Ms for Testing & Commissioning of Low Voltage Equipment
Ms for Testing & Commissioning of Low Voltage Equipment
Objective
The purpose of these specifications is to assure that all installed Low voltage switchgear and
equipment system supplied by SEE (SCHNEIDER ELECTRIC EGYPT & NEA) are operational
and within applicable standards and design specifications.
This document lists all site tests available for assessing the suitability for service and reliability
of the Low voltage equipment system.
This procedure details must be conducted during installation, commissioning and startup.
Schneider-Electric safety regulations should be followed.
These inspections and tests procedures are listed all site tests which are necessary to be done
on Low voltage, during and after installation or repair or prior to energizing, in order to confirm
that:
Contents
1. Scope .................................................................................................................................................................3
3. References........................................................................................................................................................3
4.5 DC system.................................................................................................................................................. 13
1. Scope
Schneider Low voltage switchgear or equipment for rated voltage up to 1000 V that is supplied
and installed by Schneider Electric Egypt
1- Complete the safety documents “Risk Assessment, LOTO checklist & written work permit”
to identify site hazards and control measures before starting work.
2- Ensure safe manual handling of Low voltage components and use “mechanical gloves”
while handling sharp edges.
3- Ensure that you are working in safe site condition with good ventilation and sufficient
lighting.
4- Avoid working while other contractors are working above your working area to avoid fall
of object that may cause injury to Schneider’s employee or damage to equipment.
5- During insulation resistance test, Dielectric test and phase sequence test: Never touch
the test piece body till ensuring the disconnection of power of electrical testing equipment
(e.g.: Megger) using appropriate PPE.
6- Ensure that you are using the electrical testing equipment in a safe position.
7- Use appropriate Personal Protective Equipment (PPE) such as: Helmet, electrical
insulated gloves, mechanical gloves, safety shoes, safety glasses, ear plug, dust mask,
full body harness, arc rated face shield, arc rated coverall, …. etc.) and any other PPE
required according to site condition.
8- Use arc flash PPE in energizing the switchgear by qualified persons only and keep others
away from working area.
9- Ensure that the site condition is safe and if it is not safe, don’t do it.
3. References
4.1.3 Commissioning:
1. Check the availability of the required auxiliary supply for control operation.
2. Check the phase sequence of the incoming cables using phase sequence device on the
secondary connection of the potential transformer.
3. Perform a control wiring performance test by applying control voltage and Verify that the
equipment operates as intended.
4. Test protective relays in accordance with “Section 3.10—Protective Relays” if found.
5. Perform function operation test to prove correct interaction of all sensing, processing and
protecting devices also proves that the control/auxiliary supply is connected properly and alarms
and indications are appearing correctly.
6. Perform functional interlock test to prove the proper operation and indications of interlock
scheme (electrical / mechanical)
7. Test the anti-condensation heaters by connecting the power supply and measure the consumed
current using clamp meter and check the settings of the thermostat.
8. Check ventilation fans operation.
9. Perform insulation-resistance tests (Megger Test) on each bus section, phase-to-phase and
phase-to-ground, at the DC test voltage appropriate for the equipment’s Maximum Rated
Voltage in accordance with Table 2. Record the resistances. If the resistance is lower than the
recommended values in Table 2, visually inspect the equipment for cleanliness and other
potential causes. If the visual inspection does not reveal the causes, clean the equipment well,
then re- measure. If cleaning does not reveal the causes, dry the equipment for a minimum of 4
hours using heat and fans. Then re-measure.
10. A power-frequency withstand test voltage value according to table 3 shall be performed on all
circuits for a duration of 1s in accordance to the following:
a- Between each pole of the main circuit and, the other poles and the earthed enclosure
connected together.
b- Between all the poles of the main circuit connected together and the earthed enclosure.
*When performing dielectric tests, all Instrument and Control Transformers, Arresters, TVSS
units, and other sensitive electronic equipment that may cause erroneous results or cause
damage to equipment shall be isolated before the test and put back in place after completing
the test.
*Megger test to be done before and after the Dielectric test.
* An alternative for assemblies with incoming protection rated up to 250A the verification of
insulation resistance will be measured and enough using insulation measuring device at voltage
at least 500 V d.c
*Dielectric Test not to be made at auxiliary circuits which are protected by a short circuit
protective device with a rating not exceeding 16 A.
4.2.2.2 Commissioning:
1. Verify trip and close functions.
2. Trip the circuit breaker by operating protective device (if found).
3. Make adjustments for the final settings in accordance with the customer requirements.
4. Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground,
at the DC test voltage appropriate for the equipment’s Maximum Rated Voltage in accordance
with Table 2. Record the resistances. If the resistance is lower than the recommended values in
Table 2, visually inspect the equipment for cleanliness and other potential causes. If the visual
inspection does not reveal the causes, dry the equipment for a minimum of 4 hours using heat
and fans. Then re-measure (that is done as part of switchgear Megger test).
Note: Megger test will be performed along with the switchgear (As a part of the switchgear at
the same time unless the C.B is supplied separately or as spare)
4.2.3.2 Commissioning:
1. Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground,
at the DC test voltage appropriate for the equipment’s Maximum Rated Voltage in accordance
with Table 2. Record the resistances. If the resistance is lower than the recommended values in
Table 2, visually inspect the equipment for cleanliness and other potential causes. If the visual
inspection does not reveal the causes, dry the equipment for a minimum of 4 hours using heat
and fans. Then re-measure.
2. Verify trip, close, trip-free, and anti-pump functions.
3. Trip the circuit breaker by operating protective device.
16. Verify that customer connections to remote power, operators, interlocks, and indicators have
been made.
4.3.3 Commissioning:
1. Check the availability of the required auxiliary supply for control operation.
2. Test the anti-condensation heaters by connecting the power supply and measure the consumed
current using clamp meter and check the settings of the thermostat.
3. Check ventilation fans operation.
4. Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground,
at the DC test voltage appropriate for the equipment’s Maximum Rated Voltage in accordance
with Table 2. Record the resistances. If the resistance is lower than the recommended values in
Table 2, visually inspect the equipment for cleanliness and other potential causes. If the visual
inspection does not reveal the causes, dry the equipment for a minimum of 4 hours using heat
and fans. Then re-measure
5. Apply the settings of the regulator as per the drawings (steps), measure and record the steps
value (µf) for each phase and record the regulator data as well.
6. Perform function operation test for C.B/Contactors, Remote operation, protection, alarms and
tripping indications.
7. Check the phase sequence of the incoming cables using phase sequence device on the
secondary connection of the potential transformer.
4.4.2 Commissioning:
1. Check the availability of the required auxiliary supply for control operation.
2. Check the phase sequence of the incoming cables using phase sequence device on the
secondary connection of the potential transformer.
3. Perform a control wiring performance test by applying control voltage and Verify that the
equipment operates as intended.
4. Test protective relays in accordance with “Section 3.10—Protective Relays” if found.
5. Perform function operation test to prove correct interaction of all sensing, processing and
protecting devices also proves that the control/auxiliary supply is connected properly and alarms
and indications are appearing correctly.
6. Perform functional interlock test to prove the proper operation and indications of interlock
scheme (electrical / mechanical)
7. Test the anti-condensation heaters by connecting the power supply and measure the consumed
current using clamp meter and check the settings of the thermostat.
8. Check ventilation fans operation.
9. Perform insulation-resistance tests (Megger Test) on each bus section, phase-to-phase and
phase-to-ground, at the DC test voltage appropriate for the equipment’s Maximum Rated
Voltage in accordance with Table 2. Record the resistances. If the resistance is lower than the
recommended values in Table 2, visually inspect the equipment for cleanliness and other
potential causes. If the visual inspection does not reveal the causes, clean the equipment well,
then re- measure. If cleaning does not reveal the causes, dry the equipment for a minimum of 4
hours using heat and fans. Then re-measure.
4.5 DC system
4.5.1 Pre-Commissioning visual & mechanical inspection:
1. Inspect the physical and mechanical condition of the equipment.
2. Verify the tightness of accessible bolted electrical connections using the calibrated torque-
wrench method in accordance Table 1
3. Verify correct charger/ battery rack grounding.
4. Verify the operation of the charger’s cooling fans
4.5.2 Commissioning:
1. Verify that all charger functions and alarms are operating properly:
• Switching between automatic and manual modes
• Switching between floating and charge modes – Manual
• Switching between floating and charge modes - Automatic
• Manual operation (boost charge).
• Verify the operation of alarms.
4.6.2 Commissioning:
1. Check the availability of the required auxiliary supply for control operation.
2. Test the anti-condensation heaters by connecting the power supply and measure the consumed
current using clamp meter and check the settings of the thermostat.
3. Check that ventilation Fans are working properly.
4. Perform insulation-resistance tests (Megger Test) at the DC test voltage appropriate for control
wiring in accordance with Table 2.
4.7.2 Commissioning:
1. Check the availability of the required auxiliary supply for control operation.
2. Test the anti-condensation heaters by connecting the power supply and measure the consumed
current using clamp meter and check the settings of the thermostat.
3. Check that ventilation Fans are working properly.
4. Perform function operation test to prove correct interaction of all sensing, processing and
protecting devices also proves that the control/auxiliary supply is connected properly and alarms
and indications are appearing correctly.
5. Apply the required settings/ratings for the AHF.
4.8.2 Commissioning:
1. Check the availability of the required auxiliary supply for heater.
2. Test the anti-condensation heater by connecting the power supply and measure the consumed
current using clamp meter and check the settings of the thermostat.
3. Perform insulation-resistance tests at the DC test voltage appropriate for the equipment’s
Maximum Rated Voltage in accordance with Table 2. Record the resistances. If the resistance is
lower than the recommended values in Table 2, visually inspect the equipment for cleanliness
and other potential causes. If the visual inspection does not reveal the causes, dry the
equipment for a minimum of 4 hours using heat and fans. Then re-measure.
4.9.2 Commissioning:
1. Make sure that incoming cables are connected correctly.
2. Make sure that covers are installed again after all cable works has been finished.
3. Make sure that setting for the MCCB has been applied if applicable.
Bolt Hex.nut + contact Flanged nut Nylstop lock nut + Hex.nut + Flat
Size or picot washer with teeth contact or picot or split washer
used with washers
steel
ﻣﻘﺎﺱ + ﺻﺎﻣﻭﻟﺔ ﻣﺳﺩﺳﺔ ﻋﺎﺩﻳﺔ ﺻﺎﻣﻭﻟﺔ ﺑﻭﺭﺩﺓ ﻭﺭﺩﺓ+ ﺻﺎﻣﻭﻟﺔ ﻛﻭﻧﺗﺭ ﺻﺎﻣﻭﻟﺔ ﻣﺳﺩﺳﺔ
ﺍﻟﻣﺳﻣﺎﺭ ﻭﺭﺩﺓ ﻛﻭﻧﺗﺎﻛﺕ ﺍﻭ ﺷﻭﻛﺔ ﻣﺭﻭﺣﻳﺔ ﺗﺭﺑﻁ ﻛﻭﻧﺗﺎﻛﺕ ﺍﻭ ﺷﻭﻛﺔ ﻭﺭﺩﺓ ﻣﺳﺢ+ ﻋﺎﺩﻳﺔ
ﻋﻠﻰ ﺍﻟﺻﻠﺏ ﺍﻭ ﺷﻖ
M5 7 8 7.5 5
M8 28 25 31 19
M 10 50 50 54 37.5
M 12 75 79 83 62
Recommended Minimum
Minimum DC Test
Voltage Rating Insulation Resistance In Duration
Voltage
Megaohms
Actual test results are dependent on the length of the conductor being tested, the temperature
of the insulating material, and the humidity of the surrounding environment at the time of the
test. In addition, insulation resistance tests are performed to establish a trending pattern and a
deviation from the baseline information obtained during maintenance testing enabling the
evaluation of the insulation for confined use.
Table 3: Power frequency withstand voltage for main circuits of the L.V
Page 1 of 21
Project Description
:
Client
:
Project Name
:
Order Number
:
Item Number
:
Equipment
:
Quantity
Page 2 of 21
Table of Content:
Introduction: Page 4
Page 3 of 21
1. INTRODUCTION
Working Location FAT (Factory Acceptance Test) shall be conducted by Badr testing team
and witnessed by Customer / End User representative(s). The test
procedure is applicable for routine testing of equipment at Schneider
Electric Badr Plant.
Safety & Risks To Control Risks During FAT, the following arrangement shall be done:
Quality Assurance Routine tests are systematically carried out on our material, according to
our quality system which is qualified by certified body, ISO9001. Each
project is rigorously inspected according to the instructions and procedures
of the quality system. We propose to realize in your presence a part or all
inspections described in this document.
Routine tests occur at various stage and times during assembly (not
practical to be witnessed by a third party) and FAT is considered as
replication of part from routine tests Excluding the supplier tested
component as it supplied tested with a testing certificate or tests that
required special tools / need longer time for preparation that affects the
efficiency of FAT.
Test Condition Panels are presented as they are arranged in the switchboard as per
approved drawing as much as possible, they are not physically assembled
and not bolted together.
Page 4 of 21
2. FAT Plan and Scope of FAT:
FAT Plan
Scope of % of Test
INSPECTION AND TEST REQUIRED
FAT Cells
A. GENERAL VISUAL INSPECTION*
1. Presentation and labels Yes Sample
2. Rated Voltage Yes Sample
3. Busbar Rating & Conformity. Yes Sample
4. Short Circuit Level (KA). Yes Sample
5. Degree of Protection (IP). Yes Sample
B. ELECTRICAL TEST*
1. Functional Test. Yes Sample
2. Protection Relay & Metering Test. Yes Sample
3. CT / VT Polarity & Turns Ratio Test. Yes Sample
4. Dielectric Test on the Main Circuit. Yes Sample
C. MECHANICAL TEST*
1. Mechanical Functional Test. Yes Sample
2. Mechanical Interlocking. Yes Sample
D. DOCUMENTATION
1. Internal Test Report. Yes Review
2. Supplier Certificates. Yes Review
3. Testing Tools Calibration Certificate. Yes Review
4. FAT Test Report Yes Review
E. OPTIONAL ON‐DEMAND TESTS
1. Insulation Resistance Test on the Control Circuit. No Sample
2. Dielectric Test on the Control Circuit. No Sample
3. Insulation Resistance Test on the Main Ckt. No Sample
Page 5 of 21
3. Notes on Scope of FAT:
3.1 Optional On demand tests are considered out of FAT scope and extra cost to be charged if
customer require any of it and subjected to change deliver date.
3.2 Any special test that been required from customer and it isn’t mention on that document should be
submitted before FAT date by minimum one Week to study it is applicability to be performed
during FAT. Extra cost to be charged and subjected to change deliver date.
3.4 All Documentations to be submitted During FAT or After One WEEK by Maximum.
Page 6 of 21
4. FAT Test Procedures:
Page 7 of 21
4.1.5 Degree of Protection (IP).
Page 8 of 21
4.2 Electrical Tests
Check the operation of the auxiliaries Approved drawing Power supply Conformity
Check the operation of circuit breaker Approved drawing Power supply Conformity
As per sequence of
Check the automatism operation according to the
Approved drawing Power supply operation and timers
sequence of operation
delay
4.2.1.2 Signaling.
Check the signal of any sensors. Approved drawing Power supply Conformity
4.2.1.3 Heater.
Page 9 of 21
4.2.2 Protection & Metering Test.
4.2.2.1 Protection.
Operation within
Protection Relay Secondary Injection
Check the operation of the protection function product accuracy
Manual Power Supply
Conformity
Approved drawing
Check the functionality of the output signals Buzzer Conformity
Operation within
Manual Test Kit
Automatic Trip Test for Master pact CB product accuracy
Approved drawing Power Supply
Conformity
4.2.2.3 Metering.
Check the name plate of the current transformer Approved drawing Visual Conformity
Page 10 of 21
4.2.3.2 CT Polarity Test.
Check the name plate of the Voltage transformer Approved drawing Visual Conformity
Apply a fraction voltage on the primary winding and Turns ratio within the
measure the value on the secondary winding and IEC61869‐3 Power supply VT accuracy +
compare with the turns ratio Conformity
Page 11 of 21
4.3 Mechanical Tests
4.3.1 Mechanical Operation.
Check the control plugs connection if applicable. Approved drawing Visual Conformity
Check the front doors opening and closing. Visual Visual Conformity
Page 12 of 21
4.4 Optional on Demand Tests
Conformity (Accepted
if the insulation
Apply 500 VDC between all phases& earth.
IEC61439‐2 Megger Tester resistance is equal to
or more than 1000
ohm/volt
Page 13 of 21
1. FAT Documents:
5.1 Customer Inspection Checklist
Page 14 of 21
5.2 Heater Test Sheet
Page 15 of 21
5.3 Protection Relay Test Sheet
Page 16 of 21
5.4 Power Meter Test Sheet
Page 17 of 21
5.5 CT Test Sheet
Page 18 of 21
5.6 PT Test Sheet
Page 19 of 21
5.7 Di Elec Test Sheet
Page 20 of 21
5.8 Micrologic Test Sheet
Page 21 of 21