Microsoft Project Management
Microsoft Project Management
INTRODUCTION
This book provides information about basic project management and Microsoft
Project concepts. It then leads you to how you can create a plan, track its
progress, and communicate the results.
The more successful these phases are, the greater your chance of a successful
project.
If only you could foresee your project's future....In a way you can, if you
understand three factors that shape every project:
Time: The time to complete the project as reflected in your project schedule.
Money: The project budget, based on the cost of the resources, that is, the
people, equipment, and materials required to do the tasks.
Scope: The goals and tasks of the project and the work required to complete
them.
1
_____________________________________ Micro Soft Project Management Manual
This trio of time, money, and scope is the project triangle. Adjusting one of
these elements affects the other two. While all three elements are important,
typically one will have the most influence on your project.
Before considering the tasks of your project or the resources you need, first set
your strategy. Your project strategy helps you build the big picture of the
project, so you and other project stakeholders are very clear about where
you're headed.
This information helps you and others understand the project. It can also be
instrumental when you need to respond to changes that might occur in the
midst of the project.
As you build a project plan, Microsoft Project calculates and creates a working
schedule based on information you provide about the tasks to be done, the
people who work on them, the equipment and supplies used to accomplish
them, and the costs involved.
When building your project plan, you enter the following types of information:
Tasks
Duration
Task dependencies
Resources
Costs
2
_____________________________________ Micro Soft Project Management Manual
With this information, Microsoft Project can calculate your schedule, costs, and
resource work load.
Views and tables to display the exact information you want to review.
Filters and groups to focus on the information that needs your attention.
You enter actual progress on tasks, compare your actual information to your
original plan, and see how your resource work load is balanced. You can then
effectively head off potential problems.
When you've defined project goals and thought out the major phases of your
project, it's time to begin creating your plan.
First, you start a new project plan and then enter and organize the list of tasks
to be completed, along with each task's duration and any task dependencies.
Next, you add people, equipment, and materials and their costs to your plan,
and then assign these resources to tasks. With this resource and task
information, Microsoft Project creates a schedule. You can verify the schedule
and adjust it as necessary.
SET UP A PROJECT
The first steps in creating a schedule are starting a new project plan,
designating a project start or finish date, and entering general project
information.
When you've completed this, you will have a Microsoft Project plan containing
the project name and other key information, the project's start or finish date,
and the project calendar
3
_____________________________________ Micro Soft Project Management Manual
Now that you've created your new project plan, you're ready to fill it with
tasks. First, you list the steps needed to accomplish your project's goals. It's
easiest to start with the large chunks of work and then break down each chunk
into tasks with single deliverables. Add milestones. Finally, gather and enter
duration estimates.
After you enter task information, you create an outline to help organize the
tasks logically and see the project's structure. When you've completed this,
you'll have a task list organized into summary and detailed tasks.
After you create and outline your task list, it's time to address how the tasks
relate to each other and how they meet important dates. You can link your
tasks to show a task relationship, for example, specifying that one task will
start as another finishes. These links are called task dependencies. Along with
duration and other scheduling factors, task dependencies play a large role in
the way that Microsoft Project calculates the start and finish dates for tasks.
If the scheduling for a linked task changes, tasks linked to and from the task
are automatically rescheduled. You can refine task schedules using specific
date constraints and deadlines. Then, you will have a schedule for your project.
ASSIGN RESOURCES
Track the amount of work done by people and equipment assigned to tasks,
or monitor materials used in the completion of a task.
Schedule tasks with more flexibility.
Balance resource work loads between those with too little or too much work
assigned.
Track resource costs.
When you assign resources, the work schedule and resource availability are
figured into the scheduling equation.
When you've completed this, you will have added people, equipment, and
materials to your project, set up work schedules, and assigned resources to
tasks. If you use online team collaboration such as Microsoft Project Server,
you will have published assignments, to be accepted by team members.
ENTER COSTS
4
_____________________________________ Micro Soft Project Management Manual
Whether you need to account for the expenses on each task or the overall cost
of the project, entering rates for a resource's work on tasks or for fixed costs
for tasks enables you to see whether you are staying within budget.
You can enter per-use and overtime rates for resources, plan for raises, and
choose when costs are accrued. You can also review cost information in
different ways.
When you've completed this, you will have entered cost information for
resources and tasks. If you don't need to track costs in your project, click View
the schedule in the left pane to go on to the next lesson.
After entering the basic project data, review it. Will you meet your deadlines?
What are resources working on right now? How much of the budget has been
spent so far?
First, look at the big picture: the overall start and finish date and the critical
path. Then check the details. Display tasks and resources in views that suit
your needs.
When you can examine your project from different points of view, you can
pinpoint likely trouble spots and take the necessary action to resolve them
before they become big problems.
When you've completed this, you'll know how to review overall schedule
information, and manage views and fields to review pertinent details. If you
use Microsoft Project Server, you'll also know how to see Microsoft Project
Server information with either Microsoft Project Web Access or from within
Microsoft Project itself.
After reviewing and analyzing your schedule, you might want to make certain
adjustments. If you find that the project finish date is in jeopardy, you can
adjust tasks to shorten your schedule.
Maybe projections show you'll run over budget. Or perhaps you just want to
make sure that your project plan accurately models how the project will really
run.
Can a task begin earlier? Use lead time. Is there a date when a task must
absolutely start? Add a constraint. Are some resources overworked and others
free? Reassign resources to shorten tasks.
After you've entered task, resource, and cost information for your project, you
can save a snapshot, or baseline, of your original plan.
After the project is under way, you can enter actual information and have
Microsoft Project help you compare that data to the baseline. When you've
completed this, you'll have a baseline of your project for future reference.
When you manage a project, you need to monitor the elements of the project
triangle: time, money, and scope. Adjusting one of these elements affects the
other two. Events such as unexpected delays, cost overruns, and resource
changes can cause problems in your schedule.
If you keep your project information up to date, you can always see the latest
status of the project. You can track actual progress on tasks, track actual work
by resources, compare your actual costs to your planned budget, and balance
the resource work load. With these methods, you can identify potential
problems early enough to find and implement solutions.
After you've set up your project and work has begun, you can keep track of
actual start and finish dates, task percent complete, or actual work. Tracking
actually shows you how changes affect other tasks and ultimately, the project's
finish date.
Decide on one or two progress indicators to use throughout the project. For
example, resources can quickly report percent work complete on tasks, giving
you a broad idea of task progress. At the other extreme, resources can report
exact hours of work on each task every week. This is more time-consuming,
and you have a highly accurate picture of progress. Which indicators you use
depends entirely on your preferences and priorities.
When you've completed this, you'll know which views to use for tracking and
checking progress. You'll know how to enter different types of task progress
information and see their effects on the schedule. If you're using an online
team collaboration solution like Microsoft Project Server, you'll learn how to
receive progress updates from team members.
You might need to track how much work each resource on your project
completes task by task or cumulatively for the project. Then you can compare
6
_____________________________________ Micro Soft Project Management Manual
the planned and actual amounts of work. This comparison can help you keep
track of your resources' performance and plan work loads for future projects.
When you've completed this, you'll know how to enter actual work done by a
resource and see the variance between a resource's planned and actual work.
You might want to track cost overruns in a certain phase of your project or
learn how much a particular resource costs on a certain day. Or you might
simply need to see how much total cost has accrued so far. Tracking costs for
your project can help you see where changes need to be made to finish your
project on time and within budget. It can also help you plan budgets for future
projects. When you've completed this, you'll know how to enter and view actual
costs.
Check your schedule periodically for resources with too much or too little
work. If some resources are over allocated, see if adding more resources to a
task or reassigning a task will balance out the work load better.
If this doesn't work, you can delay tasks assigned to an overworked resource
until later in the schedule or reduce the amount of work for tasks. When you've
completed this, you'll know how to find over allocated resources and
understand techniques for balancing resource work loads.
COMMUNICATE RESULTS
To manage a project effectively, you need to communicate and distribute
project information. You might prepare reports or presentations; publish
information on a Web site; or use Microsoft Project Server to communicate
with your project team on the Web.
With Microsoft Project, you can format and print views and reports to meet the
needs of a particular person or group. You can publish the information in Web
format (HTML) or include it in a presentation by using a program such as
Microsoft PowerPoint.
Especially with larger projects with extensive task lists, sometimes it can be
difficult to focus on areas that concern you. To emphasize what you need to
see, you can customize the format of the task list and the Gantt bars. You can
format categories of information, such as all tasks that must end by a certain
date. You can change or add Gantt bars for certain information. You can also
format individual text and Gantt bars if needed.
7
_____________________________________ Micro Soft Project Management Manual
Printing various aspects of your project plan can be useful when you're
analyzing the plan, or sharing project information with others. On your project
printout, you can add headers, footers, and page numbers. You can switch to a
different view, customize the view to show only the information you need, and
print it. You can also select from an array for predefined reports. When you've
completed this, you'll know how to print the project information you want.
After initial planning, you can start your project, enter your preliminary project
data, and attach your planning documents to the project.
Tip: You can also use the New Project Wizard to guide you through the
process of setting up a new project. In the Tasks side pane, click Define the
project or Define general working times, and then follow the instructions. Click
a link at the bottom of each pane to move through the wizard.
2. In the Start date box, type or select the date that you want to start your
project.
Or, if you want to schedule the project from the finish date, then
3. In the Finish date box, type or select a finish date from which to schedule
your project.
Tip If your plans change, you can change this initial project information at
any time by clicking Project Information on the Project menu.
8
_____________________________________ Micro Soft Project Management Manual
Note After you've determined how late you can start a project and still finish
by a particular date, it's often preferable to switch back to scheduling from the
start date when work begins on the project.
2 Open a project
Open a project. The first step in creating your project is to open the file you
will use throughout your project. You can create a new file, which is the usual
way of beginning, or you can base your new file on an existing file or template
that contains tasks or resources similar to those you'll need for the current
project.
Enter file properties. File properties, such as the project title or the company
name, can help you and others in the organization identify and locate your file
in the future
Link or store project-related documents in Microsoft Project. After you have
created a file, you can attach your project-related documents to it. For
example, you may want to link a scope management plan or risk management
plan to your project for easy access
Set the working time for the project calendar. You may need to change the
working days and hours for your project calendar. In Microsoft Project, the
default working times are 8:00 A.M. to 5:00 P.M. weekdays, with an hour off
for lunch. You can change working hours for all working days, specific days
(such as every Tuesday), or certain dates such as holidays.
Save a project. From time to time, you need to save your project, either to
include changes you made, to create a backup copy of your current project, or
to create a template you can use for another project. Microsoft Project
provides several ways to save a project file.
Tips:
To open a project created in another program, click the file format you
want in the Files of type box, and then double-click the file name in the
folder list. You can also type the extension in the File name box (for
example, type *.mpt to find Microsoft Project templates).
To open a project stored in a database, in the Open from Microsoft
Project Server dialog box, click Open from File. Then, in the Files of
type box, select Project Database. Double-click the file.
9
_____________________________________ Micro Soft Project Management Manual
Note Enterprise projects cannot be stored to a local database; they
must be saved locally to a computer or network first.
To open a project you've used recently, click the file name at the
bottom of the File menu. If the list of recently used files isn't
displayed, click Options on the Tools menu, click the General tab, and
then select the recently used file list check box.
You can enter a variety of file properties for your project, including a
descriptive title, the subject, the manager, and comments. You can also use
these properties to organize your files.
1. To enter basic file properties for the active project, on the File
menu, click Properties, and then click the Summary tab
2. Type the relevant project information in the file properties boxes
3. To add custom file properties for the active project, click the
Custom tab
4. Type the relevant information in the Name, Type, and Value boxes,
and then click Add.
With Microsoft Project, you can add information (such as page numbers, date
and time, a file name, or project-specific information) to the header, footer, or
legend of a view or to the header or footer of a report.
To add the current date and time, click Insert Current Date button, Insert
Current Time button, or both
Tips:
10
_____________________________________ Micro Soft Project Management Manual
Headers can have up to five lines of information, footers and legends
can have up to three lines. You can also adjust the width of the
legend's text box from 0 to 5 inches.
To format preset information, select the ampersand (&) or select the
text you want to format, click Format Text Font, and then select the
formatting options you want.
To add the file name and its path, you can select File Name and Path
in the General list box, and then click Add.
To start the first page with a number other than 1, you can click the Page tab, and then
specify the number you want in the First page number text box.
If you chose Custom as the report type, click a report in the Reports list,
click Setup, and then go to step 5.
3. Click the report you want, click Select, and then click Page Setup
4. Click Page Setup, and then click the Header or Footer tab
5. On the Header or Footer tab, click the Left, Center, or Right tab
6. In the text box, place the insertion point where you want to add
information
7. To add page numbers, click Insert Page Number button, Insert Total
Page Count button, or both.
To add the current date and time, click Insert Current Date button,
Insert Current Time button, or both
Tips:
11
_____________________________________ Micro Soft Project Management Manual
To start the first page with a number other than 1, you can click the
Page tab, and then specify the number you want in the First page
number text box.
You can set the working days and hours for your project calendar to reflect the
general working days and hours of the project. You can specify regular
nonworking times (such as weekends and evenings), as well as special days off
(such as holidays).
To change all the working days (for example, to have the working day
begins at 9:00 A.M.) click the abbreviation at the top of the first day,
and then hold down SHIFT and click the abbreviation at the top of the
last day.
4 Click Use default, Nonworking time, or No
default working time.
5 If you clicked No default working time, type the times you want work to
start in the From boxes and the times you want work to end in the To boxes.
Tips
You can also use the Project Working Times side pane to quickly set
the working time for the project calendar. On the Project Guide
toolbar, click Tasks, and then click Define general working times. Then
follow the instructions that appear in the side pane.
When setting up a shift that spans 12:00 midnight, pay close attention
to the working hours per day and not just to the shift hours. For
example, to set up a shift that runs from 10:00 P.M. to 6:00 A.M.
weekdays, you would enter the following non-default working times:
o Mondays 10:00 PM to 12:00 AM.
o Tuesdays through Fridays 12:00 AM to 6:00 AM and 10:00 PM to
12:00 AM.
o Saturdays 12:00 AM to 6:00 AM.
12
_____________________________________ Micro Soft Project Management Manual
You can also create separate calendars for resources and tasks.
You can set up project and resource working time calendars to accurately
reflect resource availability. Microsoft Project uses this information when
scheduling tasks, and examining whether resources are
overallocated.Microsoft Project uses this information when scheduling tasks,
examining whether resources are over allocated, and when leveling resources.
Set the working times and days off for all resources on the project
Tip: You can also use the Resource Working Times side pane to quickly set
working times for resources. On the Project Guide toolbar, click Resources,
and then click Define working times for resources. Then follow the instructions
that appear in the side pane.
To change all the working days, click the abbreviation at the top of
the first day, and then hold down SHIFT and click the abbreviation at
the top of the last day.
4 Click Use default, Nonworking time, or Non-default working time.
If you click Use default, the selected days adopt the default working
times, which are 8:00 A.M. to 12:00 P.M. and 1:00 P.M. to 5:00 P.M.,
Monday through Friday, and nonworking time on weekends.
If you click Non-default working time, type the times you want work to
start in the From boxes and the times you want work to end in the To
boxes.
13
_____________________________________ Micro Soft Project Management Manual
Note You can use the working hours in the project calendar to help
accommodate work on non-project tasks. If team members realistically can
only spend six hours per day working on project tasks, with the other two
hours spent on meetings and administrative tasks, you can reflect this by
indicating resource availability of six hours per day in the project calendar.
Learn more about accounting for non-project tasks.
Notes
The new base calendar you create becomes available in the list of
calendars in the Change Working Time dialog box and on the Working
Time tab in the Resource Information dialog box. You can then assign
the new base calendar to resources.
For example, if the selected resource works the night shift, click Night Shift
to assign this as the resource's base calendar.
Change the working times, days off, and vacations for individual
resources
Tip: You can also use the Resource Working Times side pane to quickly set
working times for resources. On the Project Guide toolbar, click Resources,
and then click Define working times for resources. Then follow the instructions
that appear in the side pane.
To change all the working days, click the abbreviation at the top of
the first day, and then hold down SHIFT and click the abbreviation at
the top of the last day.
4 Click Use default, Nonworking time, or Non-default working time.
If you click Use default, then your selected days adopt the working
and nonworking times of the resource's base calendar.
If you click Non-default working time, type the times you want work to
start in the From boxes and the times you want work to end in the To
boxes.
Change task scheduling defaults for scheduling days, weeks, and
months
15
_____________________________________ Micro Soft Project Management Manual
1 On the Tools menu, click Options, and then click
the Calendar tab.
2 To change the default start or end time for scheduled tasks, change the
time in the Default start time and Default end time boxes.
3 If you want to change how many hours Microsoft Project schedules for 1
day, enter it in the Hours per day box.
For example, if you want Microsoft Project to schedule 6 hours when you
enter a 1-day duration, type or select 6 in the Hours per day box.
4 If you want to change how many hours Microsoft Project schedules for 1
week, enter it in the Hours per week box.
For example, if you want Microsoft Project to schedule 30 hours when you
enter a 1-week duration, type or select 30 in the Hours per week box.
5 If you want to change how many days Microsoft Project schedules for 1
month, enter it in the Days per month box.
For example, if you want Microsoft Project to schedule 24 days when you
enter a 1-month duration, type or select 24 in the Days per month box.
Note: The settings you make on the Calendar tab do not change the project
calendar or resource calendars. To change project or resource calendars, do
one of the following:
Use the Resource Working Times side pane. On the Project Guide
toolbar, click Resources, and then click Define working times for
resources
Use the Change Working Time dialog box on the Tools menu.
To open this dialog box, on the Tools menu, click Change Working Time. Or, in
any resource view (Resource Sheet, Resource Usage, or Resource Graph), click
the resource name, and then click Resource Information button. Click the
Working Time tab. If you open this dialog box with the Tools menu, all
resource calendars are listed with the base calendars. If you open this dialog
box with the Resource Information dialog box, you'll see only the resource
calendar for the selected resource.
Use this dialog box to enter, review, or change base calendars and resource
calendars. You can:
Review and modify the working days and times in the project calendar.
Review and modify the working days and times in any base calendar or
resource calendar.
Create a new base calendar for use as the default hours for a set of
resources or as a task calendar.
16
_____________________________________ Micro Soft Project Management Manual
Change a resource's working times and days off.
Details:
For This box is available only in the version of the Change Working Time
dialog box from the Tools menu. Choose the calendar that you want to review
or modify. By default, Standard (Project Calendar) is selected. The project
calendar is set in the Project Information dialog box, available on the Project
menu. This list includes the base calendars that come with Microsoft Project,
as well as any new base calendars you create and all the resource calendars,
which are automatically created as soon as the resource is created. You can
distinguish a resource calendar from a base calendar because a resource
calendar not only takes the name of the resource, but a notation such as based
on Standard calendar appears next to the For box. The base calendars and
their working times that come with Microsoft Project are as follows. If you
create additional base calendars or modify the working times for existing base
calendars, your changes are reflected in this list.
Standard The base calendar that has a standard work day and work week of
Monday through Friday, 8:00 A.M. to 5:00 P.M., with 12:00 P.M. to 1:00 P.M.
of nonworking time for break.
24 Hours The base calendar that has no nonworking time. All time, from
Sunday through Saturday, 12:00 A.M. to 12:00 P.M., is set as working time.
Night Shift The base calendar that is set up for a graveyard shift. Working
times are Monday night through Saturday morning, 11:00 P.M. to 8:00 A.M.,
with 3:00 A.M. to 4:00 A.M. of nonworking time for break.
Base calendar This box is available only on the Working Time tab of the
Resource Information dialog box. Choose the calendar that you want the
selected resource's working times to be based on. By
default, this calendar is the Standard calendar. You can choose from the base
calendars that come with Microsoft Project, as well as any new base calendars
you have created. You can create your own base calendar by clicking New in
the Change Working Time dialog box. If you create your own base calendars,
or modify the working times in existing base calendars, your changes are
reflected in this list.
Select Date(s) Select dates in the calendar to indicate which days you want to
change. Once you select the day or days, you can use the Set selected date(s)
to options and the From and To boxes to specify the change to current working
and nonworking times.
To select a date in the current month, click the date in the calendar.
17
_____________________________________ Micro Soft Project Management Manual
To select a date in a different month, use the scroll arrows to move to the
month, and then click the date.
To select multiple adjacent days in one week, drag across the days. Or click the
first day, hold down SHIFT, and then click the last day. All days between the
first and last are selected.
To select multiple nonadjacent days in one month, click the first day, hold
down CTRL, and then click all the other days in the month that you want to
change in the same way.
To select the same day throughout the project, click the label for the day of the
week.
Remarks
If a task has a fixed duration, then Microsoft Project does not schedule the task
based on the resource calendar. The task duration remains the same
regardless of the number of resources assigned to the task or the working
times reflected in the resource calendar.
You can create a base calendar that can be applied to a task as a task calendar.
In the Task Information dialog box for the task, click the Advanced tab, and
then in the Calendar list click the base calendar you want to apply to the
selected task. If you have a task calendar and resources assigned to a task,
Microsoft Project schedules the task based on the working times the task
calendar and resource calendars have in common. If you select the Scheduling
ignores resource calendars check box, then the task is scheduled according to
the working times in the task calendar alone.
Microsoft Project does not use resource calendars for material resources.
If you change the number of working hours per day, hours per week, or days
per month in your project calendar, you might want to match the settings on
the Calendar tab of the Options dialog box. While the working times calendars
actually control when work is scheduled, it's helpful to have this synchronized
with the Calendar tab settings. The Calendar tab settings affect how Microsoft
Project converts the durations you enter for new tasks into work.
18
_____________________________________ Micro Soft Project Management Manual
Typically, one of the first things you do when building a new project plan is to
specify whether you want to schedule your project from a start date or finish
date and to specify that date. However, you can change the project start date
or finish date even after you have built your project plan. [ Click for more ]
Note:
If the finish date doesn't change after you've changed the start date,
then one or more tasks may have a date constraint applied. Review the
constraints in your plan to make sure they're necessary and
appropriate.
You can also click Adjust Dates on the Analysis toolbar to change the start
date. Using Adjust Dates, tasks with date constraints move to a date in relation to the new
start date you entered.
Notes
In most cases, you should schedule your project from a start date.
However, there are some cases where scheduling from a finish date
makes sense. Learn more about scheduling a project from a finish
date.
If the start date doesn't change after you've changed the finish date,
then one or more tasks may have actual progress reported, or it may
have a date constraint applied. Review the constraints in your plan to
make sure they're necessary and appropriate.
You can also click Adjust Dates on the Analysis toolbar to change the
start date. Using Adjust Dates, tasks with date constraints move to a
date in relation to the new start date you entered.
Different versions of Windows can have different default locations for storing
your projects. For example, Windows 2000 and Windows XP store project files
19
_____________________________________ Micro Soft Project Management Manual
in \Documents and Settings\user name\My Documents, but Windows 98 and
Windows Me store project files in C:\My Documents. The first time you open
the Open or Save As dialog box (File menu) after starting Microsoft Project,
the names of the files stored in the default working folder are displayed in the
dialog box.
You can easily change the default working folder to any convenient location.
From the Tools menu, click Options, and then click the Save tab. In the File
Types list, double-click Projects, navigate to the new default working folder
and double-click it, and then click OK.
You can add some of the data fields to the headres and footers in
project reports
You can also view the General, Statistics and Contents Tab to get
other related information.
You can display property, can create new property, can delete a property
and you can modify a property.
To create new property:
1. Choose File
2. Click Properties
3. Select the custom Tab
4. Select property from the Name drop-down list, or type a property
name in the Name Text Box.
5. If you want the property linked to an existing field in the project,
click the Link to Content check box and then select the source from
the source drop-down list. OR
6. If you choose Text, Number or date, enter a value in the value text
box.
If you choose the Yes or No option, you can use the Yes or No
buttons that appear in the value box.
20
_____________________________________ Micro Soft Project Management Manual
7. Click the Add button to add the new property to the list.
To delete a property:
1. Select the property in the Name Column of the Property.
2. Click the Delete button.
To modify a property:
1. Select the property’s name in the Properties list to move the name
and value to the appropriate text boxes at the top of the dialog box.
2. Make the desired changes to the Type, Source or Linking of the
property. The add button changes to a modify button.
3. Click Modify to accept the changes.
When you finish the project properties, click Ok to save the changes you
made; or Cancel to close the dialog box without saving the changes.
Save a project
From time to time, you need to save your project to include changes you made,
to create a backup copy of your current project, or to create a template you
can use for another project. Microsoft Project provides several ways to save a
project file.
You can save a project to a database format (.mpd), and then you can work
with the project in Microsoft Access or any program that supports the
Microsoft Access file format. The Microsoft Project database format replaces
the MPX file format as the standard interchange format for project data.
Note Enterprise projects must not be saved directly to the Microsoft Project
Server database by saving them in Microsoft Project database format. This can
lead to overwriting or corruption of project data. An enterprise project can be
saved to a local computer or network and then saved in database format, but if
you save all enterprise global template items, the project file will be very large.
It is recommended that you choose the option of saving only currently loaded
enterprise global items. If you plan to save a project from Microsoft Project
Server to Microsoft Project database format, in the Open from Microsoft
Project Server dialog box, click Open from File instead of Open from Microsoft
Project Server.
Tip You can store multiple projects in a single MPD file. In the File name box,
type the file name to which you want to save the project, click Save, and then
click Append.
You may want to save a project to your computer or a local network folder;
however, saving an enterprise project with the enterprise global template
applied can make the project file very large.
Notes
When working in an enterprise project, you must include values for all
mandatory fields defined in the enterprise global template. You will be
prompted to add information for any fields you have not entered
values for.
If you save a local project to Microsoft Project Server, you are
prompted to rename items with the same names as items in the
enterprise global template before you can save it to the server.
If you have not set a baseline for your project, you are asked if you
want to set a baseline when you save your project. Learn how to set
baselines.
22
_____________________________________ Micro Soft Project Management Manual
After you have determined the work involved in your project, you can organize
it into milestones, phases, and tasks and enter it into a Microsoft Project file. If
this data is stored in another file, you can copy or import it into Microsoft
Project.
1. DEFINING A TASK
To define your tasks most effectively, take into account the following
guidelines:
Break down tasks to the level of detail that you want to track. You
should break them down in greater detail for riskier areas.
Make sure that tasks have clear completion criteria.
Define tasks that are short compared with the overall project duration.
Shorter tasks allow you to more easily estimate time and resources.
Avoid defining such things as vacation or training as tasks. Learn how
to enter these items as nonworking time on a resource calendar.
23
_____________________________________ Micro Soft Project Management Manual
A work breakdown structure (WBS) can help you create a task list by taking a
high-level description of the work and breaking it into components. For
example, the high-level work description, "Remodel kitchen" includes such
lower level work as installing cabinets, installing a sink, and installing a
countertop. "Remodel kitchen" is considered a phase or summary task. The
lowest levels of the WBS, the installation components, are tasks or subtasks. In
some organizations, tasks may also be called work packages.
You can enter two kinds of tasks in Microsoft Project: tasks that occur once
and recurring tasks.
2 In the Task Name field, type a task name at the end of the task list.
Or, to insert a new task, click the task in the Task Name field below where
you want to add a new task. Then click New Task on the Insert menu. Type
the name of the new task.
3 Press
ENTER.
Tips:
With Microsoft Project, you can use an outline to organize your schedule as
you enter tasks or you can wait until you enter all of your project tasks.
When you outline a schedule for your project, you simplify its organization
so that your project is easier to create, manage, and maintain. Learn more
about outlining.
You can insert a task between existing tasks by selecting the row below
where you want a new task to appear. On the Insert menu, click New Task
and enter the task name in the inserted row.
Note: The task IDs are automatically renumbered after you insert a task.
2. In the Task Name field, select the row below where you want the recurring
task to appear.
3. On the Insert menu, click Recurring Task
4. In the Task Name box, type the task name
5. In the Duration box, type or select the duration of a single occurrence of the
task
6. Under Recurrence pattern, click Daily, Weekly, Monthly, or Yearly
24
_____________________________________ Micro Soft Project Management Manual
7. Specify the task frequency and select the check box next to the day of the
week that the task should occur.
8. Under Range of recurrence, type a start date in the Start box, and then
click End after or End by.
9. If you clicked End after, type or select the number of occurrences for the
task. If you clicked End by, type or select the date you want the recurring
task to end
Notes:
The task IDs are automatically renumbered after you insert a task.
If you want to apply a calendar to your recurring task, under Calendar for
scheduling this task, click the calendar you want to use.
If you don't enter a date in the Start box, Microsoft Project uses the project
start date.
If your recurring task will occur on any nonworking days, Microsoft Project
asks you if you want to reschedule those occurrences.
Tip: To move a task beneath the phase or sub phase, click the Task ID
number in the leftmost column of the task, and then click Cut button.
Select the field below where you want to insert the task, and then click
Paste button.
6. Click Indent button to indent the task or tasks beneath the phase or sub
phase
5. CREATE A MILESTONE
A milestone is a task with no duration (zero days) that you use to identify
significant events in your schedule, such as the completion of a major phase.
When you enter a duration of zero for a task, Microsoft Project displays the
milestone symbol button on the Gantt Chart on that day.
25
_____________________________________ Micro Soft Project Management Manual
Tip Some milestones may need duration. For example, your project has an
approval milestone at the end of a phase and you know that the approval
process will take a week. To mark a task as a milestone with duration of more
than 0 days, click Task Information button, and then click the advanced tab. In
the Duration box, enter the task duration, and then select the Mark task as
milestone check box
You can store information about tasks in Microsoft Project by typing notes,
attaching files, or creating hyperlinks to related information in your project file
or in other locations. If your organization has set up Microsoft Project Web
Access, you can set up document libraries and link documents to projects and
tasks in Microsoft Project Web Access. Then resources, executives, and other
stakeholders can view the associated documents through their Web browsers.
Team members who have Microsoft Project installed can also click Documents
on the Collaborate menu to access this feature.
3. Click Task Notes button, and then click the Notes tab
4. In the Notes box, type the content of the note
Tip To view the task note, rest the pointer on the notes indicator button in the
Indicators field. If the complete note is not visible, double-click the notes
indicator.
Tip: To view the task note, rest the pointer on the notes indicator button in the
Indicators field. If the complete note is not visible, double-click the notes
indicator
26
_____________________________________ Micro Soft Project Management Manual
TO MOVE OR COPY A TASK:
1. Select the entire task by clicking the ID number for the task.
2. Click the Cut or Copy button
3. Click in the row where you want the task to appear.
4. Click the paste button.
TO INSERT A ROW
1. Select the row below where you want the new row by clicking the row
number.
2. Click insert
3. Click new task
Use the Task Information dialog box to enter, review, or change detailed
information about a selected task. When you click a single task and open the
Task Information dialog box, the title bar title is Task Information and all six
tabs are available. If you click multiple tasks to make the same change to
several
tasks at once, the title bar title is Multiple Task Information, and the
Predecessors tab, the Notes tab, and the Custom Fields tab are not available. If
you click a summary task or the project summary task, the title bar title is
Summary Task Information.
To open this dialog box and tab, in any task view, click the task and then click
Task Information button. Click the General tab.
Use this tab to enter, review, or change basic information about the selected
task. You can:
27
_____________________________________ Micro Soft Project Management Manual
Enter task durations and indicate whether the durations are
estimated or set.
Track progress on a task by entering the percentage of completion.
Enter the task start or finish date to set a Start No Earlier Than or
Finish No Earlier Than constraint.
Remarks
Percent complete Type the percentage of the task that is complete to indicate
the actual progress on the task. Microsoft Project calculates the task's actual
and remaining duration using this number. If you enter a percentage for
summary tasks, the progress is distributed to its subtasks.
You can quickly mark tasks as 100% complete and on schedule by clicking
100% Complete button on the Tracking toolbar.
Priority You can set task priorities to indicate their availability for resource
leveling. You can sort tasks by priority by using the Sort command on the
Project menu. You can also use priority to filter tasks. Set the priority to 1000
(meaning do not level) if you don't want Microsoft Project to delay this task at
all when leveling.
To open this dialog box and tab, in any task view, click a task and then click
Task Information button. Click the Predecessors tab. Although you can select
and change multiple tasks at once with the other Task Information tabs, the
Predecessors tab is available only if a single task is selected.
Use this tab to enter, review, or change predecessor information about the
selected task. You can:
28
_____________________________________ Micro Soft Project Management Manual
ID Type the identification number of the task's predecessor. Type the ID of
only one predecessor per row and enter information about that predecessor in
the remainder of the row. If you don't know the ID, you can click the name of
the task in the Task Name field. You can only enter the ID of a task that
already exists. If you want to link to a task in another project, with the other
project open, you can type the project name and the task ID, for example,
Project1\8.
Task Name Click the name of the predecessor task from the list. All other
tasks in the project are listed. If you typed an ID in the ID column, Microsoft
Project automatically enters the task name in this column.
Type Specify a task dependency. You can click the dependency type from the
list. Or you can type it, using the two-letter combination shown in parentheses
below:
Finish-To-Start (FS) - The successor task cannot start until the predecessor
task finishes. This is the default task dependency.
Start-To-Start (SS) - The successor task cannot start until the predecessor task
starts.
Finish-To-Finish (FF) -The successor task cannot finish until the predecessor
task finishes.
Start-To-Finish (SF) -The successor task cannot finish until the predecessor
task starts.
None - No task dependency has been set for this predecessor task.
Lag Type the lead time or lag time between the tasks. Enter an amount
followed by a time unit abbreviation. You can also enter lead or lag as a
percentage. Indicate lead time with a negative number, for example, -2d.
Indicate lag time with a positive number, for example, 4h.
You can enter lead and lag time units as working time or as elapsed time.
Remarks:
When you link tasks in different projects that are stored in Microsoft Project
Server, the predecessor's task ID must be formatted correctly. In the Task
Information dialog box, on the Predecessors tab, in the ID column, the task ID
must be formatted as shown in the following example: <>\
projectone.published\42. In this example, the angle brackets (<>) contain no
information, projectone.published is the name of the project containing the
predecessor, and 42 is the task ID of the predecessor task.
29
_____________________________________ Micro Soft Project Management Manual
TASK INFORMATION DIALOG BOX, RESOURCES TAB
To open this dialog box and tab, in any task view, click the task and then click
Task Information button. Click the Resources tab.
Use this tab to enter, review, or change resource assignments and assignment
units for the selected task.
Resource Name Enter the name of a resource you want to assign to the task.
Enter the name of only one resource per row. You can replace one resource
assignment with another. You can also delete a resource assignment by
clicking the row and then pressing DELETE.
Units Type the number of assignment units that you are allocating to the
task. For example, to assign a work resource to work half-time on a task, type
50%. The default for assignment units is the same as the resource's maximum
units, up to 100%. That is:
The assignment units percentage is based on the working time available as set
in the resource calendar. If the resource calendar indicates that the resource is
available for 8 hours on Monday, then 100% on a task scheduled for Monday
means 8 hours of work on the task. If the resource calendar indicates that the
resource is available for 4 hours on Tuesday, however, then 100% on a task
scheduled for Tuesday means 4 hours of work on the task.
Remarks:
30
_____________________________________ Micro Soft Project Management Manual
isn't already identified in the resource pool, you can simply type the resource
name.
You can change this setting. On the Tools menu, click Options, and then click
the General tab. Clear the automatically add new resources and tasks check
box. If you change this setting and you want to assign a new resource on the
Resources tab of the Task Information dialog box, you can still type the
resource name, but then Microsoft Project asks you to confirm the new
resource when you close the tab or click OK.
To open this dialog box and tab, on the Tools menu, click Options, and then
click the General tab.
Use this tab to enter, review, or change your preferences for the general
operation of Microsoft Project. You can:
Remarks:
Individual Planning Wizard messages include the check box, Don't tell me
about this again. You can turn off individual messages by selecting this check
box when the message appears. If you turn off individual messages in some of
the Planning Wizard messages, the Advice About check boxes for the affected
wizards appear shaded.
To open this dialog box and tab, in any task view, click the task, and then click
Task Information button. Click the Advanced tab.
Use this tab to enter, review, or change supplemental task information. You
can:
Enter a deadline for the task if you want be alerted about missed
deadlines.
Change the constraint on the task to affect schedule dates.
Specify the task type for the task to affect how changes to task
information affect scheduling.
Specify the task calendar for the task.
Mark the task as effort-driven, or as a milestone.
Specify the method to use when performing earned value analysis on
this task.
31
_____________________________________ Micro Soft Project Management Manual
Details: The following are details about list choices on this tab.
Deadline Enter a date that indicates when you want this task to be
completed. Setting a deadline does not set a date constraint or affect the task
scheduling. Instead, it displays an indicator if the deadline passes and the task
is not completed. It also displays an arrow on the chart portion of the Gantt
Chart view.
Constraint type Specify any restriction on the allowable start or finish date
for the task. You can assign one constraint per task. If you specify a constraint
other than As Soon As Possible or As Late As Possible, enter the appropriate
date in the Constraint date box.
For projects scheduled from the start date, this constraint is applied when you
type a finish date for a task.
Finish No Later Than This moderate constraint indicates the latest possible
date that this task can be completed. It can be finished on or before the
specified date.
For projects scheduled from the finish date, this constraint is applied when you
type a finish date for a task.
Must Finish On This inflexible constraint indicates the exact date on which a
task must finish. Other scheduling parameters such as task dependencies, lead
or lag time, resource leveling, and delay become secondary to this
requirement.
Must Start On This inflexible constraint indicates the exact date on which a
task must begin. Other scheduling parameters such as task dependencies, lead
or lag time, resource leveling, and delay become secondary to this
requirement.
32
_____________________________________ Micro Soft Project Management Manual
Start No Earlier Than This moderate constraint indicates the earliest
possible date that this task can begin. It cannot start any time before the
specified date.
For projects scheduled from the start date, this constraint is applied when you
type a start date for a task or drag a Gantt bar.
Start No Later Than This moderate constraint indicates the latest possible
date that this task can begin. It can start on or before the specified date.
For projects scheduled from the finish date, this constraint is applied when you
type a start date for a task.
Task type Specify the effect that a change to work, assignment units, or
duration has on the calculation of the other two fields for this task.
Fixed Duration Set the task to Fixed Duration if you want the task duration to
remain constant, regardless of any change in assignment units or work for the
task. For fixed-duration tasks:
Fixed Units Set the task to Fixed Units if you want the number of assignment
units to remain constant, regardless of any change in duration or work for the
task. This is the default. For fixed-unit tasks:
Fixed Work Set the task to Fixed Work if you want the amount of work to
remain constant, regardless of any change in duration or resource assignment
units for the task. Because, by definition, fixed-work tasks are effort-driven, the
Effort driven check box is automatically selected for fixed-work tasks. For
fixed-work tasks:
33
_____________________________________ Micro Soft Project Management Manual
Calendar Specify the calendar for this task if it is anything other than the
project calendar, as set in the Project Information dialog box. You can choose
from the base calendars that come with Microsoft Project, as well as any new
base calendars you have created. You can create your own base calendar by
clicking New in the Change Working Time dialog box (Tools menu). If you have
a task calendar applied as well as resources assigned, the task is scheduled
during the working times that the task calendars and resource calendars have
in common. If you select the Scheduling ignores resource calendar check box,
then only the task calendar is used to schedule the task. The following are the
default base calendars and their working times that come with Microsoft
Project. If you add your own base calendars or modify the existing ones, your
changes are reflected in this list.
Standard The base calendar that has a standard work day and work week of
Monday through Friday, 8:00 A.M. to 5:00 P.M., with 12:00 P.M. to 1:00 P.M.
designated as nonworking time for break.
24 Hours The base calendar that has no nonworking time. All time, from
Sunday through Saturday, 12:00 A.M. to 12:00 P.M., is set as working time.
Night Shift The base calendar that is set up for a graveyard shift. Working
times are Monday night through Saturday morning, 11:00 P.M. to 8:00 A.M.,
with 3:00 A.M. to 4:00 A.M. designated as nonworking time for break.
WBS code Specify the WBS code you want to apply to this task. The WBS
field contains an alphanumeric code you can use to represent the task's
position within the hierarchical structure of the project. This field is similar to
the outline number, except that you can edit it or apply a specific WBS format,
or mask. WBS codes are generally unique; that is, each task has a separate
WBS code. The default WBS code is the task's outline number. You can type or
define a format for your own custom WBS code. Learn how to define a custom
WBS code format.
Earned Value method Specify whether you want earned value calculated by
using % Complete or Physical % Complete.
Remarks:
Because constraints affect scheduling, it's best to use the inflexible date
constraints, such as Must Start On or Finish No Later Than, only when
34
_____________________________________ Micro Soft Project Management Manual
required by conditions external to the project. Otherwise, let Microsoft Project
calculate the project schedule based on task durations and dependencies.
You can set the default task type for all new tasks. On the Tools menu, click
Options, and then click the Schedule tab. In the Default task type box, click the
task type you want.
You specify the default earned value method for Microsoft Project on the
Calculation tab of the Options dialog box. Use the Earned Value button on this
tab to apply a different method to the selected fields when you calculate
earned value.
To open this dialog box and tab, in any task view, click the task and then click
Task Information button. Click the Notes tab.
Use this tab to enter or review notes for a selected task. You can:
Remarks:
When you add a note to a task, the notes indicator button appears in the
Indicators field. You can rest your mouse pointer over the notes indicator to
read some or the entire note. You can double-click the notes indicator to open
this Notes tab.
To include task notes when you print a task view such as the Gantt Chart view,
on the File menu, click Page Setup, and then click the View tab. Select the
Print notes check box.
To enter notes about the entire project rather than an individual task, on the
File menu, click Properties, and then click the Summary tab. Type your note in
the Comments box.
You can also add the project summary task and then add a note there. On the
Tools menu, click Options, and then click the View tab. Select the Project
summary task check box, and then click OK. On the Notes tab of the Task
Information dialog box for the project summary task, add your note.
USE NOTES
You can add notes to tasks, resources, assignments, or the entire project.
Notes can be edited, deleted, and viewed as needed.
35
_____________________________________ Micro Soft Project Management Manual
Add, edit, delete, or view task notes
Tips :
To format the text in a note, select the note text, and then use the
Format Font, Align Left, Center, Align Right, and Bulleted List
buttons. You can also insert objects such as images by using the
Insert Object button.
To paste text from another program, open the program, and then
copy the information by using the program's Copy command. In
Microsoft Project, select the task, resource, or assignment you want
to add a note to. Click Notes button, and then press CTRL+V to paste
the information into the note.
To open this dialog box and tab, in any task view, click the task, and then click
Task Information button. Click the Custom Fields tab
Use this dialog box to view and assign values to task custom fields and outline
codes.
You can also use this dialog box to view and assign values to task enterprise
custom fields and enterprise outline codes.
Details: The following are details about the Custom Fields table.
Custom Field Name Task custom fields that you have created in the Customize
Fields dialog box are displayed in this column.
36
_____________________________________ Micro Soft Project Management Manual
Value Values for the task custom fields or task custom outline codes for the
selected task are displayed in this column. You can enter or change values in
the entry bar or directly in the table.
Remarks:
You can edit values but not the custom fields or custom outline codes
themselves on the Custom Fields tab of the Task Information dialog box. To
make changes to custom fields (or to change values for custom outline codes
that are limited to lookup table values), you must do so in the Customize Fields
dialog box.
If you need to change an enterprise custom field or custom outline code, you
can make changes only with the required permission. Enterprise custom fields
and custom outline codes are part of the enterprise global template.
Microsoft Project schedules a project from the information you enter about the
overall project, the individual work items (called tasks) required to complete
the project, and, if necessary, the resources (the people, equipment, and
materials) needed to complete those tasks. If anything about your project
38
_____________________________________ Micro Soft Project Management Manual
changes after you create your schedule, you can update the tasks or resources
and Microsoft Project adjusts the schedule for you.
For each task, you enter durations, task dependencies, and constraints, then
Microsoft Project calculates the start date and finish date for each task. You
can enter resources in your project and then assign them to tasks to indicate
which resource is responsible for completing each assignment, and to calculate
how many machines are needed or how much material will be consumed. If you
enter resources, task schedules are further refined according to resource
work, units, and working times entered on calendars. Other elements, such as
lead time and lag time, task types, resource availability, and the driving
resource can affect scheduling, so understanding the effects of these elements
can help you maintain and adjust your schedule as needed.
If you enter a start date for the project, by default, Microsoft Project schedules
tasks to begin on the project's start date and calculates the project's finish date
based on the last task to finish. As you enter more information about tasks,
such as task dependencies, durations, and constraints, Microsoft Project
adjusts the schedule to reflect more accurate dates for tasks.
Note You must schedule a project from a start date or from a finish date; you
cannot schedule from both start and finish dates. You pick which date you want
to use (normally a start date), and Microsoft Project schedules the other date
(normally a finish date) for you based on the information you enter into the
project plan.
Nearly all projects should be scheduled from a known start date. Even if you
know the date that a project must be completed, scheduling from a start date
gives you the maximum flexibility.
However, in some cases, you may want to schedule from a finish date. For
example, schedule from the finish date when:
You are not sure when your project will begin (for example, if you're
receiving work from another source that could be delayed).
Your project management methodology requires you to schedule from a
finish date.
39
_____________________________________ Micro Soft Project Management Manual
Typically, one of the first things you do when building a new project plan is to
specify whether you want to schedule your project from a start date or finish
date and to specify that date. However, you can change the project start date
or finish date even after you have built your project plan.
1 On the Project menu, click Project Information. Be sure that the Schedule
from box shows Project Start Date.
2 In the Start date box, type or select the
new start date.
Notes:
If the finish date doesn't change after you've changed the start date,
then one or more tasks may have a date constraint applied. Review the
constraints in your plan to make sure they're necessary and
appropriate.
You can also click Adjust Dates on the Analysis toolbar to change the
start date. Using Adjust Dates, tasks with date constraints move to a
date in relation to the new start date you entered.
Notes
In most cases, you should schedule your project from a start date.
However, there are some cases where scheduling from a finish date
makes sense. Learn more about scheduling a project from a finish
date.
If the start date doesn't change after you've changed the finish date,
then one or more tasks may have actual progress reported, or it may
have a date constraint applied. Review the constraints in your plan to
make sure they're necessary and appropriate.
You can also click Adjust Dates on the Analysis toolbar to change the
start date. Using Adjust Dates, tasks with date constraints move to a
date in relation to the new start date you entered.
40
_____________________________________ Micro Soft Project Management Manual
As you work with your project scheduled from a finish date, you should be
aware of differences in the way Microsoft Project handles some actions, such
as the following:
When you enter tasks in a project scheduled from a finish date, Microsoft
Project automatically assigns the As Late As Possible constraint. You
should set other constraints only when necessary. Learn more about task
constraints.
If you drag a Gantt bar to change the finish date of a task, Microsoft
Project automatically assigns a Finish No Later Than constraint.
If you change your project to schedule from a finish date, and it was
previously scheduled from a start date, you will remove all leveling
delays and leveling splits from tasks and assignments.
If you use automatic leveling to reduce resource overallocations in your
project, Microsoft Project will add leveling delay after a task, rather than
before a task. Learn how to level a project that is scheduled from a finish
date.
Microsoft Project starts new tasks on the project start date by default. You can, however,
specify that nw tasks start on the current date instead of the project start date.
3. ENTER A DURATION
You can enter an accurate duration for a task or a new estimated duration to
replace the estimated duration that Microsoft Project assigns to each task by default.
Note To assign the task an elapsed duration, type an e before the time
unit. For example, to assign an elapsed duration of 3 days, type 3ed.
3 To indicate or flag the new duration as an estimate, type a
question mark after it.
4 Press
ENTER.
41
_____________________________________ Micro Soft Project Management Manual
Tip You can schedule your tasks most effectively by entering a duration and
links for each task and letting Microsoft Project calculate the start and finish
dates for you. For the greatest flexibility in scheduling, avoid inflexible
constraints. Learn about avoiding constraints.
To open this dialog box and tab, on the Tools menu, click Options, and then
click the Calendar tab.
Use this tab to enter, review, or change date and time settings in Microsoft
Project. These are all local settings saved with the current project, rather than
global settings. You can:
Remarks:
Changing options in this dialog box does not affect the project calendar or
resource working times calendars. It only affects how Microsoft Project
converts the durations into related time amounts used throughout your
project. For example, if the Hours per day box is set to the default of 8 hours,
and then you enter 2d in the Duration field, the two days of duration is
displayed on the Gantt bars as 16 hours. If you set Hours per day to 5, and
then enter a 2-day duration for a task, the task has a duration of 10 hours.
The time amounts you set here also apply to the translation of duration to
work amounts. The translation of time amounts operates the same way with
the Hours per week and Days per month boxes.
To control the way the work is actually scheduled, change the appropriate
working times calendars. Also, if you change the number of hours per day,
hours per week, or days per month, you might want to update the project
calendar to match, so that times and durations are properly synchronized.
On the Tools menu, click Change Working Time.
For the Default start time and Default end time boxes, enter the beginning
and ending times you want to use as defaults when you don't enter specific
times with dates entered in your project. This is most useful when entering
constraints and actual start and finish dates. For example, unless you
explicitly specify the finish time, a Must Finish On time will be the end time
set on this tab.
42
_____________________________________ Micro Soft Project Management Manual
Settings on the Calendar tab apply only to new tasks entered after you make
the setting change. For existing tasks, the amount of work stays the same,
but the duration is recalculated to use any new values for the existing
amount of work. For example, if you have a task with a 2-day duration, and
then you change the Hours per day setting from 8 hours per day to 4 hours
per day, this still equates to 16 hours of duration (and work) on the task, but
the duration changes from 2 days to 4 days.
When you need to control the start or finish date of a task, you can add a
constraint to the task. Flexible constraints work with task dependencies to
make a task occur as soon or as late as the task dependency will allow. For
example, a task with an As Soon As Possible (ASAP) constraint and a finish-to-
start dependency will be scheduled as soon as the predecessor task finishes.
If a task constrained to a date has a predecessor that finishes too late for the
successor to begin on the date specified in the constraint, negative slack can
occur. To specify that constrained tasks with negative slack are scheduled
according to their task dependencies rather than the constraint dates, on the
Tools menu, click Options, and then click the Schedule tab.Clear the Tasks will
always honor their constraint dates check box.
Deadline dates don't usually affect task scheduling. Deadline dates are used to
indicate a target date you don't want to miss, without requiring you to set a
task constraint that could affect scheduling if predecessor tasks change. A task
with a deadline is scheduled just like any other task, but when a task finishes
after its deadline, Microsoft Project displays a task indicator notifying you that
the task missed its deadline.
Deadline dates can affect total slack on tasks. If you enter a deadline date
before the end of the task's total slack, total slack will be recalculated using
44
_____________________________________ Micro Soft Project Management Manual
the deadline date rather than the task's late finish date. The task becomes
critical if the total slack reaches zero.
You can set deadlines for summary tasks as well as individual tasks. If the
summary task's deadline conflicts with any of the subtasks, the deadline
indicator signifies a missed deadline among the subtasks.
But deadline dates can affect how tasks are scheduled if you set a deadline
date on a task with an As Late As Possible (ALAP) constraint. The task is
scheduled to finish on the deadline date, though the task could still finish after
its deadline if its predecessors slipped
Calendars determine the standard working time and nonworking time, such as
weekends and holidays, for the project. They are used to determine resource
availability, how resources assigned to tasks are scheduled, and how tasks
themselves are scheduled. Project and task calendars are used in scheduling
tasks, and if resources are assigned to tasks, resource calendars are used as
well.
Base calendars; these are the foundations for the other types of
calendars. You can also choose a base calendar to be the project
calendar, and you can apply a base calendar to tasks as a task calendar,
or as the default hours for a resource calendar. Microsoft Project
provides three base calendars, the Standard, 24-Hours, and Night Shift
calendars. Resource calendars are based on the Standard calendar by
default. You can customize your own base calendar using any of the base
calendars provided.
Project calendars; these set the standard working and nonworking times
for the project as a whole. If resource calendars or task calendars are not
used, tasks are scheduled during the working time on the project
calendar, by default.
Resource calendars; these are based on the Standard calendar by
default. You can change working time or nonworking time for specific
resources or a set of resources, ensuring that resources are scheduled
only when they're available for work. If you have changed working or
nonworking time on a resource calendar and the resource is assigned to
a task, the task is scheduled during the working time on the resource
calendar.
Task calendars; these can be used to define working times for tasks
outside the working times in the project calendar. When a task calendar
is assigned to a task and the resource assigned to the task has different
working times in its resource calendar, the task is scheduled for the
intersection of the two calendars' working times. But you can set a task
option to ignore resource calendars and schedule the task through the
resource's nonworking time
45
_____________________________________ Micro Soft Project Management Manual
WHAT ARE CALENDARS?
Calendars determine how resources assigned to tasks are scheduled and how
tasks themselves are scheduled. Base calendars are sets of working and
nonworking times and days that are used by the three other types of calendars:
Project calendar
Resource calendar
Task calendar
Base calendars can be used for the project calendar and task calendars, and
provide the basis for resource calendars. Project and resource calendars
identify when work on tasks can take place, ensuring that resources are
scheduled only when they're available for work. Project calendars affect the
default for when tasks are scheduled. Resource calendars affect a specific
resource or category of resources. Task calendars make it possible for tasks to
have a calendar different from the project calendar. Learn how to set up
working time calendars.
These calendars are distinct from the Calendar view, which shows the project
schedule in a calendar format. Learn more about the Calendar view.
Base calendars are calendars on which the resource calendars are based. You
also choose a base calendar to be the default project calendar, and you can
apply a base calendar to tasks as a task calendar. Three base calendars are
provided with Microsoft Project:
Standard
24-Hours
Night Shift
The Standard calendar is the base calendar that is used as the default for the
project, and for resource and task calendars. This calendar reflects a
traditional work schedule: Monday through Friday, 8:00 A.M. to 5:00 P.M.,
with an hour off for break.
The 24-Hours calendar reflects a schedule with no nonworking time at all. The
24-Hours calendar can be used when resources and tasks are scheduled for
different shifts around the clock, or when equipment resources work on tasks
continuously.
The Night Shift calendar reflects a graveyard shift schedule of Monday night
through Saturday morning, 11:00 P.M. to 8:00 A.M., with an hour off for break.
46
_____________________________________ Micro Soft Project Management Manual
You can also create your own base calendars. Creating your own base
calendars is particularly useful if you have alternative schedules for multiple
resources, such as a part-time schedule, a swing-shift schedule, a 12-hour shift
schedule, or a weekend schedule. Learn how to create and assign base
calendars.
The project calendar designates the default work schedule for all resources
assigned to a project. By default, the Standard base calendar is the project
calendar. The working time hours defined on the Standard calendar are the
default working hours and days off for each resource.
You can set up the working days and hours for your project calendar to reflect
the working days and hours for everyone working on your project. You can
specify regular nonworking time (such as weekends and evenings), as well as
special days off (such as company holidays). You can also indicate other
nonworking times to reflect periods when the entire team will be working on
nonproject activities (such as company meetings or departmental retreats).
Learn how to modify the project calendar.
The working hours and days off defined on the project calendar are the default
working times for each resource or resource group. In other words, the
resource calendar is initially identical to the project calendar.
If you want, you can customize the resource calendars for individual resources
to indicate specific working hours, vacations, leaves of absence, and planned
personal time. This can help you create a more accurate schedule, especially if
there are significant variations of working time among resources. Microsoft
Project only schedules resources when they are available, according to their
resource calendars. Learn how to customize resource calendars.
47
_____________________________________ Micro Soft Project Management Manual
If you're working with resources from a shared resource pool, or if you're
sharing resources from another project, there are probably different calendars
in effect. Take note of which project's calendars are in effect when sharing
resources.
You create a task calendar in the Change Working Time dialog box as a new
base calendar. You then apply the base calendar to a task using the Advanced
tab in the Task Information dialog box.
48
_____________________________________ Micro Soft Project Management Manual
for the days you want.
To change a day of the week for the entire calendar, click the
abbreviation for the day in the top row of the calendar.
7 Under Set selected date(s) to, click Use default, Nonworking time, or
Nondefault working time.
8 To change Non-default working time, type the times you want work to start
in the From boxes and the times you want work to end in the To boxes.
Note: After you create a base calendar, you need to assign that calendar to
a task.
By default, your tasks are scheduled by the project calendar. A task calendar
defines unique or specific exceptions for working and nonworking time for a
task or a recurring or summary recurring task.
2 In the Task Name field, select the task to which you want
to assign a calendar.
3 Click Task Information button, and then click the
Advanced tab.
4 In the Calendar box, click the calendar you want to
use for the task.
5 If applicable, select the Scheduling ignores resource calendars check box to
have the task calendar ignore all resource calendars.
Note: If you choose to have Microsoft Project ignore resource calendars, a
task will be scheduled even if resources assigned to the task have
nonworking time set in their resource calendar.
2 In the Task Name field, select the summary recurring task to which you
want to assign a calendar.
3 Click Recurring Task
Information button.
4 In the Recurring Task Information dialog box, click the calendar you want to
assign to the recurring task in the Calendar box.
5 If applicable, select the Scheduling ignores resource calendars check box to
have the task calendar override all resource calendars.
Note: If you choose to have Microsoft Project ignore resource calendars, a
task will be scheduled even if resources assigned to the task have
nonworking time set in their resource calendar.
49
_____________________________________ Micro Soft Project Management Manual
What do calendar options have to do with the working times settings?
The project calendar and resource calendars are used to establish when
resources are available to be scheduled for tasks. You can also use the
calendars to establish a shorter work day or work week for all resources. For
example, you might want to set up a 6-hour day and a 30-hour week to account
for non-project tasks the resources are responsible for. Learn more about
accounting for non-project tasks.
However, if you change the working times, keep in mind that Microsoft Project
still assumes that a day is 8 hours and a week is 40 hours until you change how
Microsoft Project calculates the durations and other time abbreviations you
enter. If you want Microsoft Project to interpret a day as 6 hours, or a week as
30 hours, you need to change the settings on the Calendar tab of the Options
dialog box (Tools menu).
On the Calendar tab, you can indicate the default start and end time for any
dates you enter in Microsoft Project, for example, constraint or actual dates.
You can also establish the number of hours in a day, the number of hours in a
week, and number of days in a month. If you indicate that there are 6 hours to
a day, when you enter a 1-day duration for a task, Microsoft Project schedules
this as a 6-hour day, regardless of whether resources are assigned. Likewise,
when you enter a 1-week duration for a task, Microsoft Project schedules this
as a 30-hour week.
When you first open a new project file, the Standard base calendar is set as the
default for the project calendar. The Standard base calendar reflects the
traditional Monday through Friday, 8:00 A.M. to 5:00 P.M. work week. You can
modify the Standard base calendar to meet your specific project calendar
needs. You can also base the project calendar on a different base calendar,
such as the Night Shift or 24-Hours calendar, or on another base calendar that
you create. Set the project calendar in the Project Information dialog box,
available on the Project menu.
The working times in the project calendar affect the scheduling of all
resources. The project calendar is the basis for the default resource calendar
applied to each resource in your project. You can apply a different base
calendar to a group of resources working a different shift. You can also
customize the working times for an individual resource's working schedule and
vacations. If you apply a different base calendar to resources or customize
working times of an individual resource, the new settings override the project
calendar settings when scheduling resources.
50
_____________________________________ Micro Soft Project Management Manual
The working days and times in the project calendar affect the scheduling of all
tasks. The project calendar is the basis for the default task calendar applied to
each task in your project. You can create and apply a specific task calendar to
a task. If you do this, these new settings override the project calendar settings
when scheduling the task. If resources are assigned to the task, the task is
scheduled by the working times the task calendar and resource calendar have
in common. You can have the task ignore the settings in the resource calendar
by selecting the Scheduling ignores resource calendars check box on the
Advanced tab in the Task Information dialog box.
To summarize, the project calendar applies to all tasks and resources, unless a
specific task or resource calendar is applied.
6. ESTABLISHING LINKS
After you've decided what your tasks should be, you're ready to sequence them
by linking related tasks. For example, some tasks may need to finish before other tasks can begin.
Others may depend on the start of another task.
To select adjacent tasks, hold down SHIFT, and then click the first
and last tasks you want to link.
3 Click Link Tasks button.
Note: If you want to unlink tasks, select the tasks you want to unlink in the
Task Name field, and then click Unlink Tasks button. The tasks are
rescheduled based on links to other tasks or constraints.
51
_____________________________________ Micro Soft Project Management Manual
3 In the Type box, click the task link
you want.
Tip: A simple finish-to-start link does not work in every situation. Microsoft
Project provides additional types of task links so you can model your project
realistically. For example, when two tasks need to start at the same time, you
can create a start-to-start link. When tasks need to finish at the same time, you
can use a finish-to-finish link. Learn about sequencing tasks and start-to-start
and finish-to-finish links.
When you link tasks in Microsoft Project the default link type is finish-to-start,
but you can also link tasks at their start dates or their finish dates.
For example, a museum manager determines that two tasks in her clock
exhibit project (installing the artifacts in their cases and preparing the labels
for those cases) should start as soon as the artifacts have been removed from
storage. Because these two critical tasks involve coordination between the
chief archivist and a volunteer, the manager needs to ensure that if one task is
held up, the other is held up as well. She creates a start-to-start link between
the two tasks, so that they will start as soon as possible, but the successor task
will not start before the predecessor.
When you have unavoidable constraints, such as event dates, you can tie a task or phase to a specific
date. When Microsoft Project calculates the start and finish dates based on the durations and task
dependencies you enter for each task, it applies flexible constraints, such as the default, As Soon As
Possible. Only when there are unavoidable constraints, should you tie a task or phase to a specific
date
52
_____________________________________ Micro Soft Project Management Manual
3 Click the
Advanced tab.
4 In the Constraint type box, click a
constraint type.
5 If you selected a constraint other than As Late As Possible or As Soon As
Possible, type a constraint date in the Constraint date box.
Note: When you schedule your project from a start date, you type a start date
for a task or drag a Gantt bar to change the start date, and Microsoft Project
sets a Start No Earlier Than (SNET) constraint based on the new start date. If
you type a finish date for a task, Microsoft Project automatically sets a Finish
No Earlier Than (FNET) constraint.
You can set lead or lag time for external dependencies just as you would tasks
within the same project.
Note : If a project contains external dependencies, you can open the other
projects and view these dependencies only if each of the linked projects is
saved as the same version on the enterprise server. When you save projects to
the enterprise server (including subprojects that have been inserted into
master projects), the default version is Published. If you cannot open a
subproject or project containing an external dependency, you may need to
resave the associated projects as the same version. To find a project's version,
on the File menu, click Open. Look in the Version column for the project's version.
Tip: You can quickly add lead or lag time to a successor task by double-clicking
the link line on the Gantt Chart, and then typing the amount of lead or lag time
in the Lag box.
53
_____________________________________ Micro Soft Project Management Manual
When you enter tasks and task durations, and then link those tasks, you give
Microsoft Project the most flexibility and power to calculate your schedule as it
changes and to level your resources. Because Microsoft Project takes
constraints into account when calculating your schedule and leveling your
resources, it is important to use them only when necessary.
When you enter tasks and task durations, and then link those tasks, you give
Microsoft Project the most flexibility and power to calculate your schedule as it
changes. Because Microsoft Project takes constraints into account when
calculating your schedule, it is important to use them only when necessary.
The two most inflexible constraints in Microsoft Project, which tie a task to a
specific date, are the Must Start On and Must Finish On constraints. An
appropriate use of an inflexible constraint, for example, is a requirement that a
particular task, such as an event, start on an exact date.
Note: When you enter a start or finish date for task, you automatically apply a
constraint to it. Constraining a task that is dependent on another task can
produce unwanted results, as illustrated in the following example:
The task "Pour foundation" is linked so that it starts as soon as "Dig hole"
finishes; "Dig hole" is supposed to happen on the 10th. If you enter an
inflexible constraint that forces "Pour foundation" to start on the 10th and then
"Dig hole" finishes early, Microsoft Project will not be able to take advantage
of the early finish and move "Pour foundation" to start earlier.
Rather than setting specific dates for a task, consider assigning an As Soon As
Possible (ASAP) constraint and enter a deadline for the task. Entering a
deadline causes Microsoft Project to display a deadline marker on the Gantt
Chart, and you will be alerted if the task's finish date moves past the deadline.
Sometimes, inflexible date constraints (Must Start On or Must Finish On) are
set on tasks unnecessarily or inadvertently. If you use more flexible constraints
on critical tasks, Microsoft Project can calculate the schedule with fewer
restrictions, and you might be able to meet your targeted finish date or use
resources more effectively. Learn more about ensuring that tasks start and
finish on time.
2 Review the indicators column. Any task with the constraint indicator has a
date constraint applied to it. Rest the pointer on the constraint indicator to
see the constraint type and date.
54
_____________________________________ Micro Soft Project Management Manual
3 Get more information about a task with a date constraint by clicking the
task and then clicking Task Information.
4 Click the
Predecessors tab.
5 Review the predecessors of the task to determine how the predecessors
influence the scheduling of this task. You might find that the predecessors
are sufficient to control the task scheduling constraint that's applied.
Review all tasks listed with their constraints
The Constraint Dates table shows the task name, duration, and constraint
type for all constraints (even As Soon As Possible), and the constraint date,
as applicable.
If the field you want to see isn't visible, use the scroll bar, or press TAB to
move to it.
4 On the Project menu, point to Group by, and then click
Constraint Type.
The tasks are grouped by constraint types.
5 In the Constraint Dates table, review the tasks, constraint types, and
constraint dates to determine whether the constraints are necessary.
Review only those tasks that have a date constraint
56
_____________________________________ Micro Soft Project Management Manual
In this unit, use of Ms- Project moves into a new and exciting phase. From
many small projects, it may be enough to create a simple project by setting up
the project, entering project tasks, and scheduling and linking tasks. By the
time you finish with these basic activities, you have a solid, workable plan to
serve as an excellent mangement toolas the project progresses.
In this chapter, we'll discuss how to define project resources and costs. here is
what we will cover.
Estimati
ng resource requirements
Entering
resource
Setting
working times for resources.
Entering
cost information
Project not only schedules tasks, but it schedules the full range of resources
needed to complete a project: individuals, teams, facilities, equipment,
supplies and materials.
After you need that you are going to track resources in the project, you still
have a few more questions to answer:
What kind of resources do you need?
57
_____________________________________ Micro Soft Project Management Manual
How much of each resource do you need?
Where will you get the resources?
58
_____________________________________ Micro Soft Project Management Manual
3. Preparing to Enter Resource Information into your Project
After you determine what kinds of resource you need, how much of each
resource you need, and where you will obtain your resources, you are now
ready to begin creating a draft resource list for your project. You can enter
resources into your project in three ways:
1. Create a resource list with in your Project.
2. Share the resource list created in another project.
3. Share resources with other projects in another project.
A share resource pool is a master list of resources that is shared among
multiple projects in an organization. By using a resource pool, you can
schedule work resources across projects while tracking conflicts, over and
under allocations and availability.
Adding Address book Resources with the assign Resources Dialog Box.
1. Display the Gantt chart view, and click the assign Resources button on
the standard tool bar( or chose Tools- Assign Resources) to Open the
Assign Resources dialog box.
59
_____________________________________ Micro Soft Project Management Manual
Figure
3. Click the Add resources button and then select from Address Book from
the Pull-down menu. Project will launch outlook if it is not already
running. You may be prompted to select a Outlook Profile
4. Still within the Address Book, Locate and double-click the address you
want to add, or select multiple addresses and click Add. If you add a
personal distribution group, all members of the group are added to the
resource list.
60
_____________________________________ Micro Soft Project Management Manual
5. When you finish adding all the resources from the Address book, Click
Ok in the Select Resources dialog box, and closing the Assign resources
dialog box.
You can add additional information about each resources and add material
resources using the Resources sheet and the Resource Information dialog
box.
61
_____________________________________ Micro Soft Project Management Manual
Label tons, pounds, items, gross, and so on.
Initials Text Initials to represent resource name.
Group Text Group name given to similar resources to
indicate the category of resource
(programmer, computer equp., etc). You can
use department names or codes, job titles or
job types, or accounting codes for billing.
Entering a group allows you to display, sort,
filter, or edit resources by the resource group.
Max Units Percentage/ Maximum Percentage or number of units that
Number represent the maximum capacity for which a
work resource is availbe to accomplish any
tasks during the current time period.
St.Rate(Stan Currency Rate of pay per unit for regular non-overtime
dard Rate work. The standard time unit is hour( as
dollars per hour); to enter a different time
unit, include a forward slash and the unit.
Ovt.Rate(Ove Currency Rate of pay per time unit for overtime hours.
r time Be sure to enter a rate here, even if the rate is
the same as the standard rate; otherwise,
Project will calculate overtime hours at $0.00
per hour.
TIP: If many of your resources are paid the same rate, you can set a default
standard rate and overtime rate.
Choose tools menu
62
_____________________________________ Micro Soft Project Management Manual
Choose options to open the options dialog box and then select the
Ge
ner
al
tab
.
In the Default Standard Rate field, type the rate. In the Default overtime
Rate field, enter the overtime rate.
The Default rates are applied to all new resources you created unless you
change it.
4. In the Title field, enter the display name you want to use for the field.
5. Set the assignment for the Column title by choosing Center, Right, or
Left from the Align Title field.
6. Set the assignment for the data cells in the column by choosing Center,
Right or Left from the Assign Data field.
7. Adjust the field width by clicking the box arrows on the width field.
8. Click the Best Fit button if you want project to determine the best
column width, based on the data in the field.
9. Click OK to insert the new column.
63
_____________________________________ Micro Soft Project Management Manual
consists of five tabs, in which you can list more detailed data and include
exception data, such as availability, about a resource
To change a date to a non working date, select the date and then click the Non
working Time. Projects shades the dats in the Calendar and Underlines it to
indicate that it deviates from the Default Calendar.
To change the working hours of a particular day of week( for example, all
Fridays), select the day by clicking the Day header to select the entire
column and then Click the Nondefault working time option. Enter the
scheduled working time in the From and T fields, Press Tab to move
between the To and From fields automatically Selects the contents. When
you have entered new times, project designates the edited working hours
by a lightly shaded pattern.
65
_____________________________________ Micro Soft Project Management Manual
if you want to change any of the Calendar dates back to the default
working times, select the dates and then choose the use Default option in
the Change Working Time dialog box.
Assigning a cost-Accrual Method:- The cost accrual method is the way the
costs will be paid out after the project starts. You have three accrual choices:-
Prorated is the default choice, if attributes costs to the project as the
resources are used.
Start is the choice you want to make if the costs are due to the
beginning of the project.
End is appropriate if the costs are due as the project is completed.
66
_____________________________________ Micro Soft Project Management Manual
To assign a cost-accrual method to the costs, select your choice from
the cost-Accrual drop-down list on the costs tab of the Resource
Information dialog box.
You can insert plain or formatted text into a note, or you can insert an object,
such as a file from word, Excel, or other similar program. When you insert an
object, you can choose to insert the contents of the document, or you can
include an icon like this to represent the document
Whether you insert the object as an icon or insert the entire object, you
can link the object to the original by clicking Create from File and
Selecting the Link Check Box on the Insert Object dialog Box. Any
changes made to the original object are immediately reflected in the
linked object, as long as the original object and project continue to be
stored in the same file locations.
Much of the information you entered in the Resource Information dialog box is
available in the Resource sheet view. If you added a note to a resource, a Note
icon appears in the Indicators column of the resource sheet, as shown in the
67
_____________________________________ Micro Soft Project Management Manual
figure below. Point to the icon to see all or part of the note, or double- click the
Notes icon to read the entire note.
TIP: - A resource pool is a project file created solely for the purpose of storing
resource information that is shared among multiple projects. Creating a
resource pool is generally the preferred method of sharing resources because
it easier to manage task assignments between the resources because it makes
it easier to manage task assignments between the resources shared in the
pool.
TIP:- If you want to enter fixed Costs for the entire project, display the project
Summary Task. Choose- Options from the menu to display the options dialog
box. Click the view tab. Enable the project Summary Task Check box and the
Click OK. The project Summary Task is displayed as the first task in the table.
68
_____________________________________ Micro Soft Project Management Manual
69
_____________________________________ Micro Soft Project Management Manual
Duration: - is chronological: the amount of calendar of click time that will
pass between the beginning and end of the task. Changes in duration affect the
schedule.
Work: -is the number of person- hours or machine- hours on task.
Units: - are the resources committed to the task and are usually expressed as
a percentage (although you can change this setting to use numbers.)
Duration, work, and units are interdependent because work is duration
multiplied by Units, as in the following formula:
W=D*U
Viewing Work, Duration, and Resources
If you want to see work, duration, and resources in one view, there are two
ways to do it: with the Task Form, or by inserting column in a view. Similar to
the Task Information dialog box, Task Form displays information about one
task.
1. In the Entry table, select the task(s) for which you want to make the
assignment.
2. In the Assignment Resource dialog box, select the resource(s) you want
to assign.
3. Click the Assign button.
Note:- A resource can be assigned to a task only once to assign more than
one generic resource (work, painter production and so on) assign a large
70
_____________________________________ Micro Soft Project Management Manual
percentage of the resource- for example 300% painter for three full-time
painters.
4. Adjusting Assignments
Unless you select otherwise, project assumes that all tasks are effort driven.
With effort driven tasks, the task’s duration is completely dependent on the
resources you assign to the task. If you add or remove resources after the
initial assignment, project will recalculate duration but will leave work alone,
such as:
Adjustments to duration when resources are added or removed are the result
of effort driven scheduling. Project implements this type of scheduling if you
assign a resource and then add another resource to the same task.
In the normal course of events from this point forward, adding or subtracting
resources affects only duration because the task’s default effort driven setting
forces project to calculate duration rather than work. To see the recalculation
in action, return to the assign resources dialogue box and then add another
resource. Project adjusts duration; the two people now assigned can be
complete the 16 hours (for e.g) of work in rather than two.
Effort driven scheduling is the default because in many projects, the bulk of
the tasks are effort –driven. Adding resources gets the tasks completed more
quickly.
Each time you edit one of the three variables in the assignments triangle,
project will recalculate one of the two remaining variables. To control which of
the value is calculated, you change the task’s task type and effort settings.
There are three task types: - fixed units, fixed unit, and fixed duration- that
determine which variables project calculates when you assign resources.
Note: Fixed means that project won’t recalculate the field’s value when values
change in either of the other variables. It doesn’t mean that the value can’t
change. You will typically be given the option of changing the value via a smart
tag, and it’s likely that you will often edit this value.
recalculate work. As the project progresses, you will manage fixed unit tasks
that are slipping on the schedule by increasing the units assigned to the task
so you can accomplish the task more clicking.
What happens when you change a fixed unit task?
For this type of task, change the task’s type to fixed unit, uncheck the effort
driven setting, and project will recalculate work and duration; however, it will
not recalculate units.
For this type of task, change the task’s type to fixed duration and then select
the effort driven option.
74
_____________________________________ Micro Soft Project Management Manual
FIGURE: - Use the Options dialog box to set the default task type.
Assigning Resources
An assignment relates a task to the resource responsible for the task. There
are many reasons to assign resources. Here are a few:
Establishing responsibility for the project’s task.
Reporting for project management.
Tracking individual and group performance on tasks.
Accurately measuring human and material resources
used to complete individual tasks, project phases, and the project as a
whole.
Tracking and managing project costs
If you don’t have resources working on a task, don’t assign resources to the
task.
The task form gives you a major advantage when you are assigning multiple
resources to tasks. In the assign resource dialog box, if you change the units
for one resource and then switch to another resource, project assigns the first
resource and then calculates work or duration for the entire task, based only
on the first resource. In the task form, all resources are assigned at the same
time; when you use the task form, project doesn’t accidentally calculate work
or duration prematurely.
76
_____________________________________ Micro Soft Project Management Manual
Variable consumption resources are assigned at an amount per time period
based on the material label listed for the resource.
Choosing the fixed material consumption method indicates that the amount of
material used is not related to the duration of the task.
Using the resource name form: The resource name form displays limited
information about tasks assigned to a resource.
To display the resource name form, choose- More view resource name form to
open the resource name form, shown below in figure.
Using the resource form: The resource form includes editable information
fields for the resource, such as standard, overtime, and per use rates. Double
click a task to open the task information form for the task. Use the previous
and next buttons to move form resource to resource.
Using the Resource Usage form: The resource Usage view gives you an easy
way to view each resource’s scheduled periodic activity. In this view, project
tasks are grouped by resource, and resources are listed in alphabetical order.
Actual Costs
Actual costs include costs incurred by the Project to date for resources and
fixed costs attached to a task. Project calculates this field based on Actual
Work, Actual Overtime Work, Per Use Cost, and Fixed Cost. The formula that
Project uses is
Actual Cost= (Actual Work*Standard Rate)+(Actual Overtime*Overtime
Rate)+Resource Peruse cost+Task fixed cost.
78
_____________________________________ Micro Soft Project Management Manual
Follow these steps to calculate Actual costs manually:
1. Click Tools – then the options and then click the Calculation tab.
2. Uncheck the Actual Costs, are always calculated by Microsoft Project
check box.
3. Click OK to close the options dialog box and save the changes.
4. To apply the calculation method to future Projects, click Set as default.
Actual Work
Project calculates Actual Work based on the amount of work completd by the
resources assigned to the project. This field is not available if you do not have
resources assigned to a task. When you manually enter Actual Work, Project
Calculates Percent Work Complete and Remaining Work according to these
formulas:
Percent Work Complete= Actual Work/Work.
Remaining Work= Work- Actual Work.
When you enter Percent Complete, Percent Work Complete, or Actual Work,
Microsoft Project updates Actual Work for the task.
To enter date into the Table, Click the appropriate cell and then
click the down arrow. Select a date from the drop-down Calendar.
To enter numeric values in fields such as % Comp. and Act. Dur,
first click the cell, then use the spin box controls to change the values, or
simply type a number in the cell.
79
_____________________________________ Micro Soft Project Management Manual
To update tasks for the entire project up through a specified date by using
the update Project dialog box, follow these steps:
1. On the View menu, click Gantt Chart.
2. Select Tools- then Tracking – and then Update Project.
3. Click Update Work as Complete Through; then type the date through
which you want progress updated.
4. Click set 0% or 100% Complete only.
5. Select Entire Project.
6. Click OK
NOTE: If you want to update tasks in the Project, select those tasks before
opening the update Project dialog Box.
80
_____________________________________ Micro Soft Project Management Manual
Chart, the pointer changes to a % symbol with a right-pointing arrow. Drag
the arrow over the Gantt bar until the correct Complete Through date
appears in the information box that opens.
SV=BCWP-BCWS
CV=BCWP-ACWP
Cost Performance Index (CPI) is the ratio of baseline budget costs to the actual
costs incurred for the task (CPI=BCWP/ACWP).
To see all the earned value variances and Cost estimates, display the Earned
Value Variances and Cost estimates, display the Earned Value table in any task
view. To display earned value columns in a Gantt Chart:
1. Switch to Gantt Chart view (view- then Gantt Chart).
2. Choose View- then Tables – and then Tables to open the More Tables
dialog box
3. Select the Earned value Table and then Click Apply.
To display the view bar, select view-, Repeat this procedure and then deselect
the view Bar option to hide the bar.
83
_____________________________________ Micro Soft Project Management Manual
Calendar View.
Calendar View, a member of the task view category, focuses on task date and
deadlines. To see tasks displayed as bars that span the days on which they are
scheduled, select view- Calendar.
If you want to see more weeks within the calendar windows, drag the
horizontal line between each calendar week upward. This enables you to see a
larger portion of the project timeline, although some of the tasks may be
hidden. Notice a downward pointed arrow Called the over flow Indicator) on
any date when there are tasks you can’t see Double click the indicator to
display a dialog box showing all tasks for that day, their durations, and start
and end sates.When you want to specifically focus on a particular week or two
weeks, drag the horizontal week separator downward to display fewer dates
with more detail for each date.
You can also choose a display format for month, week, and day names. You can
also choose five-day or seven-day weeks as well as a myriad other option. From
Calendar view, click Format- time Scale to Open Timescale dialog box.
On the week Heading tab, choose the formats you want to use for Monthly,
Daily, and Weekly. Enable the Previous/Next Month’s Calendars feature to see
a 30-day thumbnail of the preceding and following months.
- To Format each Calendar day to look the way you want it to, select the
Date boxes tab, choose the type and style of information you want
displayed at the top right and top left of each row; then choose a pattern
and color to shade the top of each calendar day, you can also format the
bottom of each square, but to display a pattern an/or color, you must first
change one of the Bottom Row (Left or Right) default settings to
something other than None.
-To choose specific patterns and colors for certain types of days, select the
Date Shading tab. By default, all working days show up while, and non
working days are shaded gray. Change the defaults for the standard project
calendar, the 24-hour calendar, or any of the resource calendars.
From Calendars view, choose Format- Bar Styles to open the Bar Styles dialog
box. You can see a list of the task types at the left of the Bar Styles dialog box.
Choose the task type you want to format and then do the following:
1. Set your shape options by choosing a bar, pattern, color, and split
pattern.
Note: - If there is task type you don’t want to display, choose it and then
select None as its bar type.
2. If you choose Bar as the bar type, you can enable the shadow, option, if
you want.
3. Enable the Bar Rounding feature if you want to show bars across a
fullday. Enabling or disabling this feature does not affect the actual
duration of the a task- only the way it is displayed.
4. Using the Fields drop-down list, select the fields you want to appear as
text on each bar. To choose more than one field, select the first field,
type a comma after the first field name, and the second field.
5. position the text within each bar using the Align and Wrap options
Display more of the existing fields in the task list by dragging the window
divider to the right, effectively shrinking the size of the Gantt Chart Windows.
Widen the graphical portion of the window by dragging in the opposite
direction.
Gantt Chart View is most typically used for entering tasks and all details
associated with a task, such as duration, priority, assigned resources,
predecessors, constraints, percent completed, and more.
85
_____________________________________ Micro Soft Project Management Manual
FIGURE:- The Bar Style dialog box for Gantt Chart view.
TIP: - You can also double-click any in the Gantt Chart to open the Bar Styles
dialog box.
The fields of data displayed are listed in the Name Column of the dialog box.
To delete information from the Gantt Chart, click one of the fields listed in the
Name Column and then Click the Cut Row button at the Top of the dialog box.
Add data fields in the Blank rows at the bottom of the list. If you want to add
the field in the middle of the list, click in the row below where you want the
new field added and then click in the row below where you want the name of
the field in the Name Column; then choose one of the Show for options from
the drop-down list that appears when you click in the third column. Choose the
bar formatting you want for the field by using the drop-down lists shown on the
Bars tab of the dialog box. The start and end Settings are optional; use them if
you want to display a symbol at the start or end of the bar, representing the
field you’re formatting.
Display any project field as text by choosing the field on the Text Tab of the
Bar Styles dialog-box. Decide where you want the text positioned relative to
the bar: left. right, top, bottom, or inside. Click beside that position to activate
drop-down list, and choose a field name from the list.
86
_____________________________________ Micro Soft Project Management Manual
TIP: - If you want to make a number of formatting changes to the Gantt Chart,
or you want to design your own Gantt Chart, the Gantt Chart Wizard walks you
step-by-step through a variety of formatting options for tasks, links, and fields.
There are three tiers to consider when formatting the timescale, each with its
own tab in the Timescale dialog box(There’s a fourth tab for formatting the
appearance of non-working time.) The top Tiers
(turned off by default) is typically used for displaying years or quarters. The
middle tier is typically used for displaying weeks or months. The bottom tier is
typically used for displaying individual days or hours.
1. Select the line you want to change from the list on the left. Gantt Rows
correspond to the numbered rows in the task list. Major Columns
87
_____________________________________ Micro Soft Project Management Manual
correspond to the Major Timescale, and minor Columns correspond to
the Minor Timescale.
2. In the Normal section of the dialog box, select the type and pattern for
the gridline.
3. If you want to get grid of an existing gridline, select it from the Line to
change list and then click the blank area in the type drop-down list.
4. Certain gridlines appear repeatedly, so you can apply contrasting
gridlines at specific intervals. Select an interval, line type, and line color.
If those options are disabled, it’s because you have selected a line type
that does not repeat. To skip a gridline at certain intervals, click the
blank area on the type list in the At Interval Settings.
88
_____________________________________ Micro Soft Project Management Manual
The Box Styles dialog box works the same way as the Bar Styles dialog boxes
we explored in Calendar and Gantt Chart views. Select the type of task from
the style settings for list on the left; then configure the Border and Background
settings. you’ll like the unique feature of this dialog box. You can actually
choose the task you want to use in the preview by adjusting the show data
from Task ID field.
To create a new template, click the More Templates button to open the Data
Templates dialog box; then choose New to open the Data Template Definition
dialog box; then choose new to open the Data Template Definition Dialog Box.
1. Enter a name for the Data Template in the Template Name field.
2. Click the cell layout button to choose the number of rows and columns
you want in the node. Change the cell Width setting if you want the cells
in the new template to be larger or smaller than the cells of the standard
template. you probably want to keep the merge Blank cells with cells to
the Left option; otherwise, the Task Name displayed would be cut off. As
long as the cell to the right is blank, why not let the data spill over?
3. After you configure cell layout settings, choose the data fields you want
to display in each cell. Click a cell in the choose cells area of the dialog
box to enable a drop down list of project fields. Select a field from the
list.
4. Choose a font for each cell of the node. When you click the Font button,
the settings your chose are applied to the selected cell(s). It’s easy to
bold one field and leave the rest of the data in the default font (Arial 8
pt.). To make all cells the same font, select them all from the choose
fields area of the dialog box, click Font, and Choose settings.
5. Select a Limit cell Text to setting for each cell, it makes sense to make
the Name cell two lines (or more), but you wouldn’t need that much
space for a field such as Resources Initials.
6. Choose a Horizontal and vertical alignment setting for each cell. Enable
the show Label in cell field if you want the field name to precede the data
in each cell. (You’ll need relatively large cells to do this) otherwise, most
of the data windup out of view.)
7. If the Selected cell is a date field, you can choose a date format from the
drop-down list of the same name.
8. Click OK to return to the Data Templates dialog box. Click close to turn
to box Styles, click OK, and you’re done!
You can apply this new template to any type of task in Network Diagram view.
Simply open the Box Styles dialog box (format- Box Styles), select the type of
task from the list at the left, and select the template from the Data Template
drop-down list. You can then change border and background settings for the
task type displayed in this template.
89
_____________________________________ Micro Soft Project Management Manual
Task usage view focuses on how much each resources has completed overtime.
Use this view to compare actual work and costs to budgeted works and costs.
Select View- task Usage to display the two-paned window.
The pane on the left of the figure shows tasks with the assigned resource
indented below. The fields displayed on this side of the window focus on the
task by default, but you can customize it to display other data by applying a
different table.
The right portion of the window (the timeline pane) displays information
related to the resource. By default the timeline pane describes work (total
person-hours) for each task. Add another Detail field by right-clicking any cell
in the Details column, or by clicking Format- Details on the menu and then
choosing another field.
Right-click again to deselect Detail fields you don’t want t view. If the field you
want to detail isn’t on the menu, you can gain access additional fields by
choosing Detail Styles from the shortcut menu to open the Detail styles dialog
box( Alternately, you can click Format- Detail Styles.)
Resource views
The resource views all relate to assigning and tracking the use of human
resources, materials, and equipment used to complete the project. Remember
90
_____________________________________ Micro Soft Project Management Manual
that a resource can be an individual, a company, department within a
company, a team, a piece of equipments, a room, or any other resource you
need for the project.
Many of the project views enable you to see which people you’re driving
toward premature burnout (what project politely cells over allocating);
however, resource views tend to make it overtly apparent which resources are
being worked past the number of hours available in their calendars.
Resource Graph
To see work allocation, or cost information about a resource represented
graphically, display the Resource Graph (view- Resource Graph). Similar to
Network diagram view, you can easily become lost in the resource graph. It
helps to have Specific dates in mind when you’re viewing work assigned to a
particular resource. If the project timeline is scrolled to a time period where
the selected resource has no assigned tasks, you’ll see nothing in the timeline
pane!
It may not look like it at first, but the resource Graph view is actually two
separate panes. The selected resource is displayed in the left pane, and that
resource’s allocation is shown in the right pane. Scroll the left pane of the split
window to select the resource you want to see in the pane on the right. Scroll
window to select the resource you want to see in the pane on the right. Scroll
the right pane to move the timeline to correspond with the scheduled start and
end rates for tasks assigned to the selected resource.
By default, the detail field shown in the timeline pane is Peak Units (the
combined time required for all tasks assigned to that resource at a given point
in time.). Change the detail by right-clicking on the chart and then choosing
Bar Styles. Select a new type from the Show As Field in the Bar Styles dialog
box.
Resource Sheet
Resource sheet view (view-Resource Sheet) provides a summary of information
about resources in a spreadsheet format. In this view, you can enter and
review information resources: names, assigned groups), regular and overtime
rates, and so on.
Choose this view to quickly put together a list of resources with details about
each. If you want to review information about resources with details about
each. f you want to review information about resources in a non-graphical
format, this is also a good view. Compare the number of work hours assigned
to each resource, or compare resource costs (actual& budgeted.)
Add fields to the default table by right-clicking the column header to the right
of where you want your new column. Choose Insert Column from the shortcut
menu to open the column Definition dialog box.
Choose the field you want to insert from the field Name drop-down list. Type a
different display name for the field (if you want one) in the Title field. Set
Assignment and width options, and click OK.
Resource Usage
91
_____________________________________ Micro Soft Project Management Manual
Resource Usage view (view- Resource Usage) groups tasks by resource and
displays the amount of work, allocation, and work availability for each
resource. (Of course, you can add fields to the table in the left pane by right-
clicking a column header, as described in the previous section.
Customize the timeline, gridlines, and text Styles by choosing those options
from the Format menu, or by right- clicking the portion of the view you want to
format.
More Views
Understanding and using the standard views described so far can be daunting
especially for a new user. But the true Microsoft Project experts wants more
and more Project has more to give! Select view- More views to see additional
view selections. If the available list doesn’t contain exactly what you’re looking
for, you can create your own view
Resource Tables.
Several table views are available to assess Resource information. In the More
Tables Dialog Box, Select Resource to see a list of prefabricated Resource
Tables. Again, we have already seen many of these tables as we’ve explored
Resource views.
92
_____________________________________ Micro Soft Project Management Manual
If you want to change table configurations for the active project, but you also
want to leave the original settings intact, open the More Tables dialog box
(view- table- More Tables), select the table you want to modify, and click the
copy button. A working Copy of the original table is created and the Table
Definition Dialog Box opens.
1. Select view- more views to open the More Views dialog box.
2. Click the view you want to use as a basis for your new view and then
click copy. If you want to create a new view from scratch, simply click
the New button. If you choose copy, the view Definition dialog box opens.
If you choose New, you get the Define New view dialog box.
3. If you’re starting from scratch, choose whether you want a single pane
view or combination view in the Define New dialog box and then Click
OK. The Single view choice takes you to the view Definition dialog box
shown above. The Combination view choice takes you to a slightly
different view Definition dialog box.
4. In the view Definition dialog box, type a name for your new view if you
want what you want to display in the top and bottom panes, and enable
the Show InMenu option. For new views based on another view, choose a
different table, group and/ or filter for this view.
93
_____________________________________ Micro Soft Project Management Manual
5. Click OK when you’re through, and the new view appears along with the
others in the More views dialog box. Click Apply to see your new view, or
click close to exit the dialog box without changing the current view.
Sorting a View
Changing the sort order doesn’t hide any of your data; it jut puts it in a
different order. The default sort for most table views is ascending ID order;
that is, the lowest ID number appears at the top of the list. Most views, except
Network Diagram view, can be sorted, and some have more fields available to
sort by.
In general, choose the view you want to sort, click Project- Sort, and Choose
the field you want to sort by. You’ll get ascending (A-z and 1-10) order if you
choose one of the fields on the menu.
If you want to sort in different order or if you wish to use a multilevel Sort
(resources by last name, then by first name). Click Project- Sort- SortBy to
open the Sort dialog box.
The current sort settings are displayed when the dialog box opens. Choose a
different field from the sort By List. For Secondary and tertiary sorts, choose
fields from the Then By lists, and choose ascending or descending order for
each field. If you want items permanently renumbered after the sort, enable
that option. For task lists, choose whether to maintain the outline structure.
When you sort a combination view, all panes sorts that means that bars on the
Gantt Chart are reordered when you sort the accompanying task list.
Applying a Filter.
Too much data to grasp in a single-glance? Try filtering the data displayed. It’s
fast and easy, and enables you to see relevant portions of data while hiding the
rest.
Autofilters provide one of the quickest ways to pull relevant portions of your
data for viewing. The AutoFilters appears as down arrows as the right of each
column header. Click the filter arrow for the field you choose the value you
want to display. Project applies a [field you filtered on] equals [value you
choose from the list] test to determine which rows of data to display.
94
_____________________________________ Micro Soft Project Management Manual
Project applies the filter, and shows that are within or not within the
designated range.
The Contains Exactly filter is a hybrid of both Equals and Contains. The
difference is that Contains Exactly allows you to search for individual values in
fields where you have entered multiple values.
Can’t find the filter you want to use? Spend a few extra minutes and create
your own custom filter. You’ll follow the same basic steps as you do when you
create your own tables or views. Specifically:
95
_____________________________________ Micro Soft Project Management Manual
1. Click Project- Filtered For- More Filters to display the More Fiters dialog
box.
2. Choose one of the filter options based on what you want to modify: task
filters or resource filters.
3. Choose a filter on which to base your new filter and then click copy, or
click New to create a new filter from scratch.
4. In the Filter definition dialog box, enter a name for your new filter, and
enable the ShowIn Menu option.
5. Choose new or edit existing operators, fields, and values. When multiple
tests are used, Project can apply filter criteria to groups of expressions, if
you leave a blank line between criteria groups.
6. Within groups of three (or more) expressions, the and statements are
evaluated before the Or statements, Between groups, however,
expressions are evaluated in the order they appear.
7. Use Cut, Copy, Delete, Paste, and Insert to move, duplicate, remove, or
add filter criteria.
8. Click Ok when you’re finished. The new view shows up in the More Views
list as well as on the menu, if you enabled that option.
Grouping views.
Project enables you to categorize resources by grouping them in ways that
make sense to you. After groups are assigned, you can sort, filter or edit
resources by group.
The Group field is displayed by default in Resource sheet view.
When you’re entering resource information, simply type a group name in the
field. Resources with the value in the Group field are, of course, assigned to
same group.
Let’s say you want to see the critical tasks assigned to each group. Grouping
resources based on multiple criteria requires some additional configuring.
Make sure that all resources are assigned to a primary group and then create a
custom group as follows: -
1. Click project- group- More groups to open the More Groups dialog box (It
should look familiar by now. It looks similar to the More Tables. More
Views and More Filters dialog boxes.
2. Select either Task or Resource, and click the New button to open the
Group definition dialog box. Alternately, you can choose an existing
grouping on which to base your custom group by clicking the copy
button.
3. Give your new group a name and then choose the field you want to group
by. Change the order default to descending. You might want to do this if
you’re grouping by a numeric interval, such as cost, so your highest cost
appears at the top of the sheet.
4. Configure formatting options if you want them to be different from the
default.
96
_____________________________________ Micro Soft Project Management Manual
5. If you’re grouping on a numeric field, the Define Group Intervals button
will be enabled. Configure an interval for the field in the dialog box that
appears when you click the button.
6. Enable the show Summary Tasks feature, if you want.
7. Click Ok to close the Group definition dialog box and return to More
Groups.
On the Margins tab, you can edit the default settings of ½ inch all around, and
choose whether and where to print page borders.
97
_____________________________________ Micro Soft Project Management Manual
Adjusting settings the same, whether you’re working on a header or footer or
Legend- just make sure that you’re on the appropriate tab of the dialog box
before you start; then do the following:
1. Choose whether you want the information at the left, center, or right of
the page by clicking one of the corresponding tabs below the preview
window.
2. Click in the white space below the tab you selected, and type information
you want to include, and/or
Click one of the header/footer shortcut buttons to insert page numbers,
current date and time, filename, or pictures, such as company logo. If
you want to format the text, select it and then click the Format Text Font
button.
3. insert standard information fields such as manager’s name and company
name, or select from a list of common Project fields choose from the
drop-down lists under the shortcut buttons and then click the Add button
to the right of the list.
4. For legends, you must choose whether you want the legend to appear on
every page or on a page all its own. Click the Legend Labels button to
format this area of the Legend.
5. when the preview portion of this dialog box appears like you want it,
click print to open the print dialog box and then proceed with printing.
Alternately, you can click print preview if you want to see the entire
printed page, or click OK to close the dialog box & print later.
Note: - It’s important to note that headers, footers, and legends are specific to
the view or report in which they are created. That means is you’ve configured
a legend in Gantt Chart view, the same legend does not print in Network
Diagram view unless you reconfigure it for that view.
project prints down and across, left to right, starting in the upper left corner of
the view. Each page is numbered in the sequence it prints. if you’re interested
only in printing the first few tasks in the project, you might need to print only
two of the pages from the Gantt chart view (the sheet with the few tasks and
the corresponding chart bars). You do this by clicking File- Print to open the
Print dialog box and then entering the pages you want to print in print range
section.
If you’re trying to print a specific portion of the view, try inserting manual
pages breaks before and after the section you want to print.(Select the task
you want to be first on the printed page and then click Insert- page break). In
the print dialog box, choose the page(s) you want, and make sure that the
manual page Breaks setting is enabled.
-To delete a page break, select the cell below the break and then click Insert-
Remove Page Break.
Overview Reports
An overtime report provides just: an overview of an aspect of the project at a
fixed point in time. These reports work well with managers, team members,
and stakeholders a like. Click the overview button in the Reports dialog box
and then click Select to see the Overview reports.
Cost Reports
99
_____________________________________ Micro Soft Project Management Manual
In the real world, success or failure of the project is often measured in dollars.
You might finish on time with product, but if you’re double the budget,
stakeholders are likely to be displeased.
Costs reports allow you to catch discrepancies early on while there’s still a
chance of pulling your project back on budget.
Assignment Reports.
Resource reporting is the focus of the Assignments reports. You can print task
lists for the entire team and then review them all at once; or you can select a
resource and then print a list of that person’s tasks with completed tasks
checked off . When you click the Assignments button in the Reports dialog box,
you’ll see four choices.
Customizing Reports.
There are really only two types of customization for reports (and views); you
can change the appearance (formatting), and you can change the content
certain reports such as the project Summary will let you change only
appearance. Others offer dozens of options for changing both appearance and
content
4. Click the Text button to choose a font, font style, font size and color
for fileds of a certain type.
Resource Details (or Task Details). You use the Details tab to select which
fields to display in your report. For each field that you enable, except objects,
information prints once per resource or once per task. Enable the Predecessor
check box and each task shows predecessor information.
Assignment details: - The choices you make here determine the fields that print
for each resource (in Resource reports) or each task ( in Task reports)
Show Totals: - Enable the Show Totals Check box ( on the Details tab) if you
want numeric field totaled.
Sort Order: - Choose a Sort order using the controls on the Sort of this dialog
box.
Inserting a New object.
The Insert Object button is found on the Notes tab both the Task Information
and Resource Information dialog boxes. when you click the Insert Object
button, the Insert Object dialog box opens. After you open the Insert Object
Dialog box, you have two choices, you can create a new object from scratch, or
101
_____________________________________ Micro Soft Project Management Manual
you can insert an object create a new object from scratch, or you can insert an
object that already exists.
Let’s assume that you’re attaching this new object to a resource. In the
Resource Information dialog box, click the Notes Tab; then click the Insert
Object button to open the Insert Object dialog box. Make sure that the create
New option is selected at the left. Scroll the to choose the type of object you
want to create, and Click OK.
the resource name to open the Resource Information dialog box, right-click the
Notes icon and then choose Resource Notes from the Shortcut menu. You’ll see
the object or an icon representing the object. If it’s an icon, you have to
double-click one final time and you’re there!
If you want an object you’ve attached to Notes to appear in a printed report,
you have to edit the report to include Notes in the details. From the top, do the
following:
1. Click view- reports to open the reports dialog box.
2. Choose the type of report you want to print. Let’s say you’re printing a Who
Does What report, and you want to see the pictures you’ve attached to each
resource to each resource Choose Assignments and then click select.
Drawing An object.
To create a drawing object, follow these steps: -
1. Click once on the button to select the type of object you want to draw.
The mouse pointer changes to cross- hair.
2. Click and drag on the Gantt Chart. Release the mouse when the object is
the approximate size you want.
Note: - If you’re creating a polygon, you have to drag a line for each side of
the shape. When you draw the final line that completely encloses the shape,
the polygon tool turns itself off.
3. Move and/or resize the object as needed. To resize, simply point to one of
the object handles. When the pointer changes to a two-headed arrow,
drag the object smaller or larger. (If you’re trying to resize a polygon and
dragging the handles only changes its shape, click Draw- Edit points) to
move the object, point at it(but not a handle), then click and drag to the
new location.
4. Format the object as desired (see the following section)
Formatting An Object
By default, all project drawing objects have a black line and white fill. If all you
want to do is change the fill color from white to another solid color, you can
select the object and then click the cycle Fill color button on the Drawing tool
bar. Continue clicking until you see the fill color you want.
To change the fill pattern, the border width and color or to remove the border
completely you’ll have to adjust the object’s properties. Select the object and
then choose Format- Drawing- Properties or right-click the object and then
choose properties from settings until the Preview window displays the look
you’re aiming for; then click the size and Position tab to see additional
settings.
Use the Attach To timeline option to anchor the drawn object vertically and
horizontally, relative to the timescale. the Date control determines where the
object anchored horizontally. The vertical control reflects the amount of space
between the top of the object and the timescale area of the Gantt Chart.
Use the Attach To Task Option to keep the object with the selected task, even
if the task gets delayed or scheduled for different start date. Enter the ID
number of the task you’re attaching to get and then choose whether you want
to attach at the begging or end of the task bar. Adjust the vertical and
horizontal spin settings to determine the position of the object relative to the
task bar to which it’s attached.
Here’s where it can be a bit tricky. If you’re attaching the object to the left end
of the task bar, the horizontal spin setting must be a negative number, or the
object will still appear to the right of the Task bar. If you’re attaching to the
positive number. If both horizontal and vertical settings are set to zero, the
object will appear on top of the task to which it’s attached. You can quickly
103
_____________________________________ Micro Soft Project Management Manual
access the Attach To Settings of a selected object by clicking the Attach To
Task button on the Drawing toolbar.
9. Closing a project
The single most effective trait of a successful project manager is the ability to
close a project with the same level of enthusiasm as when it is started. Closing
a Project can be the easiest and the hardest part of project management- it
involves a rigorous evaluation and review of the decisions, processes, and
effort that went into making a project success or doomed it to failure.
The process involved in closing a project can be as critical as the process
involved in defining and designing the project at the outset. if your goal is
continual quality improvement, it is imperative that
104
_____________________________________ Micro Soft Project Management Manual
every project success or failure be carried through to its conclusion- you
cannot improve if you don’t know what it is you are improving.
After you decide that a project has met its objectives= or that it will not reach
its objectives- you can proceed with the other steps involved in closing a
project. These steps include the following: -
conducting a project review, including a review of the processes
used in the project
Evaluating project results.
Communicating information about the project results to all the
stakeholders.
Preparing for future projects.
Milestones Report
105
_____________________________________ Micro Soft Project Management Manual
The milestone report, found by clicking the Overview category of the Reports
dialog box. It includes Task ID, Task Name, duration (o) Start and finish Dates,
and Predecessors.
106