0% found this document useful (0 votes)
8 views

program of works

The document outlines the proposed building project for Mr. Juan dela Cruz, detailing the program of works and associated costs, totaling PHP 315.00. It includes various construction activities such as mobilization, site preparation, earthworks, and more, with specific quantities, units, and costs listed for each item. The document also includes a detailed estimate section for materials, labor, and equipment for each work item, though many costs are currently marked as undetermined.

Uploaded by

camilleee118
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views

program of works

The document outlines the proposed building project for Mr. Juan dela Cruz, detailing the program of works and associated costs, totaling PHP 315.00. It includes various construction activities such as mobilization, site preparation, earthworks, and more, with specific quantities, units, and costs listed for each item. The document also includes a detailed estimate section for materials, labor, and equipment for each work item, though many costs are currently marked as undetermined.

Uploaded by

camilleee118
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 20

LOGO

Project Title : PROPOSED BUILDING


Location : Number, Street, Barangay, City/Municipality, Province, Country
Owner : Mr. Juan dela Cruz

A. PROGRAM OF WORKS QTY UNIT UNIT COST TOTAL COST


1.0 Mobilizaton & Demobilization 1.00 lot - -
2.0 Temporary Facility Construction 1.00 lot - -
3.0 Site Preparation Works 1.00 sq.m. - -
4.0 Earthworks 1.00 cu.m. - -
5.0 Termite Proofing Works 1.00 sq.m. - -
6.0 Scaffolding & Form Works 1.00 lot - -
7.0 Reinforcement Works 1.00 kgs. - -
8.0 Steel Works 1.00 lot - -
9.0 Concrete Works 1.00 cu.m. - -
10.0 Masonry Works 1.00 sq.m. - -
11.0 Waterproofing Works 1.00 sq.m. - -
12.0 Roofing Works 1.00 lot - -
13.0 Door Installation 1.00 lot - -
14.0 Window Installation 1.00 lot - -
15.0 Carpentry Works 1.00 lot - -
16.0 Plumbing Works 1.00 lot - -
17.0 Utility Works (Electrical, Electronic & Mechanical) 1.00 lot - -
18.0 Tile Works & Hardscapes 1.00 sq.m. - -
19.0 Ceiling Works 1.00 sq.m. - -
20.0 Painting Works 1.00 sq.m. 315.00 315.00
21.0 Accessories & Specialty Works 1.00 lot - -
22.0 Site Clearing Works 1.00 lot - -

B. TOTAL PROJECT COST PHP 315.00

Prepared by: Approved by:

MS. MARIA CLARA DELOS SANTOS MR. JUAN DELA CRUZ


Estimator Owner
C. DETAILED ESTIMATE

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

1.0 Mobilizaton & Demobilization 1.00 lot - PHP -

A. MATERIALS
1 None - lot - -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Elf Truck 0 0 Eqpt. Days 3,600.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

2.0 Temporary Facility Construction 1.00 lot - PHP -

A. MATERIALS
Includes Temporary Fence & Bunkhouse
1 Coco Lumber, 2"x4"x12' - pcs. 180.00 -
2 Coco Lumber, 2"x3"x12' - pcs. 160.00 -
3 Coco Lumber, 2"x2"x12' - pcs. 140.00 -
4 Corrugated G.I. Roofing Sheets, Gauge26 x 10' - l.mts. 420.00 -
4 Steel Matting, 4'x8'X3/16" - sheets 580.00 -
5 1/4" Ordinary Plywood - sheets 420.00 -
6 4"x4" Loosepin Hinges - pairs 180.00 -
7 Laminated Sacks - mts. 140.00 -
8 #16 G.I. Tie Wire - kgs. 75.00 -
9 1 1/2" CW Nails - kgs. 70.00 -
10 4" CW Nails - kgs. 65.00 -
11 6" CW Nails - kgs. 65.00 -
12 3" Tekscrew - pcs. 3.00 -
14 Tekscrew Adaptor - pcs. 125.00 -
16 4" x 3/32" x 5/8" Cutting Disk - pcs. 110.00 -
12 3" Umbrella Nails - kgs. 100.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Electric Drill 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

3.0 Site Preparation Works 1.00 sq.m. - PHP -


Includes Lot Staking & Site Preparation
A. MATERIALS
1 Coco Lumber, 2"x3"x12' - pcs. 160.00 -
2 Coco Lumber, 2"x2"x12' - pcs. 140.00 -
3 Nylon String Construction Line, 3mm - pcs. 55.00 -
4 #16 G.I. Tie Wire - kgs. 75.00 -
5 3" CW Nails - kgs. 65.00 -
6 4" CW Nails - kgs. 65.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 None 0 0 Eqpt. Days - -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

4.0 Earthworks 1.00 cu.m. - PHP -

A. MATERIALS
Includes Excavation & Backfilling
1 Earth Filling Material (Backfilling) - cu.m. 1,600.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Excavator 0 0 Eqpt. Days 9,000.00 -
2 Dumptruck 0 0 Eqpt. Days 4,800.00 -
3 Submersible Pump 0 0 Eqpt. Days 850.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

5.0 Termite Proofing Works 1.00 sq.m. - PHP -

A. MATERIALS
Includes Soil & Wood Treatment
1 Anti-Termite Soil Solution - gals 1,600.00 -
2 Anti-Termite Wood Solution - gals 1,400.00 -
3 1/2"dia PVC Pipe Series 900 - lgths 160.00 -
4 1/2"dia PVC Elbow - pcs 35.00 -
5 1/2"dia PVC Tee - pcs 35.00 -
6 1/2"dia PVC Cap - pcs 35.00 -
7 PVC Solvent Cement 400cc - cans 380.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 None 0 0 Eqpt. Days - -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

6.0 Scaffolding & Form Works 1.00 lot - PHP -

A. MATERIALS
Includes Props, Supports & Braces
1 2"Ø x 6.00M, G.I. Steel Pipe, Schedule 40 0.00 lgths. 1,005.00 -
2 2"Ø G.I. Connecting Clamp 0.00 pcs. 100.00 -
3 2"Ø G.I. Fixed Clamp 0.00 pcs. 100.00 -
4 2"Ø G.I. Swivel Clamp 0.00 pcs. 100.00 -
5 Ratchet Wrench 0.00 pcs. 650.00 -
6 Coco Lumber, 2"x4"x12' 0.00 pcs. 180.00 -
7 Coco Lumber, 2"x3"x12' 0.00 pcs. 160.00 -
8 Coco Lumber, 2"x2"x12' 0.00 pcs. 140.00 -
9 Phenolic Plywood, 3/4"thk. x 4' x 8' 0.00 sheets 1,510.00 -
10 1" CW Nails 0.00 box 1,050.00 -
11 1 1/2" CW Nails 0.00 box 1,050.00 -
12 2" CW Nails 0.00 box 1,050.00 -
13 3" CW Nails 0.00 box 1,000.00 -
14 4" CW Nails 0.00 box 1,000.00 -
15 6" CW Nails 0.00 box 1,000.00 -
16 #16 G.I Tie Wire 0.00 rolls 1,200.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 None 0 0 Eqpt. Days - -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

7.0 Reinforcement Works 1.00 kgs. - PHP -

A. MATERIALS
Includes Steel Reinforcements
Steel Reinforcements
1 Deformed Steel Bars, 16mm dia. x 6m - lgths 370.00 -
2 Deformed Steel bars, 12mm dia. x 6m - lgths 290.00 -
3 Deformed Steel bars, 10mm dia. x 6m - lgths 210.00 -
4 Steel Deck 965mm x 0.80mm thk - l.mts. 630.00 -
Others
5 Welding Rod 6011 x 1/8 - kgs 180.00 -
6 #16 G.I Tie Wire - rolls 1,200.00 -
7 Hacksaw Blade - pcs. 60.00 -
8 Cutting Disc, 4" dia. - pcs. 90.00 -
9 Chalk Stone - pcs. 10.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Steel Man 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Welding Machine 0 0 Eqpt. Days 400.00 -
2 Angle Grinder 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (H=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

8.0 Steel Works 1.00 lot - PHP -

A. MATERIALS
Includes Commercial Stall Module
1 2"x4"x3/16" HSS Tube (Column) - kgs 150.00 -
2 2"x6"x1/8" HSS Tube (Girder) - kgs 150.00 -
3 2"x3"x1/8" HSS Tube (Joist) - kgs 150.00 -
4 2"x4"x1/8" HSS Tube (Top Girder) - kgs 150.00 -
5 Steel Deck, 965mm x 0.80mm thk - l.mts. 630.00 -
6 6mm thk Checkered Plate - kgs 150.00 -
7 Steel Matting, 4'x8'X3/16" - sheets 950.00 -
Roof Framing
8 Steel Angle Bar, 2"x2"x1/8" thick - lgths 600.00 -
9 Steel C-Purlins, 2"x4"x0.4mm - lgths 700.00 -
10 Steel Channel Bar, 2"x6"x8mm - lgths 6,000.00 -
11 Steel Angle Bar , 2"x2"x 1/4" thick - lgths 900.00 -
12 Steel Wide Flange, (I-Beam), 8"x8"x17mm-Thick - lgths 40,600.00 -
12 Steel Wide Flange, (I-Beam), 8"x6"x10mm Thick - lgths 20,400.00 -
12 10mm Plain Round Bar-sagrods - lgths 190.00 -
Steel Railings
12 Steel Angle Bar, 1 1/2"x1 1/2"x1/8"x6m - lgths 670.00 -
12 Steel Matting, 4'x8'X3/16" - sheets 950.00 -
12 Steel Rectangular Tube, 2"x4"x3/16"x6m - lgths 910.00 -
12 Deformed Steel bars, 12mm dia. x 6m - lgths 290.00 -
Others
13 Welding Rod 6011 x 1/8 - box 3,500.00 -
14 Turnbuckle, 10mm - pcs 500.00 -
15 Bolts with Washers, 1/2" dia. - pcs 70.00 -
16 Anchor Bolts, 25mmx650mm - pcs 600.00 -
17 Base Plate, 16mm thk. - kgs 100.00 -
18 #16 G.I Tie Wire - kgs 95.00 -
19 Cutting Disc, 4" dia. - pcs. 90.00 -
20 Metal Drill Bit, 5/16" dia. - gals. 85.00 -
21 Metal Primer, Red Oxide - gals. 420.00 -
22 #4 Paint Roller w/ tray - pcs 95.00 -
23 #2 Paint Brush - pcs 75.00 -
24 Chalk Stone - pcs. 10.00 -
Sub-Total A = PHP -
B. LABOR QTY DAYS UNIT RATE/DAY
1 Foreman 0 0 Men 1,000.00 -
2 Welder/Steel Man 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Welding Machine 0 0 Eqpt. Days 400.00 -
2 Electric Drill 0 0 Eqpt. Days 250.00 -
3 Angle Grinder 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -
D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

9.0 Concrete Works 1.00 cu.m. - PHP -

A. MATERIALS
1 Portland Cement - bags 280.00 -
2 Washed Sand - cu.m. 1,050.00 -
3 3/4" Crushed Gravel - cu.m. 1,050.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Mason 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 1 Bagger Mixer 0 0 Eqpt. Days 1,000.00 -
2 Concrete Vibrator 0 0 Eqpt. Days 650.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (H=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

10.0 Masonry Works 1.00 sq.m. - PHP -

A. MATERIALS
Includes Interior Wall & Septic Vault
1 CHB 6"x8"x16" - pcs 16.00 -
2 CHB 4"x8"x16" - pcs 14.00 -
3 Portland Cement - bags 280.00 -
4 Washed Sand - cu.m. 1,050.00 -
5 3/4" Crushed Gravel - cu.m. 1,050.00 -
6 Deformed Bars 10mm dia. - lgths. 210.00 -
7 Cutting Disc, 4" dia. - pcs 100.00 -
8 #16 G.I Tie Wire - roll 1,400.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Mason 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 1 Bagger Mixer 0 0 Eqpt. Days 1,000.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

11.0 Waterproofing Works 1.00 sq.m. - PHP -

A. MATERIALS
1 Cementitious Waterproofing (Plexibond) - gals. 1,100.00 -
2 Cement Waterproofing Compound (Sahara) - bags 110.00 -
3 Portland Cement - bags 280.00 -
4 #7 Paint Roller w/ tray - pcs 110.00 -
5 #4 Paint Brush - pcs 90.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 None Eqpt. Days - -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

12.0 Roofing Works 1.00 lot - PHP -

A. MATERIALS
Roofing sheets & accessories
1 Rib Type Roofing Sheets, 0.40mmx0.90m (Long Span) - l.mts. 560.00 -
2 Transluscent Roofing Sheets, 0.87mx4.88mx0.8mm thk. - sheets 1,250.00 -

3 End Flashing, Bended Plain Sheet, 0.40mmx1.20mx2.40m - pcs. 550.00 -

4 End Moulding, Bended Plain Sheet, 0.40mmx0.40mx2.40m - pcs. 420.00 -

5 Ridge Roll, Bended Plain Sheet, 0.40mmx0.40mx2.40m - pcs. 530.00 -


6 Box Gutter, Bended Plain Sheet, 0.40mmx1.20mx2.40m - pcs. 550.00 -

Polycarbonate Sheet, Twin-wall, Gray, 10mmx1.20mx2.40m - sheets 3,100.00 -

7 Double Sided PE Foam Insulation, 4mmx1.20mx50m - rolls 3,000.00 -


8 GI Tie Wire #16 - kgs. 90.00 -
Others
9 Elastomeric Roofing Sealant - liters 500.00 -
10 Clear Rubber Silicon Sealant - tubes 275.00 -
11 Touch-up Paint (See Sample) - liters 250.00 -
12 3" Tekscrew - pcs. 3.00 -
13 Blind Revits 1/8" x 1/2" - boxes 180.00 -
14 Tekscrew Adaptor - pcs. 125.00 -
15 13/64" dia. Metal Drill Bit - pcs. 50.00 -
16 4" x 3/32" x 5/8" Cutting Disk - pcs. 75.00 -
17 Tin Snip, Heavy Duty - pcs. 410.00 -
17 Chalk Stone - pcs. 7.00 -
18 2" Concrete Nails - kgs. 110.00 -
Sub-Total A = PHP -
B. LABOR QTY DAYS UNIT RATE/DAY
1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Electric Drill 0 0 Eqpt. Days 250.00 -
2 Angle Grinder 0 0 Eqpt. Days 200.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

13.0 Door Installation 1.00 lot - PHP -

A. MATERIALS
1 D1, 0.80m x 2.10m Wooden Panel Door on 2"x5" Door Jamb - sets 13,000.00 -
2 D2, 2.00m x 2.30m Built-up Mesh-type Double Swing Steel
Gate - sets 15,000.00 -

3 D3, 0.80m x 2.10m PVC Flush Door with Louvers on 2"x5" Door
Jamb - set 7,000.00 -

4 D4, 0.60m x 2.10m PVC Flush Door with Louvers on 2"x5" Door
Jamb - set 7,000.00 -

5 D5, 0.70m x 2.10m Built-up Mesh-type Swing Steel Gate - set 8,000.00 -
5 D6, 0.80m x 2.10m Swing Glass Door on PCW Aluminum
Framing - sets 16,000.00 -

6 D6, 0.90m x 2.10m Powder Coated White Sliding Door


- sets 16,000.00 -

7 D7, 1.90m x 2.10m Powder Coated White Sliding Door on


Frosted Glass Partition - sets 10,000.00 -

8 WP1, 2.00m x 2.40m Built-up Steel Partition with Door &


Lattice - sets 10,000.00 -

9 WP1, 0.70m x 2.10m Built-up Steel Partition with Door &


Lattice - set 7,000.00 -

9 Handleset-type Entrance Lockset (Heavy Duty), Stainless


hairline finish - sets 2,400.00 -

10 Lever-type Entrance Lockset (Heavy Duty), Stainless hairline


finish - sets 1,200.00 -

11 Single Cylinder Heavy Duty Door Deadbolt, Stainless hairline


finish - set 900.00 -

12 Heavy Duty Door Chain bolt, Stainless hairline finish


- sets 500.00 -

13 Heavy Duty Floor-mounted Door Stopper, Stainless hairline


finish - sets 500.00 -

14 2" dia., Pillow Block, Heavy Duty


- pcs. 860.00 -

14 4" Loose Pin Hinges, Heavy Duty - pairs 600.00 -


Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Electric Planer 0 0 Eqpt. Days 500.00 -
2 Electric Drill 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

14.0 Window Installation 1.00 lot - PHP -

A. MATERIALS
1 CW1, 4.00m x 2.40m Sliding Door with Fixed & Awning Window - set 44,160.00 -
Sidelights on PCW Aluminum Frame (See Schedule)
1 CW2, 2.40m x 2.40m Sliding Door with Fixed & Awning Window - set 26,500.00 -
Sidelights on PCW Aluminum Frame (See Schedule)
1 W1, 0.75m x 2.40m Fixed & Awning Window on PCW - sets 8,280.00 -
Aluminum Frame (See Schedule)

2 W2, 2.40m x 2.20m Fixed Window on PCW Aluminum Frame - sets 24,290.00 -
(See Schedule)

3 W3, 0.50m x 0.50m Awning Window on PCW Aluminum Frame - set 1,150.00 -
(See Schedule)

4 W4, 0.95m x 0.50m Awning Window on PCW Aluminum Frame - set 2,190.00 -
(See Schedule)

5 W5, 1.85m x 0.50m Awning Window on PCW Aluminum Frame - set 4,260.00 -
(See Schedule)

6 W6, 2.30m x 2.40m Fixed & Awning Window on PCW - sets 25,400.00 -
Aluminum Frame (See Schedule)

7 W7, 1.60m x 0.50m Sliding Window on PCW Aluminum Frame - sets 3,680.00 -
(See Schedule)

8 W8, 3.95m x 2.40m Fixed & Awning Window on PCW - set 43,610.00 -
Aluminum Frame (See Schedule)

9 WS1, 2.50m x 1.30m Window Grill Shutter on Aluminum Frame - set 13,000.00 -

10 WS2, 3.50m x 1.30m Window Grill Shutter on Aluminum Frame - set 18,200.00 -

11 W11, 0.70m x 8.00m Awning with Fixed-type Window, on - set - -


Analok Aluminum Frame (See Schedule)
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker/Installer 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Electric Drill 0 0 Eqpt. Days 250.00 -
2 Angle Grinder 0 0 Eqpt. Days 200.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

15.0 Carpentry Works 1.00 lot - PHP -


Includes Storage shelves & cabinets
A. MATERIALS
1 3/4" Marine Plywood - sheets 1,380.00 -
2 Palochina Lumber, 2"x6"x8' - pcs. 180.00 -
2 Steel Angle Bar, 1 1/2"x1 1/2"x1/4"x6m - lgths 430.00 -
3 Welding Rod 6011 x 1/8 - box 2,600.00 -
4 Cutting Disc, 4" dia. - pcs. 90.00 -
5 Wood Screw, 1 1/2" - pcs. 3.00 -
5 Metal Drill Bit, 5/16" dia. - pcs. 85.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Skilled Worker 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Electric Planer 0 0 Eqpt. Days 500.00 -
2 Angle Grinder 0 0 Eqpt. Days 200.00 -
3 Electric Drill 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

16.0 Plumbing Works 1.00 lot - PHP -

A. MATERIALS
1 Water Closet - unit 7,000.00 -
2 Bath Tub - unit 11,000.00 -
3 Lavatory - unit 5,000.00 -
4 Lavatory Faucet - sets 1,800.00 -
5 Urinal - set 2,200.00 -
6 Multi-point Water Heater - set 9,500.00 -
7 Stainless Sink - sets 3,500.00 -
8 Sink Faucet - sets 1,500.00 -
9 Toilet Bidet - sets 400.00 -
10 Soap Holder - sets 500.00 -
11 Toilet Paper Holder - sets 500.00 -
12 Toilet Racks/Shelving - set 2,000.00 -
13 Toilet Tray - sets 1,200.00 -
14 Towel Holder - sets 1,300.00 -
15 Hose Bibb Faucet, PVC - pcs 220.00 -
16 PVC Floor Drain 4" x 4" - pcs 250.00 -
Sewer
17 6"dia PVC Pipe S900 - lgths 950.00 -
18 6" x 6" PVC Wye S900 - pcs 200.00 -
19 6" x 6" PVC Elbow 45⁰ S900 - pcs 150.00 -
20 6"dia. PVC Clean Out S900 - pcs 200.00 -
21 4"dia PVC Pipe S900 - lgths 710.00 -
22 4" x 4" PVC Wye S900 - pcs 150.00 -
23 4" x 2" PVC Wye S900 - pcs 180.00 -
24 4" x 4" PVC Elbow 90⁰ S900 - pcs 70.00 -
25 4" x 4" PVC Elbow 45⁰ S900 - pcs 70.00 -
26 4"dia. PVC Clean Out S900 - pcs 150.00 -
Drainage
27 3"dia PVC Pipe S900 - lgths 475.00 -
28 3" x 3" PVC Tee S900 - pcs 85.00 -
29 3" x 3" PVC Wye S900 - pcs 85.00 -
30 3" x 3" PVC Elbow 90⁰ S900 - pcs 70.00 -
31 3" x 3" PVC Elbow 45⁰ S900 - pcs 70.00 -
32 3" x 3" PVC Clean Out S900 - pcs 100.00 -
33 2"dia PVC Pipe S900 - lgths 255.00 -
34 2" x 2" PVC Tee S900 - pcs 65.00 -
35 2" x 2" PVC Wye S900 - pcs 65.00 -
36 2" x 2" PVC Elbow 90⁰ S900 - pcs 50.00 -
37 2" x 2" PVC Elbow 45⁰ S900 - pcs 50.00 -
38 2" x 2" PVC Clean Out S900 - pcs 80.00 -
Water Supply
39 3/4"dia PPR Pipe - lgths 350.00 -
40 3/4"dia PPR Plain Elbow - pcs 40.00 -
41 3/4"dia PPR Plain Tee Reducer - pcs 55.00 -
42 3/4"dia PPR Gate Valve - pcs 200.00 -
43 1/2"dia PPR Pipe - lgths 250.00 -
44 1/2"dia PPR Plain Elbow - pcs 40.00 -
45 1/2"dia PPR Plain Tee - pcs 50.00 -
46 1/2"dia PPR Elbow Adaptor - pcs 51.00 -
47 1/2"dia PPR Gate Valve - pcs 200.00 -
48 1/2"dia PPR Check Valve - pc 250.00 -
48 Water Sub-meters - sets - -
49 PPR Solvent Cement 400cc - cans 380.00 -
50 Elastomeric Sealant (Vulcaseal) - liters 400.00 -
51 Teflon 3/4" - rolls 25.00 -
52 1/2" G.I. Wire Mesh (Screen) - mts 90.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Plumber 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 PPR Fusion Welding 0 0 Eqpt. Days 500.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 10.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

17.0 Utility Works (Electrical, Electronic & Mechanical) 1.00 lot - PHP -

A. MATERIALS
1 Series-type Lamp Lighting Outlet - sets 7,000.00 -
2 Metal Hallide Floodlights, 400W - sets 3,800.00 -
3 T5 Fluorescent Lamp, 21W - sets 300.00 -
4 T5 Fluorescent Lamp, 5W - sets 250.00 -
5 Accent Wall Lamp, Weatherproof - sets 800.00 -
6 Pin Light w/ 3U26W CFL, 6" dia. (Recessed Type) - sets 540.00 -
7 Pin Light w/ 3U26W CFL, 4" dia. (Surface Type) - sets 480.00 -
8 1-14w Electronic Cabinet Lamp - sets 500.00 -
9 Single Gang Switch (Wide Series) - sets 150.00 -
10 Two Gang Switch (Wide Series) - sets 200.00 -
11 Three Gang Switch (Wide Series) - sets 250.00 -
12 Three Way Switch (1 Gang) - sets 150.00 -
13 Single Convenience Outlet (Universal, Classic) - sets 150.00 -
14 Duplex Convenience Outlet (Universal, Classic) - sets 200.00 -
15 Triplex Convenience Outlet (Universal, Classic) - sets 280.00 -
15 Triplex Convenience Outlet (Floor Mounted, Classic) - sets 410.00 -
20 - set 12,000.00 -
Panel Board with Circuit Breakers (100amps Main, 12 branch)

20 - set 10,000.00 -
Panel Board with Circuit Breakers (100amps Main, 9 branch)

20 - set 8,000.00 -
Panel Board with Circuit Breakers (100amps Main, 7 branch)

20 - set 6,000.00 -
Panel Board with Circuit Breakers (60amps Main, 5 branch)

20 - sets 5,000.00 -
Panel Board with Circuit Breakers (30amps Main, 4 branch)

20 Electric Meter Base (Digital Sub-meters) - set 500.00 -


21 2.2mm2 THW Copper Wire, 14/7 AWG (150 m/roll) - rolls 1,750.00 -
22 3.5mm2 THW Copper Wire, 12/7 AWG (150 m/roll) - rolls 2,500.00 -
23 5.5mm2 THW Copper Wire, 10/7 AWG (150 m/roll) - rolls 3,600.00 -
24 8.0mm2 THW Copper Wire, 8/7 AWG (150 m/roll) - m 120.00 -
25 27.0mm2 THW Copper Wire, 3/7 AWG (150 m/roll) - m 210.00 -
26 Flexible Conduit 1/2" dia. (100m/roll) - rolls 750.00 -
27 Flexible Conduit 3/4" dia. (100m/roll) - rolls 850.00 -
28 Rigid Conduit 1/2" dia., RSC - pcs 200.00 -
29 Rigid Conduit 3/4" dia., RSC - pcs 200.00 -
30 Metal Uitility Box, 2"x4" - pcs 25.00 -
31 Metal Junction Box, 4"x4" - pcs 25.00 -
Circuit Breaker
32 120amp, 250 V, Bolt On - pc 2,800.00 -
33 60 amp, 250 V, Bolt On, Single Phase - pcs 280.00 -
34 30 amp, 250 V, Bolt On, Single Phase - pcs 255.00 -
35 20 amp, 250 V, Bolt On, Single Phase - pcs 255.00 -
36 15 amp, 250 V, Bolt On, Single Phase - pcs 255.00 -
37 Electrical Tape (Big) - pcs 35.00 -
Other Utilities (Electronic & Mechanical Works)
17 Cable TV Outlet - sets 180.00 -
18 Telephone Outlet - sets 180.00 -
19 LAN Outlet - sets 180.00 -
19 CCTV Camera Outlet - sets 180.00 -
19 Speaker-Audio Outlet - sets 180.00 -
38 Electronic Works (Wires, accessories & etc.) - lot 20,000.00 -
16 ACU Outlet - sets 180.00 -
17 Range Outlet - sets 180.00 -
18 Wall Fan Outlet - sets 180.00 -
19 Ceiling Fan Outlet - sets 180.00 -
19 Exhaust Fan Outlet - sets 180.00 -
39 Mechanical Works (Wires, accessories & etc.) - lot 20,000.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Electrician / Technician 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 None 0 0 Eqpt. Days - -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 10.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

18.0 Tile Works & Hardscapes 1.00 sq.m. - PHP -

A. MATERIALS
1 600 X 600mm Porcelain Polished (Interior) - pcs 280.00 -
2 600 X 600mm Porcelain Non-Skid Tiles (Exterior) - pcs 280.00 -
3 300 X 300mm Non-Skid Tiles (Toilet & Stairs) - pcs 180.00 -
4 300 X 600mm Ceramic Wall Tiles - pcs 180.00 -
5 Concrete Pavers, Zigzag, 112.5mmX225mmX50mm - pcs 45.00 -
6 Concrete Pavers, Rectangle, 112.5mmX225mmX50mm - pcs 45.00 -
3 3/4" Crushed Gravel - cu.m. 1,050.00 -
3 3/4" Garden Stone, White - cu.m. 2,200.00 -
6 Tile Adhesive, 25 Kgs. - bags 480.00 -
7 Portland Cement - bags 280.00 -
8 Washed Sand - cu.m. 1,050.00 -
9 Tile Grout, 2 Kgs. - bags 200.00 -
10 Tile Grout Sealer - ltrs 250.00 -
11 Concrete Epoxy - gals 1,700.00 -
12 105mm/ 4" Porcelain Tile Blade Cutter Wet/Dry - pcs 235.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Tile Setter 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Diamond Tile Cutter 0 0 Eqpt. Days 200.00 -
2 Angle Grinder 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

19.0 Ceiling Works 1.00 sq.m. - PHP -

A. MATERIALS
1 FICEM Board 4.5mm thk (Hardiflex) - shts 700.00 -
2 FICEM Board 12.0mm thk (Hardi-senepa) - shts 1,800.00 -
3 Double Metal Furring Channel, 3/4"x2"x5m - lgths 145.00 -
4 Carrying Channel, 1/2"x1 1/2"x5m - lgths 155.00 -
5 W-Furring Clip - pcs 8.00 -
6 Wall Angle, 0.60mm x 1" x 1" x 10' - lgths 100.00 -
7 Spandrel Ceiling System - l.mts. 210.00 -
8 Cutting Disc, 4" dia. - pcs. 110.00 -
9 1" FICEM Screw - pcs 3.00 -
10 1" Screw with Tox - pcs 4.00 -
11 2" Concrete Nails - kgs 105.00 -
12 1/8" Metal Drill Bit - pcs 110.00 -
13 Blind Rivets 1/8" x 1/2"" - boxes 250.00 -
14 Tie Wire, ga.16 - kgs 90.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Installer 0 0 Men 600.00 -
3 Laborer 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Electric Drill 0 0 Eqpt. Days 250.00 -
2 Angle Grinder 0 0 Eqpt. Days 250.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

20.0 Painting Works 1.00 sq.m. 315.00 PHP 315.00

A. MATERIALS
1 Masonry Wall Painting 1.00 sq.m. 300.00 300.00
2 Ceiling Painting 0.00 sq.m. 300.00 -
3 Wood/Door Painting 0.00 sq.m. 340.00 -
4 Steel Works Painting 0.00 sq.m. 300.00 -
Sub-Total A = PHP 300.00

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Painter 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Compressor 0 0 Eqpt. Days 500.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP 300.00

E. OCM 5.0% OF D = 15.00


F. TOTAL COST OF WORK ITEM (F=D+E) = 315.00
G. UNIT COST = 315.00
H. ADJUSTED UNIT COST = 315.00
I. TOTAL ADJUSTED COST PHP 315.00

ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

21.0 Accessories & Specialty Works 1.00 lot - PHP -

A. MATERIALS
1 20 lbs. Fire Extinguisher - units 2,900.00 -
2 Emergency Light - units 1,800.00 -
3 Emergency Exit Sign - units 1,100.00 -
3 Smoke Detector - units 950.00 -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Technician 0 0 Men 600.00 -
3 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 None 0 0 Eqpt. Days - -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -
ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST

22.0 Site Clearing Works 1.00 lot - PHP -

A. MATERIALS
1 None - pcs. - -
Sub-Total A = PHP -

B. LABOR QTY DAYS UNIT RATE/DAY


1 Foreman 0 0 Men 1,000.00 -
2 Laborers 0 0 Men 400.00 -
Sub-Total B= PHP -

C. EQUIPMENTS QTY DAYS UNIT RATE/DAY


1 Elf Truck 0 0 Eqpt. Days 3,000.00 -
Sub-Total C= PHP -

D. TOTAL DIRECT COST (A+B+C) = PHP -

E. OCM 5.0% OF D = -
F. TOTAL COST OF WORK ITEM (F=D+E) = -
G. UNIT COST = -
H. ADJUSTED UNIT COST = -
I. TOTAL ADJUSTED COST PHP -

Prepared by: Approved by:

MS. MARIA CLARA DELOS SANTOS MR. JUAN DELA CRUZ


Estimator Owner
LOGO
Project Title : PROPOSED BUILDING
Location : Number, Street, Barangay, City/Municipality, Province, Country
Owner : Mr. Juan dela Cruz
Subject : SUMMARY OF WORKS

A. DESCRIPTION QTY UNIT UNIT COST MATERIAL COST LABOR COST EQUIPMENT COST OCM TOTAL COST
1.0 Mobilizaton & Demobilization 1.00 lot - - - - - -
2.0 Temporary Facility Construction 1.00 lot - - - - - -
3.0 Site Preparation Works 1.00 sq.m. - - - - - -
4.0 Earthworks 1.00 cu.m. - - - - - -
5.0 Termite Proofing Works 1.00 sq.m. - - - - - -
6.0 Scaffolding & Form Works 1.00 lot - - - - - -
7.0 Reinforcement Works 1.00 kgs. - - - - - -
8.0 Steel Works 1.00 lot - - - - - -
9.0 Concrete Works 1.00 cu.m. - - - - - -
10.0 Masonry Works 1.00 sq.m. - - - - - -
11.0 Waterproofing Works 1.00 sq.m. - - - - - -
12.0 Roofing Works 1.00 lot - - - - - -
13.0 Door Installation 1.00 lot - - - - - -
14.0 Window Installation 1.00 lot - - - - - -
15.0 Carpentry Works 1.00 lot - - - - - -
16.0 Plumbing Works 1.00 lot - - - - - -
17.0 Utility Works (Electrical, Electronic & Mech 1.00 lot - - - - - -
18.0 Tile Works & Hardscapes 1.00 sq.m. - - - - - -
19.0 Ceiling Works 1.00 sq.m. - - - - - -
20.0 Painting Works 1.00 sq.m. 315.00 300.00 - - 15.00 315.00
21.0 Accessories & Specialty Works 1.00 lot - - - - - -
22.0 Site Clearing Works 1.00 lot - - - - - -

B. TOTAL PROJECT COST: 300.00 - - 15.00 PHP 315.00

Prepared by: Approved by:

MS. MARIA CLARA DELOS SANTOS MR. JUAN DELA CRUZ


Estimator Owner

You might also like