542 PPT
542 PPT
Management
and
Agri Business
Entrepreneurship
ABM 542 : 3 (2+1)
Definition
• Project is a unique process, consist of a set of coordinated and controlled
activities with start and finish dates, undertaken to achieve an objective
confirming to specific requirements, including the constraints of time cost
and resource.
• Examples of project include Developing a watershed, Creating irrigation
facility, Developing new variety of a crop, Developing new breed of an
animal, Developing agro processing centre, Construction of farm building,
sting of a concentrated feed plant etc.
• It may be noted that each of these projects differ in composition, type,
scope, size and time.
Project management
• Project management is a distinct area of management that helps in
handling projects.
• It has three key features to distinguish it from other forms of management
and they include: a project manager, the project team and the project
management system.
• The project management system comprises organization structure,
information processing and decision making and the procedures that
facilitate integration of horizontal and vertical elements of the project
organization.
• The project management system focuses on integrated planning and
control.
Benefits of Project Management Approach
The rationale for following project management approach is as follows.
• Project management approach will help in handling complex, costly and risky
assignments by providing interdisciplinary approach in handling the assignments.
• Example: R&D organizations.
• Project management approaches help in handling assignments in a specified time
frame with definite start and completion points .
• Example handling customer orders by Industries involved in production of capital
goods.
• Project management approaches provide task orientation to personnel in an
Organization in handling assignments.
• Example: Organizations in IT sector handling software development assignments
for clients.
Project Characteristics
1. Unique in nature.
2. Have definite objectives (goals) to achieve.
3. Requires set of resources.
4. Have a specific time frame for completion with a definite start and finish.
5. Involves risk and uncertainty.
6. Requires cross-functional teams and interdisciplinary approach.
Classification
• There is no standard classification of the projects.
• However considering project goals, these can be classified into two broad
groups, industrial and developmental.
• It should aim at providing analysis of future market scenario so that the decision
• The analysis encompasses available alternative technologies, selection of the most appropriate
technology in terms of optimum combination of project components, implications of the
acquisition of technology, and contractual aspects of licensing.
• The technology chosen should also keep in view the requirements of raw materials and other
inputs in terms of quality and should ensure that the cost of production would be competitive.
4. Financial Analysis
The Financial Analysis, examines the viability of the project from financial or
commercial considerations and indicates the return on the investments.
Some of the commonly used techniques for financial analysis are as follows.
1. Pay-back period.
2. Return on Investment (ROI)
3. Net Present Value (NPV)
4. Profitability Index(PI)/Benefit Cost Ratio
5. Internal Rate of Return (IRR)
Risk and Uncertainty
• Risk and Uncertainty are associated with every project.
• Risk is related to occurrence of adverse consequences and is quantifiable.
• It is analysed through probability of occurrences.
• Where as uncertainty refers to inherently unpredictable dimensions and is
assessed through sensitivity analysis.
• It is therefore necessary to analyse these dimensions during formulation and
appraisal phase of the programme.
Factors attributing to risk and uncertainties of a project are grouped under the
following:
• Technical –relates to project scope, change in technology, quality and quantity
of inputs, activity times, estimation errors etc.
• Economical- pertains to market, cost, competitive environment, change in
policy, exchange rate etc.
• Socio-political- includes dimensions such as labour, stakeholders etc.
• Environmental – factors could be level of pollution, environmental degradation
etc.
Network Analysis
Project design and network analysis are important tools for effective implementation
of the project.
They are very useful for development of a detailed work plan of the project and project
time profile.
A project consists of a numerous activities.
It is examined in detail and details are utilized to compile the series wise explanation
of the constituent activities of a project.
The compilation is known as the project logic.
When it is presented in the form of a graphical presentation, it is called the network.
Importance
It helps management to minimize the total cost and total maintenance time.
Network analysis ensures the effective utilization of limited resources.
Network analysis facilitates co-ordination among the activities as well the persons
responsible for project.
Time management plays a crucial role in every project.
Network analysis helps the managers to manage activities without any delay.
Network analysis is great tool which helps in planning, scheduling and controlling
the activities of the project.
Network analysis also creates inter-relationship as well as inter-dependence of
various activities of project.
Network analysis provides the project formulation team an apparent picture of the
work elements and also sequential relationship of the project.
Classification
Classification of Network Techniques: There are number of network techniques which are
used by the various people according to their purpose. The main techniques are given below:
1. CPM: It is popularly known as Critical Path Method.
Critical path method is a project management tool used to formulate a time frame for a
project in order to determine where potential delays are most likely to take place.
2. PERT: The Programme Evaluation and Review Technique is basically a scheduling
technique.
It helps project manager in planning, scheduling, monitoring, evaluating, and controlling
large and complex projects.
It is a probabilistic model and introduces uncertainties in project network.
PERT
It shows any project or job as a set of processes of operations called activities which
must take place in a certain sequence.
It involves diagrammatic presentation of activities and events involved in a long
term project.
The diagrammatic presentation is known as Network Drawing/technique and these
techniques are most commonly used in project management.
Basic objective of PERT is to control time.
The execution of project becomes very difficult where long times involved in the
planning and scheduling of the project because it involved lot of complexities and
inter related activities.
So for the successful implementation of the project, project manager is to take
some important decisions such as estimation of resource requirement, time for
each activity, and maintaining inter-relationship amongst the activities.
PERT is helpful to the project manager for taking decisions about these
questions.
It is a technique which helps project manager in planning, scheduling,
monitoring, evaluating and controlling large and difficult projects.
In simple words we can say that projects whose time duration of activities is not
exactly known, PERT is used.
It depends upon three time estimates of activities.
The most optimistic time (𝒕𝒐 ): The minimum time that would be required to perform
the activity if everything goes extremely well, the chance of such an optimum activity
actually takes place is one in hundred.
The most likely time (𝒕𝒎 ): The length of time that will, in all probability, be required
to perform the job under the given circumstances or normal circumstances.
The most pessimistic time (𝒕𝒑 ): This is the longest or maximum probable time
involved if everything that might logically go wrong does actually go wrong. It includes
time for unusual days or unforeseen circumstances. The chance of its happening might
also be one in hundred or very less.
With the help of these above mentioned time estimates i.e. optimistic
time, most likely time, and pessimistic time, average expected time
for each activity would be determined.
Average expected time (𝒕𝒆 ) of the activity
𝒕𝒐 + 𝟒𝒕𝒎 + 𝒕𝒑
𝒕𝒆 =
𝟔
Condition
1. 𝑬𝑺𝒊 = 𝑳𝑭𝒊
2. 𝑬𝑺𝒋 = 𝑳𝑭𝒋
𝑳𝑭𝒊 𝑳𝑭𝒋
𝑬𝑺𝒊 𝑬𝑺𝒊
Starting event i j Finishing event
Procedure followed in PERT
First of all, the network of activities is drawn to indicate what activity follows what.
Then estimation of time to complete each activity is noted on the network.
Estimation of minimum time taken to complete the project.
Identification of critical activities and allocation of resources so that project can be
completed in time.
Calculation of project variability duration and profitability of the project in given
period.
In order to complete project in time closer watch on critical and other activities.
Advantages of PERT
1. It is very helpful in determine the schedule for a project within time limit.
2. It helps the management to optimum allocation of resources for the project.
3. It helps in taking right decision for the projects at a right time.
4. It is very helpful in determine the expected duration of activities.
5. It helps the management in handling the uncertainties involved in the project.
6. It helps the management to reduce the risk element in the project.
7. It suggests area of increasing efficiency, decreasing cost and maximizing profits.
8. It helps in coordinating the various activities involved in a project.
9. It enables the use of statistical analysis.
Limitations of PERT
1. PERT emphasis only on time. It ignores the cost of a project.
2. It cannot be useful for programmes that are indefinite and vague.
3. Assumption of normal probability distribution is not true.
4. It does not consider the matter of resources required for various types of
activities of a project.
5. It seems to be simple but in reality its application is too complex.
6. It is not practicable for routine planning of recurring events.
CPM
Critical path method is a special application of network analysis.
It uses network analysis for scheduling production, construction projects as well as
research and development activities.
It is also useful in situations which require estimates of time and performance.
Critical path method deals with repetitive type projects, such as overhaul of
generating plant, which has to be carried repeatedly after set time intervals.
The critical path, is the overall time, it will take to complete the project.
It is the longest path in time through the network.
In other words, the longest path in the network is called critical path. Identifying the
critical path is of great importance as it determines the duration of entire project.
Critical path method differentiates between the planning and scheduling of the
project.
A Critical path method is a very important project management tool used to
formulate a time frame for a project in order to determine where potential delays are
most likely to occur.
The process includes a step by step process that provides the developer with a visual
representation of potential bottleneck, throughout the course of the project.
Identification of the Critical Path
Earliest start time for activity (ES): It is the earliest possible time at which the
activity should start if only the ongoing activities are first completed.
Earliest finish time (EF): It is the earliest possible time to finish the activity. It is
equal to the earliest start time for activity plus the time required completing the activity.
Latest possible finish time for activity (LF): It is the latest time at which the activity
can be completing without any postpone or within the time framework.
Latest possible start time for activity (LS): it is the latest start time for an activity
and equal to the latest finish time minus the time required to complete the activity.
Slack time: Slack time is the difference between earliest start time for activity and
latest start time for activity, or between earliest finish time for activity and latest finish
time for activity.
Advantages of Critical path method
1. It is very useful for scheduling and controlling of large projects.
2. It is simple concept and not mathematically complex.
3. It is very helpful in pinpoint activities that needed to be closely watched.
4. In CPM, Project documentation and graphics point out who is responsible for
various activities.
5. It is applicable to a wide variety of projects.
6. It is very useful in monitoring schedules and costs.
7. It makes better and detailed planning possible.
8. It is helpful at many stages of project management.
9. It enables standard method for communicating project plans, schedules, time
and cost performance.
10. With the help of CPM most critical activities are identified and thus more
attention can be paid to these activities for the successful completion of project.
Limitations of CPM
1-2 1 7 13 7
1-6 2 5 14 6
2-3 2 14 26 14
2-4 2 5 8 5
3-5 7 10 19 11
4-5 5 5 17 7
6-7 5 8 29 11
5-8 3 3 9 4
7-8 8 17 32 18
Earliest Latest Total
Time Free Float
Start Finish Start Finish Float
Activity (Days) 𝑬𝒋
(ES) (EF) (LS) (LF) (TF)
𝒕𝒊𝒋 𝑬𝒋 − 𝑬𝒊 − 𝒕𝒊𝒋
𝑬𝒊 𝑬𝒊 - 𝒕𝒊𝒋 𝑳𝒋 - 𝒕𝒊𝒋 𝑳𝒋 LS-ES
1-2 4 0 4 5 9 5 4 0
1-3 1 0 1 0 1 0 1 0
2-4 1 4 5 9 10 5 5 0
3-4 1 1 2 9 10 8 5 3
3-5 6 1 7 1 7 0 7 0
4-9 5 5 10 10 15 5 10 0
5-6 4 7 11 12 16 5 11 0
5-7 8 7 15 7 15 0 15 0
6-8 1 11 12 16 17 5 17 5
7-8 2 15 17 15 17 0 17 0
8-10 5 17 22 17 22 0 22 0
9-10 7 10 17 15 22 5 22 5
Financial evaluation
techniques
Non-discounted Cash Flow Criteria
1. Payback Period (PB)
2. Average / Accounting Rate of Return (ARR)
𝐈𝐧𝐢𝐭𝐢𝐚𝐥 𝐈𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭
𝐏𝐚𝐲𝐛𝐚𝐜𝐤 =
𝐀𝐧𝐧𝐮𝐚𝐥 𝐂𝐚𝐬𝐡 𝐈𝐧𝐟𝐥𝐨𝐰
Initial Investment = 2,5,00,000
Annual Cash Inflow = 5,00,000 for 8 years
Calculate the payback period.
𝐈𝐧𝐢𝐭𝐢𝐚𝐥 𝐈𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭
𝐏𝐚𝐲𝐛𝐚𝐜𝐤 =
𝐀𝐧𝐧𝐮𝐚𝐥 𝐂𝐚𝐬𝐡 𝐈𝐧𝐟𝐥𝐨𝐰
𝟐, 𝟓, 𝟎𝟎, 𝟎𝟎𝟎
=
𝟓, 𝟎𝟎, 𝟎𝟎𝟎
= 5 years
An industry is considering investment in a project which cost 6,00,000
Cash Inflows are ₹1,20,000, ₹1,40,000, ₹1,80,000, ₹2,00,000, ₹2,50,000
Calculate Payback Period
𝟏, 𝟔𝟎, 𝟎𝟎𝟎
𝐏𝐚𝐲𝐛𝐚𝐜𝐤 = 𝟑 𝐲𝐞𝐚𝐫𝐬 +
𝟐, 𝟎𝟎, 𝟎𝟎𝟎
= 3 years + 0.8
= 3.8 years
Acceptance Rule
The project would be accepted if its payback period is less than the
maximum or standard payback period set by management.
As a ranking method, it gives highest ranking to the project, which has the
shortest payback period and lowest ranking to the project with highest
payback period.
Merits
1. It is one of the earliest methods of evaluating the investment projects.
2. It is simple to understand and to compute.
3. It dose not involve any cost for computation of the payback period
4. It is one of the widely used methods in small scale industry sector
5. It can be computed on the basis of accounting information available
from the books.
Demerits
1.This method fails to take into account the cash flows received by the company
after the pay back period.
2. It doesn’t take into account the interest factor involved in an investment outlay.
3. It doesn’t take into account the interest factor involved in an investment outlay.
4. It is not consistent with the objective of maximizing the market value of the
company’s share.
5. It fails to consider the pattern of cash inflows i.e., the magnitude and timing of
cash in flows.
2. Average Rate of Return
The accounting rate of return is the ratio of the average after-tax profit divided by
the average investment. The average investment would be equal to half of the original
investment if it were depreciated constantly.
𝐀𝐯𝐞𝐫𝐚𝐠𝐞 𝐩𝐫𝐨𝐟𝐢𝐭
ARR =
𝐀𝐯𝐞𝐫𝐚𝐠𝐞 𝐢𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭
Profit = Cash inflows – Depreciation – Tax
Average Profit = Profit / No. of Years
𝐈𝐧𝐢𝐭𝐢𝐚𝐥 𝐢𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭 + 𝐒𝐜𝐫𝐚𝐩 𝐕𝐚𝐥𝐮𝐞
𝐀𝐯𝐞𝐫𝐚𝐠𝐞 𝐢𝐧𝐯𝐞𝐬𝐭𝐦𝐞𝐧𝐭 = + Additional Working Capital
𝟐
Initial Investment = 1,60,000 ; No Scrap Value
Cash Inflows :- Year 1 2 3 4 5
₹ 56,000 48,000 30,000 64,000 80,000
= 1,60,000 / 2 = 80,000
1
Discount Factor =
(1 + r)𝒏
where “r” is the discount rate and “n” is the number of periods.
Project X
Year Cashflows DF @ 10% PV
0 (40,000) 1 (40,000)
1 10,000 0.909 9,090
2 20,000 0.826 16,520
3 20,000 0.751 15,020
4 6,000 0.683 4,098
5 4,000 0.621 2,484
The NPV method can be used to select between mutually exclusive projects; the
𝑵𝑳
𝐈𝐑𝐑 = 𝐋 + × (𝑯 − 𝑳)
𝑵 𝑳 − 𝑵𝑯
Calculate the internal rate of returns of an investment of ₹ 136000 which yields the
following cash inflows
Year Cash Inflow
1 30,000
2 40,000
3 60,000
4 30,000
5 20,000
Year Cash Inflow DF @ 10% PV DF @ 12% PV
0 (1,36,000) 1 (1,36,000) 1 (1,36,000)
1 30,000 0.909 27,270 0.893 26,790
2 40,000 0.826 33,040 0.797 31,880
3 60,000 0.751 45,060 0.712 42,720
4 30,000 0.683 20,490 0.636 19,080
5 20,000 0.621 12,420 0.567 11,340
NPV 2,280 NPV - 4,190
𝑵𝑳
𝐈𝐑𝐑 = 𝐋 + × (𝑯 − 𝑳)
𝑵𝑳 − 𝑵𝑯
𝟐, 𝟐𝟖𝟎
𝐈𝐑𝐑 = 𝟏𝟎 + × (𝟏𝟐 − 𝟏𝟎)
𝟐, 𝟐𝟖𝟎 + 𝟒, 𝟏𝟗𝟎
𝟐, 𝟐𝟖𝟎
𝐈𝐑𝐑 = 𝟏𝟎 + ×𝟐
𝟔, 𝟒𝟕𝟎
IRR = 10 + 0.70
IRR = 10.70 %
Acceptance Rule
Accept the project when r > k. k = Cost of Capital
Reject the project when r < k.
May accept the project when r = k.
In case of independent projects, IRR and NPV rules will give the
same results if the firm has no shortage of funds.
Merits
1. It consider the time value of money
2. It takes into account the cash flows over the entire useful life of the asset.
5. It has a psychological appear to the user because when the highest rate of return
projects are selected, it satisfies the investors in terms of the rate of return an
capital
Demerits
𝐏𝐕 𝐨𝐟 𝐂𝐚𝐬𝐡 𝐈𝐧𝐟𝐥𝐨𝐰𝐬
Profitability Index =
𝐏𝐕 𝐨𝐟 𝐂𝐚𝐬𝐡 𝐎𝐮𝐭𝐟𝐥𝐨𝐰𝐬
The initial cash outlay of a project is Rs 100,000 and it can generate cash inflow of ₹40,000,
₹30,000, ₹50,000 and ₹20,000 in year 1 through 4. Assume a 10 % rate of discount. The PV of
cash inflows at 10 % discount rate is:
Year
1
2
3
4
Year Cash Inflow DF @ 10% PV
1 40,000 0.909 36,360
2 30,000 0.826 24,780
3 50,000 0.751 37,550
4 20,000 0.683 13,660
NPV 12,350
𝐏𝐕 𝐨𝐟 𝐂𝐚𝐬𝐡 𝐈𝐧𝐟𝐥𝐨𝐰𝐬
Profitability Index =
𝐏𝐕 𝐨𝐟 𝐂𝐚𝐬𝐡 𝐎𝐮𝐭𝐟𝐥𝐨𝐰𝐬
𝟏, 𝟏𝟐, 𝟑𝟓𝟎
Profitability Index =
𝟏, 𝟎𝟎, 𝟎𝟎𝟎
= 1.1235
Acceptance Rule
The following are the PI acceptance rules:
Accept the project when PI is greater than one. PI > 1
Reject the project when PI is less than one. PI < 1
May accept the project when PI is equal to one. PI = 1
The project with positive NPV will have PI greater than one.
PI less than means that the project’s NPV is negative.
Merits
𝟏, 𝟑𝟗𝟎
DPP = 𝟑 +
𝟐𝟎, 𝟒𝟗𝟎
= 3 + 0.067
= 3.067 Years
= 3 + (0.067 × 12)
= 3 years & 0.8 Months
Project should be rejected because DPP exceeds target DPP (3 years)
Acceptance Rule
A company can set a target DPP and choose not to undertake any
project with a DPP in excess of a certain number of a year