A Case Study of CPM

The document outlines a construction project with various tasks, their durations, and a project network diagram. It details the critical path method calculations, identifying the critical path as tasks A, B, and C, which total 114 days. Additionally, it includes calculations for early start, early finish, late start, late finish, and total float for each activity.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

A Case Study of CPM

The document outlines a construction project with various tasks, their durations, and a project network diagram. It details the critical path method calculations, identifying the critical path as tasks A, B, and C, which total 114 days. Additionally, it includes calculations for early start, early finish, late start, late finish, and total float for each activity.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Task Description of Task Duration (Days)

A Site Setup 15
B Foundation Work 22
C Structural Frame 30
D Electricity Work 15
E Plumbing Work 12
F Interior & Finishing 25
G Final Inspection 7

Project Network Diagram

A(15
B(22)
)

E(1
2)

Task
A
B
C
D
E
F
G

Duration of
Project
A Case Study of Critical Path M
Predecessor Critical Path Calculations

A 0 A 15
B 0 15 15
C
D
D,E
G

In the below format

C(3 D(15
0) )
0 A 15
0 15 15

ES
EF
LS
LF
A
F(25) G(7) T

Duration ES EF LS LF TF
15 0 15 0 15 0
22 15 37 15 37 0
30 37 67 37 67 0
15 67 82 67 82 0
12 37 49 70 82 33
25 82 107 82 107 0
7 107 114 107 114 0

114 Days
The critical path is A B C
cal Path Method
Calculations

15 B 37 37 C 67 67 D
15 22 37 37 30 67 67 15

37 E 49 82 F 107
70 12 82 82 25 107

ow format

For Critcal Path


ES A EF Total Float
LS T LF Formula = Late Start date – Early Start date
or Late Finish date – Early Finish date
Early Start I calculated the total float of all activities and wrote
Early Finish below the activities
Late Start
Late Finish
Activity Free Float
Time or Duration Formula:
= ES of next Activity – EF of current Activity

I calculated the free float of all activities and wrote


below the activities

D F G
82
82

107 G 114
107 7 114

of current Activity