IRB Status of Selected RFI Summary 20.01.2025
IRB Status of Selected RFI Summary 20.01.2025
.500 of Vadodara Mumbai Expressway (Gandeva to Ena section) in the state of Gujarat under Bharatmala Pariyojana (Phase I-Package VII).
Client : National Highway Authority Of India
Independent Engineer : L.N.Malviya Infra Project Pvt.Ltd. In Association With Higway Engineering Consultant
Concessionaire : VM7 Expressway Private Limited
EPC Contractor : IRB Infrastructure Developers Limited
Highway
1 N/01001/11003/GJ/RFI/ 1/18/2025 192.400 192.490 90 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 15th Layer (Roadway Excavated Material 1/19/2025 10:00 AM Mr Arvind panduranji
HIGHWAY/N/7483 Ch. 190.700 RHS) karmore
2 N/01001/11003/GJ/RFI/ 1/18/2025 192.430 192.490 60 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 15th Layer (Roadway Excavated Material 1/19/2025 11:00 AM Mr Arvind panduranji
HIGHWAY/N/7484 Ch. 190.700 RHS) karmore
3 N/01001/11003/GJ/RFI/ 1/18/2025 192.440 192.490 50 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 16th Layer (Roadway Excavated Material 1/19/2025 3:00 PM Mr Arvind panduranji
HIGHWAY/N/7485 Ch. 190.700 RHS) karmore
4 N/01001/11003/GJ/RFI/ 1/18/2025 192.470 192.490 20 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 17th Layer (Roadway Excavated Material 1/20/2025 12:00 PM Mr Arvind panduranji
HIGHWAY/N/7486 Ch. 190.700 RHS) karmore
5 N/01001/11003/GJ/RFI/ 1/18/2025 192.250 192.400 150 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 10th Layer (Roadway Excavated Material 1/19/2025 10:30 AM Mr Arvind panduranji
HIGHWAY/N/7487 Ch. 190.700 RHS) karmore
6 N/01001/11003/GJ/RFI/ 1/18/2025 192.250 192.400 150 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 11th Layer (Roadway Excavated Material 1/20/2025 11:30 AM Mr Arvind panduranji
HIGHWAY/N/7488 Ch. 190.700 RHS) karmore
7 N/01001/11003/GJ/RFI/ 1/18/2025 0.600 0.650 50 NA Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 15th Layer for Interchange Loop-02(B.A. 1/19/2025 11:30 AM Mr Arvind panduranji
HIGHWAY/N/7489 170) karmore
8 N/01001/11003/GJ/RFI/ 1/18/2025 0.600 0.650 50 NA Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 16th Layer for Interchange Loop-02(B.A. 1/20/2025 10:30 AM Mr Arvind panduranji
HIGHWAY/N/7490 170) karmore
9 N/01001/11003/GJ/RFI/ 1/18/2025 1.420 1.520 100 NA Main Carriageway (Rigid Pavement) Highway FDD Checking of Embankment 14th Layer Interchange Loop-1 (B.A.No-170) 1/19/2025 12:00 PM Mr Arvind panduranji
HIGHWAY/N/7491 karmore
10 N/01001/11003/GJ/RFI/ 1/18/2025 1.420 1.520 100 NA Main Carriageway (Rigid Pavement) Highway FDD Checking of Embankment 15th Layer Interchange Loop-1 (B.A.No-170) 1/20/2025 2:00 PM Mr Arvind panduranji
HIGHWAY/N/7492 karmore
Mr Sutariya
11 N/01001/11003/GJ/RFI/ 1/18/2025 212.680 212.800 120 RHS Main Carriageway (Rigid Pavement) Highway Laying in position PCC for chute drain Excavation Geocell & Geotextile as 1/19/2025 10:00 AM Sureshkumar
HIGHWAY/N/7493 per Drawing and technical specification complete in all respect MCW.
Dalabhai
Mr Sutariya
12 N/01001/11003/GJ/RFI/ 1/18/2025 213.950 214.080 130 RHS Main Carriageway (Rigid Pavement) Highway Laying in position PCC for chute drain Excavation Geocell & Geotextile as 1/19/2025 10:30 AM Sureshkumar
HIGHWAY/N/7494 per Drawing and technical specification complete in all respect MCW.
Dalabhai
Mr Sutariya
13 N/01001/11003/GJ/RFI/ 1/18/2025 213.720 213.870 150 RHS Main Carriageway (Rigid Pavement) Highway Laying in position PCC for chute drain Excavation Geocell & Geotextile as 1/19/2025 11:00 AM Sureshkumar
HIGHWAY/N/7495 per Drawing and technical specification complete in all respect MCW.
Dalabhai
Mr Sutariya
14 N/01001/11003/GJ/RFI/ 1/18/2025 213.300 213.380 80 LHS Main Carriageway (Rigid Pavement) Highway Laying in position PCC for chute drain Excavation Geocell & Geotextile as 1/19/2025 11:30 AM Sureshkumar
HIGHWAY/N/7496 per Drawing and technical specification complete in all respect MCW.
Dalabhai
Mr Sutariya
15 N/01001/11003/GJ/RFI/ 1/18/2025 213.320 213.380 60 RHS Main Carriageway (Rigid Pavement) Highway Laying in position PCC for chute drain Excavation Geocell & Geotextile as 1/19/2025 12:00 PM Sureshkumar
HIGHWAY/N/7497 per Drawing and technical specification complete in all respect MCW.
Dalabhai
16 N/01001/11003/GJ/RFI/ 1/18/2025 191.130 191.170 40 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 12th Layer (Roadway Excavated Material 1/19/2025 10:30 AM Mr Arvind panduranji
HIGHWAY/N/7553 Ch. 190.700 RHS) karmore
17 N/01001/11003/GJ/RFI/ 1/18/2025 191.130 191.170 40 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 13th Layer (Roadway Excavated Material 1/19/2025 2:30 PM Mr Arvind panduranji
HIGHWAY/N/7554 Ch. 190.700 RHS) karmore
1of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
18 N/01001/11003/GJ/RFI/ 1/18/2025 191.110 191.150 40 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 12th Layer (Roadway Excavated Material 1/19/2025 11:00 AM Mr Arvind panduranji
HIGHWAY/N/7555 Ch. 190.700 RHS) karmore
19 N/01001/11003/GJ/RFI/ 1/18/2025 191.110 191.150 40 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 13th Layer (Roadway Excavated Material 1/19/2025 3:30 PM Mr Arvind panduranji
HIGHWAY/N/7556 Ch. 190.700 RHS) karmore
20 N/01001/11003/GJ/RFI/ 1/18/2025 191.130 191.170 40 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 14th Layer (Roadway Excavated Material 1/20/2025 11:30 AM Mr Arvind panduranji
HIGHWAY/N/7557 Ch. 190.700 RHS) karmore
21 N/01001/11003/GJ/RFI/ 1/18/2025 191.110 191.150 40 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 14th Layer (Roadway Excavated Material 1/20/2025 12:00 PM Mr Arvind panduranji
HIGHWAY/N/7558 Ch. 190.700 RHS) karmore
22 N/01001/11003/GJ/RFI/ 1/18/2025 208.390 208.420 30 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 11th Layer (MCW) (B.A.168) 1/19/2025 12:00 PM Mr Kamlakar
HIGHWAY/N/7571 Dnyanoba Ambat
23 N/01001/11003/GJ/RFI/ 1/18/2025 208.390 208.420 30 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 12th Layer (MCW) (B.A.168) 1/19/2025 11:00 AM Mr Kamlakar
HIGHWAY/N/7572 Dnyanoba Ambat
24 N/01001/11003/GJ/RFI/ 1/18/2025 208.390 208.420 30 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 13th Layer (MCW) (B.A.168) 1/20/2025 12:00 PM Mr Kamlakar
HIGHWAY/N/7573 Dnyanoba Ambat
25 N/01001/11003/GJ/RFI/ 1/18/2025 208.390 208.400 10 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 17th Layer (MCW) (B.A. 168) 1/19/2025 3:00 PM Mr Kamlakar
HIGHWAY/N/7574 Dnyanoba Ambat
26 N/01001/11003/GJ/RFI/ 1/18/2025 208.390 208.400 10 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 18th Layer (MCW) (B.A. 168) 1/19/2025 3:30 PM Mr Kamlakar
HIGHWAY/N/7575 Dnyanoba Ambat
27 N/01001/11003/GJ/RFI/ 1/18/2025 208.390 208.400 10 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 19th Layer (MCW) (B.A. 168) 1/20/2025 12:00 PM Mr Kamlakar
HIGHWAY/N/7576 Dnyanoba Ambat
28 N/01001/11003/GJ/RFI/ 1/18/2025 208.400 208.420 20 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 11th Layer (MCW) (B.A. 168) 1/19/2025 12:00 PM Mr Kamlakar
HIGHWAY/N/7577 Dnyanoba Ambat
29 N/01001/11003/GJ/RFI/ 1/18/2025 208.400 208.420 20 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 12th Layer (MCW) (B.A. 168) 1/19/2025 12:30 PM Mr Kamlakar
HIGHWAY/N/7578 Dnyanoba Ambat
30 N/01001/11003/GJ/RFI/ 1/18/2025 208.400 208.420 20 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 13th Layer (MCW) (B.A. 168) 1/20/2025 11:30 AM Mr Kamlakar
HIGHWAY/N/7579 Dnyanoba Ambat
31 N/01001/11003/GJ/RFI/ 1/18/2025 208.260 208.390 130 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 23rd Layer (MCW) (B.A. 168) 1/19/2025 11:00 AM Mr Kamlakar
HIGHWAY/N/7580 Dnyanoba Ambat
32 N/01001/11003/GJ/RFI/ 1/18/2025 208.260 208.390 130 LHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 24th Layer (MCW) (B.A. 168) 1/20/2025 12:00 PM Mr Kamlakar
HIGHWAY/N/7581 Dnyanoba Ambat
33 N/01001/11003/GJ/RFI/ 1/18/2025 208.260 208.390 130 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 23rd Layer (MCW) (B.A. 168) 1/19/2025 11:30 AM Mr Kamlakar
HIGHWAY/N/7582 Dnyanoba Ambat
34 N/01001/11003/GJ/RFI/ 1/18/2025 208.260 208.390 130 RHS Main Carriageway (Rigid Pavement) Highway FDD Checking for Embankment 24th Layer (MCW) (B.A. 168) 1/20/2025 12:00 PM Mr Kamlakar
HIGHWAY/N/7583 Dnyanoba Ambat
35 N/01001/11003/GJ/RFI/ 1/18/2025 200.605 200.668 63 LHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7362/N/1 Necessary arrangements Dnyanoba Ambat
36 N/01001/11003/GJ/RFI/ 1/18/2025 0.560 0.658 98 NA Others Other Works Approval of Soil Filling above (50 mm)HSR 200 for RE Wall-1& 2 (Ch- 1/19/2025 11:00 AM Mr Manthan Mahesh
OTHERWORKS/N/7464 196+076) Khairnar
37 N/01001/11003/GJ/RFI/ 1/18/2025 0.560 0.658 98 NA Others Other Works SBC Test for RE Wall-1&2 (CH-196+076) 1/19/2025 12:30 PM Mr Manthan Mahesh
OTHERWORKS/N/7465 Khairnar
2of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
38 N/01001/11003/GJ/RFI/ 1/18/2025 206.536 207.052 516 RHS Others Other Works Providing & Fixing of MBCB Median Side MCW 1/19/2025 12:00 PM Mr Kamlakar
OTHERWORKS/N/7466 Dnyanoba Ambat
39 N/01001/11003/GJ/RFI/ 1/18/2025 206.536 207.052 516 LHS Others Other Works Providing & Fixing of MBCB Median Side MCW 1/19/2025 12:20 PM Mr Kamlakar
OTHERWORKS/N/7467 Dnyanoba Ambat
40 N/01001/11003/GJ/RFI/ 1/18/2025 201.578 201.631 53 RHS Others Other Works Checking for Reinforcement & Approval of pouring M-20 Grade of 1/19/2025 12:40 PM Mr Kamlakar
OTHERWORKS/N/7468 Concrete for RCC drain shoulder side MCW Dnyanoba Ambat
Mr Sutariya
41 N/01001/11003/GJ/RFI/ 1/18/2025 215.390 215.490 100 LHS Utility Duct Other Works Approval for laying utility duct pipe 200mm Dia for shoulder side MCW. 1/19/2025 2:30 PM Sureshkumar
OTHERWORKS/N/7498
Dalabhai
Mr Sutariya
42 N/01001/11003/GJ/RFI/ 1/18/2025 215.390 215.490 100 LHS Utility Duct Other Works Approval of Pouring M-20 Grade concrete for utility duct shoulder side 1/19/2025 3:00 PM Sureshkumar
OTHERWORKS/N/7499 MCW
Dalabhai
43 N/01001/11003/GJ/RFI/ 1/18/2025 203.410 203.510 100 RHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 10:30 AM Mr Kamlakar
OTHERWORKS/N/7500 Dnyanoba Ambat
44 N/01001/11003/GJ/RFI/ 1/18/2025 203.410 203.510 100 RHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 11:00 AM Mr Kamlakar
OTHERWORKS/N/7501 Dnyanoba Ambat
45 N/01001/11003/GJ/RFI/ 1/18/2025 203.410 203.510 100 RHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 12:30 PM Mr Kamlakar
OTHERWORKS/N/7502 Necessary arrangements Dnyanoba Ambat
46 N/01001/11003/GJ/RFI/ 1/18/2025 203.778 203.815 37 RHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 10:50 AM Mr Kamlakar
OTHERWORKS/N/7503 Dnyanoba Ambat
47 N/01001/11003/GJ/RFI/ 1/18/2025 203.778 203.815 37 RHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7504 Dnyanoba Ambat
48 N/01001/11003/GJ/RFI/ 1/18/2025 203.778 203.815 37 RHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 12:20 PM Mr Kamlakar
OTHERWORKS/N/7505 Necessary arrangements Dnyanoba Ambat
49 N/01001/11003/GJ/RFI/ 1/18/2025 203.958 204.010 52 RHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 11:20 AM Mr Kamlakar
OTHERWORKS/N/7506 Dnyanoba Ambat
50 N/01001/11003/GJ/RFI/ 1/18/2025 203.958 204.010 52 RHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 11:50 AM Mr Kamlakar
OTHERWORKS/N/7507 Dnyanoba Ambat
51 N/01001/11003/GJ/RFI/ 1/18/2025 203.958 204.010 52 RHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 12:40 PM Mr Kamlakar
OTHERWORKS/N/7508 Necessary arrangements Dnyanoba Ambat
52 N/01001/11003/GJ/RFI/ 1/18/2025 204.098 204.153 55 RHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7509 Dnyanoba Ambat
53 N/01001/11003/GJ/RFI/ 1/18/2025 204.098 204.153 55 RHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 12:00 PM Mr Kamlakar
OTHERWORKS/N/7510 Dnyanoba Ambat
54 N/01001/11003/GJ/RFI/ 1/18/2025 204.098 204.153 55 RHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 1:00 PM Mr Kamlakar
OTHERWORKS/N/7511 Necessary arrangements Dnyanoba Ambat
55 N/01001/11003/GJ/RFI/ 1/18/2025 204.161 204.176 15 RHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 2:00 PM Mr Kamlakar
OTHERWORKS/N/7512 Dnyanoba Ambat
56 N/01001/11003/GJ/RFI/ 1/18/2025 204.161 204.176 15 RHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 2:30 PM Mr Kamlakar
OTHERWORKS/N/7513 Dnyanoba Ambat
57 N/01001/11003/GJ/RFI/ 1/18/2025 204.161 204.176 15 RHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7514 Necessary arrangements Dnyanoba Ambat
3of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
58 N/01001/11003/GJ/RFI/ 1/18/2025 204.240 204.443 203 RHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 2:30 PM Mr Kamlakar
OTHERWORKS/N/7515 Dnyanoba Ambat
59 N/01001/11003/GJ/RFI/ 1/18/2025 204.240 204.443 203 RHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 3:10 PM Mr Kamlakar
OTHERWORKS/N/7516 Dnyanoba Ambat
60 N/01001/11003/GJ/RFI/ 1/18/2025 204.240 204.443 203 RHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 4:00 PM Mr Kamlakar
OTHERWORKS/N/7517 Necessary arrangements Dnyanoba Ambat
61 N/01001/11003/GJ/RFI/ 1/18/2025 203.160 203.202 42 LHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 2:40 PM Mr Kamlakar
OTHERWORKS/N/7518 Dnyanoba Ambat
62 N/01001/11003/GJ/RFI/ 1/18/2025 203.160 203.202 42 LHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7519 Dnyanoba Ambat
63 N/01001/11003/GJ/RFI/ 1/18/2025 203.160 203.202 42 LHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 4:10 PM Mr Kamlakar
OTHERWORKS/N/7520 Necessary arrangements Dnyanoba Ambat
64 N/01001/11003/GJ/RFI/ 1/18/2025 203.822 203.832 10 LHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 2:40 PM Mr Kamlakar
OTHERWORKS/N/7521 Dnyanoba Ambat
65 N/01001/11003/GJ/RFI/ 1/18/2025 203.822 203.832 10 LHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 3:30 PM Mr Kamlakar
OTHERWORKS/N/7522 Dnyanoba Ambat
66 N/01001/11003/GJ/RFI/ 1/18/2025 203.822 203.832 10 LHS Boundary Wall Other Works Precast panels fixing for boundary wall including all necessary 1/19/2025 4:20 PM Mr Kamlakar
OTHERWORKS/N/7523 arrangements Dnyanoba Ambat
67 N/01001/11003/GJ/RFI/ 1/18/2025 203.845 203.850 5 LHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 2:50 PM Mr Kamlakar
OTHERWORKS/N/7524 Dnyanoba Ambat
68 N/01001/11003/GJ/RFI/ 1/18/2025 203.845 203.850 5 LHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 3:30 PM Mr Kamlakar
OTHERWORKS/N/7525 Dnyanoba Ambat
69 N/01001/11003/GJ/RFI/ 1/18/2025 203.845 203.850 5 LHS Boundary Wall Other Works Precast panels fixing for boundary wall including all necessary 1/19/2025 4:40 PM Mr Kamlakar
OTHERWORKS/N/7526 arrangements Dnyanoba Ambat
70 N/01001/11003/GJ/RFI/ 1/18/2025 203.850 203.851 1 LHS Boundary Wall Other Works Excavation in soil for column of Boundary wall for mcw (offset -60.00 to 1/19/2025 3:10 PM Mr Kamlakar
OTHERWORKS/N/7527 50.00 m) Dnyanoba Ambat
71 N/01001/11003/GJ/RFI/ 1/18/2025 203.850 203.851 1 LHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 4:20 PM Mr Kamlakar
OTHERWORKS/N/7528 (offset -60.00 to 50.00 m) Dnyanoba Ambat
72 N/01001/11003/GJ/RFI/ 1/18/2025 203.850 203.851 1 LHS Boundary Wall Other Works Providing & fixing of precast panel for boundary wall including all 1/19/2025 5:00 PM Mr Kamlakar
OTHERWORKS/N/7529 necessary arrangement (offset -60.00 to 50.00 m) Dnyanoba Ambat
73 N/01001/11003/GJ/RFI/ 1/18/2025 204.220 204.383 163 LHS Boundary Wall Other Works Excavation in soil for column of Boundry wall for mcw 1/19/2025 3:30 PM Mr Kamlakar
OTHERWORKS/N/7530 Dnyanoba Ambat
74 N/01001/11003/GJ/RFI/ 1/18/2025 204.220 204.383 163 LHS Boundary Wall Other Works Approval for pouring of M-20 Grade concrete for Boundary wall for mcw 1/19/2025 4:30 PM Mr Kamlakar
OTHERWORKS/N/7531 Dnyanoba Ambat
75 N/01001/11003/GJ/RFI/ 1/18/2025 204.220 204.383 163 LHS Boundary Wall Other Works Providing & fixing of Precast Panels fixing for Boundary Wall Including all 1/19/2025 5:20 PM Mr Kamlakar
OTHERWORKS/N/7532 Necessary arrangements Dnyanoba Ambat
76 N/01001/11003/GJ/RFI/ 1/18/2025 196.076 196.077 1 NA Others Other Works sampling of soil Re wal Excavated material below 1.0 (mm) Re Wall 1,2,3 1/20/2025 11:00 AM Mr Manthan Mahesh
OTHERWORKS/N/7533 & 4 (Ch-196+076) Khairnar
77 N/01001/11003/GJ/RFI/ 1/18/2025 0.536 0.635 99 RHS RE Wall Other Works RE wall 20TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 11:00 AM Mr Kamlakar
OTHERWORKS/N/7534 selected fill 20TH Layer for RE wall no.02 (B.A-168) ch 211.366 Dnyanoba Ambat
4of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
78 N/01001/11003/GJ/RFI/ 1/18/2025 0.536 0.635 99 RHS RE Wall Other Works RE wall 21st Layer Block Erection with filter media and FDD Checking for 1/19/2025 11:00 AM Mr Kamlakar
OTHERWORKS/N/7535 selected fill 21st Layer for RE wall no.02 (B.A-168) ch 211.366 Dnyanoba Ambat
79 N/01001/11003/GJ/RFI/ 1/18/2025 0.536 0.635 99 RHS RE Wall Other Works RE wall 22nd Layer Block Erection with filter media and FDD Checking for 1/20/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7536 selected fill 22nd Layer for RE wall no.02 (B.A-168) ch 211.366 Dnyanoba Ambat
80 N/01001/11003/GJ/RFI/ 1/18/2025 0.536 0.635 99 LHS RE Wall Other Works RE wall 16TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7537 selected fill 16TH Layer for RE wall no.02 (B.A-168) ch 211.366 Dnyanoba Ambat
81 N/01001/11003/GJ/RFI/ 1/18/2025 0.536 0.635 99 LHS RE Wall Other Works RE wall 17TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 2:40 PM Mr Kamlakar
OTHERWORKS/N/7538 selected fill 17TH Layer for RE wall no.02 (B.A-168) ch 211.366 Dnyanoba Ambat
82 N/01001/11003/GJ/RFI/ 1/18/2025 0.536 0.635 99 LHS RE Wall Other Works RE wall 18TH Layer Block Erection with filter media and FDD Checking for 1/20/2025 12:00 PM Mr Kamlakar
OTHERWORKS/N/7539 selected fill 18TH Layer for RE wall no.02 (B.A-168) ch 211.366 Dnyanoba Ambat
83 N/01001/11003/GJ/RFI/ 1/18/2025 0.747 0.841 94 RHS RE Wall Other Works RE wall 16TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 12:30 PM Mr Kamlakar
OTHERWORKS/N/7540 selected fill 16TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
84 N/01001/11003/GJ/RFI/ 1/18/2025 0.747 0.841 94 RHS RE Wall Other Works RE wall 17TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 12:50 PM Mr Kamlakar
OTHERWORKS/N/7541 selected fill 17TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
85 N/01001/11003/GJ/RFI/ 1/18/2025 0.747 0.841 94 RHS RE Wall Other Works RE wall 18TH Layer Block Erection with filter media and FDD Checking for 1/20/2025 2:30 PM Mr Kamlakar
OTHERWORKS/N/7542 selected fill 18TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
86 N/01001/11003/GJ/RFI/ 1/18/2025 0.841 0.844 3 RHS RE Wall Other Works RE wall 4th Layer Block Erection with filter media and FDD Checking for 1/19/2025 1:00 PM Mr Kamlakar
OTHERWORKS/N/7543 selected fill 4th Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
87 N/01001/11003/GJ/RFI/ 1/18/2025 0.841 0.844 3 RHS RE Wall Other Works RE wall 5th Layer Block Erection with filter media and FDD Checking for 1/19/2025 2:20 PM Mr Kamlakar
OTHERWORKS/N/7544 selected fill 5th Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
88 N/01001/11003/GJ/RFI/ 1/18/2025 0.841 0.844 3 RHS RE Wall Other Works RE wall 6th Layer Block Erection with filter media and FDD Checking for 1/20/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7545 selected fill 6th Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
89 N/01001/11003/GJ/RFI/ 1/18/2025 0.844 0.920 76 RHS RE Wall Other Works RE wall 16TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7546 selected fill 16TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
90 N/01001/11003/GJ/RFI/ 1/18/2025 0.844 0.920 76 RHS RE Wall Other Works RE wall 17TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 2:20 PM Mr Kamlakar
OTHERWORKS/N/7547 selected fill 17TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
91 N/01001/11003/GJ/RFI/ 1/18/2025 0.747 0.841 94 LHS RE Wall Other Works RE wall 16TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7548 selected fill 16TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
92 N/01001/11003/GJ/RFI/ 1/18/2025 0.747 0.841 94 LHS RE Wall Other Works RE wall 17TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 3:30 PM Mr Kamlakar
OTHERWORKS/N/7549 selected fill 17TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
93 N/01001/11003/GJ/RFI/ 1/18/2025 0.747 0.841 94 LHS RE Wall Other Works RE wall 18TH Layer Block Erection with filter media and FDD Checking for 1/20/2025 11:00 AM Mr Kamlakar
OTHERWORKS/N/7550 selected fill 18TH Layer for RE wall no.03 (B.A-168) ch 211.366 Dnyanoba Ambat
94 N/01001/11003/GJ/RFI/ 1/18/2025 0.900 0.946 46 LHS RE Wall Other Works RE wall 13TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7551 selected fill 13TH Layer for RE wall no.04 (B.A-168) ch 211.366 Dnyanoba Ambat
95 N/01001/11003/GJ/RFI/ 1/18/2025 0.900 0.940 40 LHS RE Wall Other Works RE wall 14TH Layer Block Erection with filter media and FDD Checking for 1/19/2025 3:30 PM Mr Kamlakar
OTHERWORKS/N/7552 selected fill 14TH Layer for RE wall no.04 (B.A-168) ch 211.366 Dnyanoba Ambat
96 N/01001/11003/GJ/RFI/ 1/18/2025 208.210 208.320 110 RHS RE Wall Other Works RE wall 18th Layer Block Erection with filter media and FDD Checking for 1/19/2025 4:00 PM Mr Kamlakar
OTHERWORKS/N/7559 selected fil 18th Layer Wall No-01 (BA.No-168) Dnyanoba Ambat
97 N/01001/11003/GJ/RFI/ 1/18/2025 208.210 208.320 110 RHS RE Wall Other Works RE wall 19th Layer Block Erection with filter media and FDD Checking for 1/20/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7560 selected fil 19th Layer Wall No-01 (BA.No-168) Dnyanoba Ambat
5of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
98 N/01001/11003/GJ/RFI/ 1/18/2025 208.320 208.402 82 RHS RE Wall Other Works RE wall 19th Layer Block Erection with filter media and FDD Checking for 1/19/2025 4:00 PM Mr Kamlakar
OTHERWORKS/N/7561 selected fil 19th Layer Wall No-01 (Ba.No-168) Dnyanoba Ambat
99 N/01001/11003/GJ/RFI/ 1/18/2025 208.320 208.402 82 RHS RE Wall Other Works RE wall 20th Layer Block Erection with filter media and FDD Checking for 1/20/2025 5:00 PM Mr Kamlakar
OTHERWORKS/N/7562 selected fil 20th Layer Wall No-01 (Ba.No-168) Dnyanoba Ambat
100 N/01001/11003/GJ/RFI/ 1/18/2025 208.402 208.479 77 RHS RE Wall Other Works RE wall 11th Layer Block Erection with filter media and FDD Checking for 1/19/2025 12:00 PM Mr Kamlakar
OTHERWORKS/N/7563 selected fill 11th Layer for RE wall no.01 (B.A-168) Dnyanoba Ambat
101 N/01001/11003/GJ/RFI/ 1/18/2025 208.402 208.479 77 RHS RE Wall Other Works RE wall 12th Layer Block Erection with filter media and FDD Checking for 1/20/2025 12:20 PM Mr Kamlakar
OTHERWORKS/N/7564 selected fill 12th Layer for RE wall no.01 (B.A-168) Dnyanoba Ambat
102 N/01001/11003/GJ/RFI/ 1/18/2025 208.210 208.340 130 LHS RE Wall Other Works RE wall 19th Layer Block Erection with filter media and FDD Checking for 1/19/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7565 selected fil 19th Layer Wall No-02 (BA.No-168) Dnyanoba Ambat
103 N/01001/11003/GJ/RFI/ 1/18/2025 208.210 208.340 130 LHS RE Wall Other Works RE wall 20th Layer Block Erection with filter media and FDD Checking for 1/20/2025 12:00 PM Mr Kamlakar
OTHERWORKS/N/7566 selected fil 20th Layer Wall No-02 (BA.No-168) Dnyanoba Ambat
104 N/01001/11003/GJ/RFI/ 1/18/2025 208.380 208.430 50 LHS RE Wall Other Works RE wall 9th Layer Block Erection with filter media and FDD Checking for 1/19/2025 2:00 PM Mr Kamlakar
OTHERWORKS/N/7567 selected fil 9th Layer Wall No-02 (BA.No-168) Dnyanoba Ambat
105 N/01001/11003/GJ/RFI/ 1/18/2025 208.380 208.430 50 LHS RE Wall Other Works RE wall 10th Layer Block Erection with filter media and FDD Checking for 1/20/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7568 selected fil 10th Layer Wall No-02 (BA.No-168) Dnyanoba Ambat
106 N/01001/11003/GJ/RFI/ 1/18/2025 208.500 208.501 1 NA RE Wall Other Works RE wall 11th Layer Block erection with filter media and fdd checking for 1/19/2025 3:30 PM Mr Kamlakar
OTHERWORKS/N/7569 selected fill 11th layer for RE wall 03 (B.A.No-168) Dnyanoba Ambat
107 N/01001/11003/GJ/RFI/ 1/18/2025 208.500 208.501 1 NA RE Wall Other Works RE wall 12th Layer Block erection with filter media and fdd checking for 1/20/2025 11:00 AM Mr Kamlakar
OTHERWORKS/N/7570 selected fill 12th layer for RE wall 03 (B.A.No-168) Dnyanoba Ambat
108 N/01001/11003/GJ/RFI/ 1/18/2025 201.965 202.090 125 LHS Others Other Works Approval of Slope Protection with Erosion Control Geomat alongwith 1/19/2025 12:00 PM Mr Kamlakar
OTHERWORKS/N/7584 materials & Excavation Top & Bottom Trench for MCW Dnyanoba Ambat
109 N/01001/11003/GJ/RFI/ 1/18/2025 201.968 202.100 132 RHS Others Other Works Approval of Slope Protection with Erosion Control Geomat alongwith 1/19/2025 11:30 AM Mr Kamlakar
OTHERWORKS/N/7585 materials & Excavation Top & Bottom Trench for MCW Dnyanoba Ambat
110 N/01001/11003/GJ/RFI/ 1/18/2025 203.470 203.516 46 RHS Others Other Works Approval of Slope Protection with Erosion control Geomet alongwith 1/19/2025 2:00 PM Mr Kamlakar
OTHERWORKS/N/7586 materials & Excavation Top & Bottom Trench Dnyanoba Ambat
111 N/01001/11003/GJ/RFI/ 1/18/2025 203.537 203.630 93 RHS Others Other Works Approval of Slope Protection with Erosion control Geomet alongwith 1/19/2025 3:00 PM Mr Kamlakar
OTHERWORKS/N/7587 materials & Excavation Top & Bottom Trench Dnyanoba Ambat
112 N/01001/11003/GJ/RFI/ 1/18/2025 217.004 217.004 0 LHS Elevated Corridor Structure Checking of Reinforcement for Span P8 to P9 Intermediate Diaphragm at 1/19/2025 10:00 AM Mr Appasaheb
STRUCTURE/N/7330/N/1 flyover Dalpatrao Hon
113 N/01001/11003/GJ/RFI/ 1/18/2025 217.004 217.004 0 LHS Elevated Corridor Structure Checking of Shuttering & Approval of Pouring of M-35 Grade Concrete for 1/19/2025 2:00 PM Mr Appasaheb
STRUCTURE/N/7331/N/1 Span P8 to P9 Intermediate Diaphragm at flyover Dalpatrao Hon
114 N/01001/11003/GJ/RFI/ 1/18/2025 215.118 215.118 0 LHS New Underpasses / Overpasses Structure Checking of Reinforcement for A1 Retaining Wall Final Lift with Bracket 1/19/2025 11:00 AM Mr SAYYAD HARUN
STRUCTURE/N/7462 LVUP MUJAFFAR
115 N/01001/11003/GJ/RFI/ 1/18/2025 215.118 215.118 0 LHS New Underpasses / Overpasses Structure Checking of Shuttering & Approval of Pouring of M-35 Grade Concrete for 1/19/2025 11:30 AM Mr SAYYAD HARUN
STRUCTURE/N/7463 A1 Retaining Wall Final Lift with Bracket LVUP MUJAFFAR
6of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
Checking of Shuttering and Approval for Pouring of M-40 Grade Concrete Mr Jitendra
117 N/01001/11003/GJ/RFI/ 1/18/2025 202.115 202.115 0 NA New Underpasses / Overpasses Structure 1/19/2025 12:00 PM
for Crash Barrier Median Side and Shoulder side including return wall Prabhakarrao
STRUCTURE/N/7470
LVUP (BHS) Deshmukh
Mr Jitendra
118 N/01001/11003/GJ/RFI/ 1/18/2025 202.115 202.115 0 RHS New Underpasses / Overpasses Structure Checking of Reinforcement for Terminal Slab for A1 Side LVUP 1/19/2025 1:00 PM Prabhakarrao
STRUCTURE/N/7471
Deshmukh
Mr Jitendra
119 N/01001/11003/GJ/RFI/ 1/18/2025 202.115 202.115 0 RHS New Underpasses / Overpasses Structure Checking of Shuttering and Approval for Pouring of Concrete M-40 Grade 1/19/2025 1:30 PM Prabhakarrao
STRUCTURE/N/7472 for Terminal Slab for A1 Side LVUP
Deshmukh
Mr Jitendra
120 N/01001/11003/GJ/RFI/ 1/18/2025 205.124 205.124 0 NA New Underpasses / Overpasses Structure Checking of Reinforcement for A2 Approach Slab VUP BHS 1/19/2025 2:00 PM Prabhakarrao
STRUCTURE/N/7473
Deshmukh
Mr Jitendra
121 N/01001/11003/GJ/RFI/ 1/18/2025 205.124 205.124 0 NA New Underpasses / Overpasses Structure Checking of Shuttering and Approval for Pouring of Concrete M-30 Grade 1/19/2025 2:30 PM Prabhakarrao
STRUCTURE/N/7474 for A2 Side approach Slab VUP
Deshmukh
Mr Jitendra
122 N/01001/11003/GJ/RFI/ 1/18/2025 205.594 205.594 0 NA New Minor Bridge Structure Checking of Reinforcement for A1 Side U Type Return Wall 7th Lift Minor 1/20/2025 11:00 AM Prabhakarrao
STRUCTURE/N/7475 Bridge
Deshmukh
Mr Jitendra
123 N/01001/11003/GJ/RFI/ 1/18/2025 205.594 205.594 0 NA New Minor Bridge Structure Checking of Weep Holes for A1 Side U Type Return Wall 7th Lift Minor 1/20/2025 11:30 AM Prabhakarrao
STRUCTURE/N/7476 Bridge
Deshmukh
Mr Jitendra
124 N/01001/11003/GJ/RFI/ 1/18/2025 205.594 205.594 0 NA New Minor Bridge Structure Checking of Shuttering and Approval for Pouring of M- 35 Grade Concrete 1/20/2025 12:00 PM Prabhakarrao
STRUCTURE/N/7477 for A1 Side U Type Return Wall 7th Lift Minor Bridge
Deshmukh
125 N/01001/11003/GJ/RFI/ 1/18/2025 207.114 207.114 0 RHS New Underpasses / Overpasses Structure Checking of Reinforcement for A1 Terminal Slab LVUP 1/19/2025 12:30 PM Mr SAYYAD HARUN
STRUCTURE/N/7478 MUJAFFAR
126 N/01001/11003/GJ/RFI/ 1/18/2025 207.114 207.114 0 RHS New Underpasses / Overpasses Structure Checking of Shuttering & Approval of Pouring of M-40 Grade Concrete for 1/19/2025 1:00 PM Mr SAYYAD HARUN
STRUCTURE/N/7479 A1 Terminal Slab LVUP MUJAFFAR
127 N/01001/11003/GJ/RFI/ 1/18/2025 207.114 207.114 0 RHS New Underpasses / Overpasses Structure Shalitex Board fixing for A1 Terminal Slab LVUP 1/19/2025 1:30 PM Mr SAYYAD HARUN
STRUCTURE/N/7480 MUJAFFAR
128 N/01001/11003/GJ/RFI/ 1/18/2025 206.204 206.204 0 LHS New Underpasses / Overpasses Structure Approval for Pouring of M-20 Grade Concrete for PCC of A1 Approach Slab 1/19/2025 12:30 PM Mr SAYYAD HARUN
STRUCTURE/N/7481 LVUP MUJAFFAR
129 N/01001/11003/GJ/RFI/ 1/18/2025 206.204 206.204 0 RHS New Underpasses / Overpasses Structure Approval for Pouring of M-20 Grade Concrete for PCC of A1 Approach Slab 1/19/2025 1:00 PM Mr SAYYAD HARUN
STRUCTURE/N/7482 LVUP MUJAFFAR
130 N/01001/11003/GJ/RFI/ 1/19/2025 193.014 193.014 0 LHS New minor bridges Structure Checking of Reinforcement for Median Side Crash Barrier Minor Bridge 1/20/2025 10:00 AM Mr Arjun Ratnappa
STRUCTURE/N/7602 Lohar
131 N/01001/11003/GJ/RFI/ 1/19/2025 193.014 193.014 0 LHS New Minor Bridge Structure Checking of Shuttering & Approval for Pouring of M- 40 Grade Concrete 1/20/2025 10:30 AM Mr Arjun Ratnappa
STRUCTURE/N/7603 for Median Side Crash Barrier Minor Bridge Lohar
132 N/01001/11003/GJ/RFI/ 1/19/2025 194.369 194.369 0 RHS New minor bridges Structure Checking of Reinforcement for A1 & A2 Terminal Slab Minor Bridge 1/20/2025 12:00 PM Mr Arjun Ratnappa
STRUCTURE/N/7604 Lohar
133 N/01001/11003/GJ/RFI/ 1/19/2025 194.369 194.369 0 RHS New minor bridges Structure Checking of Shuttering & Approval for Pouring of M- 40 Grade Concrete 1/20/2025 12:30 PM Mr Arjun Ratnappa
STRUCTURE/N/7605 for A1 & A2 Terminal Slab Minor Bridge Lohar
7of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
134 N/01001/11003/GJ/RFI/ 1/19/2025 190.285 190.285 0 RHS New Underpasses / Overpasses Structure Checking of Reinforcement for A1 Return Wall Raft SVUP (COS) 1/20/2025 12:00 PM Mr Arjun Ratnappa
STRUCTURE/N/7606 Lohar
135 N/01001/11003/GJ/RFI/ 1/19/2025 190.285 190.285 0 RHS New Underpasses / Overpasses Structure Checking of Shuttering and Approval for Pouring of M - 35 Grade Concrete 1/20/2025 12:30 PM Mr Arjun Ratnappa
STRUCTURE/N/7607 for A1 Return Wall Raft SVUP (COS) Lohar
136 N/01001/11003/GJ/RFI/ 1/19/2025 198.577 198.577 0 NA New minor bridges Structure Checking of Reinforcement for Median & Shoulder Side Crash Barrier 1/20/2025 10:00 AM Mr Arjun Ratnappa
STRUCTURE/N/7608 Minor Bridge Lohar
137 N/01001/11003/GJ/RFI/ 1/19/2025 198.577 198.577 0 NA New minor bridges Structure Checking of Shuttering and Approval for Pouring of M - 40 Grade Concrete 1/20/2025 10:30 AM Mr Arjun Ratnappa
STRUCTURE/N/7609 for Median & Shoulder Side Crash Barrier Minor Bridge Lohar
138 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Reinforcement for Span A1-P1 Median & Shoulder Side Crash 1/20/2025 11:00 AM Mr Arjun Ratnappa
STRUCTURE/N/7610 Barrier Major Bridge Lohar
139 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Shuttering and Approval for Pouring of M-40 Grade Concrete 1/20/2025 12:00 PM Mr Arjun Ratnappa
STRUCTURE/N/7611 for Span A1-P1 Median & Shoulder Side Crash Barrier Major Bridge Lohar
140 N/01001/11003/GJ/RFI/ 1/19/2025 193.996 193.996 0 LHS New Underpasses / Overpasses Structure Checking of Reinforcement for A1 & A2 Dirt Wall VUP 1/19/2025 2:30 PM Mr Arjun Ratnappa
STRUCTURE/S/7588 Lohar
141 N/01001/11003/GJ/RFI/ 1/19/2025 193.996 193.996 0 LHS New Underpasses / Overpasses Structure Checking of Shuttering & Approval for Pouring of M- 35 Grade Concrete 1/19/2025 3:30 PM Mr Arjun Ratnappa
STRUCTURE/S/7589 for A1 & A2 Dirt Wall VUP Lohar
142 N/01001/11003/GJ/RFI/ 1/19/2025 194.369 194.369 0 RHS New minor bridges Structure Checking of Reinforcement for A1 & A2 Dirt Wall Final Lift Minor Bridge 1/19/2025 2:00 PM Mr Arjun Ratnappa
STRUCTURE/S/7590 Lohar
143 N/01001/11003/GJ/RFI/ 1/19/2025 194.369 194.369 0 RHS New minor bridges Structure Checking of Shuttering & Approval for Pouring of M- 35 Grade Concrete 1/19/2025 3:00 PM Mr Arjun Ratnappa
STRUCTURE/S/7591 for A1 & A2 Dirt Wall Final Lift Minor Bridge Lohar
144 N/01001/11003/GJ/RFI/ 1/19/2025 194.369 194.369 0 LHS New minor bridges Structure Approval for Pouring of M-20 Grade Concrete for PCC of A1 & A2 side 1/19/2025 3:30 PM Mr Arjun Ratnappa
STRUCTURE/S/7592 Below Terminal Slab Minor Bridge Lohar
145 N/01001/11003/GJ/RFI/ 1/19/2025 194.369 194.369 0 LHS New minor bridges Structure Approval for Pouring of M-20 Grade Concrete for PCC of A1 & A2 side 1/19/2025 4:00 PM Mr Arjun Ratnappa
STRUCTURE/S/7593 Below Approach Slab Minor Bridge Lohar
146 N/01001/11003/GJ/RFI/ 1/19/2025 190.285 190.285 0 RHS New Underpasses / Overpasses Structure Checking of Reinforcement for A1 & A2 Return Wall 2nd Lift SVUP (COS) 1/19/2025 2:30 PM Mr Arjun Ratnappa
STRUCTURE/S/7594 Lohar
147 N/01001/11003/GJ/RFI/ 1/19/2025 190.285 190.285 0 RHS New Underpasses / Overpasses Structure Checking of Shuttering and Approval for Pouring of M - 35 Grade Concrete 1/19/2025 3:09 PM Mr Arjun Ratnappa
STRUCTURE/S/7595 for A1 & A2 Return Wall 2nd Lift SVUP (COS) Lohar
148 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Reinforcement for Span P3-P4 Shoulder Side Crash Barrier 1/19/2025 8:00 PM Mr Arjun Ratnappa
STRUCTURE/S/7596 Major Bridge Lohar
149 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Shuttering and Approval for Pouring of M-40 Grade Concrete 1/19/2025 3:40 PM Mr Arjun Ratnappa
STRUCTURE/S/7597 for Span P3-P4 Shoulder Side Crash Barrier Major Bridge Lohar
150 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Reinforcement for Span P2-P3 Median & Shoulder Side Crash 1/19/2025 3:30 PM Mr Arjun Ratnappa
STRUCTURE/S/7598 Barrier Major Bridge Lohar
151 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Shuttering and Approval for Pouring of M-40 Grade Concrete 1/19/2025 4:00 PM Mr Arjun Ratnappa
STRUCTURE/S/7599 for Span P2-P3 Median & Shoulder Side Crash Barrier Major Bridge Lohar
152 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Reinforcement for Span P1-P2 Median & Shoulder Side Crash 1/19/2025 4:30 PM Mr Arjun Ratnappa
STRUCTURE/S/7600 Barrier Major Bridge Lohar
153 N/01001/11003/GJ/RFI/ 1/19/2025 192.653 192.653 0 RHS New Major Bridge Structure Checking of Shuttering and Approval for Pouring of M-40 Grade Concrete 1/19/2025 5:00 PM Mr Arjun Ratnappa
STRUCTURE/S/7601 for Span P1-P2 Median & Shoulder Side Crash Barrier Major Bridge Lohar
8of9
Chainage Inspection
Sr. No. RFI No. RFI Date Length Side Carriageway Item Decription Time Contact Person Name Contact No. Remarks
From To Date
Legend:-
Selected RFI