BLR#2 PSSR points update as on 17.10.2021
BLR#2 PSSR points update as on 17.10.2021
Status Updated on
S.No. Point Description Category Dept Remarks 16.10.2021 Status Updated on 17.10.2022
1 Drum LHS PSV & M.S. Line PSV gagging to be removed A MMD Completed Completed
2 MSSV MOV removed condition, to be restored A EMD Completed Completed
Buckstay pin removed condition for combuster near FBHE#2 elevation
3 B MMD Completed
Completed
4 Plant air MIV near FBHE # 2 jamming condition A MMD Completed Completed
5 Boiler Expansion indicators are missing B MMD To be planned Pending
6 PA SCAPH I/L damper operating wheel missing A MMD To be planned Pending
7 SA SCAPH I/L & O/L damper operating wheel missing A MMD To be planned Pending
SA APH BYPASS -MOV missing (reinstallation) and operating wheel A EMD / MMD To be planned
8
missing Pending
9 H.P. dozing pump A gear box not available A MMD Completed Completed
10 Wind box drain MIV towords ESP side not available A MMD NEW Pending
Erected scaffolding removal required from below areas
10 LHS cyclone roof top B MMD U/P Pending
11 BAC # 2 near to vent line MEJ B MMD Completed Completed
12 FBHE # 1 I/L HDR B MMD Completed Completed
13 ECO I/L HDR B MMD Completed Completed
14 FBHE # 2 outside facing towards B-1 B MMD Completed scaffolding shifting pending
15 RHS & LHS sealpot B MMD U/P Pending
16 Soot Blower # 30 B MMD Completed scaffolding shifting pending
17 Hot PA duct above B MMD Completed Completed
18 DESH -1 B MMD NEW Pending
Scaffolding material removal required from below mentioned nearby areas
18 Soot Blower # 2 B MMD Completed Completed
19 RHS COD B MMD Completed Completed
20 Cyclone floor B MMD U/P U/P
21 DESH-1 B MMD Completed Completed
22 3rd floor near DCLF 2A B MMD U/P Pending
23 Soot Blower # 27 B MMD Completed Pending
24 Combustor manhole door area B MMD Completed Completed
25 1st pass pent house roof ladder to be removed B MMD U/P Pending
House keeping required at below mentioned areas
26 RHS side 5th floor platform B OPN Completed Completed
27 DESH-1 - Refractory material B MMD (Refractory) Completed Completed
28 FBHE # 3 roof top B OPN Completed Completed
29 FBHE # 4 near drain hopper cleaning B OPN U/P U/P
30 PA SCAPH duct roof top insulation material B MMD (Insulation) Completed Completed
31 PA, SA Fan platform B OPN Completed Completed
32 SUB - 1 & 2 floor area B OPN Completed Completed
33 SA duct to SUB # 2 B OPN Completed Completed
Unwanted material like gas cylinders, welding machines etc removal required from nearby
34 DESH -1 B MMD Completed Pending
35 4TH floor- refractory mixing machine B MMD Completed Completed
36 LHS cyclone roof top - chain block , rope etc B MMD Completed Completed
37 Soot Blower # 7 feed pipe, cladding sheet B MMD U/P Pending
38 5TH floor chain block B MMD U/P Pending
39 Cyclone floor B MMD U/P Pending
40 3rd Floor near 2A B MMD U/P Pending
41 FBHE # 1 B MMD Completed Completed
42 FBHE # 2 B MMD Completed scaffolding shifting pending
43 Bedlance -3,4 B MMD U/P U/P
Insulation in damaged condition at below areas
44 SA main damper nearby B MMD Completed Pending
SA to combuster at 3rd floor B MMD
45 To be planned
on 17-10-2021 Pending
Insulation scrap removal required from below areas
46 3rd floor near 2A B MMD U/P Pending
47 near 2A bunker hanging B MMD U/P Pending
Cable dmaged / mispositioned
48 Near FBHE # 3 & PA SCAPH (Lighting) B EMD Completed Completed
49 2A RAV near (Lighting) B EMD Completed Completed
Lighting damaged at below points
50 3rd floor -2 bulbs B EMD Completed Completed
51 4th floor -2 bulbs B EMD Completed Completed
Safety point of view requirement of
52 Hot SA O/L duct manhole door railing for stair case B MMD U/P Pending
Category of Under
PSSR Completed progress Total
/Pending
A 4 3 7
B 28 17 45