The document outlines the construction progress report for the Abdullah Ibnu-A'mer Elementary School project in Riyadh, managed by Al Bawani Co. and consulted by Khatib & Alami. It includes details on manpower, equipment, completed and ongoing activities, as well as materials delivered to the site as of February 28, 2017. The report highlights various construction tasks with their respective completion percentages and provides a comprehensive overview of the project's status.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

s13

The document outlines the construction progress report for the Abdullah Ibnu-A'mer Elementary School project in Riyadh, managed by Al Bawani Co. and consulted by Khatib & Alami. It includes details on manpower, equipment, completed and ongoing activities, as well as materials delivered to the site as of February 28, 2017. The report highlights various construction tasks with their respective completion percentages and provides a comprehensive overview of the project's status.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.

RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name Khatib & Alami Data Date 28-Feb-17
To the Engineer Report no. S13/637
School Name ABDULLAH IBNU-A'MER ELEMENTARY SCHOOL- BOYS School Code S13
Temperature Max : 23°C Min : 8°C Site Hand-Over Day 17-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low

Contractor's Manpower (including Subcontractors)* Plant/Equipment*

Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 3 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 0
Precast Manager 1 Carpenter 2 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 3 Portable Generator 0
QA/QC 1 E/M 20 Mobile Crane 0
Tech. Support 1 Mason 7 Tower Crane 0
Purch & Procurement 1 Paint labor 0 Pick up 0
Set. Manager 1 Plastering man 5 Water Tanker 1 As per attached New
Site Engineer 1 labor 15 Welding Machine 0
General Guard Fork Lift
Safety/ HSE 1 2 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 2 As per attached New
Surveyor & Survayor Assistant 1 Bulldozer 0
Levelling Machine 0
Total station 0
Container 1 As per attached New
Water Tank 3 As per attached New
Portacabin 3 As per attached New
Temporary Genset 0

Sub Total/Main 15 57 3

Sub-contractors

Sub Total/Subcon 0 0 0

Grand Total 15 57 3

Activities and Tasks*


COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building - GF 8-Apr-15 18-Apr-15 Sub Structure Boundary Wall Bituminous Waterproofing for Boundary Wall 50.00% 11-Jan-17
Multi-purpose hall 13-Jul-16 18-Aug-16 Water Proofing Main Building - RF Foam Concrete 80.00% 4-Jan-17
Electric Room 2-Jul-16 19-Jul-16 Precast Multi-purpose hall Install Precast Concrete Panels 90.00% 15-Jan-17
Canteen 7-Jun-16 24-Jul-16 Boundary Wall Precast Concret Columns for Boundary Wall 80.00% 21-Dec-16
Guard House 28-May-16 24-Jul-16 Precast Concret Panels for Boundary Wall 60.00% 24-Dec-16
Gate Work 25-Jul-16 2-Nov-16 Plaster Main Building - GF Cement Internal Plastering 95.00% 21-Nov-16
Site layout 17-Mar-15 24-Jul-16 Main Building - FF Cement Internal Plastering 90.00% 22-Aug-16
Water Tank 29-May-16 24-Jul-16 Main Building - SF Cement Internal Plastering 90.00% 15-Oct-16
Boundary Wall 5-Jun-16 30-Jul-16 Mechanical Main Building - GF Drainage Pipes for Toilets & Testing 70.00% 15-Nov-16
Earth Works Site layout 1-Mar-15 24-Jul-16 Floor Drain & Clean Out & Testing 80.00% 15-Nov-16
Sub Structure Main Building - GF 26-Apr-15 23-Jun-16 Fire Hose Cabinates 35.00% 20-Nov-16
Multi-purpose hall 21-Jul-16 17-Nov-16 HVAC Duct & Testing 85.00% 20-Jul-16
Electric Room 25-Jul-16 28-Dec-16 Main Building - FF Fire Extingushers 40.00% 6-Nov-16
Canteen 25-Jul-16 26-Nov-16 Drainage Pipes for Toilets & Testing 50.00% 25-Sep-16
Guard House 25-Jul-16 26-Nov-16 Fire Hose Cabinates 45.00% 31-Oct-16
Gate Work 30-Jul-16 9-Feb-17 HVAC Duct & Testing 80.00% 23-Sep-16
Water Tank 25-Jul-16 10-Oct-16 Ventilation Fans & Testing 20.00% 31-Oct-16
Backfilling Main Building - GF 3-Jan-16 22-Jun-16 Split Units & Testing 40.00% 15-Oct-16
Multi-purpose hall 3-Sep-16 22-Nov-16 Floor Drain & Clean Out & Testing 80.00% 22-Sep-16
Electric Room 23-Aug-16 31-Dec-16 Main Building - SF Split Units & Testing 20.00% 15-Oct-16
Canteen 8-Sep-16 28-Nov-16 HVAC Duct & Testing 45.00% 19-Sep-16
Guard House 28-Aug-16 28-Nov-16 Drainage Pipes for Toilets & Testing 60.00% 20-Sep-16
Gate Work 3-Sep-16 7-Feb-17 Floor Drain & Clean Out & Testing 80.00% 22-Sep-16
Boundary Wall 4-Jan-17 11-Feb-17 Fire Extingushers 40.00% 7-Nov-16
Slab On Grade Main Building - GF 22-Jun-16 9-Jul-16 Fire Hose Cabinates 45.00% 1-Nov-16
Multi-purpose hall 26-Sep-16 7-Nov-16 Main Building - RF Roof Drain & Testing 80.00% 22-Sep-16
Electric Room 15-Sep-16 1-Jan-17 Multi-purpose hall Drainage Pipes for Toilets 60.00% 25-Oct-16
Canteen 5-Oct-16 8-Dec-16 Canteen Drainage Pipes for Toilets 50.00% 26-Oct-16
Guard House 20-Sep-16 8-Dec-16 Guard House Drainage Pipes for Toilets 50.00% 26-Oct-16
Gate Work 25-Sep-16 10-Jan-17 Electrical Main Building - GF Grounding System , UPS &Low-Voltage Electrical Power Conductors
80.00% and20-Sep-16
Cables
Precast Main Building - GF 24-Jan-16 29-Mar-16 Lighting System Second Fix (Wires ) 80.00% 3-Sep-16
Main Building - FF 10-Feb-16 2-Apr-16 Wiring Devices Second Fix (Wires ) 80.00% 19-Oct-16
Main Building - SF 10-Feb-16 9-Apr-16 Fire Alarm Second Fix (Wires ) 80.00% 19-Oct-16
Main Building - RF 15-Jun-16 14-Jul-16 Data Communications System Second Fix (Wires ) 80.00% 19-Oct-16
Electric Room 22-Sep-16 30-Jan-17 IP Telephone System Second Fix (Wires ) 80.00% 19-Oct-16
Canteen 16-Oct-16 1-Feb-17 Main Building - FF Lighting System Second Fix (Wires ) 80.00% 21-Sep-16
Guard House 1-Oct-16 22-Feb-17 Wiring Devices Second Fix (Wires ) 80.00% 10-Oct-16
Concrete Works Water Tank 28-Jul-16 12-Feb-17 Fire Alarm Second Fix (Wires ) 80.00% 1-Oct-16
Block Work Main Building - GF 24-Jul-16 8-Aug-16 Data Communications System Second Fix (Wires ) 85.00% 1-Oct-16
Main Building - FF 13-Jul-16 20-Sep-16 IP Telephone System Second Fix (Wires ) 85.00% 1-Oct-16
Main Building - SF 13-Jul-16 30-Oct-16 Grounding System , UPS &Low-Voltage Electrical Power Conductors
80.00% and21-Sep-16
Cables
Exposed Aggr. Main Building - RF 15-Jun-16 4-Jul-16 Main Building - SF Lighting System Second Fix (Wires ) 80.00% 8-Oct-16
No R_Type Of Work Collective Tank 9-Aug-16 23-Nov-16 Wiring Devices Second Fix (Wires ) 80.00% 22-Sep-16
Septic Tank 28-Jul-16 7-Sep-16 Data Communications System Second Fix (Wires ) 80.00% 10-Oct-16
IP Telephone System Second Fix (Wires ) 80.00% 10-Oct-16
Fire Alarm Second Fix (Wires ) 80.00% 10-Oct-16
Grounding System , UPS &Low-Voltage Electrical Power Conductors
80.00% and14-Sep-16
Cables
Doors Main Building - GF Hollow Metal Frames 90.00% 28-Nov-16

Page 1 of 2
Main Building - FF Hollow Metal Frames 90.00% 28-Nov-16
Main Building - SF Hollow Metal Frames 90.00% 28-Nov-16
Tiling Main Building - GF Porcelain Tiles 40.00% 21-Dec-16
Main Building - FF Porcelain Tiles 80.00% 9-Nov-16
Main Building - SF Porcelain Tiles 80.00% 21-Dec-16
Ceiling Main Building - GF Solid Gypsum Ceiling 75.00% 21-Dec-16
Main Building - FF Solid Gypsum Ceiling 90.00% 9-Nov-16
Main Building - SF Solid Gypsum Ceiling 90.00% 21-Dec-16
Paint Main Building - GF Paint preparation 95.00% 21-Dec-16
Paint (1ST Coat) 95.00% 30-Jan-17
Main Building - FF Paint preparation 95.00% 26-Nov-16
Paint (1ST Coat) 95.00% 31-Jan-17
Main Building - SF Paint preparation 95.00% 21-Dec-16
Paint (1ST Coat) 95.00% 1-Feb-17
Main Building - RF Paint preparation For External 85.00% 2-Feb-17
No R_Type Of Work Main Building - GF Porcelain Skirting 40.00% 21-Dec-16
Main Building - FF Porcelain Skirting 80.00% 14-Nov-16
Main Building - SF Porcelain Skirting 80.00% 21-Dec-16
Electric Room Epoxy Flooring 50.00% 7-Feb-17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: Mohammad Shams Eldin Name: Ziad Al-Oudat
Signature: Signature:
Date: 28-Feb-17 Date: 28-Feb-17

* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
* Attach details on separate sheets as required.

Page 2 of 2