Awq0853-21-Cdr-Br-010 LM79.5 18.01.2023

The daily report for the Well Pad LM 79.5 project on January 19, 2023, indicates sunny weather and flat ground conditions. The report details personnel, equipment, work disruptions, and ongoing tasks, highlighting manual dewatering and surveying work. There were a total of 10 direct and indirect personnel on site, with no equipment currently in use.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views30 pages

Awq0853-21-Cdr-Br-010 LM79.5 18.01.2023

The daily report for the Well Pad LM 79.5 project on January 19, 2023, indicates sunny weather and flat ground conditions. The report details personnel, equipment, work disruptions, and ongoing tasks, highlighting manual dewatering and surveying work. There were a total of 10 direct and indirect personnel on site, with no equipment currently in use.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 30

BR company DAILY REP

SECTION I - PROJECT
PROJECT NAME Well Pad LM 79.5
PROJECT LOCATION Row 79
EPC CONTRACT NUMBER AWQ0853-021
EPC CONTRACTOR Bawabat Al Rumaila for General Contracting
CONTRACTOR NAME
BR.
(SHORT NAME, THREE CHARACTER)
WEATHER (SUNNY, RAINY, CLOUDY,
Sunny
SAND STORM, WINDY, FOG, etc.)
TEMPERATURE (℃) 12 Degree
DESCRIBE GROUND CONDITIONS The ground is flat
REPORT DATE 19-Jan-2023
(DD-MMM-YYYY)
DAILY REPORT NO. AWQ0853-021-BR-010
(AWQXXX-CDR-contracor Short name-00X)

SECTION II - PERSONNEL
DIRECT
MANPOWER
WORKERS AND JOB CATEGORIES
(HEADCOUNT)

Driver 0

Labour 5

HSE Officer 1

Forman 1
SUBTOTAL 7

INDIRECT
MANPOWER
WORKERS AND JOB CATEGORIES
(HEADCOUNT)

Geotechnical Engineer 1

Survey Engineer 1

Permit Holder 1

…...

SUBTOTAL 3

SECTION III - EQUIPM


DESCRIBE EQUIPMENT ON JOB NUMBER OF UNITS

Shovel 0

Dume Track 0

Excavator 0
Grader 0

…...

SUBTOTAL 0

SECTION IV - WORK D
Disruption Time (Start -
Description
Finish)

Manual dewatering 07.00 am to 02.00 pm

Surveying work [Install Boundary After Update] 07.00 am to 02.00 pm

SUBTOTAL

MATERIALS DELIVERED TO PROJECT


SECTION V - MATERIALS DELIVE
DESCRIPTION
SITE
SECTION VII - DESCRIBE TESTS, SA

CONTRACTOR
CONTRACTOR REPRESENTATIVE
REPRESENTATIVE
NAME
TITLE

SAJJAD SHARHAN SITE ENGINEER


pany DAILY REPORT TO EXXON
SECTION I - PROJECT DETAILS
5

maila for General Contracting

at

BR-010

TION II - PERSONNEL AND WORKERS


DIRECT
ACTIAL WORKING HOURS REMARKS

8
24

INDIRECT
ACTUAL WORKING HOURS REMARKS

24

SECTION III - EQUIPMENT ON JOB


TOTAL HOURS ON JOB REMARKS

0
0

SECTION IV - WORK DISRUPTION


Number of units
Disruption Hours TOTAL Disruption Hours
(Manpower/Equipment)

8 4

8 2

16 6 0

- MATERIALS DELIVERED TO PROJECT SITE


QUANTITY STORAGE LOCATION REMARKS
DESCRIBE TESTS, SAMPLES AND INPSECTION

CONTRACTOR
CONTRACTOR
REPRESENTATIVE EXXON PLANNER
PLANNER SIGNATURE
SIGNATURE

MOHAMMED ALI AMMAR KHAN


Reason for Disruption
Time
EXXON SITE
REPRESENTATIVE
SIGNATURE
Areawise Status & Progress
1 Well Pad 79.5 Construction
1) Today's Status & Progress of work
Construction area no. Construction area name Completed Quantity Cumulative Total Qty required
Sr. No. Work in progress, Performance issues, etc.
(see 'Instruction', e.g.DSX-BF-XXX) (e.g. Inlet separator area) today Completed Qty in BOQ
1 LM.08 GENERAL AREA Manual dewatering ZonA,ZonB N.A

2 LM.01 CUTTING PIT 1 Surveying work [Install Boundary After Update]

3 LM.02 CUTTING PIT 2 Surveying work [Install Boundary After Update]

4 LM.05 RIG AREA Surveying work [Install Boundary After Update]

2) Tests, samples, examination, inpection


Quantity Completed Cumulative Total Qty required
Sr. No. Construction area no. Construction area name Tests and samples (Field Test)
today Completed Qty in BOQ

3) Planned work for next day


Planned Quantity Planned Total Qty required
Sr. No. Construction area no. Construction area name Work in progress, Performance issues, etc.
next day Cumulative Qty in BOQ
1 LM.08 GENERAL AREA Manual dewatering ZonA,ZonB

2 LM.01 CUTTING PIT 1 Surveying work [Install Boundary After Update]

3 LM.02 CUTTING PIT 2 Surveying work [Install Boundary After Update]

4 LM.05 RIG AREA Surveying work [Install Boundary After Update]

4) Manpower and Manhour for this area


Manpower Manhours
Sr. No. Worker/Job Categories Remarks
(headcount) consumed
Geotechnical Engieer 1 8

1 survey engineer 1 8

2 3 Labour 4 8

3 PTW Holder 1 8

4 Forman 1 8

5) Machinery & equipment for this area

Sr. No. Description of equipment Number of units/equipment Hours Remarks

1 Dume Track 0 0

3 excavator 0 0

4 shovel 0 0

5 Grader 0 0
SITE PHOTOS

Photo-1 Photo-2

Manual dewatering ZonA,ZonB Manual dewatering ZonA


LM.08 GENERAL AREA LM.08

Photo-3 Photo-4
Manual dewatering ZonA,ZonB Manual dewatering ZonA

LM.08 LM.08
GENERAL AREA

Photo-6 Photo-7

Manual dewatering ZonA,ZonB Manual dewatering ZonA


LM.08 GENERAL AREA LM.08

` Photo-9 Photo-10
Surveying work [Install Boundary After Update] Surveying work [Install Boundary
LM.05 RIG AREA LM.05

Photo-12 Photo-13
Surveying work [Install Boundary After Update] TBT

LM.05 LM.08
RIG AREA

Photo-15 Photo-16

XXXXXX XXXXXX
DSx-GF/BF-XX DSx-GF/BF-XX

` Photo-18 Photo-19
XXXXXX XXXXXX
DSx-GF/BF-XX DSx-GF/BF-XX
Photo-2

Manual dewatering ZonA,ZonB


GENERAL AREA

Photo-4 Photo-5
Manual dewatering ZonA,ZonB Manual dewatering ZonA,ZonB

LM.08
GENERAL AREA GENERAL AREA

Photo-7 Photo-8

Manual dewatering ZonA,ZonB Manual dewatering ZonA,ZonB


GENERAL AREA LM.08 GENERAL AREA

Photo-10 Photo-11
Surveying work [Install Boundary After Update] Surveying work [Install Boundary After Update]
RIG AREA LM.05 RIG AREA

Photo-13 Photo-14
TBT XXXXXX

DSx-GF/BF-XX
GENERAL AREA

Photo-16 Photo-17

XXXXXX XXXXXX
DSx-GF/BF-XX

Photo-19 Photo-20
XXXXXX XXXXXX
DSx-GF/BF-XX
ZonB

AL AREA

ZonB
AL AREA
After Update]
AREA
HSSE Record
Sr. No. Activity No

1 New arrival orientation 0


2 Pre-job safety meetings 2
3 Pre-task JSA reviews conducted 1
4 New or revised JSA’s created 0
5 Weekly Safety Talk 0
6 Active Work Permits 3
7 Permit Audits Completed 0
8 Safety Stand Downs (Alerts/Corrections) 0
9 Weekly management walkthrough 0
10 Site induction 0
11 BBSO Cards submitted 3
12 Near Misses 0
13 Drills 0
14 Work Management System Assessment 0
15 Training 0

Incident Report
Date
Sr. No. Safety Mintue Brief Description Rmarks
018/01/2023
1 TBT and Genaral Hause keeping
All persons thay have safety induction
2 and full PPE
3 Tripping and falling
4
5
Area NO. construction area
LM.01 CUTTING PIT 1
LM.02 CUTTING PIT 2
LM.03 WATER PIT 1
LM.04 WATER PIT 2
LM.05 RIG AREA
LM.06 WATER SOURCE
LM.07 MUD PIT
LM.08 GENERAL AREA
LM.09 T-Wall
LM.10 Road