phone call to the customer to inform them of the delay
Q7.A project manager has compiled a project performance report as requested by the project
sponsor. The project manager prepares an email to communicate her findings. She is careful to
format the report in a way that can be easily understood by the sponsor once received. Which
of the following components of a basic communication model will be used by the project
manager and the sponsor?
Select one:
A. Encode and decode
B. Writing style
C. Interactive communication
D. Choice of media
Your answer is incorrect. Encoding and decoding are components of a basic communication
model. In preparing the email, the project manager is the sender encoding information in a
manner that can be understood by the sponsor, and as the receiver, the sponsor will decode
the message once received. An additional component transmits the message (sending the
email). Transmission occurs between the 'encode' and 'decode' steps.
The correct answer is: Encode and decode
Q8. During a status update meeting, a project manager informs stakeholders that the project is
running behind schedule but under budget. With all meeting participants being in consensus,
the decision is made to crash the schedule. Two weeks later, the finance director calls the
project manager stating that she just learned about the schedule issue but never agreed to
cover the expenses of crashing. When asked why she did not speak up during the meeting, the
finance director replies, "What meeting?"
Lack of which of the following skills most likely caused the project manager to run into this
situation?
Select one:
A. Meeting management
B. Cultural awareness
C. Conflict management
D. Active listening
Your answer is incorrect. Meeting management involves preparing an agenda, inviting
essential participants, and ensuring they attend. Eased on the scenario described, it is
reasonable to assume that you either forgot to invite the finance director to the meeting or
invited her but did not ensure she attended. Therefore, among the available choices,
inadequate meeting management is the most likely cause of the problem described by the
question.
The correct answer is: Meeting management
Q9. A project manager sends an email to the product developers notifying them of a critical
defect found by the customer and asking them to report back to her so that she could update
the sponsor. The next day, the project manager is bombarded by the developers stopping by
her office to defend their efforts and point the blame elsewhere. What could the project
manager have done differently to obtain a more positive response from the developers?
Select one:
A. Chosen different communication media
B. Used push communication method
C. Asked the developers to update the sponsor directly
D. Used pull communication method
Your answer is incorrect. The matching of media to messages is an important aspect of effective
communication and effective management. For example. deciding when it is better to
communicate in writing versus orally, or deciding when to prepare an informal memo versus
drafting a formal report. The developers' response to the email suggests that the project
manager might have been better off sharing the information verbally allowing for more
interaction between her and the developers.
The correct answer is: Chosen different communication media
Q10. A project manager recently lost some key subject matter experts due to a business
reorganization, and most of the work on the deliverable needs to be subcontracted out.
Which of the following best describes how project communications will be affected?
Select one:
A. The number of communication channels will increase.
B. The formality of the communication will increase.
C. The communication needs to be more frequent.
D. The number of communication channels will decrease.
Your answer is incorrect. With internal teams, communication can be more casual, as it is
easier to get clarification and there are fewer legal implications. In a more formal contract
situation with a vendor, communications need to be more formal and conform to what is
required under the contract.
The correct answer is: The formality of the communication will increase.
Q11. A project has been initiated and is being planned. The project sponsor is anxious for the
project to move into execution and suggests that the project manager not spend any more time
on the development of the communications management plan.
How should the project manager respond to the sponsor to support the completion of the
communications management plan?
Select one:
A. The communications management plan is a required part of the project management plan.
B. The communications management plan assists with stakeholder engagement.
C. The communications management plan is required by The Standard for Project Management.
D. The communications management plan will improve quality.
Your answer is incorrect. The key benefit of the communications management plan is a
documented approach to effectively and efficiently engage stakeholders by presenting relevant
information promptly. Therefore, of the choices provided, this statement represents the best
response the project manager can offer to the project sponsor to support the completion of the
communications management plan.
The correct answer is: The communications management plan assists with stakeholder
engagement.
Test 2
Q1.A clinical trial is underway for a project. The information on which participants are taking the
medicine vs. the placebo is highly confidential. The project manager receives notification that one of the
participants has been hospitalized and the doctor needs to know whether the patient is taking the
placebo or the medicine. What is the project manager's best course of action?
Select one:
Your answer is incorrect. In the scenario, the information about which participants are taking the actual
medicine and which participants are taking the placebo is confidential. The communications
management plan identifies the person responsible for authorizing the release of confidential
information and therefore is the best answer to the question asked.
Select one:
A. Yes. The project's architect is part of the team and must cooperate and help manage stakeholder
engagement.
B. No. Exploiting the architect's relationship with the CEO is a violation of the PMI Code of Ethics and
Professional Conduct.
C. No. The project manager should stop trying to get the attention of the CEO.
D. Yes. There is nothing wrong with exploiting the architect's relationship with the CEO.
Your answer is incorrect. Exploiting one's relationship with the project stakeholders is an example of
networking. Networking may help the project manager and the team influence the actions of their
stakeholders (e.g., the CEO), and increase stakeholder support for the work and outcomes of the
project, thus improving performance.
The correct answer is: Yes. There is nothing wrong with exploiting the architect's relationship with the
CEO.
Q3. Project communications have not been well received. While the technical stakeholders are satisfied
with the content of the reports, the human resources stakeholders feel that the content is too technical
and therefore do not read the reports. What aspect of planning communications was missed during the
development of the communications approach for the project?
Select one:
Your answer is incorrect. Cultural awareness is an understanding of the differences between individuals
or groups and adapting the project's communication strategy accordingly. People from different
professional disciplines represent different cultures and therefore, may require a different type of
communications. The project manager should have been more aware of the cultural differences within
the stakeholder community and adjusted the communications accordingly.
Q4. During project execution, you discovered that some of the key stakeholders are not keeping up with
project developments. The stakeholders indicate that most of the information on the weekly reports are
irrelevant and they do not have time to read all of the content. As a result, these stakeholders have
missed several key action items, thereby, putting the project behind schedule. What is most likely the
cause of this issue?
Select one:
c. Emailing the report rather than allowing the stakeholders to pull the information at their convenience
d. Sharing the report using information radiators instead of social media
Your answer is incorrect. Project information is distributed to many groups of stakeholders and should
be adapted to provide information at an appropriate level, format, and detail for each type of
stakeholder as specified in the communications management plan. Therefore, sending the same report
to all stakeholders without adapting it to the needs of the recipients most likely caused the issue
described in the scenario.
The correct answer is: Sending the same report to all stakeholders
Q5. A project manager has been called into an urgent meeting with senior management that starts in an
hour, which is the same time that the project manager is supposed to attend a brainstorming session
being held by the project team to determine the best technical approach for the development of the
features for the next iteration. What should the project manager do?
Select one:
A. Reschedule the brainstorming meeting so the project manager can facilitate the session
B. Attend the first half of the management meeting and then ask to leave to join the team
C. Postpone the senior management meeting until after the brainstorming meeting
D. Attend the senior management meeting, then get an update from the team later
Your answer is incorrect. The project team is capable of conducting their own brainstorming session. A
project manager's time is better spent on the senior management meeting. Communication between
the project manager and team can happen before and after the meetings.
The correct answer is: Attend the senior management meeting, then get an update from the team later
Q6. As part of the Monitor and Control Project Work process, your project team created a project status
report which included burndown charts, earned value graphs, and other information. The information
contained in the report is of vital importance to several stakeholders who rely on the information to
take appropriate action. What should be done next?
Select one:
A. Submit a change request to update the communications management plan before communicating the
report
B. Distribute the report as part of the Monitor Communications process
D. Disseminate the report through the Monitor and Control Project Work process
Your answer is incorrect. Work performance reports are the output of the Monitor and Control Project
Work process, and a project status report described in the scenario is an example of a work
performance report. These reports are then circulated to the project stakeholders through the Manage
Communications process as defined in the communications management plan. Therefore, the next step
in this scenario is to carry out the Manage Communications process by communicating the project
status report according to the communications management plan.
The correct answer is: Carry out the Manage Communications process to communicate the report
Q7. To assess the effectiveness of communications activities on your project, you review a matrix, which
compares current and desired stakeholder engagement levels. What tool or technique are you using?
Select one:
A. Expert judgment
B. Inspection
C. Data representation
D. Stakeholder register
Your answer is incorrect. You are reviewing a matrix that compares current and desired stakeholder
engagement levels. This matrix is known as the stakeholder engagement assessment matrix and is an
example of the data representation technique that can be used during the Monitor Communications
process to assess the effectiveness of communications on a project.
Q8. Executives in a certain business unit of the company have failed to attend project related meetings.
The project manager has sent multiple invites and requests to respond. Another project manager tells
him that he must work with the administrator of the respective business units to get any response and
attendance. Which skill did the other project manager demonstrate?
Select one:
C. Political awareness
D. Meeting management
Your answer is incorrect. Awareness of the relationships and power structures within the organization
is a skill that the project manager demonstrated by explaining the means to reach and influence others
in a system.
Select one:
Your answer is incorrect. Since you want to make a change to the project communications method, you
would need to update the communications management plan. This plan is a component of the project
management plan, therefore, an approved change request will be required to modify it. While this
choice does not indicate the change request, of those provided, this option is still the best answer to the
question asked.
Q10. The project manager provides a project status report at the end of each sprint as mandated by the
communications management plan. However, during a sprint retrospective, a scrum team member
states that some stakeholders are asking for interim updates, which causes a distraction from the
development work. What is the project manager's best course of action?
Select one:
A. Capture the information in the issue log as an impediment and assign the problem to the project
sponsor for follow up
B. Utilize information radiators, including burn charts, to communicate project status and refer
stakeholders to those resources
C. Invite the stakeholders to the sprint review meetings so they can see the progress being made so far
on the project
D. Ask the stakeholders to stop contacting the development team and tell them to wait until the project
status report is issued
Your answer is incorrect. The purpose of an information radiator is to provide the most current
information to interested stakeholders without disturbing the team. When information radiators are
used in digital format, the information can be updated virtually in real-time, thus allowing anyone to see
the project status instantaneously.
The correct answer is: Utilize information radiators, including burn charts, to communicate project
status and refer stakeholders to those resources
Q11. Due to organizational policy, all project messages use a common subject line to differentiate them
from other projects in the organization. The project manager has been using this communication
method to request scope validation sign-offs from key stakeholders. However, the project has suffered
delays due to missing sign-offs. What should the project manager do to keep this issue from continuing?
Select one:
A. Schedule a series of automated reminder messages after each sign-off request using several
communication methods (email, instant message, text, internet dashboard).
B. Formally deliver sign-off requests for scope validation in a weekly event for product demonstration
and follow up personally with any absent stakeholders.
C. Instead of a common subject line, make the call to action clear, such as "your sign-off requested" to
differentiate feedback requests from reports that do not require action.
D. Escalate the issue to the stakeholders' managers and ask that more responsive staff be assigned to
your project.
Your answer is incorrect. Scope validation sign-off is critical to project success and deserves a regular
event that the requisite stakeholders make a point of attending (either in person or virtually). The event
provides a forum for inspection, validates that your team has produced quality deliverables, gives your
team an opportunity to be clear on any required corrections, and allows the relevant stakeholders to
sign off on the scope that has been demonstrated.
The correct answer is: Formally deliver sign-off requests for scope validation in a weekly event for
product demonstration and follow up personally with any absent stakeholders.
Q12.The project is required to notify the public at various stages. A public relations specialist was
involved in planning the communications for the project. Now, when the project is in execution, the
communications with the public up to this point do not appear to be effective. A survey revealed only
2% of the public was aware of the project. Whom should the project manager contact first?
Select one:
A. A quality specialist
Your answer is incorrect. At this point to best monitor and control the communications the expert
judgment of a public relations subject matter expert is best to determine what is the next best action for
the project.
Q13. Which statement would you use to correctly explain the tools and techniques of the Manage
Communications process to your project team?
Select one:
A. Once a communication method is established with the membership of the stakeholder community, it
should not be changed. B. Presentations should consider the needs and expectations of the audience
rather than the needs of the project team.
C. Political awareness can be useful in helping the project manager maintain stakeholder support
throughout a project.
D. An organization's culture is not a factor that influences the organization's communication technology.
Your answer is incorrect. Political awareness involves the recognition of power relationships and the
ability to work within those structures. This would include understanding the power structure of the
stakeholder community on any project and fostering relationships accordingly. All of which will assist in
maintaining stakeholder support throughout the project lifecycle.
The correct answer is: Political awareness can be useful in helping the project manager maintain
stakeholder support throughout a project.