Module 8 - Cost Management
Module 8 - Cost Management
SESSION 8
DR. KHALID AHMAD KHAN
PROJECT COST MANAGEMENT
Project Cost Management is primarily concerned with the cost of resources needed to
complete project activities.
The cost management planning is done early in the project planning phase and sets the
framework of the cost management processes so that performance will be efficient and
coordinated.
Project Cost management should consider the stakeholder requirements for managing
costs.
How the costs be aggregated:
Each control account is
The work breakdown
Each control account has assigned a unique code or
structure (WBS) will be
a unique code account Cost is controlled at the account number(s) that
used to provide the
that links directly to the control account level. links directly to the
framework for the cost
COST
accounting system performing organization’s
management plan
accounting system
MANAGEMENT
PLAN
Variance thresholds for monitoring cost
performance may be specified to indicate an
agreed-upon amount of variation to be allowed
before some action needs to be taken.
Estimate cost of all activities required to complete
the work related to the project.
PROJECT COST
Estimates include all factors including manpower, ESTIMATE
material to be used, equipment required, facilities,
information technology required, etc., and factors
that may be related to inflation.
1. Expert Judgment
• Expert advice will be solicited for carrying out estimating of costs.
2. Analogous estimating
• Also know as Top Down approach for estimation.
• It is done by using values from similar projects and historical information available.
• The information is adjusted to the present conditions.
• The method is not very accurate, is less costly and can be done in shorter period of time.
COST ESTIMATE TECHNIQUES
3. Parametric estimating
• In this method parameters are used for developing the costs. E.g. cost per sq. ft., cost per cubic
meter of concrete, cost per ton of steel, etc.
• This method is more accurate and is used for making bill of quantities (BOQ ).
4. Bottom-up estimating
• This is the most accurate method for estimating costs.
• Costing is done for each individual work package separately and rolled up to the control account
and up the total cost of the project.
• This method is more time consuming, hence more costly.
COST ESTIMATE TECHNIQUES
1. Contingency reserves
• Contingency reserves are for uncertain events that are known. These are called known-unknowns.
• This means that you know that there could be unknown event in future. E.g. Rain in monsoons,
non-availability of manpower for construction during the cutting of wheat season, so you keep
some contingency in reserve for that event if it happens. If the event happens then the contingency
reserve is used.
• This contingency reserve is added to the cost baseline of project.
2. Management reserves
• Management reserves is kept by the management and are for unknown-unknowns.
• Management reserves are not part of the project cost baseline.
BUDGETING
After cost baseline is approved, any changes in the cost baseline can
only be done through Integrated change control process.
Work package
Step 1 contingency
reserve
Activity
contingency
Total Budget
Amount
reserve
Cost Baseline
Including
Total
or
Control Project Mngt.
Work Account Budget for Reserve
Package cost Project
Activity cost estimate Manager
Estimates
Budget Components
COST BASELINE,
EXPENDITURES,
AND FUNDING
REQUIREMENTS
Q&A
DRKHALIDKHAN.ORG