Aym Maitama Boq Original
Aym Maitama Boq Original
PRELIMINARIES
CLEARING OF RUBBLES/FURTHER
A SUM 9,000,000.00
EXCAVATION MECHANICALLY
PRELIMINARIES CARRIED TO
18,400,000.00
SUMMARY………………
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
ELEMENT NR.1
SUBSTRUCTURE
Earthwork support
Earthwork support to faces of trench and
pit excavations, maximum depth not
F 996 m2 950.00 946,200.00
exceeding 2.00m and distance between
opposing faces exceeding 1.5m
Concrete works
Plain in-situ concrete; mix 1:3:6,
38mm granite stone in:
E 50mm thick blinding in column base 15 m3 101,500 1,522,500.00
F ditto : trench faces of excn 18 m3 101,500 1,827,000.00
G ditto: lift 1 m3 101,500 101,500.00
TO COLLECTION 69,931,240.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
REINFORCEMENT
TO COLLECTION 71,965,300.00
COLLECTION
PAGE 1 69,931,240.00
PAGE 2 71,965,300.00
SUBSTRUCTURE... Carried to
141,896,540.00
Summary
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
FRAMES
Vibrated Reinforced in-situ concrete
(1:2:4-19mm granite stone filled into
formwork and packed around
reinforcement (Reinforcement and
formwork measured seaparately) in:-
REINFORCEMENT
High yield reinforcement bar to B.S.
4449
10mm - 20mm as appicable in;
E Columns 3.00 tons ### 3,600,000.00
F Ditto beams 0.38 tons ### 456,000.00
G Ditto Stirrups 1.35 tons ### 1,620,000.00
H binding wire 3.00 roll 35,000 105,000.00
workmanship 4.75 sum 95,000 451,250.00
FORMWORK
Sawn formwork to:
Soffit of horizontal floor slabs and
beams
E edges & soffits of beam 900 m2 21,500 19,350,000.00
F slab soffits 736 m2 21,500 15,824,000.00
G lift 17 m2 21,500 365,000.00
REINFORCEMENT
High yield reinforcement bar to B.S.
4449
10mm - 20mm as appicable in;
H y-20mm 4.00 tons ### 4,800,000.00
J y-16mm 7 tons ### 8,400,000.00
K y-12mm 15 tons ### 18,000,000.00
L y-10mm 4 tons ### 4,800,000.00
M lift 1 ton ### 1,200,000.00
N binding wire 2kg 16 rolls 35,000 560,000.00
workmanship 31 tons 90,000 2,790,000.00
TO COLLECTION 14,876,500
REINFORCEMENT
High yield reinforcement bar to
B.S. 4449
10mm - 20mm as appicable in;
Y-20mm in columns (54 nos) 4.25 tons ### 5,100,000
Y-12mm in lintels 2.4 tons ### 2,880,000
Y-10mm stirrups to col. & lintels 3 tons ### 3,600,000
binding wire 20kg 3 roll 35,000 105,000
workmanship 9.65 tons 95,000 916,750
J wall, 225mm thick, vertical both ext & 550 m2 35,000 19,250,000
internal walls
TO COLLECTION 31,851,750
FORMWORK
Sawn formwork to:
Soffit of horizontal floor slabs and
beams
E edges & soffits of beam 901 m2 21,500 19,371,500.00
F slab soffits 736 m2 21,500 15,824,000.00
G lift 17 m2 21,500 365,500.00
TO COLLECTION 60,428,500.00
REINFORCEMENT
High yield reinforcement bar to B.S.
4449
10mm - 20mm as appicable in;
H y-20mm 3.00 tons ### 3,600,000.00
J y-16mm 9 tons ### 10,800,000.00
K y-12mm 14 tons ### 16,800,000.00
L y-10mm 4 tons ### 4,800,000.00
M lift 1 ton ### 1,200,000.00
N binding wire 2kg 16 rolls 35,000 560,000.00
workmanship 32 tons 90,000 2,880,000.00
TO COLLECTION 40,640,000.00
2ND FLOOR SLAB CARRIED TO
101,068,500.00
SUMMARRY…….
REINFORCEMENT
High yield reinforcement bar to
B.S. 4449
10mm - 20mm as appicable in;
Y-20mm in columns (54 nos) 4.25 tons ### 5,100,000
Y-12mm in lintels 2.4 tons ### 2,880,000
Y-10mm stirrups to col. & lintels 3 tons ### 3,600,000
binding wire 20kg 3 roll 35,000 105,000
workmanship 9.65 tons 95,000 916,750
J wall, 225mm thick, vertical both ext & 550 m2 35,000 19,250,000
internal walls
TO COLLECTION 31,851,750
2ND FLOOR GRAND TOTAL
Carried to Summary 147,797,250.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
GENERAL SUMMARY
A PRELIMINARY 18,400,000.00
NOTE:
THE BILL OF QUANTITY ABOVE
COVERED FOR WORKS FROM
1 PRELIMINARIES, FOUNDATION,
GROUNDFLOOR TO THE ROOF
SLAB ONLY.
Earthwork support
Earthwork support to faces of trench and
pit excavations, maximum depth not
F 996 m2 950.00 946,200.00
exceeding 2.00m and distance between
opposing faces exceeding 1.5m
Concrete works
Plain in-situ concrete; mix 1:3:6,
38mm granite stone in:
E 50mm thick blinding in Footing base 25 m3 101,000 2,525,000.00
G ditto: lift 1 m3 101,000 101,000.00
REINFORCEMENT
TO COLLECTION 145,927,900.00
RAFT FOUNDATION TOTAL SUM 159,423,832.00