0% found this document useful (0 votes)
20 views12 pages

Aym Maitama Boq Original

The document outlines a detailed bill of quantities for a construction project, including costs for preliminaries, substructure, frames, ground floor, first floor, and second floor works. It specifies various construction activities, materials, quantities, and associated costs, totaling approximately 157,228,790 for the ground floor and 146,904,750 for the first floor. The document provides a comprehensive breakdown of expenses related to concrete work, reinforcement, formwork, and block walling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
20 views12 pages

Aym Maitama Boq Original

The document outlines a detailed bill of quantities for a construction project, including costs for preliminaries, substructure, frames, ground floor, first floor, and second floor works. It specifies various construction activities, materials, quantities, and associated costs, totaling approximately 157,228,790 for the ground floor and 146,904,750 for the first floor. The document provides a comprehensive breakdown of expenses related to concrete work, reinforcement, formwork, and block walling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 12

ITEM DESCRIPTION QTY UNIT RATE AMOUNT

PRELIMINARIES

CLEARING OF RUBBLES/FURTHER
A SUM 9,000,000.00
EXCAVATION MECHANICALLY

B SETTING OUT OF WORKS SUM 2,500,000.00

C DRAWING DOCUMENTATIONS SUM 2,000,000.00

E WATER & ELECTRICITY SUM 2,500,000.00

F WORKING & STORAGE OF MATERIALS SUM 2,000,000.00

G PROJECT SIGNBOARD SUM 400,000.00

PRELIMINARIES CARRIED TO
18,400,000.00
SUMMARY………………
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
ELEMENT NR.1
SUBSTRUCTURE

EXCAVATION AND EARTHWORK


Site Prepation

Clearing of site bushes, schrubs and


undergrowth, grup up roots, burn on site,
A including excavation for topsoil, cartaway 792 m2 950.00 752,400.00
from site to prepare site for new
construction

excavate trench, commencing from


B stripped level and maximum depth 345 m3 4,000 1,380,000.00
not exceeding 1.00m

Ditto pit, commencing from stripped


level and maximum depth not
C 294 m3 4,500 1,323,000.00
exceeding 2.00m including working
space allowance

Ditto lift 8 m3 5,000 40,000.00

Filling to excavation, average


D thickness exceeding 1m arising from 639 m3 900 575,100.00
excavation.

Disposal of excavated materials to the


E 610 m3 900.00 549,000.00
approved location

Earthwork support
Earthwork support to faces of trench and
pit excavations, maximum depth not
F 996 m2 950.00 946,200.00
exceeding 2.00m and distance between
opposing faces exceeding 1.5m

G Prepare and apply aldrex 40 solution to 736 m2 300.00 220,800.00


all exposed faces of excn 100m2/ltr

Block Walls (Solid filled)


225mm sandcrete Hollow blockwork in
foundation in cement and sand mortar (1:4)
H 498 m2 35,000.00 17,430,000.00
including filling pockets with weak
concrete.

J Filling to make up level, average thickness


not exceeding 1m, laterite earth obtained 639 m3 6,530.00 4,172,670.00
offsite and well compacted.

Level and compact bottom of


K 736 m2 500 368,000.00
excavation
TO COLLECTION 27,757,170.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
SUBSTRUCTURE CONT'D………..
GUAGE 1000 POLYHENE SHEET IN
TWO LAYERS
Damp proof membrane, width
A 736 m2 700 515,200.00
exceeding
23m work subsequently covered.

blinding bed, cement & sand mix


B 22 m3 85,000 1,870,000.00
(1:6)
poured on dpm against receiving
hdcore
300mm Hardcore filling laid under
C floor bed and blinding surface with 221 m3 39,900 8,817,900.00
fine sand.
Anti termite treatment to sides and
D
bottom of excavation
Anti termite treatment to sides and
736 m2 700 515,200.00
bottom of excavation

Concrete works
Plain in-situ concrete; mix 1:3:6,
38mm granite stone in:
E 50mm thick blinding in column base 15 m3 101,500 1,522,500.00
F ditto : trench faces of excn 18 m3 101,500 1,827,000.00
G ditto: lift 1 m3 101,500 101,500.00
TO COLLECTION 69,931,240.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT

Vibrated In - Situ Concrete (Grade 25)


total volume filled into trench and well
packed into formwork (formwork
measured separately)

A Starter columns (approx 54nrs) 11 m3 117,500 1,292,500.00


B 450mm colomn base footing 152 m3 117,500 17,860,000.00
C lift wall and base 6 m3 117,500 705,000.00
D oversite concrete (150mmthi) 110 m3 117,500 12,925,000.00

REINFORCEMENT

High yield high bond reinforcement


bar to BS 4449 and 4461 cut and
bend to sizes including tying wire
and distance spacer in any class of
concrete

10mm - 20mm as appicable in;


E 20mm in column footings 13.00 tons ### 15,600,000.00
F 20mm in column starters (54nos) 3.20 tons ### 3,840,000.00
10mm in column starter & footings
G 0.80 tons ### 960,000.00
(stirrup)
H 12mm in lift 0.74 tons ### 888,000.00
J BRC mesh to ground slab (3.5mm) 736 sq.m 2,300 1,692,800.00
K binding wire 20kg 15 roll 35,000 525,000.00
L Workmanship to cut, bend & fix 17 tons 90,000 1,530,000.00

SAWN FORMWORK; FAIR SURFACE


TO:
M sides of col. Footings 540 m 21,500 11,610,000.00
N sides of col. Starter bars in fdn 72 m 21,500 1,548,000.00
P edges of oversite concrete 46 m 21,500 989,000.00

TO COLLECTION 71,965,300.00

COLLECTION

PAGE 1 69,931,240.00
PAGE 2 71,965,300.00

SUBSTRUCTURE... Carried to
141,896,540.00
Summary
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
FRAMES
Vibrated Reinforced in-situ concrete
(1:2:4-19mm granite stone filled into
formwork and packed around
reinforcement (Reinforcement and
formwork measured seaparately) in:-

Columns not exceeding 0.10m2 cross-


A 20 m3 117,500 2,350,000.00
sectional area

B lintels 8 m3 117,500 940,000.00

FORMWORK FOR IN-SITU


CONCRETE
Sawn formwork to:

C Vertical sides of columns 80 m2 21,500 1,720,000.00

D sides of lintels 40 m2 21,500 860,000.00

REINFORCEMENT
High yield reinforcement bar to B.S.
4449
10mm - 20mm as appicable in;
E Columns 3.00 tons ### 3,600,000.00
F Ditto beams 0.38 tons ### 456,000.00
G Ditto Stirrups 1.35 tons ### 1,620,000.00
H binding wire 3.00 roll 35,000 105,000.00
workmanship 4.75 sum 95,000 451,250.00

GROUNDFLOOR WALLS & PARTITIONS


F:10 BLOCK WALLING
Hollow sandcrete block joined in a cement
and sand mortar (1:6)

J wall, 225mm thick, vertical both ext & 95 m2 35,000 3,230,000


internal walls

FRAMES… Carried to Summary 15,332,250.00

GROUND FLOOR SUMMARY


SUBSTRUCTURE 141,896,540
FRAMES 15,332,250
GROUNDFLOOR TOTAL 157,228,790
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
SUSPENDED FLOOR SLAB1
CONCRETE WORK
Vibrated Reinforced ready-mix
concrete (1:2:4-19mm granite stone
filled into formwork and packed
around reinforcement (Reinforcement
and formwork measured seaparately)
in:-

A 150mm thick suspended floor slab 121 m3 117,500 14,217,500.00


B 250mmx450mmx550mmlong 68 m3 117,500 7,990,000.00
C lift 7m x 3.3m x 0.28m 7 m3 117,500 822,500.00
D stair case 1 & 2 9 m3 117,500 1,057,500.00

FORMWORK
Sawn formwork to:
Soffit of horizontal floor slabs and
beams
E edges & soffits of beam 900 m2 21,500 19,350,000.00
F slab soffits 736 m2 21,500 15,824,000.00
G lift 17 m2 21,500 365,000.00

REINFORCEMENT
High yield reinforcement bar to B.S.
4449
10mm - 20mm as appicable in;
H y-20mm 4.00 tons ### 4,800,000.00
J y-16mm 7 tons ### 8,400,000.00
K y-12mm 15 tons ### 18,000,000.00
L y-10mm 4 tons ### 4,800,000.00
M lift 1 ton ### 1,200,000.00
N binding wire 2kg 16 rolls 35,000 560,000.00
workmanship 31 tons 90,000 2,790,000.00

FIRST FLOOR SLAB CARRIED TO


100,176,500.00
SUMMARRY…….

ITEM DESCRIPTION QTY UNIT RATE AMOUNT


FRAMEWORK FIRST FLOOR
CONCRETE WORK
Vibrated Reinforced in-situ concrete
(1:2:4-19mm granite stone filled into
formwork and packed around
reinforcement (Reinforcement and
formwork measured seaparately) in:-

columns 23 m3 117,500 2,702,000


lintels 50 m3 117,500 5,875,000
sawn formwork softwood to;
sides of columns 116 m2 21,500 2,494,000
sides & soffits of lintels 177 m2 21,500 3,805,500

TO COLLECTION 14,876,500

REINFORCEMENT
High yield reinforcement bar to
B.S. 4449
10mm - 20mm as appicable in;
Y-20mm in columns (54 nos) 4.25 tons ### 5,100,000
Y-12mm in lintels 2.4 tons ### 2,880,000
Y-10mm stirrups to col. & lintels 3 tons ### 3,600,000
binding wire 20kg 3 roll 35,000 105,000
workmanship 9.65 tons 95,000 916,750

FIRST FLOOR WALLS & PARTITIONS


F:10 BLOCK WALLING
Hollow sandcrete block joined in a cement
and sand mortar (1:6)

J wall, 225mm thick, vertical both ext & 550 m2 35,000 19,250,000
internal walls

TO COLLECTION 31,851,750

FIRST FLOOR GRAND TOTAL


Carried to Summary 146,904,750.00

ITEM DESCRIPTION QTY UNIT RATE AMOUNT


SECOND FLOOR SLAB WORK
CONCRETE WORK
Vibrated Reinforced ready-mix
concrete (1:2:4-19mm granite stone
filled into formwork and packed
around reinforcement (Reinforcement
and formwork measured seaparately)
in:-

A 150mm thick suspended floor slab 125 m3 117,500 14,687,500.00


B 250mmx450mmx550mmlong 68 m3 117,500 7,990,000.00
C lift 7m x 3.3m x 0.28m 7 m3 117,500 822,500.00
D stair case 1 & 2 9 m3 117,500 1,057,500.00

FORMWORK
Sawn formwork to:
Soffit of horizontal floor slabs and
beams
E edges & soffits of beam 901 m2 21,500 19,371,500.00
F slab soffits 736 m2 21,500 15,824,000.00
G lift 17 m2 21,500 365,500.00

TO COLLECTION 60,428,500.00

REINFORCEMENT
High yield reinforcement bar to B.S.
4449
10mm - 20mm as appicable in;
H y-20mm 3.00 tons ### 3,600,000.00
J y-16mm 9 tons ### 10,800,000.00
K y-12mm 14 tons ### 16,800,000.00
L y-10mm 4 tons ### 4,800,000.00
M lift 1 ton ### 1,200,000.00
N binding wire 2kg 16 rolls 35,000 560,000.00
workmanship 32 tons 90,000 2,880,000.00
TO COLLECTION 40,640,000.00
2ND FLOOR SLAB CARRIED TO
101,068,500.00
SUMMARRY…….

ITEM DESCRIPTION QTY UNIT RATE AMOUNT


FRAMEWORK 2ND FLOOR
CONCRETE WORK
Vibrated Reinforced in-situ concrete
(1:2:4-19mm granite stone filled into
formwork and packed around
reinforcement (Reinforcement and
formwork measured seaparately) in:-

columns 23 m3 117,500 2,702,500


lintels 50 m3 117,500 5,875,000

sawn formwork softwood to;


sides of columns 116 m2 21,500 2,494,000
sides & soffits of lintels 177 m2 21,500 3,805,500
TO COLLECTION 14,877,000

REINFORCEMENT
High yield reinforcement bar to
B.S. 4449
10mm - 20mm as appicable in;
Y-20mm in columns (54 nos) 4.25 tons ### 5,100,000
Y-12mm in lintels 2.4 tons ### 2,880,000
Y-10mm stirrups to col. & lintels 3 tons ### 3,600,000
binding wire 20kg 3 roll 35,000 105,000
workmanship 9.65 tons 95,000 916,750

2ND FLOOR WALLS & PARTITIONS


F:10 BLOCK WALLING
Hollow sandcrete block joined in a cement
and sand mortar (1:6)

J wall, 225mm thick, vertical both ext & 550 m2 35,000 19,250,000
internal walls

TO COLLECTION 31,851,750
2ND FLOOR GRAND TOTAL
Carried to Summary 147,797,250.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
GENERAL SUMMARY

A PRELIMINARY 18,400,000.00

C GROUND FLOOR 157,228,790.00

D FIRST FLOOR 146,904,750.00

2ND FLOOR 147,797,250.00

F 3RD FLOOR 147,797,250.00

G ROOF SLAB WORK 147,797,250.00


H PLUMBING PIPE LAYOUTS SUM 7,000,000.00
J ELECTRICAL & CCTV PIPE WORKS SUM 12,000,000.00
TOTAL COST 784,925,290.00
ADD:

PROFESSIONAL FEE 10% SUM 78,492,529.00

GRAND TOTAL SUM 863,417,819.00

NOTE:
THE BILL OF QUANTITY ABOVE
COVERED FOR WORKS FROM
1 PRELIMINARIES, FOUNDATION,
GROUNDFLOOR TO THE ROOF
SLAB ONLY.

ALL QUANTITIES ARE STRICTLY


MEASURED BUT THE RATES ARE
SUBJECT TO RE-EVALUATION
2
SHOULD INCASE OF FLUCTIAON
OR INFLATION OF THE
CONSTRUCTION MATERIALS
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
ELEMENT NR.1
SUBSTRUCTURE
RAFT FOUNDATION CHOICE
EXCAVATION AND EARTHWORK
Site Prepation

Clearing of site bushes, schrubs and


undergrowth, grup up roots, burn on site,
A including excavation for topsoil, cartaway 792 m2 950.00 752,400.00
from site to prepare site for new
construction

excavate trench, commencing from


B stripped level and maximum depth 896 m3 4,000 3,584,000.00
not exceeding 1.00m

Ditto lift 8 m3 5,000 40,000.00

Filling to excavation, average


D thickness exceeding 1m arising from 639 m3 900 575,100.00
excavation.

Disposal of excavated materials to the


E 610 m3 900.00 549,000.00
approved location

Earthwork support
Earthwork support to faces of trench and
pit excavations, maximum depth not
F 996 m2 950.00 946,200.00
exceeding 2.00m and distance between
opposing faces exceeding 1.5m

G Prepare and apply aldrex 40 solution to 736 m2 300.00 220,800.00


all exposed faces of excn 100m2/ltr

J Filling to make up level, average thickness


not exceeding 1m, laterite earth obtained 736 m3 5,537.00 4,075,232.00
offsite and well compacted.

Level and compact bottom of


K 736 m2 500 368,000.00
excavation

GUAGE 1000 POLYHENE SHEET IN


TWO LAYERS
Damp proof membrane, width
A 736 m2 700 515,200.00
exceeding
23m work subsequently covered.

blinding bed, cement & sand mix


B 22 m3 85,000 1,870,000.00
(1:6)
poured on dpm against receiving
hdcore
TO COLLECTION 13,495,932.00
ITEM DESCRIPTION QTY UNIT RATE AMOUNT
300mm Hardcore filling laid under
C floor bed and blinding surface with 221 m3 39,900 8,817,900.00
fine sand.
Anti termite treatment to sides and
D
bottom of excavation
Anti termite treatment to sides and
736 m2 700 515,200.00
bottom of excavation

Concrete works
Plain in-situ concrete; mix 1:3:6,
38mm granite stone in:
E 50mm thick blinding in Footing base 25 m3 101,000 2,525,000.00
G ditto: lift 1 m3 101,000 101,000.00

Vibrated In - Situ Concrete (Grade 25)


total volume filled into trench and well
packed into formwork (formwork
measured separately)

A ground beams footing 350mmthi 270 m3 117,500 31,725,000.00


B 650mm high raft stems 98 m3 117,500 11,515,000.00
C lift wall and base 6 m3 117,500 705,000.00
D oversite concrete (150mmthi) 110 m3 117,500 12,925,000.00

REINFORCEMENT

High yield high bond reinforcement


bar to BS 4449 and 4461 cut and
bend to sizes including tying wire
and distance spacer in any class of
concrete

10mm - 20mm as appicable in;


E raft footing & stems 29.00 tons ### 34,800,000.00
F 20mm in column starters (54nos) 3.20 tons ### 3,840,000.00
10mm in column starter & footings
G 7.00 tons ### 8,400,000.00
(stirrup)
H 12mm in lift 0.74 tons ### 888,000.00
J BRC mesh to ground slab (3.5mm) 736 sq.m 2,300 1,692,800.00
K binding wire 20kg 15 roll 35,000 525,000.00
L Workmanship to cut, bend & fix 41 tons 90,000 3,690,000.00

SAWN FORMWORK; FAIR SURFACE


TO:
M sides of raft stems 518 m2 21,500 11,137,000.00
N sides of footings 518 m2 21,500 11,137,000.00
P edges of oversite concrete 46 m 21,500 989,000.00

TO COLLECTION 145,927,900.00
RAFT FOUNDATION TOTAL SUM 159,423,832.00

You might also like