A Case Study of CPM
A Case Study of CPM
A Site Setup 15
B Foundation Work 22
C Structural Frame 30
D Electricity Work 15
E Plumbing Work 12
F Interior & Finishing 25
G Final Inspection 7
A(15
B(22)
)
E(1
2)
Task
A
B
C
D
E
F
G
Duration of
Project
A Case Study of Critical Path M
Predecessor Critical Path Calculations
A 0 A 15
B 0 15 15
C
D
D,E
G
C(3 D(15
0) )
0 A 15
0 15 15
ES
EF
LS
LF
A
F(25) G(7) T
Duration ES EF LS LF TF
15 0 15 0 15 0
22 15 37 15 37 0
30 37 67 37 67 0
15 67 82 67 82 0
12 37 49 70 82 33
25 82 107 82 107 0
7 107 114 107 114 0
114 Days
The critical path is A B C
cal Path Method
Calculations
15 B 37 37 C 67 67 D
15 22 37 37 30 67 67 15
37 E 49 82 F 107
70 12 82 82 25 107
ow format
D F G
82
82
107 G 114
107 7 114
of current Activity