Module 12 - Earned Value Analysis
Module 12 - Earned Value Analysis
ANALYSIS
MODULE 12
Dr. Khalid Ahmad Khan, Ph.D.,
PE, PMP
2 PROJECT PERFORMANCE
Efficiency
Is spending proportional
to work completed ?
Is progress according
to plan ?
Efficiency
Speed
A
30 30 30 30 30
B
20 20 20 20 20 20 20
C
40 40 40
D
40 40 40 40 40
E
40 40 40 40
F
30 30 30 30
G
30 30
H
20 20 20
I
10 10
9 BASELINE (PRIMAVERA)
10 METHODS FOR CALCULATING EV
METHOD How Earned Value is Calculated
% Progress X Budget value of activity
Percent Complete Activity is 30% complete and budget is 200.
EV= 30% X 200 = 60
Water
Mobilization Handling & Sub-Weir Main Weir
Care
Repair of
Right Existing
Side Left Side
Barrage Floor
Zone 9
Silt Excluder
Earth Sub-Structure Miscellaneous
Floors Apron
Works Works Works
Efficiency
EV vs. AC ?
Project Progress
Speed
Information
PV, AC, EV
EV vs. PV?
13 THE PROJECT
It’s my
pleasure to hmm...7,500 sft
award you construction, 8
this contract months to do it
for a new BHU all....3.72 million
budget....This
is going to be tough!
14 PLANNED VALUE (PV)
…Earthworks in
April should cost
PV for April 316,667…
316,667
15 BUDGET AT COMPLETION (BAC)
BC= 3.72 million
General
S ubtotal 210 0.00 0.00 0.00 0.00
Foundation
S ubtotal 54 850,000.00 850,000.00 850,000.00 950,000.00
1020 Foundation upto P linth 24 800,000.00 800,000.00 800,000.00 890,000.00 Foundation upto Plinth
1040 B lock Mas onry 15 96,000.00 96,000.00 96,000.00 106,000.00 Block Masonr y
Finis hes
S ubtotal 105 1,336,000.00 0.00 0.00 0.00
1100
1090
P lumbing
E lectrical W orks
15
25
100,000.00
200,000.00
0.00
0.00
0.00
0.00
0.00
0.00
Plumbing
x 1000 00 x 1000 00
10 40
9
AC PV 36
8 32
BAC
7 28
6 24
5 20
4 16
3 EV 12
2 8
Resource/Cost P r ofile Legend
Total of All Resour ces Detail scale (left): X 100000
1 4
Total ear ly cost per M onth (Cur r ent E stim ate) Cum ulative scale (right): X 100000
Curr ent estim ate cur ve
E arned value curve
1 2 3 4 5 6 7 8 9 10
P lanned value cur ve
Months
Sh eet 1 of 1
EV ANALYSIS – SCHEDULE PERFORMANCE
Data Date
BC
Current
Target
COST
SV
TIME
18 SCHEDULE VARIANCE
PV
BUDGET
formula: SV = EV - PV
PV
BUDGET
formula: SPI = EV / PV
Data Date
CPI (Cost Performance) BAC
EV / AC [1.0=On budget]
Target
COST
CV
AC
EV
TIME
21
COST VARIANCE
EV of the work I actually performed,
PERFORMANCE
AC BC = 3.722 M
BASED
formula: CV = EV - AC
BC = 3.722 M
how much did I budget for it to cost? PV = 1.982 M
AC = 1.640 M
how much did it actually cost?
formula: CPI = EV / AC
Utilization
% spent = AC = 1.64/3.72 = 44%
BC
Performance:
Data Date
CPI (Cost Performance)
EV / AC [1.0=On budget]
Delay
Projected
Target
COST
ETC
SV
CV
TIME
WHAT WILL BE THE FINAL COST?
Common EAC Formulae:
= BC .
.8(CPI) +.2(SPI)
= BC .
CPI * SPI (empirical formulae)
VARIANCE AT COMPLETION (VAC)
BC what the total job is supposed
to cost
BC = 3.722 M
did I budget for it to cost? PV = 1.982 M
AC ofhowthemuch
work I actually performed, EV = 1.450 M
BASED
AC = 1.640 M
did it actually cost?
BC = 3.722 M
did I budget for it to cost? PV = 1.982 M
AC ofhowthemuch
work I actually performed, EV = 1.450 M
BASED
AC = 1.640 M
did it actually cost?
PV
AC
cv
$ sv
EV
schedule variance = EV - PV =
cost variance = EV - AC =
30 POP QUIZ 2
PV
EV
$
AC
TIME NOW
schedule variance = EV - PV =
cost variance = EV - AC =
31 EARNED VALUE REVIEW EXERCISE
32 PERFORMANCE INDICES
COST PERF INDEX (CPI) = EV
AC
1.2
“GOOD”
TIME
1.0
CPI
.9
“BAD”
SPI
.8
33 EARNED VALUE PROBLEM INDICATORS
Zero variances