Letters at Contracts 21

The Contractor has requested evidence from the Employer regarding financial arrangements to ensure the ability to pay the Contract Price as per the contract terms. Additionally, the Contractor seeks notification of any material changes to these financial arrangements to avoid disruptions. The Employer has acknowledged the request and provided the necessary documentation to confirm that financial arrangements are in place and being maintained.

Uploaded by

tarekZAD
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views3 pages

Letters at Contracts 21

The Contractor has requested evidence from the Employer regarding financial arrangements to ensure the ability to pay the Contract Price as per the contract terms. Additionally, the Contractor seeks notification of any material changes to these financial arrangements to avoid disruptions. The Employer has acknowledged the request and provided the necessary documentation to confirm that financial arrangements are in place and being maintained.

Uploaded by

tarekZAD
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

69

Subject: Request for Evidence of Financial Arrangements [FIDIC 1999 & 2017].

Dear [Employer's Representative],

The Contractor refers to Sub-Clause 2.4 [Employer’s Financial Arrangements] of


the Contract and requests that the Employer provide reasonable evidence that
financial arrangements have been made and are being maintained to ensure the
Employer’s ability to pay the Contract Price as estimated at this time, in
accordance with Clause 14 [Contract Price and Payment].

The Contractor appreciates the Employer’s prompt response to this request and
looks forward to receiving the required documentation within the next 28 days, as
stipulated by the Contract.

Yours sincerely,
[Contractor's Representative]

Prepared by: Omar Lotfy email: [email protected]


Mobile: +966-563207897 +20-1111794740
LinkedIn: linkedin.com/in/omar-el-mesalamy-mba-ciccm-clac-aciarb-718317159 Ω
70

Subject: Notification of Material Change to Financial Arrangements [FIDIC 1999


& 2017]

Dear [Employer's Representative],

In accordance with Sub-Clause 2.4 [Employer’s Financial Arrangements], the


Contractor requests that the Employer notify the Contractor of any material
changes to the financial arrangements previously provided, along with detailed
particulars.

It is crucial that the Employer ensures the ongoing maintenance of financial


arrangements to avoid any disruption to the Works. The Contractor kindly requests
immediate notification should there be any significant changes that might impact
the Employer's ability to fulfill its payment obligations under the Contract.

The Contractor looks forward to the Employer’s cooperation in this matter.

Yours sincerely,
[Contractor's Representative]

Prepared by: Omar Lotfy email: [email protected]


Mobile: +966-563207897 +20-1111794740
LinkedIn: linkedin.com/in/omar-el-mesalamy-mba-ciccm-clac-aciarb-718317159 Ω
71

Subject: Submission of Financial Arrangements in Response to Contractor's


Request.

Dear [Contractor's Representative],

The Employer acknowledges receipt of the Contractor's request under Sub-Clause


2.4 [Employer’s Financial Arrangements]. In accordance with the Contract, the
Employer provides the necessary documentation and reasonable evidence that the
financial arrangements to meet the Contract Price, as estimated at this time, have
been made and are being maintained.

Please find attached the required documentation for your review. The Employer
remains committed to fulfilling all financial obligations as stipulated under the
Contract and ensuring the uninterrupted progress of the Works.

Should the Contractor have any further questions or require additional clarification,
the Employer is available to address such queries.

Yours sincerely,
[Employer's Representative]

Prepared by: Omar Lotfy email: [email protected]


Mobile: +966-563207897 +20-1111794740
LinkedIn: linkedin.com/in/omar-el-mesalamy-mba-ciccm-clac-aciarb-718317159 Ω