Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 1
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
b) Foundation column Tue 4/1/25 Wed
4/30/25 Foundation column
c) Grade beam Mon 4/7/25 Tue 5/6/25
Grade beam
2.40 Chip wood between slab Mon 4/7/25 Tue 5/6/25
panel and grade beam Chip wood between slab panel and grade beam
2.50 Reinforcement bar Tue 4/1/25 Wed
4/30/25
a) Ø8 deformed bar Tue 4/1/25 Wed
4/30/25 Ø8 deformed bar
b) Ø14 deformed bar Tue 4/1/25 Wed
4/30/25 Ø14 deformed bar
c) Ø16 deformed bar Tue 4/1/25 Wed
4/30/25 Ø16 deformed bar
2.60 Class B 20cm thick HCB Fri 4/25/25 Thu 6/26/25
Class B 20cm thick HCB
2.70 3 coats of Plastering of block Tue 5/6/25 Mon 7/7/25
wall 3 coats of Plastering of block wall
3.00 MASONRY WORK Mon 3/3/25 Mon 6/2/25
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 2
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
b) Ø14 deformed bar Thu 5/22/25 Mon
7/21/25 Ø14 deformed bar
2.10 ROOF WORK Tue 7/1/25 Thu 7/31/25
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 3
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
1.20 Bulk excavate in ordinary soil Mon 6/2/25 Mon
to reduce level to a depth not 6/30/25 Bulk excavate in ordinary soil to reduce level to a depth not exceeding 1.50m
1.30 Trench Excavation depth not Mon 6/2/25 Mon
exceeding 500mm 6/30/25 Trench Excavation depth not exceeding 500mm
1.40 Cart away Mon 6/2/25 Mon
6/30/25 Cart away
1.50 Select material supply ,fill and Mon 6/2/25 Mon
compact 6/30/25 Select material supply ,fill and compact
1.60 250mm thick hardcore Mon 6/2/25 Mon
6/30/25 250mm thick hardcore
1.70 Back filling with dry select Mon 6/2/25 Mon
material 6/30/25 Back filling with dry select material
B.SUPER-STRUCTURE Mon 6/2/25 Mon
6/30/25
2.00 Concrete Work Mon 6/2/25 Mon
6/30/25
2.10 50mm Lean concrete Mon 6/2/25 Mon
6/30/25 50mm Lean concrete
2.20 C-25 Reinforced concrete Mon 6/2/25 Mon
6/30/25
a) Beams Mon 6/2/25 Mon
6/30/25 Beams
b) Columns Mon 6/2/25 Mon
6/30/25 Columns
c) Slabs Mon 6/2/25 Mon
6/30/25 Slabs
2.30 Form work Mon 6/2/25 Mon
6/30/25
a) Beams Mon 6/2/25 Mon
6/30/25 Beams
b) Columns Mon 6/2/25 Mon
6/30/25 Columns
c) Slabs Mon 6/2/25 Mon
6/30/25 Slabs
2.40 Reinforcement bar Mon 6/2/25 Mon
6/30/25
a) Ø8 deformed bar Mon 6/2/25 Mon
6/30/25 Ø8 deformed bar
b) Ø10 deformed bar Mon 6/2/25 Mon
6/30/25 Ø10 deformed bar
c) Ø12 deformed bar Mon 6/2/25 Mon
6/30/25 Ø12 deformed bar
3.00 Block and Masonry work Mon 6/2/25 Mon
6/30/25
3.10 Class B 20cm thick HCB Mon 6/2/25 Mon
6/30/25 Class B 20cm thick HCB
3.20 50cm Masonry foundation Mon 6/2/25 Mon
6/30/25 50cm Masonry foundation
3.30 Retaining wallmasonry Mon 6/2/25 Mon
6/30/25 Retaining wallmasonry
4.00 ROOFING Mon 6/2/25 Mon
6/30/25
4.10 RHS Truss Mon 6/2/25 Mon
6/30/25
a) RHS 40*40*3 Bottom Mon 6/2/25 Mon
member 6/30/25 RHS 40*40*3 Bottom member
b) RHS 40*40*3 Top member Mon 6/2/25 Mon
6/30/25 RHS 40*40*3 Top member
c) RHS 30*30*3 Vertical and Mon 6/2/25 Mon
Diagonal 6/30/25 RHS 30*30*3 Vertical and Diagonal
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 4
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
4.20 RHS Purlin 40*40*3 Bottom Mon 6/2/25 Mon
member 6/30/25 RHS Purlin 40*40*3 Bottom member
4.30 CIS 28G Mon 6/2/25 Mon
6/30/25 CIS 28G
4.40 25*250mm facia board Mon 6/2/25 Mon
6/30/25 25*250mm facia board
4.50 Gutter Mon 6/2/25 Mon
6/30/25 Gutter
4.60 UPVC down pipe Mon 6/2/25 Mon
6/30/25 UPVC down pipe
5.00 WINDOWS AND DOORS Mon 6/2/25 Mon
6/30/25
5.10 1000*2500mm Door Mon 6/2/25 Mon
6/30/25 1000*2500mm Door
5.20 1500*1500mm Window Mon 6/2/25 Mon
6/30/25 1500*1500mm Window
6.00 FINISHING Mon 6/2/25 Mon
6/30/25
6.10 3 coats of Plastering of block Mon 6/2/25 Mon
wall 6/30/25 3 coats of Plastering of block wall
6.20 Plastic Paint (2 coats )on Mon 6/2/25 Mon
block wall 6/30/25 Plastic Paint (2 coats )on block wall
6.30 Cement Screed 20mm Mon 6/2/25 Mon
6/30/25 Cement Screed 20mm
7.00 ELECTRICAL Mon 6/2/25 Mon
INSTALLATION 6/30/25
7.10 Distribution board 2pcs ACB Mon 6/2/25 Mon
25A/1-Phase 6/30/25 Distribution board 2pcs ACB 25A/1-Phase
7.20 Light point Mon 6/2/25 Mon
6/30/25 Light point
7.30 Two way switches Mon 6/2/25 Mon
6/30/25 Two way switches
7.40 Socket outlet Mon 6/2/25 Mon
6/30/25 Socket outlet
7.50 Power Cable Mon 6/2/25 Mon
6/30/25 Power Cable
DRY LATRINE Mon 6/2/25 Mon
6/30/25
A.SUB-STRUCTURE Mon 6/2/25 Mon
6/30/25
1.00 EXCAVATION AND EARTH Mon 6/2/25 Mon
WORK 6/30/25
1.10 Clearing and grubbing Mon 6/2/25 Mon
200mm 6/30/25 Clearing and grubbing 200mm
1.20 Bulk excavate in ordinary Mon 6/2/25 Mon
soil to reduce level to a depth 6/30/25 Bulk excavate in ordinary soil to reduce level to a depth not exceeding 1.0m
1.30 Pit excavation in ordinary Mon 6/2/25 Mon
soil to reduce level to a depth 6/30/25 Pit excavation in ordinary soil to reduce level to a depth not exceeding 2.0m
1.40 Pit excavation in weathered Mon 6/2/25 Mon
rock l to reduce level to a 6/30/25 Pit excavation in weathered rock l to reduce level to a depth not exceeding 4.5m
1.50 Trench Excavation depth not Mon 6/2/25 Mon
exceeding 1000mm 6/30/25 Trench Excavation depth not exceeding 1000mm
1.60 Select material supply ,fill Mon 6/2/25 Mon
and compact 6/30/25 Select material supply ,fill and compact
1.70 Cart away Mon 6/2/25 Mon
6/30/25 Cart away
1.80 250mm thick hardcore Mon 6/2/25 Mon
6/30/25 250mm thick hardcore
2.00 Concrete Work Mon 6/2/25 Mon
6/30/25
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 5
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
2.10 50mm Lean concrete Mon 6/2/25 Mon
6/30/25 50mm Lean concrete
2.20 C-25 Reinforced concrete Mon 6/2/25 Mon
6/30/25
a) Grade Beams Mon 6/2/25 Mon
6/30/25 Grade Beams
b) Entrance steps Mon 6/2/25 Mon
6/30/25 Entrance steps
c) 10mm suspended floor slab Mon 6/2/25 Mon
6/30/25 10mm suspended floor slab
d) Entrance ramp Mon 6/2/25 Mon
6/30/25 Entrance ramp
2.30 Joint Filler Mon 6/2/25 Mon
6/30/25 Joint Filler
2.40 Form work Mon 6/2/25 Mon
6/30/25
a) Grade Beams Mon 6/2/25 Mon
6/30/25 Grade Beams
b) Entrance steps Mon 6/2/25 Mon
6/30/25 Entrance steps
c) Entrance ramp Mon 6/2/25 Mon
6/30/25 Entrance ramp
2.50 Reinforcement bar Mon 6/2/25 Mon
6/30/25
a) Ø8 deformed bar Mon 6/2/25 Mon
6/30/25 Ø8 deformed bar
b) Ø10 deformed bar Mon 6/2/25 Mon
6/30/25 Ø10 deformed bar
c) Ø12 deformed bar Mon 6/2/25 Mon
6/30/25 Ø12 deformed bar
d) Ø14 deformed bar Mon 6/2/25 Mon
6/30/25 Ø14 deformed bar
3.00 Masonry work Mon 6/2/25 Mon
6/30/25
3.10 Masonry foundation below Mon 6/2/25 Mon
ground level 6/30/25 Masonry foundation below ground level
3.20 50cm Masonry above ground Mon 6/2/25 Mon
level 6/30/25 50cm Masonry above ground level
3.30 Retaining wallmasonry Mon 6/2/25 Mon
6/30/25 Retaining wallmasonry
B.SUPER-STRUCTURE Mon 6/2/25 Mon
6/30/25
1.00 Concrete Work Mon 6/2/25 Mon
6/30/25
1.10 C-25 Reinforced concrete Mon 6/2/25 Mon
6/30/25
a) In Elevation of columns Mon 6/2/25 Mon
6/30/25 In Elevation of columns
b) In top tie beam Mon 6/2/25 Mon
6/30/25 In top tie beam
c) In Lintel Mon 6/2/25 Mon
6/30/25 In Lintel
1.20 Form work Mon 6/2/25 Mon
6/30/25
a) In Elevation of columns Mon 6/2/25 Mon
6/30/25 In Elevation of columns
b) In top tie beam Mon 6/2/25 Mon
6/30/25 In top tie beam
c) In Lintel Mon 6/2/25 Mon
6/30/25 In Lintel
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 6
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
1.30 Reinforcement bar Mon 6/2/25 Mon
6/30/25
a) Ø8 deformed bar Mon 6/2/25 Mon
6/30/25 Ø8 deformed bar
c) Ø12 deformed bar Mon 6/2/25 Mon
6/30/25 Ø12 deformed bar
2.00 Block work Mon 6/2/25 Mon
6/30/25
2.10 Class B 20cm thick HCB Mon 6/2/25 Mon
6/30/25 Class B 20cm thick HCB
2.20 Class B 15cm thick HCB Mon 6/2/25 Mon
6/30/25 Class B 15cm thick HCB
3.00 ROOF WATER PROOFING Mon 6/2/25 Mon
6/30/25
3.10 CIS 28G Mon 6/2/25 Mon
6/30/25 CIS 28G
3.20 Gutter Mon 6/2/25 Mon
6/30/25 Gutter
3.30 UPVC down pipe Mon 6/2/25 Mon
6/30/25 UPVC down pipe
3.40 Flat Sheet copping Mon 6/2/25 Mon
6/30/25 Flat Sheet copping
4.00 METAL WORK Mon 6/2/25 Mon
6/30/25
4.10 Windows Mon 6/2/25 Mon
6/30/25
a) 60*110cm Mon 6/2/25 Mon
6/30/25 60*110cm
b) 60*60cm Mon 6/2/25 Mon
6/30/25 60*60cm
5.30 Steel mesh wire Mon 6/2/25 Mon
6/30/25 Steel mesh wire
4.20 Doors Mon 6/2/25 Mon
6/30/25
a) 80*210cm Mon 6/2/25 Mon
6/30/25 80*210cm
b) 70*210cm Mon 6/2/25 Mon
6/30/25 70*210cm
5.00 CARPENTRY AND JOINERY Mon 6/2/25 Mon
6/30/25
5.10 Dia.10-12cm upper and lower Mon 6/2/25 Mon
wooden rafter 6/30/25 Dia.10-12cm upper and lower wooden rafter
5.20 Dia.8-10cm vertical and Mon 6/2/25 Mon
diagonal wooden truss 6/30/25 Dia.8-10cm vertical and diagonal wooden truss
5.30 5*7cm Zigba purlin Mon 6/2/25 Mon
6/30/25 5*7cm Zigba purlin
5.40 20*2cm Wooden Fascia Mon 6/2/25 Mon
6/30/25 20*2cm Wooden Fascia
5.50 9mm thick white pvc ceiling Mon 6/2/25 Mon
6/30/25 9mm thick white pvc ceiling
6.00 FINISHING Mon 6/2/25 Mon
6/30/25
6.10 3 coats of Plastering of Mon 6/2/25 Mon
internal wall 6/30/25 3 coats of Plastering of internal wall
6.20 Ceramic wall tile Mon 6/2/25 Mon
6/30/25 Ceramic wall tile
6.30 2 coats of Plastering of Mon 6/2/25 Mon
external wall 6/30/25 2 coats of Plastering of external wall
6.40 Ceramic Floor tile Mon 6/2/25 Mon
6/30/25 Ceramic Floor tile
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Sat 12/28/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
Page 7
CONSTRUCTION OF GABA SANBATA CROP MARKET CENTER GABA SANBATA CROP MARKET CENTER
Text1 Task Name Start Finish 2025
February March April May June July August September
6.50 Terazzo window sill Mon 6/2/25 Mon
6/30/25 Terazzo window sill
6.60 Stone pavement Mon 6/2/25 Mon
6/30/25 Stone pavement
6.70 Half dia.30cm concrete pipe Mon 6/2/25 Mon
6/30/25 Half dia.30cm concrete pipe
7.00 GLAZING Mon 6/2/25 Mon
6/30/25
7.10 4mm thick clear glass Mon 6/2/25 Mon
6/30/25 4mm thick clear glass
8.00 PAINTING Mon 6/2/25 Mon
6/30/25
8.10 3 coats of plastic emulsion Mon 6/2/25 Mon
paint 6/30/25
a) Internal walls Mon 6/2/25 Mon
6/30/25 Internal walls
b) External wall Mon 6/2/25 Mon
6/30/25 External wall
ESMP Mon 6/2/25 Mon
6/30/25
A.SUB-STRUCTURE Mon 6/2/25 Mon
6/30/25
1.00 EARTH WORK Mon 6/2/25 Mon
6/30/25
1.10 Clearing and grubbing Mon 6/2/25 Mon
200mm 6/30/25 Clearing and grubbing 200mm
1.20 Bulk excavate in ordinary Mon 6/2/25 Mon
soil to reduce level to a depth 6/30/25 Bulk excavate in ordinary soil to reduce level to a depth not exceeding 1.0m
1.30 Trench Excavation depth not Mon 6/2/25 Mon
exceeding 1000mm 6/30/25 Trench Excavation depth not exceeding 1000mm
1.40 Back filling with dry select Mon 6/2/25 Mon
material 6/30/25 Back filling with dry select material
B.SUPER-STRUCTURE Mon 6/2/25 Mon
6/30/25
1.50 Select material supply ,fill and Mon 6/2/25 Mon
compact 6/30/25 Select material supply ,fill and compact
1.60 Construction of ESM0 Mon 6/2/25 Mon
6/30/25 Construction of ESM0
1.70 250mm thick hardcore Mon 6/2/25 Mon
6/30/25 250mm thick hardcore
1.80 Retaining wall masonry Mon 6/2/25 Mon
6/30/25 Retaining wall masonry
1.90 Tapella Mon 6/2/25 Mon
6/30/25 Tapella
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Construction of Gaba S