0% found this document useful (0 votes)
15 views

BLR#2 PSSR points update as on 17.10.2021

The document outlines the status of various PSSR points related to a boiler as of October 2022, detailing completed tasks and those pending. A total of 52 points are listed, categorized into completed and pending statuses across departments. The majority of the points are marked as completed, while several require planning or are under progress.

Uploaded by

Thyssen Borl
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views

BLR#2 PSSR points update as on 17.10.2021

The document outlines the status of various PSSR points related to a boiler as of October 2022, detailing completed tasks and those pending. A total of 52 points are listed, categorized into completed and pending statuses across departments. The majority of the points are marked as completed, while several require planning or are under progress.

Uploaded by

Thyssen Borl
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Boiler - 2 PSSR Points Dtd: 12/10/2021

Status Updated on
S.No. Point Description Category Dept Remarks 16.10.2021 Status Updated on 17.10.2022

1 Drum LHS PSV & M.S. Line PSV gagging to be removed A MMD Completed Completed
2 MSSV MOV removed condition, to be restored A EMD Completed Completed
Buckstay pin removed condition for combuster near FBHE#2 elevation
3 B MMD Completed
Completed
4 Plant air MIV near FBHE # 2 jamming condition A MMD Completed Completed
5 Boiler Expansion indicators are missing B MMD To be planned Pending
6 PA SCAPH I/L damper operating wheel missing A MMD To be planned Pending
7 SA SCAPH I/L & O/L damper operating wheel missing A MMD To be planned Pending
SA APH BYPASS -MOV missing (reinstallation) and operating wheel A EMD / MMD To be planned
8
missing Pending
9 H.P. dozing pump A gear box not available A MMD Completed Completed
10 Wind box drain MIV towords ESP side not available A MMD NEW Pending
Erected scaffolding removal required from below areas
10 LHS cyclone roof top B MMD U/P Pending
11 BAC # 2 near to vent line MEJ B MMD Completed Completed
12 FBHE # 1 I/L HDR B MMD Completed Completed
13 ECO I/L HDR B MMD Completed Completed
14 FBHE # 2 outside facing towards B-1 B MMD Completed scaffolding shifting pending
15 RHS & LHS sealpot B MMD U/P Pending
16 Soot Blower # 30 B MMD Completed scaffolding shifting pending
17 Hot PA duct above B MMD Completed Completed
18 DESH -1 B MMD NEW Pending
Scaffolding material removal required from below mentioned nearby areas
18 Soot Blower # 2 B MMD Completed Completed
19 RHS COD B MMD Completed Completed
20 Cyclone floor B MMD U/P U/P
21 DESH-1 B MMD Completed Completed
22 3rd floor near DCLF 2A B MMD U/P Pending
23 Soot Blower # 27 B MMD Completed Pending
24 Combustor manhole door area B MMD Completed Completed
25 1st pass pent house roof ladder to be removed B MMD U/P Pending
House keeping required at below mentioned areas
26 RHS side 5th floor platform B OPN Completed Completed
27 DESH-1 - Refractory material B MMD (Refractory) Completed Completed
28 FBHE # 3 roof top B OPN Completed Completed
29 FBHE # 4 near drain hopper cleaning B OPN U/P U/P
30 PA SCAPH duct roof top insulation material B MMD (Insulation) Completed Completed
31 PA, SA Fan platform B OPN Completed Completed
32 SUB - 1 & 2 floor area B OPN Completed Completed
33 SA duct to SUB # 2 B OPN Completed Completed
Unwanted material like gas cylinders, welding machines etc removal required from nearby
34 DESH -1 B MMD Completed Pending
35 4TH floor- refractory mixing machine B MMD Completed Completed
36 LHS cyclone roof top - chain block , rope etc B MMD Completed Completed
37 Soot Blower # 7 feed pipe, cladding sheet B MMD U/P Pending
38 5TH floor chain block B MMD U/P Pending
39 Cyclone floor B MMD U/P Pending
40 3rd Floor near 2A B MMD U/P Pending
41 FBHE # 1 B MMD Completed Completed
42 FBHE # 2 B MMD Completed scaffolding shifting pending
43 Bedlance -3,4 B MMD U/P U/P
Insulation in damaged condition at below areas
44 SA main damper nearby B MMD Completed Pending
SA to combuster at 3rd floor B MMD
45 To be planned
on 17-10-2021 Pending
Insulation scrap removal required from below areas
46 3rd floor near 2A B MMD U/P Pending
47 near 2A bunker hanging B MMD U/P Pending
Cable dmaged / mispositioned
48 Near FBHE # 3 & PA SCAPH (Lighting) B EMD Completed Completed
49 2A RAV near (Lighting) B EMD Completed Completed
Lighting damaged at below points
50 3rd floor -2 bulbs B EMD Completed Completed
51 4th floor -2 bulbs B EMD Completed Completed
Safety point of view requirement of
52 Hot SA O/L duct manhole door railing for stair case B MMD U/P Pending

Category of Under
PSSR Completed progress Total
/Pending
A 4 3 7
B 28 17 45

You might also like