Daily Activity, Documents Maintained
Daily Activity, Documents Maintained
Responsible for all activities related to the Project at the site - fm start to finish
5 Ensure that the Contractors are loaded judiciously and there is minimum of “No Dailly Work Plan, Nil "No work report" During Contractors
Work” situations. Contractors work work
6 Completion of pending points given by customer with the help of suitable Pending point List, Customer As reqd
engineer & material as required; within the scope of PO. Sign to be taken on Work Planning Completion Report,
Completion Report Daily Activity Report
7 Reporting to E&C Engineer and Project leader. Self E&C Leader Daily
8 Customer communication Self Customer, MOM, As reqd
mail
9 Do all sundry / unplanned activities as per requirement and keep a record of Daily Work Plan Daily Activity Report As reqd
the same.
10 Maintain record of all local expenses and send vouchers to HO twice a week. Expenses, Bills, E&C Leader As reqd
Vouchers,
Requirements
11 Maintain safe Custody of all tools, tackles, Documents, Safety gear etc. Self Daily
12 Ensure site discipline as per customer’s guidelines and Doshion guidelines. Self, team, vendors, Customer satisfaction Daily
contractors, Cust
guidelines
13 Ensure use of Safety gear Self, team, vendors, Customer satisfaction Daily
contractors, Cust
guidelines
14 Daily attendance record of self and Contractors people Attendance sheet Attendance record Daily
15 Training and guidance to undertrainee engineer Requirement Training As reqd
4 Coordination with Process engineer for system validation, commissioning & Daily Plan E&I work done report When work done
handing over.
5 Reconciliation of material & work done at site and same to get signed from Daily work done Report to E&C Daily
customer. report, Cust sign Leader
6 Get PO amendment / new PO fm Customer, for every additional work done at PO amdnt, Cust mail, E&C Leader, PL As required
site. MOM
7 Keep a record of every additional work done at site and take completion report Daily work done E&C Leader, PL As required
certificate from the customer immediately on completion of the additional work. report, Cust sign,
Special report sign
8 To return excess material from site to HO. Excess material E&C Leader, PL As required
record, Material
reconilliation report
signed with cust.
9 Attending meeting at site with customer and preparing MOM of discussions and Requirement MOM As required
sending the same to HO. Act as per the MOM and close all points at the
earliest and get completion report fm Customer. Send MOM and reports to HO
10 Certifying the bills of contractors for work done at site. Contractors bills, Certified Bills On completion of
Daily Work done Work by Contractor
reports, Contractors and approval by
attendance sheet Client
NAME : Mahesh Gaikwad EMPLOYEE CODE : 3362
DESIGNATION : Site Engineer
REPORTING TO : Project Leader through E&C Leader
Responsible for all activities related to the Project at the site - fm start to finish
11 Reconciliation of Bills, vouchers, challans and other accounts related issues Documents as listed Certify As required
with customers accounts, materials and Projects department.
12 Raising points of serious, important & urgent issues to E&C Engineer / Project Problem area Customer, E&C As required
Leader / Customer Leader, PL, MOM,
mail
13 Do local purchase after approval fm Project Leader. Requirement, LP Voucher As required, and in
approval fm E&C emergency
Leader / PL
14 Arrange local labour, other support equipment on hire / purchase as per site Requirement, Voucher As reqd.
requirements. approval fm E&C
Leader / PL
15 Report of any injury, accident, theft, fire etc to HO by fastest possible means Problem area Report, Phone, Mail, As reqd.
and then tender a detailed written report. Fax, to Customer &
HO
16 Review record of undertrainee Engineers report book Daily activity report of Report on training When done
trainee, Instructions given
fm E&C Leader
17 Obtain periodic water sample reports as per requirment of Commissioning Requirement as per To customer, Water As per program
activity. procedure sample reports
18 Generate Weekly Progress report and send the same to HO after signature fm Daily Report, Self E&C Leader Weekly
Customer.
Responsible for all activities related to the Project at the site - fm start to finish
12 Keep a record of every additional work done at site and take completion report Daily activity report, E&C Leader When done
certificate from the customer immediately on completion of the additional work. MOM with customer,
additional PO,
13 Attending meeting at site with customer; Prepare MOM of discussions; Send requirement, MOM, E&C Leader When done
MOM of same to HO. Act as per the MOM and close all points at the earliest Reports
and get completion report fm Customer. Send MOM and reports to HO
System operations Log sheets Log sheets E&C Leader During System
commissioning till
handing over
SN DOCUMENTS MAINTAINED
1 Material checking at site, mtl accounting and record keeping. Mtl chk list, Cust. E&C Leader Routinely done work
sign, Cust. MRN /
GRN
2 Daily attendance record of self and Contractors people Attendance Attendance record to Weekly
E&C Leader
3 No Work" record - contractor wise - with reasons. As required
4 Record of all important communication, MOMs, with customer, suppliers, As and when it
service engineers, HO etc. happens
5 Local Purchase details with Budgetory information.
SN AREAS OF FOCUS
1 Timely completion of Work
2 Quality of Work
3 Timely, complete and Clear communication with Client, Vendors and HO
4 Maintaining record of daily activities and taking signature of Cust.
5 Forwarding Daily Reports to HO
6 Timely forwarding Vouchers, bills attendance records to HO
7 Discipline & Safety at site
8 Transperancy & clarity in work, actions, communication
9 "Happy customer"- philosophy - but not at a loss to DVWS.
3 Do “Site Audit” to get introduced to key people, verify site readiness, Look and Site Audit, Inputs fm Site Audit Report Prior to opening the
identify local support facilities like – Hotels, transport, communication facilities, Customer, Local site for work
availability of Mechanical, Electrical, labour Contractors, crane facility, m/cery & people,
equ
4 Preparation of detailed E&C barchart. Project Barchart E&C Barchart in Prior to going to site
consultation with
E&C Leader
5 Planning of site erection activities as per given Bar chart. Project Barchart E&C Barchart in Bar chart
consultation with
E&C Leader
6 Finalize & Liaison with erection Contractor, get his PO released. Negotiations details Through E&C Leader When req, As per bar
chart
7 Undertake IQ with client. IQ document, IQ signed document When due
Installation to HO
completion
8 If “No work” is due to customers reason, then, to inform the customer of special No work for self / Intimation to As reqd.
charges towards this. To get credit note released immediately for the same Contractor, Daily Customer of the
from our accounts dept through E&C Coordinator. activity report, delay, charges.
Customer Intimeta E&C Leader
instructions
NAME : Mahesh Gaikwad EMPLOYEE CODE : 3362
DESIGNATION : Site Engineer
REPORTING TO : Project Leader through E&C Leader
Responsible for all activities related to the Project at the site - fm start to finish
9 To demobilize the site with clearance fm Project Leader if the site has “No No work for more MOM with Cust. No work conditions
work” condition for more than three days in a row. Also, to inform customer than 3 days in a row Instructions fm E&C fm DVWS or
about De-mobilization and re-mobilization charges and to send the debit note to and expect the same Leader / PL Customer
customer for the same t for for more than 3
days ahead.
10 Reconciliation of material at site prior to site closure. Material accounting, Report to E&C End of Project
Reconsiliation Leader
Report, Customer
sign
11 Return of all DVWS material prior to site closure with serviceability report of Material accounting, Report to E&C End of Project
each item Reconsiliation Leader
Report, Customer
sign
12 Taking “Clean” site closure report from Client. Work Completion E&C Leader End of Project
report, Handing over
report,
13 Make site expense balance sheet & submit to Project Leader. Expences Vouchers E&C Leader Weekly
14 Make and ammend the As built drgs and send the same to HO for formallising End of Piping work, to E&C Leader Completion of piping
and record As built drg, Cust. work
Sign
15 Training to the customer and his team. During to E&C Leader After trg is completed
Commissioning, Trg
certificate fm Cust.
16 Obtain "Customer Satisfaction Certificate". End of Project
17 Obtain Certificate fm client for "Accident free work done". End of Project
18 Support After Sales Servicing section as per requirement & instructions fm E&C Go to other site for As per instructions
Engineer / Servicing head. After sales work fm E&C Leader / PL
SN JOB DESCRIPTION
1 Responsible for all activities related to the Project - fm start to finish
2 Be the incharge of the site
3 Direct and Control activities at site as per the bar chart
4 Responsible for opening the site, erectioning, commissioning and successfully handing over the site to client within the planned time frame
16 Maintain Site Related documents and update them as per current procedures.
17 Clear and complete communication with HO, team members, client, contractors etc. Maintain record of all important communication.
18 Take care and ensure safety of tools, kits, safety gears, office equipment machinery, material, personnel.
19 Get PO amendments / approvals for change schemes, extra material - in writing from customer in advance.
20 Obtain water sample analysis reports as per planned schedules and periodicity.