The quarterly progress report details the construction of a new road in Assam under the NESIDS scheme, with a total approved cost of Rs. 202.90 crores. As of the end of December 2024, the overall physical progress of the project is 18.08%, with significant advancements in clearing, grubbing, and dismantling structures. The project is being executed by the Public Works Roads Department of Assam, with a completion date set for March 14, 2027.

Uploaded by

Das Rubul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views

QPR_Dec_2024_CT

The quarterly progress report details the construction of a new road in Assam under the NESIDS scheme, with a total approved cost of Rs. 202.90 crores. As of the end of December 2024, the overall physical progress of the project is 18.08%, with significant advancements in clearing, grubbing, and dismantling structures. The project is being executed by the Public Works Roads Department of Assam, with a completion date set for March 14, 2027.

Uploaded by

Das Rubul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Annex-B

QUARTERLY PROGRESS REPORT FOR QUARTER ENDING 31/12/2024


PROJECTS UNDER NORTH EAST SPECIAL INFRASTRUCTURE DEVELOPMENT SCHEME (NESIDS)

A. Identification Particulars
1 Name of Project Construction of new road from Chowkihola to Tarapung via
Borpung (Chowkihola-Arlongwoti road with one major bridge over
river Kaliyani) Assam under NESIDS (Length L = 50.523 Km)
2 Location State : Assam
Dist. : Karbianglong
3 Approved Cost (Rs. In Crores) : 202.90
4 Date of Approval of Project/Scheme : 30/07/2024
5 Tender Cost (Rs. In Lakhs) : 19651.00
6 Date of award of Contract (First WO) : 25/09/2024
(Copy of work order to be attached (only
once for the quarter in which it was issued.
Need not be submitted if submitted in
earlier quarter)
7 Whether Contract awarded on Turnkey basis : EPC
8 Whether awarded work is being executed Yes
based on PERT/CPM :
9 Original date of Completion of project/scheme : 14/03/2027 (as per Original WO)
10 Executing Agency (State Govt./PSU/Other agency (Specify) : Public Works Roads Department, Govt. of Assam

B. Overall Progress
Physical Progress (%)
Total Expenditre
Beginning of
Items During Quarter End of Quarter incurred
Quarter (End of
(Oct-Dec'24) (Cumulative) (Rs. In Crores)
Sept' 24)
1 i) Clearing & Grubbing 0.00% 67.09% 67.09%
2 ii) Cutting & Felling Tress 0.00% 34.48% 34.48%
3 iii) Dismantling of Structures 0.00% 68.59% 68.59%
4 i) E/W in Formation Cutting 0.00% 58.88% 58.88%
5 ii) Filling 0.00% 30.62% 30.62%
6 iii) Subgrade in Shoulder 0.00% 20.61% 20.61%
7 i) Granular Sub-base in Hard Shoulders 0.00% 0.00% 0.00%
8 ii) CTSB 0.00% 19.76% 19.76%
9 iii) WMM 0.00% 14.15% 14.15%
10 ii) Tack Coat 0.00% 0.00% 0.00%
11 vi) BC-40 mm 0.00% 0.00% 0.00%
12 i) RCC Box Culvert 0.00% 30.82% 30.82%
13 i)MNB at 8+958 0.00% 0.00% 0.00%
14 ii)MNB at 15+807 0.00% 0.00% 0.00%
15 iii) MNB at 21+064 0.00% 0.00% 0.00%
16 iv) MNB at 27+733 0.00% 0.00% 0.00%
17 v) MNB at 29+726 0.00% 0.00% 0.00%
Physical Progress (%)
Total Expenditre
Beginning of
Items During Quarter End of Quarter incurred
Quarter (End of
(Oct-Dec'24) (Cumulative) (Rs. In Crores)
Sept' 24)
18 vi) MNB at 34+021 0.00% 0.00% 0.00%
19 vii) MNB at 46+345 0.00% 0.00% 0.00%
20 i) MJB at 3+500 0.00% 0.00% 0.00%
21 i)RCC Rectangular Covered drain (built up 0.00% 0.00% 0.00%
22 area) (1m x 1m) Drain (0.5m x 0.45m)
ii)CC Trapezoidal 0.00% 30.00% 30.00%
23 9) Traffic Signs, Markings and Road 0.00% 0.00% 0.00%
24 Appurtenances
i) Breast Wall 0.00% 0.00% 0.00%
25 ii) Retaining Wall 0.00% 0.00% 0.00%
Ocerall Physical Progress 0.00% 18.08% 18.08%
Total Expendature
C. No. of Photographs attached
(minimum 2 photographs of 4 x 6 size of major component
executed/ under execution, from different angle, properly pasted
on A4 size paper should be submitted. On each A4 size paper only 2
Enclosed
photographs may be pasted. Photographs should be dated and
signed by Nodal Officer. In case of Road projects photographs at a
distance of every 1 km may of road completed may be submitted.

Signature by the Nodal Officer:


Name:
Designation:
Date:
Place:
Office Seal

Signature by Chief Engineer of Implementing Department:


Name:
Designation:
Date:
Place:
Office Seal

Chief Engineer, PWD Executive Engineer, PWRD


Border Roads and NEC Works Borpathar Road Division
Chandmari, Guwahati-3 Borpothar, Assam

You might also like