document2
document2
ISSN 2091-2730
ABSTRACT - In the recent past the infrastructural development in India has been developing at a rapid rate. The
infrastructural development plays a major role in the economic development of the country. There are several risks allied with the
construction industry. Managing risks in construction projects has been recognized as a very important management process in order
to achieve the project objectives in terms of time, cost, quality, safety and environmental sustainability. Project risk management has
been intensively discussed in recent years. This paper aims to identify and analyze the risks associated with the development of
construction projects from project stakeholder and life cycle perspectives in terms of human safety and its effect on time and cost. This
can be done by calculating the productivity rate of the labors and also analyzing the organization needs from the work force. This
research found that these risks are mainly related to contractors, labors who directly take part in the construction process. Among
them, tight project schedule is recognized to have high influence on all project objectives maximally. In this study the survey has to be
conducted with in various construction industries in Tamil Nadu and the opinion at various levels of management through the standard
questionnaires are to be collected and the result are to be analyzed and aims at providing recommendations to overcome those risk
mitigations.
Keywords—risk, risk management, construction projects, labour risk, human safety, productivity, life cycle perspectives.
1. INTRODUCTION
76 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
2.1 Risk
Risk An uncertain event or condition that results from the work, having an impact that contradicts expectations. An
event is at least partially related to other parties in a business.
Risk management is recognized as an integral part of good management practice. To be most effective, risk
management should become part of an organization's culture. It should be integrated into the organization's philosophy,
practices and business plans rather than be viewed or practiced as a separate program. When this is achieved, risk management
becomes the business of everyone in the organization. Risk management enables continual improvement in decision-making. It is
as much about identifying opportunities and avoiding or mitigating losses.
• Inability to work.
• Unwillingness to work.
• Insufficient labours.
These are some of the major factors that causes damages and situation of risk in the construction site. There are several other factors
that also involved in the factor causing the situation of risk. These factors are to be identified from technicians point of view and also
from labours point of view so that the actual situation or the factors causing the risk are identified.
In the recent past 'Lean Construction' - a philosophy based on the 'Lean Manufacturing' approaches undertaken in
the automotive industry has been applied to reduce wastes and increase efficiency in construction practices. The objective of
Lean Construction is to design a production system that will deliver a custom product instantly on order but maintain no
intermediate inventories. Applied to construction, 'Lean' changes the way work is done throughout the delivery process.
Current construction techniques attempt to optimize the project activity by activity and pay little attention to how value is created
and flows to the customer.
Labor productivity has a major impact on whether a construction project is completed on time and within budget. Therefore,
it is important for construction managers to improve the conditions that affect labor productivity on their jobsites. Work sampling is a
method that evaluates the amount of productive, supportive, and non-productive time spent by the trade workers engaged in
performing their assigned work activities. It also helps identify any trends affecting labor productivity.
Construction companies are constantly searching for ways to improve labor productivity. Since labor is one of the greatest risks in a
construction contract it must be controlled and continuously improved. The construction company with the most efficient operations
has a greater chance to make more money and deliver a faster construction project to the project owner. There are several factors that
affect labor productivity on a jobsite such as weather conditions, workers’ skill level, overcrowding of work crews, construction
methods used, and material delivery/ storage/ handling procedures.
77 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
Date 12-sep-13
Time Total
No of Man- Team
Time Labour Consumed Time Reason for NVA Impact
labour days Observation
(in hrs) Consumed
08:00:00
09:00:00 Skilled 15 0.5 7.5 1 NVAN Minor Resources 4.1%
10:00:00 Skilled 190 0.5 95 12 NVA Water & restroom 4.1%
11:00:00
13:00:00 Skilled 190 1 190 24 NVA Lunch 8.2%
14:00:00
15:00:00 Skilled 190 0.5 95 12 NVA Water & restroom 4.1%
16:00:00
17:00:00
18:00:00 Skilled 190 0.5 95 12 NVA Snacks & Tea 4.1%
19:00:00 Skilled 55 2 110 14 NVA Lighting 4.8%
20:00:00 Skilled 190 0.5 95 12 NVA Snacks 4.1%
21:00:00 Skilled 20 0.5 10 1 NVAN Minor Resources 4.1%
22:00:00 Skilled 190 0.5 95 12 NVA Water & restroom 4.1%
23:00:00
00:00:00
Total 100
Total Man-day per day 285
*VA- Waste % on crew 36%
valuable activities NVA- non valuable activities NVAN-non valuable activities by labour.
78 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
Better planning improves productivity by reducing delays, getting the work done in the best constructability sequence,
matching manpower to available work, coordinating multiple interdependent activities, etc. The relationship is obvious and very
powerful. One of the very most effective things you can do to improve productivity is to improve planning.
79 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
100% 100%100%
100%100% 100% 100% 100%
100%100%
100%
100%
86%
71% 79%
79%
80% 71% 71%
71%
62%
57%
60% 54%
40% 31%
29% 29% 29%
29%
20%
0%
0%
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Pour 1 Pour 2
Fig 2.1 Floor level VsPercentage Work Completed
From the graph it is incurred that the completion of the work within the cycle time is in increasing order but not with in the
specified time of completion. An average of 70% of the planned completion of the work are carried out in every cycle time. This
shows that 30% of the remaining work are completed with extra time or extended time of completion. It is inferred that there should
be a constrain for the labours to finish the work completely within the stipulated time.
It is in the recent trend of economy that the real estate company or the builders want to finish the project as for as possible so
that the consumer will satisfied and the margin of profit will rise. The companies are in a look of finishing the project on before hand
by continues and fast working. This greatly affects the labours in several aspects such as mental stress, health problems etc. If the
workers are likely to act as per the companies needs there should be a situation of risk occurs. This create situation of damage or even
cause loss of life.
2.6 Productivity
Productivity in the sense the amount of work done by the in a work man day or in a hour. Different companies having
different productivity rate.Construction companies are constantly searching for ways to improve labor productivity. Since labor is one
of the greatest risks in a construction contract it must be controlled and continuously improved. The construction company with the
most efficient operations has a greater chance to make more money and deliver a faster construction project to the project owner.
There are several factors that affect labor productivity on a jobsite such as weather conditions, workers’ skill level, overcrowding of
work crews, construction methods used, and material delivery/ storage/handling procedures . Several methods exist for measuring and
analyzing worker productivity. In this study video visual of the progress of work is monitored using the cctv cam recording system.
This helps greatly in watching the progress of work without any obstructions. Since the camera is located in the highest elevation
points such as tower crane.
80 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
Productivity is simply the ratio of overall quantity of work done to the ratio of quantity of lobours who take part in the
completion of the work in one day or one cycle time.
In this study both the productivity rate of concrete work and the steel work are calculated as the structure was a typical shear
wall structure. The labours involved in this category are carpenter and the bar benders. They are accompanied by the helpers so as to
help the work force in the completion of the work within the stipulated time. The shear wall structure of the typical block 9 be filled
with 2950 sq.m of formwork and 20.59 tons of rebar work. Each block of the typical floor 9 is to be filled with same amount of
resource materials as mentioned. The concrete is prepared in the site itself where a RMC plant was located. Necessary peptalk and
safety precautions are provided for the labours every day before going for work by technicians and the concerned officers. These are
necessarily done to increase the productivity rate.
A meeting was held with the general manager of the contractor in question to describe the procedures of the work sampling
study. The data collection method was described as well as the type of information that could be extrapolated during the analysis
phase. After the general manager was familiar with the process and the information that could be obtained from a work sampling
study, an objective was determined. The contractor wanted to have a baseline of the labor productivity for the company’s profit
centers.
81 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
The above tables shows the total amount of workers worked in each floors to accomplish the cycle time project. It is clear
that the above work force worked in each floors only completed the work. Their productivity rate only be used or consumed for the
completion of the block 9 of the project. There is a great fluctuation in the amount of workers employed in the construction process in
every floor. Thus the productivity rate of the workers will be increased due to shortage of labours. This increase in productivity falls
on the head of the concerned labours employed to complete the project within the stipulated time.
The table shows the productivity rate of each the carpenters and the bar benders in each floor that the average rate of productivity for
each labour concerned with thework are calculated. But it is noted that the productivity rate of the company was not achieved as the
average productivity rate of each labour in the work concerned are low. There may be several problems that may cause or stops the
worker. The worker available in the work for a day will not be available on another or next day or the forth coming cycle wor k as
there is a increase in the productivity rate of the work concerned.
82 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
10.0
Productivity (in sq.m/Man – Day)
8.1 Pou
7.6 7.8
8.0 r1
6.2 6.3 6.4 6.4
6.0 5.3 5.25.3 5.4 5.3
4.7 4.9 4.3
4.9 4.6
4.0 3.8 4.2
3.8
4.0 3.4
3.33.0 3.3 3.7
2.02.4 2.4 2.7
1.7 1.9 1.6
2.0 1.1
0.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Floor (in No’s)
60
Productivity (in kg/Man – Day)
49 Pou
50 46 44 46 45 r1
43 42
42
38
38
40 35 35 34 34 35 36
35 35 35
34
30 31 32 32 30
30
30 2627 2727 28 27 27
24
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Floor (in No’s)
This shows that the average productivity rate of the form work fixing and reinforcement work. The average productivity rate
displays that the companies productivity rate was not achieved so as to complete the project within the stipulated time and also to
achieve the calculate margin of profit. In the economic point of view it recogonised that people may want the facility as for as possible
so that they can satisfied. It is why Honda maze car selling at a rapid rate than any other cars. As because the delivers of the car will be
done as soon as possible after the order and also comfortable in the economic point of view. In the same way the building and real
estate industries also in need of satisfying the market needs so that they can get the marginal profit. It is not possible to achieve the
target with the use of available resources. The availability of resources also less. So the only way of achieving the target is through
increasing the labour productivity of the available labour.
There is a matter of concern that these increased labour productivity will create several risk factors that affects the labours
concerned directly or indirectly. This also may cause the situation of accident due to increased productivity rate. This may affects the
entire course of the project and may cause even loss of life and injuries to the workforce concerned.
83 www.ijergs.org
International Journal of Engineering Research and General Science Volume 2, Issue 3, April-May 2014
ISSN 2091-2730
CONCLUSION
The increase in the economic development of the country greatly influences in creating the demand and requirement. The construction
industries are in the view of satisfying the needs of the customers and to achieve large margin of profits can readily agree with short
completion of the work. This can greatly affects the labour force by increasing their productivity rate of work.As there is shortage in the
availability of the construction labours the companies assign the work on available labour and impose them to work faster to complete the
project in stipulated time. On the other hand this may create mental disturbance for the labours working in the site due to increased
productivity and increased time of work. For working of long hours thelabours may consume drugs like pan masala, cigarette, and some
timeseven consume liquor during the course of work. This leads to poor quality of work and makes the labour lazy by diverting their
concentration over the construction process. The study shows a great decrease in the availability of labour for work when the floor level goes
on increasing. This may create the situation of risk and causes severe consequences in forms of collapse of structure, damage, time waste,
injuries, loss of life, waste of money.
REFERENCES:
[1] Arbulu, R. J. and Tommelein, I. D. (2002). ―Value stream analysis of construction supply chains: Case study on pipe supports
used in power plants.‖ Proceeding, 12th Annual Conference of the International Group for Lean Construction, Federal
University of RioGrande doSul, Brazil, 183 - 195.
[2] Polat, G., and Ballard, G. (2004), "Waste in Turkish construction: need for leanconstruction techniques." Proceeding, 12th
Annual Conference on Lean Construction,Helsingor, Denmark, 488-501.
[3] Subramanyan, H., Sawant, P., and Bhatt, V. (2012). ‖Construction Project Risk Assessment: Development of Model Based
on Investigation of Opinion of Construction Project Experts from India.‖
[4] Aggarwal,S., (2003), ―Challenges for Construction Industries in DevelopingCountries,‖ Proceedings of the 6th National
Conference on Construction, 10-11November 2003, New Delhi, CDROM, Technical Session 5, Paper No.1.
[5] Bhattacharya,C., (2002), ―JJ Hospital Flyover – Precast Piers,‖ Gammon Bulletin,Vol.126, April-June 2002.
[6] Daniel baloi, ―Risk analysis techniques in construction engineering projects‖, journal of risk sanalysis and crisis Response,
vol 2, no 2 ( aug 2012), 115-123.
84 www.ijergs.org