EEC Microproject Sayali
EEC Microproject Sayali
TECHNICAL EDUCATION
MICRO PROJECT
Guidelines For UseOf
Under Ground Cable System And
Overhead Conductor System A Long
With Cost Benefit Analysis
1
MAHARASHTRA STATE
BOARD OF TECHNICAL EDUCATION
Certificate
This is to certify that Miss. Sayali Santosh Kapade Roll No 22 of Sixth
Semester of Diploma in Electrical Engineering of Institute, TSSM’s
BSCOER POLYTECHNIC (Institute Code: 1606) has completed the Micro
Project satisfactorily in Subject –Electrical Estimation And Contracting
(22627) for the Academic Year 2023-2024 as prescribed in the curriculum.
2
GROUP DETAILS
Enrollment
Sr. No. Name of group members Roll No. Seat No.
No.
3
INDEX
1 Abstract 5
2 Introduction 6
9. Sample Sketch 16
11. Glossary 18
13. Conclusion 20
14. Annexure II 21
4
Introduction
Distribution of electricity involves the transfer of electrical energy from one electric substation
to another electrical substation ( like from 220/33 KV S/S to 33/11 KV S/S and 33/11 KV S/S
to 11/0.4 KV Distribution Transformer S/S etc) through sub- transmission and distribution lines.
These lines may be Overhead lines or Undergroundcables. Each of the two types has its
benefits as well as demerits.The choice of Overhead Network or Underground network
depends on many factors like safety requirement, Right of way, cost ,aesthetic look and other
factors. Despite being expensive, Underground cables have several advantages over OH lines.
These are mostly used where safe clearances for Overhead Network is not available as well as in
densely populated areas where Overhead Network cannot be used., whereas, Overhead Network
is cheaper, easy to install/upgrade and easy to attend the fault etc.
5
Overhead Network
In overhead power lines, a structure based network is used to transmit electrical energyfrom one
point to another. It consists of adequate size of conductors , commonly three conductor in 66
KV , 33 KV or 11 KV lines or four conductor in 11 KV lines or 5 conductor in LT lines ( 5th
conductor for street lighting) for three phase lines and two conductors for single phase lines etc
suspended by towers or poles and generally comprising of the items- such as Poles, Conductors,
Cross arms, pin insulators, Stay Wires, Stay Rod, Stay Anchor, Guy Insulator, earthing
materials, Guard wire, Barbed wire and Danger plate etc
The Poles for the electrical network may be a Steel Poles (Tubular Poles, Rolled Steel Joists and
Rails),Concrete Poles (RCC Poles, PCC poles and Pre-Stressed Concrete - PSC) Pole) of various
heights of 9 meters to 13 meters (IS: 5613 (Part 1, 2, 3) depending on site location, minimum
safety clearance and Voltage (230Volts, 415Volts, 11KV and 33KV etc.) of the overhead
network system. Along with these poles, Rail poles, which have more strength then other poles,
are generally used in overhead network along and across the Road, Public Places, Residential
areas, River crossing etc.
Sometimes, for supporting different voltages on the same poles and to maintain the adequate
clearance between the different lines of different voltage levels, poles with higher heights are
used, and in such cases, guard wires are also provided to prevent accidental over charging of
lines of lower voltage system due to conductor snapping etc.
The conductors for the overhead network can be a bare conductor or an insulated conductor
( ABC) depending on the requirement. It is an important component of overhead electrical
transmission and distribution systems. The choice of conductor depends on the power carrying
capacity, cost, growth of the load, and reliability & efficiency. While selecting an ideal
conductor, some of the following features such as -i)maximum electrical & thermal capacity and
cost effectiveness etc are considered.
6
As per CEA(Technical Standards for construction of Electrical Plants and Electric Lines)
regulations 2010, as amended upto date, adequate capacity AAC (All Aluminium
Conductor), AAAC (All Aluminum Alloy Conductor), ACSR (Aluminum Conductor Steel
Reinforced), ACAR (Aluminum Conductor, Aluminum Reinforce) or any new technology
higher current carrying conductors (AL-59, HLTS etc) may be used in sub –transmission
and Distribution system. Since, the insulations between the conductors is provided by air,
overhead power lines are generally the lowest-cost method of power transmission for large
quantities of electric energy from one point to another.
7
choice for power distribution in congested urban areas with narrow lanes and by-lanes.
ABC provide safety to human life when used in congested area and narrowlane
areas.
ABC provides flexibility to use multiple circuits of different voltages strung onthe
same set of poles without using separate poles.
ABC provides better adaptability to run concurrently with other overhead
system with bare conductor and also with communication lines without any
interference.
ABC provides insulation resistance to earth in all seasons and negligible
leakage of currents and thereby, the low losses of leakage.
ABC is unaffected by pollution in the atmosphere.
ABC, at the same time also reduces the theft of energy as it can not betapped
i.e it prevents the use of illegal hooks etc on LT lines in the theftprone areas
and helps to improve the AT&C losses of the system.
8
Underground Network
In Under Ground cable system, the power is transferred from one point to another through
underground cables laid in the ground in place of overhead lines on poles/ towers. As these cables
are not exposed to the air/ atmosphere, this makes the U/G cabling system less susceptible to outages
due to various atmospheric conditions like high wind, storm, thunder storms, heavy snow or ice
storms etc. As these cables are not visible on ground, these provide an aesthetic look to the area where
these are laid as compare to OH lines. However, the U/G cables have to be laid in the proper tranches
and also have more restoration time in case of any fault as compare to OH lines.
While selecting the rating of cables to be used, some of the parameters such as Current
carrying capacity, Voltage drop and short circuit rating are important factors toselect the
economical and optimum size of cable.
The cable generally comprises of the conductor, insulation material, bedding, beading/
armoring, and outer sheath etc. Although, the armoring and outer sheath takes care of the
9
physical safety of cable , adequate care has to be taken by cable manufactures during
manufacturing of the cable.
Normally the lifespan of a cable is about 40 to 50 years. But over the time, the insulation of
cable may get damaged or weakened due to ageing. Wrong handling of cabals, such as
damages due to wrong handling/laying of cable also weakens the insulation of the cables.
Normally, some of cable faults may be as-
1. a short circuit fault between two conductor due to failure of insulation between thetwo
conductors
2. a earth fault, i.e., fault between conductor and ground due to failure of outerinsulation
sheath
3. an open circuit fault, caused due to disconnection of the conductor etc.
The choice of whether to use overhead line (OHL) or underground cable (UGC) mustbe
made keeping in view the safety, reliability and operational constraints. The choice between
OHL and UGC is driven by technical, environmental and economic considerations.
10
Comparison Of Ug System And Oh System - Feasibility Analysis:-
Feasibility study of Overhead and Underground line on various points is classifiedbelow :
1. Cost Of Installation:-
Underground network installation is more expensive than OH lines , since the cost of cables
include cable charges along with road restoration charges which make the per unit coat of
U/G cabling system several times greater than overhead system.
The identification of fault finding and repairing on overhead wire is easy as compare to UG
cables as UG cables are buried in the ground and it require specialized techniques to find out
the fault location as compare to OH lines. Some time, it may take several days or weeks to
find and repair the fault in underground system.
In underground cables, when a fault occurs, the cost of finding its location, trenching,
cable splicing, and re-embedment is sometimes five to 10 times more expensive than
repairing a fault in an overhead line where the conductors are visible, readily
accessible and easier to repair.
11
5. Line Modifications:-
Overhead power lines are easily tapped, rerouted or modified to serve customers;while
underground lines are more difficult to modify after the cables have been laid. Such
modifications to underground power lines are more expensive becauseof the inability
to readily access lines or relocate sections of lines.
Overhead Lines are more prone to damage from severe weather conditions (mainly
lightning, hurricanes/cyclones/typhoons, tornados, other winds, and freezing) than
Underground Network.
The electric current in the conductor produces a magnetic field around it but the closer
grouping of underground power cables reduces the resultant external magnetic field and
hence provide less magnetic effect as compare to OH line conductors. Further to reduce the
magnetic effect in cables, a shielding is also provided over the cables which further reduces
the magnetic effect in surrounding areas.
8. Space Requirement:-
Underground cables do not need physical ground space as these are laid under the ground in
the dedicated tranches whereas an overhead line requires a corridor on ground along with
surrounding clearance strip permanently clear for safety, maintenance and repair.
12
9. Hazard To Wildlife:-
11.Aesthetics:-
As UG cables are not visible from outside, these provide a clean and aesthetic viewof the
city /town where UG cables are laid. The above space may be used for any other purposes
like making of roads, providing green environment/trees on sidewalks etc having
environmental benefits and increase of property values etc.
Overhead lines can easily be upgraded/ augmented by modifying line clearances and power
poles to carry more power while underground cables cannot be up-rated and must be
supplemented by laying another cables or to be replaced to increase the capacity.
13.Line Life:-
Insulation deterioration takes place in underground cables much faster because of
various loading cycles during their lifetimes as compare to OH conductor whichdo
not have any insulation layering. As time passes, the cables insulation weakens, which
increases the potential for a line fault.
14.Safety:-
As OH conductor are exposed in air, a minimum safety clearance is required for the
overhead line from any surrounding like surrounding building /trees etc which may not
13
be available in densely populated areas, while underground cables do not require such
clearances . Also, the snapping of the overhead conductors in densely populated areas poses
serious safety hazard. Hence, UG cables are preferred in the densely populated areas.
14
Cost Analysis
As discussed above, the estimated cost of the UG cabling system is about 3-4 times than the
equivalent OH system ( like the Est cost of 11 KV OH S/C line with Dog conductor is around Rs
5-6 Lakh/ km while the Est cost of 1 km of 3 x300 sq mm 11 KV cabling system would be
around Rs 20 Lakh/km). The tentative unit costs of 11 KV OH lines and UGcabling system
are given in Annex. These are only the suggestive figures and the actual costs may vary frm
utility to utility based on there technical requirement / schedule rates etc.Following is the cost
comparison for installation of one kilometer of underground and Overhead lines:
The above cost may vary depending upon road restoration cost for installation of the
underground cables/ overhead poles. The cost is much higher for installation of underground
cables depending on the nature of the road surface to be disturbed and area of installation
(Metropolitan/Rural area etc).
15
TYPICAL COST ESTIMATE FOR 1KM 11 KV (SINGLE CIRCUIT) OVERHEAD
HT LINE WITH DOG CONDUCTOR ON STEEL TUBULAR
POLE
S. No Particulars Unit Qty Rate Amount(Rs
)
1 ST Pole 9 Mtr. No. 25 2904 72600
X-arm M.S. Angle 65x65x6mm
2 No. 25 597 14925
V Type
3 Cross arms holding clamps No. 25 57 1425
11 kV Pin insulators with
4 Nos 75 67 5025
GI Pins(320CD)
5 45 kN disc insulators Nos 6 533 3198
F-bracket for fitting top
6 No. 25 228 5700
insulator
7 ACSR Dog conductor Km 3.09 59579 184099
8 Jointing sleeve for ACSR DOG No. 3 171 513
9 Danger Plate Nos 25 155 3875
10 Barbed wire Kg. 8 68 544
11 Stay Set Complete No. 8 1140 9120
Sectional D/P on Steel
12 No. 1 45593 45593
Tubular Pole
13 Concreting of supports ST Pole No. 25 969 24225
14 Stone pad 300x300x75mm No. 25 182 4550
15 Earthing complete No. 6 570 3420
Material Cost in Rs 378812
Misc. Items (Like Nut
&
Bolts,Clamps,Binding
0.50% 1894
16
TYPICAL COST ESTIMATE FOR 1 KM HT OVERHEAD LINE WITH 11KV ABC CABLE WITH SPAN
30 METERS
Sl.No Particulars Unit Qty Rate Amount(Rs
)
1 PCC Poles 11 M No. 35 5465 191275
2 ABC Cable 3CX150+150 mm2 Kms 1.02 760013 775213.26
Clamp Suspension LT ABC 3X120-
3 EA 35 244 8540
150 SQMM
EYE HOOK ANCHOR/ SUSPENSION
4 EA 35 118 4130
CLAMP 300MM
Anchor HT ABC 3CX120 TO
5 EA 10 349 3490
150 SQMM
EYE HOOK ANCHOR/ SUSPENSION
6 EA 10 118 1180
CLAMP 300MM
7 Stay Set Complete No 10 1140 11400
8 Stay Wire GI,7/8 SWG kg 100 65 6500
Full clamp assembly (alongwith
9 No 10 57 570
Nuts,Bolts and Washers) for stay
10 Egg insulators No 10 13 130
11 Barbed wire kg 35 68 2380
Pipe earth G.I. 40MMX2.5/3 M
12 EA 40 706 28240
'B'CLASS
13 PIPE HDPE SIZE 25 MM EA 120 22 2640
14 WIRE STAY GI 7/10 SWG KG 400 65 26000
LUG AL Crimping 70 SQMM
15 EA 160 20 3200
XLPE SINGLE HOLE
16 GI Strip 25x6 mm , 9 meter for earthing No 7 570 3990
Phase plate for each phase set of 3 (on
17 Set 35 57 1995
each H-Pole & 4-Pole)
18 Danger Plate No 35 155 5425
19 Number Plate No 35 70 2450
JT. KIT O/D HT ABC
20 EA 12 1797 21564
3CX150+1CX150 HS ONE
COVER INSULATION
21 EA 9 2251 20259
REOPENABLE ON INSULATOR
22 CHANNEL MS SIZE 75X40MM KG 89 65 5785
23 ANGLE MS SIZE 50X50X6MM KG 41 33 1353
24 FLAT GI SIZE 50X6MM KG 15 123 1845
Total Material Cost(Part-I) 1129554
*Labour Cost for execution of the
Scheme,Overhead charges including
Transportation, Establishment &
Supervision Charges for Erection, Testing 14% 163651
&Commissioning @14% of Total Material
Cost(Part-II)
Total cost in Rs.(Part-I+Part-II) 1332688
Say(Rs. In Lakhs) 13.33
17
Conclusion
18
WEEKLY PROGRESS REPORT
MICRO PROJECT
SIGNATURE
SR.NO. WEEK ACTIVITY PERFORMED DATE
OF GUIDE
19
ANEEXURE II
Evaluation Sheet for the Micro Project
Marks out of 4
Marks out of 6
for performance
Roll for performance Total out
Student Name in oral/
No. in group activity of 10
presentation
(D5 Col. 8)
(D5 Col. 9)
Signature of Faculty
20
21