RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name Khatib & Alami Data Date 28-Feb-17
To the Engineer Report no. S13/637
School Name ABDULLAH IBNU-A'MER ELEMENTARY SCHOOL- BOYS School Code S13
Temperature Max : 23°C Min : 8°C Site Hand-Over Day 17-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 3 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 0
Precast Manager 1 Carpenter 2 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 3 Portable Generator 0
QA/QC 1 E/M 20 Mobile Crane 0
Tech. Support 1 Mason 7 Tower Crane 0
Purch & Procurement 1 Paint labor 0 Pick up 0
Set. Manager 1 Plastering man 5 Water Tanker 1 As per attached New
Site Engineer 1 labor 15 Welding Machine 0
General Guard Fork Lift
Safety/ HSE 1 2 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 2 As per attached New
Surveyor & Survayor Assistant 1 Bulldozer 0
Levelling Machine 0
Total station 0
Container 1 As per attached New
Water Tank 3 As per attached New
Portacabin 3 As per attached New
Temporary Genset 0
Sub Total/Main 15 57 3
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 15 57 3
Page 1 of 2
Main Building - FF Hollow Metal Frames 90.00% 28-Nov-16
Main Building - SF Hollow Metal Frames 90.00% 28-Nov-16
Tiling Main Building - GF Porcelain Tiles 40.00% 21-Dec-16
Main Building - FF Porcelain Tiles 80.00% 9-Nov-16
Main Building - SF Porcelain Tiles 80.00% 21-Dec-16
Ceiling Main Building - GF Solid Gypsum Ceiling 75.00% 21-Dec-16
Main Building - FF Solid Gypsum Ceiling 90.00% 9-Nov-16
Main Building - SF Solid Gypsum Ceiling 90.00% 21-Dec-16
Paint Main Building - GF Paint preparation 95.00% 21-Dec-16
Paint (1ST Coat) 95.00% 30-Jan-17
Main Building - FF Paint preparation 95.00% 26-Nov-16
Paint (1ST Coat) 95.00% 31-Jan-17
Main Building - SF Paint preparation 95.00% 21-Dec-16
Paint (1ST Coat) 95.00% 1-Feb-17
Main Building - RF Paint preparation For External 85.00% 2-Feb-17
No R_Type Of Work Main Building - GF Porcelain Skirting 40.00% 21-Dec-16
Main Building - FF Porcelain Skirting 80.00% 14-Nov-16
Main Building - SF Porcelain Skirting 80.00% 21-Dec-16
Electric Room Epoxy Flooring 50.00% 7-Feb-17
* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
* Attach details on separate sheets as required.