PMP-Estimate Activity Resources_note
PMP-Estimate Activity Resources_note
This is a process where you look at each individual activity and determine what and
how many resources are needed to accomplish that activity. Resources are not just
people, but also include equipment, machines, and different types of supplies
needed to finish the activity.
This process lists all the resources, both physical and staff, and how many of those
resources are needed.
This particular process focuses on each activity within the schedule to calculate the
resource requirements. Another factor that will need to be considered along with the
hours’ work effort required, is the availability of the resources.
All of the above will combine and result in the project schedule which is developed in
a later process within the time management group.
There is a fundamental formula that ties together the duration of an activity against
the amount of work effort required, and the resources needed to complete that work
within the estimate activity resources process:
Activity duration = work effort/human units. For typical activities the duration will be
measured in days, the work effort in hours, and the number of people required as a
decimal fraction.
Although the Estimate Activity Resources process forms part of
developing the project time schedule, this process is normally
undertaken in parallel with the process ‘estimate costs’ (which is a
process within the cost management process group).
The documents you are most likely to use in this process include:
Risk register. This would list all the identified project risks, as well as
their impacts and response. Risk responses can lead to adding
reserve time to activities.
Cost estimates. These will be the individual costs that are assigned
to each activity. Knowing the cost of an activity will be critical to
determining what resources should be used on the project.
If you need help to get the PMP Exam results you deserve, then CLICK
HERE