Method Statement for Installation of 33KV Power Transformer
Method Statement for Installation of 33KV Power Transformer
ShareSave
Because of the high level of risk involved with this delicate activity, a
thorough evaluation needs to be carried out by the site engineer by
establishing a statement of methodology or a method statement.
As a professional quality engineer, it is essential to create a method
framework for such a task. It is your responsibility to determine the
right sequence of work to follow. The engineer’s expertise comes into
play when preparing such a vital project document.
The delicacy and importance of the work mean the engineer has to
make sure that the method statement is well crafted to ensure it
addresses all the required procedures, methods and safety
requirements.
1. Title
Method Statement for Installation of 33KV Power Transformer
4. Materials
• 33Kv Power Transformer
5. Manpower
• Project Manager
• Construction Manager
• Project Engineer
• Site Engineer
• Foreman
• Charge-hand
• Laborers
7. Methodology
7.1 Installation preliminary checks
7.1.1 Do a thorough examination of the installation area for its dryness
and cleanliness.
7.1.2. Check if the position of the base frame of the transformer is well
fitted. Ensure it is leveled and rightly grouted. As a precautionary
measure, if the leveling is unsatisfactory, get the agency responsible
for carrying out the correction.
Read also: Method Statement for Installation of Cable Tray, Trunking &
Accessories
7.1.4. Ensure the transformer can fit through the door of the
transformer room.
7.10. Inspect the transportation gear and lifting tools to ensure they
meet with the required standard regarding load-bearing capacity and
construction.
7.2 Installation
7.2.1 According to the manufacturer’s recommendation and direction
to install the system.
7.3.7 Inspect the routing of the floor cutout cables to ensure they
follow the exact drawings and specifications. Do this before the
installation of the 33KV transformer.
7.3.8 Make sure the transformer room is dirt free and dust free.
7.3.9 Ensure the following tools are available and ready by the
commencement of work;
• Hexagonal screwdriver insert (minimum length 140mm) for hexagon
socket head bolt 10mm.
• Water level
• Torque screwdriver T x 25
• Extension
• Lifting truck
• Socket spanner inserts size 17 and 18 lengths 80mm
• Torque wrench 20-50Nm
• Reinforcing bars, roller crowbars
• Ratchet, reconnectable
• Transport rollers, tubes.
7.3.10 Use the packing list and delivery note to check if the delivery is
complete. Also, check for nuts, bolts, washers and so on.
9. Safety
9.1. Use a trailer to transport the transformer to the site carefully.
Ensure all vehicles and other machinery use will not be more than ten
years old. Ensure a contractor logistic department personnel carries a
thorough check on the manufacture dates. Also, traffic regulations and
the site speed limit of 15km/h should be followed.
9.2. Subcon inspects all on-site loading and offloading regarding the
Transformer. Subcon will ensure the lifting team follows the right
procedure, utilize all the right tools and meet with safety standards. All
loading and offloading will be controlled and supervised by the
Maincon lifting supervisor.
9.4. Subcon will make sure all personnel on the ground are those with
the proper safety clearance levels. Each personnel will be briefed on
on-site safety rules, emergency procedures, and other safety
measures.
10. Environmental controls
10.1. Land contamination
a. Dispose all oil-contaminated soil from the point of spillage in
accordance with Construction Environmental Management Plan
standards.
10.2. Dust
a. Sprinkle water around the working areas when needed.