The+Scope+of+Works
The+Scope+of+Works
Theo
www.theoheath.com
1/18/2021
Contents
Page 1 of 5
What is Project Scope
The project scope should contain and specify all the key deliverables and tasks for the project.
In Scope
What is In-Scope
Ensure all responsible parties stay within the scope during the project, not working on external
activities that will not contribute to the success of the project.
Example of In-Scope
The team was given the task to design and develop a new engine for a car.
The entire team works on different parts of the engine, at the same time collaborate with the
team members and make sure the engine and engine alone take the full concentration of the
team.
Out of Scope
What is Out-of-Scope
When working on a task that was not included in the project design scope of works and does not
contribute to the success of the project.
The team was given the task to design and develop a new engine for a car.
Instead of the entire team working on the success of the engine, one team moves to work on the
car suspension. This was not part of the original scope of works.
By going out of scope the success of the project will be harder.
Page 2 of 5
Scope Change
Design
The design is approved during the design phase and no changes to this design can be made
without all the responsible stakeholders being notified and all stakeholders approve the change.
The change order request is submitted for all the relevant stakeholders to review and approve.
Changes to the scope will always have financial, quality and time related issues that must be
addressed.
Change Order
The responsible stakeholders will all review the change order and comment on changes to the
budget, quality and duration of the project before deciding if the change is feasible and within
the project objectives.
Once all the stakeholders approve the change order the document is distributed to all
management so the updates to the design can be executed.
The change in scope will have an impact on budget, time, and quality. Update the programme
and budget to ensure the duration and financial changes are indicated. The execution of the
change must also be managed with quality control to ensure no quality implications occur during
the change.
Scope Baseline
The scope baseline provides detailed information about each of the smaller activities that will
make out the project.
The activities will get a code with a description of the works and could include the resources
necessary to complete the task.
Page 3 of 5
Work Breakdown Structure
To give a clear overview of the project scope we need to create a detailed work breakdown
structure. The work breakdown structure is exactly what it says, it is a structure that breaks
down the work in smaller activities that will make out the project.
Project Name
Code Description Recourses
1 Foundation
1.1 Earthworks
Labour
Equipment
1.1.1 Surveying and setting out
Tools
Consumables
Labour
Tools
1.1.2 Excavate and level
Machinery
Consumables
Page 4 of 5
Method Statement
Item
Method Description
Describe the labour, including the number of employees as well as the description of labour.
The output of that labour is calculated and provided.
Calculate project cost, including the material, tools, transport and overheads.
Page 5 of 5