Method Statement for Precast Boundary Wall Works
Method Statement for Precast Boundary Wall Works
SharePin It
We have few projects that boundary wall is included. The boundary
wall we installed was precast, the advantage is it is easy and fast to
erect.
1. Title
Method Statement for Precast Boundary Wall Works
3. Work procedure
1. General
Erection process shall conform to the requirements of project
specification and or relevant standard.
Precast concrete element will be transported to site after the
approval by in-house QA/QC staff.
On site survey shall be carried out for all site dimensions,
axes locations, and to meet project requirements.
2. Preparation of Civil Works
Earthwork shall be carried out as per required level.
Compaction, testing and blinding shall be done before
starting erection.
Main grid line and benchmark will be marked by surveyor.
Site access road for the movement and parking of mobile
cranes and trailers will be ensured at site before starting of
erection.
Backfilling after completion of erection of boundary wall shall
be made after installation of precast elements.
Stage 1 – After erecting of footing and columns.
Stage 2 – After erecting of first boundary wall panel.
3. Erection of Footing
Footings for columns shall be transported on the bed
trailers where they are properly tied with chains and
latches.
Lifting anchors and sleeves openings are provided in the
footings in proper locations as per design requirements
for safe and easy handling and erecting purposes.
Footing shall be received at site painted with one primer
coat of water proofing bitumen followed by two finishing
coats of water proofing bitumen.
Precast Footing
4.
Footing shall either be installed in its location at site using
mobile crane of adequate capacity.
Individual markings for footings shall be made by the
surveyor.
Blinding shall be cleaned and the water proofing bitumen
shall be applied before erecting any precast footing.
Footing shall be leveled prior to receive column and four line
(axis of column) to be marked on the foundation to specify
the locations of the column face.
Backfilling around the footing shall be done as per approved
method statement of backfilling works.
5. Erection of Precast Column
Column shall be provided with 1 anchor on hole on top for
handling and for erection purposes.
Precast Column
Column shall be transported on flat-bed trailers secured to
the trailer with the help of latching chains or belt.
Precast column shall be unloaded by mobile crane of
adequate capacity.
Then column shall be tilted with crane and lifted vertically in
order to bring it to its exact location onto the footing.
Column shall be aligned at tail end to match the axis.
purposes.
1. All works shall comply with safety procedure or instruction set out
in project safety plan and Municipality rules and regulations.
2. Know the safe working load of the hoisting equipment and
hardware before use. Never exceed the Safe Working Load
(SWL).
3. Know the height and size of the precast element before rigging for
lifting.
4. Always inspect the rigging element prior to every use.
5. Never wrap the hoist line around the load.
6. Always use taglines with the precast element while lifting to keep
the load steady.
7. Always check the stability of the load before lifting.
8. Check for any over head power lines.
9. Make sure that the rigging elements are correct and safe to use
for the intended load.
10. Never use damaged slings, blocks, hooks for lifting, all damaged
lifting gears to be returned to the store for repair or replacement.
11. Basic PPE to worn by all staff and laborers.
12. Trained operator and banks man will be engaged to control or
operate heavy equipment machine.
5. Equipments and tools
1. Mobile crane
2. Flat trailers
3. Shovel and JCB for excavation
4. Plate compactors
5. Web sling
6. Grinders and drill machines
7. Hammers
8. Plastic chem for leveling
9. Total Station for survey
6. Materials and references