The document details the construction project of educational buildings in Riyadh, specifically the LABAN Secondary School for boys, managed by Al Bawani Co. It includes information on manpower, equipment, completed and ongoing activities, as well as materials delivered to the site. The report is dated February 28, 2017, and outlines various construction phases and their timelines.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views

s75

The document details the construction project of educational buildings in Riyadh, specifically the LABAN Secondary School for boys, managed by Al Bawani Co. It includes information on manpower, equipment, completed and ongoing activities, as well as materials delivered to the site. The report is dated February 28, 2017, and outlines various construction phases and their timelines.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.

RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name Khatib & Alami Data Date 28-Feb-17
To the Engineer Report no. S75/650
School Name LABAN (2-2) SECONDARY SCHOOL- BOYS School Code S75
Temperature Max : 23°C Min : 8°C Site Hand-Over Day 2-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low

Contractor's Manpower (including Subcontractors)* Plant/Equipment*

Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 0 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 0
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 0 Mobile Crane 0
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Paint labor 0 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 0
Site Engineer 1 labor 10 Welding Machine 0
General Guard Fork Lift
Safety/ HSE 1 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Levelling Machine 0
Total station 0
Container 0
Water Tank 1 As per attached New
Portacabin 3 As per attached New
Temporary Genset 0

Sub Total/Main 15 11 0

Sub-contractors

Sub Total/Subcon 0 0 0

Grand Total 15 11 0

Activities and Tasks*


COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building - GF 14-Feb-15 24-Feb-15
Multi-purpose hall 9-Jan-16 30-Jun-16
Canteen 21-Apr-16 30-Jun-16
Guard House 4-Jan-16 30-Jun-16
Gate Work 21-Apr-16 30-Jun-16
Site layout 19-Nov-15 10-Apr-16
Earth Works Main Building - GF 27-Sep-15 10-Oct-15
Multi-purpose hall 15-May-16 15-May-16
Canteen 18-Jul-16 18-Jul-16
Guard House 21-May-16 30-Jun-16
Gate Work 30-Oct-16 30-Oct-16
Site layout 10-Nov-15 30-Jun-16
Sub Structure Main Building - GF 8-Mar-15 30-Jun-16
Multi-purpose hall 6-Mar-16 3-Jul-16
Canteen 16-Feb-16 21-Jul-16
Guard House 16-Feb-16 30-Jun-16
Gate Work 19-Jun-16 13-Aug-16
Boundary Wall 8-Dec-15 30-Jun-16
Backfilling Main Building - GF 27-Jun-15 10-Oct-15
Multi-purpose hall 14-May-16 30-Jun-16
Canteen 13-Jul-16 17-Jul-16
Guard House 24-Apr-16 30-Jun-16
Gate Work 19-Aug-16 3-Nov-16
Site layout 19-May-16 30-Jun-16
Slab On Grade Main Building - GF 20-Sep-15 30-Jun-16
Multi-purpose hall 22-Jun-16 9-Jul-16
Canteen 20-Jul-16 21-Jul-16
Guard House 18-May-16 30-Jun-16
Gate Work 31-Oct-16 31-Oct-16
Water Proofing Main Building - GF 20-May-15 30-Jun-16
Main Building - RF 8-May-16 10-Jul-16
Multi-purpose hall 17-May-16 3-Dec-16
Canteen 11-Jul-16 23-Nov-16
Guard House 31-Mar-16 13-Dec-16
Gate Work 9-Aug-16 23-Nov-16
Site layout 3-Jan-16 30-Jun-16
Water Tank 28-Aug-16 18-Sep-16
Precast Main Building - GF 5-Jul-15 30-Jun-16
Main Building - FF 5-Jul-15 30-Jun-16
Main Building - SF 5-Jul-15 30-Jun-16
Main Building - RF 21-Nov-15 30-Jun-16
Multi-purpose hall 21-May-16 24-Jul-16
Canteen 2-May-16 30-Jul-16
Guard House 12-May-16 30-Jun-16
Gate Work 27-Aug-16 5-Sep-16
Site layout 27-Jun-16 25-Dec-16
Concrete Works Main Building - GF 11-Oct-15 30-Jun-16
Main Building - FF 11-Oct-15 30-Jun-16

Page 1 of 3
Main Building - SF 8-Nov-15 30-Jun-16
Main Building - RF 3-Mar-16 11-May-16
Multi-purpose hall 29-May-16 19-Jul-16
Canteen 27-Jul-16 31-Jul-16
Guard House 2-Apr-16 30-Jun-16
Gate Work 17-Sep-16 2-Oct-16
Site layout 6-Dec-15 31-Oct-16
Plaster Main Building - GF 10-Dec-15 30-Jun-16
Main Building - FF 11-Nov-15 30-Jun-16
Main Building - SF 12-Dec-15 30-Jun-16
Water Tank 20-Oct-16 25-Oct-16
Mechanical Main Building - GF 31-Oct-15 10-Jul-16
Main Building - FF 10-Sep-15 28-Jul-16
Main Building - SF 21-Sep-15 10-Jan-17
Main Building - RF 27-Dec-15 28-Jul-16
Multi-purpose hall 3-Oct-16 16-Jan-17
Canteen 20-Jul-16 9-Jan-17
Guard House 25-Sep-16 11-Jan-17
Gate Work 25-Oct-16 9-Jan-17
Site layout 8-Jun-16 7-Jan-17
Elevator Main Building - RF 8-Mar-16 11-Jul-16
Electrical Main Building - GF 14-Oct-15 30-Jun-16
Main Building - FF 21-Nov-15 9-Jul-16
Main Building - SF 25-Nov-15 30-Jun-16
Main Building - RF 20-Feb-16 31-Jul-16
Multi-purpose hall 15-Nov-16 15-Jan-17
Canteen 25-Oct-16 5-Jan-17
Guard House 15-Oct-16 10-Jan-17
Gate Work 4-Nov-16 9-Jan-17
Site layout 20-Jul-16 25-Dec-16
Doors Main Building - GF 11-May-16 25-Oct-16
Main Building - FF 11-May-16 26-Oct-16
Main Building - SF 11-May-16 26-Oct-16
Main Building - RF 17-Jul-16 2-Aug-16
Multi-purpose hall 1-Nov-16 8-Jan-17
Canteen 20-Sep-16 5-Jan-17
Guard House 5-Oct-16 12-Oct-16
Gate Work 2-Jan-17 8-Jan-17
Windows Main Building - GF 9-Feb-16 4-Jul-16
Main Building - FF 9-Feb-16 2-Jul-16
Main Building - SF 6-Feb-16 25-Jun-16
Main Building - RF 16-Apr-16 16-Aug-16
Multi-purpose hall 6-Dec-16 8-Dec-16
Canteen 15-Sep-16 22-Nov-16
Guard House 29-Oct-16 30-Oct-16
Gate Work 24-Nov-16 5-Jan-17
Skylights Main Building - RF 25-May-16 10-Jul-16
Space Frame Multi-purpose hall 24-Aug-16 20-Oct-16
Site layout 1-Sep-16 17-Dec-16
Tiling Main Building - GF 27-Mar-16 12-Jul-16
Main Building - FF 25-Apr-16 24-Jul-16
Main Building - SF 3-May-16 5-Jul-16
Main Building - RF 30-May-16 24-Jul-16
Multi-purpose hall 26-Oct-16 29-Dec-17
Canteen 4-Oct-16 5-Jan-17
Guard House 1-Oct-16 7-Jan-17
Gate Work 21-Nov-16 4-Jan-17
Site layout 5-Jan-17 10-Jan-17
Ceiling Main Building - GF 4-Feb-16 30-Jun-16
Main Building - FF 4-Feb-16 9-Jul-16
Main Building - SF 4-Feb-16 4-Jul-16
Multi-purpose hall 26-Dec-16 5-Jan-17
Paint Main Building - GF 21-Oct-15 5-Jan-17
Main Building - FF 9-Feb-16 5-Jan-17
Main Building - SF 6-Feb-16 5-Jan-17
Main Building - RF 27-Jul-16 20-Oct-16
Multi-purpose hall 15-Jun-16 8-Jan-17
Canteen 26-Oct-16 26-Nov-16
Guard House 22-Dec-16 8-Jan-17
Gate Work 20-Dec-16 25-Dec-16
Handrail Main Building - GF 1-Jun-16 11-Jul-16
Main Building - FF 12-Jun-16 30-Jun-16
Main Building - SF 12-Jun-16 30-Jun-16
Main Building - RF 12-Jun-16 10-Jul-16
Multi-purpose hall 5-Jan-17 7-Jan-17
Exposed Aggr. Main Building - RF 7-Dec-15 10-Jul-16
Multi-purpose hall 15-Aug-16 1-Sep-16
Canteen 17-Sep-16 23-Nov-16
Guard House 5-Oct-16 20-Oct-16
Gate Work 7-Nov-16 1-Dec-16
Site layout 27-Jul-16 4-Jan-17
Site Layout Site layout 5-Jan-17 11-Jan-17
Landscape Site layout 16-Nov-16 25-Dec-16
Furniture Main Building - GF 13-Jun-16 5-Jan-17
Main Building - FF 5-Jul-16 5-Jan-17
Main Building - SF 4-Jul-16 11-Jan-17
Multi-purpose hall 12-Dec-16 16-Jan-17
Canteen 25-Dec-16 5-Jan-17

Page 2 of 3
Guard House 22-Dec-16 25-Dec-16
Gate Work 25-Dec-16 5-Jan-17
Site layout 22-Dec-16 25-Dec-16
No R_Type Of Work Main Building - GF 4-Jun-16 8-Jan-17
Main Building - FF 15-Jun-16 8-Jan-17
Main Building - SF 15-Jun-16 5-Jan-17
Main Building - RF 19-Jun-16 30-Jul-16
Multi-purpose hall 24-Aug-16 16-Jan-17
Canteen 5-Jan-17 5-Jan-17
Guard House 21-Nov-16 9-Jan-17
Gate Work 5-Jan-17 8-Jan-17
Site layout 16-Nov-16 8-Jan-17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: Samy Name: Abdul Samad
Signature: Signature:
Date: 28-Feb-17 Date: 28-Feb-17

* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).