Dear students in this presentation, I shall be talking about the Work Measurement it is
importance and the techniques, which are used for work measurement and mainly I will
be covering the Time Study technique of the work measurement. Work measurement is
basically used to the standard of performance for a given job and also to find out a
ineffective time if any which is present, so that the method study can be conducted and
later on for improving the method.
The standard time is defined as the time taken by an average experienced worker for the
job, when required allowances for the force delays are taken into account. So, the
standard time includes the time taken by the worker in carrying out the job plus
allowances required for the force delays or the delays caused by the factors beyond the
control of worker.
Work measurements technique mainly starts with investigating and eliminating the
ineffective time, if it is there in existing working method and also which in turn provides
the basis for the method study. If the time study if the work measurement is to be used
for setting the standard of performance, then generally method study is conducted first
for setting the standard practice, which is not having the ineffective time. And later on
the work measurement is carried out to set the standard time for a standard practice,
which can be used for many important applications.
The objective of the work measurements are mainly to find out the presence of
ineffective time and it is extent. Whether ineffective time is present in existing method or
not and if it is there, then what is the extent of ineffective time, which is there, so that it
can be eliminated by carrying out proper method study.
So, revealing the existence of ineffective time provides the venues for method study, so
that a method of doing a particular job can be improved. Another important objective of
work measurement is to set the standard time for carrying out a job by a specific
procedure and also to set the standard output level; so that the proper production
planning and the other important activities can be carried out.
(Refer Slide Time: 03:42)
Applications of work measurement technique, which in turn results in the setting of the
standard of performance in terms of the standard time. And investigating the ineffective
time leads to have the number of benefits and these benefits appear in form of a
evaluation of the workers performance by comparing his output with the standard
performance.
The work measurement techniques can be used to compare the performance of one
worker or a group of workers and their performance can be compared with the set
standard of performance. If they are performing better then they can be then the
incentives can be given for them, so for setting the incentives and preparing the wage
plans also the standard of performance is used.
Estimating the man, material and the machinery requirement if an organization knows
that this is the rate at which the things can be produced. This is the time required for
producing an unit product then the same information can be used to quantify and to
estimate the requirement in terms of the man, material and the machinery. So, that the
production can be run smoothly and the future demands also can be met.
So, estimation of the resources for the different types of the requirements can be done
effectively if the work measurement is carried out for setting the standard of
performance. It also helps to determine the available capacity for given level of work
force and the machinery, if an organization knows this is the work force and these are the
systems available and the units can be produced at this rate, then this information can be
used to find out the rate at which the capacity of the organization for producing the given
product. So, the available capacity for a given work force and the machinery can be
calculated from the standard of performance.
To compare the work method for economic comparison purpose, if there are various
possible alternative ways for carrying out one job, then their effectiveness in terms of the
economics can be compared using the work measurement technique in terms of the work
content and the time required for carrying out the job by the different methods.
In addition to the above applications of the work measurement techniques some other
applications include establishing the wage incentive plans and the work measurement
techniques can also be used. Where the time standard set by the work measurement
technique can be used for establishing the wage incentive schemes. These are because
these are decided on the basis of performances of the worker with respect to the set
standard of performance.
The another application of the work measurement technique is to facilitate the operation
scheduling in which way things are to be done how much machine there man power is
required for completing and given output that can be successfully done, if the standard of
performance is known.
The estimation of the production cost per unit as an input can be used, if it is related with
a unit time required for producing a particular product. And, the same information can be
used for preparation of the budgets to determination of the selling price make or buy
decision and balancing the work in a group. So, the time which is required for
completing a given job and which is established by the standard of performance can be
used in number of ways in the manufacturing organizations.
What are the typical situations, work measurement techniques can be effectively used for
quantifying the work content and the setting the standard of performance is very
important to know? These are mainly applied where either entire work or the part of
work is repetitive in nature.
And, the work should have the specific characteristics apply the work measurement
related techniques like the work should be identifiable in terms of the number of units
produced by a worker. Work should be performed in reasonably consistent manner and
the volume of the work should be justifiable to perform a study and keeping the records.
The work where work measurement technique is to be applied should have very specific
characteristics, which can be quantified in terms of the units, which can be produced by a
worker. It should be done in consistent manner and whatever work measurement is
carried out.
It will involve the time and resources, so the investment of the resources will be justified
only if the volume of work which is a being done on account of the work measurement is
justified. So, the volume of the work that is why should be justifiable to perform the
study and keeping the record, then for performing the work measurement and
quantifying the standard of performance and investigating the ineffective time.
(Refer Slide Time: 10:09)
In general all measurement techniques follow seven basic steps for carrying out the work
measurement These basic steps of work measurement includes the selection of the job to
be studied, the job which is to be studied for work measurement should be economically
important and that should help in increasing the productivity of the organization.
After selection of the job next step is to record all the relevant data related to the job and
with all elements of the work. The methodology which is being used for carrying out a
particular job is recorded along with all its elements. And then after recording the
recorded method is critically analyzed to see the presence of only the required method
required movements or the required steps whether there is any unproductive or the
foreign element is present or not.
So, the critical examination of the recorded method is carried out to see the presence of
the unproductive or the foreign elements and also to see all the elements of the work are
required and necessary for carrying out the job. So, the critical examination of the
detailed breakdown of the job is carried out to find the effective motions and the method
is being used and the effective steps are separated from the unproductive and the foreign
elements.
After critical examination and separating the required steps movements and the elements
from the unproductive and the foreign elements. Next step is to quantify the work
content with the each required element, so that is the fourth step measure in which
quantification of the work involved if the each element in terms of the time is measured.
So, that work content for each element is measured in terms of the time using suitable
work measurement technique. Depending upon the nature of work and the size of the
element the different time measuring devices, and the work measurement techniques can
be used after the quantifying the time required for carrying out different elements related
with the job.
Next step is to compile, the time for each element which is time required for carrying out
the each element. So, that the time standard for the operation can be set, and this
compilation involves setting of the time for the operation using suitable allowances to
cope with the delays caused by relaxation fatigue operators personal need, etcetera.
So here, the compilation of all the elemental times plus allowances is used to find out the
standard time. And after, compiling the standard time for particular method it is defined
very precisely that, what are the steps to be used for carrying out a particular job; So, that
it will take this much time. So, that the definition regarding the time standard should be
set very precisely giving series of activities and the method of operation for which time
standard has been compiled and this the time is given for the standard specified method.
(Refer Slide Time: 14:04)
And, for carrying out the work measurement the depending upon the size of the elements
and the total time for the cycle different types of the work measurement techniques are
used. These techniques involve the time study these techniques the common techniques
are the time study work sampling standard data method and predetermined motion time
system.
The time study basically uses the use of a stop watches to quantify the time required to
carry out the different elements of the work, while the work sampling in case of work
sampling random observations of the work area is carried out to see and that what is
happening at different movements over a certain period of time. And then judgment is
made regarding the percentage of the workers who are working percentage of time the
machines are idle due to one or other reason.
So, the random observations are basically used in work sampling to see, what is
happening at any movement, the standard data method also the standard data method
uses the time already set for the basic steps and those the time values are used to find out
the total time required for carrying out the job.
And, the same thing is also used in predetermined motion time systems, where the time
values are taken from the standard data hand books for the various basic human motions
and the activities which are carried out by human being during the different kind of the
activities. Like picking up of the certain thing switching on, switching off or moving
from one place to the another with different types of with different loads all these things
have been standardized and have been and can be taken from the data hand books.
So, the predetermined time values are taken from the suitable PMTS systems and those
are compiled to find out the total time required for carrying out the particular job and
setting the standard of performance. So, actually the work study men goes to the top
floor in case of the time study and in case of the work sampling, while in other two
methods then the data which has been already developed by the time study earlier is used
for setting the standard of performance.
So here, any of these techniques can be used for setting the standard time in industry, in
case of time study suitable allowances are added to find out the standard time. And, the
standard allowances are also added in case of work sampling, while in other cases is
allowances are not added to find out the standard time.
Time study is the first and foremost and very common technique which is used for
quantifying the work content related with a particular job and its elements. This
technique is most versatile and most widely used technique of the work measurements.
It is used to estimate the time to be allowed to a qualified worker qualified and well
trained worker working at a normal pace to complete a specified job by using a specified
method. So, basically time required to carry out particular job using standard method by
a qualified worker is quantified by the time study.
And, that time is later on used to set the standard of performance, this technique is based
on measuring the work content by the prescribed method with allowances for fatigue and
other force delays and unavoidable delays. So, the time measured by the time study for
carrying out a particular job by the prescribed method plus allowances are added to set
the standard time.
The basic steps which are used in the time study and the jobs which can be taken for the
time study are very important, because the time study consumes lot of time and the
resources in its performance. So, the job selection of the job for time study is important,
because it is very time consuming and lots of efforts are required for setting the
performance for a particular job.
So, if the job is new and if it is important, then only time study should be conducted if
the job is not of that important which can affect the economy of the organization and the
productivity of the organization then time study is on an early not conducted. But, if the
job is of economic importance and its new then for setting the standard of performance
for new job time study can be conducted.
If there has been a particular method of carrying out a job and it has been changed there
is a change in material or the method of a doing particular job, then it will required new
standard time. So, a new time is standard can be set for in cases when the there is change
in material or the methods for doing a job.
The time study can also be conducted, if there is a complaint from the workers side
regarding the time standards which has already been set earlier by the time study. If they
may complaint that time standard which has been, set earlier is too tight and difficult to
achieve which can affect their earnings and the wages.
So, the workers can complaint, if the complaint is there from the workers side, then time
study can also be conducted to check whether their complaint is genuine or they are
following wrong method for carrying out a particular job that is why, because of which
they are not able to complete the job in time.
An operation which is appearing to be bottle neck in the production line can also be
taken for the time study, this will be affecting the productivity of a the manufacturing
system itself. So, may be of great economic importance, so the operation are the station
which is looking, which is appearing as a bottle neck in the in the entire production line
should also be taken can also be taken for the time study.
The need of the time standard time to introduce the incentive plans, what is the minimum
expected level of performance by a worker by an average worker that if that is to be
obtained for that the standard time is required. And, once the standard time is known
then the workers who are able to finish the job earlier they takes less time than the set
standard time is accordingly the suitable incentive plans can be made for the workers
who are quite good and doing the job fast and taking less time in completing the job and
that is why giving the more output.
For carrying out the time study, it is necessary that a worker and the machine and the
standard method is selected before carrying out the time study. Selection of the worker
for time study is important, because if the worker is either very smart or very is not well
equipped well trained with the method on which time study is to be conducted, then
unnecessary he will take long time. So, the worker should be selected in such a way that
he has got certain qualities, so that the work study can be conducted successfully.
Selection of worker for the time study is very important factor in success of the time
study. If the more than one worker are working on the same operation then method study
man and time study man can investigate and may time more than one workers at a time.
(Refer Slide Time: 24:28)
The qualities which should be there in a worker who should be selected for setting the
standard of performance and carrying out the time study. The worker on which time
study should be conducted must have necessary skills for carrying out the job he should
be well equipped and trained with the worker with the job which is to be timed. And, he
should have required experience, so that he is able to perform the same job consistently
with almost same time. If generally, what happens that, with the increase of experience
on carrying out a particular job the operator takes less time.
So, the time during which a worker learns and the time required to carry out the job
decreases with the increase of working experience in that period time study should not be
conducted. Time study should be conducted when worker has got enough experience and
he has reached to a stage when the time required for carrying out the same job does not
decrease with the further work on the same job.
So, he should have sufficient experience with the given method, so that a learning curve
a learning phenomenon is not effecting to the time required for completing the same job
and he should be an average worker as far as the speed of working is concerned neither
too fast workers or too slow workers should be selected for the time study.
He should represent to the whole lot of the workers and that is why, normally average
worker is selected for the time study and setting the standard of performance. He should
be temperamentally suited to the study, he should be unnecessary very attentive and very
cautious when either timing is carried out or when some sort of recording is carried out.
He should be able to perform successfully without getting effected in terms of the
performance. So, for that purpose he should be temperamentally suited to the study and
he should also have the knowledge about the purpose of the study, if he does not know
the purpose of the study he will not be able to work sincerely on the job which is being
investigated.
If the purpose of the work study and that the work measurement is mainly to investigate
that presence of ineffective time and improve the method of carrying out a particular job.
Then, they will work very happily and if the time study is to be carried out for setting the
standard of performance and then they may take extra precautions and they may include
extra steps. So, that the longer standard of performance can be set and a longer standard
time can be set which in turn will help them in getting better wages.
So, he should have the knowledge about the purpose for which time study is being
conducted it whether it is for just investigating the ineffective time and so as to carry out
the method study effectively or the purpose the study is to set the standard of
performance based on which the wage and incentive plans will be developed.
The time study is carried out using many equipments, but three equipments which are
normally used in carrying out the time study which are very common and other things
are a small one like pen and pencils. The following equipments are needed in time study
like timing device, time study observation sheet and time study observation board. In
addition to the above three pencil eraser and the devices like tachometer, the scale
etcetera is also used in time study. These are the three timing devices which have been
shown and are commonly used, this is the fly back timing type of the stop watch non fly
back timing type of the stop watch and this is the digital watch which can be used for
recording the time very accurately and record the data related with the timing in its
memory.
The timing devices will be covered one by one in bit detail. The stop watches are the
most widely used timing devices for the time study, although electronic timers are also
used, because of accuracy and their capability to store the data in its memory. Electronic
timers can measure the time accurately to the third decimal of the second and can keep
the large volume of the time data in its memory.
(Refer Slide Time: 30:08)
The two methods are mainly used in the time study, one is the cumulative timing and
another is fly back timing. In the cumulative timing, the stop watch is started in the
beginning of the first element and it is allowed to continue until the whole study is
completed and all elements are covered. So, while in case of fly back timing, the timing
of the each element is carried out separately, so that the time values for each element are
obtained directly.
The difference in the cumulative and fly back timing is that there is possibility of loss of
sometime well use in case of the fly back timing, while in case of the cumulative timing
the total time is required for carrying out the job is recorded without loss of any time
values.
In that cumulative timing method stop watch runs continuously throughout the study and
watch is started at the first element of the work cycle to be timed and it is not stopped
until whole study is completed. At the end of each element only watch reading is
recorded, so that later on successive subtractions can be used to find out the time values
for each element separately. And, this procedure gives the total time during which job is
done and this is recorded in the study without loss of any time like in fly back timing
method.
(Refer Slide Time: 31:47)
In fly back timing method, hands of the watch are returned to the zero at the end of each
element and are allowed to start immediately for the next element. So, at the end of the
each element hands of the watch are brought to the zero setting and again the watch is
started to time, the another element and the next element immediately. There is always
possibility of loss of some time value in stopping and starting the watch for the next
element.
The time for each element in this method is obtained directly and the time on and a time
off times are also noted down these are also known as the time start study started and
study end times. These are called check times and the difference gives the elapsed time,
so the time on and at the time off values are also called check times and the difference
gives the elapse time. And, the sum of all elemental times ineffective time and the check
time is called the recorded time.
(Refer Slide Time: 33:05)
After the timing devices we have to use the observation sheet, where the time value for
each element can be recorded clearly and separately. So, that later on representative
values of the time for the each element can be obtained. Depending upon the timing
method in different ways observation sheets can be designed, so that time for each
element can be noted down accurately. The time study observation sheet is basically a
printed form with the spaces provided for noting down the necessary information about
the operation being studied. These include the name of the operation, drawing number,
name of the worker, the name of the time study person, the date and the place where
study is being carried out.
So here, these are the three important components which are recorded in important things
which are recorded in the observation sheet, and finally used to calculate the standard
time. The recorded time for each element and the standard of performance adjusted by
the work study man during the time study and the related calculations are also shown
which will be used for setting the standard of performance and give a defining the
standard time.
In addition to the timing device and the observation sheet it is also required to use the
study board. Study board is mainly used for mounting the timing device and the study
sheet, so that all the data related with the time related data can be noted down easily and
the cleanliness and the neatness in the study sheet can be maintained.
The study board is a light weight board used for holding the observation sheet and the
stop watch in proper position. It is slightly its size is slightly larger than that of the
observation sheet and generally watch is mounted near the upper right hand corner of the
board. The board also has clamp for holding the observation sheet, so that the time can
be noted down easily by the time study man and the cleanliness in the observation sheet
can be maintained.
(Refer Slide Time: 36:12)
This diagram shows the typical study board in which in the top right hand corner stop
watch has been shown. And, this is the clip for holding the time study sheet or the
observation sheet where the time for the different elements can be noted down.
The time study procedure involves right from the selection of the job to the selection of
the worker and timing of the different elements finding the allowances and the related
calculations to set the standard of performance. It is starts with defining at the objective
of the time study is to be precisely defined regarding its use. Use of the time study results
for what purpose, what will be the use of the time study results, should be clearly
described at the same time precision desired in the time values and the required level of
the confidence in estimated time standard should also be described clearly.
So, the first step in time study is to define the objective of the study and the precision
desired and the confidence level desired in the estimated time standards. In the second
step is to verify that a standard method is being used for carrying out to particular job
and the operator is also properly trained.
If the method is not perfect then method study should be conducted first and standard
practice is followed. And, if the worker is not also properly trained, then he should be
given enough time for carrying out for proper learning and getting the training on the
method which is to be timed. If the need is felt then method study or the further training
of the operator can be done and the same, then the time study can be completed after
setting the proper standard method and proper training of the operator.
The third step in the time study procedure is to select the operator for the study purpose.
If the operator is not selected properly either he is not very familiar with the job or he is
temperamentally not suited for the time study and he should not be selected. So, operator
should be selected having the desired qualities and if they are more than one operator
than the number of operators can be selected for the study by the time study man. And,
then recording the information about the standard method operation being used operator
who is performing the work, the product on which study is being conducted equipments
and the conditions in which study is being conducted are recorded in the observation
sheet.
Any factor which can effect the time required for each element is to be recorded on the
observation sheet which can range from the standard method operator operation product
equipment or the conditions in which work is being done. And, after recording the
general information and the conditions in which the work is being done. And the
operation is divided into the reasonably small elements, so the time values for each
element can be noted down and measured accurately using the suitable time devices. So,
divide the operation into the reasonably a small elements and record them on time study
observation sheet.
After dividing the operation into the small elements and noting down them in on the
study sheet, the time values for each element which operator will be taking during the
operation are noted down. Record the data for few numbers of cycles for each element
on the study time observation sheet.
To estimate the total number of observations, how many observations should be taken
for each element, so that some degree of confidence can be achieved a proper procedure
is used to find out a number of observations should be taken for each element. And,
again the confidence and the desired accuracy in the data which is being obtained after
the time study.
Next step is to collect and record the data for required number of cycles by timing and
rating the operators. Not only the time values will be noted down for each cycle for each
element for the required number of the cycles, but the operator performance is also
judged by the time study man with respect to his own concept of the standard
performance.
So here, the editing of the operator during the work is done by the time study man and
his performance is compared with his own concept of the performance. So, if his
performance is 100 percent means that he is working at a speed at which he should work
according to the standard of performance concept of the time study man. If he is working
slow, then he will be rated low or if he is working fast, then he will be rated high
accordingly. So, in addition to noting down the time values a worker is no worker’s
performance is rated for each element.
Next step in the time study procedure is to calculate the representative stop watch
reading for each element of the operation and multiplying it by the rating factor. So, as to
get the normal time, after noting down the observed time values and rated values of the
operator the product of the two is use to find out the normal time.
So, normal time is obtained from the observed time into the rating factor and then normal
time for all the elements is added to find out the total normal time for the operation. So,
the normal time for whole operation is obtained by adding the normal time for its various
elements.
(Refer Slide Time: 43:27)
Next step is to find out the percentage of the allowances to be given, so as to cope with
the forced delays like operator’s personal need lack of material production delays are the
basic fatigue or any other special allowance which is to be given. So, that percentage of
the allowance is to be identified depending upon the kind of work which is to be done by
the worker and the organizations policy. And for determining the standard time the
normal time is added with the allowances, which has been decided as per the work to be
done or the or the policy of the organization.
If the time study is being done as a result of complaint of the workers about the standard
time as set earlier, then the method must be carefully observed and compared with the
standard practice sheet when originally study was carried out. If the time study is to be
conducted as a result of complaint from the workers that two standard has been set and it
is difficult to achieve under the normal working conditions or it is causing excessive
exertion to achieve the desired time standard. Then, it will be required to investigate the
set standard time again and for investigating that it is necessary to see and observe that,
what practice is being followed, and whether it is same as recommended in standard
practice sheet or not. Most of the time, it is found that the workers intentionally or
unintentionally include some of the foreign elements in the work cycle. And, they start to
follow the different steps which are not there in standard practice sheet, because of which
they take longer time to complete the same job.
And, that is why, it is often found when the method which is being followed is
investigated that workers use different tool machines setup parameters, temperature flow
rate or any other working conditions which can influence the production rate and the
total time required for carrying out the job. These other conditions may also be in form
of like worn out tool wrong tool geometry can take longer time for carrying out a
machining operation. So, the checking of the proper practice checking of the method
which is being followed and it is compared with the standard practice to see if any
unnecessary. And, the extra elements are there are not and if they are present then steps
can be taken to correct the method.
Checking of the method of very short cycle jobs is found very difficult, because minor
difference in the path of movement of the body parts and can lead to the change in the
time required for performing the given job. Like light assembling, packing of the things
time required for light assembly and packing of the things may vary significantly if there
is change in movement of the arms and the hand patterns.
So, it is difficult to check these movements by naked eye and to see that, what difference
is there in the method, which is being followed and how much difference is there with
the method, which has been described in standard practice sheet. And, the another
problem in checking of the existing method is related with those jobs which are carried
out rarely or they are carried out few times in year.
So, the study should be conducted carefully to record the method by which job is being
done which will help to rectify the incorrect method being used. So, especially the
problem is of checking the method is found in case, where job is done very rarely or the
jobs which are of very short cycle, so short cycle and they take very in less time.
For effective time study it is necessary that entire job to be investigated for the presence
of ineffective time and setting of the standard of performance is that it the job operation
is broken down into the fine elements. This helps to check the method properly and to
compare it to the set standard practice.
So, after checking the method the job is broken down into the elements and an element is
defined as a distinct part of the specified job selected for the convenience of observation
measurement and analysis. And, an operation can be broken into the number of elements
and these elements are identified in such a way that the time for those elements can be
measured accurately, and they can be analyzed easily using the available timing devices.
Well the work cycle is this is the sequence of the elements which are required to perform
the job. So, when an operation is broken down into the number of elements, so that each
element can be analyzed separately and all the elements are carried out in one particular
sequence, then that forms the work cycle and which is required to perform a given job,
breaking of the job into the small elements help to analyze the job very carefully and to
see the presence of any unproductive element or ineffective time.
(Refer Slide Time: 51:15)
The timing a complete task as one element is generally not satisfactory, because workers
are not able to work at the same pace on all the elements. So, timing of all the elements
in one go is not found very good for rating the various components of the work. For the
purpose of time study task is normally broken down into the short elements and each
element is timed separately. The reason for breaking the job into the short elements are
many and some of these have been highlighted like to for improved accuracy of the
rating of the worker it is necessary that his pace of work is rated separately for each
element.
Because, the workers may not be able to work at the same speed throughout the work
cycle, so if each element is rated separately it will help to improve the accuracy of rating
of the worker. He may perform some elements faster and some slower, so breaking of the
task into the short elements permits the rating of the each element separately which is
more realistic than just rating once for one complete cycle. So, breaking of the job into
the elements and the rating the worker for each element gives more clear picture about
the performance of operator while doing the job.
(Refer Slide Time: 53:04)
And, not only this when the job is carried out using the different elements and each
element is analyzed separately, it helps to reveal that what are the elements causing more
fatigue compared to the others. So, that those elements causing excessive fatigue can be
isolated and the suitable fatigue allowance can also be given for those elements.
But, this identification of a about high fatigue causing elements is possible only if they
are broken into the short elements. So, to identify the elements causing high fatigue the
breaking of the job into the short elements also help, breaking of the task into the short
elements permits the appropriate to allow the appropriate rest allowances to the different
elements.
And, also help in isolating the elements which are causing excessive fatigue, to have the
detailed description is the another important benefit which is achieved by breaking the
job into the element. This helps in detection of any variation in method that may occur
later on by the workers or that workers may follow later on which may be different from
the standard practice, so that if the workers start to follow the different methods that can
be detected easily.
If the standard if the job has been broken into the short elements and the step by step the
method, which is being followed by the workers actually, and the method which they
should follow can be detected easily means that the difference can be easily detected to
see that, why they are taking longer time. If the workers intentionally follow some other
foreign elements; obviously they will be taking longer time and then complaining about
the type time standard.
So, that complaint can be easily attended by looking into, what method is being actually
followed and what method has been recommended, so the difference can be easily
identified if the detailed job is specifications or available. And, another advantage of
breaking the job into the element is to prepare the standard data for repeatedly occurring
elements. Like, because the job is broken down the small elements some of the elements
are of constant in nature, some of the elements are very a regular type which will be
repeated in most of the operations.
If the time values for those operations those elements have been identified by the time
study it will help to develop the data bank about the elements which are repeated in the
different work cycles and in the different operations. So, these time values can be used in
the standard data method or in PMTS method.
So, as breaking of the job into the small elements and obtaining the time values for each
element also help in developing the standard data bank for repeatedly occurring
elements. One more important objective which can be achieved by the breaking the job
into the elements is that it can help us to separate the unproductive elements from the
productive elements and identification of the unproductive elements can help in
developing the better method, so that the entire job can be completed in less time.
Now, I shall summarize this presentation, in this presentation I have mainly talked about
the importance of the work measurement its techniques like the time study and the time
study procedure and the steps, which are required to be taken for carrying out the time
study and set the standard of performance.