s75
s75
RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name Khatib & Alami Data Date 28-Feb-17
To the Engineer Report no. S75/650
School Name LABAN (2-2) SECONDARY SCHOOL- BOYS School Code S75
Temperature Max : 23°C Min : 8°C Site Hand-Over Day 2-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 0 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 0
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 0 Mobile Crane 0
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Paint labor 0 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 0
Site Engineer 1 labor 10 Welding Machine 0
General Guard Fork Lift
Safety/ HSE 1 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Levelling Machine 0
Total station 0
Container 0
Water Tank 1 As per attached New
Portacabin 3 As per attached New
Temporary Genset 0
Sub Total/Main 15 11 0
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 15 11 0
Page 1 of 3
Main Building - SF 8-Nov-15 30-Jun-16
Main Building - RF 3-Mar-16 11-May-16
Multi-purpose hall 29-May-16 19-Jul-16
Canteen 27-Jul-16 31-Jul-16
Guard House 2-Apr-16 30-Jun-16
Gate Work 17-Sep-16 2-Oct-16
Site layout 6-Dec-15 31-Oct-16
Plaster Main Building - GF 10-Dec-15 30-Jun-16
Main Building - FF 11-Nov-15 30-Jun-16
Main Building - SF 12-Dec-15 30-Jun-16
Water Tank 20-Oct-16 25-Oct-16
Mechanical Main Building - GF 31-Oct-15 10-Jul-16
Main Building - FF 10-Sep-15 28-Jul-16
Main Building - SF 21-Sep-15 10-Jan-17
Main Building - RF 27-Dec-15 28-Jul-16
Multi-purpose hall 3-Oct-16 16-Jan-17
Canteen 20-Jul-16 9-Jan-17
Guard House 25-Sep-16 11-Jan-17
Gate Work 25-Oct-16 9-Jan-17
Site layout 8-Jun-16 7-Jan-17
Elevator Main Building - RF 8-Mar-16 11-Jul-16
Electrical Main Building - GF 14-Oct-15 30-Jun-16
Main Building - FF 21-Nov-15 9-Jul-16
Main Building - SF 25-Nov-15 30-Jun-16
Main Building - RF 20-Feb-16 31-Jul-16
Multi-purpose hall 15-Nov-16 15-Jan-17
Canteen 25-Oct-16 5-Jan-17
Guard House 15-Oct-16 10-Jan-17
Gate Work 4-Nov-16 9-Jan-17
Site layout 20-Jul-16 25-Dec-16
Doors Main Building - GF 11-May-16 25-Oct-16
Main Building - FF 11-May-16 26-Oct-16
Main Building - SF 11-May-16 26-Oct-16
Main Building - RF 17-Jul-16 2-Aug-16
Multi-purpose hall 1-Nov-16 8-Jan-17
Canteen 20-Sep-16 5-Jan-17
Guard House 5-Oct-16 12-Oct-16
Gate Work 2-Jan-17 8-Jan-17
Windows Main Building - GF 9-Feb-16 4-Jul-16
Main Building - FF 9-Feb-16 2-Jul-16
Main Building - SF 6-Feb-16 25-Jun-16
Main Building - RF 16-Apr-16 16-Aug-16
Multi-purpose hall 6-Dec-16 8-Dec-16
Canteen 15-Sep-16 22-Nov-16
Guard House 29-Oct-16 30-Oct-16
Gate Work 24-Nov-16 5-Jan-17
Skylights Main Building - RF 25-May-16 10-Jul-16
Space Frame Multi-purpose hall 24-Aug-16 20-Oct-16
Site layout 1-Sep-16 17-Dec-16
Tiling Main Building - GF 27-Mar-16 12-Jul-16
Main Building - FF 25-Apr-16 24-Jul-16
Main Building - SF 3-May-16 5-Jul-16
Main Building - RF 30-May-16 24-Jul-16
Multi-purpose hall 26-Oct-16 29-Dec-17
Canteen 4-Oct-16 5-Jan-17
Guard House 1-Oct-16 7-Jan-17
Gate Work 21-Nov-16 4-Jan-17
Site layout 5-Jan-17 10-Jan-17
Ceiling Main Building - GF 4-Feb-16 30-Jun-16
Main Building - FF 4-Feb-16 9-Jul-16
Main Building - SF 4-Feb-16 4-Jul-16
Multi-purpose hall 26-Dec-16 5-Jan-17
Paint Main Building - GF 21-Oct-15 5-Jan-17
Main Building - FF 9-Feb-16 5-Jan-17
Main Building - SF 6-Feb-16 5-Jan-17
Main Building - RF 27-Jul-16 20-Oct-16
Multi-purpose hall 15-Jun-16 8-Jan-17
Canteen 26-Oct-16 26-Nov-16
Guard House 22-Dec-16 8-Jan-17
Gate Work 20-Dec-16 25-Dec-16
Handrail Main Building - GF 1-Jun-16 11-Jul-16
Main Building - FF 12-Jun-16 30-Jun-16
Main Building - SF 12-Jun-16 30-Jun-16
Main Building - RF 12-Jun-16 10-Jul-16
Multi-purpose hall 5-Jan-17 7-Jan-17
Exposed Aggr. Main Building - RF 7-Dec-15 10-Jul-16
Multi-purpose hall 15-Aug-16 1-Sep-16
Canteen 17-Sep-16 23-Nov-16
Guard House 5-Oct-16 20-Oct-16
Gate Work 7-Nov-16 1-Dec-16
Site layout 27-Jul-16 4-Jan-17
Site Layout Site layout 5-Jan-17 11-Jan-17
Landscape Site layout 16-Nov-16 25-Dec-16
Furniture Main Building - GF 13-Jun-16 5-Jan-17
Main Building - FF 5-Jul-16 5-Jan-17
Main Building - SF 4-Jul-16 11-Jan-17
Multi-purpose hall 12-Dec-16 16-Jan-17
Canteen 25-Dec-16 5-Jan-17
Page 2 of 3
Guard House 22-Dec-16 25-Dec-16
Gate Work 25-Dec-16 5-Jan-17
Site layout 22-Dec-16 25-Dec-16
No R_Type Of Work Main Building - GF 4-Jun-16 8-Jan-17
Main Building - FF 15-Jun-16 8-Jan-17
Main Building - SF 15-Jun-16 5-Jan-17
Main Building - RF 19-Jun-16 30-Jul-16
Multi-purpose hall 24-Aug-16 16-Jan-17
Canteen 5-Jan-17 5-Jan-17
Guard House 21-Nov-16 9-Jan-17
Gate Work 5-Jan-17 8-Jan-17
Site layout 16-Nov-16 8-Jan-17
* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
* Attach details on separate sheets as required.
Page 3 of 3