File
File
net/publication/279958528
CITATIONS READS
0 1,821
2 authors:
All content following this page was uploaded by Venkatesh Parath on 18 July 2015.
Engineering
Study on Factors Influence of Resource
KEYWORDS :
Constraints in Time Overrun of
Construction Projects
ABSTRACT Resource constraints plays an important role in Indian construction projects. Effective resource manage-
ment is a prerequisite for project success. This paper aims to identify the factors affecting resource scheduling in
Indian construction projects, in the private and public sectors. From an extensive literature survey and based on experts’ opinion, thirty
three factors affecting resource scheduling were identified. For the quantitative confirmation of the effectiveness of factors affecting
resource scheduling during the construction stage of a project, a questionnaire survey was conducted with construction professionals
like clients, consultants and contractors. Subsequently, the collected data was analyzed, using the factor analysis method. The factor
analysis was employed to group the factors under the principal factors, which were extracted into seven factors: Lack of equipment and
manpower managerial incompetence, financial deficiencies, improper resource allocation, difficulties in special materials, improper
construction and personnel management, lack of awareness and lack of mobilization. This paper recommends some critical factors to
be considered during the resource scheduling process to minimize the construction time overrun.
without significant correlation between variables. The Kaiser- Availability of equipment 0.62
Meyer-Olkin measure of sampling adequacy is sufficient with
Complication of advanced 0.58
the value of 0.944, which is found to be greater than 0.7, which technology equipment
means the data set is likely to factor excellent. Both diagnostic
tests confirm that the data are suitable for the factor analysis. Poor quality of materials 0.58
Transportation of equipment 0.51
Table1. Total Variance Explained
Materials selection and changes
in types and specifications 0.49
Initial Eigenvalues Extraction Sums of Rotation Sums of
Squared Loadings Squared Loadings during construction
Poor procurement of materials 0.46
Component
Cumulative
Cumulative
Cumulative
% of Vari-
% of Vari-
% of Vari-
DC3: Lack of finance difficulties 1.50 5.51
Total
Total
Total
ance
ance
ance
Financing by contractor during 0.75
construction
%
%
Slab of payment during 0.69
1 13.57 40.61 40.61 13.57 40.61 40.61 5.17 15.87 15.87 construction
Financing between the owner 0.68
2 2.00 7.02 47.63 2.00 7.02 47.63 4.83 14.84 30.71 and contractor
Unavailability of financial 0.63
3 1.50 5.51 53.14 1.50 5.51 53.14 4.22 12.98 43.69 incentive
4 1.43 5.30 58.44 1.43 5.30 58.44 3.57 11.00 54.69 Cash Flow (Inflow & Outflow) 0.61
5 1.20 3.63 62.07 1.20 3.63 62.07 2.53 7.38 62.07 DC4: Deployment of resource 1.43 5.30
Lack of Motivation 0.80
Interpretation of factors
An analysis of the thirty three factor affecting resource sched- Lack of Mobilization 0.74
ule items, yielded five factors. These five factors have a smaller
set of composite variables. With respect to lack of Communi- Absenteeism of labour 0.59
cation, poor procurement of materials, damage of materials in Lack of Communication
storage, absenteeism of labour, poor quality of materials were
eliminated in the final factor loading list because of these vari- DC5: Unavailability of human 1.20 3.63
resource issues management
ables having a factor loading of less than 0.4 and a cross- load-
ing of less than 0.1. The variables which comprise one factor Shortage of labour 0.70
component with factor loadings, communalities, eigen value
Lack of skilled labour 0.51
and variance are given in Table 2 and figure 1. The extracted
factors are provided with a little cross loading and evidence of Unqualified work force team 0.45
good convergent and discriminant validity. The five factors are
weighted, based on the eigen value (1 to 7 in the descending Migrant labour 0.47
order). The five factors are named: i) Resource barrier (DC1);
ii) Inadequacy of resource (DC2); iii) Lack of finance difficulties Scree Plot
(DC3); iv) Deployment of resource (DC4); and v) Unavailability 1
0.6
0.2
Variance
Factors Loading Eigen
value Explained 0
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
Component
equipment, availability of equipment, complication of advanced Unavailability of human resource issues management
technology equipment, poor quality of materials, transporta- This factor consisted of four positively loaded elements. It has
tion of equipment, materials selection and changes in types an eigen value of 1.20, and accounted for 3.63 percent of the to-
and specifications during construction, poor procurement of tal variance. The elements of the factors are shortage of labour,
materials. All these activities are due to the inadequacy of the lack of skilled labour, unqualified work force team, and migrant
contractors and sub-contractors during the construction stage. labour. These factors are related to the inefficiency of personnel
management.
All these activities are due to the incapability of the owners and
contractors during the construction stage. Conclusion
This study identified problems related to factors affecting the
Lack of finance difficulties resource schedule, due to overruns during the construction
This factor consisted of five positively loaded elements. It has an phase from different viewpoints of the parties with respect to
eigen value of 1.50 and accounted for 5.51percent of the total three types of indices. The factor analysis is employed to group
variance. The elements of the factors are financing by contrac- them as the principal factors. With the factor analysis technique,
tor during construction, slab of payment during construction, seven factors were extracted in 67.3 percent out of the 33 prin-
financing between the owner and contractor, unavailability of cipal factors based on the eigen value (factor loading less than
financial incentive, and cash flow (Inflow & Outflow).These fac- 0.4 and cross- loading less than 0.1) as follows: lack of equip-
tors are related to incapability of the owners and contractors ment and manpower managerial incompetence, financial de-
during the construction stage. ficiencies, improper resource allocation, difficulties in special
materials, improper construction and personnel management,
Deployment of resource lack of awareness and lack of mobilization . The findings could
This factor consisted of four positively loaded elements. It has help the practitioners to gain a better understanding of the
an eigen value of 1.43, and accounted for 5.30 percent of total problems influencing the budget and time of the projects during
variance. The elements of this factor are lack of motivation, lack the construction stage. By taking care of these potential factors
of mobilization, absenteeism of labour, and lack of communica- in their present and future projects, construction participants
tion. This factor is related to a lack of awareness of the contrac- can reduce and control the extent of delays and cost overruns.
tors and sub-contractor involved in the manpower of custom-
ized items.
REFERENCE [1] Chan D.W.M and Kumaraswamy M.M, “ A comparative study of causes of time overruns in Hong Kong construction projects”, International
journal of project management, Vol. 15 (1977), No 1, pp. 55–63. | [2] Iyer K. C and Jha K. N., “Critical Factors Affecting Schedule Performance:
Evidence from Indian Construction Projects. Journal of Construction Engineering and Management, Vol. 125 (1999), No3, p. 142–150. | [3] Murali Sambasivan and Yau Wen Soon,
“Causes and effects of delays in Malaysian construction industry”, International journal of project management, Vol. 25 (2007), No 4, p. 517–526. | [4] Nirmal Kumar Acharya,
Young Dai Lee, Soo Yong Kim and Jong Chool Lee, ‘Analysis of Construction Delay Factor: A Korean Perspective’, Proceeding of the 7th Asia Pacific Industrial Engineering and man-
agement Systems conference, 17-20 December (2006), Bangkok, Thailand | [5]Yaw Frimpong , Jacob Oluwoye, Lynn Crawford, “ Causes od delay and cost overruns in construction
of ground water projects in a developing countries; Ghana as a case study”, projects”, International journal of project management, Vol. 21 (2003), pp. 321–326.