0% found this document useful (0 votes)
7 views

Quotation

The document contains a quotation from Prince Carlit Construction Services for a construction project, detailing costs for various items and services, with a total amount of $1,624.66. It also includes a bill of quantities for the construction of riprap, totaling ₱15,000.00, and a detailed unit price analysis for a solar water system project, with a total unit cost of ₱2,520.75. The document is prepared by engineers John Lloyd M. Ziganay and Reynan C. Costelo.

Uploaded by

fjbalugo19
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Quotation

The document contains a quotation from Prince Carlit Construction Services for a construction project, detailing costs for various items and services, with a total amount of $1,624.66. It also includes a bill of quantities for the construction of riprap, totaling ₱15,000.00, and a detailed unit price analysis for a solar water system project, with a total unit cost of ₱2,520.75. The document is prepared by engineers John Lloyd M. Ziganay and Reynan C. Costelo.

Uploaded by

fjbalugo19
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Prince Carlit Construction Services Quotation

DATE 1/20/2025
888 Quotation # 100
City, State ZIP Code Customer ID ABA
Phone: Enter Phone number here Fax: Enter Fax number here

Quotation For: Quotation valid until: 1/30/2025

Name Prepared by: Name


Company Name
Street Address
City, ST ZIP Code
Phone

Comments or Special Instructions: None

SALESPERSON P.O. NUMBER SHIP DATE SHIP VIA F.O.B. POINT TERMS

Due on receipt

QUANTITY DESCRIPTION UNIT PRICE TAXABLE? AMOUNT

34 Item 1 $ 44.00 T $ 1,496.00

SUBTOTAL $ 1,496.00

TAX RATE 8.60%

SALES TAX $ 128.66

OTHER $ -

TOTAL $ 1,624.66

If you have any questions concerning this quotation, contact name, phone number, e-mail.

THANK YOU FOR YOUR BUSINESS!


BILL OF QUANTITES

Project Name: Construction of Riprap


Location: Sitio Naasug, P. Zamora, Guihulngan City

Item No. Description Unit Qty Unit Cost Total Cost

A. General Requirements

1 Site Expense l.s. 1.00 15,000 15,000

Subtotal A ₱15,000.00

B. Earthworks

1 Clearing and Grubbing sq.m. 0

2 Structure Excavation(Foundation Works) cu.m. 0

3 Hauling and Disposal of Excavated Materials cu.m. 0

Subtotal B ₱0.00

C. Riprap Construction(Masonry Concrete Works)

1 Placement of Boulders Stones cu.m. 0

2 Concrete Grouting (1:2:4 Mix) cu.m. 0

3 Access Stairs cu.m. 0

4 Finishing Works sqm. 0

Subtotal C ₱0.00

D. Drainage Works
Installation of Weep Holes (PVC Pipes, Ø100
1 l.m. 0
mm)
2 Installation of Drainage Canal l.m. 0

3 cu.m. 0

Subtotal D ₱0.00

E. Miscellaneous Works

1 Backfilling and Compaction of Embankment cu.m. 0

2 Site Cleaning and Restoration l.s. 0

Subtotal D ₱0.00

Grand Total ₱15,000.00


306.5 588.00
180,222.00
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project Name : Construction of Solar Water System, Municipality of Governor Generoso, Davao Oriental
Item No./Description : 1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm thk.
Unit of Measurement : m2
Output per hour : 3.18
Quantity : 0.00
1.) Construction of Solar Water System at Poblacion, Municipality of Governor Generoso, Davao Oriental
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor

a. Construction Foreman 1 1.00 118.46 118.46


b. Skilled Laborer 2 1.00 85.65 171.30
c. Unskilled Laborer 3 1.00 65.94 197.82

Sub - Total for A 487.58


No. of
Name and Capacity No. of Unit/s Hourly Rate Amount (PhP)
Hour/s
B. Equipment

a. One-bagger mixer 1 1.00 172.00 172.00


b. Minor Tools (10% of Labor Cost) 48.76

Sub - Total for B 220.76


C. Total (A + B) 708.34
D. Output per Hour = 3.825 m2
E. Direct Unit Cost (C ÷ D) 222.75

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm thk CHB (Non-Load Bearing) pc 13.00 28.00 364.00


b. Cement bag 1.500 268.00 402.00
c. Sand cu.m 0.04 680.00 27.20
d. Reinforcing Steel kg 3.24 70.00 226.80
e. #16 Tie wire kg 0.05 84.00 4.20

Sub - Total for F 1,024.20


G. Direct Unit Cost (E + F) 1,246.95
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 149.63
I. Contractor's Profit (CP) 8% of G 99.76
J. Value Added Tax (VAT) 5% of (G + H + I) 74.82
K. Total Unit Cost (G + H + I + J) 1,571.15

Prepared by: Checked/Submitted by:

JOHN LLOYD M. ZIGANAY REYNAN C. COSTELO


Engineer II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)
Project Name : Construction of Riprap
Item No./Description :
Unit of Measurement : m2
Output per hour : 3.825
Quantity : 1.00
1.) Construction of Solar Water System at Poblacion, Municipality of Governor Generoso, Davao Oriental
No. of No. of
Designation Hourly Rate Amount (PhP)
Person/s Hour/s
A. Labor

a. Construction Foreman 1 1.00 110.00 110.00


b. Skilled Laborer 2 1.00 68.75 137.50
c. Unskilled Laborer 3 1.00 60.00 180.00
d. Site Expense (10% of Labor Cost) 42.75

Sub - Total for A 470.25


No. of
Name and Capacity No. of Unit/s Hourly Rate Amount (PhP)
Hour/s
B. Equipment

a. One-bagger mixer 1 1.00 250.00 250.00


b. Minor Tools (10% of Labor Cost) 47.03

Sub - Total for B 297.03


C. Total (A + B) 767.28
D. Output per Hour = 3.825 m2
E. Direct Unit Cost (C ÷ D) 200.59

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Stones (Boulders) cu.m 0.50 1,500.00 750.00


b. Cement bags 3.000 250.00 750.00
c. Sand cu.m 0.30 1,000.00 300.00
-
-

Sub - Total for F 1,800.00


G. Direct Unit Cost (E + F) 2,000.59
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12% of G 240.07
I. Contractor's Profit (CP) 8% of G 160.05
J. Value Added Tax (VAT) 5% of (G + H + I) 120.04
K. Total Unit Cost (G + H + I + J) 2,520.75

Prepared by: Checked/Submitted by:


JOHN LLOYD M. ZIGANAY REYNAN C. COSTELO
Engineer II Engineer II