Reliability Support of Undependable Grid Using Green Energy Systems
Reliability Support of Undependable Grid Using Green Energy Systems
ABSTRACT Developing countries’ energy sector faces a multitude of challenges, ranging from inadequate
generation to unstable grids. Power outages are among the most common issues, particularly in remote
areas. Utilizing grid-tied green energy resources to address this issue and to cover for power outages from
local grids. This article presents a cost-effective design of a grid-tied, hybrid green energy system (GES)
consisting of wind, PV, and batteries considering the influence of the grid availability. A multi-objective,
optimal techno-economic design, optimized by multi-objective particle swarm optimization technique is
presented for the grid-tied GES linked to a small hamlet in the north of Egypt. The multi-objective function
introduced in this work includes three objective functions which are, the Loss of Power Supply Probability
(LPSP), the Cost of Energy (COE), and the System Surplus Energy Rates (SSER) considering the grid
availability. The grid availability (GA) of 100% was considered as a base case and it was reduced to 70%
with a step of 5%. The simulation consequences had cleared that the lowest and largest percentage values of
SSER were obtained at GA of 85 %, and 70 %, respectively. When the value of SSER equal to 0.33%, the
system design for solving the grid unavailability consists of 12 PVs, one WT, and 1420 batteries with COE
of 0.145$/kWh and TNPC of 3,699,800 ($).
INDEX TERMS Grid availability, multi-objective optimization, loss of power supply probability, system
surplus energy rates, sizing, and optimization.
This work is licensed under a Creative Commons Attribution 4.0 License. For more information, see https://creativecommons.org/licenses/by/4.0/
14528 VOLUME 9, 2021
M. M. Samy et al.: Reliability Support of Undependable Grid Using GESs: Economic Study
Rgrid Sales of electricity to the public utility Mondal and Islam analyzed the frugal viability of
ratefeed−in Feed-in tariff rate utility-connected PV systems and concluded that this system
S Salvage value must be utilized to overcome power shortages [2]. Robert and
Tamb Ambient temperature (◦ C) Goplan had made twenty scenarios to investigate the integra-
Tc PV cell temperature (◦ C) tion of GES into the grid and concluded that the utility-linked
Tcomp Component lifespan (year) GES is the most expense-efficient energy system compared to
Tproj Project lifespan (year) the island systems [3]. The optimal sizing of grid-connected
Tref Temperature at base conditions (◦ C) three renewable energy sources (PV, wind, and fuel cell) was
Vci Cut-in wind speed (m/s) investigated to supply some domestic loads [4].
Vco Cut-out wind speed (m/s) A grid-linked grouped heat and energy project for sup-
Vr Rated wind speed (m/s) plying household loads was investigated with several tar-
iffs for buying and selling electricity from the utility [5].
A model was developed for estimating the energy produc-
ABBREVIATIONS tion, selling electricity to the local grid using wind turbine
COE Cost of electricity (WT)/Hydrogen system, thermal recovery from fuel cells
CRF Capital recovery factor (FCs) [6]. The potential of both off-grid and on-grid PV, WT,
DOD Depth of discharge FC, and biomass hybrid systems for the electrical energy
GA Grid Availability generation with a focus on the optimal size of the GES has
GES Green Energy System been inspected [7]–[14].
LPSP Loss of Power Supply Probability A detailed study about how to overcome the power outages
MOPSO Multi-Objective Particle Swarm Optimization in a rural area in Egypt by integrating a hybrid PV/WT/FC to
NWCT Normal working cell temperature the electrical utility was presented in [14]. This study focused
PPA Power Purchase Agreements on maximizing the profit from integrating these three GESs
SSER System Surplus Energy Rates to the Egyptian electric utility considering the cost of these
Pch,b Charging power of the battery GES sources. The objective function in this study was a single
Pdis,b Discharging power of the battery objective function with one objective, which is to minimize
PPV PV produced power (kW) the cost of electricity (COE). It is worth noting that this study
Pr Rated wind turbine power (kW) had presented a proposal to use FCs as storage units instead
Prated Module output power (kW) of batteries.
Pre Power produced by the renewable system Another investigation for the optimal size of an island
at hour t hybrid GES supplies a new society in Egypt was presented
TNPC Total net present cost in [15], [16]. In the preceding studies, the optimal size with
WT Wind turbine minimum capital and running costs for this proposed feeding
system was introduced. Wang et al. investigated the common
GREEK SYMBOL consequences of combining renewable energy with the elec-
ηb Efficiency of each battery trical network on provincial energy efficiency. The authors
ηinv Inverter efficiency have concluded that the effect of renewable energy genera-
ηw Wind turbine efficiency tors integrated into extra-high voltage and ultra-high voltage
power grids are either not noteworthy or even negative [17].
Kamal, et al proposed a grid-connected GES including WT,
I. INTRODUCTION solid oxide FC, Electrolyzer, and batteries to serve the electric
Instability, power block-outs, significant distribution network demand of twenty-five homes in Islamabad, the metropolis
outages, and frequently scheduled load shedding impact the of Pakistan [18]. A comprehensive literature exploration was
centralized electricity grids, especially the developing coun- conducted to assemble accessible information about unreli-
tries. The reliability of the grid is determined based on the able grid modeling but went over a couple of such exami-
ratio of the total number of customer hours that service was nations [19]. Murphy et al completed an analytical survey
available during a given period to the total customer hours for Uganda dealing with the uncertain utility by devising a
requested, which is known as the average availability service method in which a producer is produced with one hundred
index (AASI). The AASI is expected to be 0.9988 for a efficacy percentage. The survey notified that uncertain utility
reliable grid whereas an unreliable grid is characterized by consideration raised the estimate of energy contrasted to 24h
random power outages [1]. The best way to address these availability of the utility [20]. Harish et al. [21] had made a
grid issues and consequently supporting the grid reliability comparison among utility expansion and distributed genera-
is widely incorporate the production of clean green energy tion (DG) alternates to solve the problem of power outages in
into the power distribution networks. Grid-connected green rural India. Various utility reliability tactics were simulated.
energy systems (GESs) could be an applicable option to The authors concluded that off-grid DG does not seem to
provide sustainable electric outfits to developing countries. be competitive with utility expansion at distances less than
seventeen kilometers. This is because whenever the location stable and cost-effective method. While Singh et al. [27]
of the new society or the village is far from the network, on- recommended the reformed electric system cascade analy-
grid GES is the best choice from the frugal viewpoint. While sis (RESCA) approach to design the hybrid renewable energy
an island GES is a better choice for closer locations from the system (HRES), using wind conversion systems, photovoltaic
network. systems, the battery storage system, the non-intermittent
The GES integration to the electric utility is a rich area of source, and the grid as components. Four distinct HRES struc-
research in recent times to solve both the energy supply and tures are considered for study in off-grid and grid-connected
environmental problems. This research area has many chal- mode. The four HRES configurations are configured with
lenges. These challenges are summarized around the optimal restrictions from RESCA, such as final surplus capacity,
utilization of the available resources through sound economic renewable energy rate, LPSP, and annual system cost (ASC).
studies especially for the new communities and through track- The topic of integrating renewable energy sources in the
ing the maximum power point for optimal exploitation of the unreliable grid is a major technical and economic challenge,
available GES [22], [23]. especially for small or rural villages.
As discussed before, the economic study of such GES inte- The issue of unreliable grids is addressed in this article
grated into the electrical utility is a difficult issue and almost since these grids commonly suffer from the problem of fre-
to the stage of complexity. This difficulty of such issues quent power outages a grid-connected green energy system
is related and not limited to, a large number of variables, composed of solar PV, wind turbines, and battery banks have
the non-linear characteristics of GES, and the dependence of been suggested as a backup system used to compensate for
these GES on some environmental factors which in turn affect blackouts.
the power generated from these GES. Evolutionary comput- In this work, the situation where the grid is completely
ing techniques are used for such mixed-complex optimization available was first considered, and then the availability of the
problems. grid was decreased by 5 percent per time from 95 percent to
Genetic and particle swarm optimization (PSO) mecha- 70 percent to show the influence of network availability on
nisms were applied to economic studies of off-grid GES [24]. the design of the proposed hybrid system.
This study is presented also a comparison between these The optimal number of components of the grid-connected
two optimization mechanisms and the results showed the PV/WT/battery system has been identified by utilizing the
superiority of PSO. Multi-Objective Particle Swarm Optimization (MOPSO)
Harmony search (HS), enhanced flower pollination algo- which was used for reducing three objective functions of Loss
rithm (FPA), an electromagnetic field optimization is utilized of Power Supply Probability (LPSP), Cost of Energy (COE),
for enhancing the performance of grid-connected GES in the and System Surplus Energy Rates (SSER) under varying
form of FC [25]. conditions in the weather; by using actual on-site hourly
Rezvani et al. utilized lexicographic optimization and power demand data for the studied village. The Pareto front
hybrid augmented weighted epsilon-constraint algorithms for and decision-making processes are used to obtain the final
the optimal tabulating of a micro-grid to mitigate both the optimal system.
overall working estimation and the emission that was resulted This article is structured as follows: Section 1 addresses the
from the generating stations. The results showed that the background and literature review of the study. Section 2 lays
proposed hybrid optimization technique leads to good out- out the methodology. Details of the Fitness Function and
standing solutions [6]. Improvement of off-grid hybrid sys- Energy Management Scenarios are explained in Section 3.
tem performance was improved by optimal PI controllers Section 4 discusses the findings of the simulation and the
optimized by the cuckoo search mechanism [23]. This opti- optimization of the study case. Conclusions are outlined in
mization technique is applied to achieve maximum power section 5.
point tracking of three GESs (PV/WT/FC) and consequently
achieving the maximum economic benefit and reducing the II. METHODOLOGY
cost of generation. The extreme learning machine (ELM) The objective of this research is to manifest the techno-
mechanism was used to develop a model to forecast the economic feasibility through a case study of a village in
amount of the produced power of utility-tied PV system Northern Egypt. This hybrid GES comprises solar PV genera-
installed at a roof-top of PEARL laboratory at the Univer- tors, wind turbines, and battery banks. The system is attached
sity of Malaya, Malaysia [19]. The consequences from the to an unreliable grid for remote rural electrification.
introduced model were contrasted with those obtained from MOPSO has been used to design a hybrid power system to
the support vector regression and the artificial neural network assess the optimum size of its components by performing a
(ANN). The comparison illustrated that the ELM model has techno-economic analysis. Figure 1 shows the approach used
higher exactness with less predestined time. for the effective configuration and the techno-economic study
The risk theory into the allocation and placement of dis- of the proposed scheme.
tributed generation (DG) units, [26] suggested a risk-based, Information concerning energy demand and environmen-
multi-objective optimum allocation model to maximize the tal data, such as solar radiation, ambient temperature,
placement and configuration of DG units and provide a and wind speed were collected for one year between the
1st January 2019 and the 31st December for Qesm Rem-
anah, North Sinai, Egypt (latitude 31.03641 ◦ N, longitude
32.62705 ◦ E). Renewable energy supplies with an estimated
annual solar radiation of 2027kWh/m2 and an average wind
velocity of 4.22 m/s, are the main feature of this area. This
analysis uses actual hourly data in-site for the village energy
demand, with an average of 457 kWh hourly, an average
demand of 897 kW, and a load factor of 0,509. The average
daily load for the selected area is seen in Figure 2. The solar
radiation and the wind speed of the field under study were
shown in Figures 3 and 4.
the system and assessing the hybrid system’s usability and contented, and if its value is one then the load demand will
performance. eternally be served [42], [43].
The cost of electricity (COE) refers to the costs of produc- The LPSP can be described as:
ing electricity over the lifespan of the project. PT
Pdeficit (t) .1t
It is a very valuable indicator because, while the rating LPSP = PTt=1 , T = 8760 (23)
power and investment costs are different, it permits a distinc- t=1 Pdemand (t) .1t
tion between diverse energy technologies [39], [40]. The SSER is the percentage of the surplus energy in the
The COE of the grid-connected PV/WT/battery hybrid hybrid system compared with the total renewable energy
system is defined as: generated by GES [44]. The SSER is subject to the constraint
(CRF × TNPC) + Cgrid − Rgrid 0 ≤ SSER ≤ 1.
COE = (13) P
Eserved + Egridselling surplus energy
SSER = P (24)
where: Capital recovery factor (CRF) is a ratio used over EPV + EWT
the life of a project to determine the total value of a set of The fitness function for this multi-objective optimization
equivalent cash flows. The estimation of this factor is given can be expressed as follows.
by:
F1 = COE
Ir −If N
Ir −If minimize : F2 = LPSP (25)
1+If 1 + 1+If
F3 = SSER
CRF = (14)
Ir −If N
min
1 + 1+If −1 NPV ≤ N PV ≤ NPV max
min max
NWT ≤ N WT ≤ NWT
TNPC is the total net present cost of the system which is min max
subjct to : Nbat ≤ N bat ≤ Nbat (26)
composed of the NPC of the PV, WT, and battery banks.
0 ≤ LPSP ≤ LPSP , LPSP = 2%
max max
0 ≤ SSER ≤ SSERmax , SSERmax = 15%
Nproj
X
TNPC = (CI (n) + CR (n) + CO&M (n) − S (n))
n=0 C. MULTI-OBJECTIVE PARTICLE SWARM OPTIMIZATION
1 ALGORITHM (MOPSO)
× (15)
(1 + Ir )n MOPSO technique had been used in this article to tackle the
energy management dilemma.
X
CI = NPV CIPV + NWT CIWT + Nbat CIbat (16)
X Therefore, the MOPSO algorithm is utilized to achieve
CR = NPV CRPV + NWT CRWT + Nbat CRbat (17) the Pareto front of the optimization problem. The MOPSO
X procedure (Figure 7) in this research work was adapted
CO&M = NPV CO&M PV + NWT CO&M WT + Nbat CO&M bat
from [45], [46].
(18)
X
S = NPV SPV + NWT SWT + Nbat Sbat (19) D. DATA PREPARATION FOR THE SIZING OPTIMIZATION
PROCESS
The salvage value (S) was estimated by:
The hourly load demand, the solar irradiance (kWh per m2
Nproj per day), the ambient temperature (◦ C), and the wind speed
Ncomp − Nproj − Ncomp × INT Ncomp
S = CR (20) (m/s) for the hamlet used in this study are recorded in 2019
Ncomp (8760 points). A code for the MOPSO technique is progressed
in MATLABTM software package is introduced to minimize
Sales of electricity to the public utility and cost of energy
the multi-objective function proposed in this study based on
purchase can be estimated as:
the recorded data all over 2019 for this village.
8760
X
Rgrid = ratefeed−in .Egridselling (21) IV. RESULTS AND DISCUSSIONS
t=1 This article suggests a complementary PV / WT / Battery
8760
X system linked to an unreliable grid to support the grid per-
Cgrid = Cp × Egridpurchased (22) formance through compensating the power outage and con-
t=1 sequently increase the reliability of the system in addition to
where: ratefeed−in is the feed-in tariff rate (0.0617 $/kWh) and minimizing the generating cost for a village in Egypt.
Cp is equivalent to $0.0425 / kWh baased on the Egyptian grid The grid unavailability was expressed by the grid avail-
tariff [41]. ability factor (GA), in which the whole situation of the grid
The loss of power supply probability is described as the availability (GA = 100%) was considered as a base case, and
prospect that an inadequate power supply occurs when the then GA is reduced to 70% with an increment of 5%.
GES is incapable of meeting the load needs. The loss of power The optimized objectives presented in this article are to
supply probability of zero value means the load demand is minimize the COE, the LPSP, and the SSER where COE is
used to assess hybrid system economies; LPSP is for relia- A. THE EFFECT OF GA ON COE
bility assessments, and SSER is to measure hybrid system The effect of the GA percentage change on the proposed
usability and efficiency. The optimization variables include system’s COE can be seen in Figure 8, where it can be
the total number of WT, PV, and battery banks. observed that in the base GA case when GA = 100 percent,
The Pareto front estimation of the MOPSO algorithm for the MOPSO has achieved an optimal solution where the
GA from 100% to 70% with a step of 5% is shown in Figure 8. COE was $0.098/kWh, but when this percentage decreased
The Pareto front allows the decision-maker to choose an to 95 percent, the COE value increased to $0.1263/kWh.
optimum solution based on expectations for lower COE, It can be noticed that COE increases with decreasing GA
LPSP, or SSER from the optimal solutions collection. percentage.
The compromise between the three objective functions is
clearly shown in Figure 8. From this figure, the effect of B. THE EFFECT OF GA ON LPSP
GA on the three objective functions can be concluded as The maximum LPSP was set as 2% in the fitness function
follows: constraint, Figure 8 indicates that the MOPSO obtained an
Np q
X
Optimal Sol. = min (COE(i) − COE(k))2 + (LPSP(i) − LPSP(k))2 + (SSER(i) − SSER(k))2 i ∈ [1, Np ] (27)
k=1
FIGURE 8. Comparing the base GA case, the Pareto front of the three objective functions for various GA states.
[8] S. Barakat, M. M. Samy, M. B. Eteiba, and W. I. Wahba, ‘‘Feasibility study [27] R. Singh, R. C. Bansal, A. R. Singh, and R. Naidoo, ‘‘Multi-objective
of grid connected PV-biomass integrated energy system in egypt,’’ Int. J. optimization of hybrid renewable energy system using reformed elec-
Emerg. Electr. Power Syst., vol. 17, no. 5, pp. 519–528, Oct. 2016, doi: tric system cascade analysis for islanding and grid connected modes
10.1515/ijeeps-2016-0056. of operation,’’ IEEE Access, vol. 6, pp. 47332–47354, 2018, doi:
[9] S. Barakat, M. M. Samy, M. B. Eteiba, and W. I. Wahba, ‘‘Viability study of 10.1109/ACCESS.2018.2867276.
grid connected PV/Wind/Biomass hybrid energy system for a small village [28] V. P. Khambalkar, D. S. Karale, and S. R. Gadge, ‘‘Performance evaluation
in egypt,’’ in Proc. 18th Int. Middle East Power Syst. Conf. (MEPCON), of a 2 MW wind power project,’’ J. Energy Southern Afr., vol. 17, no. 4,
Dec. 2016, pp. 46–51. pp. 70–75, Nov. 2006.
[10] M. M. Samy and S. Barakat, ‘‘Hybrid invasive weed optimization— [29] M. M. Samy, S. Barakat, and H. S. Ramadan, ‘‘A flower pollination opti-
Particle swarm optimization algorithm for Biomass/PV micro-grid power mization algorithm for an off-grid PV-fuel cell hybrid renewable system,’’
system,’’ in Proc. 1st Int. Middle East Power Syst. Conf. (MEPCON), Int. J. Hydrogen Energy, vol. 44, no. 4, pp. 2141–2152, Jan. 2019.
Dec. 2019, pp. 377–382. [30] T. J. Stehly, P. C. Beiter, D. M. Heimiller, G. N. Scott, and A. Walker,
[11] S. Barakat, H. Ibrahim, and A. A. Elbaset, ‘‘Multi-objective optimization ‘‘PV O&M cost model and cost reduction,’’ Nat. Renew. Energy Lab.
of grid-connected PV-wind hybrid system considering reliability, cost, (NREL), Denver, CO, USA, Tech. Rep. NREL/TP-5C00-74840, Jun. 2020.
and environmental aspects,’’ Sustain. Cities Soc., vol. 60, Sep. 2020, [Online]. Available: https://www.nrel.gov/docs/fy20osti/74840.pdf
Art. no. 102178. [31] S. K. Ramoji and B. J. Kumar, ‘‘Optimal economical sizing of a PV-wind
[12] A. F. Tazay, M. M. Samy, and S. Barakat, ‘‘A techno-economic feasibility hybrid energy system using genetic algorithm and teaching learning based
analysis of an autonomous hybrid renewable energy sources for univer- optimization,’’ Int. J. Adv. Res. Electr. Electron. Instrum. Eng., vol. 3, no. 2,
sity building at Saudi Arabia,’’ J. Electr. Eng. Technol., vol. 15, no. 6, pp. 7352–7367, 2014.
pp. 2519–2527, Nov. 2020. [32] A. Malheiro, P. M. Castro, R. M. Lima, and A. Estanqueiro, ‘‘Integrated
[13] M. M. Samy, H. I. Elkhouly, and S. Barakat, ‘‘Multi-objective opti- sizing and scheduling of wind/PV/diesel/battery isolated systems,’’ Renew.
mization of hybrid renewable energy system based on biomass and Energy, vol. 83, pp. 646–657, Nov. 2015.
fuel cells,’’ Int. J. Energy Res., to be published. [Online]. Available: [33] K. Wu, H. Zhou, S. An, and T. Huang, ‘‘Optimal coordinate operation
https://onlinelibrary.wiley.com/doi/abs/10.1002/er.5815 control for wind–photovoltaic–battery storage power-generation units,’’
[14] M. M. Samy, M. I. Mosaad, and S. Barakat, ‘‘Optimal economic study Energy Convers. Manage., vol. 90, pp. 466–475, Jan. 2015.
of hybrid PV-wind-fuel cell system integrated to unreliable electric [34] T. Stehly, P. Maples, D. Heimiller, and G. Scott, 2017 Cost of Wind
utility using hybrid search optimization technique,’’ Int. J. Hydrogen Energy Review. Golden, CO, USA: National Renewable Energy Labora-
Energy, to be published. [Online]. Available: https://www.sciencedirect. tory, Feb. 2018, pp. 23–40, doi: NREL/TP-6A20-64281.
com/science/article/pii/S0360319920329335 [35] Simpliphi Phi 2.6 KWH Smart-Tech Hi Power LFP Battery. Accessed:
[15] M. I. Mosaad, M. O. A. El-Raouf, M. A. Al-Ahmar, and F. M. Bendary, 2016. [Online]. Available: SimpliPhiPower
‘‘Optimal PI controller of DVR to enhance the performance of hybrid [36] A. Jaiswal, ‘‘Lithium-ion battery based renewable energy solution for off-
power system feeding a remote area in Egypt,’’ Sustain. Cities Soc., vol. 47, grid electricity: A techno-economic analysis,’’ Renew. Sustain. Energy
May 2019, Art. no. 101469, doi: 10.1016/j.scs.20189.101469. Rev., vol. 72, pp. 922–934, May 2017, doi: 10.1016/j.rser.2017.01.049.
[16] W. S. Hassanein, M. M. Ahmed, M. O. abed el-Raouf, M. G. Ashmawy, and [37] S. Dhundhara, Y. P. Verma, and A. Williams, ‘‘Techno-economic anal-
M. I. Mosaad, ‘‘Performance improvement of off-grid hybrid renewable ysis of the lithium-ion and lead-acid battery in microgrid systems,’’
energy system using dynamic voltage restorer,’’ Alexandria Eng. J., vol. 59, Energy Convers. Manage., vol. 177, pp. 122–142, Dec. 2018, doi: 10.1016/
no. 3, pp. 1567–1581, Jun. 2020. j.enconman.2018.09.030.
[17] Y. Wang, W. Yan, S. Zhuang, and J. Li, ‘‘Does grid-connected clean power [38] S. M. Hakimi, S. M. M. Tafreshi, and A. Kashefi, ‘‘Unit sizing of a stand-
promote regional energy efficiency? An empirical analysis based on the alone hybrid power system using particle swarm optimization (PSO),’’ in
upgrading grid infrastructure across China,’’ J. Cleaner Prod., vol. 186, Proc. IEEE Int. Conf. Autom. Logistics, Aug. 2007, pp. 3107–3112.
pp. 736–747, Jun. 2018. [39] S. Guo, Y. He, H. Pei, and S. Wu, ‘‘The multi-objective capacity optimiza-
[18] T. Kamal, S. Z. Hassan, H. Li, S. Mumtaz, and L. Khan, ‘‘Energy manage- tion of wind-photovoltaic-thermal energy storage hybrid power system
ment and control of grid-connected wind/fuel cell/battery hybrid renewable with electric heater,’’ Sol. Energy, vol. 195, pp. 138–149, Jan. 2020, doi:
energy system,’’ in Proc. Int. Conf. Intell. Syst. Eng. (ICISE), Jan. 2016, 10.1016/j.solener.2019.11.063.
pp. 161–166. [40] M. Petrollese and D. Cocco, ‘‘Optimal design of a hybrid CSP-PV plant
[19] M. Hossain, S. Mekhilef, M. Danesh, L. Olatomiwa, and S. Shamshir- for achieving the full dispatchability of solar energy power plants,’’ Sol.
band, ‘‘Application of extreme learning machine for short term output Energy, vol. 137, pp. 477–489, Nov. 2016.
power forecasting of three grid-connected PV systems,’’ J. Cleaner Prod., [41] Cabinet Decision no. 2532, of 2016 on the Issuance of the Second
vol. 167, pp. 395–405, Nov. 2017. Phase of the Tariff System for Electric Recharge, Egyptian Electr. Util-
[20] P. M. Murphy, S. Twaha, and I. S. Murphy, ‘‘Analysis of the cost of ity Consum. Protection Regulatory Agency (EgyptERA), Cairo, Egypt,
reliable electricity: A new method for analyzing grid connected solar, 2015. Accessed: Feb. 2018. [Online]. Available: http://egyptera.org/
diesel and hybrid distributed electricity systems considering an unreliable Downloads/Laws/the%20Electricity%20Law.pdf
electric grid, with examples in uganda,’’ Energy, vol. 66, pp. 523–534, [42] M. K. Deshmukh and S. S. Deshmukh, ‘‘Modeling of hybrid renewable
Mar. 2014. energy systems,’’ Renew. Sustain. Energy Rev., vol. 12, no. 1, pp. 235–249,
[21] S. M. Harish, G. M. Morgan, and E. Subrahmanian, ‘‘When does unreliable Jan. 2008.
grid supply become unacceptable policy? Costs of power supply and [43] H. Yang, W. Zhou, L. Lu, and Z. Fang, ‘‘Optimal sizing method for stand-
outages in rural india,’’ Energy Policy, vol. 68, pp. 158–169, May 2014. alone hybrid solar–wind system with LPSP technology by using genetic
[22] M. O. A. El-Raouf, M. I. Mosaad, M. A. Al-Ahmar, and F. M. El Bendary, algorithm,’’ Sol. Energy, vol. 82, no. 4, pp. 354–367, Apr. 2008.
‘‘MPPT of hybrid solar-wind-grid power generation system,’’ Int. J. Ind. [44] S. Diaf, D. Diaf, M. Belhamel, M. Haddadi, and A. Louche, ‘‘A method-
Electron. Drives, vol. 2, no. 4, pp. 234–241, 2015. ology for optimal sizing of autonomous hybrid PV/wind system,’’ Energy
[23] N. Alshammari, M. M. Samy, and J. Asumadu, ‘‘Optimal economic anal- Policy, vol. 35, no. 11, pp. 5708–5718, Nov. 2007.
ysis study for renewable energy systems to electrify remote region in [45] S. Mostaghim and J. Teich, ‘‘Strategies for finding good local guides in
kingdom of saudi arabia,’’ in Proc. 20th Int. Middle East Power Syst. Conf. multi-objective particle swarm optimization (MOPSO),’’ in Proc. IEEE
(MEPCON), Dec. 2018, pp. 1040–1045. Swarm Intell. Symp. SIS, Apr. 2003, pp. 26–33.
[24] B. Tudu, S. Majumder, K. K. Mandal, and N. Chakraborty, ‘‘Comparative [46] N. Padhye, J. Branke, and S. Mostaghim, ‘‘Comprehensive comparison of
performance study of genetic algorithm and particle swarm optimization MOPSO methods: Study of convergence and diversity—Survey of state
applied on off-grid renewable hybrid energy system,’’ in Proc. Int. Conf. of the art,’’ in Proc. 11th Conf. Congr. Evol. Comput. (CEC), May 2009,
Swarm, Evol., Memetic Comput., Dec. 2011, pp. 151–158. pp. 2516–2523.
[25] M. I. Mosaad and H. S. Ramadan, ‘‘Power quality enhancement of grid- [47] A. R. Starke, J. M. Cardemil, R. Escobar, and S. Colle, ‘‘Multi-objective
connected fuel cell using evolutionary computing techniques,’’ Int. J. optimization of hybrid CSP+PV system using genetic algorithm,’’ Energy,
Hydrogen Energy, vol. 43, no. 25, pp. 11568–11582, Jun. 2018. vol. 147, pp. 490–503, Mar. 2018.
[26] X. Xiong, W. Wu, N. Li, L. Yang, J. Zhang, and Z. Wei, ‘‘Risk-based multi- [48] T. M. Azerefegn, R. Bhandari, and A. V. Ramayya, ‘‘Techno-economic
objective optimization of distributed generation based on GPSO-BFA analysis of grid-integrated PV/wind systems for electricity reliability
algorithm,’’ IEEE Access, vol. 7, pp. 30563–30572, 2019, doi: 10.1109/ enhancement in Ethiopian industrial park,’’ Sustain. Cities Soc., vol. 53,
ACCESS.2019.2902886. Feb. 2020, Art. no. 101915, doi: 10.1016/j.scs.2019.101915.
[49] M. Hossain, S. Mekhilef, and L. Olatomiwa, ‘‘Performance evaluation of MOHAMED I. MOSAAD received the B.Sc. and
a stand-alone PV-wind-diesel-battery hybrid system feasible for a large M.Sc. degrees from Zagazig University, Egypt,
resort center in south China sea, Malaysia,’’ Sustain. Cities Soc., vol. 28, and the Ph.D. degree from Cairo University,
pp. 358–366, Jan. 2017, doi: 10.1016/j.scs.2016.10.008. Egypt, all in electrical engineering. He is currently
[50] B. E. Türkay and A. Y. Telli, ‘‘Economic analysis of standalone and an Associate Professor with the Department of
grid connected hybrid energy systems,’’ Renew. Energy, vol. 36, no. 7, Electrical and Electronic Engineering Technology,
pp. 1931–1943, Jul. 2011, doi: 10.1016/j.renene.2010.12.007.
YIC, Saudi Arabia. His research interests include
[51] M. Abdel-Salam, A. Ahmed, H. Ziedan, K. Sayed, M. Amery, and
power system stability, control, and renewable
M. Swify, ‘‘A solar-wind hybrid power system for irrigation in toshka
area,’’ in Proc. IEEE Jordan Conf. Appl. Electr. Eng. Comput. Technol. energy. He is a regular Reviewer of many IEEE
(AEECT), Dec. 2011, pp. 38–43, doi: 10.1109/AEECT.2011.6132491. TRANSACTIONS, IET Electric Power Applications
journal, IET Generation, Transmission and Distribution journal, Interna-
tional Journal of Industrial Electronics and Drives (IJIED), and Interna-
tional Journal of Energy Engineering (IJEE). He is also the Editor-in-Chief
of YJES.