Appendix K Outside Management Control 2024 DRI (1)
Appendix K Outside Management Control 2024 DRI (1)
Following this introduction of Outside Management Control (OMC) guidelines, we have listed those cause codes
that GADS recognizes as being outside plant management control. At the end of this Appendix are guidelines for
removing OMC events from standard calculations. Annex D of IEEE 762, quoted below, sets the standard for
defining and handling OMC events. For more comments on OMC events, please refer to Section I-2 and III-13 of
these GADS Data Reporting Instructions.
There are a number of outage causes that may prevent the energy coming from a power generating plant from
reaching the customer. Some causes are due to the plant operation and equipment while others are outside plant
management control.
The standard sets a boundary on the generator side of the power station (see Figure K-1, below) for the
determination of equipment "outside management control".
Typical Interconnection
Generation Facility
(2) Out
Utility Distribution Co. ISO
Metering Metering
In
Disconnect Device Owned &
Operated by Generation Entity
Generator
Auxiliary Load
AUX Generator
PT A
Breaker
Generator
As shown in Figure K.1, a generating unit includes all equipment up to (in preferred order) (1) the high-voltage
terminals of the generator step-up (GSU) transformer and the station service transformers; (2) the GSU
transformer (load) side of the generator-voltage circuit breakers; or (3) at such equipment boundary as may be
reasonable considering the design and configuration of the generating unit.
It may be assumed that all problems within the power station boundary are within plant management control;
however that is not always the case. Therefore, there is a need for some additional clarification as to what is and
what is not under plant management control.
It is easier to identify those actions outside plant management control than to identify the responsibilities of plant
management. Therefore, the following are considered to be outside (external) of plant management control. All
other items are considered within their jurisdiction and are the responsibility of the plant management for
calculating power plant performance and statistics.
• Energy losses due to the following causes should not be considered when computing the unit controllable
performance because these losses are not considered to be under the control of plant management:
• Grid connection or substation failure. This reason relates to problems with transmission lines and
switchyard equipment outside the boundaries of the plant as specified by the “boundary of plant
responsibility” shown in Figure K-1 on this Annex.
• Acts of nature such as ice storms, tornados, winds, lightning, etc are not under plant management control,
whether inside or outside the plant boundary.
• Terrorist attacks on the generating/transmission facilities or transmission operating/repair errors are not
under plant management control.
• Special environmental limitations such as low cooling pond level, or water intake restrictions that could
not be prevented by operator action. These are acts of nature such as high ambient temperatures where
the equipment is working within design specifications. However, if the equipment is not maintained by
the plant such as opacity out of limits or NOx out of control, etc, then plant management should be
penalized. These are equipment problems and are within plant management control.
• (9130) Failure of fuel supplier to fulfill contractual obligations or a pre-arranged deal due to physical fuel
disruptions or operational impairments (e.g. force majeure on a pipeline or compressor down; making the
pipeline incapable of making its firm deliveries.)
This cause code is considered outside of management control. Examples of this would include:
Firm pipeline gas transportation segment interrupted causing disruption or reduction in the flow of
natural gas
Physical damage to pipeline or cyber disruption
Routine pipeline maintenance (e.g. pigging)
Commodity supplier fails to deliver firm gas to primary pipeline receipt point
(9131) Lack of fuel – due to contractual or tariff provisions that allow for service interruption or price
fluctuations during peak demand periods.
This cause code is not considered outside of management control. Examples of this would include:
Company’s fuel supply group allocates limited firm fuel to other fleet sites
Interruptible pipeline transportation interrupted
Pipeline issues Operational Flow Order
Pipeline enforces ratable takes provision to tariff levels
LDC confiscates or interrupts fuel scheduled for delivery to plant gate
Plant fuel buyer rejects gas at implied delivered price (possibly including penalties)
• Labor strikes. Outages or load reductions caused by labor strikes are not normally under the direct control
of plant management. These strikes may be company-wide problems or strikes outside the company’s
jurisdiction such as manufacturers (delaying repairs) or transportation (fuel supply) problems.
However, direct plant management grievances that result in a walkout or strike are under plant
management control and are included as penalties against the plant. If a labor strike is caused by plant
management/worker problems during an outage, any outage extensions are included as energy losses as
long as the unit is incapable of being restarted because of equipment failures, maintenance, overhauls, or
other activities.
• Other weather related problems such as seasonal variations in gross dependable capacity due to cooling
water temperature variations are not within plant management control.
9150 Labor strikes company-wide problems or strikes outside the company's jurisdiction such as
manufacturers (delaying repairs) or transportation (fuel supply) problems.
9200 High ash content (OMC)
9210 Low grindability (OMC)
9220 High sulfur content (OMC)
9230 High vanadium content (OMC)
9240 High sodium content (OMC)
9250 Low BTU coal (OMC)
9260 Low BTU oil (OMC)
9270 Wet coal (OMC)
9280 Frozen coal (OMC)
Background
The IEEE 762 “Definitions for Reporting Electric Generating Unit Reliability, Availability and Productivity” (Annex
D) is the basis for the OMC work. In part, Annex D states that:
“There are a number of outage causes that may prevent the energy coming from a power generating plant
from reaching the customer. Some causes are due to the plant operation and equipment while others are
outside plant management control.”
This Appendix K lists a number of cause codes that is universally accepted as those outside the control of
management by the GADS program. It also identifies certain conditions under which those specific cause codes
would be applied. The list may change with time and some additional clarifications may be added.
The list of cause codes shown hereafter should be reviewed from time to time to insure the latest cause codes are
used in the OMC equations.
It is also VERY important that all cause codes (including all OMC cause codes) be reported to GADS. Some
companies may wish to exclude a forced outage or change it to a non-curtailing event if it fits into the OMC
category. THAT IS NOT RIGHT! The event should be reported as a forced outage and the OMC calculations will
show the events without the FO.
OMC events will come in two forms: outages or deratings. The OMC event types can be either forced, maintenance
or planned but it is expected that the majority will be forced outage events.
For all existing GADS equation calculations, the OMC events will be treated as a standard event, i.e., a forced
outage, forced derate, etc. The calculation will not change and will follow the calculations shown in Appendix F of
the GADS DRI.
In calculating equations without OMC events, it is important to remember that the objective of the removal of
OMC events is to affect the availability of the unit. To that end, we handle outages differently than derates. In
removing a particular event from a unit’s event records we are faced with the question of what to put in place of
the missing event. In the case of an outage, there is no sure way of knowing in what state a unit should be
considered. The only sure thing is our objective of returning those hours to an available state. That is exactly what
we do and that is all we do. Assuming that the unit is in reserve or in service during the time of the removed OMC
outage event, and so, adding to either service or reserve hours presents a fictional summary of the unit’s
performance. In viewing the available hours we temporarily recalculate AH as (Service + Reserve + Synchronous
Condensing + Pumping + OMC).
In the case of a derating event, however, we know for certain the state of the unit at the time of the removed
event. Whenever an event is removed it is necessary to look for any derating events that may have been shadowed
by or overlapping the removed event. Those overlapping hours must be accounted for by the software processing
the OMC event. It isn’t enough to simply recalculate Equivalent Availability by adding the sum of the removed
OMC events because we need to now take into account the effect of the newly uncovered (un-overlapped)
derating events.
Before we begin defining the methods there is an important assumption that needs to be made as to the
processing of the data. Since the removal of the OMC outage event is seen as an adjustment, we’ll assume that
outage events have been processed as normal and that OMC removal is acting on clean data and that performance
totals have already been summed for the unit. Also, in the case of derate events, that loss attributed to an event
has been calculated particularly in the case of overlapping and shadowed events.
above. The NAC of the unit at the start of the overlapping event is increased, but the loss attributed
to that event remains constant. (Normal derate events are considered loss-constant throughout their
duration)
c. OMC derate event which is shadowed by a dominant derate – In this case, the overlapping derate is
dominant and so, is considered to be capacity-constant. This means that removing the OMC event has
no effect on the available capacity within the dominant overlapping derate. The adjustment to the
unit performance stats would be limited to the duration and equivalent hours of that portion of the
OMC event that exists outside the dominant derate.
d. A dominant OMC derate overlaps another derate – When the OMC derate event is marked as
dominant, multiple adjustments may be necessary. The first adjustment is to take care of the total
duration and equivalent hours of the OMC derate event. Once the OMC derate event affect is
removed, the overlapped derate event(s) need to be accounted for by adding those portions of the
event(s) that were overlapped by the OMC event to the equivalent hours total as well as any total
durations. The number of derate event occurrences would not need to be adjusted.
e. OMC derate event is shadowed by an outage – Since an outage effectively truncates the derate
event, only the portion of the OMC derate that extends outside the overlapping outage needs to be
accounted for and removed.
OMC Outage (any type) is removed from shadowed Unit available hours increase by the outage
derate. duration. Equivalent hours are adjusted upward by
the overlapped portion when derate D1 is now
accounted for at its actual value.
OMC Derate is removed from above D2 Loss attributed to D2 remains unchanged. NAC of
the unit increases
OMC Derate is removed from inside D2 The effect of removing the OMC event is to
increase availability by the portions which extend
beyond the dominant derate.
Dominant OMC Derate is removed. Events D1, D2 and D4 are extended and totalled at
their original values.
OMC Derate is removed from being shadowed by an The effect of removing the OMC event is to
outage (any type) increase availability by the portions which extend
beyond the outage.
Please note also that any equation that excludes OMC events be calculated in the same methods as that in IEEE
762 and Appendix F of the GADS DRI but the names are modified to show they exclude OMC events. These
equations will be used against the benchmark calculations to show what the unit could have done without OMC
events. Both numbers will be provided by GADS and either number can be used based on the needs and the
reports.
Equations 95-141 in Appendix F are for calculating the performance statistics without OMC events. Please note
that they are the same as the equations for calculating the performance statistics with OMC events except that
their names have an “X” in front of them.
Table K-1 below shows how the event based performance statistics can be affected by excluding OMC events. Two
statistics, Starting Reliability (SR) and Seasonal Derating Factor (SEDF), do not have without OMC definitions. XSR
is not defined because IEEE 762 does not adjust the actual/attempted starts when OMC events are removed, and
although SEDF is based on available hours (AH), a without OMC version is not defined by NERC. Service Factor (SF)
is not affected because it is only based on service hours (SH), which are not affected by removing OMC events.
Because only AH is adjusted when excluding OMC events the performance statistics do, on rare occasions, exceed
100%. That is inherent with the concept of OMC events because the objective of their removal is to affect the
availability of the unit and nothing else.