Thermofusion Procedure for HDPE Pipe
Thermofusion Procedure for HDPE Pipe
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 1of 42
TEP-SM-0010-PR-QC-1023
CONTRACTOR DATA
Prepared by: Reviewed by: Approved by: Authorized by:
Name(s): Name(s): Name(s): Name(s):
INDEX OF REVISIONS
Version Review Date Description
TO 04.06.18 Issued for internal review SM
B 06.06.18 Issued for SMI review and approval
C 23.09.17 Issued for SMI review and approval
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 2of 42
INDEX
1 OBJECTIVE ………………………………………………………………………...……………………. 4
2 SCOPE ……………………………………………………………………………………………. 4
3 REFERENCE DOCUMENTS …………………………………………….……….…………. 4
4 DEFINITIONS …………………………………………..……………………………….………….… 5
4.1 HDPE pipe
4.2 Butt Fusion Welding
4.3 Equipment operability
4.4 Polyethylene
5 RESPONSIBILITIES……………………………….…………………………………………………..5
5.1 Project Manager
5.2 Head of Production
5.3 SSOMA Chief/Supervisor
5.4 Quality Manager
5.5 Quality Supervisor
5.6 Head of Technical Office
5.7 Front Chief
5.8 Construction Supervisor
5.9 Foreman
5.10 Workers and Officers
6 DEVELOPMENT …………………………………………………………………… …… 9
6.1 Basic concepts
6.1.1 Thermoplastic material
6.1.2 Polyethylene
6.1.3 Classification of HDPE Pipes
6.1.4 Pipe welding by thermofusion
6.2 Hot-melt welding equipment for HDPE pipes
6.2.1 Heating element
6.2.2 Countersignature
6.2.3 Binding mechanism
6.3 Hot-melt welding process for HDPE pipe
6.3.1 Pipe placement
6.3.2 Presentation
6.3.3 Facing
6.3.4 Fusion and joining of ends
6.3.5 Cooling
6.4 Parameters of thermofusion welding for HDPE pipes
6.4.1 Surface Temperature
6.4.2 Facing Pressure
6.4.3 Heating Pressure
6.4.4 Union Pressure
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 3of 42
6.4.5 Warm-up time
6.4.6 Cooling Time
6.4.7 Essential Variables according to Diameter and SDR
1 OBJECTIVE
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 4of 42
Establish the general specific criteria for fusing and/or joining HDPE pipes
using a thermofusion machine and thus successfully achieve the continuity of
the line, taking into account the relevant Technical Specifications.
Establish reliable installation methods and system designs for satisfactory
product and material performance. Any improperly or inappropriately made
joint or connection could cause delays in installation, could disable or impair
system operations, or could create hazardous conditions.
2 SCOPE
The scope of this procedure is directed to all work to be carried out in HDPE
pipe thermofusion.
3 REFERENCE DOCUMENTS
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 5of 42
4 DEFINITIONS
4.1 HDPE pipe
It is a high-density polyethylene pipe, of variable diameter and thickness,
used to channel or transport liquids.
4.4 Polyethylene
Thermoplastic material obtained from the polymerization of ethylene. Four
grades of this material are distinguished according to their molecular weight:
5. RESPONSIBILITIES
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 6of 42
Support and adopt the directives and recommendations proposed by the
SMCGSA Management, in order to guarantee the safety and health of
employees in the work to be performed.
Lead the implementation of procedures that ensure a commitment to safety
and the environment in the area of influence.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 7of 42
Ensure compliance with this procedure and support in meeting the needs
for materials, equipment and human resources, and the execution and/or
inspection of all related work.
Identify and evaluate the risks of the work to be performed and take the
necessary corrective actions to control them.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 8of 42
5.7 Front Chief
Prepare this procedure regarding construction and execution
responsibilities and submit it for approval by the Head of Production.
Dissemination of this approved procedure to all personnel involved in
construction tasks, including supervisors, foremen, operators and
assistants. Presentation of the Training Record to the Quality Manager.
Request the plans, technical specifications and other contractual
documentation applicable to carrying out construction tasks in this
procedure from the Technical Office Document Control Officer.
Call the Quality Supervisor for a prior on-site review, recording construction
details to be applied according to current project plans.
Have the Mechanical Construction Supervisor jointly verify, with the Quality
Supervisor of the discipline, the mechanical equipment upon receipt before
installation.
Determination, request and administration of resources necessary for the
execution of the construction work of this procedure.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 9of 42
5.9 Foreman
Receive construction instructions from the Construction Supervisor
regarding the installation of mechanical equipment; transmit field directives
to workers and helpers and lead operational construction activities on site.
Fill out and complete the continuous IPERC records in the work team and
process their signature in the work crew.
Inspect the tools of the work crew personnel, verifying that they are in good
condition and reporting any problems to the Construction Supervisor for any
required actions.
Timely transmit to the Construction Supervisor the requirements for the
proper performance of construction work.
6. RESOURCES
6.1 Staff
DESCRIPTION
Project Manager
Head of Production.
Security Chief/Supervisor
Quality Manager
Quality Supervisor
Head of Technical Office
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 10of 42
Front Chief
Construction Supervisor
Foremen
Workers and assistants
Officials
Helpers
Figure 1. Project staff table.
DESCRIPTION
Safety helmet.
Safety glasses.
Rubber gloves.
Leather Gloves.
Safety shoes.
Safety Harness.
Uniform Pants/shirt (both with reflective tape).
Vest with reflective tape for supervisors.
Dust respirator.
Sun block.
Figure 2. Table of personal protective equipment.
DESCRIPTION
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 11of 42
60 kW Electric Generator
Hand Tools
6 Lb Jump Ropes
Thermometer
7. PROCEDURE
The equipment will also be located inside a tent which will be covered
with a fireproof blanket and always in dry places.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 12of 42
The inspection of the work area will be carried out by the production area
together with advice from the safety area.
Welding work using thermal fusion will be carried out in broad daylight. If
night work is required, it will be coordinated with the respective areas and
adequate lighting (300 lux) will be provided inside the welding tent.
The heat-sealed tent should not be placed in places where water collects
due to rain. If there is any water leak, the equipment operator will check
the area before starting work, and accordingly corrective measures will be
taken, which may range from placing the spill tray on pallets to relocating
the tent.
7.1 Basic Concepts
7.1.2 Polyethylene
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 13of 42
The higher the molecular weight, the increased hardness, impact resistance and
abrasion resistance.
Another classification is based on density:
It is worth mentioning that the higher the density, the higher the tensile strength,
that is, the ability to absorb stress without permanent deformation increases.
In the field, 16” and 10” pipes will be worked on in the first stage.
Continuing with the work, the manufacture of 3”, 6”, 8” and 10” spools will
be carried out. For the transportation of pipes, field personnel are
considered. The quantities will depend on the type of diameter and length
of the spool, and should not exceed 25kg of load capacity per person.
The pipes will be transported in 12m sections using a 12m flatbed truck
with the help of a crane truck. For the transport of spools, field personnel
are considered, the quantity will depend on the fact that the personnel
should not exceed 25kg of load per person.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 14of 42
The standardized SDRs are as follows: 41, 32.5, 26, 21, 17, 13.5, 11, 9, 7.3.
Each SDR corresponds to a specific operating pressure.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 15of 42
The Working Pressure for the HDPE lines of the project according to
Specification 0010-GD-P-007 are:
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 16of 42
The Test Pressure will be the Working Pressure x 1.5 according to standard
B31.3:
The brand of the machine to be used is: SUDA PLASTIC PIPE WELDING
MACHINERY CO. LTDA, the model is SUD-IV Series, the product name
is: HYDRAULIC BUTT FUSION WELDING MACHINE.
The latest special machines designed for this use are made up of the
following elements.
These machines will be connected to the 60kw electric generator, which
will have the controls required by the maintenance area such as:
grounding, spill tray, inspected cables, check list of the equipment and
the electrical panel for energy distribution, etc.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 17of 42
Metal heating plate based on an internal electrical resistance. The metal of
the plate is light (Al) for easy handling and has a thin asbestos cover to
prevent adhesion of the plastic material.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 18of 42
7.3.2 Presentation:
Once the pipe is placed, it is presented at the ends to verify the following
conditions:
7.3.3 Facing:
The facing machine is placed between the two ends of the pipes.
They join together with the help of the binding mechanism.
The facing machine is activated, which must remove the necessary
material until total contact is achieved between the faces.
Once the previous condition has been verified, the endorser is removed.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 19of 42
Once the energized iron has reached the recommended temperature
(KWH 425°F +/- 25°F) it is placed between the ends after cleaning it with
alcohol and an industrial cloth.
The pipes are put in contact with the plate at a certain pressure.
Heat until a sufficient bead thickness is formed on both pipes (See table
in 6.4 a)
The pipes are separated to remove the plate.
They are quickly brought together, but without violently striking them, the
ends melted at the Interfacial Fusion Pressure (75 PSI).
After removing the heating plate, the sides should not be separated
for more than 10 seconds.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 20of 42
7.3.5 Cooling:
The jaws are brought together and allowed to cool for the necessary time until
the material reaches room temperature. This time can be estimated at
approximately 25 minutes per inch of pipe thickness.
Once this step is completed, the clamps are loosened and the pipes are
moved, leaving the last end of the pipe at the height of the machine and
placing the next one, to restart the cycle.
Of all the steps mentioned, the following are considered to be phases of the
process subject to control:
Alignment
Facing
Fusion of extremes
Union of extremes
Cooling
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 21of 42
The parameters stated above are not fixed, they vary according to the thickness
of the pipe (SDR), the diameter of the pipe and the temperature of the medium.
Although there are some general recommendations on some reference values.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 22of 42
the ease of controlling the thickness of the bead, and values close to the upper
limit for pipes with larger diameters, in order to accelerate fusion. (KWH
indicates 425°F +/- 25°F)
7.4.3 Heating Pressure. - This pressure is kept slightly at zero PSI and is
controlled by the geometry of the rod that is being formed, as the material
is heated.
7.4.4 Union Pressure. - Pressure values are variable and dependent on the
diameter and thickness (SDR) of the pipe. The manufacturer has prepared
tables with some values resulting from some tests with its material. These
values are for reference only as significant variations have been observed
from one manufacturer to another.
(OD2 – ID2) X FI X Pi
PM = ---------------------------------- where:
4 X AP
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 23of 42
unions are only allowed of pipe with accessories with the same diameter and
wall thickness, that is, the same SDR.
In the event that any accessory has a variation in diameter or thickness due to
manufacturer specifications, for the heat fusion the pipe with the smallest
diameter and/or thickness will be centered on the pipe with the largest diameter
and/or thickness, trying to ensure that the largest fusion area remains in contact
with each other.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 24of 42
SDR11( PE80/PE100)
Pressure Pressure≈ Switching Rising Pressure
P2 P2 P2 P2 P2
= P1 P drag time time t 4 = P1
Diameter Thickness Surface
Flanging Heating Cooling Mpa(160/2
( mm ) ( mm ) force (N) t3 (sec) Mpa(250) Mpa(315) Mpa(450) Mpa(630)
height time t2 time t 5 00)
(mm) (sec) (sec) (min)
25 2.3 24.6 0.7 23 < 3 < 5 8 0.01 0.01 0.01 0.01
32 3 41 0.7 30 < 3 < 5 8 0.02 0.02 0.02 0.02
40 3.7 63.3 1 37 < 3 < 5 9 0.04 0.03 0.03 0.02
50 4.6 98.4 1 46 < 3 < 6 9 0.06 0.06 0.05 0.04 0.04
63 5.8 156.3 1 58 < 3 < 6 10 0.1 0.09 0.08 0.06 0.06
75 6.8 218.4 1 68 < 4 < 6 10 0.14 0.12 0.11 0.09 0.08
90 8.2 315.9 1.5 82 < 4 < 7 11 0.21 0.18 0.16 0.13 0.12
110 10 471 1.5 100 < 4 < 7 14 0.31 0.27 0.24 0.19 0.17
125 11.4 610 1.5 114 < 4 < 8 15 0.4 0.35 0.3 0.25 0.23
140 12.7 761.5 2 127 < 4 < 12 17 0.5 0.43 0.38 0.31 0.28
160 14.6 999.9 2 146 < 5 < 13 19 0.65 0.57 0.5 0.4 0.37
180 16.4 1263.7 2 164 < 5 < 14 21 0.83 0.71 0.63 0.51 0.47
200 18.2 1558.4 2 182 < 5 < 15 23 1.02 0.88 0.78 0.63 0.58
225 20.5 1974.5 2.5 205 < 5 < 12 26 1.12 0.99 0.8 0.73
250 22.7 2430.2 2.5 227 < 6 < 13 28 1.37 1.22 0.98 0.9
280 25.4 3045.9 2.5 254 < 6 < 14 31 1.52 1.23 1.12
315 28.6 3858 3 286 < 6 < 15 35 1.93 1.56 1.42
355 32.2 4895.6 3 322 < 7 < 17 39 1.98 1.81
400 36.3 6218.3 3 363 < 7 < 19 44 2.52 2.3
450 40.9 7880.9 3.5 409 < 8 < 21 50 3.19 2.91
500 45.4 9720.9 3.5 454 < 8 < 23 55 3.59
560 50.8 12183.5 4 508 < 9 < 25 61 4.5
630 57.2 15431.9 4 572 < 9 < 29 67 5.7
8. MODES OF ACCEPTANCE
Because the quality of an HDPE weld depends largely on how it has been
worked, in each phase, within the appropriate ranges of pressure, temperature
and time, these parameters will be controlled in the format called WELDING
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 25of 42
PROCEDURES SPECIFICATION, where the recommended values must be
reflected.
The configuration of the board will directly indicate the correctness of the
parameters assigned in the previous control.
The following aspects should be taken into account:
.
Higher pressure than recommended will cause the bead to overlap itself,
which may result in a poor quality fusion as the bead will be expelled to the
outer and inner diameter of the fusion, creating a “cold ring” in the central area
of the fusion.
The formed flange must be uniform in size and shape all around the joint.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 26of 42
Table No. 01
Good alignment is a basic condition for the pipe to be able to normally withstand
bending stresses in the seam area. The eccentricity must not exceed 10% of the
pipe thickness.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 27of 42
8.1.1.2 Ultrasound Test: (The procedure was sent with code number
TEP-SM-0010-PR-QC-042)
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 28of 42
According to the ASME Section IX code, the following tests will be
performed and attached in the Test package:
Length equal to 15 times the thickness on each side of the seam and with
a minimum of 6”
Width equal to 1.5 times the thickness and with a minimum of 1”.
2.00 strips of these will be taken and sent to the laboratory for their
respective testing.
Once the test is completed, the welding factor will be calculated according
to the formula:
In the test joint, the two remaining strips whose measurements were
defined in the tensile test will be taken and the following procedure will be
followed:
The strips will be bent at 60° +_ 10° taking into account making a fold on
the outside of the strip and the next fold on the inside. (As shown in the
figure).
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 29of 42
After folding, the seams should not have pores, cracks and/or visible
imperfections.
For bending tests of pipe samples with greater thicknesses, a field press
will be used, as shown in the photo:
8 ANNEXES
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 30of 42
8.1 Annex 01
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 31of 42
Control y Aseguramiento de Calidad CM121701.QCA.FOR.064
EQUIPO EMPLEADO:
LÍNEA:
PLANO DE REFERENCIA: φ TUBERÍA: SDR:
4 El ancho total del cordon de soldadura de doble fusión debe ser de 2 a 2.5 veces la altura de la soldadura desde la superficie del tubo.
5 No hay presencia de aperturas ni de vacíos visibles entre los cordones del empalme por fusión.
6 No hay desalineamiento en los extremos de los tubos mayores al 10% del espesor del tubo.
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 32of 42
8.2 Annex 02
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 33of 42
Control y Aseguramiento de Calidad CM121701.QCA.FOR.065
SUPERVISIÓN/CLIENTE: FECHA:
AREA: N° DE REGISTRO:
DATOS DE CAMPO
Espesor: Fabricante
Condiciones Ambientales (Temperatura
Longitud de Probeta:
y Humedad)
Ancho de Probeta:
PRUEBA DE DOBLEZ
Probeta A Probeta B
Doblada Doblada
La Junta esta Doblada 60º?
PARAMETROS
Temperatura de la Plancha
Tiempo de calentamiento
Presión de Fusión
Tiempo de Fusión
Parametros Ambientales
OBSERVACIONES
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 34of 42
8.3 Annex 03
Control y Aseguramiento de Calidad CM121701.QCA.FOR.045
FECHA:
DESCRIPCIÓN: TAG:
COMENTARIOS / OBSERVACIONES
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 35of 42
8.4 Annex 04
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 36of 42
8.5 Annex 04
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 37of 42
8.6 Annex 04
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 38of 42
8.7 Annex 05
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 39of 42
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 40of 42
8.8 Annex 06
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 41of 42
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.
JJB Engineering and Construction SAC
PROCEDURE
Code : TEP-SM-0010-PR-QC-
Revisio 1023
HDPE Pipe Installation and Fusion Procedure n :C
Page : 42of 42
8.9 Annex 07
The printing of this document is considered an uncontrolled copy, except for one that is properly identified.
The current versions of the documents can be found on the internal network of San Martín Contratistas Generales.