Method of statement OF external paint
Method of statement OF external paint
SYSTEM
1. PURPOSE.
2. SCOPE.
3. REFERENCES.
4. DEFINITIONS.
5. RESPONSIBILITIES.
6. MATERIALS.
8. WORK PROCEDURE.
10. DISTRIBUTION.
12. QC Forms.
To outline the procedures for the application of external paint to the building phase 5, city walk,
Dubai. ensuring quality, safety, and adherence to the project specifications.
2. SCOPE
This method statement covers the application of external paint on elevations, balcony walls, slab
soffits, and EIFS (Exterior Insulation and Finish System) for Golf Gate Tower B.
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
5.1 The Construction Manager is responsible for implementation of this Method Statement and shall
ensure that his team of Engineers and Foremen are familiar with the method statement and all the
resources (human, material and equipment) that are available to carry out the associated work as
planned and without any delay.
5.2 The Project Engineer is responsible to carry out the works as per the approved shop drawings,
method statements, specification and other Contract documents. He is also responsible to ensure that
suitable equipment for the concrete placing, finishing and curing operations are in place and ready for
use well in advance of commencement of the related works.
5.3 The QA/QC Manager is responsible to ensure that the works are done as per the approved method
statement, specification and drawings; inspections shall be carried out as per the Inspection and Test
plan and offered for inspection by the Engineer
5.4 The Safety Manager is responsible to ensure that all Safety precautions are in place, and that all
personnel on site are using the required Personal Protective Equipment such as Helmet, Gloves, Shoes,
and Coveralls. He shall also ensure that all relevant permits are obtained for the works as per the
requirements of the UAE Authorities.
6. MATERIALS
Option 4 : 1 Coat Capaacryl Primer /1 Coat Capagrain / 2 Coats Flexotop ( MEDIUM TEXTURE )
1. Site Preparation:
2. Surface Preparation:
6. Finishing Touches:
Option 4: Medium Texture (1 Coat Capaacryl Primer / 1 Coat Capagrain / 2 Coats Flexotop)
Follow the remaining steps as in Option 1, adjusting for the application of Flexotop.
Same as Option 1 but replace Flexoshield with Flexoguard for a smooth texture.
10. DISTRIBUTION
Copies of this method statement have also been issued to the following for information/
action/comments:
• HSE Engineer.
• QA/QC Engineer.
11. INSPECTION/ TEST PLAN
12. QC Forms
13. Risk Assessment