D Daily Report 12 JAN 23
D Daily Report 12 JAN 23
10
0
19.00
12
10
SPUD DATE 1/1/2023 WELL No B9-NC151 Days : 12 Days Since Last Injury: 55
Proposed TD 3600 R.O.P 64 Depth 1644 FD of Today 64 Total Footge 1644 Move From: Move To:
Rig
Move Distance: Time:
B
H
A
N 8 1/2" core head and coring assembly (8 1/2" CH, 8 15/32 STB,CB, LDA,8 15/32 STB, Top sub, XO12x8"DC, 8" jar, 8" DC,XO, 2x6 1/2" DC, 10x5" HWDP))
O
0
Bit No 3 Type BDC Size 12 1/4'' WOB 20-30 RPM 80-100 Pressure 700 STg W N/A Flow Rate 500
Pump No. 1: 70 Liner Size: 7'' Pressure: 350 T/Pressure 350 SCR Toolpusher MAHER AL OTHMAN
Mud
Pumps Pump No. 2: 70 Liner Size: 7'' Pressure: 350 T/Pressure 350 SCR Company Man WALID
Hole Size
12 1/4'' Casing Size 13 5/8'' Casing Shoe 738 Mud Weight 9
BOP A-Date Last P/T: 8/1/2023 B - PRESSURE 1500-200 C -Date Last F/T: 8/1/2023
TM for Today 90 Cumulative 141 Since Last Cut 544 Length of Rope Remaining: 3380 Safety Meeting date 12/1/2023 Supject Err:509
REPAIRS A-Last 24 Hrs 0 B-Month: 0 TOTAL PERSONNELS 68 SET CARD 7 TRIC CARD 1
From To OPERATIONS
00.00 1.00 Cont. drlg 12 1/4" hole f/ 1580' t/1584' (CP) -Circ. for sampling.
1.00 2.00 Circ. hole clean.
2.00 8.00 POOH w/ 12 1/4" Bit t/ surface no overpull.
8.00 14.30 P/U, M/U 8 1/2" core head and coring assembly (8 1/2" CH, 8 15/32 STB,CB, LDA,8 15/32 STB, Top sub, XO
12x8"DC, 8" jar, 8" DC,XO, 2x6 1/2" DC, 10x5" HWDP)) and RIH t/ 1584'
14.30 19.00 Circ. hole to condition mud-Drop ball and start Cut core#2 (Mrar D (M8) FM) f/ 1584' t/1644'.
19.00 00.00 POOH w/ core barrel#2 t/surface-RIH w/ same 12 1/4" bit#3 and BHA#3 t/1214#2.
RECEIVED / MT # 1179
RECEIVED / MT # 1178