ICT Project Management 401657 Project M Hds 8 15C
ICT Project Management 401657 Project M Hds 8 15C
Introduction
• Pro esses i ol ed i the proje t ti e a age e t i lude:
Step 1. Define Activities
Step 2 Sequence Activities
Step 3 Estimate Activity Resources
Step 4 Estimate Activity Durations
Step 5 Develop Schedule
Step 6 Control Schedule
• Ea h of these pro esses o ur at least o e i e er proje t a d i
one or more project phases (if the project is divided into phases).
I. Activity Definition
• An activity or task is an element of work normally found on the
WBS that has an expected duration, a cost, and resource
requirements.
• Project schedules grow out of the basic documents that initiate a
project.
– The project charter includes start and end dates and budget information.
– The scope statement and WBS help define what will be done.
• Activity definition involves developing a more detailed WBS and
supporting explanations to understand all the work to be done, so
you can develop realistic cost and duration estimates.
Activity Definition
Activity Definition Overview
Inputs Tools and Techniques Output
1. Project Environmental 1. Decomposition 1. Activity List
Factors 2. Templates 2. Activity attribute
2. Organizational Process 3. Action on Project charter 3. List of Milestones
Assets 4. Expert Judgment 4. Requested Changes
3. Project Scope Statement 5. Planning Components
4. WBS
5. Project Scope
Management Plan
Decomposition of Activities
Features of Decomposition of Activities
• Sub divide work packages into Schedule Activities.
• Define Activities to meet project objectives.
• Activities should be relatively smaller and manageable
components.
• Activities may be work packages or lower level items.
• WBS and Activity list may be developed sequentially or
concurrently.
Activity Attributes
• An activity list is a tabulation of activities to be included on a
project schedule. The list should include:
– The activity name
– An activity identifier or number
– A brief description of the activity
• Activity attributes provide more information about each
activity, such as predecessors, successors, logical relationships,
leads and lags, resource requirements, constraints, imposed
dates, and assumptions related to the activity.
II. Activity Sequencing
Activity Sequencing Overview
Inputs Tools and Techniques Outputs
1. Project Scope Statement 1. Precedence 1. Project Schedule
2. Activity List Diagramming Method Network Diagram
3. Activity Attributes 2. Arrow Diagramming 2. Updates Activity List
4. List of Milestones Method 3. Updates Activity
5. Approved Change 3. Schedule Network Attributes
Requests Templates 4. Requested Changes
4. Dependency
Determination
5. Apply Leads and Lags
Network Diagram
• Network diagrams are the preferred technique for showing
activity sequencing.
• A network diagram is a schematic display of the logical
relationships among, or sequencing of, project activities.
• Two main formats are the arrow and precedence diagramming
methods.
Precedence Diagramming Method (PDM)
• Activities are represented by boxes.
• Arrows show relationships between activities.
• More popular than ADM method and used by project
management software.
• Better at showing different types of dependencies.
Arrow Diagramming Method (ADM)
• Also called activity-on-arrow (AOA) network diagram.
• Activities are represented by arrows.
• Nodes or circles are the starting and ending points of activities.
• Can only show finish-to-start dependencies.
III. Activity Resource Estimating
• Before estimating activity durations, you must have a good
idea of the quantity and type of resources that will be assigned
to each activity.
• Consider important issues in estimating resources:
– How difficult will it be to complete specific activities on this project?
– What is the orga izatio ’s histor i doi g si ilar a ti ities?
– Are the required resources available?
Activity Resource Estimating Overview
– Put them in order of how the work will be done (activity sequencing),
and then
PRECEEDING SUCCESSOR
ACTIVITY
EVENT
20
• Network analysis is the general name given to certain specific techniques which can be
used for the planning, management and control of projects
Activity-on-node (AON): nodes represent activities, and arrows show precedence relationships
Activity-on-arrow (AOA) : arrows represent activities and nodes are events for points in time
•Path - A connected sequence of activities leading from the starting event to the ending
event
•Critical Path- The longest path (time); determines the project duration
•Critical Activity - All of the activities that make up the critical path
22
Situations of activities in network diagram
B
A
A must finish before either B or C can start
C
A
C both A and B must finish before C can start
B
A
B
A must finish before B can start
Dummy both A and C must finish before D can start
C
D 23
Situations of activities in network diagram: Concurrent Activities
3
Lay foundation Lay
Dummy
foundation
2 0
2 3
1
Order material 2 4
Order material
24
EXAMPLES OF THE USE OF DUMMY ACTIVITY
Network concurrent activities
a
a 2
1 2 1 Dummy
b 3
b
WRONG!!! RIGHT
25
WRONG!!! RIGHT!!!
a d a d
1 1
b e b
2 2 4
e
c f c f
3 3
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
26
Activity On Arc Diagrams for Concurrent Activity
A B
1 2 3 D
4
C
3
B
A C
1 2 4 D 5
AOA Project Network for House having dummy Activity
3
Lay foundation Dummy
D G
3 6 7
B E
A
1 2 5 H
C F
4
Network Diagrams
• Advantages
– Show precedence well
– Reveal interdependencies not shown in other techniques
– Ability to calculate critical path
– A ilit to perfor hat if e er ises
• Disadvantages
– Default model assumes resources are unlimited
• You eed to i orporate this ourself Resour e Depe de ies he deter i i g the real
Critical Path
– Difficult to follow on large projects
PERT
• Program Evaluation and Review Technique
• Based on idea that estimates are uncertain
– Therefore uses duration ranges
– And the probability of falling to a given range
• Uses a e pe ted alue or eighted a erage to deter i e duratio s
PERT
• Use the following methods to calculate the expected durations,
then use as input to your network diagram
• Start with 3 estimates
– Optimistic
• Would likely occur 1 time in 20
– Most likely
• Modal value of the distribution
– Pessimistic
• Would be exceeded only 1 time in 20
PERT Formula
• Combined to estimate a task duration
PERT Formula
• Based on a standard deviation of the expected time
• Using a bell curve (normal distribution)
Variance = [(b-a)/6]2
• For the whole critical path use, If s = standard deviation
PERT
• Advantages
– Accounts for uncertainty
• Disadvantages
– Time and labor intensive
– Assumption of unlimited resources is big issue
– Lack of functional ownership of estimates
– Mostly used on large, complex project
• PERT software is available to calculate it
CPM vs. PERT
• Both use Network Diagrams
• CPM: deterministic
• PERT: probabilistic
• CPM: one estimate, PERT, three estimates
• PERT is infrequently used
Benefits of CPM/PERT
• Useful at many stages of project management
• Mathematically simple
• Give critical path and slack time
• Provide project documentation
• Useful in monitoring costs
CPM can answer the following important questions:
•How long will the entire project take to be completed? What are the risks involved?
•Which are the critical activities or tasks in the project which could delay the entire
project if they were not completed on time?
•Is the project on schedule, behind schedule or ahead of schedule?
•If the project has to be finished earlier than planned, what is the best way to do this at
the least cost?
44
The PERT/CPM Approach for
Project Scheduling
• PERT stands for Program Evaluation and Review Technique and CPM stands for
critical path method.
– Both ere ethods for proje t s heduli g de eloped i depe de tl i the late 95 ’s.
– The concepts have merged over the years so that now we simply call the approach the
PERT/CPM approach.
• It uses a network representation (a set of nodes and a set of arcs) of the project.
– Nodes represent the activities and reflect their completion times
– Arcs reflect immediate predecessor relationships with arrows
• PERT/CPM is used for s heduli g a ti ities su h that the proje t’s o pletio
time is minimized.
Critical Chain Scheduling
• Technique that addresses the challenge of meeting project finish
• Developed by Eliyahu Goldratt in his books The Goal and Critical
Chain
• Critical chain scheduling is a method of scheduling that takes
limited resources into account when creating a project schedule
and includes buffers to protect the project completion date
48
Schedule Control
Schedule Control Overview
Inputs Tools and Techniques Outputs
1. Schedule 1. Progress Reporting 1. Updated Schedule Model Data
Management 2. Schedule change Control 2. Updated Schedule Baseline
Plan System 3. Performance Measurements
2. Schedule 3. Performance 4. Requested Changes
Baseline Management 5. Recommended Corrective Actions
3. Performance 4. Project Management 6. Updated Organizational Process
Reports Software Assets
4. Approved 5. Variance Analysis 7. Updated Activity List
Change 6. Schedule Comparison 8. Updated Activity Attributes
Requests Bar Chart 9. Updated Project Management
Plan
Schedule Control
• Goals are to know the status of the schedule, influence factors that
cause schedule changes, determine that the schedule has changed,
and manage changes when they occur.
• Tools and techniques include:
– Progress reports.
– A schedule change control system.
– Project management software, including schedule comparison charts, such
as the tracking Gantt chart.
– Variance analysis, such as analyzing float or slack.
– Performance management, such as earned.
50
Example
KLONE COMPUTERS, INC.
• KLONE Computers manufactures computers.
F Staff training
Training activities G Staff input on prototype models
H Sales training
I Pre-production advertising
Advertising activities campaign
J Post-redesign advertising campaign
Precedence Relations
Starts Completion
Activity after
Immediate Predecessor's) Days
A-Prototype Design NONE 90
Starts
B-Purchase Materials A-Prototype Design 15
After
Starts
C-Manufacture Prototypes B-Purchase Materials 5
After
Starts C-Manufacture Prototypes and
D-Design Revision 20
After G-Staff Input
Starts
E-Initial Production Run D-Design Revision 21
After
Starts
F-Staff Training A-Prototype Design 25
After
Starts C-Manufacture Prototypes and
G-Staff Input 14
After F-Staff Training
Starts
H-Sales Training D-Design Revision 28
After
Starts
I-Pre-Production Advertising
After
A-Prototype Design 30
Starts D-Design Revsion and
J-Post Redesign Advertising 45
After I-Pre-Production Advertising
The PERT/CPM Network
E
B C
21
15 5
A F G D H
90 25 14 20 28
J
I
45
30
OBJECTIVES
• Management at KLONE would like to schedule the activities to minimize the
project completion time.
• Management wishes to know:
– The earliest start and finish times for each activity that will allow the project
to be completed in this minimal time.
– The latest start and finish times for each activity which will not alter this
minimal time.
– Which activities must adhere to rigid schedules and which activities have
slack in their schedules.
Earliest Start (ES) and
Earliest Finish (EF) Times
• The ES and EF times are determined by making a forward pass through the
network as follows:
– For all the activities which have no immediate predecessors:
• The earliest start time (ES) = 0
• The earliest finish time (EF) = the a ti it ’s duratio
– Then select a node for which EF of all its immediate predecessors has been determined.
• ES = Max EF (of all its immediate predecessors)
• EF = ES + Activity Duration
– Repeat this process until all nodes have been evaluated
MAX(120,149)
(149, 194)
(90, 120)
J
I
45
30
(149, 194)
(119, 149)
Possible Delays
• There could be a delay in just one activity.
– Any delay more than the slack time for the activity will delay the entire project by the
difference between the activity delay and the slack time
• There could be delays in more than one activity.
– If activities are on different paths or on the same path but separated by a critical activity,
each of the delays is evaluated separately. The project delay = max (these delays –
corresponding slack).
– Activities on the same path which are not separated by a critical activity share the slack.
Both will have the same value for the slack and any combined delays in these activities that
exceed this common slack results in a project delay equal to (total activity delay) –
(common slack).
– Usually with multiple delays the model is simply re-solved!
Examples of Activity Delays
• Activity G is delayed 5 days
– G is on the critical path (has 0 slack) so the project will be delayed 5 days.
• Activity E is delayed 15 days
– E has 24 days of slack so the project will not be delayed
• Activity B is delayed 15 days
– B has 5 days of slack so the project will be delayed 10 days
• Activity E is delayed 30 days and Activity I is delayed 30 days
– E and I are on different paths. E has 24 days of slack which could cause a 30-24 = 6 day delay; I has 29 days of slack which
could cause 30-29 = 1 day delay. The project is delayed by the MAX(6,1) = 6 days.
• Activity B is delayed 4 days and Activity E is delayed 4 days
– B and E are on the same path but are separated by critical activities (G and D). This is the same as the case above. B has
5 days slack so delaying it 4 days would not delay the project; E has 24 days of slack so a 4 day delay will not delay the
project – Net effect– No delay.
• Activity B is delayed 4 days and Activity C is delayed 4 days
– B and C are on the same path with no critical activity in between. They share the same 5 days of slack. So sense both are
delayed 4 days for a total of 8 days, the project is delayed 8 – 5 = 3 days.
Limitations to CPM/PERT
• Specified precedence relationships
• Over emphasis on critical paths
• Deterministic CPM model
• Activity time estimates are subjective and depend on judgment
• PERT assumes a beta distribution for these time estimates, but the actual distribution
may be different
• PERT consistently underestimates the expected project completion time due to
alternate paths becoming critical
To overcome the limitation, Monte Carlo simulations can be performed on the network
to eliminate the optimistic bias
66
Monte Carlo Simulation
• The simulation can tell you:
• The probability of completing the
project on any specific day
• The probability of completing the
project for any specific amount of
cost
• The probability of any task
actually being on the critical path
• The overall project risk
Cost consideration in project
• Project managers may have the option or requirement to crash the project, or
accelerate the completion of the project.
• This is accomplished by reducing the length of the critical path(s).
• The length of the critical path is reduced by reducing the duration of the activities
on the critical path.
• If each activity requires the expenditure of an amount of money to reduce its
duration by one unit of time, then the project manager selects the least cost critical
activity, reduces it by one time unit, and traces that change through the remainder
of the network.
• As a result of a reduction in an activity’s time, a new critical path may be created.
• When there is more than one critical path, each of the critical paths must be
reduced.
• If the length of the project needs to be reduced further, the process is repeated.
68
Reducing Project Completion Time
• Crashing a project needs to balance
– Shorten a project duration
– Cost to shorten the project duration
• Crashing a project requires you to know
– Crash time of each activity
– Crash cost of each activity
Crash cost/duration = (crash cost-normal cost)/(normal time – crash time)
© Wiley 2010
Project Crashing
• Crashing a project refers to reducing the total time to complete the project to
meet a revised due date.
• Crash time is the shortest possible time the activity can realistically be
completed.
• Crash cost is the total additional cost associated with completing an activity
in its crash time rather than in its normal time.
Goal – to reduce project duration at minimum cost
Crash cost per unit of time =
Crash Cost – Normal Cost
Normal Time – Crash Time
Steps of Project Crashing
1. Find the normal critical path and identify the critical activities.
2. Compute the crash cost per week (or other time period) for all activities in the network using the
formula:
crash cost – normal cost
crash cost/time period = normal time – crash time
3. Select the activity on the critical path with the smallest crash cost per week. Crash this activity to
the maximum extent possible or to the point at which your desired deadline has been
reached.
4. Check to be sure that the critical path you were crashing is still critical. Often, a reduction in
activity time along the critical path causes a noncritical path or paths to become critical. If the
critical is still the longest path through the network, return to step 3. If not, find the new
critical path and return to step 3.
Gantt Chart
• Gantt charts provide a standard format for displaying project
schedule information by listing project activities and their
corresponding start and finish dates in a calendar format.
• A GANTT chart is a type of bar chart that illustrates a project
schedule.
• After the CPM/PERT analysis is completed, the following phase is
to construct the GANTT chart and then to re-allocate resources
and re-schedule if necessary.
• GANTT charts have become a common technique for
representing the phases and activities of a project work
breakdown structure.
• It was introduced by Henry Gantt around 1910 – 1915.
72 Maria Petridou
Gantt Chart
73
Gantt Chart
Characteristics:
– The bar in each row identifies the corresponding task
– The horizontal position of the bar identifies start and end times of the task
– Bar length represents the duration of the task
– Task durations can be compared easily
– Good for allocating resources and re-scheduling
– Precedence relationships can be represented using arrows
– Critical activities are usually highlighted
– Slack times are represented using bars with doted lines
– The bar of each activity begins at the activity earliest start time (ES)
– The bar of each activity ends at the activity latest finish time (LF).
74
Adding Milestones to Gantt Charts
• Many people like to focus on meeting milestones, especially for
large projects.
• Milestones emphasize important events or accomplishments in
projects.
• You typically create milestone by entering tasks that have a
zero duration, or you can mark any task as a milestone.
75
Gantt Chart
Advantages
Simple
Good visual communication to others
Task durations can be compared easily
Good for scheduling resources
Disadvantages
Dependencies are more difficult to visualise
Minor changes in data can cause major changes in the chart
76
Constructing Gantt Chart
• The steps to construct a GANTT chart from the information obtained by
PERT/CPM are:
1. Schedule the critical tasks in the correct position.
2. Place the time windows in which the non-critical tasks can be
scheduled.
3. Schedule the non-critical tasks according to their earliest starting
times.
4. Indicate precedence relationships between tasks.
77
Constructing Gantt Chart
• Example of an early GANTT chart construction:
78
Constructing Gantt Chart
Step 1. Schedule critical tasks:
80
Constructing Gantt Chart
Step 3. Schedule non-critical tasks
Step 4. Indicate precedence relationships:
81
Example
Note: In Project 2003 darker bars are red to represent critical tasks.
82
Reality Checks on Scheduling
• Review the draft schedule or estimated completion date in the
project charter.
• Prepare a more detailed schedule with the project team.
• Make sure the schedule is realistic and followed.
• Alert top management well in advance if there are schedule
problems.
83
Forward Pass :
Determine Earliest Start (ES) and Earliest Finish (EF) time for each Task
84
Backward Pass:
Determine Latest Start (LS) and Latest Finish (LF) time for each Task
For all Final Tasks, LF = Project completion time
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
Slack time[ST] - The length of time an activity can be delayed without affecting
the completion date for the entire project, computed as ST=LS-ES=LF-EF
Latest start & latest finish time
86
Determine Free Float (FF): Determine Total Float (TF):
Allowable delay in start of task Allowable delay in start of task
which will not delay start of any which will not delay Project
other task. Completion.
For task with tail [i] and head [j], For task with tail [i] and head [j],
FF[i,j] = ES[j] - ES[i] - t[i, j] TF[i,j] = (LF[j] – ES[i]) – t[i,j]
= ES[j] - EF[i,j]
=LS[i,j] – ES[i]
Chapter 8 89
Importance of Float (Slack) and Critical Path
1. Slack or Float shows how much allowance each activity has, i.e how long it can be delayed without
affecting completion date of project
2. Critical path is a sequence of activities from start to finish with zero slack. Critical activities are
activities on the critical path.
4. If any activity on the critical path is shortened or extended, project time will be shortened or
extended accordingly
5. So, a lot of effort should be put in trying to control activities along this path, so that project can meet
due date. If any activity is lengthened, be aware that project will not meet deadline and some action
needs to be taken.
6. If can spend resources to speed up some activity, do so only for critical activities.
7. Don’t waste resources on non-critical activity, it will not shorten the project time.
8. If resources can be saved by lengthening some activities, do so for non-critical activities, up to limit
of float.
90
Network Exercise: Q.N. 1.
A social project manager is faced with a project with the following activities:
Draw network diagram and show the critical path. Calculate project duration.
91
Network Example : For the following set of Activities draw the network diagram,
compute LS, LF, ES, EF, ST, Project completion time and critical path.
92
Computing earliest start & earliest finish time
• We are interested in the longest path through the network, i.e., the critical
path.
• The expression EF = ES + t can be used to find the earliest finish time for a
given activity.
For example, for activity A, ES = 0 and t = 5; thus the earliest finish time for
activity A is
EF = 0 + 5 = 5
93
Network with ES & EF time
D[5,8] 5
2 3
7
4
1 6
94
Network with LS & LF time
D[5,8] 5
2 3[7,10]
7
4
1 6
2
ES LS EF EF
5 8 9 12
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
96
Activity schedule for our example
Activity Earliest start Latest Earliest finish Latest finish Slack Critical path
(ES) start (LS) (EF) (LF) (LS-ES)
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
97
IMPORTANT QUESTIONS
• What is the total time to complete the project?
– 26 weeks if the individual activities are completed on schedule.
• What are the scheduled start and completion times for each activity?
– ES, EF, LS, LF are given for each activity.
• What activities are critical and must be completed as scheduled in order to keep the project on
time?
– Critical path activities: A, E, F, G, and I.
• How long can non-critical activities be delayed before they cause a delay in the project’s
completion time
– Slack time available for all activities are given.
98
Network Example : For given Network Compute ES,EF,LS,LF,
Float/Slack time and Critical path
f, 15
g, 17 h, 9
a, 6
i, 6
b, 8
d, 13 j, 12
c, 5
e, 9
99
ES and EF Times : Forward Pass
f, 15
6 21
g, 17 h, 9
a, 6
21 30
0 6 6 23 i, 6
23 29
b, 8
0 8 d, 13 j, 12
8 21 21 33
c, 5
0 5 e, 9
Project’s EF = 33
5 14
100
LS and LF Times : Backward Pass
f, 15
6 21
9 24 h, 9
21 30
a, 6 g, 17
24 33
0 6 6 23
i, 6
4 9 10 27 23 29
27 33
b, 8
0 8 d, 13
j, 12
0 8 8 21
21 33
8 21
c, 5 21 33
0 5 e, 9
7 12 5 14
12 21
darla/smbs/vit 101
Computing Float
f, 15
6 21
3 h, 9
9 24
21 30
a, 6 g, 17 3
24 33
0 6 6 23 i, 6
3 4
3 9 10 27 23 29
4
b, 8 27 33
0 8 d, 13
0 j, 12
0 8 8 21 21 33
0 0
c, 5 8 21 21 33
0 5 e, 9
7
7 12 5 14
7
12 21
102
Critical Path: B-D-J
f, 15
g, 17 h, 9
a, 6
i, 6
b, 8
d, 13
j, 12
c, 5
e, 9
103
Network Example
Construct a PERT network for a project with the following activities and times:
104
Solution – first construct the network and label activities
D
2 4
1 5
105
Solution – adding time
D
2 6 4
1 5
106
Solution: adding ES, LS, EF, LF
D [4,10]
2 6 [4,10] 4
1 5
107
Network Example
(times are in weeks)
C
2 7 5
A
D F H
5
6 3 8
1 G
B 4 10 6
3 E
7
3
108
Solution
C [5,12]
2 7 [7,14] 5
1 G [11,21]
4 10 [12,22] 6
a. Critical path: A - D - F - H
b. 22 weeks.
c. Activity D is on the critical path and cannot be delayed. Activity C can be delayed by 2 weeks.
d. Activity E schedule: ES =3, LS=4, EF=10, LF=11
109
Network Example
A project involving the installation of a computer system consists of eight activities. The
immediate predecessor and activity time in weeks are shown below:
110
Solution:
a.
E
2 4 4 5
B G H
1 6 3 9 6 3 7
111
Solution contd…
Activity ES LS EF LF Slack Critical?
A 0 1 3 4 1
B 0 0 6 6 0 Yes
C 3 4 5 6 1
D 6 6 11 11 0 Yes
E 11 11 15 15 0 Yes
F 15 15 18 18 0 Yes
G 6 9 15 18 3
H 18 18 21 21 0 Yes
Critical path activities: B - D - E - F - H
112
Solution contd….
a.
E
2 4 5
4
B G H
1 3 6 7
6 9 3
113
Network Example
Consider the PERT/CPM network shown below.
A 2 3
D
E F
B
G J
1 4 6 7
H
C
I
5
a. Add the dummy activities that will eliminate the problem of
activities having the same starting and ending nodes.
b. Add dummy activities that will satisfy the following immediate predecessor requirements:
Immediate
Activity Predecessor
H B, C
I B, C
G D, E
114
Solution
D
2 3
A E F
G J
B 6 8 9
1 4
H
C
I 7
115
Network Exercise: Q.N. 2.
Draw network diagram and show the critical path. Calculate project duration.
4
2
1 5
3
116
Network Exercise: Q.N. 3.
Draw network diagram and show the critical path. Calculate project duration.
Draw network diagram and show the critical path. Calculate project duration.
Network Exercise: Q.N. 6.
Find the critical path for the following network of a project activities
d 6
2
(15)
j
a (8)
(22) e
(10)
1 f 7
3
b (14)
(20)
g
c
(4)
(10,) i
(18)
h 5
4
(11)
119
Network Exercise: Q.N. 7.
Draw network diagram and show the critical path. Calculate project duration.
Network Exercise: Q.N. 8.
Task. A project has been defined to contain the following list of activities along with their required times for
completion:
Crash cost
Crashing activity
Normal Activity
Normal
cost
Normal
time
Direct cost
time
123
Example : Time Cost data
124
Computer Software for Project Management
• Microsoft Project (Microsoft Corp.)
• MacProject (Claris Corp.)
• PowerProject (ASTA Development Inc.)
• Primavera Project Planner (Primavera)
• Project Scheduler (Scitor Corp.)
• Project Workbench (ABT Corp.)
125
Thank You!
Project Cost Management
What is Cost and Project Cost
Management?
Cost is a resource sacrificed or foregone to achieve a
specific objective, or something given up in exchange.
2
Project Cost Management Processes
Resource Planning:
Determining what resources(people, equipment,
materials and what quantities of each should be used to
perform project activities
Cost of the resources needed to complete Project
activities
The cost of the procurement item may be measured
when committed, ordered, delivered, incurred or
recorded for accounting purposes.
3
Resource Planning
Input:-
WBS
Historical information
Scope statement
Organization policies
Resource pool description
(Identified the resources according to progress and
measure the exact number of required resources)
4
Resource Planning
Tools and technique
Expert Judgment
Alternative identification
Output:-
Resources requirements
5
Project Cost Management Processes
Cost estimating: Developing an approximation or
estimate of the costs of the resources needed to
complete a project.
6
Basic Principles of Cost Management
Cash flow analysis determines the estimated annual costs and
benefits for a project and the resulting annual cash flow
Too many projects with high cash flow needs in the same year
may not be able to be supported which will impact profitability
Tangible costs or benefits are those costs or benefits that an
organization can easily measure in dollars
A task that was allocated $150,000 but actually costs $100,000
would have a tangible benefit of $50,000 if the assets allocated
are used for other projects
Intangible costs or benefits are costs or benefits that are difficult
to measure in monetary terms
Costs – resources used to research related areas of a project but
not billed to the project
Benefits – goodwill, prestige, general statements of improved
productivity not easily translated in dollars
7
Basic Principles of Cost Management
Direct costs are costs that can be directly related to producing
the products and services of the project
Salaries, cost of hardware and software purchased
specifically for the project
Indirect costs are costs that are not directly related to the
products or services of the project, but are indirectly related to
performing the project
Cost of electricity, paper towels
Sunk cost is money that has been spent in the past; when
deciding what projects to invest in or continue, you should not
include sunk costs
To continue funding a failed project because a great deal of
money has already been spent on it is not a valid way to
decide on which projects to fund
Sunk costs should be forgotten
8
Basic Principles of Cost Management
Learning curve theory states that when many items are
produced (or tasks are performed) repetitively, the unit cost of
those items decreases in a regular pattern as more units are
produced (or more tasks performed)
Reserves are dollars included in a cost estimate to mitigate cost
risk by allowing for future situations that are difficult to predict
Contingency reserves allow for future situations that may be
partially planned for (sometimes called known unknowns)
and are included in the project cost baseline
Recruiting and training costs for expected personnel
turnover during a project
Management reserves allow for future situations that are
unpredictable (sometimes called unknowns)
Extended absence of a manager; supplier goes out of
business
9
Cost Estimating
After developing a good resource requirements list,
PMs and their teams must develop several estimates
of the costs for these resources
Project managers must take cost estimates seriously if
they want to complete projects within budget
constraints
It’s important to know the types of cost estimates,
how to prepare cost estimates, and typical problems
associated with IT cost estimates
1
0
Cost Estimating
A rough order of magnitude (ROM) estimate provides an estimate
of what a project will cost.
Also referred to as a ballpark estimate, a guesstimate, a swag, or
a broad gauge.
Done very early in a project, often three or more years prior to
project completion, or even before a project is officially started
to help PMs make project selection decisions.
Accuracy is typically -50 percent to +100 percent, meaning the
project’s actual costs could be 50 percent below the ROM
estimate or 100 percent above.
A ROM estimate that actually cost $100,000 would range between
$50,000 to $200,000. The accuracy range is often much wider for IT
projects.
Often IT project estimates for software development are doubled because of
the history of cost overruns
1
1
Cost Estimating
A budgetary estimate is used to allocate money into
an organization’s budget.
Many organizations develop budgets at least two years
into the future.
Budgetary estimates are made one to two years prior to
project completion.
The accuracy of budgetary estimates is typically -10% to
+25%
A budgetary estimate that actually costs $100,000 would
range between $90,000 to $125,000.
1
2
Cost Estimating
A definitive estimate provides an accurate estimate of
project costs (most accurate of the three types).
Definitive estimates are used for making many purchasing
decisions for which accurate estimates are required and for
estimating final project costs.
For example, if a project involves purchasing 1000
personal computers from an outside supplier in the next
three months, a definitive estimate would be required to
aid in evaluating supplier proposals and allocating the
funds to pay the chosen supplier.
Definitive estimates are made one year or less prior to
project completion
1
Accuracy range is normally -5% to +10%
3
Types of Cost Estimates
15
Estimating process and accuracy
• Past experience Rough Order
• Scale factors Of Magnitude
• Parametric curves (top-down) Less accurate
• Capacity Estimates
• Reported from
Expert previous projects
Knowledge • Analogous Budgetary
Increases • Parametric (top-down)
Accuracy • Rule of thumb
of • Indexed
cost(adjusted to
Estimates
new scope)
• Grassroots built-up
• Well-defined
engineering data Definitive Most accurate
• Quotes from (bottom-up)
vendors
• WBS costing
Surveyor Pro Project Cost Estimate
17
Surveyor Pro Software Development Estimate
18
Cost Budgeting
Cost budgeting involves allocating the project cost
estimate to individual work items over time.
19
Cost Control
Project cost control includes:
24
Earned Value Management Terms
The planned value (PV), formerly called the budgeted cost of
work scheduled (BCWS), also called the budget, is that portion
of the approved total cost estimate planned to be spent on an
activity during a given period.
Actual cost (AC), formerly called actual cost of work
performed (ACWP), is the total of direct and indirect costs
incurred in accomplishing work on an activity during a given
period.
The earned value (EV), formerly called the budgeted cost of
work performed (BCWP), is an estimate of the value of the
physical work actually completed.
EV is based on the original planned costs for the project or
activity and the rate at which the team is completing work on
the project or activity to date.
25
Rate of Performance
Rate of performance (RP) is the ratio of actual
work completed to the percentage of work planned
to have been completed at any given time during
the life of the project or activity.
26
Earned Value Formulas
27
Rules for Earned Value Numbers
28
EVM benefits
Performance tracking
Profitability analysis
Project forecasting
Better accountability
Preventing scope creep
Improving communication visibility with
stakeholders
Reducing risk
Earned Value Calculations for a One-Year
Project After Five Months
30
Earned Value Chart for Project after
Five Months
If the EV
line is
below the
AC or PV
line, there
are
problems
in those
areas.
31
Cost Variance
Cost variance (CV) is the difference of Budgeted Cost
of Work Performed (earned value) minus Actual Cost
of Work Performed. It can be expressed as:
CV = BCWP – ACWP,
where negative variance indicates cost overrun.
32
Schedule Variance
schedule variance (SV) is the difference of Budgeted
Cost of Work Performed (earned value) minus
Budgeted Cost of Work Schedule. It can be expressed
as:
SV = BCWP – BCWS
where negative variance indicates time overrun.
33
Cost & Schedule Performance
Cost performance
Cost performance can be obtained by dividing earned
value (BCWP) by Actual Cost of Work Performed
(ACWP), which can be expressed as:
Cost performance index = BCWP/ACWP
Schedule performance
Schedule performance can be obtained by dividing
earned value (BCWP) by Budgeted Cost of Work
Schedule, which can be expressed as:
Schedule performance index= BCWP/BCWS
34
Formulas
Cost variance Cost variance in percentage
BCWP – ACWP BCWP – ACWP x 100
BCWP
2000
1500
1000
500
0
1 3 5 8 10 11
39
Chapter Summary
Project cost management is traditionally a weak area in
IT projects, and project managers must work to
improve their ability to deliver projects within
approved budgets.
Cost budgeting
Cost control
40
THANK U ALL FOR YOUR ATTENTION
41
Project quality management
(PMI body of knowledge)
Introduction
• Project quality management includes the process
required to ensure that the project satisfies the
needs for which it is undertaken.
1. Prevention costs
2. Appraisal costs
5. Opportunity costs
Five Cost Categories Related to Quality
• Prevention cost: Cost of planning and executing a project
so it is error-free or within an acceptable error range.
• Appraisal cost: Cost of evaluating processes and their
outputs to ensure quality.
• Internal failure cost: Cost incurred to correct an identified
defect before the customer receives the product.
• External failure cost: Cost that relates to all errors not
detected and corrected before delivery to the customer.
• Opportunity Cost: Capital cost of equipment used to
perform prevention and appraisal activities. Cost that relate
to new innovation and chances to correct detected defect for
achieving quality of the product or services.
4
What is quality management all about?
Quality is
“uniformity and
dependability”
Focus on
statistical tools
PDCA method
1900-1993
1986
The Quality Gurus – Joseph Juran
Quality is
“fitness for use”
Pareto Principle
Cost of Quality
General
management
approach as well 1904 - 2008
as statistics
1951
History
Technical
Tools
Cultural
Customer (Process
Alignment
Analysis)
Who’s Respo si le fo the
Quality of Projects?
• Project managers are ultimately responsible for quality management on their
projects
• Several organizations and references can help project managers and their teams
understand quality
– International Organization for Standardization (www.iso.org)
• When products, systems, machinery and devices work well and safely, it
is often because they meet standards. The organization responsible for
many thousands of the standards which benefit the world is ISO (derived
from the Greek isos, ea i g e ual )
– IEEE – Standards Association (www.ieee.org)
• A leading, developer of industry standards in a broad-range of industries
(Power and Energy, Information Technology, Telecommunications,
Transportation, Medical and Healthcare, nanotechnology, cybersecurity,
information assurance, and green technology) . Globally recognized
10
Quality check in Information System
Means of Implementation of PQM
• QUALITY PLANING
• QUALITY ASSURANCE
• QUALITY CONTROL
• These processes interact with each other as well as with the
processes of other knowledge areas
• Each process involves an effort of one or more individual or
group of individuals based on the need of the project.
• Each process occurs at least once in every project phase
during the project life cycle.
Definition
• Quality Planning
- Quality Planning is identifying which
quality standards are relevant to the project
and determining how to satisfy them
Definition
• Quality Assurance
– Quality assurance is evaluating the overall project
performance on a regular basis to provide a
confidence that the project will satisfy the
relevant quality standards.
Definition
• Quality Control
– Quality Control is the monitoring of specific
project results to determine if they comply with
the relevant quality standards and identifying
ways to eliminate causes of unsatisfactory
performance.
International Standards Organization (ISO)
18
Other definitions
• Fitness for purpose or use (Juran)
• Conformance to requirements (Crosby)
OR
What the customer really needed
Quality Gurus
• Dr Edward Deming
– Total Quality Management
– Plan-Do-Check-Act
– Rule of 85
• 85% of the cost of quality is responsibility of
Management
• Dr Joseph Moses Juran (Quality Planning,
Quality Control, Quality Improvement)
• Phillip Crosby (Conformance to Requirements,
Prevention, Zero Defect, Cost of Non
_conformance)
Quality Process
PROJECT QUALITY MANAGEMENT
Plan Do
Act Check
Benchmarking
• Benchmarking involves comparing actual or planned
project practices to those of other projects to
generate ideas to:
1- Generate ideas for improvement
2- provide a standard for measurement of performance
Flow charting
Design of Experiments
Inspection
• Inspection includes activities such as measuring,
examining and testing undertaken to determine
whether results conform to requirements
• Inspection can be carried out on the level of a single
activity or a final product
• Inspections can be called reviews, product reviews,
audits, and walk-throughs
Tools and Techniques for Quality Control
Control Charts
• These charts are graphical representations that display the
result of a process over time and are used to determine if the
p o ess is i o t ol
• When in control the process should not be adjusted , however
it may be changed in order to provide improvements
• Control charts may be used to monitor any type of output
variable
• Control charts are most often used to monitor repetitive
activity in production but can also be used to monitor cost
and schedule variances
Tools and Techniques for Quality Control
Pareto Diagram
• A Pareto diagram is a histogram ordered by frequency of
occurrence which shows how many results were generated by
what category or identified cause
• The project management team should take action to fix the
problems that are causing the greatest number of defects first
• Typically the Pareto diagram reflects that a relatively small
number of causes are responsible for the majority of the
problems or defects.
Pareto Diagram
• Pareto analysis involves identifying the vital
few contributors that account for the most
quality problems in a system.
61
Tools and Techniques for Quality Control
Statistical Sampling
• Statistical sampling involves choosing a part of a
population of interest for inspection
• Appropriate sampling can effectively reduce the cost
of quality control
• There is a vast body of knowledge related to
statistical sampling and therefore the management
must be aware of the various sampling techniques
Statistical Sampling
• Statistical sampling involves choosing part of a population of
interest for inspection
– This is needed when the population is too large be to be completely
sampled
• The size of a sample depends on how representative you want
the sample to be
• Sample size formula:
Sample size = .25 X (certainty factor/acceptable error)2
Desired Certainty Sample
certainty factor size
95% 1.960 384
90% 1.645 68
80% 1.281 10
63
Six Sigma
• The term sigma means standard deviation.
• Standard deviation measures how much
variation exists in a distribution of data.
• Standard deviation is a key factor in
determining the acceptable number of
defective units found in a population.
Six Sigma
• Six Sigma is a o p ehe sive a d flexi le
system for achieving, sustaining, and
maximizing business success. Six Sigma is
uniquely driven by close understanding of
customer needs, disciplined use of facts, data,
and statistical analysis, and diligent attention to
managing, improving, and reinventing business
p o esses. *
65
Six Sigma Quality
6
• A philosophy and set of methods companies use to
eliminate defects in their products and processes
• Seeks to reduce variation in the processes that lead
to product defects
• The a e six sig a efe s to the va iatio that
exists within plus or minus six standard deviations of
the process outputs
Normal Distribution and Standard Deviation
67
Basic Information on Six Sigma
• Six Sigma projects normally follow a five-
phase improvement process called DMAIC.
68
DMAIC
• DMAIC is a systematic, closed-loop process for continued
improvement that is scientific and fact based.
• DMAIC stands for:
– Define: Define the problem/opportunity, process, and
customer requirements.
– Measure: Define measures, then collect, compile, and
display data.
– Analyze: Scrutinize process details to find improvement
opportunities.
– Improve: Generate solutions and ideas for improving the
problem.
– Control: Track and verify the stability of the improvements
and the predictability of the solution.
69
How is Six Sigma Quality
Control Unique?
70
Tools and Techniques for Quality Control
Flowcharting
72
Tools and Techniques for Quality Control
Trend Analysis
• The trend analysis involves the use of mathematical
techniques to forecast future outcomes based on
historical results it is often used to monitor:
- Technical performance – how many defects have
been identified and how many remain uncorrected
- Cost and schedule performance – how many
activities in a certain period were completed with significant
variances
Outputs for Quality Control
• Quality improvement
• Acceptance decisions, where the inspected items
will either be accepted or rejected and those
rejected may be reworked
• Rework, which is an action taken to bring defects or
nonconforming items into compliance with
requirements and specifications. Rework is a
frequent cause of project over-runs and the project
management team must make an effort to minimize
it .
Outputs for Quality Control
• Completed Checklists, which become a part of
a project record when they are used
• Process Adjustments, which involves
immediate corrective or preventive action as a
result of quality control measurements. In
some cases the adjustment may need to be
handled according to procedures for overall
change control.
TQM Basic approach
1. A committed management
2. Focused on customer
3. Involvement and utilization of the total work
force
4. Continuous improvement
5. Treating suppliers as partners
6. Establish performance measures for each
components/ persons
76
Conclusion
In conclusion we find that in order to achieve PQM or
Project Quality Management , one has to integrate the
concepts of Project management with the processes of
quality management at the project scale and throughout
its different phases.
1
Communication management
2
Importance of Good
Communications
The greatest threat to many projects is a failure to
communicate.
Our culture does not portray IT professionals as being
good communicators.
Research shows that IT professionals must be able to
communicate effectively to succeed in their positions.
Strong verbal skills are a key factor in career
advancement for IT professionals.
3
Project Communications
Management Processes
Communications planning: Determining the information
and communications needs of the stakeholders.
Information distribution: Making needed information
available to project stakeholders in a timely manner.
Performance reporting: Collecting and disseminating
performance information, including status reports, progress
measurement, and forecasting.
Managing stakeholders: Managing communications to
satisfy the needs and expectations of project stakeholders
and to resolve issues.
4
Communications Planning
Every project should include some type of
communications management plan, a document that
guides project communications.
5
Communication Techniques
• Formal, Impersonal ( • Informal, Interpersonal
• Always keeping approaches
distant)approaches – group meetings for information
dissemination and problem
– project documents
solving
– deliverables
– memos
• E-communication
– change requests – E-mail
– project schedules – E-bulletin boards
– data dictionaries – Web sites
– error tracking procedures • Interpersonal Network
• Formal, Interpersonal – informal discussion with those
outside the project
approaches
– status review meetings
– design review meetings
– code inspections
6
Communication Requirement Analysis
• The analysis of the communication requirements results in the
sum of the information needs of the project stakeholders.
• Information required to determine project communication
requirements includes:
• Organization Chart
• Project organizations and stakeholders responsibility relationships
• Disciplines, departments and specialties involved in the project
• Logistics
• Internal information needs
• External information needs
• Stakeholder information
• Project scope statement
• Project management plan
• Number of people involved and communication Channels
7
Determining the Number of
Communications Channels
As the number of people involved increases, the
complexity of communications increases because there
are more communications channels or pathways
through which people can communicate.
Number of communications channels = n(n-1)
2
where n is the number of people involved.
8
The Impact of the Number of People on
Communications Channels
9
Sample Stakeholder Analysis for
Project Communications
10
Running Effective Meetings
Define the purpose and intended outcome of the
meeting.
Determine who should attend the meeting.
Provide an agenda to participants before the meeting.
Prepare handouts and visual aids, and make logistical
arrangements ahead of time.
Run the meeting professionally.
Build relationships.
11
Using E-Mail Effectively
Make sure that e-mail is an appropriate medium for
what you want to communicate.
12
Using E-Mail Effectively (cont’d)
Limit the number and size of attachments.
13
Communication Management Plan
The communication management plan provides
• Stakeholder communication requirements
• Information to be communicated, including format, content and
level of detail
• Person responsible for communicating the information
• Person or groups who will receive the information
• A description of a collection and filing structure for gathering
and storing various types of information
• A distribution structure describing what information goes to
whom, when, and how
• A format for communicating key project information including
information security issues
• Methods or methodologies used to convey the information such
as memoranda, e-mail, press release 14
Communication Management Plan contd…
• Frequency of communication
• A project schedule for producing the information
• Access methods for obtaining the information
• A method for updating the communication
management plans as the project progress and
develops
• Escalation process identifying time frames and the
management chain(names) for escalation of issues that
can not be resolved at a lower staff level
• A stakeholder communication analysis
• Glossary of common terminology
15
Information Distribution
Getting the right information to the right people at
the right time and in a useful format is just as
important as developing the information in the first
place.
16
Distributing Information in an
Effective and Timely Manner
Don’t hide crucial information.
17
Importance of Face-to-Face
Communication
Research says that in a face-to-face interaction:
58 percent of communication is through body language.
35 percent of communication is through how the words
are said.
7 percent of communication is through the content or
words that are spoken.
Pay attention to more than just the actual words
someone is saying.
A person’s tone of voice and body language say a lot
about how he or she really feels.
18
Encouraging More Face-to-Face
Interactions
Short, frequent meetings are often very effective in IT
projects.
19
Media Choice Table
20
Understanding Group and
Individual Communication Needs
People are not interchangeable parts.
21
Personal Preferences Affect
Communication Needs
Introverts like more private communications, while
extroverts like to discuss things in public.
Intuitive people like to understand the big picture,
while sensing people need step-by-step details.
Thinkers want to know the logic behind decisions,
while feeling people want to know how something
affects them personally.
Judging people are driven to meet deadlines while
perceiving people need more help in developing and
following plans.
22
Other Communication
Considerations
Rarely does the receiver interpret a message exactly as
the sender intended.
Language barriers
23
Traceability Matrix
• A traceability matrix ties together requirements, functional
specifications, tasks, test cases, source code and other
relevant artifacts.
• It helps the team visualize the relationships between various
elements of the system and the requirements
Table: Traceability Matrix
Proposal Scope Development QA Impleme Latest
ntation Status
Goal URS SRS Functions Code Unit Peer Tests End Latest
set test review Users status
24
Information Gathering and retrieval system
•Information can be gathered and retrieved through
variety of media including filing system, electronic
database, Project management software and system that
allow access to technical documentation such as
engineering drawings, design specification and test
plans
25
Lessons Learned Reports
The project manager and project team members should
each prepare a lessons-learned report.
A reflective statement that documents important things
an individual learned from working on the project.
The project manager often combines information from
all of the lessons-learned reports into a project
summary report.
Some specific results form lesson learned includes
Update of the lessons learnt knowledgebase
Input to knowledge management system
Update corporate policies, procedures and processes
Improved business skills
Overall product and service improvements
Update to risk management plan
26
Performance Reporting
Performance reporting keeps stakeholders informed
about how resources are being used to achieve project
objectives.
27
Some useful reports
• Project Velocity: Number of work item vs date, Use case vs
date- shows how fast the project is moving towards completion
• Effort variance: Developer vs Average difference between
planned effort and actual effort-Shows the accuracy of estimates
• Schedule Failure: Number of work items vs Days due - to know
about the missed scheduled worked items
• Bug rates: Number of bugs vs date-helps in release planning
and customer satisfaction
• Bug fixing time: Developer vs Average Bug-fixing time-shows
how long it takes a developer to resolve bugs
• Defect Density: Application module vs number of defects-to
identify hot spots in the application system
28
Managing Stakeholders
Project managers must understand and work with
various stakeholders.
Issue log
29
Expectations
Management Matrix
30
Issue Log
31
Conflict Handling Modes
1. Confrontation: Directly face a conflict using a
problem-solving approach.
2. Compromise: Use a give-and-take approach.
3. Smoothing: De-emphasize areas of difference and
emphasize areas of agreement.
4. Forcing: The win-lose approach.
5. Withdrawal: Retreat or withdraw from an actual or
potential disagreement.
32
Conflict Can Be Good
Conflict often produces important results, such as new
ideas, better alternatives, and motivation to work
harder and more collaboratively.
33
Developing Better Communication
Skills
Companies and formal degree programs for IT
professionals often neglect the importance of speaking,
writing, and listening skills.
34
Using Templates for Project
Communications
Many technical people are afraid to ask for help.
35
Sample Template for a
Project Description
36
Sample Template for a Monthly Progress
Report
37
Final Project
Documentation Items
38
Project Web Sites
Many project teams create a project Web site to store
important product documents and other information.
39
Sample Project Web Site
40
Developing a Communications
Infrastructure
A communications infrastructure is a set of tools,
techniques, and principles that provide a foundation for the
effective transfer of information.
Tools include e-mail, project management software,
groupware, fax machines, telephones, teleconferencing
systems, document management systems, and word processors.
Techniques include reporting guidelines and templates,
meeting ground rules and procedures, decision-making
processes, problem-solving approaches, and conflict resolution
and negotiation techniques.
Principles include using open dialog and an agreed upon work
ethic.
41
Using Software to Assist in Project
Communications
There are many software tools to aid in project
communications.
42
Communication and Collaboration
Matrix
43
Thank You
44
Project Risk Management
1
Understanding Risk
Project risk “An uncertain event or condition that, if it occurs, has a
positive or a negative effect on at least one project objective…”
Risk management
• “…includes the processes concerned with conducting risk
management planning, identification, analysis, responses, and
monitoring and control on a project…”
• Includes “increasing the probability and impact of positive events,
and decreasing the probability and impact of events adverse to the
project”
Source: PMBOK® Guide
1. A definable event
Elements of Risk 2. Probability of occurrence
3. Impact (consequence) of occurrence
The Importance of Project Risk
Management
Project risk management is the art and science of
identifying, analyzing, and responding to risk
throughout the life of a project and in the best interests
of meeting project objectives
3
Research Shows Need to Improve
Project Risk Management
Study by William Ibbs and Kwak shows risk has the
lowest maturity rating of all knowledge areas
A similar survey was completed with software
development companies in Mauritius, South Africa in
2003, and risk management also had the lowest
maturity
KLCI study shows the benefits of following good
software risk management practices
4
Project Management Maturity by Industry Group
and Knowledge Area*
KEY: 1 = LOWEST MATURITY RATING 5 = HIGHEST MATURITY RATING
Engineering/ Telecommunications Information Hi-Tech
Knowledge Area Construction Systems Manufacturing
*Ibbs, C. William and Young Hoon Kwak. “Assessing Project Management Maturity,”
Project Management Journal (March 2000).
5
Benefits from Software Risk
Management Practices*
*Kulik, Peter and Catherine Weber, “Software Risk Management Practices – 2001,”
6 KLCI Research Group (August 2001).
Negative Risk
A dictionary definition of risk is “the possibility of
loss or injury”
7
Risk Can Be Positive
Positive risks are risks that result in good things
happening; sometimes called opportunities
8
Best Practice
Some organizations make the mistake of only
addressing tactical and negative risks when
performing project risk management
David Hillson (www.risk-doctor.com) suggests
overcoming this problem by widening the scope of
risk management to encompass both strategic risks
and upside opportunities, which he refers to as
integrated risk management
9
Broad Categories of Risk
Market risk
Financial risk
Technology risk
People risk
Structure/process risk
1
0
Risk Function
Dual Nature of Risk
Risk Types
Three Most Recognized Types of Risk in
Government and Commercial Practice
1. Technical
2. Cost
3. Schedule
Risk Types
1. Technical
• The degree to which technology is sufficiently
mature and has been demonstrated as capable
of satisfying program objectives.
• Technical risk is frequently the driver in
development phase of a program.
Risk Types
2. Cost
• Availability and sufficiency of funding for the
program.
• Government appropriations and funding cycles
are also subject to political risks.
• Commercial programs are subject to market
risks.
Risk Types
3. Schedule
• Adequacy of time allocated for the defined
tasks.
• Includes effects of changes due to
unpredictable events such as: program and
technical decisions, time-to-market pressure,
labor problems, weather and customer directed
changes.
Responsibilities in Risk Management
Project manager
• Initiate and lead the risk management process
• Provide direction to the project team on the
risk management process and tools
Project team
• Understand and follow the risk management
process
• Execute risk management strategies
• Report status on the risk management process
Risk Management Model
Risk Management Process
Project risk and process risk
Project risk : Caused by technical aspect of work or
work product.
Process risk: Caused by formation, processes of the
project or methodologies used in the project will be
affected
20
Risk Management Planning Process
An appropriate sequence for risk management activities is
risk identification, risk quantification, risk response
development and control
Questions to be addressed:
What it is important to take/ not to take “this risk” in relation to the
project objective?
How is the risk going to be mitigated?
What is the specific risk and what are the risk mitigation approaches?
Who are the individual responsible for implementing the risk management
plan?
When will the project milestone associated with the mitigation approach
occur?
How much is required in terms of resources to mitigate this particular
risk?
21
Risk Triangle
Risk triangle represents impacts of project risk and issues on
project schedule
Schedule
Risk Issue
Fig: Risk Triangle 22
Possible Areas of project risk
Skill/ Expertise: Scarcity related risk
Commitment of resources: commitment failure risk
Timeline: Schedule baseline related risk
Project Schedule: schedule management related risk
Clarity of requirement/ Scope: requirements elicitation
related risk
Financials: costing and fund management related risk
Methodology/ Process: development methodology related
risk
External environment : industry practice, competition
related risk
Technology: failure of choosing appropriate technology
related risk 23
Knowledge area and risk contradiction
PM’s Risk Condition
Knowledge Area
Integration Inadequate planning; poor resource allocation; poor integration
management; lack of post project review
Scope Poor definition of scope or work package; incomplete definition of
quality requirements; inadequate scope control
Time Errors in estimating time or resource availability; poor allocation and
management of float; early release of competitive products
Cost Estimating errors; inadequate productivity, cost, change or
contingency control; poor maintenance, security, purchasing etc
Quality Poor attitude towards quality; substandard design/ material/
workmanship; inadequate quality assurance program
Human Resource Poor conflict management; poor project organization and definition of
responsibilities; absence of leadership
Communication Carelessness in planning and communication; lack of consolation
with key stakeholders
Risk Ignoring risk; unclear assignment of risk; poor insurance management
Procurement Unenforceable conditions or conflict clauses; adversarial relations
24
Risk Management Plan
Methodology used
Role and responsibilities of different stakeholders
Budgeting for risk management
Timing-Scheduling for risk management activities
Risk categories
Determining risk probability and impact of risk
Probability and impact matrix
Revised stakeholders’ tolerances
Reporting formats
Tracking of related tasks and issues
25
Risk identification
Risk identification is an iterative process, involving the
project team, management team, stakeholders and
subject matter experts (if required)
Any “ Genuine feelings” on possibilities of any disaster
could be identified as a potential “risk item”
Risk Identification Techniques
Brainstorming
Wideband Delphi Techniques
Nominal Group Technique
SWOT analysis
Interviewing
26
Expert Judgment
Many organizations rely on the intuitive feelings and
past experience of experts to help identify potential
project risks.
Experts can categorize risks as high, medium, or low
with or without more sophisticated techniques.
Can also help create and monitor a watch list, a list of
risks that are low priority, but are still identified as
potential risks.
27
Sample Risk Register/Risk Analysis
No. Rank Risk Description Category Root Triggers Potential Risk Probability Impact Severity Status
Cause Responses Owner
R44 1
R21 2
R7 3
28
Qualitative Risk Analysis
Assess the likelihood and impact of identified risks
to determine their magnitude and priority.
Risk quantification tools and techniques include:
Probability/impact matrixes
The Top Ten Risk Item Tracking
Expert judgment
29
Probability/Impact Matrix
A probability/impact matrix or chart lists the relative
probability of a risk occurring on one side of a matrix
or axis on a chart and the relative impact of the risk
occurring on the other.
List the risks and then label each one as high, medium,
or low in terms of its probability of occurrence and its
impact if it did occur.
Can also calculate risk factors:
Numbers that represent the overall risk of specific events
based on their probability of occurring and the
consequences to the project if they do occur.
30
Probability Impact Matrix
Effect of Occurrence
Probability
of Occurrence Very Low Low Moderate High Very High
Very Low
Low
Moderate
High
Very High
3
Red
Severity of
2
Occurrence
Yellow
1
Green
1 2 3
Probability of Occurrence
Quantitative Risk Analysis
Often follows qualitative risk analysis, but both
can be done together.
Large, complex projects involving leading edge
technologies often require extensive quantitative
risk analysis.
Main techniques include:
Decision tree analysis
Monte Carlo Approach – Modeling and Simulation
Sensitivity analysis
33
Decision Trees and Expected
Monetary Value (EMV)
A decision tree is a diagramming analysis technique
used to help select the best course of action in
situations in which future outcomes are uncertain.
Estimated monetary value (EMV) is the product of a
risk event probability and the risk event’s monetary
value.
You can draw a decision tree to help find the EMV.
34
Expected Monetary Value (EMV)Example
35
Sensitivity Analysis
Sensitivity analysis is a technique used to show the
effects of changing one or more variables on an
outcome.
For example, many people use it to determine what the
monthly payments for a loan will be given different
interest rates or periods of the loan, or for determining
break-even points based on different assumptions.
Spreadsheet software, such as Excel, is a common tool
for performing sensitivity analysis.
36
Sample Sensitivity Analysis for
Determining Break-Even Point
37
Top Ten Risk Item Tracking
Top Ten Risk Item Tracking is a qualitative risk
analysis tool that helps to identify risks and maintain an
awareness of risks throughout the life of a project.
Establish a periodic review of the top ten project risk
items.
List the current ranking, previous ranking, number of
times the risk appears on the list over a period of time,
and a summary of progress made in resolving the risk
item.
38
Example of Top Ten Risk Item Tracking
Monthly Ranking
Risk Item This Last Number Risk Resolution
of Months Progress
Month Month
Inadequate 1 2 4 Working on revising the
planning entire project plan
Poor definition 2 3 3 Holding meetings with
of scope project customer and
sponsor to clarify scope
Absence of 3 1 2 Just assigned a new
leadership project manager to lead
the project after old one
quit
Poor cost 4 4 3 Revising cost estimates
estimates
Poor time 5 5 3 Revising schedule
estimates estimates
39
Risk Response Planning
Process of developing options to enhance opportunities
and reduce threats to the project’s objective, ultimately
reducing overall risk
Resolution of risk
Once possible risks are listed, the PM has to take some
definite actions for each risk item. Typical risk resolution
actions are:
Research and review
Eliminate and review
Reduce and protect
Accept and protect
40
Risk Response Strategies
After identifying and quantifying risks, you must decide how to
respond to them.
Response strategies for negative risks:
Risk avoidance : Eliminating a specific threat or by eliminating
its cause
Risk transference: Shifting the consequence of a risk and
responsibility a third party such as another person, group
location etc
Risk mitigation: Reducing the impact of a risk event by
reducing possibility of its occurrence; applying preventive
measure; changing to alternate situation
41
Risk Response Strategies
Response strategies for positive risks:
Risk exploitation : Enhance plan to ensure that the
opportunity is realized; eliminate uncertainty to ensure
opportunity happens
Risk sharing: Involve third party who are better able to
realize opportunity
Risk enhancement: Modify the size of the opportunity by
increasing probability and maximizing key drivers of positive
impact risks
42
Risk Response Strategies
Response strategies for both risks:
43
General Risk Improvement Strategies for
Technical, Cost, and Schedule Risks
44
Residual and Secondary Risks
It’s also important to identify residual and secondary
risks.
Residual risks are risks that remain after all of the
response strategies have been implemented.
Secondary risks are a direct result of implementing a
risk response.
45
Risk Monitoring and Control
It is the process of keeping track of identified risks, monitoring residual risks,
executing risk plans and evaluating the effectiveness in reducing risk.
• Monitoring means the knowing their status
• Controlling means carrying out the risk management plan as risk occur
47
Using Software to Assist in Project
Risk Management
Risk registers can be created in a simple Word or Excel
file or as part of a database.
More sophisticated risk management software, such as
Monte Carlo simulation tools, help in analyzing project
risks.
The PMI Risk Specific Interest Group’s Web site at
www.risksig.com has a detailed list of software
products to assist in risk management.
48
Benefits of Risk Management
Minimize management by crisis
Encourage proactive management
Minimize surprises and problems
Gain competitive advantage
Decrease overall probability of project variances
Increase probability of project success
Increase profitability
Focus on building the right product the first time
Prevent problems from occurring, or if they occur,
from escalating
Chapter Summary
Project risk management is the art and science of
identifying, analyzing, and responding to risk
throughout the life of a project and in the best interests
of meeting project objectives.
Main processes include:
Risk management planning
Risk identification
Qualitative risk analysis
Quantitative risk analysis
Risk response planning
Risk monitoring and control
50
THANK YOU
51
Project Procurement Management
•1
Importance of Project Procurement
Management
• Procurement means acquiring goods and/or services
from an outside source
• Other terms include purchasing and outsourcing
• Experts predict that global spending on computer
software and services will continue to grow
• People continue to debate whether offshore
outsourcing helps their own country or not
•2
Debates on Outsourcing
• Some companies, such as Wal-Mart, prefer to do no
outsourcing at all, while others do a lot of outsourcing
•3
Why Outsource?
• To reduce both fixed and recurrent costs
• To provide flexibility
• To increase accountability
•4
Contracts
• A contract is a mutually binding agreement that obligates
the seller to provide the specified products or services and
obligates the buyer to pay for them
• Contracts can clarify responsibilities and sharpen focus on
key deliverables of a project
• Because contracts are legally binding, there is more
accountability for delivering the work as stated in the
contract
• A recent trend in outsourcing is the increasing size of
contracts
•5
•6
Project Procurement Management Processes
• Project procurement management: acquiring goods and
services for a project from outside the performing organization
• Processes include:
– Planning purchases and acquisitions: determining what to
procure, when, and how
– Planning contracting: describing requirements for the
products or services desired from the procurement and
identifying potential sources or sellers (contractors,
suppliers, or providers who provide goods and services to
other organizations)
•7
Project Procurement Management
Processes (continued)
• Requesting seller responses: obtaining information,
quotes, bids, offers, or proposals from sellers, as
appropriate
• Selecting sellers: choosing from among potential
suppliers through a process of evaluating potential
sellers and negotiating the contract
• Administering the contract: managing the relationship
with the selected seller
• Closing the contract: completing and settling each
contract, including resolving any open items
•8
Procurement Management Process Flow
•9
Planning Purchases and Acquisitions
• Identifying which project needs can best be
met by using products or services outside the
organization
•10
Tools and Techniques for Planning
Purchases and Acquisitions
• Make-or-buy analysis: general management
technique used to determine whether an
organization should make or perform a
particular product or service inside the
organization or buy from someone else
•12
Make-or Buy Solution
• Set up an equation so both options, purchase and lease, are
equal
• In this example, use the following equation; let d be the
number of days to use the item:
$12,000 + $400d = $800d
Subtracting $400d from both sides, you get:
$12,000 = $400d
Dividing both sides by $400, you get:
d = 30
• If you need the item for more than 30 days, it is more
economical to purchase it
•13
Types of Contracts
A contract is an agreement between two parties that creates an
legal obligation to perform (or not perform) a particular duty.
• Different types of contracts can be used in different
situations
– Fixed price or lump sum contracts: involve a fixed total price for
a well-defined product or service
– Cost reimbursable contracts: involve payment to the seller for
direct and indirect costs
– Time and material contracts: hybrid of both fixed price and cost
reimbursable contracts, often used by consultants
– Unit price contracts: require the buyer to pay the seller a
predetermined amount per unit of service
• A single contract can actually include all four of these
categories, if it makes sense for that particular procurement
•14
Point of Total Assumption
• The Point of Total Assumption (PTA) is the cost at
which the contractor assumes total responsibility
for each additional dollar of contract cost
• Contractors do not want to reach the point of
total assumption because it hurts them
financially, so they have an incentive to prevent
cost overruns
• The PTA is calculated with the following formula:
PTA = (ceiling price – target price)/government share +
target cost
•15
Cost Reimbursable Contracts
• Cost plus incentive fee (CPIF): the buyer pays the
supplier for allowable performance costs plus a
predetermined fee and an incentive bonus
• Cost plus fixed fee (CPFF): the buyer pays the supplier
for allowable performance costs plus a fixed fee
payment usually based on a percentage of estimated
costs
• Cost plus percentage of costs (CPPC): the buyer pays
the supplier for allowable performance costs plus a
predetermined percentage based on total costs
•16
Contract Types Versus Risk
17
Considerations When Selecting
Contract Types
• Unstable labor conditions
• Unstable market conditions
• Improvement in production is required
• Complexity of product or service
• Product or service requires development
• Design is not completed or may change
• Learning must take place
• Short time to prepare for a bid or negotiation
• Short delivery period
– Which may require additional resources to meet deadlines
Contract Clauses
• Contracts should include specific clauses to
take into account issues unique to the project
•20
Contract Statement of Work (SOW)
• A statement of work is a description of the work
required for the procurement
• If a SOW is used as part of a contract to describe only
the work required for that particular contract, it is
called a contract statement of work
• A SOW is a type of scope statement
• A good SOW gives bidders a better understanding of
the u er’s e pe tatio s
•21
Statement of Work (SOW) Template
I. Scope of Work: Describe the work to be done to detail. Specify the hardware and
software involved and the exact nature of the work.
II. Location of Work: Describe where the work must be performed. Specify the
location of hardware and software and where the people must perform the work
III. Period of Performance: Specify when the work is expected to start and end,
working hours, number of hours that can be billed per week, where the work must
be performed, and related schedule information.
IV. Deliverables Schedule: List specific deliverables, describe them in detail, and
specify when they are due.
V. Applicable Standards: Specify any company or industry-specific standards that
are relevant to performing the work.
VI. Acceptance Criteria: Describe how the buyer organization will determine if the
work is acceptable.
VII. Special Requirements: Specify any special requirements such as hardware or
software certifications, minimum degree or experience level of personnel, travel
requirements, and so on.
22
Planning Contracting
• Involves preparing several documents needed for potential
sellers to prepare their responses and determining the
evaluation criteria for the contract award
– Request for Proposals: used to solicit proposals
from prospective sellers
• A proposal is a document prepared by a seller when there are
different approaches for meeting buyer needs
– Requests for Quotes: used to solicit quotes or bids
from prospective suppliers
• A bid, also called a tender or quote (short for quotation), is a
document prepared by sellers providing pricing for standard
items that have been clearly defined by the buyer
•23
Request for Proposal (RFP) Template
I. Purpose of RFP
II. Organization’s Background
III. Basic Requirements
IV. Hardware and Software Environment
V. Description of RFP Process
VI. Statement of Work and Schedule Information
VII. Possible Appendices
A. Current System Overview
B. System Requirements
C. Volume and Size Data
D. Required Contents of Vendor’s Response to RFP
E. Sample Contract
24
Evaluation Criteria
• It’s i porta t to prepare so e for of
evaluation criteria, preferably before issuing a
formal RFP
•26
Selecting Sellers
• Also called source selection
• Involves:
•27
Sample Proposal Evaluation Sheet
28
Seller Selection Process
• Organizations often do an initial evaluation of
all proposals and bids and then develop a
short list of potential sellers for further
evaluation
•30
Change Control in Contracts
• Changes to any part of the project need to be reviewed,
approved, and documented by the same people in the
same way that the original part of the plan was approved
•31
Change Control in Contracts (continued)
• Project managers and teams should stay closely
involved to make sure the new system will meet
business needs and work in an operational
environment
•32
Closing the Contract
• Involves completing and settling contracts and
resolving any open items
• The project team should:
– Determine if all work was completed correctly and
satisfactorily
– Update records to reflect final results
– Archive information for future use
• The contract itself should include requirements for
formal acceptance and closure
•33
Tools to Assist in Contract Closure
• Procurement audits identify lessons learned in
the procurement process
•34
Using Software to Assist in Project
Procurement Management
• Word-processing software helps write proposals and
contracts, spreadsheets help evaluate suppliers,
databases help track suppliers, and presentation
software helps present procurement-related information
• E-procurement software does many procurement
functions electronically
• Organizations also use other Internet tools to find
information on suppliers or auction goods and services
•35
Chapter Summary
• Project procurement management involves
acquiring goods and services for a project from
outside the performing organization
• Processes include:
– Planning purchases and acquisitions
– Planning contracting
– Requesting seller responses
– Selecting sellers
– Administering contracts
– Closing contracts
•36
Thank You!
•37
Developing Custom Processes for IT Projects
Why Custom Processes for IT Projects?
• Custo er’s role is do i a t
• Environment is more dynamic
• Tasks are mental, unique, and complex
• Society is more democratic and educated
• Individuals have higher aspirations and expectations
• Go er e t’s role is less lear, a d its perfor a e ore
closely scrutinize
• Sources of knowledge are different (tacit knowledge, the
practitioner)
Economics: Law of Supply and Demand
• Project Status
• Maximizing benefits
Economics of Project
Regulating Supply
• Cost Analysis- Peoples, work flow etc
Managing Supply and Demand for a PM
SUPPLY
Efficiency MAX. BUSINESS VALUE
DO THE PROJECT RIGHT
• Business centric IT
• Reliable Delivery
HIGH solution
Lesson Learned
19
Certification
In an increasingly projectized world, professional certification ensures that project managers
are ready to meet the demands of projects across the globe. Learn more about PMI’s
certifications and find one that’s right for you. If you already have a credential, get what you
need to maintain it, or look into earning another one.
Solidify your skill set and face project challenges head-on with a PMI certification.
The Project Management Professional (PMP)® is the most important globally-recognized and independently
validated credential for project managers, perfect if you have demonstrated experience and competence in
leading project teams.
The Program Management Professional (PgMP)® is designed for those who manage multiple, complex projects
to achieve strategic and organizational results.
The PMI Agile Certified Practitioner (PMI-ACP)® is designed for practitioners who utilize Agile approaches to
project management in their projects.
The PMI Risk Management Professional (PMI-RMP)® is a specialty credential that demonstrates competence in
assessing project risks, mitigating threats and capitalizing on opportunities.
The PMI Scheduling Professional (PMI-SP)® is a specialty credential for practitioners who want to focus on
developing and maintaining project schedules.
The OPM3® Professional Certification recognizes your experience with, and practical knowledge of, organization
project management and project management maturity.
Why Choose a PMI Certification?
You may have seen other project management certifications. What makes PMI’s special?
Our credentials:
Are flexible. PMI certifications are not based on one specific methodology, so they’re flexible and
adaptable. You can easily transfer them between industries, market segments and geographic
locations.
Keep you up-to-date. PMI continually conducts in-depth studies to ensure that our credentials
actually reflect the current skills, knowledge and best practices you need to succeed.
Encourage professional growth. You never have to worry about a PMI certification becoming
obsolete. Our certification maintenance program requires you to earn professional development
units (PDUs), which encourages you to continually develop your skills and stay current as the
profession changes.
Help you get ahead. PMI certification offers financial benefits — The PMI Project Management
Salary Survey — Seventh Edition shows that certification positively impacts project manager
salaries — and helps you stand out and better market yourself to prospective employers.
Are renowned throughout the world. Part of that marketability comes from the prestige of PMI
certifications. PMI has provided project management certifications for over 25 years, and our
PMP®credential was the first one designed specifically for project managers. Also, the quality of
our certification governance is an advantage to those or earn or seek one of our certifications.
http://www.pmi.org/Certification/What-are-PMI-Certifications.aspx
Growth in PMP Certification, 1993-2003
80,000
76,550
70,000
60,000
52,443
50,000
# PMPs
40,000 40,343
30,000 27,052
20,000 18,184
10,000 10,086
6,415
4,400
1,900 2,800
1,000
0
1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003
Year
Information Technology Project Management, Fourth
23
Edition
Ethics in Project Management
An i di idual’s Basic
convictions of
What is Right & Wro g
31
Values
33
Behavior
not illegal,
Yet People still
disagree
If not
ethical.
34
Ethics of top Project
Manager
–set the
–tone for
–Project
35
Ethics Codes
& Policies
Pro ide sig of top Ma age e t’s desires
in
Project Based
Organizational culture
36
Why Behave Ethically?
Project Manager should behave ethically
To Avoid Harming others. Managers
Responsible for Prote ti g & Nurturi g
Resources
In their Charge.
37
Leadership, Culture, I e ti e
Co pe satio Pla s help “hape
I di idual Ethi al eha ior
in Project Management
38
Promoting Ethics
40
Ethical culture: firms increasingly
seek to make good ethics part
of norm & organizational
culture.
41
Ethical decisions involve
42
Views of Ethical Decision-Making
43
CODE OF ETHICS FOR PROJECT MANAGERS
44
ARTICLE I: Project Managers shall maintain high standards of personal and
professional conduct.
a) Accept responsibility for their actions.
b) Undertake projects and accept responsibility only if qualified by training or
experience, or after full disclosure to their employers or clients of pertinent
qualifications.
c) Maintain their professional skills at the state -of-the-art and recognize the
importance of continued personal development and education.
d) Advance the integrity and prestige of the profession by practicing in a
dignified manner.
e) Support this code and encourage colleagues and co-workers to act in
accordance with this code.
f) Support the professional society by actively participating and encouraging
colleagues and coworkers to participate.
g) Obey the laws of the country in which work is being performed.
45
ARTICLE II: Project Managers shall, in their work:
48
THANK YOU
The Balanced Scorecard
STRATEGIC OUTCOMES
VALUES
What’s important to us
STRATEGY
Our game plan
BALANCED SCORECARD
Translate, Focus and Align
STRATEGIC INITIATIVES
What are the priorities
TOTAL QUALITY MANAGEMENT
What we must improve
EMPOWERMENT / PERSONAL OBJECTIVES
What I need to do
STRATEGIC OUTCOMES
– Financial
– Customer
– Internal business
– Innovation and learning
Financial Perspective
• How do we look to stakeholders?
– Survive
– Succeed
– Prosper
Customer Perspective
• How do our customers see us?
– New products
– Responsiveness
– Quality
Internal Business Perspective
• At what must we excel currently?
– Manufacturing/service excellence
– Technological leadership
– Time to market
– Employee training and satisfaction
Perspectives are Interrelated
• Innovation pleases customers which are
necessary for good financial results
Strategic Theme:
Operating Efficiency Statement of How success
what strategy in achieving The level of Key action
Financial
Profitability must achieve the strategy performance programs
and what’s will be or rate of required to
Increase critical to its measured and improvement achieve
Lower Costs
Revenue
success tracked needed objectives
Customer
Flight Lowest
is on time prices
Ground crew
alignment
The Complete Balanced Scorecard Strategy Map
Improve Shareholder Value
Financial Productivity Strategy Shareholder Value Revenue Growth Strategy
ROCE
Perspective:
the drivers of Improve Cost Create Value from
Increase Asset Enhance Customer
shareholder Structure Utilization Value New Products &
Services
value Customer
Cost per Unit Asset Turnover New Revenue
Profitability Sources
• Market and Account Share Customer Acquisition Customer Retention Customer Satisfaction
Customer Product Leader
Perspective: Customer Solutions
the
Customer Value Proposition Low Total Cost
differentiating
Product/Service Attributes Relationship Image
value
proposition Price Quality Time Function Service Relations Brand
Internal
Operations Theme Customer Innovation Theme Regulatory and
Perspective: Management Society Theme
how value is Theme (Processes that (Processes that
Create New
created and (Processes that Produce (Processes that
Products and
Improve the
and Deliver Products Enhance Customer Environment
sustained & Services) Value) Services) and
Communities)
Strengths Weaknesses
Strategic Issues
Strategic Priorities
Objectives, Initiatives, and Evaluation
Business Strategy
Business Strategy
Corporate Culture
Corporate Culture
– Implementation requires
• Thought
• Analysis
• Data-gathering
• Time
Overall Concepts
• Thought
– Never-ending process
Implementation Steps
• Initiative must start at the top
• Wo ’t produ e u -in
Implementation Steps
• Interview senior managers
• Individual reactions
– Suggested refinements
Implementation Steps
• Expand consensus
• Finishing touches
– Communicate to employees
• Lack of consensus
– Lack of commitment
The Road to Disaster
• Consultants
– Good
• Provide needed expertise
– Bad
• Take over the project
• Consensus, commitment of employees is lost
The Road to Disaster
• Failure to communicate
• Strategy
• Their roles
• Importance of the scorecard measures
The Road to Disaster
• La k of push-do
– It o ’t e perfe t, e er
• Must evolve
– We a t to e the est o ’t do
Communicating and Linking
• Corporate strategy must be communicated to
all levels