4 - Checklist Form Work
4 - Checklist Form Work
FO R M W ORK
Project New Manufacturing Factory for NETZSCH Technologies at Verna IDC.
Client NETZSCH Inspection Report No
PMC (If any) JLL Date
Contractor Harshal Buildcon LLP. Structural Member
Package Civil, Structure and Finishes work BBS.Ref.No.
Description of Work Foam Work Quantity
Wing Dwg.Ref. Rev Inspection Request
No
Floor Level Inspected by By Time
Location Grid
Sl. No Description YES NO N/A Remarks
General
1 Check for approved shuttering methodology
2 Check for latest revision of drawings
3 Quality of shuttering materials inspected and approved prior to execution
Inspection process
1 Earlier comments attended
2 Check for safe access
3 Check for working platform, guard rails, toe boards fixed correctly
4 Check dimensions, line, levels and set out are as per drawing
5 Check for plumb of formwork
6 Box, cut out- sizes and location are correct
7 Check for supports - number and position
8 Check plumb of beam column junction
9 Check supports at beam column junction
10 Check use of foam sheet all around the starter before fixing column form work
11 Check for depth of sunken slab
12 Check gaps/holes are properly closed
13 Check cleanliness of pour area
14 Shuttering oil used properly
Observations if any :
Note: The quantity mentioned above is approximate measure and can not be considered for any billing purpose. Only JMS to be considered for billing else GFC drawings
are to be referred for quantity
CONTRACTOR CLIENT
Signature Signature
Name Name
Date Date
Distribution