progress report
progress report
Description of works
Ground floor:
Excavate works;
Pedestal works;
Rebars Installation etc.
Total of Pedestal = 133
Task 3 Primer paint for "I" Beam 10/21/2024 10/26/2024 5 On-going 99%
24
24
24
24
4
20
20
20
20
02
02
02
/2
/2
/2
8/
9/
0/
1/
/2
/2
/3
/3
/1
/2
/3
10
10
10
10
11
11
11
Excavation and site preparation
Sewer works
24 24 24 24 24 24 24
20 20 20 20 20 20 / 20
/ / / / / / 0
/4 /5 /6 /7 /8 /9 /1
11 11 11 11 11 11 11
MATERIALS DESCRIPTION:
LOCATION:
TOTAL AREA OF; 566 (SQM)
LOCATION:
TOTAL AREA OF; 520 (SQM)
PREPARED BY;
Calvin tabada
WEEKLY PROGRESS REPORT CHART
Project
Task description Start date End date Status acc.% Remarks
details
Task 4 Welding works 10/21/2024 10/26/2024 pending 11% Electrical short circuit
Remarks
acc.%
Task 4 Welding works 10/21/2024 10/26/2024 pending Task 3 Primer paint for "I beam" 10/21/2024 10/26/2024 in progress
Task 2 Foundation and footing works 10/21/2024 10/26/2024 in progress Task 1 Excavation and site preparation 10/21/2024 10/26/2024 in progress