SA Standard Notes
SA Standard Notes
Brackish Water: Water with Total Dissolved Solids of 10,000 ppm or more. Compaction water shall be tested for Total
Dissolved Solids, Chloride (Cl-) and Sulfate (SO4) contents according to SAES-Q-001. Water used for compaction of fill
material shall be reasonably free of salts, oil, acid, alkalis, organic matter, or other deleterious substances.
Clean Sand: Soil meeting the following gradation containing less than 3% Wt. of organic material.
Dune Sand: Wind-deposited sand consisting of relatively single-sized particles generally passing the No.16 sieve (1.18
mm) and usually containing less than 10% soil particles passing the No.200 sieve (0.074 mm).
Marl: A wide variety of calcareous soil materials found in Saudi Arabia which may vary from clay to gravel sizes and
often include cobble and boulder sized pieces.
Controlled Low Strength Material (CLSM): A flow able, self-compacting, cementitious material used primarily as a
backfill in place of compacted fill. CLSM is recommended where traditional compaction is difficult (i.e., narrow or
congested excavation backfill). The mix design shall be 28-day compressive strength between 0.7 and 1.4 MPa (100 &
200 psi), pretested using the actual raw materials and approved by the Chairman, Civil Standards Committee before
use on the project. Minimum of 6 hours prior to proceeding with construction over the CSLM.
General Fill Material: General Fill Material shall consist of gravel, sand and/or marl. The maximum size shall be one-
half the lift thickness or 75 mm (3 inches).Fill material shall be free of frozen lumps, organic matter, trash, chunks of
highly plastic clay or other unsatisfactory material. General Fill Material shall be placed in lifts of 300mm max. In loose
depth. General Fill Material and Select Fill Material shall be placed in lifts of 100 mm max. In loose depth for hand-
operated compaction equipment.
• At least 90% of the maximum Modified Proctor density as determined by ASTM D1557
• At least 70% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesion less
• At least 85% of the maximum Modified Proctor density as determined by ASTM D1557
• At least 65% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesion less granular soils that
do not exhibit well-defined moisture density relationship.
QCI Saeed-Ul-Hassan
Select Fill Material: “Structural Fill” shall be composed only on inorganic material & shall have 100% passing the 5cm
(2 in) sieve & from 0 to 20% passing the No. 200 sieve. The portion of Select Fill material passing the No. 40 sieve shall
have a Max. Liquid limit of 35 & Max. Plasticity index of 12 per ASTM D4318. Liquid limit and plastic limit tests are
not required for select fill material with less than 15% passing the No. 200 sieve.
Within 0.6 m of the bottom elevation of foundations, spread footings, slabs-on-grade and pavements when fill is
required to achieve final grade. Select Fill Material shall be placed in lifts of 200 mm Max. In loose depth.
The moisture content of the material being compacted shall be within 3% plus or minus of the optimum moisture
content as determined by ASTM D1557.
All Select Fill Material and any fill beneath and/or adjacent to foundations, grade beams, mats, buildings, lined slopes
or drainage channels, and process areas:
• At least 90% of the maximum Modified Proctor density as determined by ASTM D1557
• At least 70% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesion less
Select Fill Material beneath and/or adjacent to foundations with static loads over 320 kPa and foundations for
vibrating or heavy machinery:
• At least 95% of the maximum Modified Proctor density as determined by ASTM D1557
• At least 85% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesion less
• At least 95% of the maximum Modified Proctor density as determined by ASTM D1557
• At least 85% Relative Density as determined by ASTM D4253 and ASTM D4254 for cohesion less
Tests of gradation, plasticity, density, and moisture content shall be performed for each type of fill material. These
tests shall include the following:
A minimum for every 5,000 m3 using a combined sample of four random samples of the fill material.
QCI Saeed-Ul-Hassan
Field Control Tests:
1. Select Fill Material under all foundations, buildings and process areas - one test every 100 m² of each
lift.
2. Select Fill Material under roadways, railroads, area pavement and parking areas, and lined slopes or
drainage channels - one test every 200 m² of each lift
3. General Fill Material - one test every 500 m² of each lift.
a. Backfill of trenches - one test for every 15 linear meter of each lift.
Site preparation:
QCI Saeed-Ul-Hassan
SAES-Q-006 Asphalt and Sulfur Extended Asphalt Concrete Paving
Specification for Preparation of Subgrade Materials:
1. The entire subgrade shall be compacted to not less than 95% of the Max. Dry density per (ASTM D1557, or
AASHTO T180) while within +/- 1.5% of the optimum moisture content or to 85% of relative density
determined by ASTM D4253 and ASTM D4254.
2. The subgrade shall be constructed so that after being compacted, it will conform to the alignment, grade, and
cross-section shown on the plans, which shall not vary by more than +/-20mm or as required by the Project
construction specification.
3. Soil characteristics of subgrade materials shall be verified by CBR of laboratory compaction, ASTM D1883.
Where existing subgrade materials have a CBR of 5 or less, a subbase with a minimum CBR of 15 shall be
provided with a minimum thickness of 20 cm. (CBR shall be as determined by ASTM D1883 at 95% compaction
according to ASTM D1557 or AASHTO T180).
4. The subgrade shall be checked and approved by the Saudi Aramco representative prior to starting
construction of sub base and base on any portion of work.
Placing:
Granular subbase and base material shall be placed in layers of uniform thickness with approved spreaders.
Layer thickness shall not exceed 150 mm after compaction.
Compaction:
1. The water content of the material shall be maintained during compaction at the optimum percentage (±1.5%)
as determined by ASTM D1557 or AASHTO T180.
2. The rolling shall continue until the base and subbase are compacted to not less than (98% for the base and
95% for the subbase) of the Max. Laboratory dry density ASTM D1557 or AASHTO T180. In-place density shall
be measured by ASTM D6938 or ASTM D1556 or other approved methods.
3. Aggregate base and sub base compaction testing shall be conducted at a frequency of 1 test per 500 sq.m.
Each test is made by the average of 3 readings within the radius of 2 m.
Finishing:
The surface of the completed aggregate subbase shall not show any deviation in excess of ±20mm and ±10mm
for base course. The completed thickness of the base shall be within ±6 mm of the thickness indicated and the
average thickness shall not be less than the design thickness.
Prime Coat:
1. The prime coat shall be applied and shall consist of MC-70 or MC-250 conforming to the requirements of MOT
2. A prime coat shall consist of the initial application of liquid asphalt into the surface of non-asphalt base
course.
3. Prime coat shall be tested as per AASHTO R 66 for a maximum of 37,800 liters usage or 31,500 m² coverage
prior to applications.
Tack Coat:
1. A thin layer of asphalt that ensures the bonding b/w old & new asphalt layer.
2. Tack coat shall be tested as per AASHTO R 66 for a maximum of 37,800 liters usage or 31,500 m²
coverage prior to applications.
3. Bitumen distributor at a maximum rate of 0.25 liters per square meter as per ASTM D2995.
4. The atmospheric temperature is less than 16°C.
5. RC 70 & RC 250.
Job Mix:
The Job-Mix Formula (JMF) shall be evaluated, tested and certified by an SA approved civil testing laboratory and be
approved by Saudi Aramco. Accordance with ASTM D2172 or ASTM D6307.
Material Percent
30% by weight of the bitumen (asphalt binder) in the mix shall be replaced with pelletized elemental sulfur. The
maximum mixing temperature for sulfur extended asphalt mixtures is 140°C.
Exception:
1. Temperature of sulfur extended asphalt mixtures shall be between 130 and 140°C when it leaves the plant.
2. A temperature of at least 115°C at the time of spreading and compaction.
3. Temperature of mixtures without sulfur shall be between 139°C and 163°C.
4. Leaves the plant and at least 139°C at the time of spreading and compaction at the site.
5. Ambient temperature is 4°C or above.
QCI Saeed-Ul-Hassan
Placement, Compaction and Thickness:
1. Existing pavement shall be saw-cut and tacked, and the base course shall be primed prior to placing new hot
mix asphalt.
2. Steel skid equipment shall not be used for placing hot mix asphalt until after the first layer is placed.
3. Bituminous mixture shall be spread in a placement thickness so that after rolling, the nominal thickness of
the compacted bituminous material shall not be more than 70 mm per layer.
4. The in-place density result on compaction shall be equal to or greater than 95% for the bituminous base and
wearing course of the Marshall density per ASTM D6926. Using material sampled at the road site.
5. All compaction shall be completed before the temperature of the mixture drops below 90°C.
6. In no case shall thin layers of materials be added to the top of the wearing course in order to achieve the
required thickness or specified tolerances.
7. Areas of base course asphalt pavement which fail to meet the required tolerances / compaction shall be
removed by saw cutting to the full depth of the course, forming parallel and perpendicular lines to the
architectural features where practical. Any wearing course which fails to meet the required tolerances and
compaction should me milled to achieve required compaction and tolerances. The area for repair shall then
receive an additional tack coat prior to placing asphalt materials.
Protection:
Asphalt pavement shall not be in contact with pipelines that are catholically protected.
After final compaction & rolling, vehicular traffic should not be permitted on asphalt concrete for at least 24
hours and until pavement has hardened sufficiently.
1. Compaction and thickness of compacted asphalt concrete shall be accepted by lot. Unless otherwise stated in
the project documents, the lot size shall be the lesser of ten thousand (10,000) square meters, or the
production of a single day for each layer constructed.
2. Cores for density and thickness shall be taken daily from previous days production. Each core shall be legibly
and permanently marked as to the location from which the core was taken. A minimum of five (5) cores of
randomly selected location shall be tested for each lot.
3. The average actual in-place density from the five cores shall be compared with the bulk density determined
by ASTM D2726 of samples prepared by the Marshall method at 75 blows per side – ASTM D 6926.
4. Saudi Aramco representative may reduce the required number of cores to three (3) cores per lot, for lots
smaller than 1800 sq. meters.
Samples for extraction, gradation and Marshall Properties shall be taken daily at the following rates of production:
QCI Saeed-Ul-Hassan
Equipment:
1. All weighing scales for mineral aggregates and bitumen shall be calibrated and certified within the 6-month
period before use by one of Saudi Aramco approved calibration agencies.
2. All temperature gauges and thermometers shall be calibrated and certified two times a year by one of Saudi
Aramco approved calibration agencies.
3. All laboratory scales and balances, including drying ovens, shall be calibrated and certified two times a year
by a Saudi Aramco approved agency.
Plant QC Equipment:
1. Where sulfur extended asphalt paving is not used Polymer Modified Asphalt (PMA) can be used as an
alternative.
2. PMA can be used in locations like gates, heavy truck traffic areas and terminals to improve pavement
durability.
3. The mixing temperature for the binder shall be 170 +5°C.
4. The polymer modified asphalt mix shall be placed and compacted at a temperature determined from the
viscosity-temperature relationship which is estimated to be in the range of 155 to 165°C.
QCI Saeed-Ul-Hassan
SAES-Q-001 Criteria for Design and Construction of Concrete Structures
PIP CVC01015 Criteria for Civil design concrete
Self-consolidating Concrete: Fresh concrete that can flow around and encapsulate reinforcement and consolidate
within formwork under its own weight without any mechanical consolidation and vibration.
Hot Weather Concrete: Can be defined as job-site conditions that accelerate the rate of moisture loss or rate of
cement hydration of freshly mixed concrete, including an ambient temperature of 29°C or higher, and an evaporation
rate that exceeds 1 kg/m²/h. Limit the maximum allowable fresh concrete temperature to 35 °C (95 °F).
Mass Concrete: Any volume of concrete with dimensions large enough to require that measures be taken to cope with
generation of heat from hydration of the cement & attendant volume change to minimize cracking.
Cracks may cause: Cracks generated due to thermal gradients may cause
Materials:
1. Environmental concrete structures shall have a minimum 28-day design compressive strength of 35 MPa
(5,000 psi).
2. Unreinforced concrete of no significant structural value such as lean concrete for sub-slabs shall have a
minimum 28 day design compressive strength (ASTM C39) of 14 MPa (2,000 psi).
1. FRP reinforcement shall be used to replace steel reinforcement for non-critical structural elements in C1 & C2
exposures.
2. Including but not limited to, slab on grade, sidewalks, surface drainage channels, concrete paving, pipe
sleepers.
3. FRP reinforcement may add value such as Magnetic Resonance Imaging (MRI) room in hospitals, electrical
equipment foundations, sewage treatment plant, and sea walls shall be investigated.
Placing Concrete:
Concrete shall be placed in accordance with ACI 301-16, ACI 304R and this standard.
1. Equipment made of aluminum alloys shall not be used for pump lines, tremies, or chutes used to discharge
concrete from a truck mixer.
2. Raking shall not be used for movement of concrete after placement.
3. Vibrators shall not be used to move concrete inside forms.
4. Re-tempering after concrete is mixed shall not be permitted.
5. The interval between concrete deliveries shall be such that no more than 20 minutes interruptions elapse
during placement of a single foundation or slab, unless approved by Saudi Aramco.
Curing:
1. Maximum total dissolved solids in water used for curing shall not exceed 1,000 parts per million.
2. Water curing shall be continuous until the compressive strength has reached 70% of the specified strength,
but not less than 7 days.
3. The saturated burlaps shall be covered with a plasticized sheet vapor barrier, minimum 0.15 mm (6 mils) in
thickness and shall be kept in contact with the concrete surface at all times.
4. Curing shall occur for a minimum of 14 days.
1. A plasticized sheet vapor barrier in accordance with ASTM E1745, Class A, minimum of 0.25 mm (10 mils) in
thickness, shall be placed beneath slabs on grade.
2. A minimum of 50 mm sub-slab (lean concrete) shall be placed beneath concrete foundations.
3. All concrete surfaces in direct contact with earth shall be coated with two coats of coal tar or bitumen coating
that conforms to APCS-3 or APCS-10 of SAES-H-001.
4. Minimum of 0.25 mm (10 mils) in thickness shall be placed below and around the sides of concrete that is
placed directly into excavation without the use of formwork, where coal tar or bitumen coating cannot be
applied.
QCI Saeed-Ul-Hassan
SAES-Q-005 Concrete Foundations
PIP STE05121 Anchor Bolt Design Guide
Anchor Rods:
1. Anchor rods shall be in compliance with Standard Drawing AA- 036322-001 (Rev. 08 or later).
2. Material selection and galvanizing of anchor rods assemblies shall be per the requirements in 12- SAMSS-007.
3. The minimum anchor rod diameter shall be 20 mm (¾”).
4. Minimum clear distance from anchor rod to edge of concrete shall not be less than 100 mm.
5. Metallic anchor rod sleeves are not permitted.
6. The design of anchor rods shall be in accordance with the requirements of SAES-Q-304 Chapter 17.
Sleeve type:
1. Partial sleeve is primarily used for alignment requirements.
2. Full sleeve is used for alignment as well as for pretensioning.
Edge Distance: Cast-in handed anchor that will be torque to have min. edge distance of 6D
Edge distance for anchor bolts in machinery foundation is 4D, 6 inches minimum.
Spacing B/W for Anchors: Min. spacing b/w anchors to be at least 4D for untorque cast-in anchors & 6D for torque
anchors.
1. Types 1/1s ASTM-A307
2. Type 2/2s ASTM-A-36
3. Type 3/3s ASTM-A-193
Formula:
Double Nut Bolts (130mm)
Thickness of grout + Thickness of plate + 2.5*dia of bolt
Single Nut Bolt (10mm)
Thickness of grout + Thickness of plate + 1.5*dia of bolt
1. Anchor rods for connecting structural elements to the foundation that are not cast into the concrete.
2. Post-installed anchor rods are typically installed in a hole drilled into hardened concrete and bonded
to the foundation using a proprietary epoxy adhesive
3. Post-installed anchor rods in foundations shall not be used for new construction unless shown on
design drawings.
4. Post-installed anchor rods are permitted for repair and replacement of missing or damaged existing
anchors if the post-installed anchors are designed, installed.
QCI Saeed-Ul-Hassan
SAES-Q-010 Cement Based, Non-Shrink Grout for Structural and Equipment Grouting
Process Industry Practice STS03600 Non-shrink Cementitious Grout Specification
1. Cementitious grout is used in the foundations of static equipment, structural base plates, anchor bolts,
precast members, i.e., wall panels, beams, post tension ducts, etc.
2. Minimum 28 days compressive strength shall be 34.5 MPA (5,000 psi).
3. Where true non-shrink characteristics are not mandatory, site mixed grout shall use clean well graded sand
that meets the requirements of 09-SAMSS-088, Type V Portland cement ( ASTM C150) and potable water.
Minimum 28-day compressive strength shall be 13.8 MPA (2,000 psi).
4. Total dissolved solids (TDS) for mixing and curing water shall not exceed 500 ppm.
5. Grout shall be free of hydrogen gas producing, oxidizing catalysts and inorganic accelerators.
6. Concrete foundations shall be cured for a minimum of 7 days before surface preparations for grouting.
7. Laitance, oil-soaked or damaged concrete shall be removed down to sound concrete by chipping to the level
of sound fractured aggregate or to a minimum of the top 1 inch (25mm) of the concrete.
8. Grout shall be mixed per the Grout Manufacturer's instructions.
9. The minimum thickness of the grout shall be the space between the bottom of the base plate and the top of
the concrete foundation; the minimum thickness of grout shall be 25mm.
10. Grout shall be placed in only one direction to prevent trapping air; Grouting shall be quick and continuous to
avoid segregation, bleeding or premature initial set.
11. The temperature of the grout when placed shall be 230C + 30C. (ASTM C 1107).
12. Two sets of 3 grout test cubes shall be cast in the field for each day that grout is mixed and placed.
13. Cure the cubes in the field for three (3) days in the same way as the placed grout is cured.
14. Test compressive strength of cubes in accordance with applicable provisions of ASTM C109. Test one cube set
at 7 days and one cube set at 28 days.
15. When the grout's water/cement ratio is 0.4 or less, the grout shall be given a continuous water cure (covered
by wet burlap and 0.15mm polyethylene) for a minimum of 7 days. (ASTM C309)
16. The grout shall be tooled to a 45 angle down from the bottom of base plates after it has reached its initial set.
QCI Saeed-Ul-Hassan
SAES-Q-011 Epoxy Grout for Machinery Support
Process Industry Practices PIP STS03601 Epoxy Grout Specification
Resin: Component shall consist of a pre-measured, prepackaged, solvent free, liquid epoxy resin specifically
formulated for the used grout system.
Hardener: Component shall consist of a pre-measured, prepackaged liquid specifically formulated to produce the
specified final properties when mixed with the other component.
Aggregate: The aggregate shall be a pre-measured, prepackaged blend of inert, inorganic particulate fillers, such as
silica, designed specifically to provide the proper flow, handling and physical properties required for the grout
product.
1. The ratio of aggregate to resin and hardener shall be per the manufacturer recommendations. If aggregate
ratio is adjusted for field conditions, physical properties shall be obtained at the recommended fill ratio.
2. Expansion joints shall be incorporated into large epoxy grout pours to reduce the possibility of cracking,
especially when machinery-to- grout temperature differentials of 30°C are encountered. Expansion joints
should be placed at approximately 1.2 m to 1.8 m intervals in the grout foundation.
3. A layered combination of non-shrink cement and epoxy grout may be used, as permitted by SAES-Q-007 for
large baseplates that have structural webs deeper than 230 mm.
4. Maximum linear shrinkage (ASTM C531): 0.080 percent.
5. Minimum bond strength of epoxy grout to concrete (ASTM C882): 2000 psi (14 MPa)
6. Fifteen days before installation, the contractor shall submit for review and acceptance, a written quality
control program. The program shall include all forming, handling, mixing, placing, joint locations, joint details,
curing, testing, and inspection procedures
7. The minimum compressive strength (ASTM C579, Method B) is 12,000psi (80 Mpa) at 7 days.
8. Grout are applied only when surrounding temperatures are between 15°C and 32°C (60°F and 90°F) unless
otherwise specified in the manufacturer's data sheets.
QCI Saeed-Ul-Hassan
SAES-H-003 Protective Coatings for Industrial Concrete Structures
Saudi Aramco Approved Protective Coating System (APCS)
1. Coat buried concrete surfaces only up to grade level if APCS-3 or APCS-10 is selected.
2. APCS-10 is not suitable for hydrocarbon contact and direct sunlight exposure.
General Requirements:
1. The purpose of surface preparation is to remove laitance, contaminants and others adhered compounds on
the concrete like the curing agents, and to create an anchoring for coatings to be well adhered with the
concrete structures.
2. Concrete surface preparation prior to coating application shall include but not limited to: Repair of cracks,
spalls, pop outs, and other irregularities, Removal of surface contaminants that inhibit coating adhesion or
induce early coating deterioration, Roughen the smooth surfaces to improve coating adhesion, and
Eliminating any weak surface layers to establish the strong base required for many coating system. Use only
approved equipment for roughening of concrete surface.
3. After cleaning is completed ensure that surfaces are free of voids which may be exposed or enlarged during
blasting process. Repair the voids if necessary.
Acceptance Criteria :( Surface preparation, moisture testing and environmental condition inspection)
1. The coating shall be applied after the full curing time of concrete in accordance to SAES-Q-001.
2. New concrete must have a moisture content of 4% or less before the coating applications commence.
Note: Test report SATR-H-1003 “Concrete Moisture Field Test” (For Coating Purposes).
3. Coating shall not be applied when the substrate temperature is less than 10°C; or less than 3°C above dew
point.
4. After rinsing, force air dry surfaces for at least 24 hours prior to making any repairs to the concrete.
5. Cracks less than 10 mm wide and holes not exceeding 10 mm in diameter shall be filled using a qualified
epoxy filler or grout before applying primer/sealer to the surface.
Documentation:
Reports, logs and final acceptance documents shall be reported on the appropriate forms in SAES-H-001 Attachment.
QCI Saeed-Ul-Hassan
Concrete Moisture Field Test for Coating Purposes:
1. Tape a 4 mil thick (0.1mm), 18"x 18" (450mm x 450mm) of clear plastic sheet to the surface to be coated; tape
all around with duct tape.
2. Sheet shall remain in place for a minimum of 16 hours. Indicate number of hour’s sheet has been in place:
_____ hrs.
3. Remove and visually check the underside for moisture.
4. A If droplets of moisture are present, the concrete shall be given more curing time.
5. After 16 hours if no moisture is present on the inside of the plastic, the concrete is ready for coating.
1. Drill 2 holes 6mm Diameter, 25mm deep and 150mm apart (holes to be repaired after test)
2. Surface contaminants such as laitance and form oils shall be removed.
3. Insert the Elcometer probes into each hole and seal in place with silicone putty.
4. Wait 24 hours for the effects of the drilling to stabilize.
5. Moisture Content Reading: ____________%
6. Begin coating only if the moisture content reading is less than 4%.
Application:
Application:
QCI Saeed-Ul-Hassan
09-SAMSS-097 Ready-mixed Concrete
Mobile Volumetric-Measurement and Continuous-Mixing: ready-mixed concrete made from materials continuously
batched by volume, mixed in a continuous truck mixer, and delivered to the purchaser in a freshly mixed and
unhardened state. SAER-10516.
Modifications:
Ordinary Portland cement (Type I) sulfate resistant Portland cement (Type V) ASTM C150/C150M
Pozzolans:
Pozzolans that include natural volcanic ash, metakaolin, silica fume, and fly ash shall be used as follows:
Silica fume: When used as replacement for cement in concrete as binary mix, shall not be less than 7% and shall not
exceed 10% by weight of cementitious material. Silica fume can also be used in combination with other pozzolans or
Ground Granulated Blast Furnace Slag (GGBFS) when used as replacement for cement in concrete (Ternary mix).
Natural Pozzolans: (Such as volcanic ash) can be used as partial replacement of cement. The replacement shall be up
to 50% based on trial mix test results for strength, durability and heat of hydration limits.
Fly ash: Can be used as partial replacement for cement in concrete (binary or ternary mix) for durability purposes.
The amount of fly ash shall not be less than 25% by weight of cementitious material. Mass concrete fly ash content
shall be in accordance with ACI 301 chapter 8.
Ground Granulated Blast Furnace Slag (GGBFS): GGBFS can be used as partial replacement for cement in concrete
(binary or ternary mix) for durability purposes. The amount of GGBFS shall not be less than 60% and shall not exceed
80% by weight of cementitious material. Mass concrete GGBFS content shall be in accordance with ACI 301 chapter 8.
Mixing water:
1. Mixing water shall conform to ASTM C1602. When combined mixing water is used, mixing water shall be free
from oils, acids, organic matter or other deleterious substances.
2. The maximum water-soluble chloride ions in concrete shall not exceed 0.15% for reinforced concrete and
0.06% for pre-stressed concrete by weight of cement. The maximum Sulfate ions as SO3 shall not exceed 4%.
Tests shall be in accordance with ASTM C1218/C1218M.
3. Wash water shall not be used as mixing water.
Concrete slump:
Concrete with high-range water reducing or plasticizing admixtures shall have a target or nominal
slump of 150 mm, (±40 mm) at the point of discharge at the job site or otherwise specified.
Concrete with Ultra High Range Super plasticizer admixtures shall have a target or nominal slump flow
of 650 mm, (±65 mm) at the point of discharge at the job site or otherwise specified. A Slump flow test
shall be conducted per ASTM C1611/C1611M.
When concrete pumps are used, the slump shall be determined at the discharge point of the concrete
placement hose.
QCI Saeed-Ul-Hassan
Compressive strength tests:
1. Compressive strength is required at 28 days unless when concrete contains fly ash, natural pozzolan, GGBFS or
combination of any cementitious material (binary or ternary mix), strength is required at 56 days.
2. Test one set of laboratory-cured specimens at 7 days and one set of specimens at 28 days. Additional test of
one set at 56 days for concrete containing natural Pozzolan, fly ash, GGBFS, or combination of any
cementitious material.
3. Test one set of field-cured specimens at 7 days and one set of specimens at 28 days. Additional test of one set
at 56 days for concrete containing natural Pozzolan, fly ash, GGBFS, or a combination of any cementitious
material.
4. When strength of field-cured cylinders is less than 85% of companion laboratory-cured cylinders.
The test report shall include the following data for each test sample of concrete taken at the placement site:
1. Name of Project, Job Order (JO) for the Project, and designation of the structure
2. Slump or slump flow in millimeters
3. Ambient air temperature in ºC
4. Concrete temperature in ºC
5. % Air, when air entrainment is used.
Test reports shall be submitted within 7 days after tests are completed.
QCI Saeed-Ul-Hassan
09 SAMSS-088 Aggregate for Concrete
Calcareous Aggregates: Aggregates which composition is mainly calcite.
Qualification Requirements:
1. Samples shall be taken at random and at a frequency of at least one sample per 200 m³ of aggregate to be
shipped, but not less than one sample per month. Any material failing to comply with the specification shall
be rejected.
2. A minimum stockpile of 500 m³ of each aggregate size shall be committed by the suppliers and accepted.
3. Sand shall be washed prior to batching with washing water that shall comply with the requirements of ASTM
C1602.
QCI Saeed-Ul-Hassan
SAEP-381 Project Quality Issues Escalation Process
Purpose: The purpose of this SAEP is to:-
1. Implement a consistent method for escalating quality issues including Internal Non-conformance Reports
(INCRs), Logbook Entries (LBEs), Saudi Aramco Non-Conformance Reports (NCRs), Worksheets (WSs) and
Delinquent Worksheets (DWSs), as defined in Appendices A-1, A-2, and A-3, “Quality Issues Reporting
Process.”
2. Clearly define the corporate process for project quality issue escalation including its documentation,
requirements and definition of violation categories, systems and procedures.
3. Ensure roles and responsibilities for project quality issue escalation are well defined and auditable.
ACD: Agreed Completion Date: The date which the violation notification will be closed upon completion of the
required corrective and preventive actions for the reported violation fully.
LBE: Logbook Entries (First level of reporting quality deficiency using Manual Logbook or the Quality Management
Information System, QMIS/EPM)
NCR: Non-conformance Report (Issued by Saudi Aramco through SAP QM). A report reporting the variation from the
specified requirements.
WS: Worksheet (Mechanism to report project major violations, repeated moderate violations or escalating overdue
Violations Categories:
Major:
1. Violations of company standards including GIs that put the quality and integrity of the facility including its
workers and equipment at risk.
2. Repeat of Moderate violations
Moderate:
1. Any violation to MSAER, project specifications and approved IFC drawings that if the next phase of work
(critical path) is continued without correcting the violation.
2. Any violation to Schedule Q.
3. Repeat of minor violation
Minor:
1. Any violation to MSAER, project specifications and approved IFC drawings that may affect the quality of the
current phase of work but not necessarily affect the integrity of subsequent phases of work. i.e., the next
phase of work is not dependent on the correction of the violation.
2. Repeat of Minor INCR.
QCI Saeed-Ul-Hassan
Repeat Violation: A non-compliance of the same reference of MSAER, project specifications, or contract requirements
with the same root cause which indicate a gap or failure in certain quality process/system, repeated within six (6)
months period.
Repeat of Minor Violation within six (6) months: Repeat of Moderate or Major violation within six (6) months will
result to a Quality Notification starting at the next higher level of Violation Category and Notification.Escalate minor
violation if repeated more than 3 times within 6 months to a Moderate violation.
Repeated Internal Non-conformance Report (INCR) within six (6) months “Contractor’s Internal NCR”:
Agreed Completion Date (ACD): For all types of quality notifications (INCR, LBE, NCR, WS, and DWS)
If the first ACD is exceeding 90 calendar days regardless of the violation category (Minor, Moderate, and Major):
1. Project Inspection Division Head agreement is required for ACD, if it does not exceed 180 calendar days.
2. Inspection Department Manager Agreement is required for ACD exceeding 180 calendar days.
After the submittal of LBE to contractor and SAPMT, Project Inspection Field Supervisor is authorized to revise
the violation degree and the first Agreed Completion Date (ACD) which proposed by the Project Inspector
within 5 working days. This revision of ACD is not considered as an extension.
After the submittal of NCR (moderate violation) to SAPMT and prior to final approval, Project Inspection Unit
Supervisor is authorized to revise the first Agreed Completion Date (ACD) within 5 working days. This
revision of ACD is not considered as an extension.
After the submittal of WS (major violation) to Project Inspection Division Head and prior to the final approval,
Project Inspection Sr. Supervisor is authorized to revise the first Agreed Completion Date (ACD) within 5
working days. This revision of ACD is not considered as an extension.
Project Inspector:
1. Highlight to SAPMT any potential non-conforming material, product or work to avoid re-work.
2. Report in a timely manner any quality or technical deficiency through the QMIS/EPM (LBE).
3. Before LBE submittal, propose the first ACD and the degree of the violation depending on the committed
violations.
4. Support the PID Unit Supervisor in categorizing the INCR and monitoring its ACD.
5. Following-up and watching the ACD status of LBE issued by him.
QCI Saeed-Ul-Hassan
Industry Codes and Standards
American Society for Testing and Materials
1. ASTM C136 Sieve Analysis of Fine and Coarse Aggregates
2. ASTM D422 Particle-Size Analysis of Soils
3. ASTM D1557 Laboratory Compaction of Soil Using Modified Proctor Density
4. ASTM D4253 Maximum Index Density and Unit Weight of Soils Using a Vibratory Table
5. ASTM D4254 Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density
6. ASTM D4318 Liquid Limit, Plastic Limit and Plasticity Index of Soils
7. ASTM D6938 In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods
Ministry of Transport MOT 1998 General Specification for Road and Bridge Construction, November, 1998 Highway
Design Manuel (MOT) Volume 2 Design of Roadways.
Concrete Related:
British Standards: BS 1881: Part 124 Testing Concrete Methods for Analysis of Hardened Concrete
1. ACI 117 Standard Specifications for Tolerances for Concrete Construction and Materials
2. ACI 237R Self-Consolidating Concrete
3. ACI 301-16 Specifications for Structural Concrete
4. ACI 304R Guide for Measuring, Mixing, Transporting, and Placing Concrete
5. ACI 305R Hot Weather Concreting
6. ACI 318-14 Building Code Requirements for Structural Concrete
7. ACI 350 Code Requirements for Environmental Engineering Concrete Structures and Commentary
8. ACI 350.5 Specifications for Environmental Concrete Structures
9. ACI 440.1R Guide for the Design and Construction of Concrete Reinforced with FRP Bars
10. ACI 440.5 Specification for Construction with Fiber-reinforced Polymer Reinforcing Bars
11. ACI 562 Code Requirements for Evaluation, Repair, and Rehabilitation of Concrete Buildings
12. ACI SP-66 Detailing Manual - Details and Detailing of Concrete Reinforcement
13. ACI 234R Guide for the Use of Silica Fume in Concrete
14. ACI 301-20 Specifications for Concrete Construction
15. ACI 308.1 Normal, Heavyweight, and Mass Concrete Cure concrete
16. ACI 360R Design of slab on ground
17. ACI 347 Formwork for concrete
18. ACI 229R Controlled Low-Strength Materials
19. ACI 212.3R Chemical admixture
20. ACI 302.1R Guide to concrete floor & slab
SCHEDULE “Q”
This Schedule describes COMPANY’s minimum requirements for CONTRACTOR’s Quality System.
QCI Saeed-Ul-Hassan