Cashflow
Cashflow
6.70 Walling(C.I.S) Gage 32 including eucalp.tree wall m2 213.00 1,151.89 245,352.57 245,352.57
6.80 Roofing(C.I.S) Gage 32 including eucalp.tree wall m2 202.00 1,126.96 227,645.92 227,645.92
6.90 Fencing(barbed wire spacing is 0.25m) m 527.84 430.59 227,281.04 227,281.04
wooden pole with Lean concrete (0.35mdia.x1.8m
6.10 high, spacing-every 1.5m) m 158.35 374.00 59,222.32 59,222.32
Sub Total-6 1,737,878.28 1,737,878.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00
7.00 Head Work (11m span length)
7.10 Cofferdam
7.1.la Site clearance for headwork m2 209.00 36.77 7,684.57 3,842.29 3,842.29
7.1.1 Soil excavation (60*2*2) m3 240.00 366.75 88,020.00 44,010.00 44,010.00
7.1.2 Rock Excavation(5*2*2) m3 20.00 705.29 14,105.77 7,052.88 7,052.88
7.1.3 Dewatering pump LPS 1.00 100,000.00 100,000.00 100,000.00
Sub Total-7.1 209,810.34 0.00 154,905.17 54,905.17 0.00 0.00 0.00 0.00 0.00
7.20 Weir(10m span)
7.2.1 Site clearing (30*30) m2 900.00 36.77 33,091.46 16,545.73 16,545.73
7.2.2 Soil excavation m3 60.00 366.75 22,005.00 11,002.50 11,002.50
7.2.3 Hard Rock Excavation m3 10.00 705.29 7,052.88 3,526.44 3,526.44
7.2.4 Hard core m2 20.00 586.94 11,738.86 5,869.43 5,869.43
7.2.5 Masonry works of mix ratio 1:3 m3 320.00 5,752.53 1,840,808.37 920,404.18 920,404.18
7.2.6 Mass Concrete RCC25 m3 68.00 10,796.00 734,128.24 367,064.12 367,064.12
7.2.7 Plastering, mix ratio 1:3 m2 650.00 400.12 260,077.14 130,038.57 130,038.57
7.2.8 Form work m2 60.00 819.69 49,181.26 24,590.63 24,590.63
Sub Total-7.2 2,958,083.22 0.00 1,479,041.61 1,479,041.61 0.00 0.00 0.00 0.00 0.00
7.30 Sittiling Basin U/s and D/s (12.8m span)
7.3.1 Soil excavation m3 720.00 366.75 264,060.00 132,030.00 132,030.00
7.3.2 Hard Rock Excavation m3 69.00 705.29 48,664.90 24,332.45 24,332.45
7.3.3 Hard core m2 260.00 586.94 152,605.20 76,302.60 76,302.60
7.3.4 Masonry works of mix ratio 1:3 m3 311.00 5,752.53 1,789,035.63 894,517.82 894,517.82
7.3.5 Plastering, mix ratio 1:3 m2 480.00 400.12 192,056.97 96,028.48 96,028.48
Sub Total-7.3 2,446,422.70 0.00 1,223,211.35 1,223,211.35 0.00 0.00 0.00 0.00 0.00
HUNDUMA NECHO WATER WORKS AND GENERAL CONTRACTOR
CASH FLOW DISTRIBUTION
Project:- Construction of Changal upgrading Small Scale irrigation project,LOT-1
Employer:Guduru Wereda Agriculture and Land Office
2025
Bill No. Description of works unit Qty Unit Rate Total cost/birr/ March Aprill May June July August September October
7.40 Wing Wall Us and D/s
7.4.1 Soil excavation m3 968.00 366.75 355,014.00 177,507.00 177,507.00
7.4.2 Compacted back fill from the material of m3 69.32 202.35 14,026.64 7,013.32 7,013.32
7.4.3 Hard Rock Excavation m3 86.00 705.29 60,654.81 30,327.40 30,327.40
7.4.4 Hard Core m3 102.00 586.94 59,868.19 29,934.10 29,934.10
7.4.5 Masonry works of mix ratio 1.3 m3 219.20 5,752.53 1,260,953.73 630,476.87 630,476.87
7.4.6 Plastering, mix ratio 1:3 m2 355.27 400.12 142,150.16 71,075.08 71,075.08
Sub Total-7.4 1,892,667.53 0.00 946,333.77 946,333.77 0.00 0.00 0.00 0.00 0.00
7.50 Pipe and pipe placing
7.5.1 Soil excavation m3 32.00 366.75 11,736.00 11,736.00
7.5.2 Compacted back fill m3 4.00 202.35 809.38 809.38
7.5.3 Hard Rock Excavation m3 2.00 705.29 1,410.58 1,410.58
7.5.4 Hard core m2 4.00 586.94 2,347.77 2,347.77
7.5.5 lean Concrete works of mix ratio 1:2:4 m2 4.00 428.72 1,714.89 1,714.89
Purchasing, transporting, and laying of plain
7.5.6 concrete pipes(dia.40cm) for both side Pcs 2.00 40,000.00 80,000.00 80,000.00
Sub Total-7.5 98,018.62 0.00 0.00 98,018.62 0.00 0.00 0.00 0.00 0.00
7.60 Gate fixing
7.6.1 Intake gate
Supply & installation of steel gate including steel
works, angle iron, sliding shaft as shown in the
Drawing Pcs 2.00 50,000.00 100,000.00 100,000.00
7.6.2 Under sluice gate
10.50 Fixing Iron metal gates at pipe inlet with frame Pcs 75.00 10,000.00 750,000.00 750,000.00
Sub Total-10 987,185.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 987,185.18