Shop_Drawing_Checking_Guide
Shop_Drawing_Checking_Guide
Contents
[hide]
3. Attention to detail
2. Geometric Accuracy
3. Buildabilitiy
Recommended checking approach
1. Check primary building datums first. This often requires the checker to create his own layout.
1.2 Span
The reason why it is important to check these things first, is that all other items fit in around these
datums. If the primary datums are right there is little chance of a major mistake.
etc. etc.
The advantage of this system is the checker does not forget what has been checked. Also the
detailer will not be confused, with what has or has not been checked, and what is a comment or an
important change.
2. Checker red marks the Detailer agrees with, are marked with yellow highlighter as they are edited
in the drawing. Red marks the Detailer disagrees with are marked with orange highlighter
3. The completed drawing and the markups are returned to the Checker. Orange markups are
discussed with the Detailer till a resolution is reached. Once this is finished, the Checker signs the
final drawing. This drawing is now ready for construction issue.
This process has been proven, through experience, to be an excellent way of reducing errors to a
commercially acceptable level.
2. Single parts
3. Purlin orders
8. Drawing index
2.7 Could I build the piece from the information shown on the detail?
6.1 Is the grade of the material noted correctly for all material?
10.4 Are all necessary dimensions shown correct on the plan / elevation views?
10.5 Are all member sizes shown correct for each member?
10.7 Are elevations at top of floors, roofs, landings etc. shown correct?
11.1 Are oversize washers required for the holding down bolts?
12. Did I thoroughly study all the design drawing to see if all the members in the in the scope of the
fabricators contract have been detailed?
12.1 Lintels.
13. Is there a better, less expensive way to fabricate any of the pieces?
14. Are any pieces detailed beyond the capabilities of the fabricator's equipment?
14.3 Are punch sizes available for the slotted and round holes shown?
15. Did I co-ordinate interface with other trades (holes for owner machinery, holes for wood, match
holes in existing members)?
16. Did I put a lot of my unwanted opinion into marking up the detail (did I mark it up the way I would
have detailed it) or did I check to see only if it was right or wrong (if it works let it go)?
17. Establish marks for typical parts such as base plates, cap plates, stiff plates, shear plates ,
connection angles.
18. Layout and confirm connections shown on design work... special concentration to brace bays,
rafters or trusses or girders and parts connecting to them. (any component that is not straight or
level
20. Layout and confirm connections for secondary items like girts, door frames and so on.
21. Layout and confirm connections for miscellaneous items stairs, handrail, ladders and so on.
22.1 Confirm no paint areas for field welding and slip critical connections
22.2 If galvanizing is involved confirm max sizes for shipping. Is there adequate drainage holes?