2022 Scrra Standard Specifications
2022 Scrra Standard Specifications
STANDARD
SPECIFICATIONS
FINAL
February 2022
PART 1 - GENERAL
1.01 SUMMARY
This section summarizes requirements and provisions for the Contractor’s execution of
the Work under this Contract.
1.02 DESCRIPTION
Refer to the Project Specifications for a summary of the Work. The general intent of the
Contract, Specifications, plans, and all other Contract Documents and provisions thereo4f
is that the Contractor shall:
C. Perform, complete, and make ready for its intended purpose, within the times
specified, including additional times provided for certain conditions, the Work or
parts thereof covered by the Contract, all in accordance with plans, specifications,
and any addendum thereto and such direction or instructions as the Authority may
give to supplement the plans and specifications. The Contractor shall retain sole
responsibility and expense for Quality Control of their work products.
D. The Work of the Project requires that the Authority and all its Contractors maintain
an active working railroad signal and highway warning system in accordance with
Federal regulations and CPUC orders at all times. The Contractor, shall integrate,
coordinate, and stage the work in order to ensure that the active railroad signal
and highway warning systems are maintained.
E. Any construction staging plans or details are not meant to be contradictory to the
requirements set forth in the contract documents. It is the responsibility of the
Contractor to schedule and coordinate the construction activities at each site, using
the Site- Specific Work Plan (SSWP) process. Tracks may be taken out of service
for planned activities through the SSWP process. The Contractor shall incorporate
into its SSWP the necessary Authority provided signal maintenance support. No
red or other restrictive signals or signal-related train bulletins shall be allowed
outside of the approved work windows and as approved in the SSWP (see also
Section 01 14 00 “Work Restrictions”).
A. The intent of the Plans and Specifications is to prescribe the details for the
construction and completion of the Work that the Contractor undertakes to perform
in accordance with the terms of the Contract. Where the Plans or Specifications
describe portions of the Work in general terms, but not complete detail, it is
understood that only commonly accepted industry practice is to prevail. Unless
otherwise specified, the Contractor shall furnish all labor, materials, tools,
equipment, and incidentals, and perform all the Work involved in executing the
Contract in a satisfactory and workmanlike manner.
B. The Authority will determine whether the Work has been completed in accordance
with the Contract, Plans, Specifications and reference Specifications. The
Authority will decide all questions that may arise as to the quality or acceptability
of materials furnished and Work performed, and regarding the interpretation of the
Plans, Specifications, and reference Specifications.
D. Words and abbreviations that have well-known technical or trade meanings are
used in the Contract Documents in accordance with such recognized meanings.
E. The word "Furnish" or the word "Install" or the word "Perform" or the word "Provide"
or the word "Supply," or any combination or similar directive or usage thereof, shall
mean furnishing and incorporating in the Work including all necessary labor,
materials, equipment, and everything necessary to perform the Work indicated,
unless specifically limited in the context used.
G. The Specifications may vary in form, format and style. Some specification sections
are written in varying degrees of streamlined or declarative style and some sections
may be relatively narrative by comparison. Omissions of such words and phrases
as "the Contractor shall," "in conformity with," "as shown," or "as specified" are
intentional in streamlined sections. Omitted words and phrases shall be supplied
by inference. Similar types of provisions may appear in various parts of a section
or articles within a part depending on the format of the section. The Contractor shall
not take advantage of any variation of form, format or style in making claims for
extra Work.
J. The Authority shall not be responsible for and shall not have control or charge over
the acts or omissions of the Contractor, Subcontractors, or any of their agents or
employees, or any other persons performing any of the Work.
K. The word “Vendor” used in the Material Specifications shall mean the Contractor.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 11 13
SECTION 01 11 15
PART 1 - GENERAL
1.01 SUMMARY
This Section provides definition of terms, abbreviations and reference standards cited in the
Contract Documents. The following definitions supplement definitions provided throughout
the Contract Documents including General Conditions Section 2.
A. Wherever in the Specifications and other Contract Documents, the following terms
and abbreviations or pronouns in place of them, are used, the intent and meaning shall
be interpreted as provided in this section unless the context otherwise requires.
1. Active Track: Any track within the Operating System on which trains and/or on-
track equipment operate or may potentially operate. All tracks shall be
considered by the Contractor to be Active unless otherwise instructed by the
Authority.
4. Amtrak: The current Authority Contractor for the train and engineer service.
The National Railroad Passenger Corporation (Amtrak) also is the nationwide
intercity passenger service. Amtrak’s Surfliner trains operate over the River,
Ventura, and Orange Subdivisions.
6. Automatic Block Signals: A signaling system where the track is broken up into
segments called “blocks,” and the presence of a train on a given block will
activate signals preventing other trains from entering that block, except as
prescribed by the General Operating Rules.
7. Auxiliary Track: Any track not otherwise specified that directly connects to any
main track, siding or industrial lead where cars or locomotives are left standing
SCRRA Standard Specifications 01 11 15 - 1 ISSUED: February 2022
Section 01 11 15 Definition of Terms and Reference Standards
8. Bad Order: A defective rail car or any other rail equipment, track or structure,
which is in need of mechanical attention or repair.
9. Ballast: Material selected for placement on the roadbed for the purpose of
holding the track in line and at surface.
12. Clearance Point: the location closest to a switch where it is safe for equipment,
and a person riding the side of equipment unless prohibited, to pass equipment
on an adjacent track. Away from turnouts, the clearance point is designated as
13 feet center to center of two tracks.
13. Coach: A passenger carrying rail car, usually with a center aisle and two rows
of twin seats.
14. Common Carrier: One who holds himself out to the general public to transport
property and passengers, intrastate, interstate or in foreign commerce for
compensation. Common carriers must operate from one point to another over
routes or in territory prescribed by the Surface Transportation Board
(interstate) and by a Public Service or Public Utilities Commission.
15. Conductor (Train Operations): The individual in charge of the train crew.
16. Contaminated Soils: All material excavated from the project site that meets the
definition of contamination, regardless of material, gradation or other material
property classifications.
17. Continuous Welded Rail (CWR): Rail length that is 400 feet or longer. Rail
installed as CWR, remains CWR, regardless of whether a joint or plug is
installed into the rail at a later time.
18. Contract Documents: The complete set of documents, describing the specific
Work to be performed by the Contractor as part of the Contract.
19. Coupler: A device located at both ends of all cars and locomotives in a
standard location and configuration to provide a means for connecting one rail
vehicle to another.
21. Crossing Protection: Signs, signals, aspects, and other objects governing
movement of trains, track equipment, and highway vehicles over railroad
crossings or grade crossings.
22. Cross Level: The difference in elevation between the tops of both rails
measured along a line perpendicular to the track centerline.
23. Crossover: Two turnouts in which the track between the frogs is arranged to
form a continuous passage between two adjacent and generally parallel tracks.
24. Cross Tie: The transverse member of the track structure to which the rails are
spiked or otherwise fastened to provide proper gage and to cushion, distribute,
and transmit the stresses of traffic through the ballast to the roadbed.
25. Current of Traffic: The movement of trains on a main track, in one direction,
specified by the General Operating Rules.
26. Departure Track: One of the tracks in a rail yard on which outgoing cars are
placed.
27. Derail: A safety device attached to one rail of a siding or storage track, that will
cause derailment of a car, engine or on track machinery, in order to prevent
unintended and undesired movement to other tracks.
28. Derailment: Anytime the wheels of a rail car engine or on track machinery
come off the head of the rail.
29. Dispatcher: Person stationed in the Operations Control Center who monitors
and directs movement of trains.
30. Dynamic Stabilizer: The dynamic stabilizer is a machine that sets the track in
horizontal oscillation while applying a static vertical load at the same time.
Dynamic track stabilization is to achieve improved anchoring of the track in the
ballast bed. After dynamic stabilization, the condition of the track offers greater
operating safety and enables travel at the maximum subdivision speed on
newly laid track or after full track maintenance.
31. Emergency: Any sudden generally unforeseen occurrence such as a fire, flood,
storm, earthquake, epidemic, civil disorder or other natural and/or man-made
disaster that has the potential to adversely affect the safety of life, the Work,
and/or adjacent property; to interrupt contracts essential to the provision of
railroad passenger and/or freight service; and/or to cause catastrophic failure
of revenue-producing equipment and/or facilities.
36. Excavation (Cut): the material removed to expose the ground surface upon
which the roadbed, embankment fills, or other proposed improvements, will be
placed.
38. Field Side: The side of rail opposite the gage side or on the outside of the
running surface of any rail.
39. Field Weld: A weld joining two rails together after rails are installed in track.
41. Guard Rail: A rail or other structure laid parallel with the running rails of a track
to prevent wheels from being derailed; or to hold wheels in correct alignment
to prevent their flanges from striking the points of turnout or diamond crossing
or the points of switches. A rail or other structure laid parallel with the running
rails of a track to keep derailed wheels adjacent to running rails.
42. Insulated Switch: A switch in which the fixtures, principally the gage plates and
the switch rods, connecting or reaching from one rail to the opposite rail, are
provided with insulation so that the electric track circuit will not be shunted.
44. Job Briefing: A meeting among all of the employees who are involved or will
be involved in a particular task or a job at the same work site. The briefing must
be conducted before conducting any task and/or any employee fouls the track.
45. Ladder Track: A track connecting successively the body tracks of a yard.
51. Main Track: A term referring to the primary or most heavily used tracks of a
railroad. A track extending through yards and between stations, upon which
the operation of trains is controlled and authorized by the Train Dispatcher.
Note that sidings on Authority property are operated under the same rules as
the Main Track(s).
52. Milepost: Designated location(s) along the main and branch lines normally
sequentially one mile apart and indicated by nearby numbered sign
corresponding to the “mile” location.
53. Operating Envelope: An imaginary line, measured 20 feet horizontally from the
rail on the track on which trains or “on-track” equipment operate or may
potentially operate. The Operating Envelope also includes the width and length
of any active station platform. This imaginary pair of lines, which define the
outside boundaries of the Operating Envelope, extend vertically up and down
infinitely.
54. Operating System: Includes but is not limited to the tracks on which trains and
on-track equipment operate or may potentially operate, and in addition any
facilities closely related to the operation of the railroad system including signal
and communication masts, bridges, poles, cables, and houses, track bridges,
tunnels, culverts, grade crossings and station platforms.”
56. Passing Track: A track connected to the main track for meeting or passing
trains. Today this is called a siding.
57. Preferred Rail Laying Temperature: The temperature that the rail is to be
installed at, or adjusted to, in order to balance the thermal expansion and
contraction forces for optimum track maintenance practices. The Preferred Rail
Laying Temperature (PRLT) is defined in the SCRRA Track Maintenance
Manual.
59. Quality Assurance (QA): The process by which the Authority elects to monitor
and assure that it receives proper construction related documentation from the
Contractor. QA procedures measure the setting of schedules for the receipt
and review of documentation and the quality of the information contained within
the documentation.
60. Quality Control (QC): The process by which the Authority receives
documentation from the Contractor that proves that the Contractor is providing
the contractually mandated services, such as training, testing and inspection.
The Contractor must show evidence of internal procedures demonstrating how
he will perform these mandated functions and submit documentation that QC
verifications have been completed. QC is the responsibility of the Contractor.
61. Rail: In track, a rolled steel shape, commonly a T-section, designed to be laid
end to end in two parallel lines on crossties or other suitable supports to form
a track for railway rolling stock.
62. Rail Anchor: A device attached to the base of a rail bearing against a crosstie
to prevent the rail from moving longitudinally under traffic.
63. Rail Joint: A fastening designed to unite the abutting ends of contiguous rails.
Often referred to as angle bars or joint bars. When rails of different sections
are joined, a compromise rail joint is used.
65. Rail Section: Designates and describes a specific size and shape of steel cast
and rolled into railroad rail. The rail mills identify the different shapes and types
of rails by code numbers, which typically indicate the nominal weight,
measured in pounds per yard (3 lineal feet of rail). As example: 136-pound RE
section.
66. Relay Rails: Rails taken up from tracks where formerly used, suitable for
relaying in other tracks.
67. Railroad Tie: The transverse member of the track structure to which the rails
are spiked or otherwise fastened to provide proper gage and to cushion,
distribute, and transmit the stresses of traffic through the ballast to the
roadbed. Also referred herein as a crosstie.
68. Relocate: Change the location, position or station of an item through removal
from existing location and reinstallation of existing equipment to new location.
Relocation may involve installation of new connections or accessories.
69. Restricted Speed: A speed that allows stopping within half the range of vision
short of: Trains, Engine, Railroad Car, Maintenance of Way Equipment, stop
signal, or derail or switch not properly lined.
70. Reverse Curve: Adjoining or nearby curves on a track that turn in opposite
directions.
71. Right-of-Way: The real property, inclusive of all estates and interests therein,
that is necessary for ownership and operation of the Project. Right-Of-Way, as
the term is used in the Contract, specifically excludes:
72. Roadbed: The foundation upon which the ballast, ties and rails of a railroad
are laid.
73. Roadway Maintenance Machine: Any device which is powered by any means
of energy other than hand power which is being used on or near railroad track
for maintenance, repair, construction or inspection of track, bridges, roadway,
signal, communications or electric traction systems. Roadway maintenance
machines may have road or rail wheels or may be stationary.
74. Roadway Worker: Any employee of Authority or the Contractor to the Authority,
whose duties include inspection, construction, maintenance l or repair of
railroad track, bridges, roadway, signal and communications4 systems,
roadway facilities or roadway machinery within the Authority right of way.
76. Roadway Worker On-Track Safety Manual (or Instructions): When used in
these specifications, SCRRA On-Track Safety Manual for Roadway Workers
(OTSM) and Roadway Worker Protection (RWP) Safety Manual will replace all
locations where SCRRA Roadway Worker On-Track Safety Manual (or
Instructions) is stated. If a particular section of the old Roadway Worker On-
Track Safety Manual (or Instructions) was called out, Contractor shall review
the new OTSM & RWP manuals for the updated section reference.
77. Salvage: To save any removed item. The salvaged item shall be reused in the
contract or delivered and stockpiled for the Authority as specified in the
Contract Documents.
79. Site Specific Work Plan (SSWP): A program, plan, and schedule prepared and
submitted by the Contractor and approved by the Authority that accurately
describes and illustrates the manner in which Work within the Operating
Envelope will be accomplished, the impacts on any elements of the Operating
System and the manner in which Work will be accomplished with the Authority
allotted Work Windows.
81. Siding: A track auxiliary to the main track for meeting or passing trains. See
“Passing Track”.
82. Special Trackwork: Any trackwork consisting of more than two rails and ties.
Examples are turnouts, switches and diamond crossings.
84. Spur Track: As distinguished from a Side Track, a Spur Track is of indefinite
length, extending out from the main line.
85. Standard Gage: The standard distance between rails of most North American
railroads, being 4’ 8-1/2“ measured between the inside gauge faces of the rail
heads, 5/8 inch down from the running surface.
86. Storage Track: A track on which cars are placed when awaiting disposition or
when not in service.
87. Stub Track: A form of sidetrack connected to a running track at one end only
and usually protected at the end by some form of bumping post or other solid
obstruction.
88. Subballast: Any material spread on the finished subgrade of the roadbed below
the ballast to provide better drainage, prevent upheaval by frost, and better
distribute the load over the roadbed.
89. Subgrade: The finished surface of the roadbed below the ballast and track.
90. Subgrade Preparation: Preparing the earth surface upon which the subballast
and roadbed or other proposed improvements will be placed.
92. Superelevation: The intentional difference in elevation between the top of the
outer rail and the top of the inner rail measured along a line perpendicular to
the track centerline.
93. Switch: A track structure with movable rails to divert rolling stock from one
track to another.
94. Switch Angle: The angle included between the gauge lines of the switch rail at
its point and the stock rail.
95. Switching: Switching service consists of moving cars from one track to another
track or to different positions on the same track. It includes the moving of cars
in the make-up and break-up of trains; also moving of cars on industrial
switching tracks or interchange tracks, and the general movement of cars
within terminals or at junctions.
97. Tangent: Any straight portion of a railway alignment. Tangent track means a
section of track that connects two curves.
98. Ticket Vending Device (TVD): a vending machine that produces paper or
electronic tickets or recharges a stored-value card or smart card or the user’s
mobile wallet. Also referred to as a Ticket Vending Machine (TVM).
100. Track: An assembly of rails, ties, rail fastenings, hardware and roadbed over
which cars, locomotives and trains are moved and the space between the rails
and space of not less than four feet outside of each rail.
101. Track Maintenance Manual: When used in these specifications, SCRRA Track
Maintenance Manual (TMM) will replace all locations where SCRRA Track
Maintenance and Engineering Instructions is stated. If a particular section of
the old TMEI was called out, Contractor shall review the new Track
Maintenance Manual for the updated section reference.
103. Truck: The complete assembly of parts, including wheels, axles, bearings, side
frames, bolster, brake, rigging, springs and all associated connecting
components, the function of which is to provide support, mobility and guidance
to the railroad car.
104. Train: An engine or more than one engine coupled, with or without cars
displaying markers. For practical purposes, a train is a group of coupled cars
hauled by a locomotive.
105. Turnout: An arrangement of a switch and a frog with closure rails by means of
which rolling stock may be diverted from one track to another. Also referred to
as “track switch.”
106. Walkway: A portion of the railroad embankment or ballast section shaped4 and
finished to conform to SCRRA ES2001, ES2002, and CPUC requirements for
train employee walking surfaces.
107. Watchman: An Authority or employee contracted with the Authority who has
been annually trained and Qualified to provide warning to Roadway Workers
of approaching trains or on-track equipment.
108. Wheel: The cast or forged steel cylindrical element that rolls on the rail carries
the weight and provides guidance for rail vehicles. Railway wheels are semi-
permanently mounted in pairs on steel axles and are designed with flanges
and a tapered tread to provide for operation on track of a specific gage. The
wheel also serves as a brake drum on cars with on-tread brakes.
109. Wheel Set: The term used to describe a pair of wheels mounted on an axle.
110. Work: The Work, as stated in this document shall be taken to mean the total
effort put forth by the Contractor to construct the improvements shown on the
Contract Documents.
111. Work Window: A period of time with specific beginning and ending time and
durations for which the track, signals, bridges and other Operating System
elements within the Operating Envelope are temporarily removed4 from
service or modified in some other manner and train and other operations
suspended or modified to allow construction or maintenance work to occur.
Written Authority from the Authority and an approved Site Specific Work Plan
(SSWP) is required before the Contractor is granted a Work Window. The
Contractor’s Work Window shall have specific geographic limits, which are
defined in the approved SSWP. Modifications or suspension of train and on-
track equipment movements resulting from a Work Window involves written
changes to the Railroad’s Rules of Train and On-Track Equipment Operations.
These written changes are known as Track Bulletins and are categorized as
follows:
a. Limited Track Window: An approved Work Window for some, but not
all tracks within a general Work area (e.g. one track remains for
operation of trains, other tracks are available for the Contractor’s
Work). Movement of trains over the track(s) of a Limited Track Window
is under the control of the RWIC who will not authorize train movement
unless and until the Contractor personnel and equipment are clear of
the operating track. The Contractor may remove, construct, or obstruct
only the track designated by the SSWP and must arrange the Work so
that trains can operate without delay on the remaining track(s) in the
Work area. This Work may be protected by track out of service, track
and time, or by Form B Track Bulletin.
113. Work Train: A train engaged in services for the Authority for which no revenue
is received, such as trains distributing ballast, bridge material or other material
and supplies for maintenance or for additions and improvements.
114. Yard: A system of tracks within defined limits provided for the making up of
trains, storing of cars and other similar purposes.
115. Yard Lead: An extended track connecting either end of a yard with the main
track.
117. Yard Office: A building in terminal yards to provide office accommodations for
the yardmaster and office personnel.
1.03 ABBREVIATIONS
A. Association Abbreviations:
AA Aluminum Association
AABC Associated Air Balance Council
AIEE American Institute of Electrical and Electronics Engineers
AAMA American Architectural Manufacturers Association
AAN American Association of Nurserymen
AAR Association of American Railroads
AASHTO American Association of State Highway and Transportation
Officials
ACI American Concrete Institute
C. Text Abbreviations:
AL Allowance
AMP or amp Ampere
AWG American Wire Gage
CDF Controlled Density Fill
CF Cubic foot or feet
CFM or cfm Cubic feet per minute
CY Cubic Yard
EA Each
FPM or fpm Feet per minute
FPS or fps Feet per second
Ft. or ' Feet
GPM or gpm Gallons per minute
in. or " Inches
Kip or kip thousand pounds force
Ksi or ksi thousand pounds per square inch
Ksf or ksf thousand pounds per square foot
KV or kV Kilovolt
KVA or kva Kilovolt amperes
SCRRA Standard Specifications 01 11 15 - 14 ISSUED: February 2022
Section 01 11 15 Definition of Terms and Reference Standards
KW or kW Kilowatt
KWH or kwh Kilowatt hour
LBS Pounds
LF or lf linear foot or feet
LS Lump Sum
MPH or mph Miles per hour
PCF or pcf Pounds per cubic foot
PSF or psf Pounds per square foot
PSI or psi Pounds per square inch
SF or sf Square foot or feet
SY or sy Square yard
TF Track Feet
TON Ton
C. The Contractor shall maintain the latest copy of applicable sections of standards at
jobsite during submittals, planning, and progress of specific Work, until substantial
completion, and shall make the standards available for Engineer's use upon request.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 11 15
WORK BY SCRRA
PART 1 - GENERAL
1.01 SUMMARY
This section describes the Authority furnished labor necessary to support the Contractor’s
construction operations. It is the Contractor’s responsibility to furnish any and all other
labor, materials, and equipment required to complete the work set forth in the Contract
Documents, specifically excepting those Authority furnished resources described below
and in the Specifications. Authority furnished materials and equipment is shown in Section
01 64 00, SCRRA Furnished Material & Equipment.
A. FRA: Federal Railroad Administration, 49 CFR Part 213, Track Safety Standards,
and 49 CFR Part 214, Railroad Workplace Safety
A. Authority will provide an Roadway Worker in Charge (RWIC), and 49 CFR Part
213.7 qualified personnel to monitor the interface between the Contractor’s work
and train movements and facilitate temporary rearrangements or tracks out of
service. The Contractor shall include requests for Authority furnished labor in his
Site Specific Work Plan (SSWP), which shall be prepared and submitted in
accordance with Section 01 14 00 which identifies “Work Restrictions,” the
Contractor’s Responsibilities and Key Definitions for “Operating Envelope,”
“Operating System,” and “Work Windows” to determine the conditions for which
Authority furnished labor is utilized. The allocation of the number of Authority
furnished RWIC's is subject to the following:
b. The maximum shift duration for one RWIC is 10.5 hours. Under
“Form B” protection, the 10.5 hours includes 8 hours of the
Contractor work (excluding train interruptions) and 2.5 hours to
install and remove Form B flags and provide daily job briefings. The
Contractor shall not be allowed to work within the Operating
Envelope during the 2.5-hour flag installation and removal. The
minimum shift duration for flagging services is 4 hours. If the
Contractor desires to perform activities requiring an RWIC that are
longer than 8 hours’ duration, then the Contractor shall coordinate
with the Authority to schedule multiple RWIC’s for said Work.
c. The Contractor shall schedule and establish its work limits within
the range of vision of the assigned RWIC. If the Contractor’s
requested work limits are outside the normal range of vision of the
RWIC due to curves, topography, or distance, multiple Subgroup
Coordinators will be needed. One Subgroup Coordinator is needed
for every 10 roadway workers. The Contractor shall include in the
SSWP how many RWIC and Subgroup Coordinators are needed.
PART 3 - EXECUTION
4.01 MEASUREMENT
A. Authority provided RWIC will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
Unless provided for otherwise in the Specifications, the Authority shall provide the Contractor
the services of RWIC(s) for up to 10.5 hours per day, 5 days per week, at no cost to the
Contractor as noted below.
A. The Authority has determined the RWIC services based on its own calculations
and schedule. Authority will provide a maximum of [TBD] days’ worth of RWIC. An
RWIC day is considered to be one 10.5 hour day, Monday through Friday during
the day for up to 10 roadway workers. Work that is additional hours above this, at
night, on weekends, or with more than 10 roadway workers will count as additional
RWIC’s accordingly. The Contractor shall prepare the SSWP based on this
information and Authority and Contractor shall agree to the SSWP, including the
RWIC shift times and number of RWIC’s needed. If the Contractor requires
additional RWIC services, the Contractor shall pay for these flagging services. In
such a case, the Contractor shall pay for the actual costs of flagging services, as
shown in the rate sheet in the link below. RWIC rates are subject to change at any
time and may be found on the Metrolink website at:
https://metrolinktrains.com/globalassets/about/engineering/scrra_schedule_of_fe
es_for_third_party_construction.pdf
B. If the Contractor cancels scheduled RWIC work and does not make arrangements
with the RWIC 48 hours in advance for cancellation, the Contractor shall reimburse
SCRRA for the cost of the RWIC. If the Contractor sets up a Form B or other type
of protection required to be in the next day’s SCRRA Railroad Bulletin, and the
Contractor does not work or cancels the RWIC for reasons other than Force
Majeure, the Contractor shall reimburse SCRRA for the cost of the RWIC.
C. SCRRA railway flagging cannot be scheduled until the Temporary Right of Entry
Permit has been issued and the SSWP has been agreed upon by SCRRA. SCRRA
recommends scheduling SCRRA railway flagging a minimum of 15 working days
in advance of work. Work that impacts the SCRRA right of way will not be allowed
to be done without SCRRA railway flagging.
The items E-H below are in connection with the below fee schedule posted on
SCRRA’s website:
https://metrolinktrains.com/globalassets/about/engineering/scrra_schedule_of_fe
es_for_third_party_construction.pdf
D. SCRRA fees associated with obtaining Roadway Worker Protection (RWP) Safety
training class will be paid by [the Project Sponsor] for up to [TBD] classes
maximum.
E. SCRRA fees associated with Signal and Communications line location markouts
will be paid by [the Project Sponsor].
G. Related costs for compliance with all other SCRRA requirements, including but not
limited to additional insurance, labor hours related to preparing/obtaining permits,
attending training, re-submitting documents if required, delays in obtaining the
right-of-entry, shall be considered as included in the prices in the Bid for the various
items of work and no additional compensation will be allowed.
END OF SECTION 01 11 16
WORK RESTRICTIONS
PART 1 - GENERAL
1.01 SUMMARY
This Section outlines requirements and provisions for rules and hours of operation for the
Contractor execution of the Work under this Contract.
Comply with the provisions of all local, State, and Federal codes, specifications,
standards, industry recommended practices and Authority policy including:
B. FRA: Federal Railroad Administration Track Safety Standards, 49 CFR Part 214
C. SCRRA: Track Maintenance Manual and On-Track Safety Manual for Roadway
Workers
Some key definitions that pertain to this Section are listed below. Refer to Section 01 11
15 and the Contract General Conditions for more key definitions.
D. Site-Specific Work Plan (SSWP) – See Section 01 11 15. 1.02 Definition of Terms.
1.05 SUBMITTALS
Provide submittals such as the Site Specific Work Plan (SSWP) in accordance with
Section 01 33 00, Submittal Procedures.
A. Cooperate with the Authority in all matters requiring coordination for execution of
the Work including eliminating or minimizing to the greatest extent possible
interference and delays to all scheduled passenger and freight trains movements.
Information regarding train movements is available to the Contractor, upon
request. A sample activity report of train movements for one week may be obtained
from the Authority.
B. The Contractor shall keep the Authority fully informed regarding any night or
weekend Work.
C. The Authority may require the Contractor to finish a section on which Work is in
progress before Work is started on any additional section.
D. Authority will be conducting work on other contracts at the same time as the
Contractor’s Work. The Contractor shall coordinate with other contractors and use
the same Form B used by other contractors.
A. The Contractor shall perform Work in accordance with the Contract and all
applicable codes, ordinances, rules, regulations, orders, and other legal
requirements of governmental bodies and public agencies having jurisdiction,
including the Authority.
B. Any damage caused by the Contractor to rails, ties, structures, embankment, third-
party property, signal and communications equipment, or any other facilities shall
be repaired at the Contractor's expense to a condition equal to or better than the
condition prior to the Contractor entry, and as accepted by the Authority. At the
sole discretion of the Authority, the Authority may direct that repairs be performed
by other Contractors. The charges for such repairs shall be deducted from the
Contractor’s payment due under this Contract.
D. The Contractor shall not perform any work on or adjacent to the Main Track without
prior written approval of the Authority. Perform work within the Operating Envelope
or which affects the Operating System only after submitting a Site-Specific
Work Plan (SSWP) and receiving written approval of the SSWP from the Authority.
E. Furnish all labor, materials, equipment and other incidentals as required to perform
and complete the Work within the Work Windows, in accordance with the approved
schedule in the SSWP.
A. The Contractor shall coordinate access, use, and preparation of facilities adjacent
to the Project areas with owners and agencies. Coordination shall include but not
be limited to the following:
3. Fences, walls, signs, and gates affected by the Contractor’s access to the
Right of Way shall be restored to full serviceability prior to demobilization.
C. Work on Private Property Other Than Railroad: Any additional easement areas
requested by the Contractor shall be obtained by separate contract between the
Contractor and the property owner and shall be solely at the Contractor's own risk
and expense. The Authority will not be a party to nor assume any liability for those
separate contracts. The Contractor shall transmit copies to the Authority of all
executed property agreements, easements and contracts with third parties within
3 working days of the execution. The Contractor shall coordinate scheduling of
Work to be performed on private property with property owner and property tenant
so as to minimize inconvenience to the property owner and property tenant.
Contractor can secure additional areas with respective owners at Contractor’s own
expense and responsibility. The Contractor shall make arrangements, pay for, and
assume all responsibility for acquiring, using, and disposing of Work areas and
facilities temporarily acquired by the Contractor in addition to those provided by
the Authority. The Contractor shall indemnify and hold the Authority harmless for
all claims for damages caused by such actions.
F. The Contractor shall consider the safety of the Work, train operations personnel,
and property on and adjacent to the Worksite when determining amount, location,
movement, and use of materials and equipment on Worksite. The Contractor shall
not load Worksite with excessive amounts of material, equipment, or other items
that have the potential to interfere with the Work or with train operations. The
Contractor shall relocate stored products, equipment, and materials that interfere
with train operations, public and private utilities, or visibility at railroad crossings.
Materials and equipment shall not be so piled, stored, or parked when not in use.
G. The Contractor shall adhere to the noise levels and hours of Local Ordinances,
except as provided and approved in the Site-Specific Work Plan (SSWP).
H. The Contractor shall be responsible for coordinating its Work with all property
owners affected by the Contractor’s operations. The Contractor shall protect the
general public and residents within Worksite boundaries from Work-related
activities, and shall not unnecessarily inconvenience those persons by Work
activities.
I. The Contractor shall submit the proposed location of staging areas for the
Authority’s approval.
J. As necessary, the Contractor will preserve and relocate railroad signs (mileposts,
speed limits, “no trespassing” signs, station signs, crossing whistle signs, etc.)
during the full period of construction. Signs shall be maintained during construction
or restored upon completion of the Work, in accordance with the requirements of
Section 01 35 23, SCRRA Site Safety Requirements. The Contractor shall protect
at-grade crossing warning signs and shall coordinate the schedule for relocation
or revision of Crossing warning signs and signals by Others, if necessary.
K. The Contractor will preserve drainage facilities throughout the duration of the Work
so that there is no pending or accumulation of water in any Worksite area, there is
no flow of water diverted toward the track or out of normal drainage channels, and
all culvert inlets and outlets are kept free of debris.
L. Except where specifically designated in the design of the Work, the Contractor will
preserve the ability of maintenance Contractors to access the Right of Way using
highway vehicles. If the original right-of-way roads become blocked with the
Contractor’s materials, equipment, or excavations or spoils, alternate routes must
be arranged.
M. The Contractor will preserve existing right-of-way fences and walls, and will
replace any such fences or walls damaged during the work to the satisfaction of
the owner(s) of the fences or walls.
A. The time limits for all types of Work Windows include the time for the Contractor to
restore and test the signal and communication system before the operation of
trains; therefore, the full duration of the Work Window is not available for the use
of the Contractor. The SSWP shall designate both the time at which the Contractor
must make the track ready (in full compliance with the FRA Track Safety Standards
and with the Authority’s Track Maintenance Manual) for the passage of trains, and
the remaining time within the Work Window that will be required for the signal and
communications system restoration. The SSWP shall be prepared and submitted
in accordance with the Work Window requirements shown in the Project Specific
Specifications.
C. The Contractor does not have exclusive rights to the Work Windows. The
Contractor may have to share these Work Windows with other Contractors and the
Authority’s maintenance forces as described in the General Conditions.
D. The Contractor shall not perform any fieldwork during three annual designated
holidays. Fieldwork shall not include receipt or delivery of materials or equipment
or work performed in field offices. The designated holidays are Labor Day,
Thanksgiving Day and Christmas Day.
E. Contractor shall not work on state holidays, federal holidays, nights, or weekends
without prior approval of the Engineer.
During these periods, the Authority will not have the resources (labor and equipment) or
construction management personnel to issue track bulletins or to support, inspect, or
oversee the Contractor’s Work.
A. All work with the potential to impede the normal functioning of any part of the
Operating System shall include a detailed SSWP’s showing schedule of events,
indicating the expected hourly progress of each activity that has duration of one
hour or longer. The schedule shall include a time at which each activity planned
under the SSWP and the requested Work Window will be completed, and the total
duration of all the construction activities shall be less than the approved Work
Window. Failure of the Contractor to complete the scheduled activities by the
planned time or to put in place an approved contingency plan may adversely affect
the operations of scheduled trains.
B. The Contractor shall refer to SCRRA’s Site Specific Work Plan Scope of SSWP
prior to submitting SSWP. The Contractor shall submit SCRRA’s SSWP Checklist.
4. A schedule of the work, showing each activity and where and how it affects
normal operation of the Operating System. This schedule shall integrate
and allow for the necessary work of the Signal and Communication forces.
Each activity in the plan shall include all labor, materials, and equipment
required to complete the activity within the Authority allotted time period.
The Contractor shall identify on the schedule all Authority furnished labor,
equipment and materials.
6. List all of the approved proposed work plans to be performed under the
SSWP and provide the name(s) and number(s) of the Contractor’s
supervisor(s) in charge of the SSWP tasks.
D. The SSWPs must be of sufficient detail, clarity, and organization to permit easy
review and approval by the Authority before the proposed work is performed.
1. At least 14 calendar days prior to start of the work within the Operating
Envelope for work other than signal or third-party activity.
2. At least 30 calendar days prior to the start of work for work involving signal
or third-party installation.
E. The Authority may request explanations and changes to the SSWP to conform the
SSWP to the requirements of the Contract Documents. If the SSWP is not
acceptable, the Contractor shall revise the SSWP to make it acceptable. The
Contractor is responsible for submitting a revised SSWP that can be reviewed and
approved by the Authority at least seven days in advance of any work that affects
the Operating System.
F. The Contractor will be informed if the SSWP is acceptable not less than seven
calendar days prior to the scheduled start of work within the Operating Envelope.
Once the plan is accepted, the Contractor shall assemble the resources necessary
to perform the work represented by the SSWP, so that necessary resources are
available one calendar day before the work is to be accomplished, thereby
demonstrating to the Authority the readiness of the Contractor to perform the Work.
At this time, the Authority will make a final decision as to whether or not the Work
is to proceed as planned or be canceled.
A. The Contractor’s construction activities that affect the Operating System including
tracks, grade crossings, bridges, stations, public highways, and related facilities in
active service shall be subject to the following requirements:
2. The Contractor shall perform the Work expeditiously and continuously, with
no gaps or breaks in the work activities or substantive reductions in the
labor force, equipment, and materials necessary to construct, reconstruct,
or repair the affected facility to full service upon the conclusion of the
approved “Work Window.”
3. The size and scope of the affected facilities within the Operating System,
(e.g., tracks, bridges) removed shall not exceed the Contractor’s capacity
to conservatively return the facility to the required level of service within the
approved “Work Window.”
6. When not in use, materials and equipment shall not be piled, stored, or
parked, closer than 20 feet horizontally from the centerline of the nearest
operating track, or within 250 feet of an open public grade crossing.
4. The Contractor shall use a dynamic track stabilizer on all tracks that have
been significantly disturbed (i.e., ties or ballast removed).
A. At the end of each Work Window shown in the approved SSWP, the Contractor
shall return all tracks to Class 5 as defined by FRA guidelines. If the track does not
meet Class 5 specifications, a slow order (Form A) will be issued. It is the intent of
the Contract Documents that Main Line Slow Orders only be allowed on a very
limited basis. See Section 01 35 15, Maintenance and Protection of Railroad
Traffic, or the Specifications for the number of allowed speed restrictions.
B. The time of train delays caused by the Contractor’s operation will be calculated as
in Section 01 35 15, Maintenance and Protection of Railroad Traffic. The
Contractor shall include all slow order (Form A) requests in his proposed SSWP.
All slow orders shall be subject to the approval of the Authority.
C. The Authority will require final inspection before train service can resume on tracks
previously taken out of service.
D. Allowing train service on reconstructed or shifted track at the end of each approved
Work Window is not considered beneficial occupancy or final acceptance. The
Contractor shall remain fully responsible for any loss or damage arising from the
Contractor’s activities under this Contract.
2. The Contractor exceeds the total allowable Slow Order Delay Time
described in Section 01 35 15, Maintenance and Protection of Railroad
Traffic.
A. The Contractor shall have qualified personnel at each distinct work site to ensure
that all tracks are constructed to the required specifications. The Contractor shall
perform a track inspection and determine its classification and conformance with
the approved SSWP.
B. The Authority shall furnish staff for the final inspection required in order to place
track and bridge facilities in service for the Authority’s use at the end of the Work
Window.
C. The Contractor shall schedule his operations to allow for the necessary inspection
and any remedial work required in order to place the tracks and signal system back
in service at the prescribed time.
D. If the track does not meet Class 5 standards due to track or bridge construction
irregularities (e.g. gage, distressing, cross level, surface, profile, alignment,
improper CWR temperature, loose fasteners, missing components), the track will
be slow ordered to the next lower class with which it complies (according to the
FRA guidelines).
E. The Authority reserves the right to have its Maintenance Contractor perform
remedial work to return the track to Class 5. In addition to the assessment cost
noted in the paragraphs above, the costs to perform the remedial work will be
deducted from the Contractor’s progress payment.
F. No additional time will be allowed for completion of the work in the event that the
Authority is required to perform the remedial work to return the track to Class 5.
The Contractor may be required to interface with other contractors, utility companies,
public agencies, private companies, and railroad forces. This interface shall be provided
in accordance with the General Conditions and Section 01 14 16, Coordination with
SCRRA. In addition, routine or emergency maintenance of existing Authority facilities may
occur during the progress of the Work. Such activities shall have priority and the Authority
shall make efforts to minimize interference where possible.
B. The Authority RWIC will conduct job briefings as required under the Roadway
Worker Policy Manual at the following intervals:
C. The Contractor shall immediately execute all verbal and written directives of the
Authority or the Authority RWIC.
D. Refer to Section 01 14 16, Coordination with SCRRA, for rules governing Work
adjacent to active tracks.
F. Refer to Section 01 35 23, Site Safety Requirements, and the SCRRA Roadway
Worker Protection Regulations, incorporated as Section 214.3 of the SCRRA On-
Track Safety Instructions, for any clarifications or additional requirements.
A. Refer to Project Specific Specifications for allowable Work Windows with the
Operating System.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 14 00
PART 1 - GENERAL
1.01 SUMMARY
This Section outlines the requirements for coordination with the Authority and related
railroads for Work performed on the railroad right-of-way.
A. Upon award of this Contract Work, the most current edition of each of the following
publications shall apply to the Contractor’s work. The Contractor shall comply with
all requirements from the Railroad Operators, CPUC, FRA and all other governing
entities. These requirements may include the following:
B. In addition, the Contractor shall comply with the most current edition of the AREMA
Manual for Railway Engineering for standards of construction not fully explained by
the above regulations or these Specifications. Possible conflicts between
publications identified in this Section shall be brought to the attention of the Authority,
who will make a determination as to the direction that the Contractor should follow.
1.04 COORDINATION
A. All Work within or adjacent to the Authority’s Right-of-Way shall, at a minimum, meet
the above regulations and be coordinated through the Authority. The Contractor shall
cooperate and coordinate the Work as necessary in the most efficient manner for the
execution and completion of the Work. If there is a conflict between SCRRA and
other railroad’s Rules and Regulations, the Contractor shall follow the Authority’s
direction as to which set of rules shall prevail. The Contractor shall coordinate its
work, so it does not interfere or otherwise delay the work performed by SCRRA’s
forces.
B. Track will be used both for passenger and freight operations. The Authority
dispatches all train traffic. The Contractor's Work shall be scheduled to provide
minimal interference with all train traffic; in particular, Work will not be permitted to
delay any trains. Requirements for slow orders through Work zones are contained
elsewhere in these Specifications.
C. The Contractor activities shall not delay any trains except as approved in advance
by the Authority.
D. The Contractor should participate in the jobsite visit prior to submittal of bids to
assess the level of train activity. Some schedule variations should be anticipated
during the Project due to normal growth and train schedule refinement by the
Authority and other operators.
E. Authority RWIC will obtain track Authority directly from the Authority dispatcher. The
Contractor shall not coordinate with the Authority dispatcher.
G. The Contractor's work shall be coordinated with the Authority in accordance with
Section 01 14 00, Work Restrictions, which establishes procedures and lead times
required for Authority provided labor, including RWIC.
H. The Contractor must make arrangements to remove all on-track equipment from the
Main Track in order to pass trains as specified in Section 01 14 00, Work Restrictions.
The Contractor may not assume that its equipment can be placed or stored in spur
tracks or sidings unless approved in advance by the Authority.
A. The Contractor shall obtain permission in writing from the Authority for movement of
equipment on track or across tracks at locations other than public crossings. Such
permission may not necessarily be granted. If it is granted, the Contractor shall
comply with any condition required such as, but not limited to, the bridging of rail and
protection of ballast section. Damages to the track structure will be repaired at the
Contractor’s sole expense.
B. The mainline tracks, within the limits of Work, are under direct control of the Authority
Dispatcher. No track shall be fouled without authorization and presence of an
Authority RWIC on the scene.
1. For all Work with the potential to foul the track, the Contractor shall allow
sufficient time in his work schedule for the RWIC to clear trains. Up to 15
minutes may be required for the RWIC to clear each train, during which time
the Contractor must not foul the track. Such time required to clear scheduled
trains shall not be an acceptable reason for submitting contract change
requests or delay claims to SCRRA.
2. Scheduled trains may run behind schedule, and such tardiness will not be an
acceptable reason for submitting Contract change requests or delay claims
to SCRRA.
A. Track within the Work limits will be in use for high-speed freight and passenger train
operations throughout the construction period. Train movements are governed by
signal systems and the Contractor shall take no action which would:
2. Cause delay to any train (e.g., display of a signal aspect less permissive than
track conditions allow, obstruction of right-of-way).
B. Existing overhead and buried communications and signaling cables and track wires
are located at various locations along and across the Right-of-Way. The Contractor
shall take all steps necessary to protect active cabling from damage during the Work.
Specific utilities associated with the Work of this Contract are detailed in the Plans
and Specifications. The minimum precautions to be taken by the Contractor to
protect communications and signaling cables are as follows:
2. At least 14 days before performing any excavation Work, the Contractor shall
contact the Authority to schedule a signal department mark-out. The
Contractor shall call the SCRRA's "Call Before You Dig" number prior to
commencing work at (909) 592-1346 during normal business hours. In case
of emergencies involving SCRRA signal or communication facilities, the
Contractor shall call (888) 446-9721. The exact location of communications
and signaling cables shall be determined by a careful examination of site and
hand potholing. The Contractor may utilize a search coil to determine the
general vicinity of buried cabling. All such aforementioned locating activities
shall be performed in the presence of the Authority.
4. SCRRA will, if required, rearrange its communications and signal lines, grade
crossing warning devices, train signals, tracks and facilities that are in use
and maintained by SCRRA forces in connection with its operation. This work
by the SCRRA will be done by its own forces or by contractors under a
continuing contract and is not a part of the work under the Contract for the
construction of the Project. The Contractor must allow sufficient time in its
schedule to permit SCRRA to issue the necessary task orders to its
contractors order material, and perform any necessary work.
C. All communications and signaling cables proximate to the Work shall be physically
located by means of potholing with hand tools. Excavation by hand tools shall be
done by skimming soil in small increments, rather than by digging straight down with
the point of a shovel.All such locating activities shall be performed in the presence
of the Authority. Excavation by machinery will be allowed only where the preceding
precautions have been taken, as approved by the Authority, to ensure that existing
cabling is not at risk of being damaged.
D. Where the placement of existing cabling interferes with placement of track work, or
where cabling is at risk of damage from track work, the Contractor shall request such
cabling be relocated or protected by Authority forces.
E. The relocation of cables may require delays of up to 72 hours after the Authority has
been notified of conflicts. Such delays will not be grounds for the Contractor
submitting a claim for extension of the Contract Time. The Contractor shall
coordinate its work so it does not interfere or otherwise delay the work performed by
SCRRA’s forces.
A. Train movements are governed by Positive Train Control (PTC), which are GPS-
based safety systems that combine wireless radio and computing technology.
Onboard technology will active safety features that interact with a Back Office Server
(BOS) System.
1. Contractor shall perform all work described within these Specifications and
Contract Plans in accordance with SCRRA’s Positive Train Control
Configuration and Change Management Policy (CCMP). The Contractor shall
coordinate all CCMP requirements with the SCRRA Engineer.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 14 16
PART 1 - GENERAL
1.01 SUMMARY
This Section outlines requirements and provisions regarding the Contractor responsibility
for coordination with all utility companies to ensure that all utilities are clearly marked,
protected for the duration of the construction activities or relocated. The exhibit to this
Specification Section entitled Project Utility Responsibilities when included in the Project
Specific Specifications shall identify each of the utilities affected by the Work.
1.03 SUBMITTALS
A. Where required by the Contract Documents, the Contractor shall prepare Shop
Drawings showing existing utility information and the installation of any utility
protection facilities or features to be established on the site prior to initiating
construction, maintained for the duration of construction and removed upon
completion of construction. This submittal information to the local utility and to the
Authority shall identify all necessary Work to adjust, move, or relocate existing
utility structures, utility poles, lines, services, or other utility appurtenances located
in or affected by construction.
B. The Contractor shall coordinate with all Utilities and authorities having jurisdiction
over these facilities and shall remove and relocate existing utilities and equipment
whenever an existing installation interferes with new construction. Carefully
examine each location and make arrangements in advance with the Authority to
ensure that construction has a minimum impact on the daily operations of the
Authority.
D. The relocated utilities shall be specifically identified in the record documents. The
types of material and methods of relocation and reconnection of utilities shall
match the existing unless otherwise noted.
E. The Contractor shall furnish the Authority copies of all utility required permits or
approvals obtained prior to starting Work at or adjacent to the utility facilities.
PART 3 - EXECUTION
3.01 GENERAL
Prior to the start of Construction, the Contractor shall engage an underground utility
detection company to detect and locate all existing underground utilities within the Work.
All underground utility information, including the approximate depth, shall be clearly
marked on surface and existing pavement for reference. The information shall also be
recorded in the Project files. Before commencing work, the Contractor shall notify Dig Alert
at 811 or 1-800-422-4133, 72 hours in advance of excavation and advise the Authority of
Dig Alert Identification number two working days before excavation begins. Before
commencing work, the Contractor shall also notify utility companies which have
underground facilities within the limits of the Work, but which do not participate in Dig Alert
(e.g. UPRR Dig Ticket, CBUD 1-800-336-9193), in accordance with each utility's
notification requirements, and have them locate and mark the facilities within the area of
excavation. The Contractor shall keep marking current in accordance with the
requirements of Dig Alert and the other utility companies.
SCRRA is not a member of Underground Service Alert (DigAlert) and SCRRA signal and
communication lines must be located by contacting the SCRRA Signal Department. Refer
to Section 01 14 16, Coordination with SCRRA for additional details.
Potholing and subsurface utilities and facilities verification work shall be completed at least
30 days in advance of any excavation work within the limits of any construction. The intent
of performing potholing and field verification of underground utilities well in advance of any
relocation, protection or modification of utilities is to preclude any delays or disruption
arising from utility relocation and allow for redesign and reissuance of plans and related
Contract Documents. Accordingly, any failure on the Contractor's part to perform the
potholing and field verification of utilities within the time frames listed above shall be
sufficient cause to reject any claims by the Contractor for delays associated with utility
relocations.
1. The Contractor shall pothole and physically locate all utilities under
Traffic/Pedestrian gate footing or within 2 feet of Traffic/Pedestrian gate
footing.
2. The Contractor shall notify the Gas Utility when excavating within 5 feet of
any natural gas pipeline and schedule Utility personnel if required. The
Contractor shall hand-dig within 5 feet of any natural gas pipeline.
3. The Contractor shall notify pipeline owner when excavating within 5 feet of
any oil pipeline and schedule standby personnel if required. The Contractor
to hand-dig within 5 feet of any oil pipeline.
4. The Contractor shall notify the Utility providing electrical service when
excavating within 5 feet of any energized electric facilities and schedule
utility personnel as required. The Contractor to hand-dig within 5 feet of any
energized electric facilities.
B. Utilities and pipelines, unless otherwise indicated, shall be in operation during the
construction work. The safe and proper handling of the utilities and pipelines is the
responsibility of the Contractor. The Contractor shall be liable for any injuries, line
breakage, damage to the line and damage to property. In addition, Contractor shall
be responsible for and shall reimburse Authority or owner of the utility, or pipeline
for all damages during construction and for any product (gas, oil or service) lost
there from. Precautions must be taken to contain any possible oil spills. Any
spillage of gas or oils shall be contained and if the material is not contained and
causes damages or gets into natural drainage courses, the Contractor shall be
solely responsible. Failure to respond within a reasonable time frame (herein
defined as a maximum of four hours or sooner for emergencies as determined by
the Authority or the Utility) will constitute cause for Authority to restore such utility
damages and to deduct all costs of restoration from the next Progress Payment to
the Contractor.
C. At Limited NTP or the project kick-off meeting, the Authority shall provide contact
numbers for all entities to be contacted in case of emergency including signal and
grade crossing problems and signal and communications cable locations. This will
include the Authority’s Chief Dispatcher and the Metrolink Sheriff's Dispatcher. The
Contractor shall ensure that Work Site personnel have immediate access to these
contact numbers.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
EXHIBIT
UTILITY RELOCATIONS/REARRANGEMENT
Name of Utility:
Contact Person:
Address:
Phone:
Email:
NOTES:
END OF SECTION 01 14 19
ALLOWANCES
PART 1 - GENERAL
1.01 SUMMARY
A. At the earliest practical date after award of the Contract, advise the Authority of the
date when final selection and purchase of each product or system described by an
allowance must be completed to avoid delaying the Work.
B. When specified or at the Authority's request, obtain proposals and prepare detailed
pricing for each allowance for use in making final selections. Include
recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by the Authority from the designated
supplier
Submit proposals for purchase of products, equipment, facilities, systems or for payment
of services included in allowances, in the form and detail specified for Change Orders.
The Authority will review the Contractor’s information relevant to the proposed price
including all pricing documentation supporting quotations from vendors, calculations,
estimating factors, risk analyses, equipment rates, productivity, as well as any other items
reasonably required by the Authority to satisfy itself as to the reasonableness of the
Contractor’s assumptions used to determine price.
B. Submit time sheets and other documentation to show labor time and cost for
installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in the same manner as for
other portions of the Work.
A. Allowances shall include the cost to the Contractor of specific products and
materials ordered or selected by the Authority under the allowance, and shall
include taxes, freight, and delivery to the Project site.
B. Unless otherwise indicated, the Contractor's costs for receiving and handling at
the Project site, labor, installation, overhead and profit, and similar costs related to
products and materials ordered or selected by the Authority under the allowance
shall be included as part of the Contract Price and not part of the allowance.
C. Whenever the actual cost of the materials, products, or equipment selected by the
Authority is more than or less than the allowance amount, the Contract Price will
be adjusted accordingly by Change Order.
D. Unused Materials: After installation has been completed and accepted, return
unused materials purchased under an allowance to the manufacturer or supplier
for credit to the Authority or if requested by the Authority, retain and prepare
unused material for storage by the Authority. Deliver unused material to the
Authority's storage space as directed.
A. Use the contingency allowance only as directed by the Authority for the Authority's
purposes, and only by Change Orders that indicate amounts to be charged to the
allowance.
B. The Contractor's overhead, profit, and related costs for products and equipment
ordered by the Authority under the contingency allowance are included in the
allowance and are not part of the Contract Price. These costs include delivery,
installation, taxes, insurance, equipment rental, and similar costs.
C. Change Orders authorizing use of funds from the contingency allowance will
include the Contractor's related costs in accordance with the Changes Section of
the General Conditions.
B. Include installation costs in the purchase amount only where indicated as part of
the allowance.
E. Submit requests for increased costs because of a change in scope or nature of the
allowance described in the Contract Documents, whether for the purchase order
amount or the Contractor's handling, labor, installation, overhead, and profit in
accordance with the Changes Section of the General Conditions. Do not include
the Contractor's or Subcontractor's indirect expense in the Change Order cost
amount unless it is clearly shown that the nature or extent of work has changed
from what could have been foreseen from information in the Contract Documents.
No change to the Contractor's indirect expense is permitted for selection of higher
or lower priced materials or systems of the same scope and nature as originally
indicated.
3.01 EXAMINATION
3.02 PREPARATION
Coordinate materials and their installation for each allowance with related materials and
installations to ensure that each allowance item is completely integrated and interfaced
with related Work. Furnish templates as required to coordinate installation.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 21 00
UNIT PRICES
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for Unit Prices. Unit
Prices are amounts stated on the Schedule of Quantities and Prices that represent full
compensation for furnishing all necessary labor, materials, tools, equipment and ancillary
services necessary to complete all the Work covered by each item as required in the
Contract documents.
1.03 PROCEDURES
A. Unit prices include all necessary submittals, shop drawings, materials, labor,
delivery or shipping charges, unloading or handling, insurance, installation costs,
profit, all applicable taxes, and other direct and indirect expenses. Where Unit
Price items require related Work specified in other sections of the Contract
Specifications, but which is not specifically mentioned in the Unit Price description,
the Contractor shall be responsible for and include all related work that is normally
required for Work similar to the Unit Price item. Detailed descriptions and other
provisions concerning Unit Price items are contained in other sections of the Plans
and Specifications.
B. Measurement and Payment: See individual Specification Sections for work that
requires establishment of Unit Prices. Methods of measurement and payment for
Unit Prices are specified in those Sections.
C. The Authority reserves the right to reject the Contractor's measurement of work-
in-place that involves use of established Unit Prices, and to have this work
measured by the Authority or an independent surveyor acceptable to the
Contractor. If the Contractor’s measurement is determined to be inaccurate, the
Contractor shall bear the cost of this Authority quantity survey. If the Contractor’s
measurement is confirmed as accurate, the Authority shall bear the cost of the
quantity survey.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 22 00
LUMP-SUM PRICES
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for lump sum prices
which are amount(s) proposed by the Contractor and stated on the Schedule of Quantities
and Prices for contracted amounts for materials, products, and operations to be provided
in the envisioned scope of the Work. Lump sum prices include all necessary materials,
labor, delivery or shipping charges, unloading or handling, installation costs, profit, all
applicable taxes, and other direct and indirect costs.
1.03 PROCEDURES
Contactor performance of Work for which Contract lump sum payments will be made shall
be listed in the approved Schedule of Values. Payment for each lump sum item provides
full compensation for furnishing the labor, materials, tools, and equipment, and for
performing all of the Work involved to complete the Work covered by each item and
included in the Contract Documents.
Where lump sum price items require related Work specified in other Sections of the
Contract Specifications, but which is not specifically mentioned in the lump sum price
description, the Contractor shall be responsible for and include all related Work that is
normally required for work of a similar nature to the item.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 22 05
OPTIONS
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for OPTIONS which are
amount(s) proposed by the Contractor and stated on the Schedule of Quantities and
Prices for specific Work defined in the bidding requirements. Options may be added to or
deducted from the base bid amount if, at its sole discretion, the Authority decides to accept
an option, either in the amount of construction to be completed or in the products,
materials, equipment, systems, or installation methods described in the Contract
Documents.
1.03 PROCEDURES
C. Immediately following award of the Contract, notify the Authority in writing, of the
status of each option. Indicate if options have been accepted, rejected, or deferred
for later consideration. Notification shall include a complete description of
negotiated revisions to alternates.
D. Authority reserves the right to accept or reject any option, in any order, and to
award or amend the Contract accordingly.
E. Execute accepted options under the same conditions as other work of the
Contract. The cost or credit for each option is the net addition to or deduction from
the Contract Price to incorporate an option into the Work. No other adjustments to
the Contract Price relating to options shall be allowed.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 23 00
PART 1 – GENERAL
1.1 SUMMARY
A. Related Specification Sections include but are not necessarily limited to:
1.3 DEFINITIONS
B. Field Office Overhead: Time-related costs of field office overhead include, but are not
limited to, salaries, benefits, and equipment costs of project managers, general
superintendents, field office managers, and other field office staff assigned to the
Project, as well as rent, utilities, maintenance, security, supplies, and equipment
costs of the field office.
C. Regional and Home Office Overhead: Regional and Home office overhead refers to
the costs of operating the Contractor’s business. These costs include, but are not
limited to, salaries, benefits, and equipment costs of general administration, new
business development, marketing, insurance, personnel and subcontract
administration, purchasing, accounting, and project management and estimating.
D. Contract Time: As defined in the Contract, the Contract Time is the original duration
of the Contract in calendar days plus Change Order(s) adjustments.
A. The first calendar day for the purpose of measuring time-related overhead shall be
the effective date of the Notice to Proceed authorizing job-site mobilization.
B. The last calendar day for the purpose of measuring time-related overhead shall be
the Date of Substantial Completion.
A. One day of time-related overhead will be paid for every calendar day designated in
Specification Section 01 31 99 Period of Performance. Calculation of time-related
overhead costs will be based on working days with a corresponding adjustment in
calendar days for Contract Time. Any adjustments must satisfy at least one of the
following criteria:
B. In the event an early completion progress schedule proposed by the Contractor and
approved by the Authority, the quantity of time-related overhead days eligible for
payment will be based on the reduced number of calendar days for the Project as
approved by the Authority.
A. If the final quantity of time-related overhead days exceeds the original bid quantity
by more than 50 percent, the Contractor shall, within 60 days of the Authority's
written request, submit to the Authority an audit examination and report performed
by an independent certified public accountant of the Contractor's actual overhead
costs. The audit examination and report shall depict the Contractor's project and
companywide financial records and shall specify the actual overall average daily
rates for both field office and home office overhead for the entire duration of the
project, and whether the costs have been properly allocated. The rates of field office
and home office overhead shall exclude unallowable costs as determined in the
Federal Acquisition Regulations, 48 CFR, Chapter 1, Part 31.
C. The actual rate of time-related overhead specified in the audit, and submitted by the
Contractor, will be subject to approval by the Authority.
A. For the purpose of progress payments, the number of Calendar Days to be paid
for TIME-RELATED DAILY OVERHEAD RATE contract item in each monthly
payment cycle will be the number of working days for that month.
B. Provisions relating to increased or decreased Unit Price quantities shall not apply
to the TIME-RELATED DAILY OVERHEAD RATE contract item.
END OF SECTION 01 23 50
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for Value Engineering
Change Proposals (VECPs) by the Contractor. The Authority encourages the Contractor
to submit VECPs whenever the Contractor identifies areas or instances in which
improvements can be made, in order to achieve Project cost savings.
6. Date by which a Change Order adopting the VECP must be issued in order
to obtain the maximum cost reduction, noting any effect on Contract
completion time or delivery schedule.
C. The Contractor shall submit VECPs to the Authority. The Authority will process
proposals expeditiously, but shall not be liable for any delay in acting upon any
proposal submitted pursuant to this Section. The Contractor may withdraw all or
part of any VECP at any time prior to acceptance by the Authority, but will, at the
sole discretion of the Authority, be liable for costs incurred by the Authority in
reviewing the proposal. The decision of the Authority as to the rejection or
acceptance of any VECP shall be at the sole discretion of the Authority.
D. At its sole discretion, the Authority may accept, in whole or in part and by Change
Order, any VECP submitted pursuant to this Section. Designs for accepted VECPs
will be accepted by the Authority for incorporation into the drawings and
specifications. Until a Change Order is executed authorizing the VECP, the
Contractor shall remain obligated to perform in accordance with the Contract.
1. Net savings are defined as gross savings less the Contractor's costs and
less the Authority's costs.
4. The Authority's costs means reasonable costs incurred by the Authority for
evaluating and implementing the VECP, such as testing, redesign, and the
effect on other contracts.
G. Within the limits stated in the Contract, the Contractor may restrict the Authority's
right to use any part of a VECP or the supporting data thereof in accordance with
the terms of the following:
2. This restriction does not limit the Authority's right to use information
contained in this VECP if it is or has been obtained, or is otherwise
available, from the Contractor or from another source without limitations.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 24 13
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for substitutions which
are the Contractor proposed changes in products, materials, equipment, and methods of
construction from those required by the Contract Documents.
The Contract Documents, including Contract Drawings, and Specifications have been
prepared to complement and accommodate certain specified equipment, products or
systems, and any modifications, adjustments, or redesign required to assimilate any
Authority approved substitution of “or equal” equipment, products, or systems shall be at
the Contractor’s sole expense. The Contractor shall provide a complete and workable
application and shall satisfy design criteria and aesthetic values to the sole satisfaction of
the Authority. The Contract Time for completion of the Work specified in the Contract
Documents shall not be affected by any circumstances whatsoever arising from the
provisions of this Specification.
1.04 EQUALS
Except as may be provided in the Special Conditions, or stated otherwise in the various
sections of the Specifications, whenever any material, product, thing, or service is
specified or indicated in the Contract Documents by brand, trade, patent, or proprietary
name or by the name of the manufacturer, the item so specified or indicated shall be
deemed to be followed by the words “or equal.”
During the Contract Bid Period, the Contractor may at its own risk, submit an item not
specified in the Contract Documents as an “or equal” for consideration by the Authority.
Failure to do so within the time frame described in the Instructions to Bidders shall bar the
Contractor from proposing or substituting an “or equal” item for an item specified in the
Contract Documents.
If the Contractor submits an “or equal” item, the Contractor must submit sufficient data to
the Authority to substantiate the specific characteristics and qualities that make the “or
equal” item the equivalent, as described in the paragraph below. The Contractor shall
furnish such substantiating data or arrange for any necessary tests to verify the equivalent
qualities of the “or equal” item at the Contractor’s sole expense.
The Authority, in its sole discretion, shall determine whether the substantiating data
demonstrates that an “or equal” item is equivalent in all respects to the item specified in
the Contract Documents. If the Authority determines that the “or equal” item has not been
substantiated to be equivalent in all respects, the item specified in the Contract Documents
shall be furnished and installed by the Contractor, without modification of the cost proposal
amount or Contract Documents.
7. A list of similar installations for completed projects, with project names and
addresses and the names and addresses of pertinent Engineers and
Authorities.
11. Cost information, including a proposal of change (if any) in the Contract
Price.
12. The Contractor's certification that the proposed substitution complies with
requirements in the Contract Documents, except as indicated in the
substitution request; is compatible with related materials; and is appropriate
for the indicated applications.
13. The Contractor's waiver of rights to additional payment or time that may
subsequently become necessary because of any failure of the proposed
substitution to produce indicated results.
2. Use the product specified if the Authority does not issue a decision on use
of a proposed substitution within the time allocated.
PART 2 - PRODUCTS
2.01 SUBSTITUTIONS
The Authority will consider the Contractor's request for substitution when the
following conditions are satisfied. If the following conditions are not satisfied, the
Authority will return requests without action, except to record noncompliance with
these requirements:
B. Substitutions for Convenience: The Authority will consider requests for substitution
if received within 45 days after the Notice of Award. Requests received after that
time may be considered or rejected at the discretion of the Authority. The Authority
will consider the Contractor's request for substitution when the conditions below
are satisfied. If the following conditions are not satisfied, Authority will return
requests without action, except to record noncompliance with these requirements:
11. If requested substitution involves more than one Contractor, the requested
substitution has been coordinated with other portions of the Work, is
uniform and consistent, is compatible with other products, and is
acceptable to all Contractors involved.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 25 00
PART 1 - GENERAL
1.01 SUMMARY
This Section covers the general requirements for the Contractor’s Requests for
Information and pertains to all portions of the Contract Documents.
A. The Contractor shall examine all Contract Documents; shall verify all figures in the
Contract Documents before laying out the Work; shall promptly notify the Authority
of all errors, discrepancies, inconsistencies, or omissions that it discovers; and, in
instances where such nonconformities are discovered, shall obtain specific
instructions in writing from the Authority by utilizing the RFI process before
proceeding with the Work.
B. When the Contractor is unable to determine from the Contract Documents the
exact material, process, or system to be installed, the Contractor shall ask the
Authority to clarify the indeterminate item. Wherever possible, such clarification
shall be requested at the next appropriate project meeting, with the response
entered into the meeting minutes. When clarification at the meeting is not possible,
either because of the urgency of the need or the complexity of the item, the
Contractor shall prepare and submit a written RFI to the Authority in the form and
format established by the Authority.
D. In the event of any doubt or question concerning the true meaning of the Contract
Documents, or should it appear that the Work to be done or any of the matters
relative thereto are not sufficiently detailed or explained in the Contract
Documents, the Contractor shall submit a RFI to the Authority for such further
written explanations as may be reasonably necessary, and shall conform to the
written explanation given as if it were part of the Contract Documents. The decision
of the Authority in such cases shall be final.
E. RFIs shall be submitted on the latest SCRRA RFI form provided by the Authority.
Forms shall be completely filled in, and, if prepared by hand, shall be fully legible
after photocopying. Each page of attachments to RFIs shall bear the RFI number
in the lower right-hand corner. Each RFI shall reference a drawing number or a
Specification Section. RFIs from Subcontractors or Material suppliers shall be
submitted through, reviewed by, and signed by the Contractor prior to submittal to
the Authority.
F. The Contractor shall submit RFIs in a timely manner to avoid delays to the progress
of the Work. RFIs prepared and submitted by the Contractor shall be complete and
shall include all information or references necessary for The Authority to respond.
G. The Authority will respond to RFIs in a timely manner. The target response time
for RFIs will be 10 working days but will be no longer than 20 working days. In the
event that there are numerous RFIs pending, the Contractor shall cooperate with
the Authority in establishing a priority for responding to the RFIs.
J. The Contractor shall not assert any claims for delay or interference against the
Authority if the Contractor fails to submit any RFI in a timely manner to the Authority
(taking into account the time allowed for a response period allowed for the
Authority).
K. The response to an RFI shall not, by itself, constitute authorization for the
Contractor to perform any Change Work that causes an adjustment to either the
Period of Performance or the Contract Amount.
M. In the event the Contractor believes that a clarification by the Authority results in
additional cost, the Contractor shall not proceed with the Work indicated by the
RFI until a Change Order is prepared and approved. Neither answered nor
unanswered RFIs shall be construed as approval to perform extra work or
entitlement to adjust Period of Performance or the Contract Amount.
O. The Contractor shall prepare and maintain a log of RFIs and, at any time so
requested by the Authority, the Contractor shall furnish copies of the log showing
all outstanding RFIs. The Contractor shall note all unanswered RFIs in the log.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 26 14
SCHEDULE OF VALUES
PART 1 - GENERAL
1.01 SUMMARY
1.03 DEFINITIONS
B. Correlate line items in the Schedule of Values with other required administrative
forms and schedules, including the following:
2. Submittal schedule
C. Where the Work is separated into phases requiring separately phased payments,
provide values correlated with each phase of payment. Where the Contractor's
construction schedule defines separate elements of the Work, provide values
correlated with each element.
D. Format and Content: Use the Specification sections as a guide to establish line
items for the schedule of values. Provide at least one line item for each
Specification section.
5. Date of submittal
F. Arrange the Schedule of Values in a manner consistent with the format of CSI
Master Format 2004.
G. Arrange the Schedule of Values in tabular form, with separate columns to indicate
the following for each item listed:
3. Name of Sub-Contractor
5. Name of supplier
I. Include separate line items under the Contractor and principal subcontracts for
project closeout requirements in an amount totaling one half of one percent of the
Contract Price and five percent of the subcontract amount.
J. Each item of the Schedule of Values shall include its proportionate share of profit,
and all other expenses involved.
1. The summation of extensions of quantities and unit prices and related costs
shall equal the amount of the lump-sum price of the applicable Contract bid
item indicated in the Schedule of Quantities and Prices.
2. Round amounts to the nearest whole dollar; the total shall equal the
Contract Price.
3. Provide a separate line item in the Schedule of Values for mobilization and
demobilization for each time and part and phase of the work where the
Contractor is required to mobilize and demobilize its operations.
4. Provide a separate line item in the Schedule of Values for each part of the
Work where Applications for Payment may include materials or equipment
purchased or fabricated and stored, but not yet installed.
6. Provide separate line items in the Schedule of Values for the preparation
of submittals, initial cost of materials, for each subsequent stage of
completion, and for total installed value of that part of the Work.
7. Allowances: Provide a separate line item in the Schedule of Values for each
allowance. Show line item value of unit-cost allowances, as a product of
the unit cost, multiplied by measured quantity. Use information indicated in
the Contract Documents to determine quantities.
9. Each item in the Schedule of Values and Applications for Payment shall be
complete. Include total cost and proportionate share of general profit for
each item.
10. Mobilization and Demobilization and other major cost items that are not
direct cost of actual work in place may be shown either as separate line
items in the Schedule of Values or distributed within the costs allocated to
the values of Time-Related Overhead, at the Contractor's option.
K. The Contractor shall be responsible for the accuracy of the quantities and values
used in the Schedule of Values. No adjustment in compensation will be made due
to differences between the quantities shown in the Schedule of Values furnished
by the Contractor and the quantities required to complete the Work as shown on
the Contract Drawings and as specified in these Contract Documents.
L. The Authority will not approve the Schedule of Values if the amounts are
unreasonable and unbalanced. The Contractor shall provide any supporting
documentation necessary for the Authority to determine acceptability.
PART 3 - EXECUTION
3.01 PREPARATION
At the Preconstruction Meeting or within 7 days after the effective date of the Notice to
Proceed, the Contractor shall submit to the Authority a detailed Schedule of Values that
must be approved by the Authority prior to the Contractor’s first application for progress
payment.
3.02 APPROVAL
Upon approval by the Authority, the Schedule of Values will form a basis for determining
the compensation payable to the Contractor based on actual progress of Work, in
accordance with the approved progress schedule, with respect to each Contract bid item
to be paid by lump sum. No progress payment for Contract bid items to be paid by lump
sum shall be made without an approved Schedule of Values.
If review by the Authority indicates that changes to the Schedule of Values are required,
the Contractor shall revise and resubmit in the same manner as the original Schedule of
Values was approved.
Update and resubmit the Schedule of Values before each application for payment when
Change Orders or Work Authorization Change Notices result in a change in the Contract
Price.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 29 73
PART 1 - GENERAL
1.01 SUMMARY
1.03 COORDINATION
B. Each Contractor shall coordinate its construction operations with those of other
contractors and entities to ensure efficient and orderly installation of each part of
the Work.
5. Progress meetings.
6. Pre-installation conference.
E. Coordinate construction activities to ensure that operations are carried out with
consideration given to conservation of energy, water and materials. Coordinate
use of temporary utilities to minimize waste.
c. Phasing
f. Lines of communications
l. Submittal procedures
p. Work restrictions
q. Working hours
x. Parking availability
aa. Security
a. Contract Documents
b. Options
c. Related RFIs
e. Purchases
f. Deliveries
g. Submittals
h. Review of mockups
i. Possible conflicts
j. Compatibility requirements
k. Time schedules
l. Weather limitations
n. Warranty requirements
o. Compatibility of materials
p. Acceptability of substrates
u. Installation procedures
z. Safety requirements
h. Submittal procedures
1) Interface requirements
2) Sequence of operations
3) Status of submittals
4) Deliveries
5) Off-site fabrication
6) Access
7) Site utilization
9) Progress cleaning
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 31 00
PARTNERING
PART 1 - GENERAL
1.01 SUMMARY
The Authority will promote the formation of a “Partnering” relationship with the Contractor
to effectively complete the Contract to the benefit of both parties. This partnering
relationship will be structured to draw on strengths of each organization to identify and
achieve mutual goals. The purpose of this relationship will be to maintain cooperative
communication and mutually resolve conflicts in accordance with the terms of the
Contract.
To implement this partnering initiative, prior to starting field Work, the Contractor’s
management personnel and the Authority will initiate a partnering development Team-
building workshop. Project personnel shall work with the assistance of a Facilitator to
make arrangements and to determine attendance, agenda, duration, and location of the
workshop. Persons required to be in attendance will be the Authority’s management staff
and key project personnel representing the Authority, the Contractor’s management staff
and key project supervision personnel of both the Contractor and principal Subcontractors
and suppliers, and representatives of respective utility companies. The project design
engineers and other key personnel will also be invited to attend, as necessary.
If mutually agreed, follow-up workshops may be held periodically throughout the duration
of the Contract.
PART 3 - EXECUTION
The Contractor shall be responsible for making all the necessary arrangements to provide
a Facilitator, associated materials and a workshop site. Such arrangements shall be
mutually agreed upon in advance by the Contractor and the Authority.
The Authority shall approve all direct costs, and each party will be assessed for 50% of
such costs. The reimbursable portion of the Contractor’s costs associated with Partnering
will be made by modification to the contract and payment will be made under the allowance
item for Partnering in the Schedule of Quantities and Prices.
END OF SECTION 01 31 19
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for a two-step Notice-to-
Proceed process, and defines allowable conditions for Contract Time extensions.
1.03 DEFINITIONS
B. Notice to Proceed: SCRRA written authorization to proceed with all or portions of the
Work, as specified.
C. Contract Time: As stated in the Contract, the original duration of the Contract in
calendar days plus Change Order adjustments
The Authority will employ a two-step Notice to Proceed. As specified in the Contract Special
Conditions, the Authority will issue a “Limited Notice to Proceed,” no later than 20 days after,
or as early as one day after, execution of the Contract. The Contractor is not authorized to
perform any work until the Contractor has received the Limited Notice to Proceed from the
Authority. Should the Contractor begin Work in advance of receiving the Limited Notice to
Proceed, such Work shall be considered as having been done at the Contractor’s own risk.
The Limited Notice to Proceed will initiate the Contract Time and will constitute a notice to
proceed with specified Work tasks and deliverables.
The full “Notice to Proceed” will not be issued prior to the Authority’s acceptance of
completion of all activities initiated by the “Limited Notice to Proceed,” above. The issuance
of the full “Notice to Proceed” will be a notice for the Contractor to proceed with all remaining
Work and diligently prosecute the same to completion within the Contract Time.
The date of the Limited Notice to Proceed is the start date for the Contract Period of
Performance.
A. Delays beyond the Contractor’s control: The Contractor will be granted an extension
of time and will not be assessed with liquidated damages for any delay in
substantially completing the Work (or parts thereof) beyond the time set forth in the
Contract, provided that such delay was caused by unforeseeable causes beyond the
control and without the fault or negligence of the Contractor. Examples of such
causes include acts of a public enemy, fire, floods, adverse weather, tidal waves,
earthquakes, hurricanes, epidemics, quarantine restrictions, strikes, labor disputes
and freight embargoes, or negligent acts of the Authority.
B. Authority caused delays: In the event the Contractor is actually and necessarily
delayed by any act or omission on the part of the Authority (as determined by the
Authority), and provided that the Contractor notifies the Authority in writing within 5
days from the beginning of any such delay, specifying the act or omission causing
such delay, the time for completion of the Work may be extended at the sole
discretion of the Authority. In all cases, any extension of time is contingent on all of
the following:
1. That the cause is not due to the fault or negligence of the Contractor, and the
Contractor has taken reasonable precautions to prevent the delays and
minimize the effects thereof.
2. That the Contractor submits a Request for Change (RFC) specifying the
nature of the delay and the measures that have been or will be taken to
prevent or minimize the delay. Failure to submit written notice within this time
period shall constitute an absolute waiver of any claim for a time extension.
The RFC submitted by the Contractor shall also include a Time Impact
Analysis as required in the Specification.
3. No extension of time will be granted under this Section for any Authority
caused delay in which (1) the performance of Work would have been
concurrently delayed by the Contractor induced causes, including an act or
omission of the Contractor or its Subcontractors, or (2) remedies are included
or excluded by any other provision of the Contract. Only the actual delay
necessarily resulting from the causes specified in this Section shall be
grounds for an extension of time. In case the Contractor is delayed at any
time or for any period by two or more of the causes specified in this Section,
the Contractor shall not be entitled to a separate extension for each one of
the causes; only one extension will be granted for the entire delay.
5. The term “shortage of materials,” as used in this Section, shall apply only to
materials, articles, parts, or equipment that are not custom items; it and shall
not apply to equipment, materials, parts, or articles that are processed, made,
constructed, fabricated, or manufactured to meet the specific requirements of
the Contract Documents. Only conditions not in the control of the Contractor
that result in the physical shortage of materials will be considered as a cause
for extension of time, and no consideration will be given to any claim that
material could not be obtained at a reasonable, practical, or economical cost
or price, unless it is shown to the satisfaction of the Engineer that such
material could have been obtained only at exorbitant prices entirely out of line
with current rates, taking into account the quantities involved and the usual
practices in obtaining such quantities.
C. When inclement weather at the Project site affects Critical Path activities, the
Contractor may provide the Authority with a written request for a weather impact day
that fully describes the inclement weather delay on the Critical Path activities.
Excusable, non-compensable Contract time extensions for weather delays will only
be considered for such delays that affect activities on the critical path of the Contract,
as defined by the schedule current at the time of the delay. Such time extensions, if
approved, will be non-compensable and shall be requested by the Contractor in
accordance with Contract Change Order procedures subject to the following:
2. The table below lists the typical number of inclement weather days per month.
Only days lost due to weather in a given month in excess of the number listed
for that month will be considered for a time extension. Weather delay days
are not cumulative from month to month.
February 5 August 0
March 5 September 0
April 4 October 0
May 3 November 3
June 0 December 5
3. Weather impact days will not be granted for inclement weather that occurs
on non-scheduled workdays. If the effects of inclement weather from a non-
scheduled work day carry forward to a scheduled work day and affects the
Critical Path as noted above, then the scheduled work day will be
considered affected by weather.
4. If the Contractor asks to work a specific weekend or holiday and gives the
Authority advance written notification of critical-path work to be performed,
and if a substantial amount of precipitation occurs that prevents the work
from being performed, that day can be claimed as a weather impact day.
Any unused rain day allowance at the end of the project will be shown as
available float to the Substantial Completion milestone.
D. Time Extensions for Critical Path activities only: No extensions of time will be
granted for delays that have no measurable impact on the completion of the Work
(or parts thereof) under the Contract Documents. When extensions of time are
granted, they shall be limited to the period equivalent to the actual number of days
lost on the Critical Path or controlling operations of the Project Baseline Schedule
or other applicable construction schedule, taking into account the extent to which
that delay could be decreased by reasonable mitigation measures by the
Contractor. All requests for extensions of time shall be supported with a critical
path analysis showing the critical path and impacts on it. The Contractor’s failure
to submit this analysis will be sufficient cause for denial of any request for a time
extension.
E. An extension of time granted shall not release the Contractor's Surety from its
obligations. Work shall continue and be carried on in accordance with all provisions
of the Contract. The Contract shall remain in full force and effect during the
continuance and until completion and acceptance of the Work covered by the
Contract, unless formally suspended or terminated in accordance with the terms
of the Contract. Permitting the Contractor to finish the Work, or any part thereof,
after the time fixed for completion (or after the date to which the time for
completion may have been extended), and/or making payments to the Contractor
after any such periods, shall not constitute a waiver on the part of the Authority of
any rights under the Contract.
F. Neither the granting of an extension of time beyond the date fixed for the
completion of any part of the Work nor the performance and acceptance of any
part of the Work after the time specified for the completion of the Work shall be
deemed to be a waiver by the Authority of the Authority's right to terminate the
Contract for abandonment or failure to complete within the time specified, or to
impose and deduct damages as may be specified.
G. In all cases in which the Contractor either Claims or intends to Claim a delay, the
Contractor shall comply with those provisions contained in the Contract.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 31 99
PART 1 - GENERAL
1.01 SUMMARY
Section includes requirements for preparing, submitting, revising, and updating project
scheduling information. The purpose of this section is to ensure adequate planning and
execution of the Work by the Contractor and to establish a standard against which
satisfactory completion of the Project can be measured by the Authority and provide
justification for progress payments.
1.02 GENERAL
A. The scheduling and execution of the Work in accordance with the Contract
Documents are the responsibility of the Contractor. Schedules shall represent a
practical plan to complete the Work within the Contract Time and shall convey the
Contractor’s intent in the manner of prosecution and progress of the Work. The
submittal of schedules shall be understood to be the Contractor’s representation
that the schedule meets the requirements of the Contract Documents and that the
Work will be executed in the sequence and duration indicated in the schedule.
B. Schedules shall be consistent with the time and work requirements of the Contract.
The Contractor shall execute the Work in the sequence indicated on the current
approved schedule.
C. The Contractor shall involve and coordinate with all Subcontractors, third parties,
and material suppliers in the development and updating of schedules.
E. If after a schedule has been accepted or approved by the Authority, either the
Contractor or the Authority discovers that any aspect of the schedule has an error
or omission, the Contractor shall correct it on the next Progress Schedule.
F. Errors or omissions on schedules shall not relieve the Contractor from finishing all
work within the Contract Time.
G. The Contractor shall adjust, add to, or clarify any portion of a schedule which the
Authority determines to be insufficient for monitoring the Work or to be impractical
for any reason.
1.04 DEFINITIONS
B. Actual Dates: The actual start or finish date of an activity which occurs prior to the
data date. Dates occurring after the data date are forecasted dates and are not
actual dates.
D. Baseline Schedule: The initial schedule representing the Contractor's work plan on
the first working day of the project as approved by the Authority.
F. Controlling Operation: The activity, within that series of activities defined as the
applicable critical path, which if delayed or prolonged will delay the scheduled
completion date of the Work.
G. Critical Path: The longest continuous chain of activities for the project that has the
least amount of total float of all chains. In general, a delay on the critical path will
extend the scheduled completion date.
I. Data Date: The day after the date through which a schedule is current. Everything
occurring earlier than the data date is "as-built" and everything on or after the data
date is "planned."
J. Day: Refers to working days, which are any days other than any days declared
holidays by the Authority.
K. Early Completion Date: A scheduled completion date which is earlier than the
contract completion date.
L. Free Float: The amount of time an activity can be delayed before affecting a
subsequent activity.
O. Narrative Report: A document submitted with each schedule that discusses topics
related to project progress and scheduling.
P. Near Critical Path: A chain of activities with total float exceeding that of the critical
path but having no more than 10 working days of total float.
Q. Open Ended Activity: An activity without at least one predecessor and one
successor.
R. Out of Sequence Activities: Any activity which actually starts in a sequence other
than shown in the current approved schedule.
T. Revision: A change in the schedule that modifies logic, adds or deletes activities,
or alters activities, sequences, or durations.
U. Scheduled Completion Date: The planned date of completion of the Work shown
on the current approved schedule.
W. Total Float: The amount of time that an activity or chain of activities can be delayed
before extending the scheduled completion date.
1.05 SUBMITTALS
E. Subcontractor Documentation:
G. Submit for Authority’s use two (2) Primavera P6 Enterprise Project Portfolio
Management Scheduling Software licenses (registered to the Authority).
H. Three Week Look Ahead Schedule: Submit first Three-Week Look Ahead
Schedule at Pre-Construction Meeting. Submit three hard copies of the weekly
thereafter at Construction Progress Meetings until Substantial Completion.
A. Each submittal of Baseline, Preliminary and Progress Schedules shall include the
elements listed herein.
C. Gantt Activity Bar Charts: Show activities grouped by work areas and sorted by
early start. Submit six (6) hard copies, 11 by 17 inch, and two (2) color E-size plots,
34 inches by 44 inches.
A. Baseline Schedule shall utilize computerized Critical Path Method (CPM) network
scheduling.
C. Baseline Schedule shall show the order in which the Contractor proposes to carry
out the work with logical links between work activities, and calculations made using
the critical path method to determine the controlling operation or operations.
Ensure that activity sequences are logical and that schedule shows a coordinated
plan for complete performance of the work.
D. Baseline Schedule shall include the entire scope of work through the end of
Contract Time. Show how the Contractor plans to complete the Work. Show the
activities that define the critical path. Show float on other activities. Keep multiple
critical paths and near-critical paths to a minimum. A total of not more than 30
percent of the baseline schedule activities shall be critical or near critical, unless
otherwise authorized by the Authority.
E. The data date for the Baseline Schedule shall be the date of Limited Notice to
Proceed (LNTP) and shall include actual dates and durations for work completed
prior to Notice to Proceed (NTP). Baseline Schedule shall not attribute negative
float or negative lag to any activity.
F. Baseline Schedule shall define non-working days as the following 9 holidays: New
Years Day, Martin Luther King Day, President’s Day, Memorial Day, Independence
Day, Labor Day, Thanksgiving Day, Day after Thanksgiving Day and Christmas
Day.
G. Float: Float shall not be considered as time for the exclusive use of or benefit of
either the Authority or the Contractor, but shall be considered as a jointly owned,
expiring resource available to the project and shall not be used to the financial
detriment of either party. Use of float suppression techniques such as preferential
sequencing, special lead/lag logic restraints, extended activity durations or
imposed constraints will be cause for rejection of the Baseline Schedule and
subsequent Progress Schedules. The Contractor shall not create artificial activities
that eliminate any or all float in the project schedule.
I. Autocost rules: Autocost rules shall link the remaining duration and the schedule
percent complete. The updated percent complete against the budget shall be used
to estimate Actual Cost to Date, and Actual to Date shall be linked to Actual This
Period. Other automatic cost/resource calculation rules shall be in a format
acceptable to the Authority.
J. Retained Logic: When schedule calculations are performed, the “Retained Logic”
setting shall be used.
1. The difference between the early completion date and the contract
completion date is considered float. Float time shall not be for the exclusive
benefit of either the Authority or the Contractor. Float shall be a resource
available to both parties.
L. Baseline Narrative Report: Submit a narrative report with the Baseline Schedule
describing the schedule development process, activity coding structure, basis of
proposed durations, work sequence, approach or methods the Contractor intends
to employ in the Work, and explanation of early scheduled completion date, if
proposed.
A. Activity Coding: The Contractor shall develop its own activity coding structure.
Activities shall be coded to a level sufficient to allow for multiple sorting such as
that specified for tabular reports under “Tabular Reports” and “Gantt Activity Bars”
in the Section entitled “Submittal Details” (1.06) herein.
8. Acquisition of permits.
3. Duration not less than one full day, except for milestone activities, and not
more than 15 working days, with the exception of submittals, fabrication,
procurement, and summary activities, unless otherwise approved by
Authority.
4. At least one predecessor and one successor activity, except for project
start and finish milestones.
6. Activity codes for responsibility, phase, area, stage, work shifts, and
contract bid item numbers. Code for responsibility shall denote the entity
performing the activity, i.e. Authority, Contractor, Subcontractor, or utility.
B. Updates to Preliminary 90-Day Schedule are basis for payment to the Contractor
during the first three-month period. Timely submittal and acceptance of such
updates shall be a condition precedent to payment by Authority.
C. Preliminary 90-Day Schedule shall also identify activities and milestones that will
or may affect or be affected by activities of the Authority, Utilities, Railroads and
other third parties.
D. Partial cost loading for purpose of Progress and Earned Value Measurement as
described in Section 1.11 covering the Work for first 90-Days after the LNTP or
NTP shall be submitted with the Preliminary 90-Day Schedule.
D. For the detail procedures for Monthly Progress Review Meeting and the required
formats for Preliminary Progress Schedule, refer to Section 1.11-A.
E. Include the following information in the Progress Schedule: Status of work actually
completed to date and the work yet to be performed as planned; actual activity
start dates, and finish dates, as applicable; and durations for work that has been
completed as the work actually occurred, including Authority submittal review and
Contractor resubmittal times. Show approved time adjustments and project
completion dates. Show approved Contract Change Order work. Show weather
delay days which have already occurred and have been acknowledged by the
Authority in writing.
2. Explanation of any lack of work on activities on the critical path during the
reporting period.
A. As a part of the monthly update cycle, a progress review meeting utilizing the
Preliminary Update Schedule, will be held at least 3 working days prior to the data
date between the Contractor and the Authority.
1. The schedule shall be based on the approved Progress Schedule from the
previous month.
2. The format shall include added blank columns in which the Contractor will
pencil in the updated information including start dates, finish dates, percent
completes, and remaining durations. The Contractor shall indicate activities
for which Physical Percent Complete is used. The anticipated actual
progress between the meeting date and the data date shall also be
projected and included in the Preliminary Update Schedule. The format for
the draft update schedule is shown below.
3. Any logic revisions that need to be incorporated into the Progress Schedule
shall be brought to the Authority’s attention in the monthly progress review
meeting for Authority’s initial review, including, but not limited to, fixing the
logic of out-of-sequence activities, adding any approved time impact
fragnets, reflecting the Contractor’s work plan changes, and any other
minor logic revisions.
3. Each activity’s cost loading should be made based on the predefined cost
account numbers so that a Schedule of Value report can be generated from
the scheduling software after the entire cost loading is done. The format of
the Schedule of Value shall be the same as the Schedule of Quantities of
Price in the contract document.
C. The amount of monthly progress payment shall match the sum of the Earned
Values generated from the cost loaded activities as a result of updating the
Progress Schedule.
2. The Schedule of Value shall be the base from which an Earned Value
Report will be generated each month. The Earned Value Report shall be
attached to each monthly payment application submittal package.
D. After the monthly progress review meeting, the Contractor shall formally update
the monthly Progress Schedule based on the agreed-upon schedule update data.
Then the monthly Earned Value Report shall be generated and included in the
monthly Progress Schedule submittals, which shall be submitted no later than 5
working days after the data date. The Earned Value Report shall be a direct output
from the scheduling software which shows subtotal for each Schedule of Value
grouping category and grand total for the entire project. The Earned Value Report
format is shown below.
A. Three-Week Look Ahead Schedule shall contain one week of historical information
and three weeks of planned activities in support of and consistent with the Baseline
Schedule or current Progress Schedule.
D. Clearly show each activity requiring track access during specified work windows;
schedule activities performed during single or multiple track outage work windows
utilizing an hourly time scale.
E. Show weather delay days which have already occurred and have been
acknowledged by the Authority in writing.
A. The Authority will review and return the Contractor’s schedule submittals and
deliverables with a written response according to the following schedule from the
date of receipt from the Contractor.
B. The Authority will review and return resubmittals to the Contractor with a written
response according to the following schedule from the date of receipt from the
Contractor.
C. If the Contractor does not agree with the Authority’s comments, provide written
notice of disagreement within 5 working days from the receipt of the Authority’s
comments. Resolve any Authority’s comments with which the Contractor
disagrees in a meeting held for that purpose.
D. The first of each type of submittal and deliverable submitted by the Contractor will
be reviewed for format, as well as content. The Authority may require format
changes. Once the format has been approved, submit subsequent submittals and
deliverables in the approved format.
E. Baseline Schedule Review Meeting: Within 10 working days after the submittal of
the Baseline Schedule, the Authority will conduct a Baseline Schedule Review
Meeting with the Contractor.
F. Recovery Schedule: If Contractor’s actual progress of the Work falls ten (10)
working days behind the approved Baseline Schedule for the Contract completion
date, the Contractor shall prepare and submit a Recovery Schedule within five (5)
working days to explain and display how the Contractor intends to regain
compliance with the Contract completion date. The Recovery Schedule shall detail
the Contractor’s plan for bringing the work back on schedule. The Contractor’s plan
for recovery shall conform to all other Contract requirements. Incorporate revisions
accepted by the Authority in the next Progress Schedule. Do not incorporate
proposed revisions in the Progress Schedule prior to their acceptance.
B. Illustrate the impacts of each change or delay on the current Contract completion
date or interim milestone, as appropriate. Use the approved Progress Schedule
which has a data date closest to and prior to the event for which an extension is
being requested.
C. Include a schedule showing all schedule logic revisions, duration changes, cost
changes, and additions or deletions of activities for the work in question and its
relationship to other activities on the Progress Schedule. Provide additional
supporting evidence if requested by the Authority.
D. The Authority’s determination as to the total number of days of time extension will
be based upon the current schedule for the time period in question, and all other
relevant information. Actual delays in activities which, according to the Progress
Schedule, do not affect the critical path or the Contract completion date will not be
the basis for a time extension.
E. The Authority will review the facts and advise the Contractor in writing of the
Authority’s decision. If the Authority determines that the Contractor is entitled to an
extension of time to an interim milestone, the Contract completion date will remain
the same, unless the Authority specifies another date. Any change to Contract
milestones or to the Contract completion date will be made by Change Order.
F. If the Authority has not yet made a full determination as to the amount of time
extension to be granted and the parties are unable to agree as to the amount of
extension to be reflected in the Progress Schedule, reflect that amount of time
extension in the Progress Schedule as determined to be appropriate by the
Authority for such interim purpose. It is understood and agreed that such interim
determination by the Authority for the purposes of this Section will not be binding
upon either party for any other purpose, and that, after the Authority has made a
final determination as to any time extension, revise the Progress Schedule in
accordance with the final decision.
The Contractor shall allow for inclement weather in the Baseline Schedule by incorporating
an activity titled “Rain Day Impact Allowance” as the last activity prior to the Substantial
Completion milestone. No other activities may be concurrent with it. The duration of the
Rain Day Impact Allowance activity will be based on Section 01 31 99, Period of
Performance.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 32 17
PHOTOGRAPHIC DOCUMENTATION
1.01 SUMMARY
This Section includes administrative and procedural requirements for the following:
A. Preconstruction photographs
A. Key Plan: Submit a key plan of the Project site and any buildings, with notation of
vantage points marked for location and direction of each photograph and video
recording. Indicate the elevation of construction. Include same information as
corresponding photographic documentation.
2. Format: Minimum of 1,600 by 1,200 pixels and 400 dpi, in unaltered JPG
format original files having the same aspect ratio as the sensor, uncropped,
date- and time-stamped, in a folder named by the date of the photographs,
and accompanied by a key plan file.
PART 2 - PRODUCTS
A. Digital Images: Provide images in JPG format, produced by a digital camera with
a minimum sensor size of 10 megapixels, and at an image resolution of not less
than 1,600 by 1,200 pixels and 400 dpi.
PART 3 - EXECUTION
A. General: Take photographs using the maximum range of depth of field, producing
images that are in focus so as to clearly show the Work. Photographs with blurry
or out-of-focus areas will not be accepted.
B. Maintain a key plan with each set of construction photographs that identifies each
photographic location.
C. Digital Images: Submit digital images exactly as originally recorded in the digital
camera, without alteration, manipulation, editing, or any modifications using
image-editing software.
1. Date and Time: Include date and time in file name for each image.
2. Field Office Images: Maintain one set of images accessible in the field
office at the Project site, available at all times for reference. Identify images
in the same manner as used for those submitted to the Engineer.
3. When utility pipes, conduits, and ducts are installed but not covered
F. Final Completion Construction Photographs: Take color photographs after the date
of Substantial Completion for submission as Project record documents.
2. Begin each video recording with the name of the Project, the Contractor's
name, the videographer's name, and the Project location.
2. Show existing conditions adjacent to the Project site before starting the
Work.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 32 33
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.01 SUMMARY
This Section includes requirements for the submittal schedule and procedural
requirements for submitting Shop Drawings, Product Data, Samples, administrative and
miscellaneous (non-administrative) work-related submittals.
1.03 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that
require the Authority’s responsive action. Action submittals are those submittals
indicated in individual Specification Sections as action submittals.
C. Plans and Procedures: Shall include, but are not limited to, narrative descriptions,
diagrams, equipment, procedures for excavation, demolition, site clearing,
maintenance of traffic, etc.
D. Certificates: Shall include, but are not limited to, certified material test reports,
certification of proper disposal of demolition materials, or tickets demonstrating
compliance with materials, tests or Specifications indicated.
F. Product Data: Shall include, but is not limited to, standard printed information on
materials, products and systems to be furnished by the Contractor for this Contract.
G. Shop Drawings: Shall include, but are not limited to, detailed manufacturing and
layout information, demonstrating the Contractor’s approach to meeting the intent
of the Plans and Specifications.
H. Samples: Include physical examples of materials either for limited visual inspection
or (where indicated) for confirmation, testing, and analysis by the Authority.
1.04 PATENTS
In the event that any patented article, material, or process is to be installed or used in the
performance of the Work as shown on the drawings or particular specifications thereof,
the Contractor shall pay the royalty chargeable and shall save, keep, and bear the
Authority harmless from (a) all damage, costs, and expenses by reason of any
infringement of the patent or any failure to pay the royalty chargeable for use thereof, or
(b) any loss to the Authority in the event that the Authority is enjoined from using such
patented article or material, or (c) the incidental damage caused by the loss of use and
damage to Authority property in removing same, and (d) the cost of replacing the article
or material the use of which is enjoined. It is further provided that the Bond for faithful
performance shall be deemed to expressly apply to this provision of the specifications.
A. The Contractor may not begin the work prior to delivery of the submittal schedule.
B. Coordinate the submittal schedule with the list of subcontracts, the Schedule of
Values, and the Contractor's construction schedule.
D. Final Submittal: Submit concurrently with the first complete submittal of the
Contractor's construction schedule. Submit a revised submittal schedule to reflect
changes in the current status and timing for submittals.
4. Name of Subcontractor
10. Float
1. Each submittal shall only contain items from one specification section, and
duplicate submittals will not be accepted.
5. The Contractor shall show his executed internal review and approval
marking. Submittals, which are received from sources other than through
the Contractor’s office or which have not undergone Contractor review, will
be returned marked "without action."
C. Processing Time: Allow time for submittal review, including time for resubmittals,
as follows. Time for review shall commence on the first full working day after the
Authority receives the submittal. No extension of the Contract Time will be
authorized because of failure to transmit submittals enough in advance of the Work
to permit processing, including resubmittals.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow
additional time if coordination with subsequent submittals is required. In the
event that Submittal is reviewed by a third party (including Railroads
Operators and authorities having jurisdiction), allow up to an additional 14
working days’ time for Authority’s response. The Authority will advise the
Contractor when a submittal being processed must be delayed for
coordination.
a. Project name
b. Date
c. Source (From:)
l. Remarks
m. Signature of transmitter
a. Project name
d. Manufacturer name
e. Product name
2. Name the file with its submittal number or another unique identifier,
including revision identifier. The file name shall use a project identifier and
the Specification Section number, followed by a decimal point and then a
sequential number (e.g., LNHS-061000.01). Resubmittals shall include an
alphabetic suffix after another decimal point (e.g., LNHS-061000.01.A).
F. Identify Applicable standards, ASTM, ACI, OSHA, etc. and identify options
requiring selection by the Authority.
H. Resubmittals: Make resubmittals in the same form and with the same number of
copies as the initial submittal.
2. Note the date and content of the revision in the label or title block, and
clearly indicate the extent of revision.
J. Use for Construction: Retain full copies of approved submittals on the Project Site.
Use only final submittals that are marked with approval notation from the
Engineer’s action stamp.
A. Normal Submittals:
B. Data for Commissioning: Authority will request specific information needed about
each piece of commissioned equipment or system. Information requested
includes, but is not limited to, the following:
B. The Contractor shall show his executed internal review and approval marking.
Submittals, which are received from sources other than through the Contractor’s
office or which have not undergone Contractor review, will be returned marked
"without action."
PART 2 - PRODUCTS
A. Any Work performed without an approved submittal will be done at the Contractor’s
own risk
B. Product Data: Collect information into a single submittal for each element of
construction and type of product or equipment. A Material Safety Data Sheet shall
be submitted for each product.
2. Mark each submittal clearly to show which products and options are
applicable.
k. Mill reports
b. Performance curves
a. Identification of products
b. Product Schedules
m. Design calculations
2. Sheet Size: Except for templates, patterns, and similar full-size drawings,
submit Shop Drawings on sheets at least 11 by 17 inches but no larger
than 24 by 36 inches.
D. Samples: Submit full-size units or Samples of the size indicated, prepared from the
same material to be used for the Work, cured and finished in the manner specified,
physically identical with the material or product proposed for use, and showing
the full range of color and texture variations expected. Samples include, but are
not limited to, the following: partial sections of manufactured or fabricated
components; small cuts or containers of materials; complete units of repetitively
used materials; swatches showing color, texture, and pattern; color range sets;
and components used for independent testing and inspection.
c. Sample source
1. State that the product complies with the respective Contract Specification
and Contract Drawing requirements.
3. Product Test Reports: Submit written reports indicating the current product
produced by the manufacturer complies with requirements in the Contract
Documents. Base reports on an evaluation of tests performed by the
manufacturer and witnessed by a qualified testing agency, or on
comprehensive tests performed by a qualified testing agency.
b. Date of evaluation
e. Description of product
g. Limitations of use
7. Field Test Reports: Submit reports indicating and interpreting results of field
tests performed either during installation of the product or after the product
is installed in its final location to verify compliance with requirements in the
Contract Documents.
a. Preparation of substrates
c. Sequence of installation
e. Required adjustments
PART 3 - EXECUTION
A. Review each submittal and check for coordination with other Work of the Contract
and for compliance with the Contract Documents. Note corrections and field
dimensions. Mark with an approval stamp before submitting to the Authority.
C. Approval Stamp: Stamp each submittal with a uniform approval stamp. Include
Project name and location, submittal number, Specification Section title and
number, name of reviewer, date of Contractor's approval, and statement certifying
that the submittal has been reviewed, checked, and approved for compliance with
the Contract Documents.
A. The Authority will not review submittals that do not bear the Contractor's approval
stamp, and will return such submittals without action.
1. The review is not conducted for the purpose of determining the accuracy
and completeness of other details, such as dimensions and quantities, or
for substantiating instructions for installation or performance of equipment
or systems, all of which remain the responsibility of the Contractor.
B. Action Submittals: The Authority will review each submittal, make marks to indicate
corrections or modifications required, and return it. The Authority will stamp each
submittal with an action stamp and mark the stamp appropriately to indicate the
action required.
C. Informational Submittals: The Authority will review each submittal and will
generally not return it (it will be returned it if it does not comply with requirements).
The Authority will forward each submittal to the appropriate party.
D. Partial submittals prepared for a portion of the Work will be reviewed when use of
partial submittals has received prior approval from the Authority.
F. Submittals not required by the Contract Documents may not be reviewed and may
be discarded.
A. Submittals reviewed by the Authority and returned to the Contractor will be marked
with one of the following designations:
1. No Exceptions Taken.
2. Approved as Noted.
4. Rejected.
5. No Action Taken.
B. The Contractor shall take responsibility for and bear all cost of damages, which
may result from the ordering of any material or from proceeding with any part of
the Work prior to being marked "No Exceptions Taken" or "Approved as Noted" by
the Authority.
C. Where drawings are stamped "Approved as Noted”, the Authority shall indicate the
corrected detail or information as required.
D. Submittals stamped “NO Exceptions Taken” do not relieve the Contractor from the
responsibility of performance of Work as intended in the Plans and Specifications.
B. If corrections to the submittals are required, the submittals will be returned to the
Contractor will be marked "Rejected, Resubmit”, or "Revise and Resubmit“ and the
required corrections shall be made on the re-submittal.
D. The Contractor shall notify the Authority prior to execution of any correction, which
constitutes a change of the Contract requirements indicated on the submittals.
B. Submittals made by the Contractor that are not required by the Contract
Documents or were not otherwise requested shall be designated “No Action
Taken.”
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 33 00
PART 1 - GENERAL
1.01 SUMMARY
This Section sets forth the procedures for Contractor work on or near track and track
structures.
A. The Contractor’s work on the track structure prior to returning the track to full
service, shall be protected by speed restrictions for train traffic consistent with the
direction of the Authority, who will interpret the current issue of the SCRRA Track
Maintenance Manual, and the Track Safety Standards of the FRA. The Contractor
shall comply with the SCRRA interpretation of all requirements relating to work on
track and track structures.
B. The Contractor shall abide by the instructions of the Authority, its authorized
inspectors, RWICs, watchmen, and other designated Authority work forces.
Returning the track to service after the Contractor’s work near an operating railroad
track, during construction on an interim basis only, shall be the sole responsibility
of the Authority at the end of the work window.
2. Any necessary inspection and testing of the system, before and after
replacement of the damaged equipment
D. If the location of underground signal equipment interferes with the work, refer to
Section 01 14 16, Coordination with SCRRA, for coordination requirements.
A. Refer to Section 01 14 00, Work Restrictions, for designated work windows for
each project location.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 35 15
PART 1 - GENERAL
1.01 SUMMARY
Work specified in this Section consists of initiating, maintaining, and supervising all safety
precautions and programs and assuring a safe Work Site and safe operations around
active tracks. The Contractor shall be solely responsible for ensuring that all Work
performed under the Contract is performed in strict compliance with all applicable Federal,
State, local occupational safety regulations and SCRRA rules and requirements adopted
to protect all operations. This includes the proper manner of protecting the tracks, signals,
fiber optic cables, pipe lines, other Property, and tenants or licensees upon, adjacent to,
across (under or over), and along SCRRA and Member Agency Property during the
construction or maintenance activities on or adjacent to Railway Property. This Work
includes furnishing, operating, maintaining, and utilizing safety equipment and providing
protective equipment, safeguards, and safety devices on construction equipment.
Comply with the provisions of all local, State, and Federal regulations; with all applicable
Specifications, standards, and recommended practices; and with Authority and Authority-
adopted policies, procedures and requirements. Where the State and Federal regulations
have differing requirements, the Contractor shall comply with that which is more stringent.
These requirements include but are not limited to:
1.04 SUBMITTALS
The Contractor shall submit to the Authority for review and approval the submittals listed
below. The Contractor shall obtain SCRRA approval of the following submittals prior to the
start of construction, or as specified in a Limited Notice to Proceed:
A. Site Specific Injury and Illness Prevention Program (IIPP) including a Site Specific
Emergency Action Plan, to be revised and resubmitted as conditions warrant. This
Program shall include details of procedures, equipment and training in accordance
with Cal OSHA requirements including work in confined spaces, lock out/tag out
and fall protection procedures to ensure that the Contractor's and sub-Contractor's
workers are properly protected. An Environmental Health and Safety Plan per
Section 01 35 44 may also be required prior to beginning Work.
C. Work Plans for all excavation for which a protective system is required by CCR
Title 8 Article 6. This includes plans and drawings for any ground support system
to be used during the excavation and the slopes and configurations of sloping or
benching systems. Any engineered shoring within the railroad load influence zone
shall be designed by a Professional Engineer, Structural or Civil, licensed in the
State of California.
F. All cranes and on-track equipment operated on the Project Site by the Contractor
and or Sub-Contractors of any tier require annual and four-year certifications. Any
crane subjected to upset, overloading, side pulling, shock loading or support
failure, shall be re-certified to allow further use.
B. The Contractor’s Safety Representative shall have no other duties unless those
duties are specified elsewhere or approved by the Authority. The Safety
Representative shall not be utilized in any other Authority Contract or any other
project without prior written consent from the Authority.
D. At Limited NTP, or the project kick-off meeting, the Authority shall provide contact
numbers for all entities to be contacted in case of emergency. This will include the
Chief Dispatcher, the Metrolink Sheriff's Dispatcher, signal emergencies and grade
crossing problems, and signal and communications cable locations.
2. The Contractor shall reproduce, and distribute to each employee during the
training session, the SCRRA On-Track Safety Manual for Roadway
Workers.
1. .
B. As identified in the IIPP, the Contractor shall provide job specific fall protection
from hazards such as: skylights (at any angle), floor and wall openings, leading
edges, and steel erection. Methods of protection may include: fixed systems
(guardrails, covers, nets, etc.) and personal fall arrest systems.
C. All equipment, tools and or other items used to complete the Work shall be
inspected by the Contractor to ensure compliance with applicable regulatory
standards. Equipment shall be used in accordance with the respective
manufacturer‘s design, directions, and intended use.
Testing equipment, as applicable to Work Site safety, shall conform to the requirements
of the California Code of Regulations, Title 8, Division of Industrial Safety, unless indicated
otherwise.
B. Contractor personnel shall wear hard hats, orange safety vests or orange T-shirts
with reflective strips, safety glasses, and safety shoes at all times while on the
Project.
During operations adjacent to live track, all Work within the foul zone of the live track or
adjacent track, or as directed by the RWIC must be stopped when trains are approaching
and equipment and employees moved to a safe distance from the tracks unless otherwise
approved. All Contractor equipment within the Authority Right of Way will stop Work when
trains are approaching.
PART 3 - EXECUTION
The Contractor is solely responsible for all construction means, methods, techniques, and
procedures and for coordinating all portions of the Work under the Contract. This shall
include the following:
B. The Contractor shall secure all Work areas by barricade in accordance with local
and State requirements as applicable at the end of each day. All excavations shall
be covered to prevent tripping hazard.
C. In the event the Authority discovers that the Contractor has created an unsafe
condition or has failed to restore the track to service at the specified time, the
Authority with its own forces may perform the remedial Work to secure the required
safety and train performance. Such remedial Work will be at the sole discretion of
the Authority; however, Contractor may perform such Work if agreed to by
Authority. If this action is required, the Authority may unilaterally terminate Work
under the Contract, and will pay only for the quantities of Work actually performed,
less the cost of Authority’s remedial Work. In the event Work is halted under this
circumstance, the Mobilization line item will not be paid. In the event that Work is
not halted, the Contractor must take immediate steps to correct the situation. There
will be no extra payment for Work required to correct unsafe conditions or to
promptly restore track to service. For purposes of this Section, an unsafe condition
is defined as creating a track condition which does not meet the FRA Track Safety
Standards for Class of Track, willful damage to facilities or material, or any other
unsafe condition for trains, employees, passengers or the public, at the sole
determination of the Authority.
D. Prior to operating cranes on the Site, all crane operators shall have successfully
completed testing that verifies the crane operator's ability to read and understand
the load chart for the equipment to be operated. This testing may be performed by
an independent certifying agency or a qualified member of the Contractor‘s
supervisory staff who is acceptable to the Authority, has a minimum of five years
heavy civil construction experience, and can satisfactorily demonstrate the ability
to read and understand load charts and rigging tables to the Authority when
requested, without prior notice. Written records of this testing shall be maintained
on the Site and made available to the Authority for review without prior notice. Re-
certification is required for any crane involved in an incident involving upset,
overloading, side pulling, shock loading, or support failure. Re-certification and
written acceptance by the manufacturer is also required for any modification to a
crane. All crane operators shall be licensed by the Authority having jurisdiction for
the equipment type to be operated and copies of said licenses shall be submitted
to the Authority. All crane operations where the load is beyond the direct view of
the operator shall be observed by a signal person who can directly observe the
load and be observed by the operator. The Contractor shall stop load movement
in the event the signal Person is unable to observe the load or fails to continuously
observe the load and signal the operator.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 35 23
PART 1 - GENERAL
1.01 SUMMARY
Contaminated and Hazardous Soils may be encountered during the Work. The Contractor
shall be solely responsible for ensuring that all Work performed when these Soils are
present complies with all applicable Federal, State, local occupational safety regulations
and SCRRA rules and requirements. In order to properly handle these types of soil, the
Contractor shall prepare and implement an Environmental Safety and Health Program and
require that all its Subcontractors perform excavation and handling of soils in full
compliance with the requirements of the Environmental Safety and Health Program.
C. California Code of Regulations (CCR) Titles 4, 8, & 22, the Code of Federal
Regulations (CRF) Title 29 and all applicable Code of Federal Regulations Titles.
1.03 PROCEDURE
If the Contractor encounters substances during performance of the Work that are
reasonably believed to be potentially chemically-impacted as defined in Section 31 20 50,
the Contractor shall notify the Authority immediately, submitting written documentation of
the incident and notification within 24 hours. Contractor will proceed with work in
accordance with Section 31 20 50, Removal and Disposal of Contaminated Soils.
Excavation in the immediate area of the potentially chemically-impacted soil shall be
suspended, and work shifted to another location until authorization to resume is received.
Equitable adjustments, if any, for time lost or costs incurred due to the inability to relocate
the work as a result of such encounters will be made in accordance with Contract Change
Order Procedures. The Authority reserves the right to use other labor forces for
exploratory work to determine the nature and extent of the potentially chemically-impacted
soil and to remove the substances from the area.
For lead-containing materials, the Contractor shall submit a Work plan to the Authority for
review and approval prior to any demolition work. All Work shall be done in full compliance
with requirements of the California Code of Regulations, Title 8 specifically Section 5192,
Hazardous Waste Operations and Emergency Response (HAZWOPER).
1.04 SUBMITTALS
C. Certificates of training for the Site Safety and Health Officer: minimum initial 40-
hour HAZWOPER training, 8-hour annual refresher, 8-hour Site Supervisor
training, respiratory protection and fit-testing, medical clearance, experience, and
credentials.
E. The Work Plan for removal of lead-containing material shall include the following:
PART 2 - PRODUCTS
2.01 MATERIALS
PPE and monitoring equipment shall conform to requirements set forth by CAL/OSHA,
Federal-OSHA, and the Contractor’s Environmental Safety and Health Program.
Contractor shall provide high-efficiency particulate air (HEPA) filters for persons working
on lead-containing materials.
PART 3 - EXECUTION
3.01 PREPARATION
B. The Contractor will be responsible for performing soil monitoring and sampling for
disposal purposes, with oversight by the Authority, as specified in Section 31 20
50. The Contractor shall be responsible for loading, unloading, and transporting all
soils to the designated area. The contaminated and clean soils shall be stored in
separated piles. The designated area shall be protected with visqueen sheets
covering the ground and fenced off to prevent trespassing. The soils shall be
covered with visqueen sheets prior to legally disposing of them from the site. The
Contractor will be responsible for analyzing soil, as well as for trucking and
disposing of the contaminated soil accordingly. The Contractor shall be
responsible for loading contaminated soil into trucks furnished by the Contractor.
C. Designate a full-time Site Safety and Health Officer to recognize hazards and
implement and manage the Environmental Safety and Health Program. The Safety
and Health Officer can be a Safety Engineer, provided the individual is qualified to
conduct air monitoring and identify environmental hazards, and meets all training
requirements set forth in 8 CCR 5192 (e), in addition to the qualifications set forth
in the Construction Safety and Security Manual. As a minimum, the Safety and
Health Officer shall (a) monitor air quality and hazards to personnel and the Work
area during removal of lead-containing material and excavation and handling of
chemically-impacted and/or hazardous waste soil and groundwater, and (b) assign
PPE and other equipment necessary for the implementation of the Safety and
Health Program.
E. Supply high efficiency particulate air (HEPA) filters for persons working on removal
of lead-containing materials.
F. The Contractor is responsible for any delays associated with lack of preparation,
PPE, trained and qualified personnel.
3.02 PERFORMANCE
B. The Contractor will be responsible for performing soil monitoring and sampling for
disposal purposes, with oversight from the Authority, as specified in Section 31 20
50. If the sampled soil is found to be clean, the Contractor shall dispose of it in the
same manner and location as used for other clean soil removed from the site. The
Contractor shall be responsible for loading, unloading, and transporting all soils to
the designated area. The contaminated and cleans soils shall be stored in separate
piles. The designated area shall be protected with visqueen sheets covering the
ground, and fenced off to prevent trespassing. The soils shall be covered with
visqueen sheets prior to legally disposing of them from the site. The Contractor will
be responsible for analyzing the soil, as well as for trucking and disposing of the
contaminated soil accordingly. The Contractors shall be responsible for loading
contaminated soil into trucks furnished by the Contractor.
F. The wet method for removal of lead-contained materials shall be used to prevent
dust. Lead dust shall be properly disposed of. Air monitoring shall be performed
before, during, and after each lead-related activity. A third party without conflict of
interest with the Contractor shall conduct the air and clearance monitoring. Surface
clearance monitoring shall be conducted after completion of the removal of lead
materials. The purpose of the air monitoring is to ascertain that the building air
quality is maintained during and after the completion of the Project. All air
monitoring results shall be submitted to the Authority’s Corporate Safety
representative for review within 24 hours of receipt from the laboratory.
G. The Contractor is responsible for the safety and health of its employees and its
Subcontractors. The Contractor shall conduct air monitoring to ensure compliance
with monitoring requirements under the Environmental Safety and Health
Program, the Site-Specific Safety and Health Plan, CAL/OSHA, and any other
local, state, or federal requirements.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 35 44
PART 1 - GENERAL
1.01 SUMMARY
This Section includes general protection and treatment procedures for designated historic
spaces, areas, rooms, and surfaces in the Project and the following specific work:
B. Bird-excrement removal
1.03 DEFINITIONS
K. Refinish: To remove existing finishes to base material and apply a new finish to
match the original, or as otherwise indicated.
M. Remove: Specifically for historic spaces, areas, rooms, and surfaces, the term
means to detach an item from existing construction to the limits indicated, using
hand tools and hand-operated power equipment, and legally dispose of it off-site,
unless indicated to be salvaged or reinstalled.
N. Repair: To correct damage and defects, retaining existing materials, features, and
finishes while employing as little new material as possible. This includes patching,
piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials.
O. Replace: To remove, duplicate, and reinstall entire item with new material. The
original item is the pattern for creating duplicates unless otherwise indicated.
Q. Reproduce: To fabricate a new item, accurate in detail to the original, and in either
the same or a similar material as the original, unless otherwise indicated.
U. Salvage: To protect removed or dismantled items and deliver them to the Authority
ready for reuse.
W. Strip: To remove the existing finish down to base material, unless otherwise
indicated.
A. Historic items, relics, and similar objects—including but not limited to cornerstones
and their contents, commemorative plaques and tablets, antiques, and other items
of interest or value to the Authority that may be encountered during removal and
dismantling work—remain the Authority's property. Carefully dismantle and
salvage each item or object.
1.05 SUBMITTALS
A. Construction Schedule for Historic Treatments: Indicate for the entire Project the
following for each activity to be performed in historic spaces, areas, and rooms,
and on historic surfaces:
E. Historic Treatment Program: Prepare a written plan for historic treatment for the
whole Project, including each phase or process and protection of surrounding
materials during operations. Describe in detail materials, methods, and equipment
to be used for each phase of Work. Show compliance with indicated methods and
procedures specified in this and other Sections.
1. Dust and Noise Control: Include the locations of proposed temporary dust-
and noise-control partitions and means of egress from occupied areas
coordinated with continuing on-site operations and other known Work in
progress.
2. Debris Hauling: Include plans clearly marked to show debris hauling routes,
turning radii, and locations and details of temporary protective barriers.
F. Fire-Prevention Plan: Prepare a written plan for preventing fires during the Work,
including placement of fire extinguishers, fire blankets, rag buckets, and other fire-
prevention devices during each phase or process. Coordinate the plan with the
Authority's fire-protection equipment and requirements. Include each fire watch's
training, duties, and Authority to enforce fire safety.
b. Allow a waiting period of not less than seven days after completion
of removal work to permit a study of mockup for deleterious effects.
1. Clean only loose debris from salvaged historic items unless more extensive
cleaning is indicated.
1. Repair and clean historic items as indicated and to functional condition for
reuse.
2. Pack or crate items after cleaning and repairing; cushion against damage
during handling. Label contents of containers.
D. Storage and Protection: When taken from their existing locations, catalog and store
historic items within a weather-tight enclosure where they are protected from
wetting by rain, snow, condensation, or ground water, and from freezing
temperatures.
C. Conditions existing at the time of inspection for bidding purposes will be maintained
by the Authority as far as practical, unless otherwise indicated in the Contract
Documents.
D. Notify the Authority of discrepancies between existing conditions and the Contract
Documents before proceeding with removal and dismantling Work.
1. Proceed with the Work only when forecasted weather conditions are
favorable.
b. Do not perform exterior wet work when the air temperature is below
40 F.
2. Perform cleaning and rinsing of the exterior only during daylight hours.
1.09 COORDINATION
Coordinate historic treatment procedures in this Section with public circulation patterns at
the Project site. Some Work is near public circulation patterns and active railroad tracks.
Public circulation patterns cannot be closed off entirely, and in places can be only
temporarily redirected around small areas of Work. Railroad traffic will not be stopped.
Plan and execute the Work accordingly.
PART 3 - EXECUTION
3.01 NOTIFICATION
1. Hand-held power tools and cutting torches are permitted only as submitted
in the historic treatment program. They must be adjustable so as to
penetrate or cut only the thickness of material being removed.
2. Pry bars over 18 inches long and hammers weighing over 2 pounds are not
permitted for dismantling Work.
3.03 EXAMINATION
C. Perform surveys as the Work progresses to detect hazards resulting from historic
treatment procedures.
A. Ensure that supervisory personnel are on site and on duty when historic treatment
Work begins and during its progress.
1. Use only proven protection methods, appropriate to each area and surface
being protected.
4. Contain dust and debris generated by removal and dismantling work and
prevent it from reaching the public or adjacent surfaces.
6. Protect floors, paving, and other surfaces along haul routes from damage,
wear, and staining.
D. Comply with each product manufacturer's written instructions for protections and
precautions. Protect against adverse effects of products and procedures on people
and adjacent materials, components, and vegetation.
F. Existing Drains: Prior to the start of Work in an area, test the drainage system to
ensure that it is functioning properly. Notify the Authority immediately of inadequate
drainage or blockage. Do not begin Work in an area until the drainage system is in
working order.
1. Prevent solids such as stone or mortar residue from entering the drainage
system. Clean out drains and drain lines that become sluggish or blocked
by sand or other materials resulting from historic treatment work.
2. Protect drains from pollutants. Block drains or filter out sediments, allowing
only clean water to pass.
G. Existing Roofing: Prior to the start of Work in an area, install roofing protection
where indicated on the Contract Documents.
B. Cover adjacent surfaces with protective materials that are proven to resist
chemicals selected for the Project unless chemicals being used will not damage
adjacent surfaces, as indicated in the historic treatment program. Use covering
materials and masking agents that are waterproof and UV-resistant, and that will
not stain or leave residue on surfaces to which they are applied. Apply protective
materials according to the manufacturer's written instructions. Do not apply liquid
masking agents or adhesives to painted or porous surfaces. When no longer
needed, promptly remove protective materials staining.
D. Neutralize and collect alkaline and acid wastes and legally dispose of them off of
the Authority's property.
E. Collect and dispose of runoff from chemical operations by legal means and in a
manner that prevents soil contamination, soil erosion, undermining of paving and
foundations, damage to landscaping, or water penetration into structure interior.
1. Remove and keep the area free of combustibles, including, rubbish, paper,
waste, and chemicals, except to the degree necessary for the immediate
Work.
3. Prohibit smoking by all persons within the Project Work and staging areas.
1. Obtain the Authority's approval for operations involving use of open flame
or welding or other high-heat equipment. Notify the Authority at least 72
hours before each occurrence, indicating the location of such Work.
4. Use fireproof baffles to prevent flames, sparks, hot gasses, or other high-
temperature material from reaching surrounding combustible material.
5. Prevent the spread of sparks and particles of hot metal through open
windows, doors, holes, and cracks in floors, walls, ceilings, roofs, and other
openings.
C. Fire Extinguishers, Fire Blankets, and Rag Buckets: Maintain fire extinguishers,
fire blankets, and rag buckets for disposal of rags with combustible liquids.
Maintain each as suitable for the type of fire risk in each work area. Ensure that
nearby personnel and the fire watch are trained in fire-extinguisher and blanket
operation.
A. Ensure that supervisory personnel are present when historic treatment work
begins and during its progress.
F. Identify new and replacement materials and features with permanent marks hidden
in the completed work to distinguish them from original materials. Record a legend
of identification marks and the locations of the items on Record Drawings.
B. Perform work in accordance with the historic treatment program and approved
mockups.
2. Perform cutting by hand or with small power tools wherever possible. Cut
holes and slots neatly to size required, with minimum disturbance of
adjacent work.
4. Do not drill or cut columns, beams, joints, girders, structural slabs, or other
structural supporting elements, without having the Contractor's
professional engineer's written approval for each location before such work
is begun.
1. Use only dismantling tools and procedures within 12 inches of the historic
surface. Do not use pry bars. Protect the historic surface from contact with
or damage by tools.
2. Unfasten items to be removed, in the opposite order from which they were
installed.
4. Dismantle anchorages.
2. Use only nonmetallic tools such as plastic spatulas and brushes with
natural fiber or nylon bristles.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 35 91
QUALITY REQUIREMENTS
PART 1 - GENERAL
1.01 SUMMARY
B. Testing and inspecting services are required to verify compliance with specified or
indicated Work requirements. These services do not relieve the Contractor of
responsibility for compliance with Contract Documents requirements.
C. Specific tests and inspection requirements are not specified in this Section but
rather indicated or included elsewhere in the Contract Drawings (Plans) and
Specifications.
B. Requirements for the Contractor to provide quality assurance and quality control
services required by the Authority, or authorities having jurisdiction, are not limited
by provisions of this Section.
C. Specified tests, inspections and related actions do not limit Contractor’s other
quality-assurance and quality-control procedures that facilitate compliance with the
Contract Documents requirements.
1.03 DEFINITIONS
D. Preconstruction Testing: Tests and inspections that are performed specifically for
the Project, before products and materials are incorporated into the Work in order
to verify performance or compliance with specified criteria.
F. Source Quality Control Testing: Tests and inspections that are performed at the
source (e.g., plant, mill, factory, or shop).
G. Field Quality Control Testing: Tests and inspections that are performed on-site for
installation of the Work and for completed Work.
C. Items indicated on the Contract Drawings (Plans) but not included in the
Specifications, or included in the Specifications but not indicated on the Plans,
shall have the same effect as if indicated or included in both the Plans and
Specifications.
A. Comply with all applicable requirements of the laws, codes, ordinances, and
regulations of Federal, State, and Municipal authorities having jurisdiction, and
obtain necessary approvals from all such authorities.
A. Shop Drawings
A. Contractor Quality Control (CQC) Plan: Submit a formal plan detailing Contractor’s
quality assurance and quality control activities and responsibilities. Submit in a
format acceptable to the Authority. The CQC Plan is due within 15 calendar days
following receipt of Award.
p. Prior to welding.
B. Manufacturer Qualifications
C. Fabricator Qualifications
D. Installer Qualifications:
F. Specialists
2. Submit specimens in a timely manner with sufficient time for testing and
analyzing results to prevent delaying the Work.
4. Build site-assembled test assemblies and mockups using installers who will
perform the same tasks for the completed Work.
L. Mockups: Before installing portions of Work requiring mockups, build mockups for
each form of construction and finish required to comply with following
requirements, using materials indicated for completed Work:
2. Notify Resident Engineer seven (7) days in advance of dates and times
when mockups will be constructed.
5. Allow seven days for initial review and each re-review of each mockup.
A. Contractor Responsibilities: Quality Control tests and inspections shall be the sole
responsibility of the Contractor. The Contractor shall perform additional quality
control activities necessary to verify that the Work complies with specified
requirements.
E. Testing Agency Responsibilities: Testing Agency shall cooperate with all parties in
performance of Testing Agency’s duties. Testing Agency shall provide qualified
personnel to perform required tests and inspections.
2. Determine the location from which test samples will be taken and in which
in-situ tests are conducted.
3. Conduct and interpret tests and inspections, and state in each report
whether the tested and inspected work complies with or deviates from the
specified requirements.
B. Notify the Authority at least 48 hours in advance of time when Work that requires
testing or inspecting will be performed. Also provide the following in support of
testing and inspection services:
5. Preliminary design mix proposed for use for material mixes that may
require production control by testing agency.
6. Security and protection for samples and for testing and inspecting
equipment at Project site.
A. The Authority shall approve the source of supply of each type of the materials
supplied by the Contractor before the Contractor or subcontractor purchases or
delivers these materials to the Project. Promptly after receiving the Contract award,
the Contractor shall notify the Authority of all proposed material sources. If it is
found after trial that sources of supply previously approved do not produce uniform
and satisfactory products, or if the product from any source proves unacceptable
at any time, the Contractor shall furnish materials from other sources as approved
by the Authority.
PART 3 - EXECUTION
The Contractor shall provide the Authority with full access to the Work and reasonable
time for inspection for ascertaining whether or not the Work is performed in accordance
with the requirements and intent of the Contract. No Work shall be covered or materials
used without making the Work products or materials available for inspection by the
Authority and any Work that is required to be uncovered, removed or replaced shall be at
the Contractor's expense. Inspection will not relieve the Contractor from the responsibility
of the quality of this Work and obligation to perform the Work in accordance with the
requirements of these Contract Documents.
A. All materials and every process of manufacture and construction shall be subject
to inspection at all times. The Authority and his designated representatives shall
have free access to all such operations. The Contractor shall furnish necessary
materials and the Authority shall have the right to select suitable samples of
materials for testing or examination which the Contractor shall supply without
charge. In case such samples must be shipped to some other point for inspection
or testing, the Contractor shall box or crate samples as necessary and shall deliver
them to points designated for shipment without charge. Omission of inspection
shall not relieve the Contractor of its obligations to perform the Work required by
the Plans and Specifications. Non-conforming or defective materials not in
compliance with Contract requirements shall be removed promptly from the vicinity
of the Worksite, and the Contractor, at its sole expense, shall promptly remove,
reconstruct, replace, and make good any defective Work. Oversight or error in the
judgment of inspectors, or previous acceptance of the Work shall not relieve the
Contractor from the obligation to correct any defects whenever discovered at the
Contractor’s sole expense. Authority and the other authorized agencies may
inspect at any time the Contractor’s production of Goods at off-site facilities,
including any manufacturer's plant.
B. Adequate facilities shall be made available for the necessary inspections and free
access to all parts of the Work shall be available at all reasonable times. The
Contractor shall have appropriate provisions inserted into each Subcontract it
enters into providing for document, facility or in-plant Inspection by the Authority.
C. In the event the Contractor does not correct nonconforming Work or remove
rejected materials within a reasonable time fixed by written notice, the Authority
may direct removals and corrections be performed by other Contractors. The
charges for such removals and corrections shall be deducted from the Contractor’s
payment due under this Contract or may be paid for by the Contractor’s bonds held
for this Contract.
D. All inspection by the Engineer is for the protection of the Authority and its interest
and shall not relieve the Contractor of responsibility for performing work in
accordance with the Contract Documents. After completing the Work, a final
inspection will be made and any previous inspection or acceptance will not
preclude rejection at the time of final inspection for any item that is not satisfactory
to the Authority or not in accordance with the Contract Documents.
E. In the event, within such period of time as may be prescribed by law or by the terms
of any applicable special warranty required by the Contract Document, whichever
is longer, any of the Work is found to be defective or not in accordance with the
Contract Documents, the Contractor shall correct it promptly after receipt of a
written notice from the Authority. This obligation shall survive acceptance of the
Work or termination of the Contract. In the event the Authority prefers to accept or
not require correction of defective or nonconforming Work, the Authority may do
so instead of requiring its removal and correction, in which case the Authority shall
determine an appropriate sum to be deducted from the Contract price or
otherwise charged against the Contractor, which determination shall be final and
binding upon the Parties. Such monetary adjustment shall be effected whether or
not final payment has been made.
F. All defective Work, which has been rejected, shall be remedied or removed and
replaced by the Contractor at its own expense in a manner acceptable to the
Authority.
G. The Authority may charge the Contractor for any additional costs it incurs for tests
and Inspections, wherever and whenever Work is not ready at the time indicated
by the Contractor’s notice or when an additional reinspection is necessitated by
prior rejection.
H. The Authority will have access, at all reasonable times, to the Contractor's
documents, calculations, supporting materials, data, and information concerning
the Work, including computer programs and printouts, which supportive
information Authority may determine is required to review the Work properly and
expeditiously.
A. Contractor shall prepare a record of tests and inspections, and shall include the
following:
B. Maintain log at Project site. The Contractor shall post changes and modifications
as they occur. The Contractor shall provide access to the test and inspection log
for the Authority's reference during normal working hours. No notice will be
required for Authority’s access to Contractor’s test and inspection the logs and
associated documents.
B. The Contractor shall provide materials and comply with installation requirements
specified in other Specification Sections. Restore patched areas and extend
restoration into adjoining areas with durable seams that are as nearly invisible as
possible.
D. Repair and protection are the sole responsibility of the Contractor, regardless of
the assignment of responsibility for quality-control services.
If any Work provided by the Contractor is determined to be deficient, the Authority shall
provide written notice to the Contractor of enumerating such deficiencies, and may
thereafter do one or more of the following:
A. Require the Contractor to promptly segregate and remove rejected Work from the
Project at Contractor’s own expense and without any extension of Contract Time.
E. Terminate the Contract and obtain the remedies provided for therein.
A. Work of this Section is considered incidental to Work under other payment items
and no separate measurement or payment will be made to the Contractor for Work
of this Section;
B. The Testing Agency engaged by Authority for testing and inspection will be
provided and paid by the Authority. All other services of this Section will be paid
by the Contractor.
END OF SECTION 01 40 00
PART 1 - GENERAL
1.01 SUMMARY
This Section outlines requirements and provisions to which the Contractor shall provide
professional construction staff and equipment capable of safely executing the Work
required by these Contract Documents part of which are on an operating railroad system,
with little or no disruption to the passenger/commuter and freight operations, as well as
other public facilities.
B. SCRRA: Track Maintenance Manual, FRA: Title 49 CFR Part 213 and Part 214
1.04 SUBMITTALS
A. The Contractor shall submit the resumes for all personnel listed herein to the
Authority within 15 days after the Limited Notice to Proceed. Each resume shall
provide sufficient detail to demonstrate compliance with the appropriate
specifications. Submit the number of each classification of employee to be
assigned to the Work and the duration of their assignments.
C. The Contractor shall submit a list of the equipment proposed to be used to the
Authority for approval, within 15 days after the Award. This list shall have sufficient
detail to demonstrate compliance with the appropriate Specification sections,
regulatory authorities, and Railroad Operators.
D. All equipment other than railroad track and ballast equipment shall be equipped
with multi tonal directional “white noise” backup alarm that complies with OSHA
Regulation 1926.601(b)(4). The Contractor shall submit a list of the equipment
proposed to be used to the Authority for approval prior to NTP.
F. The Contractor or their designated on-site personnel shall have attended a South
Coast Air Basin Fugitive Dust Control Class within the last two years (SCAQMD
Rule 403).
A. The Contractor shall have a Railroad Construction Project Manager who will
manage and coordinate the overall aspects of the track, station, grade crossing,
site civil, systems, and bridge construction. The Railroad Construction Project
Manager’s qualifications and experience must include the following:
5. The ability to read and understand track, bridge, station, construction plans
and specifications, and SSWPs, and to develop and work from construction
schedules.
C. This Railroad Construction Project Manager shall have the necessary authority to
receive and promptly execute instructions and orders from the Authority or its
authorized representatives. The Project Manager shall not be replaced without
advance approval by the Authority. Any replacement Project Manager shall be
subject to the approval of the Authority.
A. The Contractor shall have at least one Railroad Track Construction Manager who
will direct the day-to-day operations of the Track Foreman and assist in managing
and coordinating the overall aspects of the track, station, grade crossing, and
bridge construction. The Railroad Track Construction Manager’s qualifications and
experience must include the following:
5. The ability to read and understand track, site civil, systems, and
construction plans.
7. The ability to identify FRA or other defects in track for the given class, and
to prescribe appropriate remedial measures.
C. The Railroad Track Construction Managers shall be solely dedicated to this Project
and not permitted to work on other projects during any track or associated
construction work.
A. The Contractor shall have a MCM to plan, direct, and coordinate the activities of
the Contractor (including all Subcontractors) in performance of the Work to assure
compliance with Contract terms and conditions, applicable regulations, SCRRA
standards, , coordination with other Authority Contractors and public agencies, and
provision of quality railroad service by the Authority. Serves as the point of contact
for Authority staff for all matters relating to the Agreement and performs regular
consultation and planning meetings with the Authority's Manager of Maintenance.
The MCM shall review, revise, and develop contract submittal documents including
annual budgets and work plans, training schedule and curriculums, CTOs,
inspections, and invoices. The MCM shall assist training managers in developing
training schedule and curriculum and shall supervise, promote, manage, transfer,
and discipline Contractor staff and arrange with Authority for replacement
personnel in the event of vacancies. The MCM is required to respond immediately
to extraordinary conditions and to initiate inspections or repairs to track or facilities
as required to maintain Authority facilities and operations.
10. Knowledge of the time for completion and the cost of repair for track and
Right-of-Way facilities, and the ability to make value judgments regarding
economic repair and/or replacement of these facilities.
12. Ability to read and interpret drawings, plans, and specifications for railroad
track and civil construction and to inspect track and supervise the work of
others for compliance with these documents.
13. Ability to complete work under time pressures and to maintain composure
under the stress of emergency situations.
15. Must have, or obtain within six weeks of Limited NTP, a valid California
driver license with no more than three moving violations and no Driving
Under the lnfluence (DUI) in any state within the last three years.
17. Ability to work outdoors in all weather conditions, to lift objects weighing a
minimum of 50 Ibs. and must have the ability to distinguish colors and to
hear warning signals and radio and telephone devices.
18. Shall be on-call 24 hours each day, 365 days a year, with allowances for
vacations, sick leave, and related time off with duties assigned to the
Assistant Contract Manager when off duty.
A. The Contractor shall have at least one Railroad Bridge Construction Manager who
will direct the construction of all railroad bridges and culverts and assist in
managing and coordinating the track and other work in the immediate vicinity of
the bridge and culvert work. The Rail Bridge Construction Manager’s qualifications
and experience must include the following:
8. Must have, or obtain within six weeks of Start Date, a valid California Class
"A" driver’s license with no more than three moving violations and no DUl’s
in any state within the last three years.
10. Ability to work outdoors in all weather conditions, to lift objects weighing a
minimum of 50 Ibs and must have the ability to distinguish colors and to
hear warning signals and radio and telephone devices.
The Contractor shall provide qualified Railroad Machine Operators and the Contractor will
not be allowed to operate any equipment within the Authority Right-of-Way until the
following requirements are met:
A. Railroad Machine Operators qualifications and experience must include the
following:
a. Ballast Regulator
b. Backhoe Tractor
c. Ballast Stabilizer
C. Must have a valid California Class “CA” driver’s license with no more than three
moving violations and no DUI’s in any state within the last three years.
E. Ability to work outdoors in all weather conditions, to lift objects weighing a minimum
of 50 lbs. and must have ability to distinguish colors and to hear warning signals
and radio and telephone devices.
The Contractor shall have a Track Foreman with the following qualifications and
experience:
B. Knowledge of FRA standards, and qualified under FRA Track Safety Standards,
Part 213.7, and SCRRA Track Maintenance, Right-of-Way and Structures
Engineering Instructions.
C. Previous qualification with a railroad to obtain track and time and working time; to
place and remove restrictions for train movement; and the ability to qualify under
all Authority requirements.
F. Five years’ railroad track experience, with a minimum two years’ track foreman
experience.
H. Must have a valid California Class “CA” driver’s license with no more than three
moving violations and no DUI’s in any state within the last three years.
J. Ability to work outdoors in all weather conditions, to lift objects weighing a minimum
of 50 lbs. and must have ability to distinguish colors and to hear warning signals
and radio and telephone devices.
B. Railroad Track Equipment Repairer qualifications and experience must include the
following:
5. Must have a valid California Class "A" driver’s license with no more than 3
moving violations and no DUl’s in any state within the last 3 years.
A. The Contractor shall have a Railroad Track Equipment Repairer Helper (Helper)
to work under the supervision of the Railroad Track Equipment Repairer. The
Helper may work independently or as a member of a crew as directed only for the
purpose of servicing and maintaining equipment.
6. Must have, or obtain within two weeks of Start Date, a valid California Class
"A" driver's license with no more than 3 moving violations and no DUls
within the last 3 years.
A. The Contractor shall provide Railroad Track Welder with the following
qualifications and experience:
B. The Contractor shall provide Railroad Track Welder trained and qualified to
perform the following procedures:
7. Five years’ railroad track experience with a minimum two years of track
welding experience
C. Railroad track welders shall be available as needed to the Project for the duration
of track-welding activities.
The Contractor shall provide Mandatory Track and Structures Laborer/Welder Helper as
needed for the project with the following qualifications and experience:
D. All Welder Helpers and 50 percent of the Track and Structures Laborers must have
a minimum of one year of general track construction or maintenance experience.
C. Must have a valid California Class “CA” driver’s license with no more than three
moving violations and no DUI’s in any state within the last three years.
E. Ability to work outdoors in all weather conditions, to lift objects weighing a minimum
of 50 lbs. and must have ability to distinguish colors and to hear warning signals
and radio and telephone devices.
B. Signal construction and installation personnel shall work under the Authority of the
Signal Engineer. The Contractor’s signaling construction forces shall work under
the Authority of a Signal Engineer.
1. Signal Engineer shall plan, direct, and oversee the adjustment, installation,
and testing of signal related work and shall coordinate signal work with
related track construction work and roadway work.
2. Signal Engineer shall be responsible for all work under his charge and must
have the Authority to remove any personnel from the project who are not
performing the work in a satisfactory manner. The Signal Engineer shall
obtain, review, and maintain documentation of the required minimum
experience, a copy of the Electrician’s license(s), and a record of wage rate
paid for each Signal Electrician that performs Signal or Crossing Warning
System work prior to that Electrician starting any Signal related work. This
documentation shall be available for review by the Authority at all times
upon request.
C. Signal Engineer shall direct and organize the performance of all tests on signaling
equipment and systems, prior to requesting the release of systems for service. The
Signal Engineer shall be responsible to ensure that all applicable test
documentation other than that documentation provided by the Authority, is
completed prior to, or immediately after, in-service testing is completed. The Signal
Engineer shall demonstrate experience in the philosophy, application, and testing
requirements of the various signaling systems. The Signal Engineer shall have a
minimum of 10 years signal supervisory or management related experience on a
Class I railroad, or commuter railroad comparable to SCRRA. The Signal Engineer
shall also demonstrate knowledge of the governing General Code of Operating
Rules, including CPUC and FRA regulations and procedures. This demonstration
shall be by interview of the Signal Engineer by the Authority prior to
commencement of any work that may affect the signal system. The Work of this
project includes working within tight windows on a live railroad consisting of freight
trains, inter-city passenger trains, and SCRRA commuter trains. Candidate shall
have a similar level of experience. The Authority's decision concerning the
candidate's qualifications will be final. The Contractor shall not begin any signaling
related Work prior to obtaining Authority’s approval of each Signal Engineer. The
Contractor shall obtain Authority approval of and provide additional Signal
Engineers as required depending upon the level and type of Work being
performed. Propose alternate personnel if the original candidate is found
unacceptable.
D. The Contractor shall propose alternate personnel if the original candidate is found
unacceptable. Previous qualification as a Signal Engineer on other SCRRA
projects does not constitute qualification as a Signal Engineer for this Contract.
E. The Authority reserves the right to disqualify any Signal Engineer, at any time
during the course of the Work. This right is at the sole discretion of the Authority
and is not subject to protest or appeal.
C. The Contractor shall propose alternate personnel if the original candidate is found
unacceptable. Previous qualification as a Signal Manager on other SCRRA
projects does not constitute qualification as a Signal Manager for this Contract.
D. The Authority reserves the right to disqualify any Signal Manager at any time
during the course of the Work. This right is at the sole discretion of the Authority
and is not subject to protest or appeal.
E. Must have a valid California Class “CA” driver’s license with no more than three
moving violations and no DUI’s in any state within the last three years.
B. The Signal Electricians shall have a minimum 1,000 hours of experience in the
wiring and installation of railroad signal and grade crossing warning system
circuits, components, control equipment and associated devices including their
primary and backup power supply systems. Signal Electricians shall perform the
wiring, labeling and connection/continuity/resistance testing, as appropriate, of all
railroad signal and grade crossing warning system circuits, components, control
equipment and associated devices including their primary and backup power
supply systems. All Signal Electricians shall be licensed Journeyman or Inside
Electricians or equal. Signal Electricians shall be paid at the prevailing wage rate
for the locality of the construction.
C. The Contractor shall propose alternate personnel if the original candidate is found
unacceptable. Previous qualification as a Signal Electrician on other SCRRA
projects does not constitute qualification as a Signal Electrician.
D. The Authority reserves the right to disqualify any Signal Electrician at any time
during the course of the Work. This right is at the sole discretion of the Authority
and is not subject to protest or appeal.
PART 3 - EXECUTION
A. Once personnel are deemed acceptable by the Authority, the Authority will make
arrangements to provide the training and testing required for personnel to be
qualified under subject areas described in Part 1 of this Specification Section.
2. The Contractor will be notified of test results in writing. The Authority will
make arrangements for retesting if personnel fail the initial test. Retesting
of the course material will be allowed one time within 55 days after the full
NTP.
C. The Contractor shall provide the required personnel in accordance with Part 1. If
the Contractor fails to provide the appropriate personnel due to a substitution or if
the personnel described in Part 1 are not available within 30 days as specified in
these Contract Documents, and the Contractor has not acted in good faith to
secure replacement personnel, the Authority is entitled to implement one of the
following options, at his sole discretion:
D. Option 2: Allow the Contractor’s operation to proceed and deduct $500 per day for
each operation that was under the direct supervision of the subject personnel. If
this option is used, this deduction shall be taken until the construction operation is
completed or until the appropriate personnel are provided.
E. Immediately remove from the Work, when so ordered by the Authority, and not re-
employ on any of the Work, without written permission from the Authority, any
Contractor or SubContractor employee doing unsafe, improper, and defective
Work; who, in the Authority’s judgment, refuses or neglects the direction of the
Authority given to the Contractor; who is deemed incompetent or disorderly; or who
commits any trespassing on any public or private property in the vicinity of the
Work.
A. The Contractor shall make the railroad construction equipment available for
inspection a minimum of 30 days prior to its first use on the project, or as otherwise
agreed upon with the Authority.
B. The Contractor shall make arrangements for initial inspection of the equipment by
the Authority. The railroad construction equipment shall not be operated on the
Authority’s Operating System until the initial inspection and approval is completed.
C. The Contractor shall inspect all railroad construction equipment daily to ensure
compliance with manufacturer instructions, FRA regulations, CPUC regulations,
and the Authority’s Operating and Safety Rules. The equipment not in compliance
shall not be used on the Authority’s Operating System.
D. The Contractor shall provide the required equipment described in Part 1 to perform
the work specified in these Contract Documents. Permission given by the Authority
to use any particular methods, equipment, or appliances shall not be so construed
to relieve the Contractor from furnishing other equipment or other appliances or
adopting other methods when those in use prove unsatisfactory or as to bind the
Authority to accept Work which does not comply with the Contract. Compliance
with determinations by the Authority shall not relieve the Contractor from other
obligations imposed by law or regulation nor serve as the basis of a Request for
Change Order to the Work. Once mobilization is paid, if the Contractor fails to
provide the appropriate equipment in accordance with Part 1, and if the Contractor
has not acted in good faith in providing and maintaining the equipment, the
Authority shall be entitled, at its own discretion, to implement one of the following
options:
2. Option 2: Allow the Contractor’s operation to proceed and deduct $500 per
day for each piece of equipment not on the job site. If this option is used,
this deduction shall be taken until the construction operation is completed
or until the appropriate equipment is provided.
A. The Contractor shall have roadway work equipment used to move other railcars or
equipment that is fully compliant with the FRA power brake, safety appliance, and
wheel requirements, and shall be fully stenciled to indicate such compliance. The
inspection and testing of the equipment, and the approval of the Contractor’s
operators, will be done by the Authority’s Manager, Rules, and Training as
scheduled by the Authority. The Contractor shall demonstrate to the Authority that
the operator can make an initial brake test before moving any equipment or
railcars, and obtain approval by inspection from the Authority, that equipment
meets all safety appliance, maintenance, and clearance requirements.
B. Unless amended by the Specifications, the Contractor shall have on hand and use
the minimum equipment or approved equal listed below in performing the Work of
the Contract Documents.
2. One Unit Ballast Stabilizer, using a model of the Plasser PTS-62 Dynamic
Track Stabilizer or equivalent that is no older than 10 years from
manufacture date.
3. A minimum of one Ballast Regulator or equivalent from the list below, using
a model no older than 10 years from manufacture date:
4. A minimum of one dust control tanker capable of spraying water with dust
control additive in advance and during surfacing and brooming and
regulating activities. The water tank shall have a capacity of at least 3,000
gallons.
C. The Contractor shall furnish all other on-track and off-track equipment necessary
to complete the work.
D. The Contractor shall maintain the equipment such that is operational and in proper
working order. Measures that may be necessary, include, but are not limited to,
the following:
E. Use of backup equipment not meeting the requirements listed above will be
permitted subject to the following conditions:
Work of this Section is considered incidental to work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 43 23
PART 1 - GENERAL
1.01 SUMMARY
This Section specifies provisions for the Contractor furnishing, erecting and maintaining
temporary barricades, changeable message signs, signs, flaggers, lights, road surfaces,
pavement markings for detours, object markers and other safeguards necessary to protect
the safety of the public during performance of the Project Work including but not limited to
automotive traffic, pedestrian traffic, and bicycle traffic.
A. The Contractor shall comply with provisions of the most recent edition, including
all addenda, of the following codes, specifications, standards, and recommenced
practices, except as otherwise indicated:
1.04 SUBMITTALS
The Contractor shall comply with Local Agency Requirements including the preparation of
all traffic control plans for the Grade Crossing Work, any advance message signs required
by the local agencies. The Contractor shall coordinate approval for the traffic control plans
for each Grade Crossing and obtain the no-fee traffic control and encroachment permits.
The temporary warning devices shall be designed to minimize the inconvenience to the
general public and shall comply with the regulations of the California Public Utilities
Commission (CPUC) and governmental agencies having jurisdiction.
B. Flashing yellow beacons shall be used on all W20-1 signs and all Type II
barricades guarding the work area overnight.
C. The Contractor shall have all signs, delineators, barricades, and other devices
properly installed prior to commencing construction. All signs shall be reflectorized
and standard size. All delineators shall be 28" minimum portable, reflectorized and
maintained erect in indicated position at all times, and shall be repaired, or cleaned
as necessary to preserve their appearance and continuity.
E. Post “Temporary No Parking Tow Away" signs defining the time and date of any
such restriction 72 hours prior to work.
F. A. The Contractor shall be responsible for location and protection of traffic signal
loop-sensors and signal and interconnect conduits. Where damage is caused by
the Contractor's operation, the Contractor shall replace damaged City facility at no
cost to the Authority or local jurisdiction.
Detour: In no case shall traffic be diverted from the existing traveled way without prior
approval of the Authority and appropriate municipalities and local agencies. The following
representatives of appropriate local agencies shall be notified 48 hours in advance of any
detour or construction activities:
City Civil
Engineer/Field
Inspector/Traffic
Engineer
Police Department (give location and duration)
Fire Department
Transit Buses
Detour striping will not be permitted on any finish course of asphalt concrete pavement.
PART 2 - PRODUCTS
All striping and marking shall conform to Section 310-5.6 of the Standard Specification for
Public Works Construction. Temporary removable striping tape (detour grade) may be
used in lieu of painted striping.
PART 3 - EXECUTION
A. All traffic control devices shall be installed in accordance with Caltrans’ current
Standard Specifications and WATCH, Standard Plans; and CA MUTCD. In
addition to work included above, the Contractor shall furnish and install guide
markers and delineators at the locations indicated on the Contract Documents and
where directed by the Authority.
B. The Contractor shall provide for access to all adjacent properties during working
hours. Construction operations shall be conducted in such a manner as to cause
as little inconvenience as possible to abutting property owners/operators. The
Contractor shall provide access to pedestrian all times. Construction operations
shall be conducted in such a manner as to cause as little inconvenience as possible
to pedestrian. Pedestrian shall be protected as required by CA MUTCD, Part 6D-
1 or WATCH Manual Latest Edition, Section 11.
C. The Contractor shall maintain on a 24-hour basis all signs, delineators, barricades,
etc., to ensure proper flow and safety of traffic.
A. Traffic control work completed in accordance with the contract documents will be
paid for at the contract unit price, as listed in the Schedule of Quantities and Prices.
This price shall be full compensation for furnishing all labor, materials, tools and
equipment including furnishing, erecting, maintaining and removing barricades,
traffic flaggers, construction area signs, temporary railing (Type K), portable
changeable message signs, channelizers, supplies, supervision including
preparing traffic control plans and obtaining traffic control and encroachment
permits, and incidental materials and work necessary for controlling traffic during
construction as described by the Contract Documents or required by the local
jurisdiction.
B. Full Compensation for furnishing and installing construction area traffic control
devices as ordered by the Engineer, for the sole convenience and direction of
public traffic shall be considered as included in the prices and no additional
compensation will be allowed.
END OF SECTION 01 55 26
PART 1 - GENERAL
1.01 SUMMARY
This Section addresses providing, operating, and maintaining security at the Work site
during construction. “Security” refers to the protection of both Authority property and the
property of the Contractor from theft, vandalism, pilfering or other destructive activities. It
is the Contractor’s sole responsibility to provide protection for any property (including
equipment and supplies) under the Contractor’s care, custody, and control.
1.03 REQUIREMENTS
B. The Contractor shall comply with CCR Title 8, as well as all other federal, state,
and local regulations, statutes, and codes applicable to security operations.
C. Compliance with all parts of this Section shall be considered entirely the
responsibility of the Contractor. No delays to the Contractor period of performance
relating to any Worksite Security requirements will be allowed by the Authority.
D. The SLPP shall comply with CFR 1926.800 (b) (3), which states: “The employer
shall control access to all openings to prevent unauthorized entry underground.
Unused chutes, manways, or other openings shall be tightly covered, bulkheaded,
or fenced off and shall be posted with warning signs indicating ’Keep Out’ or similar
language.” The SLPP shall include methods of protecting physical structures
above, below, or at grade from trespassers and malicious mischief.
F. The Contractor shall comply with the Authority requirements regarding the
protection of the public, group tours, site visitors, and office safety.
1.04 SUBMITTALS
A. The Contractor shall submit, for acceptance by the Authority, a written site- specific
SLPP that addresses both active and passive security measures to be
implemented by the Contractor for project-related Work sites. This SLPP will be
revised and resubmitted as conditions warrant and shall include at least the
following:
C. The Contractor shall not perform Work on the Work site for this Contract or any
work order thereunder, until the Authority has returned the submittals marked "No
Exceptions Taken." Authority refusal to issue permission to perform Work on the
Work site, due to the Contractor's failure to submit listed safety submittals, or due
to Authority rejection of unacceptable submittals, shall not constitute a basis for
any claim of delay, interference, disruption, or other similar types of claims.
PART 3 - EXECUTION
A. Authority shall be contacted at the start of the project to determine the necessity
of a security services and equipment.
B. Select, provide, and retain a reputable uniformed armed security guard service.
Security guards assigned by the security Subcontractor shall be assigned to only
Project Work sites for patrol and other security related activities.
C. Provide security guards with motor vehicles to enhance patrolling the entire Project
during construction work activities, including holidays and weekends. Personnel
assigned by the security Subcontractor shall perform only duties directly related to
the security function.
D. Security guards shall be equipped with cell phones to enhance their ability to report
incidents in a timely manner and allow direct contact with emergency
communications dispatchers.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 56 37
BIRD PROTECTION
PART 1 - GENERAL
1.01 SUMMARY
This work includes protecting migratory and nongame birds, their occupied nests, and
their eggs. Nesting or attempted nesting by migratory and nongame birds is anticipated to
occur but is not limited to March 15 through September 15.
A. The Federal Migratory Bird Treaty Act (16 USC §703-711.), 50 CFR 10, and Fish
& Game Code §3503, §3513, and §3800, protect migratory and nongame birds,
their occupied nests, and their eggs.
B. The Federal Endangered Species Act of 1973 (16 USC §1531,§1543) and
California Endangered Species Act (Fish & Game Code §2050-§2115.5) prohibit
the take of listed species and protect occupied and unoccupied nests of threatened
and endangered bird species.
PART 3 - EXECUTION
3.01 PROCEDURE
A. When migratory or nongame bird nests are discovered which may be adversely
affected by construction activity, or when a bird is found injured or killed as a result
of construction activity, immediately stop work within 100 feet (500 feet for raptors)
of the nest or bird and notify the Authority. Work must not resume until the Authority
provides written notification that work may resume at that location.
A. Exclusion devices, nesting prevention measures and nest removal that are ordered
by the Authority will be paid for by Change Order.
END OF SECTION 01 56 38
PART 1 - GENERAL
1.01 SUMMARY
This Section concerns general protection and pruning of existing trees and plants that are
affected by execution of the Work, whether temporary or permanent construction.
1.03 DEFINITIONS
A. Caliper: Diameter of a trunk measured by the average of the smallest and largest
diameters at 6 inches above the ground for trees up to and including, 4- inch size;
and 12 inches above the ground for trees larger than 4-inch size.
B. Plant Protection Zone: Area surrounding individual trees, groups of trees, shrubs,
or other vegetation to be protected during construction, and so indicated on
Drawings.
1.04 SUBMITTALS
C. Tree Pruning Schedule: A written schedule detailing the scope and extent of
pruning of trees to remain that interfere with or are affected by construction.
E. Certification: Certification from the arborist, certifying that trees indicated to remain
have been protected during construction according to recognized standards, and
that trees were promptly and properly treated and repaired when damaged.
B. Tree Service Firm Qualifications: Use an experienced tree service firm that has
successfully completed temporary tree and plant protection work similar to that
required for this Project, and that will assign an experienced, qualified arborist to
the Project site during execution of the Work.
3. Foot traffic
5. Impoundment of water
C. Prohibit heat sources, flames, ignition sources, and smoking within or near
protection zones and organic mulch.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Topsoil: Use natural or a cultivated top layer of the soil profile or manufactured
topsoil, containing organic matter and sand, silt, and clay particles; friable,
pervious, and black or a darker shade of brown, gray, or red than underlying
subsoil. Material should be reasonably free of subsoil, clay lumps, gravel, and
other objects more than ½-inch in diameter; and free of weeds, roots, and toxic
and other nonsoil materials.
B. Topsoil Source: Obtain topsoil only from well-drained sites where topsoil is 4
inches deep or more; do not obtain from bogs or marshes.
C. Organic Mulch: Should be free from deleterious materials and suitable as a top
dressing for trees and shrubs, and consisting of one of the following:
3. Color: Natural
a. Height: 4 feet
a. Height: 4 feet
PART 3 - EXECUTION
3.01 EXAMINATION
A. Erosion and Sedimentation Control: Examine the site to verify that temporary
erosion and sedimentation control measures are in place. Verify that flows of water
redirected from construction areas or generated by construction activity do not
enter or cross protection zones.
B. For the record, prepare a written report, endorsed by the arborist, listing conditions
detrimental to tree and plant protection.
3.02 PREPARATION
A. Locate and clearly identify trees, shrubs, and other vegetation to remain or to be
relocated. Flag each tree trunk at 54 inches above the ground.
B. Protect tree root systems from damage caused by runoff or spillage of noxious
materials while mixing, placing, or storing construction materials. Protect root
systems from ponding, eroding, or excessive wetting caused by dewatering
operations.
C. Tree Protection Zones: Mulch areas inside tree-protection zones and other areas
as indicated below Apply a 4-inch average thickness of organic mulch. Do not
place mulch within 6 inches of tree trunks.
1. Posts: Set or drive posts into ground one-third the total height of the fence
without concrete footings. Where a post is located on existing paving or
concrete to remain, provide appropriate means of post support acceptable
to the Authority.
3.04 EXCAVATION
A. General: Excavate at the edge of protection zones and for trenches indicated
within protection zones according to requirements in the Specifications titled "Earth
Moving."
B. Trenching near Trees: Where utility trenches are required within protection zones,
hand-excavate under or around tree roots or tunnel under the roots by drilling,
auger boring, or pipe jacking. Do not cut main lateral tree roots or taproots; cut
only smaller roots that interfere with installation of utilities. Cut roots as required
for root pruning.
C. Redirect roots in backfill areas where possible. If encountering large, main lateral
roots, expose roots beyond excavation limits as required to bend and redirect them
without breaking. If encountered immediately adjacent to the location of new
construction and redirection is not practical, cut roots approximately 3 inches back
from new construction and as required for root pruning.
D. Do not allow exposed roots to dry out before placing permanent backfill. Provide
temporary earth cover or pack with peat moss and wrap with burlap. Water and
maintain in a moist condition. Temporarily support and protect roots from damage
until they are permanently relocated and covered with soil.
A. Prune roots that are affected by temporary and permanent construction. Prune
roots as shown on Drawings and as follows:
1. Cut roots manually by digging a trench and cutting exposed roots with
sharp pruning instruments; do not break, tear, chop, or slant the cuts. Do
not use a backhoe or other equipment that rips, tears, or pulls roots.
2. Cut Ends: Coat cut ends of roots more than 1½ inches in diameter with an
emulsified asphalt or other coating formulated for use on damaged plant
tissues and that is acceptable to the arborist.
3. Temporarily support and protect roots from damage until they are
permanently redirected and covered with soil.
B. Root Pruning at Edge of Protection Zone: Prune roots 12 inches outside of the
protection zone, by cleanly cutting all roots to the depth of the required excavation.
C. Root Pruning within Protection Zone: Clear and excavate by hand to the depth of
the required excavation to minimize damage to root systems. Use narrow-tine
spading forks, comb soil to expose roots, and cleanly cut roots as close to
excavation as possible.
A. Prune branches that are affected by temporary and permanent construction. Prune
branches as shown on Drawings and as follows:
1. Prune trees that are to remain to compensate for root loss caused by
damaging or cutting the root system. Provide subsequent maintenance
during the Contract period as recommended by the arborist.
2. Pruning Standards: Prune trees according to ANSI A300 (Part 1) and the
following:
3.07 REGRADING
A. Lowering Grade: Where new finish grade is indicated below the existing grade
around trees, slope the grade beyond the protection zone. Maintain existing grades
within the protection zone.
B. Lowering Grade within Protection Zone: Where new finish grade is indicated below
the existing grade around trees, slope the grade away from trees as recommended
by the arborist, unless otherwise indicated.
C. Root Pruning: Prune tree roots exposed by lowering the grade. Do not cut main
lateral roots or taproots; cut only smaller roots. Cut roots as required for root
pruning.
D. Raising Grade: Where the new finish grade is indicated above the existing grade
around trees, slope the grade beyond the protection zone. Maintain existing grades
within the protection zone.
A. General: Repair or replace trees, shrubs, and other vegetation that are indicated
to remain or be relocated if damaged by construction operations, and in a manner
approved by the Authority.
1. Submit details of proposed root cutting and tree and shrub repairs.
2. Have the arborist perform the root cutting, branch pruning, and damage
repair of trees and shrubs.
3. Treat damaged trunks, limbs, and roots according to the arborist's written
instructions.
B. Trees: Remove and replace trees indicated to remain that are more than 40
percent dead or in an unhealthy condition before the end of the corrections period,
or that are so damaged during construction operations that the Authority
determines they are incapable of restoration to a normal growth pattern.
1. Provide new trees of the same size and species as those being replaced
for each tree that measures 6 inches or smaller in caliper size.
2. Provide two new trees of 6-inch caliper size for each tree being replaced
that measures more than 6 inches in caliper size. The species is to be
selected by the Authority.
3. Plant and maintain new trees as specified in the Division 32 Section titled
"Plants."
C. Soil Aeration: Where directed by Authority, aerate surface soil compacted during
construction. Aerate 10 feet beyond drip line and no closer than 36 inches to tree
trunk. Drill 2-inch- diameter holes a minimum of 12 inches deep at 24 inches on
center. Backfill holes with an equal mix of augered soil and sand.
Disposal: Remove excess excavated material, displaced trees, trash and debris, and
legally dispose of them off Authority's property.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 56 39
PART 1 - GENERAL
1.01 SUMMARY
The Work specified in this Section consists of eliminating or minimizing air, water, and
noise pollution generated by construction activities, and of complying with all legal
requirements applicable to any construction generated hazardous wastes, including
preparation and implementation of waste and wastewater management plans.
1.03 REGULATIONS
The Contractor shall comply with all pertinent regulations including the following:
D. The Federal Occupational Safety and Health Act (OSHA) and the California
Occupational Safety and Health Act (CAL/OSHA).
1.04 SUBMITTALS
A. Certificates that materials provided comply with Standard Specifications for Public
Works Construction.
C. Stormwater Pollution Prevention Plan as required under the Clean Water Act and
related federal and state laws and regulations: Required within 30 calendar days
of effective date of LNTP. Authority or its designee will have the right to review,
modify, and approve this SWPPP, and to provide quality assurance/quality control
monitoring on the Contractor's implementation of this Plan.
1. The Plan shall be prepared consistent with the provisions of the National
Pollution Discharge Elimination System (NPDES) General Permit No.
CAS000003 for Waste Discharge Requirements for Discharges of Storm
Water Runoff Associated with Construction Activity adopted by the State
Water Resources Control Board on September 2, 2012, as Order No. 2010-
0014-DWQ (CGP).
E. The Contractor shall prepare permit applications and obtain permits not provided
by Authority as necessary for performance of the Work under this Contract
including, but not limited to:
7. Written permission from the property owner for right-of-entry work that
requires entering private property.
PART 3 - EXECUTION
A. The Contractor shall comply with all requirements for controlling fugitive dust
including specific impact mitigation measures contained in the latest version of
the South Coast Air Quality Management District (SCAQMD) Rules and
Regulations that include minimum procedures and techniques:
3. Establish regular cycles and locations for cleaning trucks that haul soil from
site.
5. If conveyors are used, cover all transfer points along the conveyor system
that is moving soil. Minimize the drop height to the stockpile. Provide a
sprinkler system that will apply water to soil before it drops to stockpile.
B. Burning of wastes is prohibited. Remove scrap and waste material and dispose of
it in accordance with laws, codes, regulations, ordinances and permits.
D. Establish and maintain records of the routine maintenance program for internal
combustion engine powered vehicles and equipment used on the Project. Keep
records available for inspection by the Authority or its designee.
E. During excavation, gases may be released from soil and from underground
reservoirs. Gases may contain methane, other more complex hydrocarbons, or
hydrogen sulfide, and may present hazards due to flammability or toxicity. Safety
during construction is required by regulations of OSHA and CAL/OSHA. Although
the composition, quantity, and concentration of gases that might be released are
unknown, release of gases into the atmosphere may be subject to control by
SCAQMD and the California Air Resources Board (CARB). The Authority will
coordinate this issue with SCAQMD and CARB and will inform the Contractor of
further required actions.
A. The Authority retains the sole right to determine whether discharged wastewaters
will be discharged to the sanitary or the storm drain system. The Contractor shall
treat wastewater, including storm runoff that is pumped from excavations and other
water encountered during operations; remove suspended particles, pollutants, and
hydrocarbons through settling basins or hydrocarbon separators in order to comply
with Authority direction and regulatory criteria for pollutants in water set by state
and local water agencies.
A. The Contractor is responsible for, and shall indemnify, defend, and hold the
Authority harmless against any costs (including attorney's fees and costs),
demands, claims, damages, losses, delay costs ("Claims") arising from or
associated with the management, abatement, removal, remediation, clean-up,
transport, reuse, recycling, storage, and disposal of any Contractor Generated
Hazardous Waste, or associated with any noncompliance with the Contractor
Generated Waste Management Plan.
B. In the event that the Contractor or the Authority reasonably suspects that the
Contractor has generated, released, or discharged the Contractor Generated
Hazardous Waste, the Contractor is to bear all costs of sampling and monitoring
tests and other investigations to determine whether said waste is Solid Waste or
Hazardous Waste in accordance with all federal, state and local requirements,
including, without limitation, RCRA and Title 22, CCR Chapter 30, Article II (as
amended, modified, or replaced from time to time). The Authority reserves the right
(but not the obligation) to perform its own physical and chemical analyses and tests
on suspected Contractor Generated Hazardous Waste. The Contractor shall
furnish samples, at the Contractor's cost, as directed by the Authority.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 57 19
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.01 SUMMARY
C. Hazardous materials shall not be stored within 25 feet of an Active Track without
written approval of the Authority.
D. The Contractor shall also maintain a file of relevant MSDSs at the work site. MSDS
files shall be kept current; new or updated MSDSs shall be added immediately,
and a copy provided to the Authority.
PART 2 - PRODUCTS
A. General Product Requirements: Provide products that comply with the Contract
Documents, that are undamaged, and, unless otherwise indicated, that are new at
time of installation.
4. Where products are accompanied by the term "as selected," the Authority
will make the selection.
PART 3 - EXECUTION
A. The Contractor shall, at its own expense, deliver, unload, store, handle, and be
responsible for all materials, whether furnished by the Authority or by the
Contractor. All Authority furnished material, whether unloaded by the Authority or
by the Contractor, shall be moved by the Contractor, at its expense, from the point
where it is delivered by the Authority to the site of the Work.
B. Deliver, unload, store, and handle products using means and methods that will
prevent damage, deterioration, and loss, including theft. Comply with
manufacturer's written instructions. The unloading, storing, and hauling of all the
Authority’s or the Contractor's material shall be considered as incidental to
Contract pricing.
5. Track materials shall be handled and stored in accordance with the SCRRA
Track Maintenance Manual and as per these specifications.
D. Storage:
2. Store materials in a manner that will not endanger Project structures and
material shall not be placed nor stored within 25 feet of the centerline of
any active railroad track.
3. Store products that are subject to damage by the elements under cover in
a weather-tight enclosure above ground, or with impervious sheeting
allowing for ventilation adequate to prevent condensation. Comply with the
product manufacturer's written instructions regarding temperature,
humidity, ventilation, and weather-protection requirements for storage.
6. Store foam plastic away from exposure to sunlight, except to the extent
necessary for a period of installation and concealment.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 60 00
PART 1 - GENERAL
1.01 SUMMARY
The Authority may elect to furnish without cost to the Contractor a portion of the materials
required for the Project. All materials that the Authority intends to furnish will be specified
in the Project Specific Specifications. This Section includes administrative and procedural
requirements for delivery, storage, and handling of Authority furnished products.
B. The Contractor shall check all material upon receipt for quantity and condition, and
after acceptance shall be fully responsible for properly protecting the material from
loss or damage due to theft, fire, weather, or any other cause. For any of the
material lost or damaged beyond repair after delivery, or for any of the materials
not incorporated into the Work and not returned, the Contractor will be charged the
same amount that the original materials cost the Authority, or amounts equal to
replacement costs, whichever are higher. Any materials damaged after delivery to
the Contractor, that the Authority, at its sole discretion, deems can be repaired
satisfactorily, shall be repaired at the Contractor's expense and under the direction
of the Authority.
PART 3 - EXECUTION
A. The Contractor shall submit with the SSWP what Authority furnished materials are
required and confirm with the Authority the location of the material. Unless
otherwise stated in the Specifications, Project Specific Specifications or Special
Conditions, all CWR and Crossties will be stored within the Project Right-of-Way
limits. The Contractor shall make arrangements to pick up and transport these
materials to the job site as needed.
B. Within ten days of the NTP, the Contractor and the Authority shall conduct a joint
inventory of the Authority furnished materials. The Contractor shall complete and
update on a weekly basis the inventory of the Authority furnished materials, based
on the use of the materials. Included in this inventory shall be information regarding
amount of material removed from each storage location and its current location. In
addition, the Contractor shall provide the Authority a log of all Authority furnished
materials installed, to include a listing of the type, size, kind, and date/location
where the material was installed, as well as a log of all Authority owned materials
released or removed from the property.
END OF SECTION 01 64 00
PART 1 - GENERAL
1.01 SUMMARY
A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking
areas for construction personnel.
B. Fire Safety Program: Show compliance with requirements of NFPA 241 and
authorities having jurisdiction. Indicate the Contractor personnel responsible for
management of fire prevention program.
D. Dust Control Plan: Submit coordination drawing and narrative that indicates the
dust control measures proposed for use, proposed locations, and proposed time
frame for their implementation. Identify further options if proposed measures are
later determined to be inadequate. Include the following:
A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for
temporary electric service. Install service to comply with NFPA 70 and the
requirements of jurisdictional authorities.
B. Tests and Inspections: Arrange for authorities having jurisdiction to test and
inspect each temporary utility before use. Obtain required certifications and
permits.
PART 2 - PRODUCTS
The Contractor shall provide storage and fabrication sheds sized, furnished, and equipped
to accommodate materials and equipment for construction operations and shall store
combustible materials apart from buildings and structures. Provide portable, UL rated; with
class and extinguishing agent as required by locations and classes of fire exposures.
Project sign shall be as per Engineering Standard ES5201. The Project sign shall be one
32 square foot aluminum panel sign mounted on two 2¼” x 2¼” square posts embedded
in the ground. Bottom of the sign shall be 7’ above ground.
PART 3 - EXECUTION
A. The Contractor shall maintain all utility facilities placed by the Contractor in
temporary locations and all utilities that are shored or supported by the Contractor
during construction. The cost of providing and maintaining all necessary or
required temporary structures, and of making any necessary repairs,
replacements, or similar operations, shall be paid by the Contractor; no separate
payment shall be made.
B. The Contract Price includes all costs that may be incurred by the need to remove
or relocate existing public utilities or other structures, including public utilities or
other structures identified at the time of the Bid due date. It is the Contractor's
responsibility to schedule its Work and labor and equipment to minimize the impact
of such delays and costs. Accordingly, except as provided in the California
Government Code in the case of existing main or trunkline utility facilities, the
Contractor agrees that its sole remedy resulting from any unreasonable delay or
removal or relocation of such utilities will be an adjustment in accordance with the
Change Order provisions of the Contract.
A. The Contractor shall be responsible for the protection of public, private, and
Authority property adjacent to and within the Work site, and shall be responsible
for bearing the cost and performing the repair work necessary to restore or repair
damaged areas.
B. The Contractor shall supply all firefighting equipment, supplies, and personnel, and
perform all Work required by the laws and regulations pertaining to fire prevention.
D. Place steel plates to cover trenches and excavation outside of fenced construction
areas at all times that Work is not ongoing. The steel trench plate shall be a
minimum of 1 inch thick, with anti-slip coating or treatment and having sufficient
bearing surface to support heavily loaded trucks and emergency equipment. The
steel traffic plate shall be anchored and have approach ramping against
movement.
A. Electric Power Service: Provide electric power service and a distribution system of
sufficient size, capacity, and power characteristics required for construction
operations.
B. Lighting: Provide temporary lighting with local switching that provides adequate
illumination for construction operations, observations, inspections, and traffic
conditions. Install and operate temporary lighting that fulfills security and protection
requirements without operating the entire system and install lighting for the Project
identification sign.
A. Staging and laydown areas for use in this Contract are as detailed in the Plans and
Specifications. Staging and laydown areas not covered in the Contract Documents
shall be requested in writing and approved by the Authority. This approval may or
may not be granted by the Authority. No equipment may be operated or materials
stored or placed for any period of time in unfenced areas closer than 25 feet from
live tracks unless an Authority RWIC is present. The Contractor shall provide a
fence to enclose each laydown or staging area within the right of way. The
Contractor shall furnish the Authority with photographs of all staging and laydown
areas to document their condition prior to the start of Work.
B. The Contractor shall confine Work site operations to areas permitted by law,
ordinances, permits, and the Contract.
C. The Contractor shall relocate stored products, equipment, and materials that
interfere with train operations, public and private utilities, or the visibility at railroad
crossings. Materials and equipment shall not be piled, stored, or parked when not
in use.
D. As needed for the proper execution of the Work, the Contractor shall coordinate
operations and secure additional storage/work areas from the property owners, at
no cost to the Authority. The Contractor shall adhere to the noise levels and hours
of local ordinances, except as provided and approved in the Site-Specific Work
Plan (SSWP) in accordance with Section 01 14 00, Work Restrictions.
E. The Contractor shall submit the proposed location of staging areas for the
Authority’s approval. No use of proposed locations shall be allowed prior to
approval.
A. Access to the Work from existing public roads, private property, or along the right-
of-way of the Authority shall be arranged for and provided by the Contractor. No
payment will be made to the Contractor by the Authority for any work done in
constructing, improving, repairing or maintaining any road or structure thereon for
use in the performance of the Work. The Authority assumes no responsibility for
the condition or maintenance of any road or structure thereon that may be used by
the Contractor in performing the Work or in traveling to and from the site of the
Work.
B. Existing roads and trails shall be used whenever possible for access to the Work.
Construction of new access roads or use of existing roads shall be subject to
approval by the appropriate governmental agency, landowner, and Authority.
Temporary access roads shall be rehabilitated upon termination of the use of the
road. The roads shall be graded to conform to original topography to the degree
possible. Cut slopes shall be reduced to a grade consistent with adjacent
topography, protected from erosion, and re-vegetated.
C. The Contractor's haul or service road shall be located so that, upon the completion
of the Work, a continuous road, where possible, will remain on the right-of-way
throughout the entire length of the project. The Authority will designate the location
of the road.
F. The Contractor may, upon approval of the Authority, construct temporary private
railroad crossings for the purpose of performing the Work required. An Authority
RWIC shall be provided at all such crossings at all times during construction. A
physical barrier shall be provided to protect the crossing when not in use for
construction. Access across the crossing may be limited by the presence of trains
on the live track, as described in Section 01 14 00, Work Restrictions. Temporary
crossings shall be removed upon completion of the Work. The Contractor shall
submit plans for the Authority’s approval. Any requirement for at- grade railroad
crossings (other than public at-grade railroad crossings) or use of the Right of Way
for the Contractor's equipment, vehicles, or materials shall be as approved by the
Authority.
G. All costs associated with the construction, maintenance, and removal of the haul
or service road, and restoration of any area off the Authority's right-of-way will be
considered, as incidental to other items of the Contract and no additional payment
for any of this Work will be made.
H. The Contractor shall provide dust-control treatment that is non-polluting and non-
tracking. Reapply treatment as required to minimize dust.
I. Upon completion of the Project, restore access and staging areas to a condition
that is equal to or better than that prior to the Contractor entry, and as accepted by
the Authority. All residual Materials shall be removed and all areas used shall be
bladed smooth upon completion of use. Drainage in all areas affected by the
Project shall be restored to a condition that ensures that no water ponds on the
Right of Way, and no water is diverted to drain to the track structure. The
Contractor shall photograph the project site(s) and submit the photographs to the
Authority to demonstrate that staging and access areas have been restored to the
pre-construction condition.
J. Fences, walls, signs, and gates affected by the Contractor’s access to the Right of
Way shall be restored to full serviceability prior to demobilization.
K. Maintain traffic controls, access for fire-fighting equipment and access to fire
hydrants. Protect existing site improvements that are to remain, including curbs,
pavement, and utilities.
A. If the Contractor anticipates using any vehicles or equipment over 20,000 pounds
(loaded) during the performance of the Work, dimensions and weights of such
equipment shall be submitted to the Authority for approval prior to use.
B. The Safe Drinking Water and Toxic Enforcement Act of 1986 (Proposition 65)
prohibits employers from knowingly discharging or releasing a chemical or other
material known to the State of California to cause concern, birth defects, or other
reproductive harm into water or onto land where such chemical passes or probably
will pass into any source of drinking water. Notwithstanding any provisions in this
Act exempting the Contractor, the Contractor hereby agrees to comply with all
provisions of the Act relating to the discharge of hazardous chemicals and
materials on the Work site.
C. The Contractor’s employees and Subcontractors of any tier shall not discharge
such chemicals or materials on the Work site that will result in the discharge of
such chemicals, and shall, upon completion of performance of all other duties
under this Contract, remove all supplies, materials, and waste remaining on the
job site which if exposed, could result in the discharge of such chemicals,
materials, and wastes.
D. The Contractor, the Contractor’s employees, and Subcontractors of any tier shall
also comply with the State of California anti-smoking laws that, in part, prohibit
smoking in the workplace and in enclosed areas.
A. The Contractor shall comply with all local, state, and federal rules and regulations
of the Department of Food and Agriculture, the Department of Health, the
Department of Industrial Relations, the Department of Toxic Substance Control,
and all other agencies that govern the use of pesticides, fuel oil, and grease
required in the performance of the Work. Fuel, oil, and grease include any crude
oil or any products, byproducts, or fractions thereof.
B. Disposal of all Hazardous Materials shall be done in accordance with all laws and
regulations. Copies of a required regulatory documentation, including copies of
final manifests, shall be submitted to the Authority. No payment will be made for
such work without proper and complete manifests.
A. Site Enclosure Fence: Before construction operations begin, furnish and install a
site enclosure fence in a manner that will prevent people and animals from easily
entering the site except by entrance gates.
1. Extent of Fence: As required to enclose the entire Project site or that portion
determined sufficient to accommodate construction operations.
4. Provide temporary standpipes and hoses for fire protection. Hang hoses
with a warning sign stating that hoses are for fire-protection purposes only
and are not to be removed. Match hose size with outlet size and equip them
with suitable nozzles.
A. The Contractor shall conduct its operations so as to offer the least possible
obstruction and inconvenience to the public and shall have under construction no
greater length or amount of work than can be prosecuted properly with due regard
to the rights of the public. The Contractor shall control temporary noise from
construction equipment by using work hour controls and maintenance of muffler
systems on machinery.
C. The Contractor, at its expense, shall provide adequate safeguards, safety devices
and protective equipment and take any other needed action both of its own volition
and responsibility or that which the Authority may determine is reasonably
necessary to protect property, life, health and public safety in connection with the
performance of the Work covered by the Contract.
D. The Contractor shall make all reasonable efforts to maintain good will among
landowners, tenants, lessees, and members of the general public and shall not
knowingly violate any right of such persons in the performance of the Work
covered by the Contract. To this end, the Contractor specifically agrees to not:
E. In the event the Contractor's operations cause injury to any persons or damage to
public or private property, including above and below ground structures, the
Contractor shall immediately contact emergency services for the local Authority
and within twenty-four (24) hours, give notification in writing to the Authority of such
damage or injury. The Contractor shall be responsible and liable for all damages
and injuries.
G. All paved areas, including asphalt concrete berms cut or damaged as a result of
construction, shall be replaced with similar materials of equal thickness to match
the existing adjacent undisturbed areas, except where specific resurfacing
requirements have been called for in the Contract Documents or in the
requirements of the agency issuing the permit. All temporary and permanent
pavements shall conform to the requirements of the affected pavement owner. All
pavement that is subject to partial removal shall be neatly saw-cut in straight lines.
H. In order to obtain a satisfactory junction with adjacent surfaces, the Contractor shall
saw-cut back and trim the edge of the surface so as to provide a clean, sound,
vertical joint before temporary or permanent replacement of an excavated or
damaged portion of pavement. Damaged edges of pavement along excavations
and elsewhere shall be trimmed back by saw-cutting in straight lines. All pavement
restoration and other facilities restoration shall be constructed to finish grades
compatible with adjacent undisturbed pavement.
I. Where sidewalks or bike lanes have been removed for purposes of construction,
or damaged, the Contractor shall place properly protected, suitable temporary
sidewalks including bike lanes, promptly after backfilling, and shall maintain them
in satisfactory condition until the final restoration thereof has been made.
A. The Authority, the Authority’s Contractors and other railroads will occupy the Work
site during the entire construction period for the conduct of the Authority’s and the
railroad’s normal operations. The Contactor shall cooperate with the Authority and
the railroads, through the Authority, in scheduling operations to minimize conflicts
so as to not interfere or impair the normal operation of the Authority or other
railroads.
B. The Contractor shall develop and submit for the Authority’s approval a Disruption
Mitigation Plan that identifies and establishes criteria for the performance of the
Work that requires coordination and sequencing based on the operational
requirements of the Authority and the other railroads, and to allow the free flow of
public traffic within the public rights-of-way. The Contractor shall incorporate
operational data and information and requirements given by the Authority, other
railroads, and local municipal transportation agencies in developing the Disruption
Mitigation Plan, and in planning and scheduling its work to prevent interruption or
impairment of the normal operations of the Authority, the other railroads, and public
traffic. The Contractor shall avoid disruptions to the normal operations of the
Authority, other railroads, and public traffic, and shall plan, schedule, coordinate
and construct the Work in such a way as to accommodate the normal operations
of the Authority, other railroads, and public traffic.
C. Upon the completion of each day’s Work, the Contractor shall make the railroad
tracks and facilities suitable for the passage of trains. The operation of trains over
portions of the Work not completed will be in accordance with the FRA
requirements. The operation of trains over such Work will not constitute Beneficial
Occupancy.
A. Temporary Facility Changeover: Do not change over from using temporary security
and protection facilities to permanent facilities until Substantial Completion.
B. Termination and Removal: Remove each temporary facility when need for its
service has ended, when it has been replaced by authorized use of a permanent
facility, or no later than Substantial Completion. Complete or, if necessary, restore
permanent construction that may have been delayed because of interference with
a temporary facility. Repair damaged Work, clean exposed surfaces, and replace
construction that cannot be satisfactorily repaired.
1. Materials and facilities that constitute temporary facilities are the property
of the Contractor. The Authority reserves the right to take possession of
Project identification signs.
2. Remove temporary roads and paved areas not intended for or acceptable
for integration into permanent construction. Where an area is intended for
landscape development, remove soil and aggregate fill that do not comply
with the requirements for fill or subsoil. Remove materials contaminated
with road oil, asphalt, other petrochemical compounds, and other
substances that might impair the growth of plant materials or lawns. Repair
or replace street paving, curbs, and sidewalks at temporary entrances, as
required by authorities having jurisdiction.
3. 100 percent of the amount bid for mobilization and demobilization will be
paid after the Authority has determined that the project work is complete in
accordance with the Contract and technical specifications, and the
Contractor has left the wok site in a clean and acceptable condition.
END OF SECTION 01 71 13
FIELD ENGINEERING
PART 1 - GENERAL
1.01 SUMMARY
This Section includes general administrative and procedural requirements for field
engineering and surveying for the Work including, establishing and maintaining baselines,
design lines, grades and field control points as required for construction layout survey.
The Work of this Section also includes field survey of existing track and track grade to
verify final layout, point of switch stations, alignment, and grade for new turnouts and
bridges and other structures.
1.03 SUBMITTALS
A. Submit for the Authority’s approval the name and professional history of the land
surveying firm designated by the Contractor as its Project Surveyor. The Project
Surveyor or professional engineer selected must be a current California State
licensed land surveyor and have a minimum of five years of verifiable experience
performing field surveys of railroad, track, and bridge alignments and related office
engineering.
B. On request, the Contractor shall submit to the Authority all documentation that
verifies the accuracy of the survey work.
C. Certificates and Site Drawings: Prior to Completion and when requested by the
Authority, submit a certificate and site drawing signed by, a Land Surveyor, or
Professional Engineer, certifying that the location and elevation of improvements
are in conformance with Contract Documents.
D. The Contractor shall submit a complete copy of the baseline survey field notes and
final survey layout. The layout will include data and offset calculations.
A. The Contractor shall maintain a complete and accurate log of control and survey
work as it progresses.
B. The Authority reserves the right to check the Contractor's survey measurements
and calculations. Whether the Authority exercises this right or not, the requirement
for accuracy will not be waived.
PART 3 - EXECUTION
3.01 EXAMINATION
The Contractor shall verify locations of survey control points prior to starting any Work on
the Project site. The Contractor shall immediately notify the Authority of any discrepancies
discovered.
A. The Contractor shall locate and protect survey controls, existing benchmarks,
control points, survey monuments, property corners and reference points and
preserve permanent reference points during construction.
B. The Contractor shall report to the Authority the loss or destruction of any reference
points or relocation required because of changes in grades or other reasons.
C. The Contractor shall replace dislocated survey control points based on the original
survey control, and shall make no changes without prior written notice to and
approval by the Authority.
D. The Contractor shall report to the Authority the need to relocate permanent
benchmarks or control points before proceeding.
A. Identification: The Authority will identify existing benchmarks, control points, and
property corners. Control datum for the survey is indicated on the Drawings.
A. Before proceeding to lay out the Work, the Contractor shall verify layout
information shown on Drawings, in relation to the property survey and existing
benchmarks. If discrepancies are discovered, the Contractor shall notify the
Authority promptly.
B. General: Engage a land surveyor or professional engineer to lay out the Work
using accepted surveying practices in accordance with the following:
1. Establish benchmarks and control points to set lines and levels at each
phase of construction and elsewhere as needed to locate each element of
the Project. Establish limits on use of the Project site.
4. Check the location, line and grade of every major element as the Work
progresses. Notify the Authority when deviations from required lines or
grades exceed allowable tolerances. Such notification shall include a
thorough explanation of the problem, and a proposed plan and schedule
for remedying the deviation. Remedial work shall not proceed without the
Authority’s concurrence of the remediation plan. Work progressed after a
deviation is noted shall be removed and redone at no cost to the Authority.
5. Close site surveys with an error of closure equal to or less than the standard
established by authorities having jurisdiction.
C. Site Improvements: Locate and lay out site improvements, including top of rail,
special track work, crossing panels, pavements, grading, fill and topsoil placement,
utility slopes, and rim and invert elevations.
D. Building Lines and Levels: Locate and lay out control lines and levels for structures,
building foundations, column grids, and floor levels, including those required for
mechanical and electrical work. Transfer survey markings and elevations for use
with control lines and levels. Level foundations and piers from two or more
locations.
E. Record Log: Maintain a log of layout control work. Record any deviations from
required lines and levels. Include beginning and ending dates and times of
surveys, weather conditions, name and duty of each survey party member, and
types of instruments and tapes used. Make the log available for reference by the
Authority.
F. The contractor shall stake out location of the railroad warning devices and provide
horizontal and vertical control survey sheet prepared by a registered surveyor and
tied to the project survey control for grade crossings. This service is necessary to
coordinate street geometry and curb return layouts with railroad signal contractor.
B. The Contractor shall calculate and measure required dimensions as shown on the
Contract Drawings (within recognized tolerances if not otherwise indicated and
immediately notify the Authority of any discrepancies. The Contractor shall use
written rather than scaled dimensions.
D. The Contractor shall inform tradesmen performing the Work of marked lines and
grades provided for their use in layout work.
E. The Contractor shall provide a complete copy of baseline survey field notes and
final layout to the Authority prior to starting construction.
G. The basis for dimensioning railroad track is the centerline between the rails and
elevation of the top surface of the rail unless noted otherwise in the plans or the
Specifications or by the Authority. On curved track with super-elevation, the
elevation specified is that of the low rail (inside of curve) unless noted otherwise in
the plans or the Specifications or by the Authority.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 71 23
PART 1 - GENERAL
1.01 SUMMARY
1.03 DEFINITIONS
A. Construction Waste: Building and site improvement materials and other solid
waste resulting from construction, remodeling, renovation, or repair operations.
Construction waste includes packaging.
1.05 SUBMITTALS
1. Material category
PART 3 - EXECUTION
D. Procedures: Separate recyclable waste from other waste materials, trash, and
debris. Separate recyclable waste by type at the Project site to the maximum
extent practical, according to the approved construction waste management plan.
4. Stockpile materials away from the construction area. Do not store within
the drip line of remaining trees.
5. Store components off the ground, and protect them from the weather.
C. Disposal: Remove waste materials from the Authority’s property and legally
dispose of them.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 74 19
SUBSTANTIAL COMPLETION
PART 1 - GENERAL
1.01 SUMMARY
A. The Contractor shall prepare and submit the following a minimum of 14 days prior
to requesting inspection for determining the date of Substantial Completion.
3. Make the final changeover of permanent locks and deliver keys to the
Authority. Advise the Authority of the changeover in security provisions.
8. Terminate and remove temporary facilities from the Project site, along with
mockups, construction tools, and similar elements.
10. Deliver tools, spare parts, extra materials, and similar items to the location
designated by the Authority. Label with manufacturer's name and model
number where applicable.
B. Beneficial Occupancy shall not be deemed an acceptance of the Work. While the
Authority is in such possession, the Contractor shall be relieved of the
responsibility for maintenance, loss, or damage to that portion of the Work for
which the Authority has taken Beneficial Occupancy other than that resulting from
the Contractor's act or omission, negligence willful misconduct, or breach of
warranty. If such possession or use by the Authority unreasonably delays progress
of the Work or causes additional expense to the Contractor, an adjustment may be
made in the compensation or time to perform the Work, in accordance with
Contract Change Order Procedures.
PART 2 - PRODUCTS
Provide products, spare parts, maintenance and extra materials in quantities specified in
Section 01 78 23, Operation and Maintenance Data and individual Specification Sections.
PART 3 - EXECUTION
1. Clean the Project site, yard, and grounds in areas disturbed by construction
activities—including landscape development areas—of rubbish, waste
material, litter, and other foreign substances.
3. Rake grounds that are neither planted nor paved to a smooth, even-
textured surface.
8. Vacuum carpet and similar soft surfaces, removing debris and excess nap;
clean according to the manufacturer's recommendations if visible soil or
stains remain.
13. Replace disposable air filters and clean permanent air filters. Clean
exposed surfaces of diffusers, registers, and grills.
14. Clean ducts, blowers, and coils if units were operated without filters during
construction, or if they display contamination with particulate matter on
inspection.
15. Clean light fixtures, lamps, globes, and reflectors to function with full
efficiency.
C. Remove and replace chipped, scratched, and broken glass, reflective surfaces,
and other damaged transparent materials.
D. Touch up and otherwise repair and restore marred or exposed finishes and
surfaces. Replace finishes and surfaces that that already show evidence of repair
or restoration.
E. Do not paint over "UL" and other required labels and identification, including
mechanical and electrical nameplates. Remove paint applied to required labels
and identification.
F. Replace parts subject to operating conditions during construction that may impede
operation or reduce longevity.
G. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective
and noisy starters in fluorescent and mercury vapor fixtures to comply with
requirements for new fixtures.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 77 00
PROJECT CLOSEOUT
PART 1 - GENERAL
1.01 SUMMARY
This Section specifies procedures and requirements for Contract close out, including but
not limited to final submittals, final acceptance, all required financial and legal
documentation, and release of final payment to the Contractor at completion of the
Contract Work.
Submittals Prior to Final Completion: Before requesting final completion, the Contractor
shall submit the following:
A. Summary:
B. Closeout:
C. Compliance:
D. Financial:
a. Lien Releases from all Subcontractors and vendors that have filed
preliminary notice of liens.
E. Construction:
4. Final meter readings for utilities, a measured record of stored fuel, and
similar data as of the date of Substantial Completion (or when the Authority
took possession of and assumed responsibility for corresponding elements
of Work), if applicable.
6. As-Built Drawings.
7. As-Built Schedule.
A. When the Contractor determines that the Work is fully completed, the Contractor
shall submit the Authority a written Request for Acceptance of Work. Within 30
Days after receipt of the Contractor’s Request for Acceptance of Work, the
Authority shall review all requirements of the Work and either:
B. If the Authority rejects the Contractor’s Request for Acceptance of Work, the
Contractor shall promptly remedy the defective or uncompleted Work items.
Thereafter, the Contractor shall again give Authority a written Request for
Acceptance of Work. The foregoing procedure shall apply successively thereafter
until Authority has issued the Contractor a Certificate of Final Acceptance.
C. Authority reserves the right to direct any and all Punch List work prior to completion
of Work or Final Acceptance. Notwithstanding any other provision of this Contract
that could be interpreted to the contrary (including in Contract Documents of higher
precedence), it shall be the Contractor’s continuing responsibility to complete and
deliver every portion, and the integrated whole, of the Work in accordance with all
of the requirements of the Contract. The issuance of a Certificate of Substantial
Completion by Authority shall not be construed to relieve the Contractor of this
responsibility, or any part thereof. If, after the issuance of a Certificate of
Substantial Completion, the Authority discovers any deficiency, or item not
completed or otherwise requiring correction or remedial action, whether or not the
item appears on any Punchlist or other list of clean up items, Authority may direct
the work to be performed and the Contractor shall correct the deficiency, complete
the item or otherwise remedy the condition to bring it into full compliance with the
Contract prior to Final Completion and Authority’s acceptance of the Work.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 77 19
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for preparing operation
and maintenance manuals, including the following:
B. Emergency manuals
1.03 DEFINITIONS
2. Name each indexed document file in the composite electronic index with
the applicable item name. Include a complete, electronically linked
C. Initial Manual Submittal: Submit a draft copy for Authority approval of each manual
at least 30 days before commencing demonstration and training. The Authority will
comment on whether the general scope and content of the manual are acceptable.
D. Final Manual Submittal: Submit each manual in final form prior to requesting
inspection for Substantial Completion, and at least 21 days before commencing
demonstrations and training. The Authority will provide comments for revisions as
needed.
E. Correct or revise each manual to comply with the Authority's comments. Submit
copies of each corrected manual within 15 days of receipt of the Authority's
comments, and prior to commencing demonstration and training.
In preparation of operation and maintenance data, use personnel thoroughly trained and
experienced in the operation and maintenance of the equipment or systems involved.
Where manuals require written instructions, provide technical writing that clearly
communicates essential data. Where maintenance manuals require drawings or
diagrams, prepare drawings clearly, in an understandable format. Where operation and
maintenance documentation includes information on installations by more than one
factory-authorized service representative, assemble and coordinate information furnished
by those representatives and prepare manuals.
PART 2 - PRODUCTS
1. List of documents
2. List of systems
3. List of equipment
4. Table of contents
1. Title page
2. Table of contents
3. Manual contents
4. Date of submittal
7. Names and contact information for major consultants to the Engineer that
designed the systems contained in the manuals
C. Table of Contents: List each product included in the manual, identified by product
name, indexed to the content of the volume, and cross-referenced to the
Specification Section number in the Project manual.
3. Operating standards.
4. Operating procedures.
5. Operating logs.
6. Wiring diagrams.
7. Control diagrams.
1. Product name and model number. Use designations for products indicated
on the Contract Documents. Include manufacturer's name, equipment
identification, with the serial number of each component.
1. Start-up procedures.
5. Instructions on stopping.
1. Instructions on stopping
A. Organize manual into a separate section for each product, material, and finish.
Include source information, product information, maintenance procedures, repair
materials and sources, and warranties and bonds, as described below.
B. List each product included in the manual, identified by product name and arranged
to match the manual’s table of contents. For each product, list:
1. Name
2. Address
2. Manufacturer's name
1. Inspection procedures
5. Repair instructions
G. Warranties and Bonds: Include copies of warranties and bonds and lists of
circumstances and conditions that would affect the validity of warranties or bonds.
Include the procedures to follow and the notifications required for warranty claims.
A. List each system, subsystem, and piece of equipment not part of a system,
included in the manual, identified by product name and arranged to match the
manual's table of contents. Include source information, manufacturers'
maintenance documentation, maintenance procedures, maintenance and service
schedules, a spare parts list, maintenance service contracts, and warranty and
bond information, as described below. For each product list:
1. Name
2. Address
C. Maintenance Procedures: Include the following information and items that detail
essential maintenance procedures:
2. Troubleshooting guide
G. Spare Parts List and Source Information: Include lists of replacement and repair
parts, with parts identified and cross-referenced to the manufacturers'
maintenance documentation and local sources of maintenance materials and
related services.
I. Warranties and Bonds: Include copies of warranties and bonds and lists of
circumstances and conditions that would affect the validity of warranties or bonds.
Also include procedures to follow and required notifications for warranty claims.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 78 23
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for all warranties and
guarantees necessary for Contract closeout.
A. Compile digital files (PDF) of each required warrantee and guarantee properly
executed by the Contractor, or by the Contractor and Subcontractor, Supplier, or
manufacturer. Collect and assemble all warranties and guarantees into PDF format
and provide to SCRRA for final review and acceptance. Prior to submission, verify
that documents are in proper form, contain all required information, and are
properly signed.
B. Organize the warranty documents into an orderly sequence based on the table of
contents of the Specifications and CSI Master Format 04 and the table of contents
of the Project manual.
1. Warranty Electronic File: Scan warranties and bonds and assemble the
complete warranty and bond submittal package into a single indexed
electronic PDF file, with links enabling navigation to each item. Provide a
bookmarked table of contents at the beginning of the document.
C. Special Project Warranty and Manufacturer's Guarantee Forms: Forms for Special
Project warranties and for manufacturer's guarantees are included at the end of
this Section. Prepare document utilizing the appropriate form, ready for execution
by the Contractor or the Contractor and Subcontractor, Supplier, or manufacturer.
Submit a draft to the Authority though the Engineer for approval prior to final
execution.
2. In other cases, submit a draft of the guarantee to the Authority for approval
prior to final execution of the guarantee.
D. Final Submittal: Submit fully executed copies of warranties and guarantees within
seven days of the date of Substantial Completion, but not later than three days
prior to the date of application for final payment.
C. Related Damages and Losses: When correcting warranted Work that has been
found defective, remove and replace other Work that has been damaged as a
result of such defect or that must be removed and replaced to provide access for
correction of the warranted Work.
E. Replacement Cost: Upon determination that Work covered by a warranty has been
found to be defective, replace or reconstruct the Work to a condition acceptable to
the Authority, complying with applicable requirements of the Contract Documents.
The Contractor shall be responsible for all costs for replacing or reconstructing
defective Work, regardless of whether the Authority has benefited from use of the
Work through a portion of its anticipated useful service life.
G. Rejection of Warranties: The Authority reserves the right to reject warranties and
disallow the use of products with warranties in conflict with Contract Document
requirements.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this Section.
END OF SECTION 01 78 36
PART 1 - GENERAL
1.01 SUMMARY
This Section addresses administrative and procedural requirements for preparing project
As-Built drawings, specifications, product data and other miscellaneous documents
submitted as required by the Contract.
PART 2 - PRODUCTS
A. Record Prints: Maintain one set of marked-up paper copies of the Contract
Drawings and Shop Drawings, incorporating new and revised drawings as
modifications are issued.
2. Content: Types of items requiring marking include, but are not limited to,
the following:
4. Mark the As-Built set digitally with red line annotation on the PDF. Use
other colors to distinguish between changes for different categories of the
Work at same location.
2. Mark copy with the proprietary name and model number of products,
materials, and equipment furnished, including substitutions and product
options selected.
3. Record the name of the manufacturer, supplier, and Installer, and include
other information necessary to provide a record of the selections made.
4. For each principal product, indicate whether record Product Data has been
submitted in operation and maintenance manuals instead of submitted as
record Product Data.
5. Note related Change Orders, record Product Data, and record Drawings
where applicable.
B. Format: Submit As-Built Specifications as paper copy and scanned PDF electronic
files of the marked-up paper copy of the Specifications.
The most current approved construction schedule shall be marked by red line annotation
on the PDF showing all deviations occurring since the schedule was approved. Submit the
final “As-Built” Project Schedule as paper copy and a scanned PDF electronic file of the
marked-up paper copy of the final Project Schedule.
2. Include significant changes in the product delivered to the Project site, and
changes in the manufacturer's written instructions for installation.
B. Format: Submit record Product Data as paper copy and scanned PDF electronic
file(s) of the marked-up paper copy of the Product Data. Include a record Product
Data directory organized by Specification Section number and title, electronically
linked to each item of the record Product Data.
B. Format: Submit miscellaneous record submittals as paper copy and scanned PDF
electronic file(s) of marked-up miscellaneous record submittals. Include a
miscellaneous record submittals directory organized by Specification Section
number and title, electronically linked to each item of the miscellaneous record
submittals.
PART 3 - EXECUTION
A. The monthly progress payment application will not be processed by the Authority
until the Contractor is found by the Authority to have completely and accurately
recorded all as-built information for Work performed through the period of the
progress payment application.
B. Store any non-digital record documents and Samples in the field office. Provide
access to As-Built documents for the Authority’s reference.
A. Work of this Section is considered incidental to Work under other payment items
and no separate measurement or payment will be made to the Contractor for Work
of this Section. As-Built drawings and photographs will be reviewed each month
and the monthly progress payment will only be approved and processed if the
Contractor is found by the Authority to be in conformance with the requirements of
this Section.
B. If the Contractor does not provide both the As-Built Summary and Record
Documents for Authority review, the Contractor’s final pay request or other
applicable progress payment request may be withheld until proper as-built and
record documents are provided.
END OF SECTION 01 78 39
PART 1 - GENERAL
1.01 SUMMARY
This Section includes administrative and procedural requirements for instructing the
Authority's personnel, including the following:
D. Attendance Record: For each training module, submit a list of participants and
the length of the instruction time.
E. Evaluations: For each participant and for each training module, submit the results
and documentation of a performance-based test.
Demonstration and Training Video Recordings: Submit the recordings within seven days
of the end of each training module.
1. Name of Project
B. Transcript: Prepared in PDF electronic format. Include a cover sheet with the
same label information as the corresponding video recording, and a table of
contents with links to corresponding training components. Include the name of
the Project and the date of the video recording on each page.
1.06 COORDINATION
1. Inspect and discuss locations and other facilities required for instruction.
2. To avoid delays, review and finalize the instruction schedule and verify
the availability of educational materials, instructors' personnel, audiovisual
equipment, and facilities needed.
PART 2 - PRODUCTS
2. Equipment, including but not limited to loading dock equipment and waste
compactors: 2 hours each
B. Training Modules: Develop a learning objective and teaching outline for each
module. Include a description of specific skills and knowledge that participant is
expected to master. For each module, include instruction for the following as
applicable to the system, equipment, or component:
c. Operating standards
d. Regulatory requirements
e. Equipment function
f. Operating characteristics
g. Limiting conditions
h. Performance curves
a. Emergency manuals
b. Operations manuals
c. Maintenance manuals
e. Identification systems
b. Instructions on stopping
a. Startup procedures
e. Control sequences
f. Safety procedures
g. Instructions on stopping
a. Alignments
b. Checking adjustments
a. Diagnostic instructions
a. Inspection procedures
a. Diagnosis instructions
b. Repair instructions
PART 3 - EXECUTION
3.01 PREPARATION
3.02 INSTRUCTION
1. The Authority will provide the instructor to the basis of system design,
operational requirements, criteria, and regulatory requirements.
3. The Authority will provide the Contractor with names and positions of
participants.
1. Schedule training with the Authority with at least seven days advance
notice.
G. Cleanup: Collect used and leftover educational materials and deliver to the
Authority. Remove instructional equipment. Restore systems and equipment to
the condition existing before initial training use.
B. Video: Provide minimum 1280 x 720 video resolution converted to a format file
type acceptable to the Authority, on electronic media.
2. File Hierarchy: Organize the folder structure and file locations according
to the Project manual table of contents. Provide a complete screen-based
menu.
3. File Names: Utilize file names based on the name of the equipment
generally described in the video segment, as identified in Project
Specifications.
b. Business address
d. Point of contact
e. E-mail address
D. Light Levels: Verify light levels are adequate to properly light equipment. Verify
equipment markings are clearly visible prior to recording. Furnish additional
portable lighting as required.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this
Section.
END OF SECTION 01 79 00
PART 1 - GENERAL
1.01 SUMMARY
Commissioning is the process by which the Contractor will demonstrate to SCRRA that it
has completed the project in conformance with the contract documents and that the
project will perform as specified in the contract documents. This Section includes
general requirements that apply to implementation of commissioning for systems,
assemblies, or components. Authority will require the Contractor to perform facility
commissioning for the purpose of verifying compliance of the project to the requirements
of the contract along with any amendments approved by Authority during the
construction process. The Contractor shall be solely responsible for providing all test and
commissioning equipment, tools, software, programming, programming support and
incidentals and qualified technicians to start–up, calibrate, debug and verify proper
function of the systems and sub-systems as required by the Commissioning Plan.
The Contractor shall assign representatives with expertise and authority to act on its
behalf, and shall schedule them to participate in and perform commissioning process
activities including, but not limited to, the following:
C. Organize and lead the commissioning team and convene the commissioning
team meetings held on a weekly basis. Integrate and coordinate commissioning
process activities with the construction schedule.
The Contractor shall have completed all start-up procedures and testing, all adjusting
and balancing required for all of the component systems and all systems and sub-
systems shall be fully functional and operating in normal operational mode before the
commissioning plan is implemented and completed. This includes the complete
installation of all equipment, materials, controls, etc. per the contract, scoping
documents and related directives, clarifications, approved changes, etc.
F. Systems to be commissioned
Corrective work shall be completed in a timely fashion to permit the timely completion of
the commissioning process. Experimentation to render system performance will be
permitted. If Authority deems the experimentation work to be ineffective or untimely to
the commissioning process, Authority will notify the Contractor indicating the nature of
the problem, expected steps to be taken and the deadline for completion of activities. If
the deadline passes without resolution of the problem, Authority reserves the right to
obtain supplementary services and equipment to resolve the problem. Costs incurred to
solve the problems in an expeditious manner will be the sole responsibility of the
Contractor.
The Commissioning Field Book will be created by the Contractor to identify and track all
pertinent commissioning documentation required during the installation start-up, check-
out and commissioning phases. The Field Book will be managed and maintained by the
Contractor in digital format and will be made available to all subcontractors for their use.
The Field Book provides a central location for the subcontractors and Authority to
identify, copy, and organize all pertinent information. The Field Book will at a minimum
include the following format:
D. Tabs for each specification section with copies of pre-functional and functional
test check sheets provided by coordination of subcontractors and Authority for
Contractor completion and space for related contractor-supplied documents.
Using the Pre-functional Construction Checklists, the Contractor must verify that the
systems installed are in compliance with the Construction Documents and are fully
functional. Commissioning is not intended to be a testing or inspection function that
replaces any of the Contractor’s or subcontractors’ obligations for testing and proof of
performance. Functional testing will only begin when checklists are completed by the
appropriate subcontractors, initialed, signed and returned to the Contractor.
1.12 DOCUMENTATION
When a Project Report is issued to address an identified deficiency, the Contractor shall
forward the reports to the appropriate parties to initiate corrective action in an
expeditious manner. The Engineers of Record are relied on for supplemental
instructions or design modifications and issuance of final design details and the
Contractor, subcontractors and equipment suppliers are relied on for implementation of
that design.
Work of this Section is considered incidental to Work under other payment items and no
separate measurement or payment will be made to the Contractor for Work of this
Section.
END OF SECTION 01 91 13
REINFORCING STEEL
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.2 REFERENCES
4. A706, Standard Specification for Deformed and Plain Low-Alloy Steel Bars
for Concrete Reinforcement.
1.3 SUBMITTALS
A. Shop Drawings:
A. Qualifications:
2. Welding operators must have been qualified during the previous 12 months
prior to commencement of welding.
B. Ship to jobsite with attached plastic or metal tags with permanent mark numbers
which match the Shop Drawing mark numbers.
2. Handle bundled bars to prevent sagging that could damage the coating.
PART 2 - PRODUCTS
2.2 MATERIALS
D. Smooth Dowel Bars: ASTM A615, grade 60 with metal end cap to allow
longitudinal movement equal to joint width plus 1 inch.
E. Epoxy-Coated Rebars: ASTM A775 and ASTM A615, Grade 60, meeting Annex
A1 for epoxy coating.
2. Inert in concrete.
4. Obtained from the manufacturer of the epoxy resin that was used to
originally coat the rebars.
H. Welding Electrodes:
2.3 ACCESSORIES
A. Metal Chairs, Runners, Bolsters, Spacers, Hangers, and Other Rebar Supports:
2.4 FABRICATION
A. Tolerances:
1. Place on each tag the mark number of the rebar corresponding to the mark
number indicated on the Shop Drawing.
3. For epoxy-coated rebars, use only plastic tags secured to rebars by nylon
or plastic ties.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Tolerances:
1. Rebar placement:
c. Beam and slab rebars shall be threaded through the column vertical
rebars without displacing the column vertical rebars and still
maintaining the clear distances required for the beam and slab
rebars.
1. Three (3) inches for concrete cast against earth, 2 inches all other
locations.
a. Service splices and ultimate butt splices shall be either butt welded
or mechanical splices, shall be used at the locations shown on the
plans, and shall conform to the requirements of these Specifications
and the Plans.
8. Mechanical Splices:
a. Mechanical splices shall not be used for any reinforcing steel in the
“Ultimate Splice Zone” as indicated on the Plans.
c. Only the joint details and dimensions as shown in Figure 3.2, "Direct
Butt Joints," of AWS D 1.4, shall be used for making complete joint
penetration butt welds of bar reinforcement.
d. Butt welds shall be made with multiple weld passes using a stringer
bead without an appreciable weaving motion.
g. In the event that any of the specified preheat, interpass, and post
weld cooling temperatures are not met, all weld and heat affected
zone metal shall be removed and the splice rewelded.
a. Testing and reporting of test results for Service and Ultimate Butt
Splices shall conform to the California Department of
Transportation Standard Specification, Section 52 Reinforcement.
E. Placing Rebars:
3. Rebar support:
a. Uncoated rebar:
b. Coated rebar:
10. Embed rebars into hardened concrete utilizing adhesive anchor system
specifically manufactured for such installation:
2. Do not place any concrete until the Engineer submits a solution to rebar
congestion problem.
4. If rebars are moved more than one bar diameter, obtain Engineer's
approval of resulting arrangement of rebars.
1. Coated rebars will be inspected on the jobsite for handling defects, coating
abrasion, coating thickness and continuity of coating.
2. Engineer may defer final inspection of rebar coating integrity and repairs
until the rebars have been erected and all handling is completed.
5. Rebar welds and adjacent bare rebar areas to also be patched after
welding is completed.
3. Test three (3) samples of each bar size and each type of weld in accord
with AWS D1.4.
a. The tensile strength of each test shall be not less than 125 percent
of the required yield strength of the rebar tested.
a. In addition, if any welds are found defective, test five (5) previous
welds performed by same welder.
4.1 MEASUREMENT
A. Reinforcing Steel will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. If a nominal weight is not available, steel will be assumed to have a unit weight of
490 lbs per cu ft of volume.
4.2 PAYMENT
B. Full compensation for furnishing all tie wires, blocks, chairs and other supporting
devices shall be considered as included in the contract Unit Price by the unit and
no separate payment will be made therefore.
C. Full compensation for furnishing and testing sample splices, for radiographic
examinations performed by the Contractor and for furnishing access facilities for
inspection and non-destructive testing by the Engineer shall be considered as
included in the Contract Unit Price by the unit and no additional compensation will
be allowed therefore.
END OF SECTION 03 21 00
STRUCTURAL CONCRETE
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1. C31, Standard Practice for Making and Curing Concrete Test Specimens
in the Field.
5. C138, Standard Method of Test for Density (Unit Weight), Yield, and Air
Content (Gravimetric) of Concrete.
10. C173, Standard Test Method for Air Content of Freshly Mixed Concrete by
the Volumetric Method.
11. C231, Standard Test Method for Air Content of Freshly Mixed Concrete by
the Pressure Method.
16. C618, Standard Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use in Concrete.
17. C1077, Standard Practice for Agencies Testing Concrete and Concrete
Aggregates for use in Construction and Criteria for Testing Agency
Evaluation.
20. D994, Standard Specification for Preformed Expansion Joint Filler for
Concrete (Bituminous Type).
22. D1751, Standard Specification for Preformed Expansion Joint Filler for
Concrete Paving and Structural Construction (Nonextruding and Resilient
Bituminous Types).
1.03 DEFINITIONS
1.04 SUBMITTALS
A. Shop Drawings:
1) Location of use
3) Target strength
10) Slump.
1) Joint fillers.
2) Curing agents.
4. Reinforcing steel:
A. Quality Assurance:
2. Do not begin concrete production until proposed concrete mix design has
been approved by Engineer.
B. Qualifications:
2. Formwork, shoring and reshoring for slabs and beams except where cast
on ground to be designed by a professional engineer currently registered
in the state where the Project is located.
A. Storage of Material:
2. Aggregate:
3. Admixtures:
B. Delivery:
1. Concrete:
c. Ticket to show:
2) Quantity delivered.
PART 2 - PRODUCTS
A. Subject to compliance with the Contract Documents, the following products and
manufacturers are acceptable, or approved equivalent as a comparable product:
2. Epoxy grout:
a. .
b. Rubatex Corp.
4. Form coating:
5. Prefabricated forms:
c. Universal "Uniform."
6. Bonding agent:
7. Calcium nitrate:
1) DCI.
2) DCI'S.
1) Eucon BCN.
2) Eucon CIA.
2.02 MATERIALS
B. Fly Ash:
2. Non-Staining.
5. Obtain proposed fly ash from a source approved by the State Highway
Department in the State of California for use in concrete for bridges. A list
of pre-approved products may be obtained from the following website:
http://www.dot.ca.gov/hq/esc/approved_products_list/
C. Admixtures:
3. Maximum total water soluble chloride ion content contributed from all
ingredients of concrete including water, aggregates, cementitious materials
and admixtures by weight percent of cement:
E. Aggregates:
2. Fine aggregate:
3. Coarse aggregate:
F. Concrete Grout:
2. Epoxy grout:
G. Forms:
2. Wood forms:
3. Metal forms:
5. Form ties:
e. Provide ties with built-in waterstops at all walls that will be in contact
with process liquid during plant operation.
6. Form release: Nonstaining and shall not prevent bonding of future finishes
to concrete surface.
I. Bonding Agent:
1. High solids acrylic latex base liquid for interior or exterior application as a
bonding agent to improve adhesion and mechanical properties of concrete
patching mortars.
b. ASTM D994.
3. Other use:
b. ASTM D1751.
K. Bead Board
1. The bead board panels shall be a minimum of two (2) inch thick, four (4)
feet wide, and 8 feet long and shall meet the requirements of ASTM C578.
A. General:
B. Strength:
1. Provide specified strength and type of concrete for each use in structure(s)
as follows:
Reinforced Structures
Miscellaneous
C. Air Entrainment:
1. Provide air entrainment in all concrete resulting in a total air content percent
by volume as follows:
3. Pumped concrete:
a. Provide additional water at batch plant to allow for slump loss due
to pumping.
E. Selection of Proportions:
1. General:
2. Minimum cement contents and maximum water cement ratios for concrete
to be as follows:
3. The Contractor may perform trial mixes prior to the delivery in order to
adjust the desired air content, set time, and slump.
PART 3 - EXECUTION
A. Formwork:
6. Coat form surfaces with form release agents prior to placing reinforcing
bars in forms.
5. Thoroughly clean and remove all laitance and loose and foreign particles
from construction joints.
C. Embedments:
1. Set and build in anchorage devices and other embedded items required for
other work that is attached to, or supported by concrete.
2. Use setting diagrams, templates and instructions for locating and setting.
D. Placing Concrete:
6. Where free fall of concrete will exceed 4 feet, place concrete by means of
tremie pipe or chute.
F. Protection:
OUTDOOR CONCRETE
TEMPERATURE AT TEMPERATURE AT
PLACEMENT (IN SHADE) MIXING
Below 30˚ F 70˚ F
Between 30˚-45˚ F 60˚ F
Above 45˚ F 50˚ F
G. Curing:
8. If forms are removed before 7 days have elapsed, finish curing of formed
surfaces by one of above methods for the remainder of the curing period.
b. Allow the preceding coat to completely dry prior to applying the next
coat.
d. Vertical surface at the time of receiving the first coat shall be damp
with no free water on the surface.
H. Form Removal:
2. Remove fins and projections, and patch voids, air pockets, and honeycomb
areas with cement grout.
1. Patch voids, air pockets and honeycomb areas with cement grout.
C. Troweled Finish:
D. Broom Finish: Immediately after concrete has received a float finish as specified,
give it a transverse scored texture by drawing a broom across surface.
3.03 GROUT
A. Preparation:
B. Application:
2. Epoxy grout:
b. Completely fill all cavities and spaces around dowels and anchors
without voids.
A. SCRRA will select a concrete testing agency that meets ASTM C1077-12 criteria
and requirements. The Contractor will pay for services of a concrete testing
agency to perform testing of concrete placed during construction.
1) One at 7 days.
2) Two at 28 days.
b. Not less than one test for each 50 cy or major fraction thereof placed
in one day.
c. Not less than one test for each type of concrete poured.
d. Not less than one test for each concrete structure exceeding 2 cy
volume.
3. Slump test:
4. Air content:
C. Evaluation of Tests:
D. Acceptance of Concrete:
3.05 SCHEDULES
A. Form Types:
B. Grout:
2. Epoxy grout:
C. Concrete Finishes:
1. Unformed surfaces:
4.01 MEASUREMENT
A. Concrete Structures will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
C. Concrete Pavement will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
D. Concrete in structures will be measured by the neat line dimensions shown on the
Plans or such other dimensions as may be ordered by the Engineer. No deduction
will be made for the volume occupied by bar reinforcing steel or other embedded
steel items.
E. Precast Concrete Members will be measured by the various types and lengths
shown in Contract Documents and for erecting the members as shown in the
Contract Documents.
F. Concrete Pavement area to be paid for will be calculated on the basis of the
dimensions shown on the Plans adjusted by the amount of any change ordered by
the Engineer. No allowance will be made for concrete pavement placed outside
those dimensions unless otherwise ordered by the Engineer.
G. Concrete and Concrete Aggregate Testing for field quality control conducted by
the testing agency selected by SCRRA is considered incidental to work under other
payment items under this Section and no separate measurement and payment will
be made to the Contractor.
4.02 PAYMENT
D. The Contract Unit Price for concrete structures shall include full compensation for
all work involved in constructing the concrete work, complete-in-place, as shown
on the Plans, as specified in these Specifications and as directed by the Engineer.
E. The Contract Unit Price for concrete structures shall include full compensation for
all forming and shoring, joints, joint filler, joint seals and waterstops necessary for
constructing the concrete work complete-in-place.
F. The Contract Unit Price for concrete in reinforced concrete box and culverts, and
in headwalls, endwalls, and wingwallls for culverts shall also include the payment
for the earthwork involved with such structures.
G. The Contract Unit Price paid for furnishing precast concrete members shall include
full compensation for including reinforcing and prestressing steel as required, and
for doing all work involved in constructing and furnishing precast members at the
site of the work complete and ready for erection, as shown on Plans, and as
specified in these Specifications, and as directed by the Engineer.
I. All holes remaining in the concrete pavement after the thickness measurements,
if required, shall be completely filled by the Contractor, at the Contractor’s
expense.
K. Concrete and Concrete Aggregate Testing shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 03 31 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes:
4. Place bolts, anchors, hardware, metal frames and other insert items.
B. Related Specification Sections include but not are not necessarily limited to:
1.02 REFERENCES
A. All Work specified herein shall conform to or exceed the applicable requirements
of the referenced portions of the following publications to the extent that the
provisions thereof are not in conflict with other provisions of these Specifications.
1. ASTM C140, Standard Test Methods for Sampling and Testing Concrete
Masonry Units and Related Units.
1.03 SUBMITTALS
1. Samples: Submit 3 samples each of each type of masonry unit required for
work to SCRRA for review prior to ordering, receiving or installing units in
field.
A. Concrete Masonry units: Sample and test in accordance with ASTM C140.
E. Compressive Tests:
1. Mortar: Not less than 900 psi at 7 days and 2,800 psi at 28 days.
2. Grout: Not less than 1,000 psi at 7 days and 2,000 psi at 28 days.
3. Do not test 28 day specimen when 7 day tests exceed 28 day requirements.
G. All costs incurred for retests and re-inspections required because of failure of
original tests will be charged to Contractor, and deducted from Contract price by
Change Order.
H. Should core testing be required by the Engineer, all masonry cut or damaged by
coring operation shall be removed and replaced with new masonry to match
adjoining work. All costs of removal and replacement shall be borne by Contractor.
A. Store units above ground on level platforms which allow air circulation under
stacked unit.
C. Handle units on pallets or flat bed barrows. Free discharge from conveyor units or
transportation in mortar trays not permitted.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Concrete Unit Masonry: Modular medium weight conforming to ASTM C90, grade
N-1 (Hollow load-bearing concrete unit masonry). Angelus Block Co. (818) 767-
8576
F. Admixture for Grout: Grout Air No. 2 use, as manufactured by Sika Chemical
Corporation, must be approved by SCRRA, see Section 01 40 00 - Quality
Requirements.
H. Cleaning Materials: Shure Klean No. 600 Detergent by Process Solvent Co. Inc.
PART 3 - EXECUTION
A. Mortar
B. Colored Mortar custom match samples shall be submitted for approval prior to
construction.
C. Grout: Dry, loose volumes. Mix proportions shall be verified by Material Testing
Laboratory.
E. Mixing: Place, sand, cement, and water in mixer in that order, while mixer is
running; mix for 3 minutes, add lime, and admixture (for grout), and continue mixing
until a uniform mass is secured, but in no case less than 10 minutes.
F. Retempering Time Limit; Retemper on mortar boards, for not less than 3 minutes
not more than 10 minutes when required, by adding water into a basin formed by
mortar, and working mortar into it. Dashing, or pouring of water over mortar will not
be permitted.
2. 2. Discard mortar which has not been used within one-hour after
original mixing.
G. Ready-Mix Grout: Grout batched off-site and delivered by mixer truck shall be
subject to same procedures and controls as prescribed in UBC. See Section 01
40 00 - Quality Requirements.
A. Workmanship: Erect masonry plumb and truc to line; with straight, level joints of
uniform thickness. Maintain proper equipment, skilled masons, and adequate
supervision. Keep masonry clean during and after laying.
2. Assist other trades with built-in items which require cutting and fitting of
masonry.
3. Cut block units with a steel saw or carborundum wheel. Trowel or chisel
cutting will not be permitted.
C. Shoring: Provide, in place, temporary shoring for lintels, strong enough to carry
load without deflecting. Remove temporary shoring after masonry has been in
place 28 days.
D. Laying Block: Clean all dirt and dust from surfaces before laying.
2. After bond bed has hardened slightly, spread mortar to required joint
thickness. Lay blocks with 3/8” mortar bed on entire horizontal surface. Fill
head joint solid, shove tightly to adjoining units. All joints shall be 3/8”.
b. No toothing allowed.
3. Anchor Bolts: Provide 1” minimum grout space around all protruding bolts.
6. Grouting: Unless noted otherwise on Drawings, completely fill all cells with
grout.
A. After mortar in joints has firmly set, cores are cleaned of mortar and debris,
reinforcing is properly in place and checked, grout cells in 2’-0”. Maximum lifts,
using specified pea gravel grout mix.
C. Grout may be placed by pump, tremie or bucket, using hoppers to avoid spilling on
exposed surfaces.
D. Place an initial 2’-0” high lift all around thoroughly compact, then place balance of
each lift, compacting again through total lift, using hardwood spading sticks or
pencil vibrators.
F. Remove and discard spilled grout from upper units before grout can harden.
G. Bracing: Adequately brace walls against wind and other forces during construction.
C. Use bond beam units, inverted for start course, and omit alternate blocks or cut
openings in alternate face shell on bottom course for cleanouts.
D. Use a hardwood stick to knock off projecting mortar fins. Wash out every cell
thoroughly using a water jet which has sufficient force to remove all mortar from
the interior of the cells and from reinforcing steel.
E. Plug each cleanout by setting a “soap” in mortar into opening and securely bracing
it in place to prevent displacement. If masonry is not exposed in finish work,
cleanouts may be formed.
F. Grouting:
2. Do not place grout until masonry has set a minimum of 3 days in warm 50˚
to 85˚ F. weather or 5 days in cool 35˚ to 50˚ F. damp weather.
3. Pump grout from mixer into grout cell space as rapidly as practical. Discard
grout not in place within one hour after water was first added to batch.
G. Compacting:
3. Top lift shall be re-compacted not sooner than 30 minutes after grout has
been placed.
H. Bracing: Adequately brace walls against wind and other forces during construction.
B. Do not saturate masonry with water for curing or any other purposes.
C. Where atmosphere is dry, dampen the wall surface with a very light fog spray for
3 days to help cure mortar in joints.
D. At completion of masonry work, remove all misplaced mortar, grout or other foreign
substances, and clean surfaces which will be exposed in finish work with specified
cleaner, or with clean water and stiff fiber brushes.
4.01 MEASUREMENT
A. Concrete Unit Masonry will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
A. Concrete Unit Masonry furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
END OF SECTION 04 22 00
ENVIRONMENTAL PAVING
PART 1 - GENERAL
1.01 DESCRIPTION
A. The work specified in this Section includes providing labor, materials, tools and
equipment to furnish and install a permeable concrete paving stone system
(Environmental Paving Section) as indicated on the plans and as specified herein.
C. The Environmental Paving Section was derived from the “Permeable Interlocking
Concrete Pavements” publication by the Interlocking Concrete Pavement Institute
(ICPI), and from systems similar to the “Bio-Aquifer Storm System (BASS) supplied
by Orco Pavingstones of Riverside, California, located at www.orco.com. This
system or an approved equal permeable paving system with nominal ½ inch
spacer bars to provide permeability, may be proposed by the Contractor.
In addition to the sample section provided by the representative “BASS” system, the
structural section will include an additional sand filter base course composed of 6” of
clean concrete sand.
Coordinate the Work of this Section with all other Contract Documents and in particular:
B. Section 31 20 00 - Earthwork
1.03 REFERENCES
1.04 DEFINITIONS
A. Base Course: Layer of open-graded aggregate beneath the bedding course layer,
comprised of small- to medium-particle-sized crushed stone (typically 1/2” to 1”).
Recommended depth of the base layer shall be four inches (4”), but shall not
exceed six inches (6”).
B. Bedding Course: Layer of open-graded aggregate directly beneath the unit pavers,
comprised of small particle-sized crushed stone chips (typically 1/4” to 3/8” rock).
Also commonly called the “setting bed”. Recommended depth of the bedding
course layer shall be two inches (2”).
C. Bundle: Several layers of paver clusters stacked vertically, packaged, and tagged
for shipment. Also commonly called a “cube”.
D. Chamfer: A 45-degree beveled edge around the top of a paver unit, usually 1/8” to
¼” wide. It helps prevent edge chipping and delineates the individual paver units.
E. Cluster: The group of pavers forming a single layer taken from a bundle of pavers
or the group of pavers held by the clamp of a paver laying machine.
F. Flats: The portion of the vertical side faces of a paver other than the spacer bars.
G. Laying Face: The working edge of the pavement where the laying of pavers is
occurring.
I. Method Statement: The paver installer’s and manufacturer’s plan for construction
and quality control of the pavers.
J. Spacer Bars: Small protrusions on each side of pavers which are used have spacer
bars.
K. Sub-base Course: Layer of open-graded aggregate beneath the base course layer,
comprised of large particle-sized (typically 2-1/2” to 3”) crushed stone. Depth shall
vary depending upon site conditions and specific requirements. Minimum depth of
the sub-base course shall be twelve inches (12”).
L. Void Filler: Open-graded aggregate used to fill the openings in the paver units. The
bedding course aggregate may be used as the void filler. Smaller particle-sized
stone chips (1/8” to 1/4”) are preferable, if available.
1.05 SUBMITTALS
C. Material samples of pavers showing the range of variation within the selected
color(s) for approval by SCRRA, void filler aggregate, bedding course aggregate,
base and sub-base course aggregate including a current sieve analysis of each
showing conformance to the specifications.
2. The installer and manufacturer shall agree upon a method for measuring
the clusters at the factory and in the field. That method shall be submitted
in writing to the owner for approval.
3. The Quality Control Plan shall contain at a minimum, but not limited to, the
following elements:
Pavers shall be tested for density and dimensional variation, compressive strength
(ASTM C140), density and absorption (ASTM C140) and abrasion resistance (ASTM
C418).
The initial testing frequency shall be one set of tests for each 100,000 full-sized
pavers delivered to the site or at any time a change in the manufacturing process,
mix design, cement, aggregate or other material occurs.
2. If all pavers tested pass all requirements for a sequence of 400,000 pavers
then the testing frequency may be relaxed to one set of tests for each
500,000 full-sized pavers. If any pavers fail any of the required tests then
the testing frequency shall revert to the initial testing frequency.
3. When any of the individual test results fail to meet the specified
requirements, the cube of pavers represented by that test sample shall be
rejected. The manufacturer shall provide additional testing of paver
samples taken from both before and after the rejected test sample to
determine the sequence of the paver production run that should be
rejected. In addition, the testing frequency shall revert to the initial testing
frequency specified in Item B.1 for the balance of the project.
5. Pavers shall be sound and free from defects that would interfere with the
proper placing of the pavers or impair the strength or performance of the
construction.
The installer and manufacturer shall each prepare a SSWP describing the overall
plan to complete the work. This plan shall include at a minimum:
2. A description of the anticipated mold life, rate and effect of mold wear on
pavers produced, individual mold runs, and a mold rotation plan.
3. Clear diagrams of the site showing the proposed starting point of the
installation and the proposed direction of installation.
5. A description of the anticipated growth in cluster size due to mold wear and
a plan for dealing with that growth or other dimensional variances.
7. The manufacturer’s proposed daily production rate and mold life for this
project and supply data demonstrating experience on similar past projects.
Installer shall state the proposed daily installation rate.
D. Qualifications
Every manufacturer and installer shall demonstrate that they have supplied and/or
installed Environmental pavers for projects of a similar nature. Qualifications of
installers shall be submitted at the time of bid, without exception.
A. Concrete paving stones shall be delivered to the site, with or without pallets, in
such a way that no damage occurs to the product during hauling and unloading.
B. All pavers shall be delivered to the site in approximately the chronological order in
which they were manufactured. They shall be staged on the site as per the SSWP.
PART 2 - PRODUCTS
A. All interlocking paving stones shall comply with the quality specifications for solid
concrete interlocking paving units as required per ASTM C936.
5. Compressive Strength: At the time of delivery to the work site, the average
compressive strength of the pavers shall not be less than 8,000 psi, with
no individual unit less than 7,200 psi. Testing procedures shall be in
accordance with ASTM C140.
6. Absorption: The average absorption shall not be greater than five percent
(5%) with no individual unit result greater than seven percent (7%) per
ASTM C140.
11. The measurement across a cluster from any cube shall not vary by more
than the allowable tolerance of the individual paver units (1/16” per paver
times the number of pavers across the cluster).
A. All units shall be sound and free of defects that would interfere with the proper
placing of the unit or impair the strength or permanence of the construction. Minor
cracks incidental to the usual methods of manufacture, or minor chipping resulting
from customary methods of handling in shipment, delivery and installation, shall
not be deemed grounds for rejection.
The bedding course and void filler aggregate shall be washed, crusher run, free of
organics and soluble salts, or other contaminants likely to cause efflorescence. The
grading requirement shall be in compliance with the following gradation chart.
The base course aggregate shall consist of washed, crusher run, open-graded stone
and meet the following gradation chart:
The sub-base course aggregate shall consist of washed, crusher run, open-graded
stone and meet the following gradation chart:
PART 3 - EXECUTION
3.01 SUBGRADE
A. The Engineer shall verify that the subgrade has been shaped and compacted in
conformance to the lines, grades and cross-sections shown on the plans, to
provide for the construction of the Environmental Paving System pavement
structure.
B. Site grades can be raised to the design subgrade elevation using clean native
earth fill (free of deleterious material). This fill should be placed in lifts not
exceeding six inches (6”) and compacted to a minimum of ninety-five percent
(95%) Standard Proctor density. The final subgrade profile should be uniformly
compacted to a minimum of ninety-five percent (95%) Standard Proctor density
and proof-rolled using a vibratory steel drum roller to delineate soft areas.
Removing the unstable soil and replacing with clean, dry compacted earth fill shall
be performed to repair these areas.
A. The thickness of the sub-base course layer will depend upon the subgrade soil
conditions and the anticipated traffic loadings. It is recommended that a site
assessment be carried out by an experienced qualified geotechnical engineer to
determine the required thickness of the sub-base course.
B. The sub-base course shall consist of a minimum thickness of twelve inches (12”)
and be compacted using a vibratory smooth-drum roller. It shall be installed in lifts
not to exceed six inches (6”). Upon completion of the sub-base course installation,
the area shall be proof-rolled using a heavy rubber-tired vehicle (such as a loaded
tandem truck) to identify any areas requiring additional compaction. The sub-base
course shall be installed to the elevation and cross-section per the plan
documents.
A. All edge restraints shall be constructed as shown on the plans and in place prior
to the installation of the base course, bedding course and pavers. Poured-in-place
concrete curbs are recommended for the Bio-Aquifer Storm System.
A. The base course shall consist of a thickness of four inches (4”), placed in one lift,
and be compacted using a vibratory smooth-drum roller until there is no visible
movement of aggregate under static rolling. The base course shall be installed to
the elevation and cross-section per the plan documents.
A. The bedding course shall be spread loose in a uniform layer to give a depth after
compaction of the paving units of two inches (2”), plus or minus 1/2”. The contractor
shall screed the bedding course using either a mechanical screed beam apparatus
or by the use of screed guides and boards.
B. The screeded bedding aggregate shall not be subjected to any traffic by either
mechanical equipment or pedestrian use prior to the installation of the paver units.
The voids left after the removal of the screed rails shall be filled with loose
aggregate as the paver bedding course proceeds.
A. Lay pavers in the pattern as shown on the Plans. Lay pavers away from the existing
laying face or edge restraint in such a manner as to ensure that the pattern remains
square. Chalk lines shall be used upon the bedding course to maintain straight
joint lines. Joint spacing between pavers shall be between 1/8” and 1/4”; however,
the joint width may need to be increased to 3/8” (if necessary) to maintain straight
joint lines. Lines and grades shown on the plans shall be established and
maintained during the installation of the wearing course.
B. Pavers shall be cut using a table-mounted masonry saw. Block splitting shall not
be permitted. All cut faces shall be vertical. Dry cutting of the pavers shall be
performed utilizing a dust collection system.
C. Once the pavers have been placed upon the bedding course and all cut pavers
have been inserted to provide a full and complete surface, inspect the pavers for
damaged units and remove and replace those units. Once all pattern lines have
been straightened, the void filler shall then be placed into the paver openings to
the top of the chamfer on the pavers and the surface swept broom clean.
E. On completion of vibration after void filling, the surface tolerances shall be plus or
minus ½” from finish levels. The pavers shall be flush to ½” above edge restraints.
Additional void filler material shall be swept in the paver voids, as required, to within
½” from the bottom of the chamfer on the paving stones. Upon completion, the
wearing course surface shall be swept clean of all excess materials. Remove from
the site all surplus materials, equipment and debris resulting from these
operations.
4.01 MEASUREMENT
4.02 PAYMENT
END OF SECTION 04 22 10
STRUCTURAL STEEL
PART 1 - GENERAL
1.01 SUMMARY
2. Furnish anchor bolts, loose bearing plates, wedges, guying and bracing as
required for this work.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
A. Comply with all applicable local, State and Federal Codes Standards,
Specifications and Recommended Practices, latest edition thereof and in
particular:
1.03 SUBMITTALS
1. Shop drawings: Complete shop drawings and erection diagrams for this
work. Make submittals as complete as possible on their first submittal.
2. Current qualifications and certifications for welders used for this Work.
2. Local stock steel: Local stock structural steel that can be identified by heat
number and is accompanied by mill test reports may be used without
testing provided it conforms to these Specifications.
PART 2 - PRODUCTS
2.01 MATERIALS
D. Fastening materials:
2.02 FABRICATION
A. Fabrication shall be equal to that produced in modern structural steel shops, and
shall conform to the applicable provisions contained in the AISC Code of Standard
Practice, except where the drawings or these specifications differ, they shall take
precedence.
B. Wire-brush structural steel before its fabrication to remove all loose mill scale and
heavy rust that would prohibit primer from satisfactorily bonding to it. Straighten
structural steel members that do not conform to AISC tolerances by non-injurious
methods.
3. Members without ends finished for contact bearing, which are to be framed
to other steel parts of the structure, may have a variation from the detailed
length not more than 1/16 inch for members 30 feet or shorter, and not
more than 1/8 inch for members over 30 feet long.
D. Make all holes by punching or drilling; burned holes will not be acceptable.
2. Protect painted work until paint is thoroughly dry. Do not load material for
shipment until shop coat is fully dry. Touch-up damaged primer
immediately after delivery to site.
PART 3 - EXECUTION
3.01 INSPECTION
Inspect adjacent construction and make sure that all conditions detrimental to the proper
and timely execution of this work have been corrected before proceeding.
3.02 ERECTION
A. Erect all structural steel in accordance with the Drawings and the referenced AISC
Specifications, except provide washers on bolted connections using ASTM A 325
bolts regardless of the tightening method used. Use hardened washers with high
strength bolts as required by ASTM A 325.
B. Field assembly:
3. Rolled sections, except for minor details, shall not be heated without prior
approval.
C. Contact:
D. Gas Cutting:
1. Use of a cutting torch is allowed where the metal being cut is not carrying
stress during the operation, and provided stresses will not be transmitted
through a flame-cut surface.
3. To determine the effective width of members to cut, deduct 1/8 inch from
the width of the gas cut edges.
4. Make the radius of re-entrant gas cut fillets as large as practicable, but no
less than 1 inch.
1. Material may be punched 1/16 inch larger than the nominal diameter of the
bolt, wherever the thickness of the metal is equal to or less than the
diameter of the bolt plus 1/8 inch.
2. Where the metal is thicker than the diameter of the bolt plus 1/8 inch, the
holes shall be drilled or sub-punched and reamed.
3. The die for sub-punched holes, and the drill for sub-drilled holes, shall be
1/16 inch larger than the nominal diameter of the bolt to be accommodated.
F. Bolting: Use high-strength steel bolts (A 325, slip-critical, Class A) hot dipped
galvanized. Conform to the latest edition of Specifications for Structural Joints
Using ASTM A 325 or A 490 Bolts as approved by the Research Council on
Riveted and Bolted Structural Joints of the Engineering Foundation.
1. Erect this work plumb, square and true to line and level, and in precise
positions as indicated.
H. Temporary connections:
2. No field welding or high-strength bolting shall be done until this work has
been properly aligned, plumbed and leveled.
I. Set column base plates in exact position, both as to alignment, level and elevation
and support on steel wedges, or equivalent, until the grout thereunder has
thoroughly set.
1. The center of each base shall be true to the column center within 1/16 inch.
J. Sequence: The erection of structural steel shall be carried out in proper sequence
with the work of other trades, and shall be framed, bedded, and anchored to related
work in strict accordance with the Drawings.
3.03 WELDING
A. Welding and welded joints: Detail and execute welds in accordance with the
requirements of the American Welding Society Standards D1.1, unless otherwise
modified by the referenced AISC Specifications or as otherwise noted on the
Drawings.
1. Clean welds each time the electrode is changed and chip entire area of
hand-guided and controlled flame cut edges before welds are deposited.
E. Characteristics of welds: After being deposited, welds shall be wire brushed and
shall exhibit uniform section, smoothness of welded metal, feather edges without
undercuts of overlays and freedom from porosity and clinkers. Visual inspection at
edges and ends of fillet welds shall indicate good fusion and penetration into base
metal.
F. In assembling and during welding, hold components with sufficient clamps or other
adequate means to keep parts straight and in close contact.
2. Do not weld in windy weather until adequate wind protection has been
provided and set up.
3. Welds or parts of welds found defective may be removed using the air-arc
process or power chisels and replaced with satisfactory welds.
G. Tack welds shall be subject to the same quality requirements as the final welds
except that:
1. Pre-heat is not mandatory for single pass welds which are re-melted and
incorporated into continuous submerged arc welds.
3. Tack welds not incorporated into the final weld shall be removed. Tack
welds incorporated into the final weld shall be cleaned thoroughly and
multiple pass tack welds shall have cascaded ends.
H. Peening, in accordance with AWS Article 309, is allowed at the fabricator's option.
A. Furnish all anchor bolts and connection material to be embedded in the concrete
when and as required to maintain job progress.
B. Provide the necessary drawings and templates for the setting of such anchor bolts
and connection material in the concrete forms.
A. Be responsible for maintaining bearing plates in proper location and in proper level
while they are being grouted. Note that all grouting is specified to be performed by
Section 03 31 00, Structural Concrete.
3.06 TOUCH-UP
A. Clean abraded areas of shop primer to bright metal, and touch-up with same
primer used for shop priming. Extend touch-up at least 2 inches onto sound,
undamaged primer.
A. The registered Deputy Building Inspector employed by SCRRA will inspect field
welding and high-strength bolting of structural steel framing in accordance with
Building Code Requirements. Coordinate with the registered Deputy Building
Inspector and afford him full and safe access to the work as required for the
performance of his duties.
B. The registered Deputy Building Inspector will be required to certify in writing upon
completion of this work that all welding and high-strength bolting has been
performed in accordance with the Drawings, Specifications, and Building Code
Requirements.
4.01 MEASUREMENT
A. Structural Steel will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
END OF SECTION 05 12 23
PART 1 - GENERAL
1.01 SUMMARY
A. This Section addresses the products, materials and work for the installation of
metal hand railing, stainless steel hand railing, Right-of-Way (ROW) Security
Gates, and pedestrian barricade as shown on the Contract Plans and as specified
in these Specifications, and as directed by the Engineer.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
D. American Iron and Steel Institute: Type 302 and 304 Steel
I. Use finishes for stainless steel complying with “Metal Finishes Manual” by
NAAMM.
J. The sheet Work, except as otherwise indicated or specified, shall comply with
“Architectural Sheet Metal Specifications” and “Architectural Sheet Metal Manual”
by SMACNA.
1.03 SUBMITTALS
1. Shop Drawings: In accordance with the Contract Plans, showing the details
and dimensions of all removable metal hand railing and metal hand railings,
sleeve post, and posts and fences. Note dimensions which have been field
verified.
E. Submit Shop Drawings for the fabrication and erection of stainless steel
assemblies and proprietary products which are not otherwise completely shown by
manufacturer’s data sheets. Include plans and elevations at not less than one-inch
to one-foot scale, and include details of sections and connections at not less than
three inches to one foot scale. Show anchorage and accessory items, and finishes.
A. All uncoated spots or damaged coating shall be repaired by hot-dip process. Small
areas as determined by the Engineer may be repaired by recoating them with
“Galvicon” or “Gavalloy” or approved equivalent.
C. Set handrails and posts true to location, alignment and grade as indicated in the
Contract Plans. The railings shall present a smooth, uniform appearance in their
final positions.
PART 2 - PRODUCTS
A. Pipe for post, sleeve post, rail and pickets shall be seamless steel pipe, conforming
to ASTM A53, Type S, Grade A.
2.02 GENERAL
A. Metal Surfaces – For the fabrication of Work which will be exposed to view, use
materials which are smooth and free of surface blemishes. Do not use materials
which have stains and discolorations, including welds which do not match the
materials in color and grain characteristics.
B. Surface Flatness and Edges – For exposed Work provide materials which have
been cold-rolled, cold-finished, cold-drawn, extruded, stretcher leveled, machine
cut or otherwise produced to the highest commercial standard for flatness with
edges and corners sharp and true to angle or curvature as required.
A. Use AISI Type 302 or Type 304 (at fabricator’s option), except as otherwise
indicated. Comply with the following general standards, with specific type, alloy,
heat treatment and finish as required to produce the specific Work. Finish products
to a No. 4 directional satin unless otherwise shown or specified. Protect with
adhesive paper covering.
1. Sheet – ASTM A167, ASTM A480, and AISI Type 302 or 304
A. Welding Electrodes and Filler Metal – Provide the alloy and type required for
strength, workability, compatibility, and color match after grinding smooth and
finishing the fabricated product.
B. Fasteners – Some basic metal or alloy as the metal fastened, and finished to match
in color and texture. Comply with FS FF-S-92 for machine screws. Provide the type
of fasteners indicated and provide Phillips flat-head screws for exposed fasteners.
C. Anchors and Inserts – Either furnish inserts to be set in concrete and masonry
Work, or provide other anchoring devices as required for the installation of
stainless steel Work. Furnish stainless steel or epoxy-coated inserts (See
Concrete and Masonry Sections for installation); provide toothed stainless steel
expansion bolt devices for drilled-in-place anchors.
A. Fabricate from the thicknesses, sizes and shapes indicated, or if not indicated, as
required to produce Work of adequate strength and durability, without
objectionable deflections or “oil canning.”
B. Form exposed Work true to line and level, with flush surfaces and accurate angles.
Ease exposed edges to a 1/32-inch radius, unless otherwise indicated. Miter
exposed corner joints and machine fit to a hairline joint.
C. Weld corners and seams continuously, grind smooth and flush on exposed
surfaces. For exposed metal finishes, use metals which will blend and match with
sheet metals being joined; discolorations or stains will not be acceptable for
exposed portions of natural finish metals. Comply with recommendations of AWS
for welding.
D. Provide brackets, plates and straps with each assembly, as may be required for
proper support and anchorage to other Work.
E. Cut, reinforce, drill and tap Work as may be required to receive finish hardware
and similar items of Work.
A. Comply with ANSI A12.1 and CAL OSHA requirements for railings around floor
openings and exposed edges of floors, stairs, ramps, and similar locations. Install
railings and supports able to withstand a horizontal force of 150 pounds per linear
foot and vertical force of 100 pounds per linear foot at the top or 50 pounds per
foot along the top rail, whichever is greater.
B. In tubular members, where mechanical joints are necessary, use bar stock inserts
with flat-head screws located on the least visible surfaces. Where bends are
shown, form members to a smooth, uniform radius without distortion of the cross-
sectional shape.
C. Miter and cope members at corners and intersections. Bevel, weld and grind
smooth, without fillets, to form smooth transitions and maintain sharp lines.
F. Comply with ASTM D4956 Standard Specifications for Retroreflective Sheeting for
Traffic Control for yellow sheeting on railing.
PART 3 - EXECUTION
3.01 FABRICATION
Fabrication of metal hand railings and fencing shall be in accordance with SSPWC Current
Version Sub-Section 304-2.1.2.
3.02 INSTALLATION
A. Set stainless steel Work accurately as measured from established building lines
and levels, plumb and in true alignment with previously completed Work.
Temporarily brace or anchor securely in formwork where Work is to be built into
concrete, masonry or similar construction.
C. Accurately fit mechanical joints together to form tight joints and uniform reveals
and shapes for joint fillers and sealants. Restore finishes that have been damaged
by shipment and installation.
D. Do not cut or abrade finishes which cannot be completely restored in the field.
Return units with such finishes to the shop for required alterations, followed by
complete refinishing.
F. Form bends and simple and compound curves in tubing by bending members in
jigs to produce uniform curvature, maintain profile of member throughout bend
without buckling, twisting or otherwise deforming exposed surfaces of handrail and
railing components.
H. Provide weep holes or other means for evacuation of entrapped water in hollow
Sections of railing members.
I. Provide wall returns at ends of wall mounted handrails, except where otherwise
indicated.
J. Close exposed ends of handrail and tubular rail members by use of plates welded
and ground smooth.
K. Furnish inserts and other anchorage devices for connecting handrails and railings
to concrete or masonry Work. Fabricate and space anchorage devices as indicated
and as required providing adequate support. Coordinate anchorage devices with
supporting structure.
L. The galvanized bolt thread for removable metal hand railing shall not be deformed
after installation.
N. Excavation - Remove material to the width and depth required for construction of
the pedestrian gate foundation. Take care not to disturb the bottom of the
excavation before the concrete for the foundation is placed. Replace excavation
below the required grade or more than the required width with the same class of
concrete specified for the foundation, at no additional cost to the Authority.
4.01 MEASUREMENT
A. Railings, Hand Railing, and ROW Security Gates will be measured by the unit or
fraction thereof furnished and completed in accordance with the Contract
Documents and as measured by the Engineer. The quantities as contained on the
Schedule of Quantities and Prices, or approved schedule of values, as applicable,
as derived from the Plans will be used as the basis for this measurement.
B. Pedestrian Barricade will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Railings, Hand Railing, and ROW security Gates will be paid for at the Contract
Unit Price, as listed on the Schedule of Quantities and Prices. This price shall
include full compensation for furnishing all labor, Materials, tools, equipment,
supplies, supervision, and incidentals, and doing all work, as shown on the Plans,
and as specified in these Specifications, and as directed by the Engineer.
B. Pedestrian Barricade will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
C. Full compensation for furnishing and placing concrete footings, and connecting
new railing to structures and existing cross railing shall be considered as included
as listed on the Schedule of Quantities and Prices.
END OF SECTION 05 52 00
PART 1 - GENERAL
1.01 SUMMARY
A. The work involves furnishing and installing self-closing pedestrian swing gates at the
highway-rail and pedestrian-rail grade crossings on the Metrolink commuter rail
system. Install gates on the locations shown on the Contract Plans.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
PART 2 - PRODUCTS
1. Shop-assemble and test the swing gates for proper operation before
installation at the worksite.
C. Gate Material - Fabricate the gate from steel tubing conforming to ASTM A500,
Grade B. Provide gate post caps fabricated from flat steel plate conforming to
ASTM A6, continuously welded in place, welded watertight, and made flush and
smooth with the gate posts.
1. Fabricate the gate hinges and stop plates, except for the hinge sleeves,
from steel material conforming to ASTM A36. Neatly miter and cope all
intersections, weld continuously in place and finish so that adjoining surfaces
are flush and smooth.
2. Fabricate the gravity gate hinge top and bottom sleeves from hardened steel
conforming to ASTM A4140 heat treated and borided. Precision machine
to the nearest 0.001 of an inch. Polish the rotating curved contract surfaces
of the top and bottom hinge sleeves.
E. Galvanizing - After fabrication, hot-dip galvanize the swing gates including the gate
posts, gate frames, hinges (except the rotating curved contact surfaces of the top
and bottom hinge sleeves), and stop plates, in accordance with ASTM Al23 or
ASTM A153. Provide minimum weight of the galvanizing coating of 2.0 ounces per
square feet. Repair and re-coat any coating which has been shop or field cut,
burned by welding, or otherwise damaged so that the base metal is not exposed.
F. Gate Signs - Provide signs as indicated in the Contract Plans. Use reflective
sheeting on 0.080-inch aluminum sign panel. Provide anti-graffiti coating per Section
09 96 23
PART 3 - EXECUTION
C. Excavation - Remove material to the width and depth required for construction of
the pedestrian gate foundation. Take care not to disturb the bottom of the
excavation before the concrete for the foundation is placed. Replace excavation
below the required grade or more than the required width with the same class of
concrete specified for the foundation, at no additional cost to the Authority.
E. Swing Gates Installation - Install swing gates on gate posts. Adjust gate operation,
as necessary, to ensure proper operation.
H. Bicycle Traffic Control During Construction – Maintain bicycle traffic flow at all
times during construction.
I. Submittal Requirements - Submit a pedestrian and bicycle traffic control plan for
approval before commencing construction work at the pedestrian crossing.
Describe in detail how pedestrian traffic will be maintained during construction,
including temporary pedestrian crossing requirements, measures to be
implemented for pedestrian safety in the vicinity of open excavation and other work
areas during construction.
4.01 MEASUREMENT
A. Pedestrian Swing Gates will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
A. Pedestrian Swing Gates furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Full compensation for furnishing and placing concrete footings, and connecting to
structures and existing railing shall be considered as included as listed on the
Schedule of Quantities and Prices.
END OF SECTION 05 52 10
METAL GRATING
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes:
1.03 SUBMITTALS
2. Paint products
C. Shop Drawings: Show fabrication and installation details for gratings. Include
plans, elevations, sections, details, and attachments to other work. Provide
templates for anchors and bolts specified for installation under other Sections.
1.06 COORDINATION
PART 2 - PRODUCTS
2.01 MATERIALS
E. Uncoated Steel Sheet: ASTM A1011 (A1011M), structural steel, Grade 30 (Grade
205)
F. Galvanized Steel Sheet: ASTM A653 (A653M), structural quality, Grade 33 (Grade
230), with G90 (Z275) coating
2.02 FASTENERS
A. Provide Type 304 or 316 stainless steel fasteners for exterior use and zincplated
fasteners with coating complying with ASTM B633, Class Fe/Zn 5, at exterior walls.
Select fasteners for type, grade, and class required.
B. Expansion Anchors: Anchor bolt and sleeve assembly of material indicated below
with capability to sustain, without failure, a load equal to six times the load imposed
when installed in unit masonry and equal to four times the load imposed when
installed in concrete, as determined by testing per ASTM E488, conducted by a
qualified independent testing agency.
A. Welding Rods and Bare Electrodes: Select according to AWS specifications for
metal alloy to be welded.
2.04 FABRICATION
B. Form from materials of size, thickness, and shapes indicated, but not less than
that needed to support indicated loads.
C. Cut, drill, and punch metals cleanly and accurately. Remove burrs and sharp or
rough areas on exposed surfaces.
E. Form from materials of size, thicknesses, and shapes indicated, but not less than
that needed to support indicated loads.
1. Use materials and methods that minimize distortion and develop strength
and corrosion resistance of base metals.
J. Shop Finish: Hot-dip galvanized with a coating weight of not less than 1.8 oz./sq.
ft. (550 g/sq. m) of coated surface.
1. Heavy Duty Grating: Minimum four weld lugs for each heavy-duty grating
section, with each lug shop welded to two bearing bars.
2. Furnish threaded bolts with nuts and washers for securing grating to
supports.
3. Furnish galvanized malleable iron flange clamp with galvanized bolt for
securing grating to supports. Furnish as a system designed to be installed
from above grating by one person.
1. Edge band openings in grating that interrupt four or more bearing bars with
bars of the same size and material as bearing bars.
A. Steel Frames and Supports: Fabricate from structural steel shapes, plates, and
bars of welded construction to sizes, shapes, and profiles indicated and as
necessary to receive gratings. Miter and weld connections for perimeter angle
frames. Cut, drill, and tap units to receive hardware and similar items.
B. Equip units with integrally welded anchors for casting into concrete or building into
masonry.
1. Unless otherwise indicated, space anchors 24 inches (600 mm) o.c. and
provide minimum anchor units in the form of steel straps 1-1/4 inches wide
by 1/4 inch thick by 8 inches long (32 mm by 6 mm by 200 mm).
2.07 FINISHES
A. Comply with NAAMM's Metal Finishes Manual for Architectural and Metal Products
for recommendations for applying and designating finishes.
C. Galvanizing: Apply zinc coating by the hot dip process complying with ASTM A123.
PART 3 - EXECUTION
3.01 INSTALLATION
B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for
installing gratings. Set units accurately in location, alignment, and elevation;
measured from established lines and levels and free from rack.
C. Provide temporary bracing or anchors in formwork for items that are to be built into
concrete or masonry.
1. Use materials and methods that minimize distortion and develop strength
and corrosion resistance of base metals.
B. Attach removable units to supporting members with type and size of clips and
fasteners indicated or, if not indicated, as recommended by grating manufacturer
for type of installation conditions shown.
3.03 CLEANING
A. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas
and repair galvanizing to comply with ASTM A780.
END OF SECTION 05 53 00
MISCELLANEOUS METALS
PART 1 - GENERAL
1.01 SUMMARY
A. Section includes:
1. Pull irons, inserts, channels and other items required by utility companies.
B. Coordinate work of this Section with all other Sections of this Specification and in
particular:
1.02 REFERENCES
A. Comply with all applicable local, State and Federal codes, specifications,
standards and recommend practices, and in particular:
2. AISI - American Institute of Steel and Iron: “Specifications for the Design of
Cold-Formed Steel Structural Members”.
C. ASTM
1.03 SUBMITTALS
A. All steel fabrications shall be done by a licensed fabrication shop with a minimum
of five (5) years experience in this type of work.
PART 2 - PRODUCTS
2.01 MATERIALS
B. Steel tubing:
C. Iron castings:
D. Polyvinyl chloride coated and zinc coated woven steel wire with 11 GA core, 8GA
finish with custom color to be selected by Authority.
1. ASTM F668 2A
2. AASHTO M181
3. Type IV Class
F. Fasteners: Galvanized steel fasteners of the type, grade and class required for the
installation of miscellaneous metal items.
G. Welding electrodes: Low hydrogen type conforming to AWS D1.4, E70 XX Series.
2.02 FABRICATION
A. Metal Work Exposed to View - Use materials that are smooth and free of surface
blemishes including pitting, seam marks, and roller and grinding marks, before
cleaning, treating and applying finishes including zinc coatings.
B. Use materials of size and thicknesses indicated or, if not indicated, of required size
and thickness to produce adequate strength and durability in finished product for
intended use. Work to dimensions shown on reviewed and accepted Shop
Drawings, using proven details of fabrication and support. Use types of materials
indicated for various components of Work.
C. Form exposed Work true to line and level, with accurate angles and surfaces and
straight, sharp edges. Ease exposed edges to a radius of approximately 1/32 inch
unless otherwise indicated. Form bent-metal corners to smallest radius possible
without causing grain separation or otherwise impairing Work.
E. Form exposed connections with hairline joints flush and smooth, using concealed
fasteners wherever possible. Exposed fasteners - f type indicated or, if not
indicated, use Phillips flat-head countersunk screws or bolts.
F. Pre-drill bolt and screw holes as indicated and required for attachment of
metalwork and adjacent materials.
I. Cut, reinforce, drill and tap metalwork as required to receive finish hardware and
similar items of Work.
J. Use hot-rolled steel bar for Work fabricated from bar stock, unless Work is
indicated to be fabricated from cold-finished or cold-rolled stock.
N. Form and finish to shape and size with sharp angles and lines.
P. Weld on hardware mounting plates. Drill or punch holes for bolts and screws.
Conceal fastenings wherever possible.
R. Brackets, lugs and similar accessories required for installation - Include as part of
fabrication.
S. Welding:
1. Weld all shop and field connections continuously in accordance with the
referenced AWS specifications, unless bolted connections are specifically
shown.
2. Grind all exposed welds flush and smooth with parent metal surfaces.
T. Form bent metal corners to the smallest radius possible without causing grain
separation or otherwise impairing the work.
U. Bend pipe without collapsing or deforming the walls, to produce a smooth, uniform
curved sections and maintain uniform sectional shape.
2.03 FINISHING
1. Clean steel surfaces of all oil and other foreign substances that would
interfere with paint bond in accordance with applicable SSPWC
specifications.
3. Apply the shop primer within the time limits recommended for the
pretreatment system used. The shop primer shall be a smooth and even
coating with a dry film thickness of not less than 1-1/2 mils.
PART 3 - EXECUTION
3.01 INSPECTION
A. Inspect adjacent construction and make sure that all conditions detrimental to the
timely and proper execution of this work have been corrected before proceeding.
3.02 INSTALLATION
A. Perform all cutting, drilling and fitting required for the installation of this work. Install
all items accurately in their proper location, alignment and elevations, plumb and
level, free of rack as measured from established lines and levels. Provide
temporary bracing or anchors for items that are to be built into concrete, masonry
or similar construction.
B. Fit exposed connections accurately to form tight hairline joints. Weld connections
that are not to be left as exposed joints, but cannot be shop welded because of
shipping size limitations. Grind exposed joints smooth and flush with parent metal
and touch-up shop paint coat.
A. Clean the damaged shop primer, sand smooth, re-clean and spot-prime with the
same paint used for shop priming.
B. Promptly replace work damaged beyond satisfactory field repair before its
acceptance, with new materials at no additional cost to Authority.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 05 55 00
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes specifications for Detectable Warning Panels for pedestrian
grade crossings, curb ramps, and platforms at Metrolink stations.
B. Also included in this section are specifications for Directional Bar Tiles for platforms
at Metrolink Stations
1.02 REFERENCES
A. ASTM International:
8. D5420 Test Method for Impact Resistance of Flat, Rigid Plastic Specimen
by Means of a Striker Impacted by a Falling Weight (Gardner Impact)
9. G155 Practice for Operating Xenon Arc Light Apparatus for Exposure of
Non-Metallic Materials
1.03 SUBMITTALS
A. Shop Drawings
2. The Shop Drawings do not need to feature a full dimensional layout of the
platform edges.
3. Platform Shop drawings shall depict the platform edge and end treatments.
B. Product Data
C. Samples
E. Maintenance Instructions
A. Panels and accessories, including panel adhesive, fasteners, and sealants, shall
be from a single source. Products shall have been in successful service for a period
of five (5) years.
B. Installer's Qualifications
D. Detectable Warning Panel and Directional Bar Tile must be compliant with
ADAAG, PROWAG, and California Title 24 Requirements.
B. Packages shall be stored in a manner that preserves the new condition of the
panels.
1.07 WARRANTY
A. Panels shall be covered by a written warranty for a period of five (5) years from
date of final completion. The warranty includes defective work, breakage,
deformation, holes, delamination, fading and chalking of finishes, and loosening of
panels. Warranty shall include furnishing new materials, removal of existing
panels, and installation of new panels.
1.08 SPARES
A. Furnish a minimum of five (5) percent additional panels of the total amount installed
of each panel type, and corresponding fasteners or required adhesive. Deliver
spares to location (within 50 mile radius of work site) designated by the Engineer.
Furnish spare materials from same manufactured lot as materials installed and
enclose in protective packaging with appropriate identification.
PART 2 - PRODUCTS
2.01 PANELS
C. Panel color shall be Federal Yellow conforming to Federal Color No. 33538. Color
shall be homogeneous throughout the panel.
1. Truncated dome surface shall comply with Americans with Disabilities Act
(ADA) Standards and California Building Code, and Caltrans A88A.
b. Platforms:
2. Panel shall be 4 feet long by 3 feet wide, and consist of 3 rows of bars,
containing 16 bars per row. See ES 3203.
F. Panel Configuration
1. Panel Thickness
2. Panel Size
3. Butt Joints
a. The detectable warning panel shall feature a butt joint detail from
panel to panel. Alternatively a ship lap detail may also be furnished.
1. Holes for fasteners shall be formed in the factory. Holes for fasteners,
whether made in the factory or in the field, shall be located only at the
centers of the truncated domes.
H. Performance
2.02 ACCESSORIES
1. Color matched nylon expansion sleeves with 1/4 inch diameter by 1-1/2
inches long stainless steel drive pins, or as recommended by panel
manufacturer for specific job conditions and accepted by the Engineer.
B. Adhesive
C. Sealant
D. Backer Rod
PART 3 - EXECUTION
3.01 INSTALLATION
A. Apply adhesives, sealants and mechanical fasteners in strict accordance with the
guidelines set by their respective manufacturers.
C. Form recess for panels by either milling with diamond blade head or casting recess
in place (at new paving) so that installed panel will still flush relative to adjacent
surface. Grind or form to the depth and width required by the approved shop
drawings and manufacturer's instructions. Finish cast-in-place recess with
equivalent of a light broom finish. When milled, substrate shall have a light ribbed
finish.
D. Contain and remove slurry resulting from concrete milling and saw cutting. Do not
wash slurry into track bed area.
1. Utilize diamond bladed double headed wet saw to achieve parallel grooves
to receive panels. Both saw cuts shall be made simultaneously from the
same machine. Saw cut parallel to platform edge.
2. After saw cutting, vacuum and power wash surface with clean clear water,
free from all dirt and debris. Visually inspect surface for obtrusions or
foreign matter. If obtrusions are present, remove by grinding. Remove
foreign matter by grinding or further washing, as appropriate.
1. Wherever possible, install full size (uncut) panels. Do not install panel
sections measuring less than 24 inches in length. Only cut panels where
absolutely necessary.
3. At platform expansion joints, cut panels on their short sides, finish cut
edges smoothly, and lay panels with cut edges aligned with the edges of
the substrate along the joints. Install fasteners on either side of the
expansion joint at the time of initial installation. After a minimum of 4 hours,
make a saw cut measuring 5/16 inch wide across the composite detectable
warning panel and fill with sealant. Make saw cut in the zone between
truncated domes.
4. Cutting through panel domes shall be kept to a minimum. Where less than
half of the truncated dome remains, grind off balance of dome; where over
half of the truncated dome remains, feather dome so as not to present a
tripping hazard.
A. After the area has been fully paneled and sealant system applied, clean panel
surface, following the manufacturer recommended maintenance and cleaning
procedures.
B. Protect sealant and panels against damage during construction period. Comply
with panel and sealant manufacturers' recommendations.
C. Protect panels against damage from rolling loads following installation by covering
with plywood or hardwood.
4.01 MEASUREMENT
4.02 PAYMENT
END OF SECTION 09 61 50
PART 1 - GENERAL
1.01 DESCRIPTION
A. Furnish all labor, materials, tools and equipment necessary and incidental to the
painting, and finishing the surfaces as indicated on the Contract Drawings, as
specified herein and as directed by the Engineer.
B. Painting shall include shop coat and field finish painting of all metal surfaces,
including the complete canopy, railings, handrails, base plates, covers, connecting
hardware, mounting brackets; field painting of railings and guardrails, fences,
flashings, pipe bollards, and exposed mechanical or electrical equipment including
housing; and the finish painting over shop coated exposed equipment.
C. Related Specification Sections include but are not necessarily limited to:
3. Division 05 - Metals
4. Division 26 - Electrical
1.02 REFERENCES
A. Comply with all applicable local, State and Federal Codes, regulations,
specifications, standards and recommended practices, and in particular:
2. Federal Specification
1.03 SUBMITTALS
3. Samples: Of all paints and finishes proposed for use on the project,
minimum size 8-1/2 inches by 11 inches. No painting or coating will be
accepted prior to approval of the color sample.
PART 2 - PRODUCTS
A. For metal surfaces paint materials shall be the products of Tnemec Co., Inc., or
equal products by Ameron Protective Coatings Group, Rust-Oleum Industrial
Coatings, Sherwin Williams, Porter International, or Pittsburgh Paints.
B. For gypsum board surfaces paint and stain materials shall be the products of
Dunn-Edwards or equal products by Frazee Paint Co. or Sherwin Williams.
C. Materials selected for coating systems for each type of surface shall be the product
of a single manufacturer.
D. All paint materials shall be the respective equivalent, in the opinion of the Engineer,
to the several types of materials specified. Deliver all materials to the job site in
the original, unbroken containers, bearing the manufacturers' labels indicating the
contents and directions for use, storage, and handling.
E. Materials not specifically noted but required for the work, such as linseed oil,
shellac, thinners, etc., shall be the product of the approved paint manufacturer.
2.02 MIXING
A. The color selection will be made by the Engineer from submitted manufacture’s
standard colors.
B. Submit color samples, allowing minimum two weeks for consideration before the
material to be painted is to be ordered and delivered or ready for painting.
2.04 IDENTIFICATION
A. The manufacturers' identification numbers and specifications listed are for the
purpose of indicating the type and quality of paint product desired for the purpose
indicated.
PART 3 - EXECUTION
3.01 GENERAL
B. Vary colors or sheen between coats and apply all coats to uniform thicknesses.
C. Cut sharp lines against glass, other materials, and different colors. Recoat suction
spots in the first coat as necessary to produce uniformity of color and gloss.
D. Refinish any work judged defective at no additional cost to SCRRA; repair all work
damaged during the progress of the construction.
A. General: Clean all surfaces thoroughly, removing all rust, mill scale, fabrication
films, dust, dirt, and other foreign matter from surfaces. Grind smooth all welds
flush with adjacent surfaces. Apply film to completely dry surfaces.
B. Galvanized metal: Thoroughly clean surfaces, wiping with mineral spirits or xylol.
If silicone surface treatments have been applied in the fabrication shop, use xylol;
remove silicates or similar surface treatments and deposits of "white rust" by
sanding or other approved abrasive methods. Thoroughly clean and rinse
contaminants from surfaces.
C. Ferrous metal surfaces: Thoroughly clean using mineral spirits, xylol, or toluol in
accordance with SSPWC-SP No. 1. Take care to ensure that adequate ventilation
is provided at all times when using solvents. Carefully rinse and clean surfaces
before applying paint.
D. Gypsum Board:
1. Remove dust, loose particles or other matter that would prevent proper
paint adhesion.
2. Check to see that joints and screw heads are properly covered with joint
compound and sanded smooth and flush with adjacent surfaces.
F. Mixing and thinning: Mix and thin paint products in strict accordance with the
manufacturers' directions; mix and thin other materials in accordance with the
"best" trade practices as approved.
3.03 APPLICATION
C. Color of coats: Tint prime coats if necessary to obtain uniform finish coats. Vary
color between coats; the final coat shall exactly match approved samples.
D. Approval of successive coats: Obtain the Engineer's approval of each coat before
the succeeding coat is applied; if this approval is not obtained, the Engineer
reserves the right to require an additional coat.
A. Apply primer and 2 finish coats as specified for the appropriate metal surface
according to the finish schedule.
A. Use tarpaulins or drop cloths when working above or adjacent to completed work.
Clean all paint splatters and stains from finished surfaces. Protect all work from
dust and insects.
A. General: Provide the following paint systems for the various substrates, as
indicated.
C. Paint system:
1. Spot prime for galvanized surfaces and surfaces primed with zinc-rich
primer: 90-97 Tneme-Zinc applied at 2.5 to 3.5 mils DFT.
END OF SECTION 09 90 00
GRAFFITI-RESISTANT COATING
PART 1 - GENERAL
1.01 SUMMARY
B. Related Specification Sections include but are not necessarily limited to:
1. Section 03 31 00
2. Section 04 22 00
3. Section 09 90 00
1.02 REFERENCES
Comply with all applicable local, State and Federal Codes, regulations, specifications, standards
and recommended practices, and in particular:
1.03 SUBMITTALS
Submit the following in accordance with Section 01 33 00, Submittal Procedures.
A. Sample panel:
1.06 CONDITIONS
Environmental requirements:
A. Compliance with air quality regulations: VOC of coatings used for this work shall
not exceed limits prescribed by law.
E. Provide and maintain protection as required to protect finished work from damage
until its acceptance.
1.07 MAINTENANCE
PART 2 - PRODUCTS
2.01 COATING
PART 3 - EXECUTION
3.01 INSPECTION
Examine surfaces to be coated for conditions that would adversely affect the permanence and
quality of this work. Make sure that unsuitable conditions are corrected before proceeding with
painting.
A. Open containers only as required for use. Mix coating in designated areas.
B. Thoroughly stir and agitate coating to uniformly smooth consistency suitable for
proper application.
D. In all cases, prepare and handle coating to prevent deterioration and inclusion of
foreign matter.
3.04 APPLICATION
A. Test coating on each type of substrate for compatibility and desired results before
proceeding further.
B. Apply coating only under conditions that will insure finishes free from blemishes
and defects.
END OF SECTION 09 96 23
ROADWAY SIGNAGE
PART 1 - GENERAL
1.01 DESCRIPTION
A. Section Includes:
1. Traffic signs.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1. AISC 303 - Code of Standard Practice for Steel Buildings and Bridges,
Section 10, Architecturally Exposed Structural Steel.
2. A53 (A53M) – Standard Specification for Pipe, Steel, Black and Hot
Dipped, Zinc Coated, Welded and Seamless.
4. A153 (A153M) – Standard Specification for Zinc Coating (Hot Dip) on Iron
and Steel Hardware.
6. A307 – Standard Specification for Carbon Steel Bolts and Studs, 60,000
PSI Tensile Strength.
10. A780 – Standard Practice for Repair of Damaged and Uncoated Areas of
Hot-Dip Galvanized Coatings.
11. B209 – Standard Specification for Aluminum and Aluminum Alloy Sheet
and Plate.
1. Paint 20 – Specification for Zinc Rich Primers (Type I, Inorganic, and Type
II, Organic)
1.03 SUBMITTALS
C. Coating Systems:
2. List each material and cross-reference to the specific coating, finish system
and application.
D. Shop Drawings:
1. Submit Shop Drawings for fabrication and erection indicating all materials,
sizes, configurations and required location of connections, junction boxes,
and equipment provided under other Sections.
F. Layout Drawings: Show sign layout at each location to assure all signs are
readable and do not block and are not blocked by other safety lights, signs, or
railroad or roadway equipment.
A. Manufacturer Qualifications: Provide work required under this section from sign
manufacturers regularly engaged in work of this magnitude and scope for minimum
of five years.
B. Qualifications for Welding Work: Qualify welding processes and welding operators
in accordance with the AWS Standard Qualification Procedure.
1. Where fabrication is done more than 100 miles (160 kilometers) from job
site, allow 14 days for observation and review before fabrication and
installation of additional units.
B. Do not delay job progress; allow for trimming and fitting wherever taking field
measurements before fabrication might delay work.
A. Protect sign units during transportation to AUTHORITY by wrapping all sign units
individually in soft, nonabrasive material.
B. Pay special attention to protection of sign faces with artwork and to porcelain
enamel finish.
PART 2 - PRODUCTS
2.01 GENERAL
2.02 MATERIALS
A. Provide metal work composed of metals of the forms and types which comply with
requirements of referenced standards and which are free from surface blemishes
where exposed to view in the finished unit.
1. Exposed to view surfaces exhibiting pitting, seam marks, roller marks, “oil
canning,” stains, discolorations, or other imperfections on finished units are
not acceptable.
B. Stainless Steel Sheet, Strip, Plate, and Flat Bars: ASTM A666, Type 304.
E. Galvanizing: G60 (Z180) zinc coating for steel fabrications; where zinc coating is
reduced below average thickness required by applicable standard referenced
above, apply galvanizing repair paint as specified.
F. Fasteners: Provide Type 304 or 316 stainless steel fasteners for exterior use and
zinc plated fasteners with coating complying with ASTM B633, Class Fe/Zn 5,
where built into exterior walls. Select fasteners for type, grade, and class required.
G. Welding Electrodes and Filler Metal: Type and alloy of filler metal and electrodes
as recommended by producer of metal to be welded, complying with applicable
AWS Specifications, and as required for color match, strength and compatibility in
the fabricated items.
H. Anchors and Inserts: Provide anchors of type, size, and material required for type
of loading and installation condition shown, as recommended by manufacturer,
unless otherwise indicated.
1. Use nonferrous metal or hot dipped galvanized anchors and inserts for
exterior locations and elsewhere as required for corrosion resistance.
K. Galvanizing Repair Paint: High zinc dust content paint for regalvanizing welds in
steel, complying with SSPC-Paint 20; two-component, moisture-cured urethane,
zinc-rich.
L. Traffic Signs: Minimum 0.067 inch thick (aka 14 gauge) sheet steel and
reflectorized porcelain white beaded background and black lettering; size required
by sign type and Caltrans Standard Specifications Section 56-2.
2.03 FABRICATION
3. Form exposed connections with hairline joints, flush and smooth, using
concealed fasteners wherever possible.
8. Cut, fit, and assemble units with exposed surfaces smooth and square, free
of cutting marks, shear distortion, burrs and nicks.
9. Form exposed work true to line and level with accurate angles, surfaces,
and edges.
10. Form simple and compound curves by bending members in jigs or other
system to produce uniform curvature for each repetitive configuration
required.
B. Steel Fabrication: Fabricate with special care using material selected for best
appearance, in accordance with AISC specifications and as indicated on final Shop
Drawings.
C. Aluminum Fabrication: Allow for thermal movement in the design, fabrication, and
installation of installed metal assemblies to prevent buckling, opening up of joints
and over stressing of welds and fasteners.
D. Welded Construction: Comply with AWS Code for procedures, appearance, and
quality of welds, and methods used in correcting welding work.
a. Grind smooth exposed fillet welds; grind butt welds flush and
smooth; dress all exposed welds, feather edges onto base material
and polish as required for smooth painted surfaces.
E. Holes for Other Work: Provide holes required for securing other work to sign
supports, brackets and frames, and for passage of other work through metal
members as shown on approved Shop Drawings.
2. Drill holes 1/16 inch (1.6 mm) oversize for field alignment and fitting.
F. Bearing Plates: Provide bearing plates for steel items bearing on concrete
construction, made flat, free from warps or twists, and of required thickness and
bearing area.
G. Furnish inserts and anchoring devices which must be set in concrete for installation
of metal work. Coordinate delivery with other work to avoid delay.
H. Surface Preparation: After inspection and before finishing, remove loose rust, mill
scale, and deposits of spatter, slag, or flux.
PART 3 - EXECUTION
3.01 EXAMINATION
3.02 PREPARATION
1. Do not delay job progress; allow for trimming and fitting where taking field
measurements before fabrication might delay work.
A. Porcelain Panels: Assemble all porcelain enamel sign components flush, true and
accurately straight as indicated on approved Shop Drawings for each type of sign.
B. Hardware:
1. Furnish and install all hardware for the attachment of porcelain panels to
other sign components.
2. In addition, furnish any other hardware item not specified which would
normally be furnished or required for proper functioning of signs as
indicated on the Plans.
C. Anchor Bolts:
1. Furnish anchor bolts and other connectors required for securing sign
supports to in-place work.
2. Furnish templates and other devices as necessary for pre-setting bolts and
other anchors to accurate locations.
B. All signs shall be of high intensity grade (Diamond Grade Reflective) with
protective overlay film.
C. Existing signs and poles as shown on the plans shall be relocated to a new location
(Protected) and reinstalled.
4.01 MEASUREMENT
A. Roadway Signs will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Roadway Signs on posts will be measured by the unit from actual count. One or
more sign panels mounted on a single post installation will be counted as a
roadway sign-one post.
4.02 PAYMENT
B. This price shall be full compensation for including multiple sign faces, sign post,
anchors, hardware, concrete post foundation, galvanizing, and fasteners
described by the Contract Documents and as directed by the Engineer.
END OF SECTION 10 14 53
RAILROAD SIGNAGE
PART 1 - GENERAL
1.01 SUMMARY
A. This Section consists of furnishing all labor, materials and equipment necessary
and incidental to maintaining existing railroad signage and constructing new
railroad signage at the locations indicated in the reference Specifications, on the
contract plans, and/or as directed by the Engineer.
B. Related Specification Sections include but are not necessarily limited to:
C. Work Included:
1. All Work associated with constructing new and maintaining existing railroad
signage along the right-of-way, including excavation for signposts.
1.02 SUBMITTALS
PART 2 - PRODUCTS
2.01 MATERIALS
A. The Contractor shall use materials and methods, which comply with the SCRRA
Engineering Standards (ES). Railroad signage shall conform to the following
Standard Drawings:
4. Safety lock indication signage shall be at the option of the Contractor, and
approved by the Engineer.
6. Station train and locomotive position spot signs shall conform to SCRRA
ES3330-01 through ES3330-06.
9. Private, pedestrian and bicycle railroad grade crossing signs shall conform
to SCRRA ES4102, Private, Pedestrian and Bicycle Railroad Grade
Crossing Signs.
10. Private crossing closure notification sign shall conform to SCRRA ES4312,
Private Crossing Closure Notification Signs.
12. Sign post, anchors and fasteners shall conform to SCRRA ES5210, Details
for Installing Signs at Grade.
13. Milepost signs shall conform to SCRRA ES5211, Milepost. Tenth mile post
signs shall conform to SCRRA ES5214, No Trespassing and Tenth Mile
Post Sign.
16. Stop, slow and resume speed flags and signs shall conform to SCRRA
ES5215, Stop, Slow and Resume Speed Flags and Signs.
18. Yard limit signs for terminal tracks shall conform to SCRRA ES5217, Yard
Limit Sign for Terminal Tracks.
19. Control Point (CP) limit signs and markings shall conform to ES5218,
Control Point (CP) Limit Sign and Markings.
21. Station signs for other than CTC territory shall conform to SCRRA ES5222,
Station Signs for Other Than CTC Territory.
22. Mechanical Limit and No Ride Zone signs shall conform to SCRRA
ES5223, Mechanical Limit and No Ride Zone Signs.
24. Warning Signs for Underground Cables shall conform to SCRRA ES5229.
25. Bridge, trestle and culvert number signs shall conform to SCRRA ES6101,
Bridge, Trestle and Culvert Numbers.
26. Radio channel sign shall conform to ES6103, Radio Channel Sign.
27. Tunnel exit sign shall conform to SCRRA ES6104, Tunnel Exit Sign.
29. Radio channel signs shall conform to SCRRA ES6103, Begin Channel
Sign.
32. Begin CTC/End CTC sings shall conform to SCRRA ES8291, Begin
CTC/End CTC Sign.
34. Block signal with “P” Plate signs shall conform to SCRRA ES8545, Block
Signal With “P” Plate.
PART 3 - EXECUTION
A. Maintain and protect in place the existing railroad signage until such time as it can
be replaced with new signage, or relocated at a permanent location, as shown on
the Contract Drawings. Signs may be temporarily relocated to prevent their
damage. Contractor must confer with the Engineer for proper location and
orientation of relocated signs.
D. Placement of temporarily relocated and permanent signs shall comply with current
editions of CPUC General Order 26 and 118.
4.01 MEASUREMENT
A. Railroad Signs will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Railroad Signs on posts will be measured by the unit from actual count. One or
more sign panels mounted on a single post installation will be counted as a railway
sign-one post.
4.02 PAYMENT
B. This price shall be full compensation for including multiple sign faces, sign post,
anchors, hardware, concrete post foundation, galvanizing, and fasteners
described by the Contract Documents and as directed by the Engineer.
END OF SECTION 10 14 55
PART 1 - GENERAL
1.01 SUMMARY
A. This Section consists of the Contractor furnishing all labor, materials, tools and
equipment necessary and incidental to the provision and installation of benches
and trash containers as indicated on the Contract Drawings, as specified herein
and as directed by the Engineer.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
Comply with all local, State and Federal codes, regulations, specifications, standards and
recommended practices and in particular:
1.03 SUBMITTALS
B. Samples: Submit manufacturer's color chips for standard colors. The Engineer will
select the color from the colors submitted.
1.04 DELIVERY
A. Delivery: Do not deliver benches or trash containers until the platform construction
is ready for their installation.
B. Store benches and trash containers in a manner to protect from harm, vandalism,
or damage.
PART 2 - PRODUCTS
2.01 MANUFACTURER
A. Trash Containers shall be blast resistant construction with high strength steel outer
shell and compressive inner layer designed to absorb major blast energy with
remaining blast energy vented upwards away from public. Trash Container will
have interior removable plastic trash bag.
PART 3 - EXECUTION
3.01 INSPECTION
Verify conditions and measurements affecting the work of this Section at site. Make sure
that detrimental conditions are corrected before proceeding with installation.
3.02 INSTALLATION
A. Install equipment plumb, level and secure in compliance with their manufacturer's
recommendations. Trash containers and benches are to be securely bolted to the
concrete where they are installed.
4.01 MEASUREMENT
A. Benches will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
B. Trash Containers will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Benches furnished and completed in accordance with the Contract Documents will
be paid for at the Contract Unit Price, as listed on the Schedule of Quantities and
Prices. This price shall include full compensation for furnishing all labor, Materials,
tools, equipment, supplies, supervision, and incidentals, and doing all work, as
shown on the Plans, and as specified in these Specifications, and as directed by
the Engineer.
END OF SECTION 12 67 23
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes: Basic requirements for electrical systems, including lighting for
all platforms, parking lots and landscape area, wayside power.
1. Site electrical.
2. Service Pedestals.
8. Training requirements.
1.02 REFERENCES
F. ASTM A123, Standard Specification for Zinc (Hot-Dip galvanized) Coating on Iron
and Steel products.
G. ASTM A153, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
1.03 DEFINITIONS
A. Product Types:
B. For the purpose of providing material and installing electrical work the following
definitions shall be used:
4. Highly corrosive and corrosive area: areas identified in the drawings where
there is a varying degree of spillage or splashing of corrosive materials such
as water, wastewater or chemical solutions; or chronic exposure to corrosive,
caustic or acidic agents, chemicals, chemical fumes or chemical mixtures.
1.04 SUBMITTALS
1. General Requirements:
1.05 COORDINATION
B. Provide complete power and control raceway and wiring for all mechanical
equipment electrical loads.
D. Coordinate chases, slots, inserts, sleeves, and openings for electrical supports,
raceways, and cable with general construction work.
H. Coordinate location of access panels and doors for electrical items concealed by
finished surfaces.
PART 2 - PRODUCTS
2.02 MATERIALS
1. Approved Manufacturers:
a. Modular Strut:
2) B-Line.
3) Globe Strut.
2. Material requirements:
a. Modular strut:
b. Mounting hardware:
1) Galvanized steel.
2) Stainless steel.
A. Steel Pipe Sleeve: ASTM A53 Type E, Grade B, Schedule 40, galvanized steel,
plain ends.
PART 3 - EXECUTION
A. Install and wire all equipment, including pre-purchased equipment, and perform all
tests necessary to assure conformance to the Plans and Specification Sections
and ensure that equipment is ready for operation and safe for energization.
C. Measure indicated mounting heights to bottom of unit for suspended items and to
center of unit for wall-mounting items.
E. Materials and Components: Install level, plumb, and parallel and perpendicular to
other building systems and components, unless otherwise indicated.
G. Right of Way: Give to raceways and piping systems installed at a required slope.
3.02 APPLICATIONS
A. Raceways:
1. Outdoor Installations:
2. Indoor Installations:
A. Conceal raceways and cables, unless otherwise indicated, within finished walls,
ceilings, and floors.
B. Keep legs of raceway bends in the same plane and keep straight legs of offsets
parallel.
1. Use oven polypropylene or monofilament plastic line with not less than 200
LB tensile strength.
F. Install interior telephone and signal system raceways, 2 IN trade size and smaller,
in maximum lengths of 150 FT and with a maximum of two 90 degree bends or
equivalent.
H. Set floor boxes level and trim after installation to fit flush to finished floor surface.
A. Use wiring methods specified below to the extent permitted by applicable codes
as interpreted by authorities having jurisdiction.
A. Make splices and taps that are compatible with conductor material and that
possess equivalent or better mechanical strength and insulation ratings than
unspliced conductors.
C. Fire-Rated Assemblies: Install sleeves for penetrations of fire-rated floor and wall
assemblies unless openings compatible with firestop system used are fabricated
during construction of floor or wall.
D. Cut sleeves to length for mounting flush with both surfaces of walls.
F. Size pipe sleeves to provide 1/4 IN annular clear space between sleeve and
raceway or cable, unless indicated otherwise.
G. Seal space outside of sleeves with grout for penetrations of concrete or masonry.
1. Promptly pack grout solidly between sleeve and wall so no voids remain.
1. Install sleeves and seal raceway and cable penetration sleeves with
firestop materials.
3.07 FIRESTOPPING
A. Apply firestopping to cable and raceway sleeves and other penetrations of fire
rated floor and wall assemblies to restore original undisturbed fire resistance
ratings of assemblies.
A. Cut, channel, chase, and drill floors, walls, partitions, ceilings, and other surfaces
required to permit electrical installations.
B. Repair, refinish, and touch up disturbed finish materials and other surfaces to
match adjacent undisturbed surfaces.
A. General Requirements:
d. Hours for training shall be between 7:00 a.m. and 7:00 p.m. unless
specifically permitted otherwise.
B. The Contractor is responsible for ensuring that training instructors are not only
familiar with technical information, but also able to utilize proper methods of
instruction, training aids, audiovisuals, etc., to ensure effective presentations.
C. The Contractor is responsible for providing all training aids, audiovisual equipment,
and visual aids for the conduct of these courses.
D. Training materials are to become the property of the SCRRA at the conclusion of
training.
1. The Contractor shall meet with SCRRA's quality assurance manager not
later than three weeks prior to the start of formal training.
2. The Contractor will submit in writing his plans for meeting the Specification
training requirements.
F. The Contractor will outline specific objectives for each of the courses that he is
required to present.
1. The course should include sessions in safety and machine operation, as well
as a comprehensive seminar teaching basic skills and knowledge of each
operation.
G. Training related to electrical systems shall include, but not be limited to, the
following:
2. Troubleshooting instruction.
4.01 MEASUREMENT
A. Basic Electrical Materials and Methods will be measured by the unit or fraction
thereof furnished and completed in accordance with the Contract Documents and
as measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 05 00
PART 1 - GENERAL
1.01 SUMMARY
A. Specifier: Keep this description brief. The SUMMARY Article is intended to only
outline the contents of topics in this Specification Section. Do not stipulate
specification requirements in this Article.
B. Section Includes:
a. Manholes.
b. Handhole.
C. Related Specification Sections include but are not necessarily limited to:
2. Division 03 - Concrete.
A. Referenced Standards:
1.03 DEFINITIONS
A. Direct-buried conduit(s):
1.04 SUBMITTALS
A. Shop Drawings:
PART 2 - PRODUCTS
a. Quazite Composolite.
c. Synertech.
c. Lister Industries.
a. Neenah.
b. Unistrut.
3. Open bottom.
5. Cover:
2. AASHTO live load rating: H-20 for full deliberate vehicle traffic.
5. Gasketed removable top slab with lifting eyes and cast in frame for cover.
3. Diameter: 30 IN.
C. Duct Spacers/Supports:
2. Interlocking.
4. Accessories, as required:
b. Ductbank strapping.
PART 3 - EXECUTION
3.01 GENERAL
A. Drawings indicate the intended location of manholes and handholes and routing of
ductbanks and direct buried conduit.
6. Determine the exact locations after careful consideration has been given
to the location of other utilities, grading, and paving.
4. Install so that the surrounding grade is 1 IN lower than the top of the
handhole.
5. Size: As indicated on the Drawings or as required for the number and size
of conduits.
2. Construction:
6. Handhole size:
7. Manhole size:
2) Under railroads.
1) Under roads.
c. Direct-buried conduit(s):
1) Area/Roadway lighting.
2. Do not place concrete or soil until conduits have been observed by the
Engineer.
4. During construction and after conduit installation is complete, plug the ends
of all conduits.
10. Field cuts requiring tapers shall be made with the proper tools and shall
match factory tapers.
a. Prove joint integrity and test for out-of-round duct by pulling a test
mandrel through each conduit.
1) Test mandrel:
a. Install a heavy nylon cord free of kinks and splices in all unused
new ducts.
13. Transition from rigid non-metallic conduit to rigid metallic conduit, per
Specification Section 26 13 00, prior to entering a structure or going above
ground.
14. Place warning tape in trench directly over ductbanks, direct-buried conduit,
and direct-buried wire and cable in accordance with Specification Section
26 07 50.
3. Where identified and for a distance 10 FT either side of the area, the
concrete shall be reinforced.
C. Direct-Buried Conduit(s):
4.01 MEASUREMENT
A. Manholes will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
B. Handholes will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
4.02 PAYMENT
A. Manhole furnished and completed in accordance with the Contract Documents will
be paid for at the Contract Unit Price, as listed on the Schedule of Quantities and
Prices. This price shall include full compensation for furnishing all labor, Materials,
tools, equipment, supplies, supervision, and incidentals, and doing all work, as
shown on the Plans, and as specified in these Specifications, and as directed by
the Engineer.
END OF SECTION 26 05 43
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
C. The Contractor shall furnish an Arc Flash Hazard Analysis Study per the
requirements set forth in NFPA 70E-Standard for Electrical Safety in the
Workplace. The arc flash hazard analysis shall be performed according to the
IEEE 1584 equations that are presented in NFPA70E, Annex D.
1.02 REFERENCES
C. IEEE 399 – Recommended Practice for Industrial and Commercial Power System
Analysis.
I. Comply with IEEE 399 latest revision for general study procedures.
J. Comply with IEEE 242 latest revision for short-circuit currents and coordination
time intervals.
A. Product Data: The short-circuit and protective device coordination studies shall be
submitted to the Design Engineer prior to receiving final approval of the distribution
equipment Shop Drawings and/or prior to release of equipment Drawings for
manufacturing. If formal completion of the studies may cause delay in equipment
manufacturing, approval from the Engineer may be obtained for preliminary
submittal of sufficient study data to ensure that the selection of device and
characteristics will be satisfactory.
5. Setting report.
A. The results of the short-circuit, protective device coordination and arc flash hazard
analysis studies shall be summarized in a final report.
1. Executive Summary.
A. Studies shall use computer programs developed as listed in Part 2.01 in this
Section.
D. Fault levels indicated on Drawings are for guidance only; device IC's shall be
determined from study results.
PART 2 - PRODUCTS
3. ESA, Inc.
4. CYME International.
1. Optional Features:
a. Arcing faults.
b. Simultaneous faults.
PART 3 - EXECUTION
3.01 EXAMINATION
B. Proceed with coordination study only after relevant equipment submittals have
been assembled.
A. Source Impedance:
D. Study Report: Enter calculated X/R ratios and interrupting (5-cycle) fault currents
on electrical distribution system diagram of the report.
1. List other output values from computer analysis, including momentary (1/2-
cycle), interrupting (5-cycle), and 30-cyclefault-current values for 3 PH, 2
PH, and phase-to-ground faults.
A. Gather and tabulate the following input data to support coordination study:
a. Load current that is the basis for sizing continuous ratings of circuits
for cables and equipment.
B. Perform coordination study and prepare a written report using the results of fault-
current study and approved computer software program. Comply with IEEE 399.
C. Comply with NFPA 70 for overcurrent protection of circuit elements and devices.
D. Comply with IEEE 242 recommendations for fault currents and time intervals.
a. Device tag.
a. Device tag.
B. Testing: SCRRA will engage a qualified testing agency to perform the following
device setting and to prepare test reports.
C. All equipment provided shall meet or exceed the fault current level provided in the
study.
A. The arc flash hazard analysis shall be performed according to the IEEE 1584
equations that are presented in NFPA70E, Annex D.
B. The flash protection boundary and the incident energy shall be calculated at all
significant locations in the electrical distribution system (switchboards, switchgear,
motor-control centers, panelboards, busway and splitters) where work could be
performed on energized parts.
C. The Arc-Flash Hazard Analysis shall include all significant locations in 240 V and
208 V systems fed from transformers equal to or greater than 125 kVA where work
could be performed on energized parts.
D. Safe working distances shall be based upon the calculated arc flash boundary
considering an incident energy of 1.2 cal/cm2.
E. When appropriate, the short circuit calculations and the clearing times of the phase
overcurrent devices will be retrieved from the short-circuit and coordination study
model. Ground overcurrent relays should not be taken into consideration when
determining the clearing time when performing incident energy calculations.
F. For each equipment location with a separately enclosed main device (where there
is adequate separation between the line side terminals of the main protective
device and the work location), calculations for incident energy and flash protection
boundary shall include both the line and load side of the main breaker.
G. When performing incident energy calculations on the line side of a main breaker
(as required per above), the line side and load side contributions must be included
in the fault calculation.
A. The Contractor of the Arc Flash Hazard Analysis shall provide a 3.5 x 5 IN thermal
transfer type label of high adhesion polyester for each work location analyzed.
1. Location designation.
2. Nominal voltage.
5. Incident energy.
6. Working distance.
E. Arc flash labels shall be provided in the following manner and all labels shall be
based on recommended overcurrent device settings.
1. For each 600, 480 and applicable 208 V panelboard, one arc flash label shall
be provided.
2. For each motor control center, one arc flash label shall be provided.
3. For each low voltage switchboard, one arc flash label shall be provided.
5. For medium voltage switches one arc flash label shall be provided.
A. The Contractor of the Arc Flash Hazard Analysis shall train the Owner’s qualified
electrical personnel of the potential arc flash hazards associated with working on
energized equipment (minimum of 4 HRS).
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 26 05 50
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
B. Regulatory Requirements:
1.04 SUBMITTALS
A. Product Data: Technical data for ground rods and grounding conductors.
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with:
1. Ground rods and bars and grounding clamps, connectors and terminals:
b. Burndy.
d. Heary Brothers.
e. Joslyn.
h. Thompson.
c. Thermoweld.
a. Quazite Composolite.
2.03 COMPONENTS
10. Grounding Bus: Bare, annealed copper bars of rectangular cross section,
with insulated spacer.
11. Connectors: Comply with IEEE 837 and UL 467; listed for use for specific
types, sizes, and combinations of conductors and connected items. Use
compression type where exposed and exothermic-welded type, in kit form,
selected per manufacturer's written instructions where concealed or buried
in earth.
C. Ground Bars:
1. Solid copper:
a. 1/4 IN thick.
b. 2 or 4 IN wide.
4. Insulated standoffs.
D. Ground Rods:
2. 3/4 IN x 10 FT.
1. Mechanical type:
a. Standards: UL 467.
a. Standards: UL 467.
c. Non-reversible.
d. Terminals for connection to bus bars shall have two bolt holes.
c. Non-reversible.
PART 3 - EXECUTION
3.01 INSTALLATION
A. General:
4. Where ground conductors pass through floor slabs or building walls provide
non-metallic sleeves and install per Specification Section 01 73 20.
7. Do not use exothermic welding if it will damage the structure the grounding
conductor is being welded to.
B. Use copper conductors for both insulated and bare grounding conductors in direct
contact with earth, concrete, masonry, crushed stone, and similar materials.
D. Exothermic Welded Connections: Use for connections to structural steel and for
underground connections.
1. Use insulated spacer; space 1 IN from wall and support from wall 18 IN
above finished floor.
G. Equipment Grounding Conductors: Comply with NFPA 70, Article 250, for types,
sizes, and quantities of equipment grounding conductors, unless specific types,
larger sizes, or more conductors than required by NFPA 70 are indicated.
6. Signal and Communication Systems: For telephone, alarm, voice and data,
and other communication systems, provide No. 4 AWG minimum insulated
grounding conductor in raceway from grounding electrode system to each
service location, terminal cabinet, wiring closet, and central equipment
location.
H. Metal Frame Grounding for Buildings: Drive a ground rod at the base of every
corner column and at each intermediate exterior column. Connect rod to column
with an underground grounding conductor. Interconnect ground rods with a
continuous underground conductor (counterpoise), extending around the
perimeter of the building, 24 IN minimum from building foundation. Use tinned
copper conductor not less than No. 4/0 AWG for underground conductor, and bury
18 IN below grade, minimum.
I. Ground Rods: Drive ground rods until tops are 12 IN below finished floor or final
grade, unless otherwise indicated.
M. Water Meter Piping: Use braided type bonding jumpers to electrically bypass
water meters. Connect to pipe with grounding clamp connectors.
N. Bond interior metal piping systems and metal air ducts to equipment grounding
conductors of associated pumps, fans, blowers, electric heaters, and air cleaners.
Use braided type bonding straps.
O. Bond each above ground portion of gas piping system upstream from equipment
shutoff valve.
5. Coat and seal connections having dissimilar metals with inert material to
prevent future penetration of moisture to contact surfaces.
9. Tighten screws and bolts for grounding and bonding connectors and
terminals according to manufacturer's published torque tightening values.
If manufacturer’s torque values are not indicated, use those specified in UL
486A.
Q. Duct Banks: Install a No. 4/0 grounding conductor below each duct bank in direct
contact with the earth.
R. Manholes and Handholes: Install a driven ground rod close to wall and set rod
depth so that 4 IN will extend above finished floor. If necessary, install ground rod
before manhole is placed and provide a No. 1/0 AWG bare, copper conductor from
ground rod into manhole through a waterproof sleeve in manhole wall. Protect
ground rods passing through concrete floor with a double wrapping of pressure-
sensitive tape or heat-shrunk insulating sleeve from 2 IN above to 6 IN below
concrete. Seal floor opening with waterproof, non-shrink grout.
T. Pad Mounted Transformers and Switches: Install two ground rods and
counterpoise circling pad. Ground pad mounted equipment and noncurrent
carrying metal items associated with substations by connecting them to
underground cable and grounding electrodes. Use copper conductor not less than
No. 4/0 AWG for counterpoise and for taps to equipment ground pad. Bury
counterpoise not less than 18 IN below grade and 6 IN from the foundation.
3. Provide Drawings locating each ground rod, ground rod assembly, and
other grounding electrodes. Identify each by letter in alphabetical order, and
key to the record of tests and observations. Include the number of rods
driven and their depth at each location and include observations of weather
and other phenomena that may affect test results. Describe measures
taken to improve test results.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 06 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1.02 REFERENCES
2. A307, Standard Specification Carbon Steel Bolts and Studs, 60,000 psi
Tensile Strength.
3. F1554, Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi
Yield Strength.
1.03 DEFINITIONS
B. Mobile Structural Element: A part of the building structure such as a slab, floor
structure, roof structure, or wall that may move independently of other structural
elements during an earthquake.
1.04 SUBMITTALS
A. Product Data: Technical data illustrating and indicate types, styles, materials,
strength, fastening provisions, and finish for each type and size of seismic-restraint
component used. Include documentation of evaluation and approval of
components by agencies acceptable to authorities having jurisdiction.
1.07 COORDINATION
E. Design and install seismic anchorage and bracing for all floor or roof mounted
equipment weighing 400 LBS or more and all suspended or wall mounted
equipment weighing 20 LBS or more.
F. The following components are exempt from the requirements of this Section:
G. Seismic forces shall be presumed to act through the center of mass of the
equipment in a direction that will produce the largest single anchor force.
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with Section 01 60 00 -
Product Requirements.
2.02 MATERIALS
3. Erico, Inc.
4. GS Metals Corp.
B. Restraints:
B. Concrete and Masonry Anchor Bolts and Studs: Steel expansion wedge type.
D. Through Bolts: Structural type, hex head, high strength. Comply with ASTM A325.
F. Beam Clamps for Steel Beams and Joists: Double sided. Single sided type is not
acceptable.
G. Bushings for Floor Mounted Equipment Anchors: Neoprene units designed for
seismically rated rigid equipment mountings, and matched to the type and size of
anchor bolts and studs used.
A. Slotted Steel Channel: 1-5/8 IN by 1-5/8 IN cross section, formed from 0.1046 IN
thick steel, with 9/16 IN by 7/8 IN slots at a maximum of 2 IN OC in webs, and
flange edges turned toward web.
B. Channel Type Bracing Assemblies: Slotted steel channel, with adjustable hinged
steel brackets and bolts.
C. Hanger Rod Stiffeners: Slotted steel channels, installed vertically, with internally
bolted connections to hanger rod.
PART 3 - EXECUTION
3.01 INSTALLATION
1. Use bolted connections with steel brackets, slotted channel, and slotted-
channel fittings to spread structural loads and reduce stresses.
A. Testing Agency: SCRRA will engage a qualified testing and inspection agency to
inspect seismic-control installation for compliance with indicated requirements.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 07 10
ELECTRICAL IDENTIFICATION
PART 1 - GENERAL
1.01 SUMMARY
1.03 SUBMITTALS
1.04 COORDINATION
PART 2 - PRODUCTS
B. Raceway and Cable Labels: Comply with ASME A13.1, Table 3, for minimum size
of letters for legend and minimum length of color field for each raceway and cable
size.
5. Colored Adhesive Marking Tape for Raceways, Wires, and Cables: Self-
adhesive vinyl tape, not less than 1 IN wide by 3 mils thick.
D. Tape Markers for Wire: Vinyl or vinyl cloth, self adhesive, wraparound type with
preprinted numbers and letters.
1. Color Coding Cable Ties: Type 6/6 nylon, self locking type. Colors to suit
coding scheme.
J. Fasteners for Nameplates and Signs: Self tapping, stainless steel screws or
No. 10/32 stainless steel machine screws with nuts and flat and lock washers.
PART 3 - EXECUTION
A. Install at locations for most convenient viewing without interference with operation
and maintenance of equipment.
2. Colors:
F. Tag and label circuits designated to be extended in the future. Identify source and
circuit numbers in each cabinet, pull and junction box, and outlet box. Color coding
may be used for voltage and phase identification.
1. Color code 208Y/120-V system secondary service, feeder, and branch circuit
conductors throughout the secondary electrical system as follows:
a. Phase A: Black.
b. Phase B: Red.
c. Phase C: Blue.
a. Phase A: Yellow.
b. Phase B: Brown.
c. Phase C: Orange.
H. Install warning, caution, and instruction signs where required to comply with
29 CFR 1910.145, and where needed to ensure safe operation and maintenance
of electrical systems and of items to which they connect. Install engraved plastic
laminated instruction signs with approved legend where instructions are needed
for system or equipment operation. Install metal backed butyrate signs for outdoor
items.
I. Install engraved laminated emergency operating signs with white letters on red
background with minimum 3/8 IN high lettering for emergency instructions on
power transfer, load shedding, and other emergency operations.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 07 50
ELECTRICAL TESTING
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1.02 REFERENCES
1. Field personnel:
3. Analysis personnel:
a. Minimum three (3) years combined field testing and data analysis
experience.
PART 3 - EXECUTION
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 08 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
a. Building wire.
b. Power cable.
c. Control cable.
e. Instrumentation cable.
g. Wire connectors.
h. Insulating tape.
i. Pulling lubricant.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
2. 262, Standard Method of Test for Flame Travel and Smoke of Wires and
Cables for Use in Air-Handling Spaces.
4. 486A, Standard for Safety Wire Connectors and Soldering Lugs for use
with Copper Conductors.
7. 1277, Standard for Safety Electrical Power and Control Tray Cables with
Optional Optical-Fiber Members.
8. 1581, Standard for Safety Reference Standard for Electrical Wires, Cables,
and Flexible Cords.
1.03 DEFINITIONS
A. Cable: Multi-conductor, insulated, with outer sheath containing either building wire
or instrumentation wire.
B. Instrumentation Cable:
E. Building Wire: Single conductor, insulated, with or without outer jacket depending
upon type.
1.04 SUBMITTALS
A. Shop Drawings:
1) Wire connectors.
2) Insulating tape.
3) Cable lubricant.
A. Regulatory Requirements:
PART 2 - PRODUCTS
2.01 MATERIALS
b. Alphawire.
c. Cerrowire.
e. General Cable.
f. Okonite Company.
g. Southwire Company.
2. Instrumentation cable:
a. Analog cable:
1) Alphawire.
2) Belden Inc.
3) General Cable.
3. Wire connectors:
a. AFC Cable Systems, Inc., div. Tyco Electrical and Metal Products.
c. Burndy Corporation.
e. Buchanan.
f. Ideal.
g. Ilsco.
h. 3M Co.
k. Phoenix Contact.
a. 3M Co.
A. Building Wire:
B. Power Cable:
C. Control Cable:
E. Instrumentation Cable:
2. Analog cable:
c. Twisted with 100 percent foil shield coverage with drain wire.
3. Digital cable:
1. All multimode fiber optic cable, patch cords and connectors shall be colored
orange. SC type connectors shall be used for all fiber optic cable
connections. The fiber optic cable shall be multimode 850 nm, supplied by
Corning Cable Systems or Approved equal and shall meet or exceed the
following minimum specifications:
G. Wire Connectors:
1. Twist/screw on type:
b. 600 V rated.
a. 600 V rated.
2. Premium grade.
6. Color:
PART 3 - EXECUTION
A. Installation:
a. Building wire and power and control cable in architectural and non-
architectural finished areas.
b. Building wire and power and control cable in conduit below grade.
a. Building wire and power and control cable No. 8 AWG and smaller
in architectural and non-architectural finished areas.
a. For the wiring of control equipment within control panels and field
wiring of control equipment within switchgear, switchboards, motor
control centers.
1. Feeder and branch power conductors shall not be smaller than No. 12
AWG unless otherwise indicated on the Drawings.
a. Solid copper type conductors for No. 12 AWG and No. 10 AWG.
2. Control conductors shall not be smaller than No. 14 AWG unless otherwise
indicated on the Drawings.
1. Building wire:
a. When a bare ground is not provided, one (1) of the colored insulated
conductors shall be re-identified by stripping the insulation from the
entire exposed length or using green tape to cover the entire
exposed length.
2. Where field conditions dictate and written permission is obtained from the
Engineer.
3. Control circuits shall be isolated from feeder and branch power and
instrumentation circuits but combining of control circuits is permitted.
4. Instrumentation circuits shall be isolated from feeder and branch power and
control circuits but combining of instrumentation circuits is permitted.
5. Multiple branch circuits for lighting, receptacle and other 120 Vac circuits
are allowed to be combined into a common raceway.
F. Ground the drain wire of shielded instrumentation cables at one (1) end only.
1. The preferred grounding location is at the load (e.g., control panel), not at
the source (e.g., field mounted instrument).
G. Splices and terminations for the following circuit types shall be made in the
indicated enclosure type using the indicated method.
d. Manholes or handholes:
2. Control circuits:
1. For insulating connections of No. 8 AWG wire and smaller: 7 mil vinyl tape.
2. For insulating splices and taps of No. 6 AWG wire or larger: 10 mil vinyl
tape.
A. Testing: Perform each electrical test and visual and mechanical inspection stated
in NETA ATS (Acceptance Testing Specifications), Section 7.3.1. Certify
compliance with test parameters. See Specification Section 26 08 00.
3. Test results that do not comply with requirements and corrective action
taken to achieve compliance with requirements.
4.01 MEASUREMENT
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 12 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 DEFINITIONS
F. RGS: Rigid Galvanized Steel conduit. Also listed as RMC: Rigid Metallic Conduit.
1.03 SUBMITTALS
A. Product Data: For surface raceways, wireways and fittings, floor boxes, hinged-
cover enclosures, and cabinets.
a. The term "withstand" means "the unit will remain in place without
separation of any parts from the device when subjected to the
seismic forces specified and the unit will be fully operational after
the seismic event."
1.05 COORDINATION
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with Section 01 60 00 -
Product Requirements.
1. AFC Cable Systems, Inc., Div. Tyco Electrical and Metal Products.
3. Electri-Flex Co.
4. Allied Tube and Conduit, Div. Tyco Electrical and Metal Products.
2. Arnco Corp.
3. Cantex Inc.
5. Condux International.
6. Elecsys Corporation.
7. Electri-Flex Co.
10. AFC Cable Systems, Div. Tyco Electrical and Metal Products.
D. ENT and RNC Fittings: NEMA TC 3; match to conduit or tubing type and material.
3. Wiremold / Legrand.
B. Material and Construction: Sheet metal sized and shaped as indicated, NEMA 1 or
3R as required to suit installation situation.
C. Description: PVC plastic, extruded and fabricated to size and shape indicated, with
snap-on cover and mechanically coupled connections with plastic fasteners.
A. Surface Metal Raceways: Galvanized steel with snap-on covers. Finish with
manufacturer's standard prime coating.
2. Wiremold / Legrand.
4. Panduit Corp.
5. Wiremold / Legrand.
E. Types, sizes, and channels as indicated and required for each application, with
fittings that match and mate with raceways.
8. Robroy Industries.
C. Cast-Metal Outlet and Device Boxes: NEMA/ANSI FB 1, Type FD, with gasketed
cover.
I. Hinged-Cover Enclosures: NEMA 250, Type 1, with continuous hinge cover and
flush latch.
J. Cabinets: NEMA 250, Type 1, galvanized steel box with removable interior panel
and removable front, finished inside and out with manufacturer's standard enamel.
Hinged door in front cover with flush latch and concealed hinge. Key latch to match
panelboards. Include metal barriers to separate wiring of different systems and
voltage and include accessory feet where required for freestanding equipment.
PART 3 - EXECUTION
A. Outdoors:
B. Indoors:
1. Exposed: Rigid steel below 8 feet AFF; EMT more than 8 FT AFF.
2. Concealed: EMT.
D. Raceway Fittings: Compatible with raceways and suitable for use and location.
1. Intermediate Steel Conduit: Use threaded rigid steel conduit fittings, unless
otherwise indicated.
2. PVC Externally Coated, Rigid Steel Conduits: Use only fittings approved
for use with that material. Patch all nicks and scrapes in PVC coating after
installing conduits.
F. Where aluminum raceways are installed for such circuits and pass through concrete,
install in nonmetallic sleeve.
3.02 INSTALLATION
A. The Contractor shall conduct field investigations to ensure the locations of existing
and new conduits, pull boxes, junction boxes, and equipment prior to developing
shop plans.
B. All conduits shall be adequately separated from crossing other utilities per
requirements in these specifications and per SCRRA Design Criteria. Per the
Design Criteria, outside plant conduits shall be spaced at least 12 inches from
other parallel utilities, and at least 6 inch when crossing with other utilities
perpendicularly.
D. Outside fiber optic cable and conduits, where installed, shall be protected using
detectable marking tape placed 6 inch below grade for a length of at least 1,000
feet over the cable installed area to be protected.
E. All required interfaces for connection to the LCD Monitor and FOPP, to the LED
Message sign and FOPP, to the EMP, and to speakers shall be installed as per
requirements of these Specifications.
F. The Contractor shall install two (2), 1 inch conduits from the nearest electrical
pullbox and communications pullbox, respectively, to the location of LCD
monitor(s) installation. One conduit shall be used for communications
transmission/data transmission to LCD and the requirements for that conduit
including pulling cables are described in the CIS section. The other conduit shall
carry power to the monitor(s). The fiber shall be interfaced to the monitor through
the FOPP as shown in the contract plans.
G. The contractor shall provide electrical and communications cables and conduits
for LED message signs as shown in contract documents. The Contractor shall
install two (2), 1 inch conduits from the nearest electrical pullbox and
communications pullbox, respectively, to the location of LED message sign(s)
installation.
H. The Contractor shall extend power from Communications Shelter to the LCD
monitor(s). Within each monitor enclosure(s) the Contractor shall provide and
install power strip to connect/disconnect power to the Network Media Player (NMP)
and the monitor(s). The Contractor shall provide a duplex receptacle; one for the
AC and other for the power strip.
L. Protect stub-ups from damage where conduits rise through floor slabs.
M. Arrange so that curved portions of bends are not visible above the finished slab.
N. Make bends and offsets so that ID is not reduced. Keep legs of bends in the same
plane and keep straight legs of offsets parallel, unless otherwise indicated.
O. Conceal conduit and EMT within finished walls, ceilings, and floors, unless otherwise
indicated.
P. Raceways Embedded in Slabs: Install in middle 1/3 of slab thickness where practical
and leave at least 2 IN of concrete cover.
3. Run conduit larger than 1 IN trade size parallel or at right angles to main
reinforcement. Where at right angles to reinforcement, place conduit close
to slab support.
4. Change from nonmetallic tubing to rigid steel conduit before rising above
the floor.
2. Make parallel bends in parallel or banked runs. Use factory elbows only
where elbows can be installed parallel; otherwise, provide field bends for
parallel raceways.
R. Join raceways with fittings designed and approved for that purpose and make joints
tight.
S. Terminations:
T. Install pull wires in empty raceways. Use polypropylene or monofilament plastic line
with not less than 200 LB tensile strength. Leave at least 12 IN of slack at each end
of pull wire.
U. Telephone and Signal System Raceways, 2 IN Trade Size and Smaller: In addition
to above requirements, install raceways in maximum lengths of 150 FT and with a
maximum of two 90-degree bends or equivalent. Separate lengths with pull or
junction boxes where necessary to comply with these requirements.
V. Install raceway sealing fittings at suitable, approved, and accessible locations and
fill them with UL-listed sealing compound. For concealed raceways, install each
fitting in a flush steel box with a blank cover plate having a finish similar to that of
adjacent plates or surfaces. Install raceway sealing fittings at the following points:
Z. Set floor boxes level and flush with finished floor surface.
AA. Set floor boxes level. Trim after installation to fit flush with finished floor surface.
BB. Install hinged-cover enclosures and cabinets plumb. Support at each corner.
3.03 PROTECTION
A. Provide final protection and maintain conditions that ensure coatings, finishes, and
cabinets are without damage or deterioration at time of Substantial Completion.
3.04 CLEANING
4.01 MEASUREMENT
A. Conduits, Raceways, and Boxes for electrical and communications systems will
be measured by the unit or fraction thereof furnished and completed in accordance
with the Contract Documents and as measured by the Engineer. The quantities as
contained on the Schedule of Quantities and Prices, or approved schedule of
values, as applicable, as derived from the Plans will be used as the basis for this
measurement.
C. Cabinets will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
4.02 PAYMENT
A. Conduits, Raceways, and Boxes; Enclosures; and Cabinets for electrical and
communications systems furnished and completed in accordance with the
Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
END OF SECTION 26 13 00
WIRING DEVICES
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
4. Floor service outlets, poke through assemblies, service poles, and multi
outlet assemblies.
B. Related Specification Sections include but are not necessarily limited to:
1.02 SUBMITTALS
B. Shop Drawings: List of legends and description of materials and process used
for pre-marking wall plates.
C. Samples: For each type of device and wall plate specified, in each color
specified.
A. Regulatory Requirements:
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with:
2.02 MATERIALS
1. Wiring Devices:
2. Multioutlet Assemblies:
b. Wiremold / Legrand.
B. Receptacles:
C. Switches:
1. Single and Double Pole Switches: Comply with DSCC W-S-896F and
UL 20.
3. Dimmer Switches: Modular, full wave, solid state units with integral, quiet
on/off switches and audible frequency and EMI/RFI filters.
D. Wall Plates: Single and combination types to match corresponding wiring devices.
1. Plate Securing Screws: Metal with head color to match plate finish.
2. Material for Finished Spaces: Smooth, high impact thermoplastic 0.04 IN.
4. Material for Wet Locations: Cast aluminum with spring-loaded lift cover,
and listed and labeled for use in wet locations.
2.03 FINISHES
A. Color:
PART 3 - EXECUTION
3.01 INSTALLATION
A. Install devices and assemblies level, plumb, and square with building lines.
B. Install wall dimmers to achieve indicated rating after derating for ganging.
E. Adjust locations of floor service outlets and service poles to suit arrangement of
partitions and furnishings.
3.02 IDENTIFICATION
3.03 CONNECTIONS
1. After installing wiring devices and after electrical circuitry has been
energized, test for proper polarity, ground continuity, and compliance with
requirements.
2. Test GFCI operation with both local and remote fault simulations according
to manufacturer's written instructions.
B. Remove malfunctioning units, replace with new units, and retest as specified
above.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 14 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
3. Fuses.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
3. C37.17, Trip Devices for AC and General Purpose DC Low Voltage Power
Circuit Breakers.
1.03 SUBMITTALS
A. Shop Drawings:
d. Accessories.
e. Wiring diagrams.
C. Miscellaneous Submittals:
1. Reports:
1.04 MAINTENANCE
A. Extra Materials: Provide Owner with 10 percent, but not less than 3, each type
and rating installed fuses at completion of Project.
PART 2 - PRODUCTS
1. Circuit breakers:
a. Eaton/Cutler-Hammer.
b. Schneider Electric/Square D.
c. Siemens.
d. General Electric.
2. Fuses:
b. Eaton/Cutler-Hammer.
c. Siemans.
d. General Electric.
1. General:
b. Unit construction.
k. Bolt on type.
c. Frame sizes 225 to 400 amp (trip settings less than 400A):
1) Standard: UL 943.
b. Frame size 400 amp to 1200 amp (trip settings between 400 and
1200A):
2.04 FUSES
3. Voltage: 600 V.
4. Ratings: As indicated.
7. UL Class:
9. Motor Protection: Coordinate fuse size with motor to provide motor running
protection.
10. Instruction Label: When standard holder type fuses are specified, Class
K1 or K5, provide each enclosure where fuses are installed with instruction
label fastened at obvious location in enclosure.
PART 3 - EXECUTION
3.01 INSTALLATION
D. Field settings:
F. Circuit Breakers:
a. Frame sizes 400 amp and less with trip setting less than 400A shall
be thermal magnetic type.
b. Frame sizes 400 amp and larger shall be solid state trip type.
c. Frame sizes 1000 amp and above shall include integral ground fault
protection.
1. Set all circuit breaker adjustable taps as per Protective Device Coordination
Study recommended trip settings, refer to Specification Section 26 05 50
except adjust motor circuit protectors per the motor nameplate and NFPA
70 requirements.
C. Testing:
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 28 00
SAFETY SWITCHES
PART 1 - GENERAL
1.01 SUMMARY
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
A. Shop Drawings:
PART 2 - PRODUCTS
A. Subject to compliance with the Contract Documents, the following safety switch
manufacturers are acceptable:
1. Cutler-Hammer.
3. Square D Company.
4. Siemens.
6. Crouse-Hinds.
7. Killark.
A. General:
4. Switch blades will be fully visible in the OFF position with the enclosure
door open.
B. Ratings:
a. Non-fused: 10,000A.
b. Fused: 200,000A.
1. Neutral kits.
D. Enclosures:
1. NEMA 1 rated:
a. Body and cover: Sheet steel finished with rust inhibiting primer and
manufacturers standard paint inside and out.
2. NEMA 3R rated:
a. Body and cover: Sheet steel finished with rust inhibiting primer and
manufacturers standard paint inside and out.
3. NEMA 4 rated:
a. Body and cover: Sheet steel finished with rust inhibiting primer and
manufacturers standard paint inside and out.
7. NEMA 12 rated:
a. Body and cover: Sheet steel finished with rust inhibiting primer and
manufacturers standard paint inside and out.
1. Fuses.
PART 3 - EXECUTION
3.01 INSTALLATION
B. Install switches adjacent to the equipment they are intended to serve unless
otherwise indicated on the Drawings.
C. Provide auxiliary contact kit on local safety switches for motors being controlled by
a variable frequency drive.
2. Provide PVC coating in corrosive and highly corrosive areas when PVC
coated conduit is used.
2. Provide PVC coating in corrosive and highly corrosive areas when PVC
coated conduit is used.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 28 16
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 SUBMITTALS
A. Product Data: For each type of product indicated. Include rated capacities;
shipping, installed, and operating weights; furnished specialties; and accessories.
1. UL 1283 certification.
C. Field Test Reports: Written reports of tests specified in Part 3 of this Section.
Include the following:
E. IEEE Compliance: Comply with IEEE C62.41, IEEE Guide for Surge Voltages in
Low Voltage AC Power Circuits, and test devices according to IEEE C62.45, IEEE
Guide for Surge Suppressor Testing.
1. Notify Engineer not less than two days in advance of proposed utility
interruptions.
C. Service Conditions: Rate surge protective devices for continuous operation under
the following conditions, unless otherwise indicated:
1.05 COORDINATION
1.06 WARRANTY
A. General Warranty: Special warranties specified in this Article shall not deprive
Authority of other rights Authority may have under other provisions of the Contract
Documents and shall be in addition to, and run concurrent with, other warranties
made by Contractor under requirements of the Contract Documents.
A. Furnish extra materials described below that match products installed and that are
packaged with protective covering for storage and identified with labels describing
contents.
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with Section 01 60 00 -
Product Requirements.
2.02 MANUFACTURERS
f. Intermatic, Inc.
b. Telebyte, Inc.
A. Surge Protective Device Description: Non-modular type with the following features
and accessories:
3. One set of dry contacts rated at 5 A, 250 Vac, for remote monitoring of
protection status.
8. Red and green LED indicator lights for power and protection status.
10. One set of dry contacts rated at 5 A and 250 Vac, for remote monitoring
of protection status. Coordinate with building power monitoring and control
system.
E. Protection modes and UL 1449 clamping voltage for grounded wye circuits with
voltages of 480Y/277; 208Y/120; 3 PH, four-wire circuits, shall be as follows:
F. Protection modes and UL 1449 clamping voltage for 240/120 V, single phase,
three-wire circuits, shall be as follows:
G. Protection modes and UL 1449 clamping voltage for 240/120 V, 3 PH, four-wire
circuits, with high leg shall be as follows:
A. Surge Protective Device Description: Non-modular type with the following features
and accessories:
3. One set of dry contacts rated at 5 A, 250 Vac, for remote monitoring of
protection status.
7. Red and green LED indicator lights for power and protection status.
9. One set of dry contacts rated at 5 A, 250 Vac, for remote monitoring of
protection status. Coordinate with building power monitoring and control
system.
D. Protection modes and UL 1449 clamping voltage for grounded wye circuits with
voltages of 480Y/277 or 208Y/120; 3-phase, 4-wire circuits, shall be as follows:
E. Protection modes and UL 1449 clamping voltage for 240/120 V, single phase,
three-wire circuits, shall be as follows:
F. Protection modes and UL 1449 clamping voltage for 240/120 V, 3 PH, four-wire
circuits, with high leg shall be as follows:
A. Surge Protective Device Description: Unit type, panel-mounted design with the
following features and accessories:
3. One set of dry contacts rated at 5 A, 250 Vac, for remote monitoring of
protection status.
5. Red and green LED indicator lights for power and protection status.
C. Protection modes and UL 1449 clamping voltage for grounded wye circuits with
voltages of 480Y/277; 208Y/120; 3 PH, four-wire circuits, shall be as follows:
D. Protection modes and UL 1449 clamping voltage for 240/120 V, single phase,
three-wire circuits, shall be as follows:
E. Protection modes and UL 1449 clamping voltage for 240/120 V, 3 PH, four-wire
circuits, with high leg shall be as follows:
2. LED indicator lights for reverse polarity and open outlet ground.
3. Circuit breaker and thermal fusing. When protection is lost, circuit opens
and cannot be reset.
A. Protectors for copper control and data conductors entering the building from the
outside shall be as recommended by the manufacturer for the type of line being
protected.
2.08 ENCLOSURES
A. NEMA 250, with type matching the enclosure of panel or device being protected.
PART 3 - EXECUTION
A. Install devices at service entrance on load side, with ground lead bonded to service
entrance ground.
B. Install devices for panelboard and auxiliary panels with conductors between
suppressor and points of attachment as short and straight as possible. Do not
exceed manufacturer's recommended lead length. Do not bond neutral and
ground.
3.02 CONNECTIONS
A. Testing: SCRRA will engage a qualified testing agency to perform the following
field quality-control testing:
1. After installing surge protective devices, but before electrical circuitry has
been energized, test for compliance with requirements.
3. Perform each visual and mechanical inspection and electrical test stated in
NETA ATS, Section 7.19. Certify compliance with test parameters.
3.04 DEMONSTRATION
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 28 90
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 SUBMITTALS
A. Product Data: Technical data for each type of switch and circuit breaker
indicated.
A. Regulatory Requirements:
B. Source Limitations: Obtain switches and circuit breakers through one source from
a single manufacturer.
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with Section 01 60 00 -
Product Requirements.
2.02 MATERIALS
1. ABB Group.
B. Enclosed Switches:
2. Enclosed, Fusible Switch, 800 A and Smaller: NEMA KS 1, Type HD, with
clips to accommodate specified fuses, and lockable handle, interlocked
with cover.
d. Shunt Trip: 120-V trip coil energized from separate circuit, capable
of tripping at 75 percent of rated voltage.
D. Enclosures:
PART 3 - EXECUTION
3.01 INSTALLATION
A. Testing: After installing disconnect switches and circuit breakers and after
electrical circuits have been energized, demonstrate product capability and
compliance with requirements.
B. Inspections and Tests for Switches and Circuit Breakers: Make internal and
external inspections and perform tests, including the following:
1. Inspect for freedom from physical damage, proper unit rating, mechanical
condition, enclosure integrity, cover operation, unit anchorage, clearances,
and tightness of electrical connections. If a loose electrical connection is
observed on any unit, check each electrical connection for each switch
and circuit breaker with a torque wrench for compliance with
manufacturer's torquing instructions.
3. Test cover and other interlocks and interlock release devices for proper
operation.
1. Inspect for proper frame, trip, and fault current interrupting rating.
2. Test shunt trip devices, circuits, and actuating components for proper
operation.
E. Correct defective and malfunctioning units on site, where possible, and re-
inspect and retest to demonstrate compliance; otherwise, remove and replace
with new units and retest.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 41 00
ENCLOSED CONTROLLERS
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 SUBMITTALS
A. Product Data: For each type of enclosed controller. Include dimensions and
manufacturer's technical data on features, performance, electrical characteristics,
ratings, and finishes.
b. Nameplate legends.
a. The term "withstand" means "the unit will remain in place without
separation of any parts from the device when subjected to the
seismic forces specified and the unit will be fully operational after
the seismic event."
E. Qualification Data: For firms and persons specified in "Quality Assurance" Article.
G. Load-Current and Overload-Relay Heater List: Compile after motors have been
installed and arrange to demonstrate that selection of heaters suits actual motor
nameplate full-load currents.
A. Store enclosed controllers indoors in clean, dry space with uniform temperature to
prevent condensation. Protect enclosed controllers from exposure to dirt, fumes,
water, corrosive substances, and physical damage.
1.05 COORDINATION
A. Furnish extra materials described below that match products installed and that are
packaged with protective covering for storage and identified with labels describing
contents.
1. Spare Fuses: Furnish one spare for every three installed, but not less than
one set of three of each type and rating.
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with Section 01 60 00 -
Product Requirements.
2.02 MANUFACTURERS
a. ABB.
A. Description: NEMA ICS 2, general purpose, Class A, with toggle action and
overload element.
A. Description: NEMA ICS 2, Class A, full voltage, non-reversing, across the line,
unless otherwise indicated.
2.05 ENCLOSURES
2.06 ACCESSORIES
B. Push-Button Stations, Pilot Lights, and Selector Switches: NEMA ICS 2, heavy-
duty type.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Examine areas and surfaces to receive enclosed controllers for compliance with
requirements, installation tolerances and other conditions affecting performance.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.02 APPLICATIONS
3.03 INSTALLATION
B. For control equipment on walls, bolt units to wall or mount on lightweight structural-
steel channels bolted to wall. For controllers not at walls, provide freestanding
racks complying with Section 26 05 00 - Basic Electrical Materials and Methods.
3.04 IDENTIFICATION
3.06 CONNECTIONS
C. Ground equipment.
1. Perform each electrical test and visual and mechanical inspection indicated
in NETA ATS, Sections 7.5, 7.6, and 7.16.
3. Test results that do not comply with requirements and corrective action
taken to achieve compliance with requirements.
3.08 ADJUSTING
3.09 CLEANING
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 42 00
SWITCHBOARDS
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
C. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
B. Shop Drawings: For each switchboard and related equipment. Include the
following:
A. Verify the space required for the switchboard is equal to or less than the space
allocated
B. Regulatory Requirements:
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for comparable
products and substitutions in accordance with Section 26 60 00 - Product
Requirements.
2.02 MATERIALS
1. ABB Group.
B. Manufactured Units:
4. Rodent barrier.
5. Seismic qualified.
8. Suitable for use as service entrance when not more than 6 main
disconnecting means are provided.
11. Means to padlock all main and feeder devices in the open position.
12. Buses and Bus Connections: Service entrance rated three phase, four
wire, and copper ground bus unless otherwise indicated. Materials and
Features as follows:
14. Material for Main Bus: Hard drawn copper of 98 percent conductivity.
16. Use copper for protective device line and load connections.
19. Bus Transition and Incoming Pull Sections: Match and align with basic
switchboard.
22. Load Terminals: Insulated, rigidly braced, silver plated, copper runback
bus extensions equipped with pressure connectors for outgoing circuit
conductors.
24. Equipped with pressure connectors for feeder and branch circuit ground
conductors. For busway feeders, extend insulated equipment grounding
cable to busway ground connection and support cable at intervals in
vertical run.
26. Main Phase Buses, Neutral Buses, and Equipment Ground Buses:
Uniform capacity for entire length of switchboard's main and distribution
sections. Provide for future extensions from both ends.
27. Neutral Buses: 100 percent of the ampacity of the phase buses, unless
otherwise indicated, equipped with pressure connectors for outgoing
circuit neutral cables.
28. Future Devices: Equip positions with mounting brackets, supports, bus
connections, load terminals, and appurtenances rated at maximum
capacity available for future unit.
29. Bus Bar Insulation: Flame retardant, 105 DegC minimum tape wrapping,
or flame retardant, sprayed on insulation of same temperature rating,
factory applied to individual bus bars.
4. Electronic Trip Unit Circuit Breakers: Required for circuit breaker frame
size 400 A and larger. RMS sensing; field replaceable rating plug; with field
adjustable settings:
5. Instantaneous trip.
9. Current Limiting Circuit Breakers: Frame sizes 400 A and smaller; let
through ratings less than NEMA FU 1, RK-5.
10. Molded Case Circuit Breaker Features and Accessories: Standard frame
sizes, trip ratings, and number of poles.
11. Application Listing: Appropriate for application; Type SWD for switching
fluorescent lighting loads; Type HACR for heating, air conditioning, and
refrigerating equipment.
12. Ground Fault Protection: Integrally mounted sensor, relay, and trip unit
with adjustable pickup and time delay settings, push to test feature, and
ground fault indicator.
13. Shunt Trip: 120-V trip coil energized from separate circuit, capable of
tripping at 75 percent of rated voltage.
14. Auxiliary Switch: Two SPDT switches with "a" and "b" contacts; "a"
contacts mimic circuit-breaker contacts, "b" contacts operate in reverse of
circuit breaker contacts.
D. Instrumentation:
d. Megawatts: ±2 percent.
e. Megavars: ±2 percent.
E. Control Power:
3. Control Power Fuses: Primary and secondary fuses for current-limiting and
overload protection of transformer and fuses for protection of control
circuits.
F. Accessory Components:
2. Portable Test Set: To test functions of solid state trip devices without
removal from switchboard. Include relay and meter test plugs suitable for
testing switchboard meters and switchboard class relays.
PART 3 - EXECUTION
3.01 INSTALLATION
B. Outdoor location:
1. NEMA 3R enclosure.
D. Operating Instructions: Frame and mount the printed basic operating instructions
for switchboards, including control and key interlocking sequences and emergency
procedures. Fabricate frame of finished wood or metal and cover instructions
with clear acrylic plastic. Mount on front of switchboards.
3.02 IDENTIFICATION
D. Main and feeder breakers: Utilize four (4) individual current sensors; the phase
sensors are integral to the circuit breaker and the neutral sensor is external to the
circuit breaker Testing: After installing switchboards and after electrical circuitry
has been energized, demonstrate product capability and compliance with
requirements.
E. Infrared Scanning: After Substantial Completion, but not more than 60 days after
Final Acceptance, perform an infrared scan of each switchboard. Remove front
and rear panels so that joints and connections are accessible to portable scanner.
3.04 ADJUSTING
A. Set field adjustable switches and circuit breaker trip ranges as per
Section 26 05 50 - Overcurrent Protective Device Coordination.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
END OF SECTION 26 44 10
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
a. Pulling Section.
b. Metering Compartment.
B. Related Specification Sections include but are not necessarily limited to:
1.02 SUBMITTALS
B. Shop Drawings: For each electric cabinet, lighting control cabinet and
panelboard:
a. Enclosure types and details for types other than NEMA 250,
Type 1.
A. Definitions:
PART 2 - PRODUCTS
2.01 MATERIALS
1. ABB Group.
B. For electric service pedestal and lighting control cabinets custom engineered,
approved manufacturers:
2. Tesco Electric.
C. Components:
2. Front: Secured to box with concealed trim clamps. For surface mounted
fronts, match box dimensions; for flush mounted fronts, overlap box.
6. Equipment Ground Bus: Adequate for feeder and branch circuit equipment
ground conductors; bonded to box.
10. Skirt for Surface Mounted Panelboards: Same thickness and finish as
panelboard front with flanges for attachment to panelboard, wall, and
ceiling or floor.
11. Feed through Lugs: Locate at opposite end of bus from incoming lugs or
main device.
2. Doors: Front mounted with concealed hinges; secured with flush latch
with tumbler lock; keyed alike.
E. Distribution Panelboards:
1. Doors: Front mounted, and secured with vault type latch with tumbler
lock; keyed alike.
a. For Circuit Breaker Frame Sizes 125 A and Smaller: Bolt on circuit
breakers.
PART 3 - EXECUTION
3.01 INSTALLATION
C. Mounting: Plumb and rigid without distortion of box. Mount recessed panelboards
with fronts uniformly flush with wall finish.
E. Provision for Future Circuits at Flush Panelboards: Stub four 1 IN empty conduits
from panelboard into accessible ceiling space or space designated to be ceiling
space in the future. Stub four 1 IN empty conduits into raised floor space or below
slab not on grade.
F. Wiring in Panelboard Gutters: Arrange conductors into groups and bundle and
wrap with wire ties after completing load balancing.
3.02 IDENTIFICATION
A. Testing and Inspection: After installing panelboards and after electrical circuitry
has been energized, demonstrate product capability and compliance with
requirements.
B. Balancing Loads: After Substantial Completion, but not more than 60 days after
Final Acceptance, measure load balancing and make circuit changes as follows:
3. After circuit changes, recheck loads during normal load period. Record
load readings before and after changes and submit test records.
C. Infrared Scanning: After Substantial Completion, but not more than 60 days after
Final Acceptance, perform an infrared scan of each electrical cabinet, service
pedestal and panelboard. Remove panel fronts so joints and connections are
accessible to portable scanner.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 44 20
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
2. Distribution transformers.
B. Related Specification Sections include but are not necessarily limited to:
1.02 SUBMITTALS
A. Regulatory Requirements:
PART 2 - PRODUCTS
2.01 GENERAL
A. Where products and manufacturers are listed, make submittals for proposed
comparable products and substitutions in accordance with Section 01 60 00 -
Product Requirements.
2.02 MATERIALS
4. Magnetek, Inc.
B. Factory assembled and tested, air cooled units for 60-Hz service.
A. Comply with NEMA ST 20, and list and label as complying with UL 1561.
1. Core and coil shall be encapsulated within resin compound, sealing out
moisture and air.
G. Taps for Transformers 7.5 to 24 kVA: One (1), 5 percent tap above and one (1),
5 percent tap below normal full capacity.
H. Taps for Transformers 25 kVA and Larger: Two (2), 2.5 percent taps above and
two (2), 2.5 percent taps below normal full capacity.
1. Construct unit to not overheat when carrying full load current with
harmonic distortion corresponding to designated K factor.
A. Transformer: Self cooled, two winding dry type, rated for continuous duty,
complying with NEMA ST 1, and listed and labeled as complying with UL 506.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Install wall mounting transformers level and plumb with wall brackets fabricated
by transformer manufacturer.
3.02 CONNECTIONS
3.03 ADJUSTING
A. Record transformer secondary voltage at each unit for at least 48 HRS of typical
occupancy period. Adjust transformer taps to provide optimum voltage conditions
at secondary terminals. Optimum is defined as not exceeding nameplate voltage
plus 10 percent and not being lower than nameplate voltage -5 percent. Submit
recording and tap settings as test results.
C. Output Settings Report: Prepare a written report recording output voltages and
tap settings.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 26 46 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
c. Lamps.
d. Ballasts.
e. Light poles.
f. Lighting control.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
6. 1598, Luminaires.
1.03 SUBMITTALS
A. Shop Drawings:
PART 2 - PRODUCTS
2. Lamps:
a. Osram/Sylvania.
b. General Electric.
c. Philips.
d. Venture.
1. UL labeled.
C. Provide standard plaster frame for all recessed lighting fixtures installed in plaster
walls or ceilings.
E. When intended for use in wet areas: Mark fixtures "Suitable for wet locations."
F. When intended for use in damp areas: Mark fixtures "Suitable for damp locations"
or "Suitable for wet locations."
A. Fluorescent:
1. UL 1598.
4. Finish:
5. Prewired and provided with lamps that are properly mated to the ballast
operating characteristics.
1. UL 1598.
2. Finish:
3. Prewired and provided with lamps that are properly mated to the ballast
operating characteristics.
2.04 LAMPS
A. Fluorescent:
c. Minimum initial lumen ratings for each lamp type shall be:
b. Clear lamps:
c. Minimum initial lumen ratings for metal halide lamps with a medium
base in a vertical position shall be:
1) 14250 lumens for 150 watt, ED-17 (ANSI M102) clear lamp.
d. Minimum initial lumen ratings for metal halide lamps with a mogul
base in a vertical position shall be:
1) 14250 lumens for 150 watt, ED-28 (ANSI M102) clear lamp.
2) 25000 lumens for 250 watt, ED-28 (ANSI M138) clear lamp.
3. The specified fixture in the fixture schedule shall dictate the required lamp
operating position and base type.
4. Provide lamps that have the correct bulb shape for the fixture specified.
2.05 BALLASTS
1. UL 935.
6. Input current with Total Harmonic Distortion (THD) of less than 32 percent.
7. Lamp current crest factor: Less than 1.7, in accordance with lamp
manufacturer's recommendations and NEMA/ANSI C82.1.
a. 0.925 for rapid start 265 mA (T8) and 430 mA (T12) ballasts.
a. Class A for rapid start 265 mA (T8) and 430 mA (T12) ballasts.
10. Coil temperature not to exceed 150 DegF temperature rise over 40 105
DegF ambient.
11. Meet the requirements of the FCC 47 CFR 18, for non-consumer
equipment for EMI and RFI.
12. Meet all applicable ANSI and IEEE standards regarding harmonic distortion
and transient protection such as IEEE C62.41, Cat. A, for transient
protection.
1. UL 935.
5. Lamp current crest factor: Less than 1.7, in accordance with lamp
manufacturer's recommendations and NEMA/ANSI C82.11.
11. Light output to remain constant for a line voltage fluctuation of +5 percent.
12. Meet the requirements of the FCC 47 CFR 18, for non-consumer
equipment for EMI and RFI.
15. Comply with all applicable state and federal efficiency standards.
2. Metal halide:
g. Types:
2.06 POLES
B. Furnish a minimum of 10 percent of total of each type and amperage of fuses for
fixtures indicated to be fused.
PART 3 - EXECUTION
3.01 INSTALLATION
1. Provide mounting hardware for the ceiling system in which the fixture is to
be installed.
2. When fixtures are supported from outlet boxes, install per NFPA 70.
I. Install exterior fixtures so that water can not enter or accumulate in the wiring
compartment.
J. Where indicated provide two-level control of three (3) and/or four (4) lamp
fluorescent fixtures.
1. Provide two (2) ballasts per fixture and control inside lamp(s) in each fixture
by one (1) switch or set of switches and the outside two (2) lamps by a
second switch or group of switches.
D. Conductors:
b. Standard: UL 248-4.
2. Fuseholder:
B. Exterior wall mounted and pole mounted fixtures controlled as detailed on the
Drawings.
B. Replace all inoperable lamps with new lamps prior to final acceptance.
C. Aim all emergency lighting units, so that, the path of egress is illuminated.
4.01 MEASUREMENT
A. Light Fixtures including lamps and ballast will be measured by the unit or fraction
thereof furnished and completed in accordance with the Contract Documents and
as measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
B. Light Poles will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Light Fixtures including lamps and ballast furnished and completed in accordance
with the Contract Documents will be paid for at the Contract Unit Price, as listed
on the Schedule of Quantities and Prices. This price shall include full
compensation for furnishing all labor, Materials, tools, equipment, supplies,
supervision, and incidentals, and doing all work, as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
B. Light Poles furnished and completed in accordance with the Contract Documents
will be paid for at the Contract Unit Price, as listed on the Schedule of Quantities
and Prices. This price shall include full compensation for furnishing all labor,
Materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 26 50 00
PART 1 - GENERAL
1.01 SUMMARY
A. This section describes the minimum requirements for the SCRRA Access Control
System (ACS).
C. The controller(s) shall receive data input from other hardware components of the
system, such as readers and relays. All system controllers shall be connected to
the system server(s) where event history, cardholder data and system
programming data shall reside. The controller(s) shall receive data input from, and
provide system data to, the controlling system server(s).
D. The system shall include, but not be limited to, all equipment, materials, labor,
documentation and services necessary to furnish and install a complete and
operational system to include, but not be limited to, the following functions:
E. The standard Access Control System used by SCRRA is Identicard PremiSys Pro
by Identicard Systems.
1.03 DEFINITIONS
Abbreviation Description
#A Ampere
ACO Alarm Company Operator
ACS Access Control System
CSLB Contractors State License Board (California)
DIP Dual In-Line Package
EOL End of Line
FIPS Federal Information Processing Standards
HID HID Corporation
Hz Hertz
ID Identification
I/O Input/Output
IP Internet Protocol
IT Information Technology
LAN Local Area Network
LED Light-Emitting Diode
MB Megabyte
MUX Multiplexer
OSDP Open Supervised Device Protocol
PC Personal Computer
SCRRA Southern California Regional Rail Authority
SDRAM Synchronous Dynamic Random-Access Memory
SRAM Static Random-Access Memory
UL Underwriters Laboratories, Inc.
V Volts
VAC Volts Alternating Current
VDC Volts Direct Current
YMCKO Yellow, Magenta, Cyan, Black, Clear Overlay
A. All work and materials shall conform to all applicable SCRRA, Federal, State, local
and/or municipal codes and regulations governing the installation. If there is a
conflict between this specification and the referenced standards, federal, state,
local and/or municipal codes, it is the bidder's responsibility to immediately bring
the conflict to the attention of SCRRA for resolution. National standards shall
prevail unless local codes are more stringent. Contractor shall not attempt to
resolve conflicts directly with the local authorities unless specifically authorized by
SCRRA.
C. All controllers and connected boards, readers and the like shall be tested to ensure
that a fully functioning system is designed and installed. The system supplied
under this specification shall be a microprocessor-based system. The system shall
utilize independently addressed, microprocessor-based controllers as described in
this specification.
D. Contractor shall submit a detailed project plan that will describe in detail how they
will approach the project, from inception to finalization. The plans must include the
following information (at a minimum):
1. Equipment Schedules
1.05 SUBMITTALS
2. Shop Drawings: Provide shop drawings that are applicable and pertain to
ACS provisions.
c. Riser diagrams
d. Complete floor plan drawing locating all system devices and scaled
plan and elevation of all equipment in the access-control system,
showing the placement of each individual item of access-control
equipment as well as raceway size and routing, junction boxes, and
conductor size, quantity, and color in each raceway
D. The Contractor shall have an office and service department located within the
Metrolink service area.
F. The Contractor shall serve as the single point of responsibility for the work
described in this section.
H. All equipment and components shall be installed in strict compliance with each
manufacturer's recommendations. Consult the manufacturer's installation manuals
for all wiring diagrams, schematics, physical equipment sizes, etc., before
beginning system installation. Refer to the manufacturer's riser/connection
diagram and details for all specific system installation/termination/wiring data.
5. Train the Authority operations and maintenance staff in the care, operation,
troubleshooting and maintenance of the equipment.
A. The Contractor shall be responsible for all receiving, handling and storage of all
equipment and materials for the project.
A. The Contractor shall be responsible for inspecting the job site and becoming
familiar with the conditions under which the work will be performed. Inspection of
the facility may be made by appointment with SCRRA. Contractors are requested
to inspect the building prior to submitting any technical data for approval or
commencement of work.
B. The Contractor shall be responsible for prior coordination of all work and demolition
with SCRRA.
C. The Contractor shall verify that the proposed equipment and methods of
installation are compatible with the existing conditions.
D. Notify SCRRA in writing if modifications of the existing facility are required in order
to accommodate the new equipment. These modifications shall be reviewed and
approved by SCRRA.
E. The Contractor shall protect all facility property (buildings, walls, floors, etc.) from
damage resulting from installation work. Any and all damage to facility property
caused by installation work shall be repaired by the Contractor at its own expense.
F. The Contractor shall clean up areas in which it has been working following each
day’s work. Dispose of all trash and waste in the appropriate designated areas.
G. Upon project completion, return project site to a condition equal to or better than
original.
1.10 WARRANTY
A. The Contractor shall warranty all materials, installation and workmanship for one
(1) year from final acceptance.
1. The Contractor shall be responsible for and make good, without any
expense to SCRRA, any and all defects arising during this warranty period
that are due to imperfect materials, equipment, improper installation or poor
workmanship.
PART 2 - PRODUCTS
2.01 GENERAL
A. Unless otherwise specified, products for the ACS shall be consistent with and
compatible with the established standards for SCRRA ACS.
B. The specified hardware to be used with the ACS management software shall be
hardware designed for use with Identicard PremiSys Pro software by Identicard
Systems.
C. Any existing legacy hardware (e.g. Identicard Series 9000 Panels) shall be
replaced with hardware listed in this section, and designed for use with the
Identicard PremiSys Access Control System.
E. Provide and install required cabling, connectors, patch cords, resistor packs,
terminators, and all other miscellaneous items required for a fully functional
system.
F. Access control panels and all supporting system power supplies shall typically be
located in temperature controlled telecommunications rooms (e.g. server room,
data center, etc.), unless otherwise specified.
C. SCRRA utilizes the ID badging (PremiSys Pro) and mobile app features of the
PremiSys Pro software.
A. Two-Reader Controller
d. A 3-volt lithium coin cell shall provide SRAM and clock backup.
4. The Two-Reader Controller shall provide two reader ports built into the
controller. Such reader ports shall support up to two (2) reading devices of
the same or different technologies.
7. Any controller within the network of controllers shall have an address that
is different from any other on the same port of the PC. The Two-Reader
Controller's address shall be selected by means of a configuration Web
page stored on the Two-Reader Controller and accessed through a Web
browser using a default IP address.
8. The Two-Reader Controller shall provide eight (8) supervised inputs for use
as door-position inputs, request-to-exit inputs etc. The states of the inputs
shall be as follows: normally open; normally closed; 1 K normal, 2 K active;
and 2 K normal, 1 K active. It additionally shall be possible to set the
debounce and hold times for each input on the board. It shall be possible
to set all input configuration via the system software.
9. Held-open times (the time during which a door may be held open without
generating a system alarm) for inputs on the board assigned as door-
position points shall be software-selectable in two-second increments
between 2 and 65,534 seconds.
10. All input points shall have a corresponding LED on the board that indicates
the state of the point.
11. The Two-Reader Controller shall include two (2) Form-C, noninductive
relay outputs for door-lock control or alarm signaling. Control of the relays
shall be software-assignable to be triggered by card presentations, time
zones and/or other system actions. The contact ratings shall be 5A at 30
VDC. The relays shall be configurable for normal (relay energized when
“on”) or inverted (relay de-energized when “on”) action. Pulse time of a
relay used as a door-lock relay shall be software-selectable between 1 and
255 seconds.
12. It shall be possible via the system software to link an input or relay on the
Two-Reader Controller to cause an action on any other relay in the system
and to select the action that a linked relay will take when the triggering input
or relay is activated.
13. The Two-Reader Controller shall have a dedicated input point for optional
connection to a controller enclosure tamper switch and another dedicated
input point for optional connection to a power-loss monitoring device.
Systems requiring use of one of the available system input points for this
monitoring shall be unacceptable.
14. The system shall allow the incorporation of a rechargeable battery as part
of the power supply to provide full functionality for the controller, system
communications and board-powered readers in the event of a power
failure.
B. Two-Reader Board
2. The Two-Reader board shall support up to two (2) reading devices of the
same or different technologies, the type being selectable through the
application software. Systems that are unable to use readers of different
technologies on the same board or require a change in software, firmware
or "other" interface devices shall be unacceptable.
3. The Two-Reader board shall use quick-disconnect terminal blocks for all
interconnections to the interface. The Two-Reader board shall be intended
for use in low voltage, Class 2 circuits only.
7. The Two-Reader board shall provide sensor monitoring via eight (8)
supervised inputs, which can be used as door-position inputs, request-to-
exit inputs and for other purposes. The states of the inputs shall be as
follows: normally open; normally closed; 1 K normal, 2 K active; and 2 K
normal, 1 K active. It additionally shall be possible to set the debounce and
hold times for each input on the board. It shall be possible to set all input
configuration via the system software.
8. Held-open times (the time during which a door may be held open without
generating a system alarm) for inputs on the board assigned as door-
position points shall be software-selectable in two-second increments
between 2 and 65,534 seconds.
9. Each input point shall have a corresponding LED on the board that
indicates the state of the point.
10. It shall be possible via the system software to link any input or relay on the
Two-Reader board to cause an action on any other relay in the system and
to select the action that the linked relay will take when the triggering input
or relay is activated.
11. When using the two readers on the same door, for example, to provide
antipassback capability, it shall be possible to assign a single input point
on the board as the door-position point shunted by either reader connected
to the board. It shall also be possible to assign a single relay on the board
as the door-lock relay controlled by either reader.
12. The Two-Reader board shall also include six (6) Form-C, non-inductive
contact relays with ratings of 5A at 28 VDC for optional use in controlling
door locks, alarm signals or other devices. Control of the relays shall be
software-assignable to be triggered by a reading device, cardholder, time
zone and/or other system actions. The relays shall be configurable for
normal (relay energized when “on”) or inverted (relay de-energized when
“on”) action. Pulse time of a relay used as a door-lock relay shall be
software-selectable between 1 and 255 seconds.
13. It shall also be possible to define the response desired for each relay when
communications go offline between the Two-Reader board and the
controller: The relay shall be active, the relay shall be inactive, or the relay
shall maintain its status at the moment communications are lost. Each relay
shall have a corresponding LED on the board that indicates when the relay
is energized.
14. The Two-Reader board shall also provide two digital inputs for optional use
to indicate tamper and power fault status.
15. It shall be possible via the system software to link any relay on the Two-
Reader board to cause an action on any other relay on the same board or
on any other board wired to the same controller and to select the action
that the linked relay will take when the triggering relay is activated.
16. The Two-Reader board shall accept 12 VDC for power. It shall be possible
to select the input voltage to be passed through the board to the reader,
with a maximum of 125mA available per reader port. The power selection
shall be made via a jumper on the board and shall apply to both reader
ports.
17. The Two-Reader board shall have a dedicated input point for optional
connection to an enclosure tamper switch and another dedicated input
point for optional connection to a power-loss monitoring device. Systems
requiring use of one of the available input points on the Two-Reader board
for this monitoring shall be unacceptable.
C. Input Board
2. The Input Board shall also include two (2) Form-C contact relays for
optional use in controlling door strikes or other devices. Control of the
relays shall be software-assignable to be triggered by system actions.
Pulse time of the relays shall be software-selectable between 1 and 255
seconds, inclusive.
3. It shall be possible via the system software to link any input or relay on the
Input Board to cause an action on any other relay in the system and to
select the action that a linked relay will take when the triggering input or
relay is activated.
6. Each input board shall be uniquely addressable by the user through the
settings of a dual in-line package (DIP) switch on the board. In addition,
this DIP switch shall be used to select the baud rate of communication with
the controller.
9. The Input Board shall have a dedicated input point for optional connection
to an enclosure tamper switch and another dedicated input point for
optional connection to a power-loss monitoring device. Systems requiring
use of one of the available input points on the Input Board for this
monitoring shall be unacceptable.
D. Output Board
3. It shall be possible via the system software to link any relay on the Output
Board to cause an action on any other relay in the system and to select the
action that a linked relay will take when the triggering input or relay is
activated.
6. Each Output Board shall be uniquely addressable by the user through the
settings of a dual in-line package (DIP) switch on the board. In addition,
this DIP switch shall be used to select the baud rate of communication with
the controller.
9. The Output Board shall have a dedicated input point for optional connection
to an enclosure tamper switch and another dedicated input point for
optional connection to a power-loss monitoring device. Systems requiring
use of one of the available input points on the Output Board for this
monitoring shall be unacceptable.
10. Provision to set end-of-line (EOL) resistance for the board itself shall be
built into the board should this resistance be needed.
2. The communications interface for the primary port on the board shall be
jumper-selectable as RS-232 or RS-485. It shall be possible to connect the
eight-channel MUX board between an IP or Two-Reader controller and
“downstream” I/O boards.
5. Turn around delay (the time a device must wait before it can begin a new
transmission) shall be user-configurable by DIP switches.
7. The eight-channel MUX board shall accept 12 VDC ± 15% at 250 mA for
power.
F. Power Supply
1. 12 VDC Power
b. Power supply shall be rated for use in low voltage, Class 2 circuits.
c. Input:
d. Output:
e. Battery backup:
2. 24 VDC Power
b. Power supply shall be rated for use in low voltage, Class 2 circuits.
c. Input:
d. Output:
1) 24 VDC output
e. Battery backup:
G. Surge Protection
a. Card reader
b. Electrified lock
2. Contractor shall coordinate, furnish and install all required electrified door
hardware and associated power supplies. Contractor shall complete all
required connections and terminations for intended operation, and shall
interface this equipment with the ACS.
I. Card Reader
2. The readers shall operate at 13.56 MHz at 13.56 MHz and 125 KHz in the
same reader device, and shall operate across a voltage range of 5 VDC to
16 VDC. The readers shall be manufactured with at least 10.5% of recycled
content.
4. The readers shall provide an operating reading distance from .5 inches (1.3
centimeters) to 3.5 inches (8.6 centimeters) depending on reader model
and credential used.
5. Card reader shall be the appropriate model for the associated door
application and configuration, or as required by SCRRA.
6. Card Reader: HID multiCLASS SE models RP10, RP15, RP30, RP40 (no
substitutions)
1. Low voltage cable and wire shall be furnished and installed as required
2. Cable and wire shall be selected, sized and used as appropriate for the
device application in accordance with the device manufacturer’s
specifications, power requirements, and length of cable/wire run
a. Belden
d. General Cable
1. The standard proximity access card used by SCRRA is HID model 1386-
LGGMN ISOProx II. No exceptions.
L. Card Printer
1. The standard proximity access card printer used by SCRRA is HID model
Fargo DTC4500e, single-sided card printer with Ethernet. No exceptions.
2. Printer Cartridge
PART 3 - EXECUTION
3.01 INSTALLATION
A. Provide, install and make fully operational all components required for a fully
functional system.
E. Coordinate work with SCRRA, existing conditions and applicable trades to verify
exact routing of cable, wires, conduits, raceways, etc. prior to installation. Verify
final location and mounting height of all equipment with SCRRA prior to installation.
F. Contractor shall use existing conduit and surface raceway where possible and
practicable. All work shall be concealed using existing facility infrastructure
throughout project site. If concealment is impossible or impractical, SCRRA shall
be notified before starting that part of the work.
G. Where required, Contractor shall be responsible for cutting, patching, coring and
associated work for the system at no additional cost to SCRRA.
H. All conduit and sleeve openings used for the installation of the ACS shall be
waterproofed or fireproofed in compliance with State and Local Building and Fire
Codes.
I. All building conduits and sleeves installed or used for the installation of ACS shall
be fire stopped, or re-fire stopped, upon cable placement through such pathways.
J. Contractor shall patch all openings remaining around and inside all conduit,
sleeves and cable penetrations devices to maintain integrity of any fire rated wall,
floor, ceiling, etc.
K. All cables and patch cables shall have a label attached at both ends. All equipment
components shall have a label specifying pertinent information and shall be clearly
visible on the exterior of equipment. Contractor shall confirm specific labeling
requirements with SCRRA prior to cable installation or termination, and equipment
installation.
N. All electrical work shall be done in accordance with Division 26 of the SCRRA
Standard Specifications.
A. Contractor shall assist SCRRA with implementing all new ACS equipment into the
current SCRRA access control management system deployed agency-wide.
3.03 TESTING
c. Valid request-to-exit
f. Door shunt
g. Local alarm
C. Upon successful completion of tests, Contractor shall submit test results in a formal
report. The report shall include the following information (at a minimum):
4. Test description
5. Results of test
D. Certify that all new ACS equipment has been tested and is ready for
commissioning.
3.04 COMMISSIONING
B. The Contractor shall be Manufacturer certified and solely responsible for providing
all test and commissioning equipment, tools, software, programming,
programming support and incidentals and qualified technicians to start–up,
calibrate, debug and verify proper function of the systems and subsystems.
4.01 MEASUREMENT
A. Access Control System (ACS) will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
A. Access Control System (ACS) furnished and completed in accordance with the
Contract Documents will be paid for as at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall be full compensation for
furnishing all labor, materials, tools, equipment, supplies, supervision and
incidentals necessary for the ACS, and doing all work, as shown on the Plans, and
as specified in these Specifications, and as directed by the Engineer.
END OF SECTION 28 13 00
PART 1 - GENERAL
1.01 SUMMARY
A. This section describes the general requirements for Video Surveillance System
(VSS) equipment. The VSS to be installed at stations and various SCRRA facilities
shall consist of the following major equipment:
5. Power supplies
C. All network video products proposed shall conform to ONVIF (Open Network Video
Interface Forum) Profile S.
D. The standard VSS cameras to be installed throughout stations and various SCRRA
facilities will communicate with the localized NVR via Internet Protocol (IP) over a
dedicated VSS LAN.
E. The installation of VSS cameras and related equipment shall include the use of
Pan-Tilt-Zoom (PTZ), 180-dgree and 360-degree color cameras only. Fixed
cameras require SCRRA approval for use prior to installation.
1.03 DEFINITIONS
Abbreviation Description
CAT-6 Category 6
CIS Customer Information System
EIA Energy Information Administration
EIS Electronic Image Stabilization
FOPP Fiber Optic Patch Panel
FOV Field of View
GB Gigabyte
Gbps Gigabits per Second
GHz Gigahertz
HD High Definition
HDD Hard Disk Drive
HDTV High Definition Television
Hz Hertz
IEEE Institute of Electrical and Electronics Engineers
IP Internet Protocol
JPEG Joint Photographic Experts Group
KVM Keyboard-Video-Mouse
LAN Local Area Network
LCD Liquid Crystal Display
Mbps Megabits per Second
MIMO Multiple-Input and Multiple-Output
MMFO Multimode Fiber Optic
MP Megapixel
1.04 SUBMITTALS
A. Product Data: For each type of product indicated. Include dimensions and data on
features, performance, electrical characteristics, ratings and finishes.
B. Shop Drawings: For video surveillance. Include plans, elevations, sections, details
and attachments to other work.
3. The Contractor shall serve as the single point of responsibility for the work
described in this section.
B. Drawings and layouts will depict the location of VSS equipment throughout the
project site. Block and wiring diagrams shall show how VSS equipment should be
interconnected. Information provided by the Authority may be general or
conceptual, and may require the Contractor to undertake system design and
functionality prior to installation.
C. All cameras in the VSS shall use TCP/IP protocol and be of the IP/network type.
All cameras shall operate via PoE. Any existing analog cameras shall be removed,
replaced with an IP/network camera, or connected to a video encoder for analog
to digital signal conversion per SCRRA approval.
E. All video captured by the IP/Network cameras shall be recorded by the NVR. Per
California Government Code Section 34090.8, recorded images shall be stored for
at least one (1) year or 365 days prior to being written over.
F. Audit Trail: The VSS shall provide an audit trail of the recorded video to enable
verification that the video has not been altered from date and time of recording.
Video recordings must have the capability to be exported into a desirable media
format that can easily be viewed using a standard PC with standard codec/media
installed (e.g. Windows Media Player).
G. Other than the IP/network camera, all supporting VSS equipment shall be housed
in a temperature controlled telecommunications room (e.g. station
communications shelter, data center, server room, etc.), weatherproof enclosure,
or air conditioned equipment cabinet (for locations without an existing
telecommunications room).
H. All equipment in the VSS shall have surge protection and be connected to a UPS
when available.
PART 2 - PRODUCTS
2.01 GENERAL
A. Unless otherwise specified, products for the VSS shall be consistent with and
compatible with the established standards for SCRRA VSS.
C. When applicable, all products proposed for the VSS shall conform to ‘Buy America’
provisions.
E. All cameras shall be network (IP) cameras and will connect to an Ethernet switch
as indicated in the Contract Documents.
F. SCRRA VSS camera types include the following: PTZ, 180-degree and 360-
degree. Fixed cameras require SCRRA approval prior to installation.
H. All cameras shall have PoE functionality. PoE power for cameras shall originate
from an IEEE 802.3at compliant, backwards compatible, PoE network switch or
PoE mid-span injector.
I. All cameras shall have PoE surge protection. PoE surge protection shall typically
be placed between the PoE network switch/mid-span injector and PoE network
camera.
J. All cameras and VSS network cabling shall use outdoor-rated or plenum-rated
CAT-6 UTP cable for signal transport, terminated with RJ45 connectors. Cable
jacket color shall be white. Camera power and video signal shall be transported on
the same cable.
K. PoE extenders can be used to extend a PoE connection beyond the 328 ft. (100
m) distance limitation. Up to one (1) PoE extender can be used to extend the PoE
connection another 328 ft. (100 m), for a total cable length (from switch to camera)
of 656 ft. (200 m).
L. Unless otherwise specified, all CAT-6 network cabling shall be installed from each
camera back to a telecommunications room (e.g. station communications shelter,
data center, server room, etc.), weatherproof enclosure, or air conditioned
equipment cabinet (for locations without an existing telecommunications room).
M. For camera locations which cannot be supported by long distance PoE network
connectivity, fiber optic cable and wireless Ethernet radio systems can be used as
an alternative for camera data signal transport within the VSS LAN. These
locations will be considered as “remote” camera locations within the VSS LAN.
Use of these communication mediums requires SCRRA approval prior to
installation.
N. Use of a NAS is permitted to fulfill the one (1) year or 365 days recorded image
retention requirements per California Government Code Section 34090.8
O. All VSS equipment at the telecommunications room requiring building power shall
connect to a UPS, dedicated to the VSS only.
a. Pole mount
b. Wall mount
c. Corner mount
d. Parapet mount
e. Pendent mount
3. Minimum Illumination:
b. Motion JPEG
6. Frame Rate: no less than 30 frames per second for all required Digital
Video Compression methods and Video Resolutions.
9. Pan Movement:
a. 220°, minimum
a. 30x optical zoom and 12x digital zoom for a total of 360x zoom,
minimum
13. Camera shall be equipped with environmental housing suited for outdoor
weather conditions and equipped with sunshield, fan and heater.
b. Motion JPEG
6. Frame Rate: no less than 30 frames per second for all required Digital
Video Compression methods and Video Resolutions.
9. Pan Movement:
a. 90°, minimum
a. Pole mount
e. Corner mount
f. Parapet mount
g. Pendent mount
3. Minimum Illumination:
b. Motion JPEG
6. Frame Rate: no less than 12 frames per second with power line frequency
(50/60 Hz) for all required Digital Video Compression methods and Video
Resolutions.
11. Camera shall be equipped with environmental housing suited for outdoor
weather conditions and equipped with sunshield, fan and heater.
a. Pole mount
f. Corner mount
g. Parapet mount
h. Pendent mount
3. Minimum Illumination:
b. Motion JPEG
6. Frame Rate: no less than 30 frames per second with power line frequency
(50/60 Hz) for all required Digital Video Compression methods and Video
Resolutions.
8. Digital PTZ
10. Camera Angle Adjustment: Pan ±180°, tilt -5 to +75°, rotation ±95°
12. Camera shall be equipped with environmental housing suited for outdoor
weather conditions and equipped with sunshield, fan and heater.
a. Pole mount
b. Wall mount
c. Corner mount
d. Ceiling mount
3. Minimum Illumination:
b. Motion JPEG
8. Digital PTZ
11. Camera shall be equipped with environmental housing suited for outdoor
weather conditions and equipped with sunshield, fan and heater.
a. Pole mount
b. Wall mount
c. Corner mount
d. Ceiling mount
b. Motion JPEG
10. Camera shall be equipped with environmental housing suited for outdoor
weather conditions.
B. Allows a minimum of 20 camera connections at the same time for live-viewing and
recording via 1Gbps Ethernet port with included camera license, and can be
extended to allow additional camera connections by adopting an “additional
camera license” that can be purchased separately.
C. A second, or additional, 1 Gbps Ethernet port for video distribution to client PCs.
D. General:
E. Recorder Hardware:
1. H.264
3. MPEG-4
G. Storage Components:
I. Playback Function:
1. Normal playback
2. Slow playback
3. Fast playback
5. Frame-by-frame playback
1. Time/data search
2. Alarm search
L. Electrical:
M. Environmental:
N. Mechanical:
1. One (1) – 1 Gbps dual network interface card with RJ45 ports (auto
negotiation)
B. NVR shall be built to operate reliably in harsh usage environments and conditions
such as strong vibrations, extreme temperatures and dusty conditions.
C. NVR shall employ a compact, hardened, fully fanless and ventless chassis design
for protection against dirt dust, tampering, strong vibrations and extreme
temperatures.
D. NVR shall allow a minimum of 25 camera connections at the same time for live-
viewing and recording via 1Gbps Ethernet port.
E. NVR shall include a second 1Gbps Ethernet port for video distribution to client
PCs.
F. General:
G. Recorder Hardware:
1. H.264
3. MPEG-4
I. Storage Components:
1. SSD only
K. Playback Function:
1. Normal playback
2. Slow playback
3. Fast playback
5. Frame-by-frame playback
1. Time/data search
2. Alarm search
N. Electrical:
O. Environmental:
P. Mechanical:
7. Two (2) – Audio jack: One (1) line-in, One (1) mic-out (minimum)
B. Memory:
D. Internal Drive:
1. Minimum of four (4) hard drive bays that can support 3.5” or 2.5” SATA
6Gb/s HDDs
G. Ports:
H. Electrical:
2. The maximum length for a cable segment is 328 feet (100 meters). If longer
runs are required, the use of active hardware (e.g. extender, repeater,
switch) is required.
2. Contractor shall use EZ-RJ style connectors with strain relief (p/n: PLAT-
202015J or equivalent).
4. All new conduit shall be free from defects, including non-circularity, foreign
inclusions, etc. It shall be uniform in color, density and physical properties.
It shall be straight and the ends shall be cut square to the inside diameter.
5. All new conduit shall display the Underwriters Laboratory certification (UL
Listed).
A. PoE Midspan:
1. For cameras requiring IEEE 802.3af or IEEE 802.3at PoE power, furnish
and install new rack-mount PoE midspan power injectors in equipment
racks, as required. Camera manufacturer provided single-port PoE
midspan power injector can be used in lieu of rack-mount injector per
SCRRA approval. Contractor responsible for mounting configuration of
single-port PoE midspan power injector in telecommunications room.
2. Port Configuration: no less than eight (8) ports of IEEE 802.3af and IEEE
802.3at compliant PoE for 10/100/1000 Base-T networks
B. PoE Extender:
1. Furnish and install new PoE extenders, as required. Up to one (1) PoE
extender can be used to extend a PoE connection another 328 ft. (100 m),
for a total cable length (from switch to camera) of 656 ft. (200 m).
2. Environmental:
4. PoE Standards: IEEE 802.3af, IEEE 802.3at and custom PoE up to 60W
1. Furnish and install new PoE surge protectors, as required. PoE surge
protectors can be rack mount (for multiple ports) or surface mount (for
single port).
c. PoE Standards: IEEE 802.3af, IEEE 802.3at and high wattage PoE
Plus
c. PoE Standards: IEEE 802.3af, IEEE 802.3at and high wattage PoE
Plus
f. Housing: ABS
5. Other requirements shall include; flow control, full duplex, and layer 3
switching, auto-sensing per device and VLAN support.
1. The 7-port PoE switch shall be a PoE PSE (Power Sourcing Equipment)
that powers remote PoE cameras.
4. The 7-port PoE switch shall have five (5) 10/100Tx RJ45 ports.
5. The 7-port PoE switch shall include two (2) 100/1000 SFP slots.
7. The switch shall have four (4) RJ45 ports that support 802.3at PoE+.
9. Electrical:
1. General:
a. Rack-mountable
c. Laptop style keyboard and touch pad style mouse with PS/2 and
USB connections available
2. Display:
3. Environmental:
5. KVM cable assembly shall be from the same manufacturer as the KVM
rack console provided. Contractor to verify that manufacturer provided
cable matches KVM port configuration of NVR. If not, contractor to furnish
and install new KVM cable assembly to match KVM port configuration of
NVR. Consult manufacturer for cable assembly selection type.
1. The UPS shall be rack mountable. The UPS shall provide temporary
electrical backup for PoE cameras, servers and switches associated with
the VSS.
b. Input: 120V
c. Output: 240V
a. Output: 48V
C. Equipment Rack
2. Floor Mounted:
3. Wall Mounted:
e. Rack shall feature a locking swing open center section for front and
rear access.
A. Mounting Options:
1. Pole mount
2. Wall mount
C. The cases shall have quick release latches with padlock hasps.
E. The weatherproof enclosure shall include mounting plate, duplex 120 VAC outlet
and thermostat controlled cooling system.
F. The weatherproof enclosure shall have one (1) ½-inch conduit connector for power
and two (2) 1-inch conduit connectors for data/signal.
G. The weatherproof enclosure exterior dimensions shall not exceed: 19.5-in. x 17.5-
in. x 10-in.
A. Outdoor air conditioned equipment cabinet shall consist of the cabinet assembly,
rack-mounted air conditioner, cabinet foundation and all materials, components,
appropriate connectors, tools, equipment and incidentals necessary for a fully-
functional air conditioned equipment cabinet.
B. Cabinet shall meet the requirements of the model 334 traffic controller cabinet
standard used by the State of California Department of Transportation (Caltrans).
F. Cabinet shall have two full size (2) doors for access: one (1) for front and one (1)
for rear of cabinet. Both doors shall be louvered for air conditioning ventilation and
include door stops.
G. Cabinet door handles shall be stainless steel, ¾-in round, with provisions for a
padlock.
H. Cabinet shall include an electrical service panel assembly, and a minimum of one
(1) 30-amp circuit breaker and one (1) 20-amp NEMA 5-20 receptacle.
6. Thermostatically controlled
A. See Section 26 12 00 - Conductors and Cables - Low Voltage, for fiber optic cable
requirements.
2. For remote camera locations, fiber optic cable shall be terminated onto a
FOPP that shall include a single-panel connector housing, brackets,
connectors and splice trays as specified and as shown on the Contract
Documents. FOPP must be securely mounted inside weatherproof
enclosure and must fit inside enclosure with other applicable VSS
equipment and components.
A. The wireless Ethernet radio system shall consist of all materials, components,
appropriate connectors, tools, equipment and incidentals necessary to establish a
wireless link to camera locations (beyond PoE distance limits) within the VSS LAN.
B. The wireless Ethernet radio system shall meet the minimum requirements:
8. VOIP and PTZ control traffic prioritized over other traffic (for better latency)
A. The pole mounted solar power supply system shall consist of all materials,
components, appropriate connectors, tools, equipment and incidentals necessary
to establish an “off-grid” power source to camera locations.
C. Pole mounted solar power supply system shall be side-pole mounted unless
otherwise specified.
D. The pole mounted solar power supply system shall generally consist of the
following components:
3. Battery bank
E. The pole mounted solar power system shall meet the minimum requirements:
1. Solar Panel:
a. Provide 12VDC
2. Weatherproof Enclosure:
d. Support 12VDC
PART 3 - EXECUTION
3.01 INSTALLATION
D. Cameras shall be located so that their Field of View (FOV) is not restricted by other
station installations such as walls, ceilings, columns, signs, and luminaries. Plans
demonstrating the unobstructed FOV of each camera shall be submitted for
SCRRA review.
E. Cameras shall be located so that they never directly view the sun. The FOV of
cameras shall be adequately illuminated either by natural light or by luminaries.
Within the FOV, particular care shall be taken to avoid extremes of light and
shadow.
H. Pole Mounts used for outside cameras shall use custom mounts. Coordination with
architect and SCRRA for style and color may be required. All parts shall be
protected from corrosion, including insulation against dissimilar metals.
I. Contractor shall use existing conduit and surface raceway where possible and
practicable. All work shall be concealed using existing facility infrastructure
throughout project site. If concealment is impossible or impractical, SCRRA shall
be notified before starting that part of the work.
J. Where required, Contractor shall be responsible for cutting, patching, coring and
associated work for the system at no additional cost to the Owner.
K. Provide easy, safe, and mandated clearances at equipment racks and enclosures,
and other equipment requiring maintenance and operation. All telecommunications
room equipment racks shall be mounted a minimum of 36-inches from the wall or
other cabinets, equipment or power panels. SCRRA to review and approve all
equipment mounting locations and configurations inside telecommunications room
prior to installation.
L. All cables and patch cables shall have a label attached at both ends. All equipment
components shall have a label specifying pertinent information and shall be clearly
visible on the exterior of equipment. Contractor shall confirm specific labeling
requirements with SCRRA prior to cable installation or termination, and equipment
installation.
M. For remote camera locations requiring electrical power, splice into existing power
circuit wherever possible. Splice points to occur in the nearest pull box at each
remote camera location. Consult with existing power circuit owner prior to splicing.
Splices into existing CIS power circuit require SCRRA approval.
3.02 TESTING
A. Factory and field testing shall be performed in accordance with SCRRA Standard
Specification 01 91 13 - General Commissioning Requirements.
B. Factory Tests: Perform factory test of each camera type to demonstrate correct
operation as defined in these Specifications.
C. Field Tests: Perform cable tests as indicated in the approved test plan. Furnish all
equipment, appliances, and labor necessary to test the installed cable mediums
throughout the VSS.
2. Perform continuity test on fiber cables. Fiber cables need to be tested three
(3) times:
c. The final continuity test shall be a complete end to end test using
LED sources and documenting each fiber cables result.
3. Perform all continuity testing after final termination (except fiber cable) and
cable installation, but prior to connection of any electronics or field devices.
4. Replace any cable that fails to meet the parameters, or if any testing
reveals defects in the cable. Retest new cable as specified above.
D. Perform the following local field operations tests on site in accordance with an
SCRRA approved field test plan. Demonstrate the following after the camera
controller assemblies, other camera hardware, power supplies and connecting
cabling have been installed:
3.03 COMMISSIONING
B. The Contractor shall be Manufacturer certified and solely responsible for providing
all test and commissioning equipment, tools, software, programming,
programming support and incidentals and qualified technicians to start–up,
calibrate, debug and verify proper function of the systems and subsystems as
required by the Commissioning Plan.
4.01 MEASUREMENT
A. Video Surveillance System (VSS) will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
END OF SECTION 28 23 00
PART 1 - GENERAL
1.01 DESCRIPTION
A. The Customer Information System (CIS) will include: PA, LED message signs,
Personal Computer (PC), Liquid Crystal Display (LCD) Monitor(s), Strobe lights on
each LED message sign, power supplies, cables, wires, connectors,
miscellaneous equipment such as mounting posts, brackets, enclosures, media
converters, and switches. The CIS will interface with the SCRRA network through
Multiprotocol Label Switching (MPLS) router.
C. This SOW includes Work to be performed by the Contractor. The Work includes
furnishing, installing, testing and upgrading the PA/CMS system on existing
stations to CIS and installing CIS on the new stations. The Work shall be performed
as specified in this document and in the station specific Specifications, materials
list, and Plans. A general summary of the SOW is included in this section, with
details included in Section 29 20 20, Communications Services. This document
and accompanying materials form the Standard Plans, Standard Materials List,
and Standard Specifications.
1. The Contractor shall provide final Shop Drawings and shall submit them to
SCRRA for review and Approval. The Plans shall include all details of
equipment installation, wiring, cabling, equipment interconnection, and
rack mounting of equipment, materials list, and cut sheets of the equipment
to be installed. Upon review, SCRRA may Approve, Conditionally Approve,
or may Disapprove the Plans. If Conditionally Approved or Disapproved,
the Contractor shall correct the deficiencies within a reasonable time and
shall submit the Plans to SCRRA for final Approval.
2. Upon Approval of final Shop Drawings the Contractor shall seek Approval
from SCRRA for equipment procurement in writing. The SCRRA may
request different equipment or Approved equal from those listed in the
materials list prior to ordering the equipment. Upon Approval from the
SCRRA, for equipment procurement the Contractor shall develop final
Shop Drawings which shall include but shall not be limited to wiring
diagrams, equipment assembly and installation, cable routing, and all
equipment interfaces including rack layout. The Contractor shall submit
these Plans to SCRRA for review and Approval prior to installing any
equipment. All comments by SCRRA on the previous revisions and the
preliminary Plans shall be resolved in the final shop drawings. Upon review,
SCRRA may Approve, Conditionally Approve, or Disapprove the Plans. If
Conditionally Approved or Disapproved, the Contractor shall correct any
deficiencies until the Plans are Approved. Only after Approval of Plans and
Approval from SCRRA to procure equipment the Contractor shall proceed
to procure the necessary equipment. The Contractor shall seek Approval
from SCRRA to install the indicated equipment. Upon completion of
installation the Contractor shall seek Approval from SCRRA to test all
equipment specified in this SOW. Installation shall comply with these
Standard Specifications, associated Standard Plans, and Standard
Materials List. The Contractor shall also comply with all other SCRRA
documents such as site-specific Station CIS Installation Design, Design
Criteria, Communications and Signaling Design, and other Standard Plans.
The Contractor shall provide all equipment and labor for this Work with no
additional cost to SCRRA. At any stage, if the Plans, installations, or test
process or test results are disapproved by SCRRA, the Contractor shall
correct all deficiencies within reasonable time at no additional cost to
SCRRA and if necessary re-install the equipment. If necessary, the
Contractor shall re-test the equipment. These activities shall be completed
with no additional cost to SCRRA
3. CIS shall include, but not limited to: ethernet switch, rack mounted media
converters, rack mounted fiber patch panel, amplifier(s), audio decoder,
priority controller, Emergency Management Panel (EMP), LED message
signs, strobe lights, cables, and connectors. 42-inch LCD monitor(s) with
an embedded Network Media Player (NMP) shall be also installed in
area(s) indicated on the Plans to display train schedule.
4. As indicated in this document and the Plans, the Contractor shall use the
existing cables where appropriate or pull additional cables as required,
remove existing equipment as indicated herein and install the new
equipment. If the Contractor proposes any change including but not limited
to change in equipment; installing additional equipment; adding conduits,
pull boxes, junction boxes, the Contractor shall submit a change request in
writing to SCRRA. The change request shall include the following as a
minimum:
D. The Contractor shall not proceed with any changes without written Approval by
SCRRA.
PART 2 - PRODUCTS
2.01 MATERIALS
A. SCRRA will provide a Materials List of equipment to the Contractor for major CIS
equipment. Based on the Materials List the Contractor shall procure equipment in
quantities identified. The Materials List may vary from station to station. The
Contractor shall furnish, install, and test all miscellaneous material that is required
for a complete and functional system.
2.02 SCHEDULE
A. As part of this Contract, the Contractor shall submit a schedule to SCRRA for
review and Approval. This schedule shall include details including developing
Plans, procurement of equipment, site preparation, installation, and testing. The
Contractor shall update this schedule every two weeks and shall submit it to
SCRRA for review and Approval. The schedule shall be in bar chart or Gantt chart
format and shall also show planned activities for next two weeks.
PART 3 - EXECUTION
A. Upon Authorization, the Contractor shall install all equipment per requirements in
this Specifications and Plans and per the Contractor developed Plans. The
Contractor shall seamlessly interface the new equipment with the existing
equipment to deliver a fully functional system.
C. Upon completing the installation, the Contractor shall test all equipment and verify
that the equipment functions as intended.
D. All equipment and installations shall meet the Los Angeles region zone 4
earthquake requirements.
4.01 MEASUREMENT
A. Customer Information System (CIS) will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
D. All material, work, and services for Conductors and Cables for communications
system is considered incidental to work associated with project item in Section 26
12 00, Conductors and Cables – Low Voltage and no separate measurement and
payment will be made to the Contractor for Work of this Section.
E. All material, work, and services for Conduits, Raceways, and Boxes for
communications system is considered incidental to work associated with project
item in Section 26 13 00, Conduits, Raceways, and Boxes and no separate
measurement and payment will be made to the Contractor for Work of this Section.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 29 00 00
PART 1 - GENERAL
1.01 SUMMARY
A. This section defines the standards, abbreviations, and definitions used throughout
these CIS specifications.
B. The Contractor shall use the most current versions of standards, codes,
regulations at the time of contract award. The Contractor shall comply with all
applicable standards, codes, and regulatory requirements even if those standards,
codes, and regulations are not specifically identified herein.
1.02 REFERENCES
Agency Standard Description
ASTM A53 Standard Specifications for Pipe, Steel, Black and Hot Dipped,
ASTM
Zinc Coated, Welded and Seamless
CIS Customer information system
DOT Americans with Disabilities Act (ADA) Requirements
EIA-232 Interface Between Data Terminal Equipment and Data Circuit-
EIA
Terminating Equipment Employing Serial Binary Data Interchange
EIA EIA-310 Racks, Panels, and Associated Equipment
EIA-485 Standard for Electrical Characteristics of Generators and
EIA
Receivers for Use in Balanced Digital Multipoint Systems
EIA/TIA-530-A High Speed 25-Position Interface for Data Terminal
EIA Equipment and Data Circuit-Terminating Equipment, Including Alternative
26-Position Connector
EIA/TIA EIA/TIA-568 Commercial Buildings Telecommunications Wiring Standard
EIA/TIA-569 Commercial Building Standard for Telecommunications
EIA/TIA
Pathways and Spaces
EIA/TIA-606 Administration Standard for the Telecommunications
EIA/TIA
Infrastructure of Commercial Buildings
EIA/TIA-607 Commercial Building Grounding and Bonding Requirements
EIA/TIA
for Telecommunications
FCC FCC Class A Part 15 Emissions Requirements
IEEE 42 Practice for Grounding of Industrial and Commercial Power
IEEE
Systems (IEEE Green Book)
1.03 ABBREVIATIONS
Abbreviation Description
A Amperes
AC Alternating Current
ADA Americans with Disabilities Act
A-D/D-A Analog to Digital/Digital to Analog
ANS Ambient Noise Sensor
BNC Bayonet Neill-Concelman
BTU British Thermal Units
C&S Communications and Signaling
CMS Changeable Message Sign
CIS Customer Information System
CVBS Composite Video Baseband Signal
EMP Emergency Management Panel
FO Fiber Optic
FOPP Fiber Optic Patch Panel
GRS Galvanized Rigid Steel
Hz Hertz
HDMI High Definition Multimedia Interface
IC Interface Converter
I/O Input/Output
LCD Liquid Crystal Display
LED Light Emitting Diode
MC Media Converter
MCI Building SCRRA Headquarters in Downtown Los Angeles
MOC Metrolink Operations Center
MPLS Multi Protocol Label Switching
NMP Network Media Player
NTCIP National Transportation Communications for ITS Protocol
PA Public Address
PC Personal Computer
PIP Picture-in-Picture
SCRRA Southern California Regional Rail Authority
SFP Small Form Factor Pluggable
Abbreviation Description
SOW Statement Of Work
TCIP Transit Communications Interface Profile
TFT Thin Film Transistor
THD Total Harmonic Distortion
UL Underwriters Laboratories
UPS Uninterruptible Power Supply
USB Universal Serial Bus
V Volts
VGA Video Graphics Array
VLAN Virtual Local Area Network
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 29 00 20
PART 1 - GENERAL
1.01 SUMMARY
A. This section identifies the requirements for testing and commissioning the power
distribution to all the installed equipment. Power to the following equipment shall
be tested for both existing and new stations:
1. Ethernet switch
2. Amplifiers
4. Audio Decoder
5. Interface converters
6. Media converters
8. LCD monitor(s)
PART 2 - PRODUCTS
PART 3 - EXECUTION
A. The Contractor shall develop a test procedure and shall submit it for SCRRA’s
review and Approval. SCRRA may Approve, Conditionally Approve, or Disapprove
the procedure and shall provide appropriate comments. If Conditionally Approved,
the Contractor shall correct the deficiencies prior to testing at no additional cost to
SCRRA. If Disapproved the Contractor shall correct the deficiencies and resubmit
the procedure to SCRRA for Approval at no additional cost to SCRRA. The
procedure shall include the following as a minimum:
1. Test objective.
2. List of equipment required to setup and conduct the test and calibration
dates, calibration due dates. With proof of certifications.
3. Support needed from SCRRA for site access and access to SCRRA’s
locked communications shelters and cabinets.
5. Provisions for recording test results and test data forms to record test
results.
B. The Contractor shall obtain Approval for testing and shall test all enclosures,
conduits, raceways, exposed expansion joints, for continuity to the ground. The
test results shall be submitted to SCRRA for review and Approval.
C. The Contractor shall obtain Approval for testing, test, and record ground resistance
of all grounded equipment and shall ensure that they are adequately grounded.
The test results shall be submitted to SCRRA for review and Approval.
D. The Contractor shall obtain Approval for testing, test and verify insulation
resistance. The test results shall be submitted to SCRRA for review and Approval.
E. The Contractor shall give at least two weeks notice to SCRRA prior to the testing
date. SCRRA at its discretion may witness any tests or may not witness the tests.
The test results shall be signed by the person or persons conducting the test,
engineering manager, and quality control staff of the Contractor. The Contractor
shall submit four (4) copies and an original of the test results to the SCRRA for
review and Approval.
F. If any of the above tests fail and results are Disapproved by SCRRA, the
Contractor, at no additional expense to SCRRA shall re-test the equipment,
assembly, enclosures, conduits, raceways, expansion joints, and any other
elements as necessary. The Contractor shall ensure that the cause of test failures
is corrected in a reasonable time and that all tests pass.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 29 10 60
COMMUNICATIONS SERVICES
PART 1 - GENERAL
A. This section describes the general requirements for the CIS equipment
procurement and installation. The CIS to be installed in stations shall consist of
the following major equipment:
1. Ethernet Switch.
3. Media converter(s).
6. Power supplies.
1. Fiber optic cables shall be routed from the Communications Shelter based
Ethernet Switch to the message signs via the FOPPs as shown in the
contract plans. Fiber strands shall be dropped at each message sign in a
drop-and-continue topology as shown in contract documents.
2. The LCD monitors shall be installed as shown in contract plans. The LCD
monitors shall be installed at a location convenient for passengers to view
train schedules and it may be mounted on a stand-alone post or may be
mounted on a structure such as a canopy. The Contractor shall submit the
shop plans showing the installation and mounting detail for each LCD
Monitor for Engineer’s approval.
4. The stations shall interface with the SCRRA’s Network with MPLS Router
installed in the station communications shelter/Room.
5. The SCRRA will provide all CIS related software interface between the
SCRRA and Amtrak at the DOC/MOC. The Contractor shall coordinate
with the SCRRA to ensure that proper messages are displayed on the LED
message signs, LCD monitors, and PA system for Amtrak and SCRRA
trains at each station.
PART 2 - PRODUCTS
2.01 MATERIALS
B. The materials list only describes the major equipment. The Contractor shall
procure brackets for mounting LED message signs, brackets and posts for
mounting LCD monitor, wires, cables, connectors and heat shrink fusion splice
protector. If the Contractor chooses to propose equipment other than that identified
above, the Contractor shall submit all cut sheets, data sheets, reports, and other
necessary documentation to SCRRA for review and seek Approval for utilizing the
equipment. Based on the review of documents and discussion with the Contractor,
SCRRA may or may not approve such request. SCRRA shall have the right to
request Approved equivalent of any and all the equipment prior to ordering the
equipment.
1. Category 6 cable and patch cords procured by the Contractor, shall have
attenuation of less than or equivalent to 23.6 dB at 100 MHz; and 39.1 dB
at 250 MHz.
f. Maximum length of the Cat 6 cable shall be 328 feet including all
patch and cross-connect cables.
2. The fiber optic cable and fiber optic patch cords shall be multimode 850 nm
(minimum OM2), supplied by Corning Cable Systems or Approved
equivalent and shall meet or exceed the following minimum Specifications:
3. The Contractor shall get an approval from the Engineer if the conductor
size of the speakers/microphone/2 wire handset/audio cable (s) needs to
be changed due to distance, current, or voltage limitation. The Audio
Connector shall be selected such that they are compatible to the
Equipment port they are connected to.
PART 3 - EXECUTION
A. This section describes the detailed requirements for the PA System. The speakers’
cable continuity test shall be based on audio announcement tests from the DOC,
MOC, and Gateway Building, and the EMP conducted by the Contractor with
AUTHORITY and SCRRA’s oversight. The following describe the requirements for
PA part of the CIS.
6. The Contractor shall interface the ambient noise sensor at each platform
with the priority controller. The contractor shall terminate the existing
ambient noise sensor and handset to the priority controller in the
communication shelter/room as shown on the contract plans. The amplifier
and associated electronics shall adjust the PA output based on the ambient
noise levels. If the ambient noise levels exceed acceptable levels the
System shall delay non-EMP originated announcements until the ambient
noise subsides to acceptable levels.
f. The amplifier shall detect and isolate channel specific faults. Fault
or failure in one channel shall not affect other channels.
i. Durable industrial or transit use with forced air ventilation from the
front to the side panels.
8. Half the speakers on each platform shall be part of a loop known as a zone
1 and remainder of the speakers shall be on the second loop also known
as zone 2 as shown in contract plans. Each platform shall be equipped with
two (2) zones. In case of failure in one loop, the other loop shall function
without interruption. Dual platform stations shall be equipped with four
zones. Triple platform stations shall be equipped with six zones. These
shall be connected to separate outputs from the amplifier(s) and each
alternate speaker shall be connected to one loop. Failure in one loop shall
not cause failure in the other loops.
10. The PA part of the CIS System shall be equipped with priority control. The
System shall be able to detect the input source and shall be able to assign
priority to each input as shown below.
Priority
Input
Level
First From the EMP
From Microphone in AUTHORITY Security
Second
Room
Third From DOC, MOC, and Gateway
Fourth Pre-recorded announcements
11. If a higher level priority message is in progress, and a lower priority level
message attempts to make an announcement, the system shall permit the
high level priority message and shall hold the lower level priority message.
After the completion of the higher level priority message the lower level
priority message shall be permitted to play automatically. If a lower level
priority message is in progress and a message with higher level priority is
transmitted, the lower level priority message shall be interrupted and the
message with the higher priority shall be broadcasted.
A. The Contractor shall procure and install LED message signs and associated
equipment as part of the CIS per requirements in these specifications and Contract
plans. The equipment shall include signs and associated electronics, enclosures,
strobe lights, patch panels, wires, cables, connectors, media/interface converters,
and interfaces with the Communications Shelter/Room. The following describe
requirements for the LED message signs.
B. The Contractor shall install the LED message signs at their original locations and
shall interface them as shown in the contract plans, per LED message sign
manufacturer’s installation guidelines, and per requirements in the specifications.
The LED message signs shall be protected by a 120 VAC, 1P, 20 A circuit breaker.
1. The LED message signs shall be individually IP addressable with fiber optic
interface as shown in the plans and required by Specifications.
2. The LED message signs including the enclosure shall have following
characteristics:
a. Not more than seventeen (17) IN high x fifty five (55) inch wide x
eleven (11) inch deep.
d. Character height shall not be less than three (3) inch and shall have
the ability to display a minimum of four (4) font styles.
4. The signs and their installation shall comply with Section 49 CFR parts 27,
37, and 38; California Building Code, Section 414, and shall comply with
all local jurisdictions.
5. The Contractor shall ensure that all the signs shall be able to accept the
data in XML format and display the messages correctly as intended.
6. The Contractor shall coordinate closely with SCRRA’s staff for proper
message format, letter heights, fonts, message display methods and other
characteristics.
7. Each LED message sign shall have capability to store at least sixty (60)
messages. The signs shall be able to flash, scroll, and roll messages.
Service life of the LEDs shall not be less than 100,000 hours.
9. The LED message sign lens shall be at least 1/8 IN shatterproof, UV coated
polycarbonate with structural aluminum and the enclosures shall be vandal
resistant and tamper-proof.
10. The message sign with the enclosure shall be mounted with the mounting
bracket as shown in the contract plans. Mounting bracket shall be powder
coated to match the sign.
11. The total weight of the LED message sign including the media/interface
converters, enclosures, mounting hardware, sunshield, strobe, and all
associated assembly and equipment shall not be more than 70 LBS.
12. LED message signs shall be hinged at the top of the enclosure to provide
front access for easy maintenance. It shall not be necessary to remove the
sign from the mounted position for either resetting the processor within the
sign and to maintain it.
13. LED message signs shall be equipped with high security tamper proof
fasteners and screws.
15. The signs shall be mounted at a height of twelve (12) FT nominal from the
top of the platform to the bottom of the sign enclosure. Deviations from this
mounting height, based on site specific conditions shall be requested in
writing by the Contractor. The mounting height specified herein shall
remain unless a deviation is approved by SCRRA. The signs shall be
clearly visible and shall not be obstructed by structures or other objects on
the stations.
16. All installations shall meet all the requirements of Americans with
Disabilities Act (ADA).
A. The Contractor shall procure and supply strobe lights with double flash strobe, with
a flash rate of 80 flashes/minute. The strobe shall be powered by 120 VAC, 60
Hz. and shall be equipped with clear dome.
1. The strobes shall be less than nine (9) inch high and less than six (6) inch
in diameter. The strobes shall contain their own strobe power supply in the
base of the light.
2. The strobe flash tube is mounted in an eight (8) pin octal socket base. The
tube shall be able to withstand the weather typically encountered in Los
Angeles region.
4. The Strobe light shall have a minimum life of at least 10,000 hours. The
total weight shall not exceed 3.4 lbs.
5. The Strobe lights shall be interfaced with the LED sign enclosure and shall
function as one single unit. All interfaces to the Strobe light shall be
included within the LED message sign enclosure.
A. The Contractor shall install LCD monitors at each station, near the TVMs, on its
own stand alone stainless steel post or on steel columns inside canopy. The
Contractor shall develop and submit the installation and mounting detail for each
LCD monitor for Engineer’s approval.
B. One 1 IN conduit shall be installed as shown in the plans from the nearest
communications pullbox to the LCD to transmit signals.
C. The Contractor shall follow the power conduit requirements for the LCD Monitors
as indicated in these contract documents.
D. The LCD monitor shall be enclosed in a NEMA 4X compliant enclosure and shall
have the screen visible through a, vandal-resistant, laminated glass. The enclosure
shall be able to house a MC and a NMP which shall be interfaced with the LCD
monitor with HDMI cable.
E. The LCD monitor shall interface with the MPLS switch via 850 nm multimode
(minimum OM2) fiber optic cable as shown in the plans.
F. The LCD monitor, the NMP, MC, and the enclosure shall comply with the following
requirements:
1. The LCD shall be Viewsonic, forty-two (42) inch commercial display, model
CD4220 or approved equivalent. TFT active matrix display with minimum
display area of 36.6 inch horizontal x 20.6 inch vertical. Minimum resolution
shall be 1366 x 768 pixels. The contrast ratio shall be 1500:1 typical.
2. The monitor shall support all viewing angles from 178 degrees horizontal
to 178 degrees vertical. The light source shall have typical life of 50,000
HRS. The aspect ratio shall be 16:9 and the panel shall be coated with
anti-glare coating.
3. The monitor shall accept HDMI, S-video, component, composite, and RCA
type video inputs. The video outputs shall permit images to be displayed
in VGA, BNC, and RCA formats.
6. The monitor shall be equipped with two (2) 10-Watt speakers, an analog
15-pin mini D-sub (VGA), digital HDMI.
7. The monitor shall function on standard 120 VAC, 60 Hz and shall consume
less than 250 Watts, typical.
8. The monitor shall be equipped with the following controls: Power (On/Off),
mute, input, volume control, channel up/down, brightness, contrast,
sharpness, black level, noise reduction, and tint, color, color temperature,
and color control. The monitor shall have PIP capability.
10. The LCD monitor shall be mounted at a height of 8 feet, to the bottom of
LCD enclosure with 20 degrees tilt to the monitor for clear visibility. The
mounting shall avoid glare and reflected light. The final mounting and angle
may differ for each station.
A. As part of this Contract, the Contractor shall supply an enclosure for the LCD
monitor from ITS Enclosures which includes 42 inch universal view station, arm
support assembly, 4 inch drop pipe, T20 outdoor 2000 BTU AC unit, T20
suspension assembly and interior support bracket:
5. Suspension Assembly:
6. Bracket:
8. This list includes only major items. The Contractor shall include all
brackets, assemblies, and additional equipment required to complete the
installation as required either for a post or wall mount installation.
9. At Contractor shall submit the shop plans for Engineer’s approval showing
the installation type at each location based on the best visibility and
available means and methods for installation.
10. The enclosure shall also be able to house the NMP and the media
converter with sufficient room for power strip.
11. The enclosure shall be aluminum body, with painted finish and shall be
water resistant. It shall be equipped with anti-reflective tamper-resistant,
laminated glass window with anti-reflective coating on the glass.
12. The enclosure shall be industrial quality for outdoor LCD installations. It
shall be equipped with locks, 3 or 4 tubular keyed compression latches
located in the rear of the enclosure. The struts, latches, or other
mechanism associated with the enclosure shall not interfere with opening
and closing of the enclosure.
13. The enclosure shall be equipped with a 6-outlet 115VAC, 15 amp power
strip. The front cover shall be easily opened for maintenance and
replacement using gas struts.
14. The enclosure shall also be equipped with slip hinges for cover removal.
The enclosure shall be equipped with a built-in air conditioner and heater
of sufficient capacity to maintain the LCD monitor, up to two NMPs, and up
to two media converters.
15. The enclosure shall meet all the temperature requirements per SCRRA’s
Design Criteria.
B. The display size of the enclosure shall allow space for air circulation near the front
window.
D. The enclosure shall not weigh more than 210 lbs. including the air conditioner and
heater unit.
E. The enclosure shall be installed to face either North or South direction whenever
possible to avoid direct sunlight.
A. This NMP shall be installed within the LCD monitor enclosure. The NMP shall be
interfaced with the monitor as shown in the Plans. The NMP shall meet or exceed
the requirements identified below.
1. The NMP shall be able to interface with a PC with any Windows or Linux
operating system capable of running a web server with a 100 Base-Tx
interface. The NMP shall be network ready and shall include integrated
web browser with Flash plug-in, standalone Flash player, HD player.
2. The NMP shall use IP and shall comply with MPEG4 formats and
Macromedia Flash platform. NMP shall also support the multicast and
unicast digital broadcast applications. The NMP shall be equipped with
multiple video outputs and shall be controllable remotely from a network or
internet connections.
3. The NMP shall be equipped with at least one USB port, at least one HDMI
interface, S-Video/YPbPr interface, CVBS interface, audio interfaces, at
least one RS232 port, at least one Ethernet 10/100 port, and shall function
on 5VDC power.
A. The ANS and priority controller shall be interfaced with the EMP as shown in the
Contract Plans.
B. The ANS and priority controller shall be a stand-alone unit with one rack space. It
shall be capable of providing full functional inputs and outputs with at least 16
analog inputs and outputs configurable by input cards and output cards, without
the need of on-line dedicated computer.
C. Combination of microphone and line inputs shall be provided together with channel
selectable 48 volt phantom power per input. The unit shall be equipped with a
tamper-resistant front panel with no user-adjustable controls. The front panel
LEDs shall provide the monitoring of communications presence, clip and network
status.
F. An RS-232 port shall be provided to allow control of the ANS and priority controller.
The ANS and priority controller shall be supplied with software to aid in system
management. The software shall provide methods of event logging and
diagnostics. The event log shall include failures, warnings and information notices.
Each event shall be stamped with time and date.
B. The media converter shall have the capability of hot-swappable converter cards. It
shall support half and full duplex transparently.
A. The Contractor shall supply a UPS with surge protection and internal battery. Upon
power failure, the battery shall support the LED signs and CIS Equipment in
Communications Shelter/Room. If the internal battery is unable to support the
required time, then the Contractor shall supply external batteries to support the
equipment.
B. The battery shall support one third of the LED message signs on the station for
one (1) HR. Alternatively, the battery shall be able to support all the LED message
signs on the station for at least 20 minutes with all signs functioning. To meet UPS
and Battery requirements, the Contractor may choose to select a UPS and
transient voltage suppression system of a different make and model than those
identified in these Specifications. If the Contractor chooses to identify and install
a different UPS and transient voltage suppression system, the Contractor submit
all data sheets, cut sheets and other information for Engineer’s review and
Approval.
3. The surge protector shall be equipped with Metal Oxide Varistors, dry Form
C contacts for remote status monitoring, LEDs to monitor each phase.
4. The unit shall comply with ANSI IEEE Cat A1, C3, B3/C1, and UL1449 (3rd
Edition) requirements.
5. The UPS shall be rated for the connected load plus a minimum of 25
percent spare capacity but not less than 2000 VA. It shall function on 120
VAC, 60 Hz and shall be rack mountable. It shall be equipped with two
individually controlled load segments, communications bay, and at least
one USB port. It shall include hot swappable batteries.
6. The UPS shall be equipped with graphical LCD with backlight and status
indicating LEDs. It shall be capable of self-test and indicate failures on the
LEDs.
A. The Ethernet switch shall be equipped with 48, RJ-45 connectors for 10Base-T,
100Base-Tx, and 1000Base-T with four (4) shared Small Form-Factor Pluggable
(SFP) slots.
B. The Contractor shall use UTP Category 6 cable for interfaces. The switching
capacity shall be 96 Gbps, nonblocking and shall have at least 256 Virtual Local
Area Networks (VLANs).
C. The Ethernet switch shall be equipped with Built-in web user interface for easy
browser-based configuration.
D. The Ethernet switch shall support port based, 802.1p VLAN priority based, Internet
Protocol (IP) to ToS/DSCP based, and IPv6 traffic-class-based class of services.
E. The Ethernet switch shall comply with all applicable Ethernet standards. It shall
function in the environment encountered in Los Angeles region.
3.11 SPEAKERS
C. Speakers shall be at least one (1) feet above the top of the LED message signs
and shall be installed as specified and as shown in contract documents.
A. The EMP contains ambient noise sensor and telephone set. The priority controller
shall interface with the ambient noise sensor and the telephone set within the
Emergency Management Panel (EMP). The Contractor shall submit the shop
plans showing the installation detail for a typical EMP for Engineer’s approval.
B. The PA system shall be able to adjust the speaker output level based on the noise
level sensed by the Ambient Noise Sensor located in the EMP.
C. The telephone set inside the EMP shall be interfaced such that the intelligible
paging can be done from the telephone set to the platform speakers.
A. The Audio Decoder also known as Voice Gateway shall provide live audio over the
IP network. The audio decoder shall convert live messages on IP network to
interface with the analog speakers.
B. The Audio Decoder shall provide one (1) 10/100BaseTnetwork port and one (1)
analog audio channel.
A. The voltage suppressor shall be able to perform the intended function in the
environment typically encountered in Los Angeles Area.
b. Phase loss.
c. Transients.
C. The suppressor shall comply with applicable UL, ANSI, NEMA, and IEEE
requirements.
A. The Contractor shall provide a fully functional rack mounted fiber optic patch panel
(FOPP) inside the Communications Shelter/Room including Connector housing,
brackets, connectors, and splice tray as specified and as shown in these Contract
Documents.
B. The contractor shall provide appropriate number of brackets, connector panels and
Splice trays as specified and as shown in these Contract Documents.
3.16 FOPP
A. The Contractor shall provide a fully functional fiber optic patch panel (FOPP) which
comes in form of an environmental distribution center and shall be capable of
mounted on the following:
1. Light Pole.
2. Wall.
3. Inside a Cabinet.
B. The fiber optic patch panel (FOPP) shall include environmental distribution center,
brackets, connectors, and splice tray as specified and as shown in these Contract
Documents.
C. The Contractor shall provide appropriate number of connector panels and Splice
trays as specified and as shown in these Contract Documents.
A. Adequate space shall be provided for termination of cables and in the area
surrounding racks.
C. Passive equipment such as patch panels shall be located on the top of the
equipment rack.
E. Equipment rack space shall be managed and the installation shall be neat and
clean.
F. Patch cables shall be arranged in a manner that will cause minimal disruption for
maintenance and modifications. All bends in the fiber patch cables, audio patch
cables, and CAT 6 patch cables shall abide by the manufacture specified minimum
bending radius. Use cable management equipment such as cable ties where
possible.
G. All copper cables shall use shielding, isolating, balancing, and grounding
techniques in compliance with SCRRA’s Design Criteria and Signaling and
Communications Standards to minimize EMI.
4.01 MEASUREMENT
B. Replacement of the LED message signs, strobe lights and PA equipment are
considered incidental to work under other payment items and no separate
measurement and payment will be made to the Contractor for Work of this Section.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 29 20 20
PART 1 - GENERAL
1.01 SUMMARY
A. The work specified in this section includes testing and commissioning the CIS. The
Contractor shall provide staff and all necessary equipment for testing,
commissioning, and delivering a fully functional CIS.
PART 3 - EXECUTION
A. SCRRA may choose to witness any or all the tests. The Contractor shall furnish a
written notice at least two (2) weeks in advance to SCRRA before the testing is
scheduled to begin. SCRRA at its discretion may witness some, all, or none of the
testing.
B. The Contractor shall develop a test procedure and shall submit it for SCRRA’s
review and Approval. The procedure shall include the following as a minimum:
1. Test objective.
5. Provisions for recording test results and test data form to record test
results.
6. Provisions for recording the manufacturer, model number, part number and
serial number for each equipment installed in each station area.
C. The test results shall be signed by the person(s) conducting the test, engineering
manager, and quality control staff of the Contractor. The Contractor shall submit
four (4) copies and one (1) original of the test results for SCRRA’s review and
Approval. Upon review the SCRRA may Approve, Conditionally Approve, or
Disapprove the test results. If Conditionally Approved or Disapproved, the
Contractor shall remove all deficiencies including but not limited to conducting
repairs, retesting, reinstalling, and rewiring at no additional costs to SCRRA within
a reasonable time. The Contractor shall ensure that after the deficiencies are
removed and corrective actions are taken AND the test(s) is/are repeated and that
they/it pass/passes.
D. As part of the testing process, the Contractor shall test the PA function, the LED
message sign function, LCD train arrival/departure function, and finally the
integrated CIS function.
1. After the equipment is installed in its entirety, the Contractor shall schedule
and conduct the PA function test. The testing shall include broadcasting
audio messages from MOC, EMP, and stored or canned messages. The
test shall verify the message priority and broadcast of audio from all
speakers on the platform.
3. The Contractor shall confirm that the LCD monitor displays web pages
correctly.
4. The Contractor shall ensure and confirm that all installations meet
SCRRA’s safety and security requirements.
E. As a result of failure during the test, or if the test does not complete successfully,
the Contractor shall take corrective action and shall retest at no additional cost to
SCRRA. The Contractor shall take all necessary steps to successfully complete
the tests and provide a fully functional CIS as specified herein.
F. All test results, equipment list, and documents become the property of SCRRA.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 29 20 60
SITE CLEARING
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERNCES
1.03 SUBMITTALS
A. General:
B. The Contractor must take possession of material and debris collected from site
clearing procedures and be responsible for disposing of them in accordance with
these Specifications, any project permits, and applicable laws and regulations in
accordance with Division 01 requirements.
D. Site cleanliness, sweeping and dust control shall be in accordance with Division
01 requirements.
PART 3 - EXECUTION
3.01 PREPARATION
A. Protect existing trees, other vegetation, and existing site improvements on SCRRA
or adjacent property that are to remain.
2. Avoid foot or vehicular traffic or parking of vehicles within drip line of trees
or shrubs.
2. Remove trees that are damaged to the extent that a certified arborist or
tree surgeon determines they cannot be repaired and restored to full-
growth status.
C. SCRRA will obtain authority for removal and alteration work, as required by the
Plans, on adjoining property prior to Contractor starting work.
A. Topsoil, fertile, friable soil of a loamy character with organic matter normal to the
area, Removal:
4. Topsoil from borrow sources shall be free of subsoil, objects over 2 inches
diameter, weeds and roots.
5. Clearing: Clear from within limits of construction all trees except those
marked to remain. Maintain worksite in this cleared condition.
B. Removed materials shall become the property of the Contractor and shall be
disposed of outside the public right of way in conformance with the provisions in
Section 01 74 19 and reference Section 300-1.3 “Removal and Disposal of
Materials” of the Standard Specifications for Public Works Construction, Current
Edition. Within the limits of clearing, all stumps, roots, root mats, logs, debris and
other objectionable material shall be removed as follows:
1. Grubbing shall extend to the outside excavation and fill slope lines except
where tops of slopes are to be rounded. In these locations, the areas shall
extend to the outside limits of slope rounding.
3.03 CLEAN-UP
3.04 SCHEDULE
A. Contractor must complete clearing and grubbing work far enough in advance of
other operations to permit the placement of construction stakes. Construction
schedule shall be adjusted so cleared areas are not left susceptible to erosion or
sediment runoff due to weather.
3.05 ACCEPTANCE
A. Upon completion of the site clearing, obtain Engineer's written acceptance of the
extent of clearing, depth of stripping, and removal of deleterious material.
4.01 MEASUREMENT
A. Site Clearing will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Site Clearing furnished and completed in accordance with the Contract Documents
will be paid for at the Contract Unit Price, as listed on the Schedule of Quantities
and Prices. This price shall include full compensation for furnishing all labor,
Materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 31 11 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
2. Section 31 20 00 - Earthwork
5. Section 34 72 00 – Trackwork
1.02 SUBMITTALS
A. General
3. Private property owner’s release for material removed from the Authority’s
project site and deposited on private property.
a. Releases shall absolve SCRRA and its member agencies from any
responsibility in connection with the disposal of materials on private
property.
4. Disposal certification for materials removed from job site indicating they
have been disposed of in accordance with applicable laws and regulations.
A. General:
2. Clean, list and tag each item in a manner acceptable to the Engineer for
storage.
B. Demolished Materials:
C. Environmental Requirements:
PART 2 - PRODUCTS
A. Subject to compliance with the Contract Documents, the following products and
manufacturers are acceptable for nonshrink grout and epoxy bonding adhesive to
be used for patching of concrete to remain after demolition:
1. Nonshrink grout:
2.02 MATERIALS
A. Nonshrink Grout:
D. Backfill Material:
PART 3 - EXECUTION
3.01 GENERAL
A. No party other than the Contactor shall remove demolished material from the
Authority’s property.
B. Contractor shall perform the demolition, removal, salvage, cutting and patching
including handling of demolished debris in accordance with the Contract Plans,
Project Specifications and the submitted approved site demolition plan.
C. The Contractor shall replace or repair, at no expense to the Authority, any existing
structure or portion of existing structure or related facility designated to remain that
are damaged during removal of the portions designated for demolition.
3.03 PAVEMENT
1. Portland cement concrete pavement removal shall have a second full depth
relief saw cut offset 12 to 18 inches parallel to the initial saw cut unless
approved otherwise.
2. If a saw cut in concrete falls within three feet of a construction joint, cold
joint, expansion joint, or edge, the concrete shall be removed to the joint or
edge.
D. The Contractor shall replace at no expense to the Authority any existing pavement
designated to remain that is damaged as a result of Contactor activities.
3.05 UTILITIES
B. The Contractor shall cap and plug storm drain, sanitary sewer, and underdrain in
accordance with the utility owner’s standard details and instructions. Cap and plug
pipe and other conduits abandoned due to demolition, with approved type caps
and plugs as required by the utility owners.
C. Abandoned utilities under railroad tracks shall be removed and backfilled or filled
in accordance with these specifications and the project plans and technical
Specifications.
B. Cut track to limits shown on the Plans or as called for in this Specification. Rail
shall be cut with rail saw to a tolerance of 1/32 inch from square. All burrs shall be
removed and ends made smooth. Torch cut rails will be rejected.
C. Remove trackwork, including rail, ties, ballast, subballast, and other track materials
in accordance with this Section.
4.01 MEASUREMENT
C. Removal of traffic lines and marking will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
A. When the Contract Documents include separate items, and units or lump sum
prices for removing, salvaging, adjusting, modifying, remodeling, abandoning,
obliterating, relaying, reconstructing, relocating or resetting any of the facilities, the
quantities will be paid for at the Contract unit, or lump sum price for the item of
work involved.
B. This price shall be full compensation for furnishing all labor, materials, tools,
equipment, supplies, supervision, incidentals, and for doing all the Work involved
in completing the operations as shown or depicted on the Plans, and as specified
in these Specifications, or as directed by the Engineer.
C. Full compensation for all excavation and backfill required to remove, dispose of,
salvage, relay, reset, relocate, and/or reconstruct facilities, for which payment is
not otherwise provided, shall be considered as included in the Contract unit or lump
sum price paid for the items of work involved and no separate payment will be
made.
D. When the Contract does not include separate items for removing any of the
existing facilities encountered within the area to be cleared and grubbed or the
removal is not included in another item, then payment for removing the facilities
shall be considered incidental to work under other payment items and no separate
measurement and payment will be made to the Contractor for Work of this Section.
E. Payment requests for Demolition, Cutting and Patching shall include certificates
showing legal disposal of Materials from SCRRA’s right-of-way. No payment will
be considered without such certificates.
END OF SECTION 31 11 50
EARTHWORK
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
2. D1556, Standard Test Method for Density and Unit Weight of Soil In Place
by the Sand Cone Method.
4. D2419, Standard Test Method for Sand Equivalent Value of Soils and Fine
Aggregate.
5. D4254, Standard Test Methods for Minimum Index Density and Unit Weight
of Soils and Calculation of Relative Density.
6. D4318, Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity
Index of Soils.
8. D6938, Standard Test Methods for IN-Place Density and Water Content of
Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depths).
1.03 SUBMITTALS
A. General:
C. Certificates:
1. Material Test Reports for products purchased and used in the project.
4. Certified laboratory test reports for fill material, imported or obtained from
SCRRA property, documenting:
E. Samples:
1. Submit samples, soils test results, and sources of fill, backfill and borrow
materials proposed for use.
F. Miscellaneous Submittals:
1. Submit test results for density and compaction tests performed by certified
test laboratory hired by the Contactor and approved by the Engineer to
perform and report testing.
A. Prior to commencing Work, the Contractor shall examine the Contract Plans and
Specifications, inspect the site, consult all available record Plans of existing Work
and utilities, and note all conditions and limitations, which may influence Work
required by this Section.
B. Materials not meeting the requirements of this specification shall not be used in
the Work.
B. The Contractor must barricade open excavations and post with warning lights
those excavations occurring on property adjacent to or within public access areas
and along the SCRRA tracks in accordance with requirements of Section 31 50
00. Operate warning lights during hours from dusk to dawn each day and as
otherwise required. Warning lights shall be located to avoid shining directly into
Locomotive Engineer’s eyes in oncoming trains.
C. The Contractor must protect utilities, structures and facilities designated as protect
in place from damage caused by settlement, lateral movement, undermining,
washout, and other hazards created by excavation and backfill operations.
D. The Work shall allow rainfall to drain freely at all times in accordance with project
environmental requirements and permit conditions in accordance with Division 01
requirements.
A. The Contractor must protect against erosion and uncontrolled run-off within and
adjacent to right-of-way in accordance with the Project’s Storm Water Pollution
Prevention Plan and the approved NPDES Permit in accordance with Division 01
requirements.
B. The Contractor must obtain all required permits for dewatering and legally dispose
of water from dewatering operations.
E. The Contractor shall maintain in good working order all erosion and sedimentation
controls throughout the duration of the work.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Structure Excavation:
Embankment fill and backfill shall consist of suitable material from project site
excavation, from other SCRRA property or off site borrow as shown in the Plans
and approved by the Engineer.
1. Suitable fill materials may be obtained from on-site excavation and rough
grading operations provided the Contractor submits laboratory test results
demonstrating that the materials meet or exceed the criteria established in
this Section. If sufficient suitable materials are not available to meet
requirements, the material shall be obtained from outside sources.
3. Nesting of rock pieces that will create voids will not be permitted.
4. Fill and backfill material shall be free from organic matter, excessive fines,
or unsuitable products of demolition. Fill and backfill shall contain no rocks
or lumps over 3 inches in greatest dimension within 1 foot of the top of
subgrade.
5. Fill and backfill material shall have plasticity index of 15 or less and a liquid
limit of 30 or less and expansion index of 30 or less, except where
otherwise approved by the Engineer.
C. Structural Backfill:
2. Material shall have a Sand Equivalent value of not less than 20 and shall
conform to the following grading in Table 1:
The Contractor shall submit in writing to the Engineer for approval of the
substitution that is being requested.
PART 3 - EXECUTION
3.01 PROTECTION
A. Protect existing surface and subsurface features on-site and adjacent to site as
follows:
5. Provide full access to public and private premises, fire hydrants, street
crossings, sidewalks and other points as designated by Owner to prevent
serious interruption of travel and emergency services.
8. At all times during the execution of this Work, the Contractor must maintain
safe and stable excavations. Where required by California Construction
Safety Orders, the Contractor must employ side slope layback, benching,
or shoring. Required excavation support methods shall be in accordance
with Section 31 50 00.
2. Obtain all permits for and legally dispose of water dewatering operations to
facilitate construction. Comply with requirements of the permits, project
environmental conditions and agencies having jurisdiction.
1. Prior to rough grading, the Contractor must complete clearing and grubbing
in accordance with Section 31 11 00.
2. Contract Plans may indicate both existing grade and finished grade
required for construction of Project.
a. Stake all units, structures, piping, fills and cuts, roads, parking areas
and walks and establish their elevations upon completion of site
clearing in accordance with SCRRA Standard Specification 31 11
00.
3. The Contractor must not place any embankment fill or sub-ballast onto the
ground surface for embankment fills or base of excavations without prior
acceptance of the excavated and rough graded areas by the Engineer.
8. Fill and backfill shall be placed as promptly as work permits but not until
completion of the following:
d. Contractor must keep graded areas free of trash and debris until
final inspection and acceptance by the Engineer.
C. Borrow:
D. Construct embankment and structure cuts and fills as required by the Contract
Plans:
2. Provide approved fill material for embankment fill or backfill which is free
from roots, organic matter, trash, frozen material as follows:
a. Ensure that stones larger than 3 inches are not placed in upper 12
inches of fill or embankment.
3. Provide approved fill material for structural fill or backfill which is free from
roots, organic matter, trash, frozen material, and stones as follows:
a. Ensure that stones larger than 3 inches are not placed against any
concrete or other foundation material or used as structural fill or
backfill.
A. Contractor must determine the type, size and weight of the compaction equipment
best suited to perform the work at hand. Select and control the lift (layer) thickness
within the Specifications with approval of the Engineer. Proper control over the
moisture content of the material shall be maintained to obtain required compaction
results.
A. Include in bid price for earthwork the cost of inspection services indicated herein
as being performed by the Contractor’s Soils Engineer.
a. At least one density test must be performed for each 200 cubic
yards of embankment compacted fill.
D. Give minimum of 24 hours advance notice to the Engineer when ready for
compaction or subgrade testing observation and inspection.
A. General:
6. In the paragraphs of this Section of the Specifications, the word "soil" also
includes any type of rock subgrade that may be present at or below existing
subgrade levels.
1. General:
2. Dimensions:
6. Dewatering:
7. Subgrade stabilization:
8. Protection of structures:
9. Shoring:
10. Drainage:
C. Structural Fill and Backfill below Foundations, Base Slabs, Floor Slabs, Equipment
Support Pads and Piping:
1. General:
c. Do not place any fill or backfill material until subgrade under fill or
backfill has been inspected and approved by the Engineer as being
free of undesirable material and compacted to specified density.
2. Obtain approval of fill and backfill material and source from the Engineer
prior to placing the material.
e. Do not place fill and backfill when the temperature is less than 40
deg. F and when subgrade to receive fill and backfill material is
frozen, wet, loose, or soft.
b. 5 feet.
Or
1. This paragraph of this Specification applies to fill and backfill placed outside
of structures above bottom level of both foundations and piping but not
under paving.
d. Use only hand operated equipment for filling and backfilling within
a distance of 5 feet from walls, retaining walls and other concrete
structures.
a. Do not backfill around any part of structures until each part has
reached specified 28-day compressive strength and backfill
material has been approved by the Engineer.
4.01 MEASUREMENT
A. Excavation and backfill will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
B. Excavation and backfill will be acceptably excavated or filled within the limits of
lines and slope described in typical sections and cross sections in the plans and
contract documents. Measurement will be by type of excavation or backfill:
1. Excavation.
C. Materials excavated outside of the designated sections or from borrow pits will not
be measured. When the project is constructed essentially to the dimensions
shown on the plans no further measurement will be required, and payment will be
made for the quantities shown in the contract for the various bid items involved. If
disagreement exists between the Contractor and the Engineer as to the accuracy
of the plan quantities, either party shall, before any work is started which would
affect the measurement, have the right to request in writing and thereby cause the
quantities involved to be measured. If measured quantities do not reveal a
discrepancy when compared to plan quantities, the Contractor must pay for the
cost of the Engineer to perform measurements and calculations of quantities.
4.02 PAYMENT
A. Excavation will be paid for at the contract unit price, as listed on the Schedule of
Quantities and Prices, of excavation of proper classification within the limits of lines
and slopes described in the typical sections and cross sections as defined in the
plans and Contract Documents. This price shall be full compensation for furnishing
all labor, materials, tools, equipment, supplies, supervision, and incidentals
necessary for excavating, loading, transporting, and depositing materials in
embankment, spoil bank, stockpile, or other designated location by whatever
method is adopted, including all permission/permitting for haul operations.
B. Embankments will be paid for at the contract unit price, as listed on the Schedule
of Quantities and Prices, of embankment of proper type within the limits of lines
and slopes described in the typical sections and cross sections as defined in the
plans and Contract Documents. This price shall be full compensation for furnishing
all labor, materials, tools, equipment, supplies, water for compaction, supervision,
and incidentals necessary for excavating, loading, transporting, and depositing
borrow material when required; loading, transporting, and depositing select
material from stockpile when required; loading, transporting, and distributing water;
spreading, aerating if necessary, and compacting the embankment material; and
finishing the embankment sections to the designated line and grades.
C. Structural backfill and pervious backfill material will be paid for at the contract unit
price, as listed on the Schedule of Quantities and Prices, of material within the
limits of lines and slopes described in the typical section and cross sections as
defined in the Plans and Contract Documents. This priced shall be full
compensation for furnishing all labor, material, tools, equipment, supplies water for
compaction, supervision and tools necessary for backfilling structures in
accordance with these Specifications and the designated lines and grades in the
Plans.
D. Removal of unsuitable material and backfill with approved suitable material will be
paid for at the contract unit price per unit of material within the limits of lines and
slopes agreed upon by the Contractor and Engineer and measured as applicable.
This price shall be full compensation for furnishing all labor, material, tools,
equipment, supplies water for compaction, supervision and tools necessary for
excavating and backfilling areas of unsuitable material in accordance with these
Specifications.
END OF SECTION 31 20 00
PART 1 - GENERAL
1.01 SUMMARY
General: Soil on Project Worksite shall be managed per Contractor’s approved Soil
Management Plan within confines of Project Worksite including chemically-impacted
soil that is encountered which exceeds thresholds for hazardous waste per these
specifications.
Section Includes:
5. Section 31 20 00 – Earthwork
1.02 DEFINITIONS
SOIL CATEGORIES
(PID) reading equal to or exceeding 50 ppmv when calibrated to hexane and held no
more than 3 inches from the soil surface. This is a temporary soil category.
Potentially-contaminated soil is sampled and subjected to laboratory analysis after
which it will be categorized as non-impacted soil, chemically-impacted soil or
hazardous waste soil depending upon the laboratory analytical results and the
established regulatory concentration limits that distinguish between the categories.
Category 4: Hazardous Waste Soil – Excavated soil that is sampled and analyzed by
a laboratory where the results show concentrations of COCs meeting the criteria of
hazardous waste as defined in 22 CCR section 66261.3. The hazardous waste soil
is classified as either being subject to RCRA, found in 40 CFR, or it is subject to HSC
and 22 CCR. The hazardous waste categories include acutely hazardous waste,
extremely hazardous waste, non-RCRA hazardous waste, RCRA hazardous waste,
special waste and universal waste (further described in Article 3.05 D).
DEFINITIONS (OTHER)
1.04 SUBMITTALS
Before starting soil grading, excavating, and handling, Contractor shall submit:
Before starting soil grading, excavating, and handling, provide for the Authority’s file
copy of Contractor’s site-specific Health and Safety Plan (HASP), complying with 29
CFR 1910.120.
impacted soil and/or hazardous waste soil. HAZWOPER trained workers may also
be required if chemically-impacted soil or hazardous wates soil is to be considered
an exposure hazard to workers, in accordance with Contractors site-specific HASP.
Before starting soil grading, excavating, and handling, submit for the Authority’s
approval Contractor's plan for sequencing of excavation, hauling routes, and soil
stockpile management.
After sample analysis, export of non-impacted soil shall comply with specifications
set out in Section 31 20 00 Earthwork.
The Authority, as the Generator of Waste, shall provide the following to the contractor:
2. Generator name.
3. Generator address.
4. Site address.
Submit for the Authority approval letters of commitment from waste transporters
agreeing to handle soil that shall be disposed of off-site as as chemically-impacted
soil or hazardous waste soil. Commitment letters shall include:
1. EPA ID number.
Submit for the Authority’s files, copies of waste profile documentation that Contractor
submitted to proposed disposal facilities for chemically-impacted soil.
Submit for the Authority’s files, copies of hazardous waste profile documentation that
Contractor submitted to proposed hazardous waste soil disposal facilities.
Before soil loading for disposal as chemically-impacted soil, submit to the Authority
for review and signature completed copies of bills of lading for each load of
chemically-impacted soil that has been properly characterized as chemically-
impacted soil based on laboratory analysis results.
Before soil loading for disposal as hazardous waste soil, submit to the Authority for
review and signature completed copies of waste manifests for each load of
hazardous waste soil that has been properly characterized as hazardous waste soil
based on laboratory analysis results.
Within two business days after notification of receipt at disposal facility, submit for the
Authority’s files completed bill of lading and waste manifest records.
Submit for the Authority’s files Contractor's log for tracking disposal information for
chemically-impacted soil and hazardous waste soil removed from Worksite. Disposal
log shall include:
Submit for the Authority’s files, copies of weight records obtained from disposal
facilities.
Training – Personnel working with hazardous waste soil shall be 40-hour trained
under HAZPOWER requirements (29 CFR 1910.120) and have current 8-hour
HAZPOWER refresher within the past year. If the material being excavated and
handled has not yet been categorized, for the purposes of contractor training the
hazardous waste soil requirements shall apply.
1. Training.
2. Training refreshers.
3. Medical surveillance.
Contractor licensing and training for personnel working with soil identified as
chemically-impacted soil or hazardous waste soil shall be determined by Contractor’s
site-specific HASP.
Non-impacted soil, if it is excess and has no use on the work site, can remain in
stockpiles stored onsite indefinitely (and if space available) until such time a beneficial
use is identified. If non-impacted soil is to be exported, the final destination(s) should
be identified in the Contractor’s Soil Management Plan. The receiving location(s) shall
be described in sufficient detail to confirm that offsite re-use of the non-impacted soil
at the receiving location(s) is compliant with all regulatory requirements.
Chemically-impacted soil shall not be exported until sufficient laboratory analysis has
been conducted to meet the characterization requirements of the receiving facility(s).
The receiving facility(s) soil characterization sampling requirements shall be included
in the Contractor’s Soil Management Plan. Stockpiles of chemically-impacted soil
shall not remain stored onsite longer than 120 days from the accumulation start date.
Hazardous waste soil shall not be exported until sufficient laboratory analysis has
been conducted to meet the characterization requirements of the receiving facility(s).
The receiving facility(s) soil characterization sampling requirements shall be included
in the Contractor’s Soil Management Plan. Stockpiles of hazardous waste soil shall
not remain stored onsite longer than 90 days from the accumulation start date..
All soil categories shall be handled and stockpiled separately from other categories
and stockpiles labeled as to which category each belongs. Handling, separate
category soil stockpiles, and stockpile labeling shall be maintained until any or all soil
categories are prepared to be exported offsite. Preparation for export means all
required laboratory analyses, signed bills of lading, signed manifests, properly
permitted transporters, and receiving facilities pre-approval are in place.
Obtain and pay for permits and fees required for off-site disposal of the three
categories of soil. 1. Non-impacted soil (“clean” excess soil); 2. Chemically- impacted
soil; and 3. Hazardous waste soil (see 4.02 for incremental cost reimbursement).
The findings of any previous environmental site assessments and soil sampling will
be provided by the Authority as an attachment.
PART 2 - PRODUCTS
Stockpile Foundation:
Stockpile Liners: 60 mil high density polyethylene (HDPE) plastic sheeting, minimum.
Leachate and Stormwater Collection Storage Tanks: Minimum storage tank capacity
shall be 20,000 gallons.
Tanks shall have sample ports and drain valves to facilitate characterization and
disposal of accumulated liquid.
PART 3 - EXECUTION
3.01 NOTIFICATION
Contractor shall notify the Authority in conformance with this Section, of discovery of
potentially chemically-impacted soil, which has been identified by staining,
discoloration, odor, free product or a PID reading of 50 ppmv or greater.
Contractor shall maintain field notes of visual observations, odor detections, PID
readings, and locations of these observations and readings.
Contractor shall sample and analyze excess soil that will be exported from Project
Worksite for characterization prior to export. Analytical results will be used to
determine appropriate re-use or disposal of export material per Article 3.05.
All soil categories: Soil stockpiling activities must conform to sedimentation and
erosion control measure requirements as described in Section 32 91 00 Soil Erosion,
Sediment Control, Top Soiling and Seeding.
All soil categories: Plastic sheeting shall be secured with sand bags while in storage
on the Project Worksite and while being used to cover stockpiles to prevent plastic
from blowing into other areas of the Project Worksite.
All soil categories: Due to limitations of the Project Worksite, stockpiling storage
space will be limited, and materials shall be exported immediately where possible.
Stockpile information and storage durations must be submitted to the Authority and
approved by the Engineer.
Non-impacted soil category: Contractor shall separately stockpile and protect in like
manner as other soil categories described in Section 3.03, except that stockpile liner,
stockpile cover, and special labeling will not be required except to mitigate other
conditions, such as fugitive dust or stormwater runoff.
Hazardous waste soil category: Contractor shall stockpile and segregate this soil
category as follows:
2. Hazardous waste soil storage onsite shall not exceed 90 days from
the date that accumulation started.
Implement best available control measures to comply with SCAQMD PM10 emission
limits. If necessary, place miniature real-time aerosol monitor (MiniRam) on the
prevailing downwind side of the soil excavation area to monitor for airborne
particulate emissions during excavation or soil handling activities.
Prevent stormwater runoff from flowing into or out of excavated areas or stockpile
areas as described in SWPPP.
Excess soil for export shall be sampled for proper profiling prior to off-site disposal.
Laboratory analysis shall include, at a minimum:
Contractor shall sample, analyze, and receive analytical results for soil to establish
profile prior to export and disposal.
Contractor’s soil samples shall be transported in cooler with ice to a State of California
certified environmental laboratory within the laboratory specified holding time.
Samples shall remain in cooler with ice. Completed chain-of-custody documentation
shall accompany these samples.
Soil identified as hazardous waste soil shall be transported by Contractor off-site for
appropriate disposal at an appropriately-permitted facility that is approved by the
Authority. Basis for off-site disposal of soil as hazardous waste includes results of soil
sample analyses equaling or exceeding California Title 22 Total Threshold Limit
Concentrations (TTLC) or Soluble Threshold Limit Concentrations (STLC) or US EPA
Toxicity Characteristic Leaching Procedure (TCLP) maximum concentrations, where
applicable.
In the event additional soil sampling and analyses are required by Contractor’s
proposed disposal facility for soil profiling and acceptance by disposal facility,
Contractor shall perform those additional sampling and analyses as part of disposal.
Use state-approved manifest system so that hazardous waste hauled from Worksite
can be tracked from point of generation to ultimate disposal. Manifests must comply
with provisions of state and federal DOT regulations. Use Department of Toxic
Substances Control (DTSC) Form 8022A/Environmental Protection Agency Form
8700-22 (Uniform Hazardous Waste Manifest). If receiving disposal site is outside of
California, Contractor shall comply also with regulations of the state or states in which
materials are being transported to and disposed of. Contractor shall be responsible
for providing completed manifests and supporting documentation to the Authority for
each load prior to shipment.
Contractor shall be responsible for accurate and timely completion of final waste
manifests. Transporters must sign appropriate portions of manifest and must comply
with provisions established in state and federal DOT regulations. Disposal facility
must sign appropriate portions of manifest and return it to Contractor on day of
disposal.
Trucks shall be properly lined with material compatible with wastes to be hauled.
Upon completion of truck loading, waste shall be covered with a tarp or container lid
prior to departure.
Thoroughly decontaminate and inspect transport vehicles before leaving work area.
Each vehicle leaving work area shall be inspected by Contractor to ensure that no
soil adheres to wheels or undercarriage. Remove soil at the work area or
decontamination pad before allowing the truck to leave the Worksite.
Remedy situations involving materials spilled in transit or mud and dust tracked off-
site. Cost of remedy, including fines, shall be sole responsibility of Contractor.
4.01 MEASUREMENT
ALLOWANCE – Removal and Disposal of each category of soil, Allowance for [TBD
by Project] CY, will be measured by the unit or fraction thereof furnished and
completed with the Contract Documents and as measured by the Contractor and
verified by the Authority or their designee. Each category of soil will be measured in-
situ in cubic yards.
1. UNIT COST – Contractor shall provide unit costs per cubic yard that
represent the incremental costs of handling and disposing of the
three final soil categories over and above the base cost of earthwork
under bid item 31 20 00.01.
4.02 PAYMENT
ALLOWANCE – Removal and Disposal of the three final soil categtories will be paid
from an allowance included on the approved Schedule of Quantities based on the
incremental labor, equipment, and handling costs incurred to dispose of each
category of soil over and above normal earthwork. These incremental costs will be
measured based on the total volume of each category of soil vs total volume of
earthwork.
For example, for 5000 cubic yards of earthwork, if based on laboratory analysis, 20%
of the soil was categorized as chemically-impacted, the Authority would pay for 5000
cubic yards of earthwork (paid under bid item 31 20 00.01) and the incremental costs
incurred to handle and dispose of 1000 cubic yards of chemically-impacted soil under
this allowance. The incremental costs will be paid based on the Unit Cost provided
by the Contractor and will require additional invoicing backup. Contractor will be
required to submit documentation of their additional incurred costs of handling and
disposing of each category of soil above and beyond the earthwork costs.
END OF SECTION 31 20 50
EXCAVATION SUPPORT
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
7. Section 31 20 00 - Earthwork.
9. Section 34 80 21 - Piling.
1.2 REFERENCES
1.3 SUBMITTALS
A. General:
B. Contractor’s Superintendent:
C. Contractor’s Engineer:
D. Design:
E. Plans:
c. Construction schedule.
d. Contingency plans.
G. Construction Verification:
1. The Contractor shall submit a detailed monitoring plan, including Plans and
procedures for inspection and surveying. The monitoring plan shall comply
with the Contract Documents, approved working Plans and the SCRRA
Design Criteria Manual, Chapter 15.0, Excavation Support Criteria.
B. Contractor:
B. The Contractor must barricade open excavations and post with warning lights
those excavations occurring on property adjacent to or within public access areas
and along the tracks in accordance with the SCRRA Design Criteria Manual,
Chapter 15.0, Excavation Support Criteria. Operate warning lights during hours
from dusk to dawn each day and as otherwise required. Warning lights shall be
located to avoid shining directly into Locomotive Engineer’s eyes in oncoming
trains.
D. The Work shall allow rainfall to drain freely at all times in accordance with project
environmental requirements, permit conditions, and with Division 01 requirements.
A. The Contractor must protect against erosion and uncontrolled run-off within and
adjacent to right-of-way in accordance with the Project’s Storm Water Pollution
Prevention Plan, the approved National Pollution Discharge Elimination System
(NPDES) Permit, and in accordance with Division 01 requirements.
B. The Contractor must obtain all required permits for dewatering and legally dispose
of water from dewatering operations.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Soil and rock materials for fill, backfill or subgrade preparation shall be in
accordance with Section 31 20 00 or as specified by the Engineer in Responsible
Charge.
B. Hot Mix Asphalt (HMA) pavement shall meet the requirements of Section 32 12
00.
D. Handrails and Walkways: See Contract Documents and SCRRA Design Criteria
Manual, Chapter 15.0, Excavation Support Criteria.
E. Materials used in the excavation support system shall be new unless otherwise
approved by SCRRA. Structural materials that compose the excavation support
system shall meet the requirements for the applicable material type as listed,
unless specified otherwise by the Engineer in Responsible Charge in the Contract
Documents or approved Working Plans:
1. Structural steel: Section 05 12 23 for steel soldier piling and steel sheet
piling and Section 34 80 51 for all other structural steel members.
8. Ground anchors and rock anchors: See Contract Documents and SCRRA
Design Criteria Manual, Chapter 15.0, Excavation Support Criteria.
PART 3 - EXECUTION
1. Examine the Contract Documents, inspect the site, obtain all available
Record Plans of existing structures and utilities and note all conditions and
limitations that may influence excavation and temporary excavation
support at the site.
B. Provide safe and stable excavations and maintain the integrity of excavations
throughout the duration of construction.
A. The Contractor will be allowed to propose and submit alternate methods, designs
and details for excavations and temporary excavation support. Only alternates
that comply with the SCRRA Design Criteria Manual, Chapter 15.0, Excavation
Support Criteria and satisfy the contract requirements will be considered for
acceptance. Acceptance of alternates will be at SCRRA’s sole discretion.
C. For alternate designs, the Contractor must retain a Contractor’s Design Engineer
who will be the Engineer in Responsible Charge for the excavation and will act as
the Contractor’s Engineer to verify construction in accordance with the design and
approved working Plans and specifications prepared by said Engineer.
E. The Contractor agrees, upon and at such a time that an alternate design is
submitted to SCRRA, to compensate SCRRA for the full cost of reviewing the
alternate design. This compensation shall include the initial review and any
subsequent review of additional submittals or re-submittals to address previous
SCRRA comments and must be paid regardless of the final disposition
(acceptance or rejection) of the alternate design.
3.3 INSTALLATION
A. Preparation:
B. Operational Constraints:
9. Remove rubbish and spoil piles and return the area to a condition equal to
or better than original and in accordance with Section 32 90 00.
D. Excavation Safety:
3. Contractor must immediately comply with orders from SCRRA to stop work
or perform immediate backfilling of open excavations or other emergency
remedial work when SCRRA, at its sole discretion, determines that the
safety of trains, passengers and SCRRA employees may be in peril.
E. Schedule:
A. Construction Verification:
2. The Contractor must prepare a letter and submit to SCRRA confirming that
the shoring system has been inspected and verified. The letter must be
signed and sealed by the Contractor's Engineer who is a licensed
Professional Engineer in the State of California.
a. Any field changes must be noted and the effect of those changes
must be evaluated and reported by the Contractor’s Engineer. Any
deficiencies noted must be corrected by the Contractor.
Deficiencies and corrections must be noted in the letter with
verification of adequate correction by the Contractor’s Engineer.
B. Track Monitoring:
1. Monitor the excavation and the supported track in accordance with the
approved Track Monitoring Plan, as described in the SCRRA Design
Criteria Manual, Chapter 15.0, Excavation Support Criteria, and as directed
by SCRRA.
3.5 ACCEPTANCE
A. Inspections:
1. Request, schedule and provide the means and access for inspection of the
installed excavation support system and finished excavation by SCRRA
before proceeding with construction.
B. Final Acceptance:
1. Apply for and obtain final acceptance from SCRRA, with or without
inspection at the sole discretion of SCRRA, upon submittal of the final track
monitoring data.
4.1 MEASUREMENT
A. No separate measurement and payment will be made to the Contractor for Work
of this Section. Work of this section shall include furnishing all labor, materials,
tools, equipment, supplies, supervision, and incidentals, and doing all work, as
shown on the Plans, and as specified in these Specifications, and as directed by
the Engineer.
D. Any required testing and sacrificial test elements are incidental to Section 31 20
00 and no additional payment will be made therefore.
END OF SECTION 31 50 00
PART 1 - GENERAL
1.01 SUMMARY
Work covered by this Section includes preparation, placement and compaction of all hot-mix
asphalt for roadways, highway-rail grade crossing paving, yards, access roads, miscellaneous
surface improvements in RR R/W, temporary improvements, dikes, asphalt overlays, and slurry
sealing the existing pavement. Section also includes the prime coat, tack coat, base course and
wearing course.
For HMA for Track and Bridges, see Section 34 80 33 – Hot Mix Asphalt (HMA) for Track and
Bridges.
A. Related Specification Sections include but are not necessarily limited to:
2. Section 31 20 00 – Earthwork
1.02 REFERENCES
1.03 SUBMITTALS
A. Make all the following submittals in accordance with Section 01 33 00, Submittal
Procedures.
4. Test reports from an independent laboratory for materials and mix designs
or proof that mix designs and all Materials are currently approved for use
as asphaltic concrete pavement by Caltrans.
5. Tests reports for field density tests performed after placement and
compaction of each course of asphaltic concrete.
1.04 DELIVERABLES
PART 2 - PRODUCTS
2.01 MATERIALS
A. Asphalts:
3. Liquid asphalt for the prime coat shall be of the grade designated by the
contract item or specified in the special provisions.
4. Asphaltic emulsion for the tack coat shall be of the grade designated by the
Engineer.
B. Aggregate:
C. Prime Coat:
D. Tack Coat:
F. Miscellaneous Areas and Dikes: HMA for miscellaneous areas and dikes shall
conform to Caltrans Standard Specifications, current edition, Section 39.
A. Take the following aggregate samples in the presence of the Engineer and, if
requested, transport samples to Authority-hired testing laboratory. Samples will
be used by the Authority-hired testing laboratory to test aggregate quality:
B. Provide Engineer access for sampling stockpiles, hot bin analyses, and other tests
PART 3 - EXECUTION
3.01 GENERAL
A. Subgrade, aggregate base, curbs, gutters and drains shall be approved by the
Engineer before asphalt-Pavement operations are started.
B. Emulsion – Aggregate Slurry shall conform to the SSPWC, current edition, Section
302-4.
3.03 PREPARATION
A. When placing HMA for access road paving, provide an aggregate base course in
accordance with Section 34 11 27.
D. Spreading of HMA shall not be permitted when the mixing temperature of HMA is
below 250˚ F.
E. HMA shall only be placed when the atmospheric temperature is above 50˚ F.
H. Compact patch to produce a tight surface conforming to the adjacent paving area.
J. Fill wide joints and cracks with asphalt concrete/sand mix material and compact.
3.04 SPREADING
B. The prime coat shall be applied at a rate of 0.25 gal/sq yd and shall be in
conformance with the Caltrans Standard Specifications, Section 39.
C. The tack coat shall be applied in one application at a rate of 0.02 gal to 0.10 gal/sq
yd of surface covered and shall be in conformance with the Caltrans Standard
Specifications, Section 39.
D. Following application of the tack coat, the HMA shall be spread in conformance
with the Caltrans Standard Specifications, current edition, Section 39.
1. Successive lifts may be laid upon previously laid lifts as soon as the
previous lift has cooled sufficiently to show no displacement under
equipment or loaded material delivery trucks.
3.05 COMPACTION
A. Rollers:
a. Rear group wheels shall not follow the tracks of forward group
wheels.
d. The total maximum load per axle, whether single axle or a group of
axles in the same alignment, shall be 22,400 lbs.
B. Rolling:
3. Make initial rolling, using tandem type rollers, parallel to the center line of
the paved surface beginning at the curbs or edges of the paved surface
and working toward the center, overlapping on successive trips by one-half
the rear wheel roller.
4. First make final roll longitudinally with the paved surface and then
diagonally or at right angles.
5. Test after the mixture has been rolled with approved straight edge and
surface testing machine laid parallel to the centerline of the paved surface.
4.01 MEASUREMENT
A. Prime Coat and Tack Coat will not be measured for payment. Costs associated
with the prime or tack coats will be considered as incidental to the Hot Mix Asphalt
Pavement.
B. Hot Mix Asphalt Pavement will be measured by the unit or fraction thereof Installed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
Schedule of Values as derived from the Contract Drawings will be used as the
basis for this measurement. Separate measurements will be made for each
specified thickness of asphaltic concrete material as included on the approved
Schedule of Values.
4.02 PAYMENT
B. When there is no item for place Hot Mix Asphalt Dike and the work is shown on
the Plans, full compensation therefore, including any necessary excavation,
backfill, and preparation of the area, shall be considered as included in the
Contract Unit Price paid for the Hot Mix Asphalt Pavement.
END OF SECTION 32 12 00
PART 1 - GENERAL
1.01 SUMMARY
A. This Section consists of furnishing all labor, Materials and equipment necessary,
and incidental to the manufacture, transport and placement of the curbs and
gutters, related Material, and providing all associated items.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
2. Samples: Sampling and testing for compliance with the contract provisions
shall be in accordance with SSPWC 2012 Section 201-1.1.
PART 2 - PRODUCTS
A. Portland cement concrete for the construction of curbs and gutters shall conform
to SSPWC 2012 Section 201-1.
2.02 REINFORCEMENT
A. All reinforcement for this portion of the Work shall conform to the provisions of
Section 03 21 00. Reinforcing chairs shall be plastic or concrete.
A. Pre-molded joint fillers shall conform to SSPWC Current or Latest Edition, Section
201-3.2.
PART 3 - EXECUTION
3.01 GENERAL
A. Establish and maintain required lines and elevations. Make gradual and smooth
transitions to pavements.
A. Curb face shall be tapered to zero height within 10 feet of track centerline in order
to comply with walkway requirements provision of CPUC General Order 118.
B. For curbs constructed on existing paving, refer to the Contract Documents for
specific details and requirements for attaching curbs to existing paving.
C. Space joints in extruded curbs to match joints in adjacent paving. When the
adjacent paving is not jointed, locate joints at angles, corners, points of curvature,
and points of tangency at intervals of not more than 15 feet.
D. Joints shall be 1/8 inches minimum thickness and constructed to a minimum depth
of 1 inch by scoring with a tool which will leave the corners rounded and destroy
aggregate interlock to a depth of 1 inch.
E. Place expansion joints filler to full cross-section with 1/4 inches thick filler in the
curb at abutting structures and at 100-foot intervals.
F. Cure the extruded concrete for not less than 72 hours by the methods specified in
Section 03 31 00.
A. Construction of cast-in-place curb, and combined curb and gutter shall meet the
requirements of Section 03 31 00.
4.01 MEASUREMENT
A. Concrete curbs, curb and gutters, sidewalks, and driveways will be measured by
the unit or fraction thereof constructed in accordance with the Contract Documents
and as measured by the Engineer. The quantities as contained on the Schedule
of Quantities and Prices, or approved Schedule of Values as derived from the
plans will be used as the basis for this measurement.
4.02 PAYMENT
END OF SECTION 32 16 00
PAVEMENT MARKINGS
PART 1 - GENERAL
1.01 SUMMARY
A. Work involves furnishing all labor, materials and equipment necessary and
incidental to applying pavement and platform striping, markings, markers, and
painting of curbs.
1.02 REFERENCES
1.03 SUBMITTALS
A. Pavement striping, markings, and markers shall be applied by workers with proven
skills required to perform the work in accordance with the correct location,
alignment, and dimensions of the striping and markings as shown in the Contract
Plans or as modified by the Engineer.
C. Until accepted by the Engineer, the Contractor must be responsible for the
maintenance of all pavement striping, markings, and markers until the roadway is
open to vehicular traffic.
D. All pavement striping and marking for roadways, whether temporary or permanent
shall be completed before the roadway is opened for vehicular traffic.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Paint for traffic striping and markings shall comply with Caltrans Standard
Specifications Current or Latest Edition Section 84-3. Type of paint shall either
be Fast Dry or Rapid Dry solvent borne. Thermoplastic traffic stripes and
pavement markings shall comply with Caltrans Standard Specifications Section
84-2. Markers shall comply with Standard Specifications Section 85-1.02.
2.02 COLOR
A. Color for roadways shall be Caltrans Standard Specifications "white" and “yellow”
unless otherwise indicated in the plans.
B. Painting of curbs shall use the color indicated in the Contract Plans.
PART 3 - EXECUTION
3.01 GENERAL
A. Apply paint by using a striping machine, except for special areas and markings,
which are inaccessible or not adaptable to machine application, in which case hand
application will be permitted with approved masking or stencil use.
C. The minimum wet film thickness of the paint shall be 15 mils or in accordance with
the manufacturer's recommendation and approved by the Engineer.
D. Application of the paint shall be made only on a dry and clean surface free from
grease, oils, dirt, curing compound or any other foreign matter, when the weather
is not windy and humid, and the ambient air temperature is not less than 40 DegF.
Contractor must not apply paint to uncured concrete.
F. Contractor must clean up all overspray with approved Materials and leave a clean
and complete project.
4.01 MEASUREMENT
A. Pavement Markings will be measured by the unit or fraction thereof furnished and
placed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved Schedule of Values as derived from the plans will be used as the basis
for this measurement.
4.02 PAYMENT
END OF SECTION 32 17 23
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Chain link fencing and gates including the chain-link fence fabric and posts,
concrete for post bases, rails, ties, bands, bars, rods and other fittings and
hardware designed to support the fabric in a vertical, taut position.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
2. A153, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
10. F900, Standard Specification for Industrial and Commercial Steel Swing
Gates.
C. Chain Link Manufacturer's Institute for "Galvanized Steel Chain Link Fence Fabric
and Accessories."
D. SCRRA Engineering Standards ES5106, Right of Way Fencing, Chain Link Fence.
1.03 DEFINITIONS
C. Installer or Applicator:
1.04 SUBMITTALS
A. Shop Drawings:
A. Qualifications:
1. Installer shall have a minimum two (2) years experience installing similar
fencing.
B. Construct fence within reasonable close conformity to lines and grades shown on
the Plans and at the locations as directed by the Engineer.
PART 2 - PRODUCTS
2.01 COMPONENTS
1. Fabric type:
2. Wire gage shall be 11-gage for fences 6 feet-0 inches and less and 9-gage
for fences over 6 feet-0 inches in accordance with the Project Plans or as
determined by the Engineer based on field conditions in accordance with
SCRRA Engineering Standards ES5106.
4. Selvage treatment:
a. Top: Knuckled.
b. Bottom: Knuckled.
C. Concrete:
D. Line Post:
2. Tension bars used in fastening fabric to end and corner posts and gate
frames:
H. Fence Fittings (Post and Line Caps, Rail and Brace Ends, Sleeves-Top Rail, Tie
Wires and Clips, Tension and Brace Bands, Tension Bars, Truss Rods):
1. ASTM F626.
2. Tie wires shall not be smaller than 11 gage galvanized steel, 6 gage
aluminum wire or approved noncorrosive bands.
3. Truss or tension rods shall be adjustable 3/8 inches dia. galvanized steel
rod.
I. Security Gate:
1. ASTM F900.
3. Hardware:
4. Hang gates on at least two (2) steel or malleable iron hinges not less than
3-inches in width, designed to clamp to the gate post and permit the gate
to be swung as indicated in the plans. The bottom hinge shall have a
socket to take the ball end of the gate frame.
6. Stops to hold gates open and a center rest with catch shall be provided
where required.
J. Security Extension:
1. Extension arms for barbed wire shall be a type that can be attached to the
tops of posts and carry three wire at approximately 5-1/2 inches centers.
PART 3 - EXECUTION
3.01 INSTALLATION
1. Manufacturer's instructions.
C. Work shall be performed by workmen who are thoroughly trained and experienced
in the skills required to install the products of this Section.
D. Do not start fence installation before final grading is complete and finish elevations
are established.
G. Posts shall be set in concrete footings conforming to the details shown on the plans
or SCRRA Engineering Standards ES5106 and crowned at the top to shed water.
H. Place fence with bottom edge of fabric at maximum clearance above grade, as
shown on Plans.
J. Provide post braces for each gate, corner, pull and terminal post and first adjacent
line post.
1. Rails: Fit rails with expansion couplings of outside sleeve type when called
for in plans.
2. Install rails continuous for outside sleeve type for full length of fence
3. Provide expansion couplings in top rails at not more than 20 feet intervals.
L. Install bracing assemblies at all end and gate posts, as well as side, corner, and
pull posts.
2. Secure to posts at not over 15 inches o.c., and to rails at not over 24-inches
o.c., and to tension wire at not over 24-inches o.c.
5. Fabric shall be placed on the outside of poles away from the track or as
directed by the Engineer.
O. Gates:
4.01 MEASUREMENT
A. Chain Link Fencing will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Chain Link Gates will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
C. Quantities of gates will be determined from actual count. When more than one
gate is placed in an opening, each single unit placed will be counted as a gate. A
gate unit complete shall include one gate with necessary fittings, hardware and
gate posts with braces.
D. Chain Link Fencing and gates shall consist of a fabric, including posts, horizontal
members, post anchorages, stretcher bars, tension wires and other required
hardware and fittings, as shown on the Contract Documents.
4.02 PAYMENT
A. Chain Link Fencing furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Chain Link Gates furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
C. Full compensation for furnishing and installing connections on Fencing and Gates,
drilling anchor bolt holes and bolts shall be considered as included in the prices
and no additional compensation will be allowed.
D. Full compensation for furnishing and installing fabric, posts, post tops, tension
wires, post clips, wire ties and hog rings shall be considered as included in the
prices and no additional compensation will be allowed.
E. Full compensation for clearing the line of the fence and disposing of the material,
excavating high points in the existing ground, excavating and backfilling holes,
disposing of surplus excavated material, and furnishing and placing concrete
footings and connecting new fences to structures and existing cross fencing, and
constructing temporary fences for protection of stock, shall be considered as
included as listed on the Schedule of Quantities and Prices.
END OF SECTION 32 31 13
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work involves furnishing all materials, labor and equipment necessary and
incidental to the installation of wire mesh fence at the locations shown on the
Contract Plans.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
A. Comply with all local, State and Federal codes, regulations, Specifications,
standards and recommended practices.
1. A53 Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-
Coated, Welded and Seamless
10. D2794 Standard Test Method for Resistance of Organic Coatings to the
Effects of Rapid Deformation (Impact)
1.03 SUBMITTALS
A. Work shall be performed by workmen who are thoroughly trained and experienced
in the skills required to install the products of this Section.
B. Construct fence to lines and grades shown on the Contract Plans and at other
locations as directed by Engineer.
PART 2 - PRODUCTS
2.01 MATERIALS
C. Clamps: Welded Wire Clamps with tamper proof bolts designed to attached welded
wire panels to the post for support and security.
PART 3 - EXECUTION
B. Triangular shaped stiffening beam shall be placed horizontally and face away from
track, or from the public side of sidewalks.
E. Use tamper resistant bolts to secure welded wire mesh panels to posts via line
wrap around brackets.
4.01 MEASUREMENT
A. Welded Wire Fencing will be measured by the unit or fraction thereof furnished
and Installed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved Schedule of Values as derived from the Plans will be used as the
basis for this measurement.
A. Welded Wire Gates will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Quantities of gates will be determined from actual count. When more than one
gate is placed in an opening, each single unit placed will be counted as a gate. A
gate unit complete shall include one gate with necessary fittings, hardware and
gate posts with braces.
C. Welded Wire Fencing and gates shall consist of a fabric, including posts, horizontal
members, post anchorages, stretcher bars, tension wires and other required
hardware and fittings, as shown on the Contract Documents.
4.02 PAYMENT
A. Welded Wire Fencing and Gates constructed in accordance with the Contract
Documents will be paid for at the Contract Unit Price as included on the approved
Schedule of Quantities and Prices. This price shall be full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals necessary for Welded Wire Fencing and Gates described by the
Contract Documents.
B. Gates installed in accordance with the Contract Documents will be paid for by
actual count at the Contract Unit Price as listed on the Schedule of Quantities and
Prices.
D. Full compensation for furnishing and installing fabric, posts, post tops, tension
wires, post clips, shall be considered as included in the prices and no additional
compensation will be allowed.
E. Full compensation for clearing the line of the fence and disposing of the material,
excavating high points in the existing ground, excavating and backfilling holes,
disposing of surplus excavated material, and furnishing and placing concrete
footings and connecting new fences to structures and existing cross fencing, and
constructing temporary fences for protection of stock, shall be considered as
included as listed on the Schedule of Quantities and Prices.
END OF SECTION 32 31 16
PART 1 - GENERAL
1.01 DESCRIPTION
A. This Work involves furnishing all materials, labor and equipment necessary and
incidental to the installation of tubular steel fencing, inter-track fence, edge fencing,
and gates, including station platform center and edge, as shown on the Contract
Plans. This work also includes providing locks, keys and emergency access
system.
B. Coordinate the work of this Section with all other Sections of this Specification and,
in particular:
1.02 REFERENCES
A. Comply with all local, State and Federal codes, regulations, specifications,
standards and recommended practices.
3. A153 Standard Specification for Zinc Coating (Hot-dip) on Iron and Steel
Hardware
1.03 SUBMITTALS
B. Construct fence to lines and grades shown on the Contract Plans and at other
locations as directed by Engineer.
1.05 DELIVERABLES
C. Furnish certificate of inspection stating that the material has been sampled, tested
and inspected per ASTM A525.
PART 2 - PRODUCTS
B. Panel height: Finished fence height shall be 6 feet for Inter-Track fence and 3’-2”
feet at platform edge fence. Panel width shall be as per SCRRA Engineering
Standards ES 5102 and 5104.
C. Posts:
2. Posts shall be 2-1/2 inches x 2-1/2 inches minimum, with a wall thickness
of 12 gauge.
D. Horizontal Rails:
2. Rails shall be 1 inch by 2 inches minimum, with a wall thickness of 1/8 inch.
E. Gate Hardware: Hinges, latches, drop rods, as needed, shall be hot dipped
galvanized steel in accordance with ASTM A153 and sized to assure proper gate
operation.
2.02 CONCRETE
A. Zinc: Hot dipped galvanize pickets, rings, rails, and posts after fabrication in
accordance with ASTM A123.
B. Powder Coat: Powder coat all parts of fence including hardware after galvanizing
and in accordance with coating manufacturer’s instructions. Powder coat: O’Brien
TGIC-Polyster or approved equal. Color: Black.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Concrete Footings: Drill or dig holes for post footings in firm, undisturbed or
compacted soil. Size footings in accordance with Contract Plans or approved
Shop Drawings. Trowel tops of footings and slope or dome to direct water away
from posts. Slope, do not dome, in pedestrian paving.
B. Posts: Spaced at 10 feet or less on center and set in concrete footings, plumbed
vertical. Post depth as specified on the Contract Plans. Space posts at lesser
distance between centers to compensate for terrain variation such as sharp
variations in incline or decline. Any high points that interfere with placing the fence
shall be excavated to provide the clearance shown on the Contract Plans.
C. Field Joints: Field joints shall be kept to a minimum and concealed to the greatest
extent possible. Field joints shall be strong, rigid, watertight and flush with hairline
fit. Ease sharp corners.
D. Adjust fence for uninterrupted visual continuity and tight, non-rattling connections.
3.02 REPAIR
A. Welded and abraded areas of galvanized surfaces shall be wire brushed and
repaired with two (2) coats of cold galvanized compound.
4.01 MEASUREMENT
A. Tubular Steel Fencing will be measured by the unit or fraction thereof Installed in
accordance with the Contract Documents and as measured by the Engineer. The
quantities as contained on the Schedule of Quantities and Prices, or approved
Schedule of Values as derived from the plans will be used as the basis for this
measurement.
B. Tubular Steel Gates will be measured by the unit or fraction thereof Installed in
accordance with the Contract Documents and as measured by the Engineer. The
quantities as contained on the Schedule of Quantities and Prices, or approved
Schedule of Values as derived from the plans will be used as the basis for this
measurement.
C. Quantities of gates will be determined from actual count. When more than one
gate is placed in an opening, each single unit placed will be counted as a gate. A
gate unit complete shall include one gate with necessary fittings, hardware and
gate posts with braces.
D. Tubular Steel Fencing and Gates shall consist of a pickets and rings, including
posts, horizontal members, post anchorages, rails and other required hardware
and fittings, as shown on the Contract Documents.
4.02 PAYMENT
A. Tubular Steel Fencing constructed in accordance with the Contract Documents will
be paid for at the Contract Unit Price as included on the approved Schedule of
Quantities and Prices. This price shall be full compensation for furnishing all labor,
Materials, tools, equipment, supplies, supervision, and incidentals necessary for
Tubular Steel Fencing described by the Contract Documents.
B. Gates installed in accordance with the Contract Documents will be paid for by
actual count at the Contract Unit Price as listed on the Schedule of Quantities and
Prices.
D. Full compensation for furnishing and installing pickets and rings, posts, and post
tops, shall be considered as included in the prices and no additional compensation
will be allowed.
E. Full compensation for clearing the line of the fence and disposing of the material,
excavating high points in the existing ground, excavating and backfilling holes,
disposing of surplus excavated material, and furnishing and placing concrete
footings and connecting new fences to structures and existing cross fencing, and
constructing temporary fences for protection of stock, shall be considered as
included as listed on the Schedule of Quantities and Prices.
END OF SECTION 32 31 19
PART 1 - GENERAL
1.01 SUMMARY
A. Furnish and install a complete microprocessor based vehicular swing gate or slide
gate operator system, with a solid-state board to control all functions of the gate
operator, as described herein and shown on the plans. Include all necessary
control boards, power supplies, loop detectors, connectors, and accessories for a
complete operational system.
A. All equipment and work specified in this section shall comply, with all the General
Conditions of the specifications, contract documents, and drawings as indicated.
A. Gate operator systems contractor shall coordinate all work with other contractors
and trades where necessary.
B. All necessary conduit, raceways and pull boxes shall be installed by the electrical
contractor.
C. Installation of the vehicular gate operator system shall be coordinated with the
installation of other applicable systems and components (e.g. access control
system, fire department key access box, etc.)
B. All equipment shall be new, in current production, and the standard products of a
manufacturer of vehicular gate operator equipment.
C. Manufacturer shall guarantee availability of parts, for a minimum of seven (7) years
from date of shipment.
F. On-site maintenance and repair service shall be available locally and within four
(4) hours of notification for emergency condition.
A. Vehicular swing gate and slide gate operator shall be in compliance with
Underwriter Laboratories Inc. (UL) Standard for Safety - Door, Drapery, Gate,
Louver and Window Operators and Systems, UL 325 Fourth Edition; and
Underwriters Laboratories Inc. (UL) Standard for Safety - Tests for Safety-Related
Controls Employing Solid-State Devices, UL 991 Second Edition.
B. Vehicular Swing Gate Operator shall be tested for compliance to UL 325 and UL
991 and shall be LISTED by a Nationally Recognized Testing Laboratory (NRTL).
1.06 SUBMITTALS
1.07 WARRANTY
A. Products shall include a factory warranty that equipment is free from defects in
design, material, manufacturing and operation. Factory warranty period shall be
for five (5) years parts and workmanship; 60-months from date of shipment.
C. Installing contractor shall guarantee the equipment, wire and installation for 12-
months from date of acceptance.
PART 2 - PRODUCTS
2. Primary reduction system shall be provided by single cog belt drive train
and 60:1 worm gear reduction running in a continuous oil bath.
3. Operator shall employ magnetic sensing to set open and close limit
adjustment. Mechanical type limit switches shall not be allowed.
5. Operator shall be designed for either left or right-hand mount and shall be
designed for pad mounting.
6. Operator frame shall be welded steel anodized black. Control box shall be
constructed from 16-gauge G90 galvanized steel, painted black, to avoid
rusting. Operator cover shall use polyethylene finished in charcoal gray,
suede texture.
7. Operator shall have three 115 VAC convenience outlets available for
accessory transformer power and shall have a built-in lockable power
disconnect and reset switch.
B. Control Circuit:
1. Control board shall have connections for optional board to record operator
cycles (x100), input errors, loop detector errors, obstruction hits, and power
up events. Record shall be time and date stamped.
2. Control board shall be capable of controlling two (2) vehicular swing gate
operators in a true bi-parting gate operation.
3. Control board shall have a gate overlap feature for bi-parting gate
operation.
4. Control board shall have ports for plug in of vehicular loop detectors.
5. Control board shall have separate inputs for external contact and non-
contact entrapment protection devices.
7. A dry set of relay contacts shall be available for external use, and have four
programmable functions.
8. The control board shall have terminals for direct connection of a magnetic
lock.
C. Manual Operation
F. Technical Features
6. Single cog belt driving a 60:1 worm gear reduction system running in a
continuous oil bath
3. Operator shall employ magnetic sensing to set open and close limit
adjustment. Mechanical type limit switches shall not be allowed.
4. Operator shall automatically set both open and close limit adjustments
upon power-up and activation in the open direction. Operator shall
automatically sense for any gate coasting to insure true limit settings.
6. A positive dead bolt shall activate only when the gate is forced open, to
reduce solenoid lock wear and failure.
8. Operator frame shall use 12-gauge G90 galvanized steel to avoid rusting
and shall be painted charcoal gray.
9. Operator shall have two 115 VAC convenience outlets available for
accessory transformer power and shall have a built-in lockable power
disconnect and reset switch.
B. Control Circuit:
1. Control board shall have connections for optional board to record operator
cycles (x100), input errors, loop detector errors, obstruction hits, and power
up events. Record shall be time and date stamped.
2. Control board shall allow a stop or a stop and reverse function (settable)
from a safety related input.
3. Control board shall have ports for plug in of vehicular loop detectors.
4. A dry set of relay contacts shall be available for external use, and shall
have four programmable functions.
6. A timer override function shall cause an opening gate to stop and then
reverse direction when the reverse loop(s) or reverse input is clear even if
the gate has not reached the full open position, to help reduce tailgating.
7. Control board shall have separate inputs for external contact and non-
contact entrapment protection devices.
C. Fail-Safe Operation
2. For enhanced safety, the control circuit shall check the obstruction sensing
system circuit prior to the start of each cycle of operation. Should the control
circuit detect a fault in the obstruction sensing system, the motor shall not
be allowed to start.
F. Technical Features
9. Anti-Tailgate feature
PART 3 - EXECUTION
3.01 INSTALLATION
B. Swing gate operator shall only be pad mounted, as required. Slide gate operator
shall either be pad or post mounted, as required.
1. Pad mount: Mounted directly to a concrete pad, firmly secured, plumb and
level.
2. Post mount: Mounting posts shall be welded to base plate and mounted in
concrete, firmly secured, plumb and level.
C. Wiring shall be uniform and in accordance with national electric codes and
manufacturer’s instructions.
E. All cable runs in all junction boxes shall be tagged and identified.
A. System shall be completely tested to assure that all components and accessories
are hooked-up and in working order.
A. Contractor shall provide owner with (2) copies of standard factory prepared
operation, installation and maintenance manuals. Manuals shall include typical
wiring diagrams.
B. Contractor shall provide owner with (2) copies of any risers, layouts, and special
wiring diagrams showing any changes to standard drawings, if required on project.
3.06 MAINTENANCE
4.01 MEASUREMENT
A. Automated vehicular swing gate operator system will be measured by the unit or
fraction thereof furnished and completed in accordance with the Contract
Documents and as measured by the Engineer. The quantities as contained on the
Schedule of Quantities and Prices, or approved schedule of values, as applicable,
as derived from the Plans will be used as the basis for this measurement.
B. Swing Gates will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
C. Automated vehicular swing gate operator system shall consist of automatic exit
gate detectors, safety/reverse loop detectors, swing gate operators, underground
conduits and cables, power conduit and line, communications conduit and line, fire
department key access box and other required hardware and fittings, as shown on
the Contract Documents.
D. Quantities of swing gates will be determined from actual count. When more than
one swing gate is placed in an opening, each single unit placed will be counted as
a swing gate. A swing gate unit complete shall include one gate with necessary
fittings, hardware and gate posts with braces.
4.02 PAYMENT
B. Swing Gates furnished and completed in accordance with the Contract Documents
will be paid for at the Contract Unit Price, as listed on the Schedule of Quantities
and Prices. This price shall include full compensation for furnishing all labor,
Materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
D. Full compensation for clearing the line of the swing gate and disposing of the
material, excavating high points in the existing ground, excavating and backfilling
holes, disposing of surplus excavated material, and furnishing and placing
concrete footings and connecting gate to structures shall be considered as
included as listed on the Schedule of Quantities and Prices.
END OF SECTION 32 31 32
PART 1 - GENERAL
1.01 DESCRIPTION
A. Work involves furnishing all labor, materials and equipment necessary and
incidental to constructing gravity block retaining walls to the limits and at the
locations shown on the Contract Drawings and as modified by the Engineer. This
work consists of furnishing and constructing gravity block retaining walls of
prefabricated modular units at locations shown or as directed by the engineer, and
in close conformity to the lines, grades, and dimensions shown or established.
3. Section 31 20 00 - Earthwork
5. Section 33 46 00 – Underdrains
1.02 SUBMITTALS
A. Shop drawing showing wall materials and construction details as provided by the
supplier of the wall system. Drawings are to be certified by a qualified Engineer
licensed in the State of California, and shall be suitable for obtaining City permits,
as necessary.
B. Contractor shall prepare and submit a wall layout drawing that depicts the wall
layout and section developed with input from manufacturer recommendation.
PART 2 - PRODUCTS
2.01 MATERIALS
B. Blocks are to be standard grade, gray color with smooth face finish, unless noted
otherwise.
C. Blocks shall be sound and free of cracks or other defects that would interfere with
the proper placement of the block or significantly impair construction of the wall.
D. Block face exposed to view shall be free of chips, cracks or other imperfections
when viewed from a distance of 10 feet under diffused light.
E. Tolerance - Molded dimensions are not to differ more than 1/4 inch from the
manufacturer’s published dimensions, except height, which is not to differ more
than 1/8 inch.
A. Contractor shall check all materials upon delivery to assure that the proper type,
grade, color, and certification have been received.
B. Contractor shall protect all materials from damage due to jobsite conditions in
accordance with manufacturer’s recommendations.
PART 3 - EXECUTION
3.01 PREPARATION
A. Preparation
1. Place geotextile fabric over the full width and sides of the zone of unsuitable
subgrade over excavation. Geotextile shall be laid smooth without wrinkles
or folds in accordance with the manufacturer’s directions. Joints or overlaps
are not allowed along the width of the excavation. Adjacent rolls of
geotextile shall have a minimum overlap of 40 inches in the longitudinal
direction. There shall be no wheeled or tracked equipment permitted on the
unprotected geotextile fabric.
3. The top of the backfill shall be shaped to a slope to match the base of the
lowest block. Each block shall be placed with full contact with the
compacted base at the angle indicated on the approved submittal.
2. Place the first course of blocks on top of and in full contact with the
prepared base pad surface.
C. Install drain pipe filter fabric and pervious rock in accordance with the plans and
Section 33 46 00.
4.01 MEASUREMENT
A. Gravity Block Retaining Wall will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the plans will be used as the basis for this measurement.
C. Perforated underdrain, filter fabric, permeable rock, subballast and fence are not
included in payment for gravity block retaining wall.
4.02 PAYMENT
A. Gravity Block Retaining Wall furnished and completed in accordance with the
Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall be full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals necessary for Gravity Block Retaining Wall described by the Contract
Documents.
END OF SECTION 32 32 16
PART 1 - GENERAL
1.01 SUMMARY
This work shall consist of furnishing materials and placement of mechanically stabilized
earth walls constructed in accordance with these specifications and in reasonably
conformity with the lines, grades, design, and dimensions shown on the plans or otherwise
established, including gutters and cable railing and/or chain link fencing.
The mechanically stabilized earth wall shall consist of a leveling pad, concrete facing
panels, and soil reinforcement elements mechanically connected to each facing panel.
Soil reinforcement shall have sufficient length, strength, and frictional resistance as
required by the design outlined in these specifications.
A. Section Includes:
2. Reinforcement
3. Joint Material
4. Galvanizing
5. Inspection Elements
6. Soil Reinforcement
7. Drainage aggregate
8. Reinforced Backfill
9. Drainage System
4. Section 31 20 00 - Earthwork
1.02 REFERENCES
A. Comply with local, State, and Federal codes, regulations, specifications, standards
and recommended practices.
5. T-24 Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
1. C140 Standard Test Methods for Sampling and Testing Concrete Masonry
Units and Related Units
4. D448 Standard Classification for Sizes of Aggregate for Road and Bridge
Construction
6. D1556 Standard Test Method for Density and Unit Weight of Soil In Place
by the Sand Cone Method
10. D3034 Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC)
Sewer pipe and Fittings
11. D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity
Index of Soils
12. D4491 Standard Test Method for Water Permeability of Geotextiles by the
Permittivity Method
13. D4595 Standard Test Method for Tensile Properties of Geotextiles by the
Wide-Width Strip Method
16. D5262 Standard Test Method for Evaluating the Unconfined Tension
Creep Behavior of Geosynthetics
17. D5321 Standard Test Method for Determining the Coefficient of Soil and
Geosynthetic or Geosynthetic and Geosynthetic Friction by the Direct
Shear Method
23. G51 Standard Test Method for Measuring pH of Soil for Use in Corrosion
Testing
25. A82/A82M Standard Specification for Steel Wire, Plain, for Concrete
Reinforcement
29. A370 Standard Test Methods and Definitions for Mechanical Testing of
Steel Products
1. Elias, V., Christopher, B., and Berg, R., “Mechanically Stabilized Earth
Walls and Reinforced Soil Slopes Design and Construction Guidelines”,
Federal Highway Administration Report No. FHWA-NHI-00-043, March
2001.
1.03 DEFINITIONS
B. Reinforced Backfill: Soil which is used as fill behind the MSE unit, and within the
reinforced soil mass (if applicable).
C. Drainage Aggregate: Material used (if applicable) within, between, and directly
behind the concrete retaining wall units.
D. Geotextile Filter: Material used for separation and filtration of dissimilar soil types.
E. Foundation Soil: Soil mass supporting the leveling pad and reinforced soil zone of
the retaining wall system.
1.04 SUBMITTALS
B. Design drawings shall be 11" x 17" in size, and each drawing and calculation sheet
shall include the State assigned designations for the contract number, bridge
number, full name of the structure as shown on the contract plans, and District-
County-Route-Post Mile. The design firm's name, address, and phone number
shall be shown on the working drawings. Each sheet shall be numbered in the
lower right hand corner and shall contain a blank space in the upper right hand
corner for future contract sheet numbers.
C. The design drawing shall include all details, dimensions, quantities and cross-
sections necessary to construct the wall and shall include but shall not be limited
to the following:
D. An elevation view for each wall shall include the top of wall elevation at all
horizontal and vertical break points and at least every 50 feet along the face of
wall, the elevation of all steps in the leveling pads, the designation as to the type
of panel, the length of soil reinforcing elements, the distance along the face of the
wall to where changes in length of the soil reinforcing elements occur; and an
indication of the final ground line and maximum calculated bearing pressures.
H. All panel details shall show all dimensions necessary to construct the element, all
reinforcing steel in the element, and the location of soil reinforcing connection
devices embedded in the panels
K. The details for diverting soil reinforcements around obstructions such as piles,
catch basins and other utilities.
L. The details for connections between the concrete panel and the reinforcements.
M. The Contractor shall verify the existing ground elevations at the site before
preparing the working drawings. The working drawings shall contain all
information required for the proper construction of the system at each location
including existing ground line at face of wall as verified at the site and any required
revisions or additions to drainage systems or other facilities. The working drawings
shall include "General Notes" that contain design parameters, material notes, and
wall construction procedures and shall be accompanied with calculations. The
working drawings and calculations shall be stamped and signed by an engineer
who is registered as a Civil Engineer in the State of California. The Contractor
shall allow the Engineer 30 days to review the drawings after a complete set has
been received.
N. Unless otherwise specified, at the completion of each structure for which working
drawings were submitted and if the work detailed in these working drawings is
permanent, the Contractor shall submit to the Engineer one set of corrected as-
built prints 11" x 17" in size and on 20-pound (minimum) bond paper, showing as-
built conditions. As-built drawings that are common to more than one structure
shall be submitted for each structure.
O. Due to the nature of MSE Retaining Wall Systems, contractors shall provide a
system specific submittal package to the Civil Engineer at least thirty (30) days
prior to construction for approval. Incomplete submittal packages will not be
reviewed.
Submit the following at least thirty (30) days prior to construction for approval:
1. Product Data
c. Notarized letter from the MSE manufacturer stating that the units
supplied for this project are manufactured in complete compliance
with Section 2.01 of this specification. The letter shall state that the
MSE units shown in the attached test reports are representative
samples of the plants normal mix design and regular production
runs.
2. Test Reports:
a. Shop Drawings: For initial review, Five (5) sets of the retaining wall
system design, including wall elevation views, geosynthetic
reinforcement layout, pertinent details, and drainage provisions. A
registered professional engineer licensed in the State of California
shall sign and certify that the shop drawings are designed in
accordance with the project civil plans and specifications. After
review, between six (6) to twelve (12) sets of the retaining wall
system design, including wall elevation views, soil reinforcement
layout, pertinent details, and drainage provisions shall be submitted
for final approval and use during construction. A registered
professional engineer licensed in the State of California shall sign
and certify that the shop drawings are designed in accordance with
the project civil plans and specifications.
A. Designs for MSE’s using extensible soil reinforcement shall be prepared according
to design methodology presented in the SCRRA Design Criteria Manual. Design
submittals not meeting this design criteria or technical/administrative criteria as
specified will be rejected in their entirety until complete compliance is achieved.
The Authority reserves all rights in determining compliance for plan approval and
may reject any submittals.
B. Design of the MSE shall be based on the soil parameters as determined during the
geotechnical investigation as provided in the Contract Documents.
C. The Design Engineer of Record shall be responsible for selecting and specifying
reinforced fill material. The General Contractor is responsible for ensuring and
documenting the reinforced fill meets the specified parameters for both strength
and compaction. Compacted retained soil shall meet the minimum requirements
specified.
4. 2.0 against panel connection pullout or rupture, and 1.5 against a panel
connection deformation of 0.5 inch under the maximum allowable
reinforcement tension. (i.e. the resulting deformation should not exceed
0.5 inch at 1.5 times the design load).
A. Concrete Retaining Wall Units and Accessories: Deliver, store, and handle
materials in accordance with manufacturer's recommendations, in such a manner
as to prevent damage. Check the materials upon delivery to assure that proper
material has been received. Store above ground on wood pallets or blocking.
Remove and replace damaged or otherwise unsuitable material, when so
determined, from the site.
B. Exposed faces of concrete wall units shall be free of chips, cracks, stains, and
other imperfections detracting from their appearance, when viewed from a distance
of 10 feet.
C. Prevent mud, wet cement, adhesives and similar materials that may harm
appearance of units, from coming in contact with system components.
D. Panels shall be stored and shipped in stacks, front face down. Firm blocking, of
sufficient thickness to prevent the attachment devices from contacting the panel
above, shall be located immediately adjacent to the attachment devices. Lifting
inserts shall be installed on the top edge of the precast panels to permit lifting at
the project site. Reinforcement connection inserts (tie strips or loop inserts) shall
not be used for lifting or handling the panels.
PART 2 - PRODUCTS
2.01 MATERIALS
4. The panels shall be cast face down in level forms supported on a flat
working surface. Guides shall be used to locate and support attachment
devices set in the back face of the panel. The concrete in each panel unit
shall be placed without interruption and shall be consolidated by the use of
an approved vibrator, supplemented by such hand tamping as may be
necessary to force the concrete into the corners of the forms and to prevent
the formation of stone pockets or cleavage planes. Clear form oil or release
agent shall be used throughout the casting operation.
5. The units shall be cured for a sufficient length of time so that the concrete
will develop the specified compressive strength. Any production lot which
does not conform to the strength requirements shall be rejected
6. The forms shall remain in place until they can be removed without damage
to the unit.
8. All units shall be manufactured within the following tolerances with respect
to the dimensions shown on the shop drawings.
10. Precast panels shall be accepted for use in wall construction provided the
concrete strength meets or exceeds the minimum compressive strength
requirement, the soil reinforcement connection devices and the panel
dimensions are within tolerances and any chipping, cracks, honeycomb or
other defects are within acceptable standards for precast concrete as
determined by the Engineer.
11. It is recognized that certain cracks and surface defects are not detrimental
to the structural integrity of the panel if properly repaired. The Engineer
shall determine the need for and proper method of such repair. All repairs
shall be approved by the Engineer prior to acceptance of the panel for use
in wall construction.
12. The date of manufacture, the production lot number, and the piece-mark
shall be clearly marked on the side of each panel.
13. The concrete leveling pads for the Mechanically Stabilized Embankment
(MSE) system shall conform to the provisions in the Caltrans Standard
Specifications, Section 90-10, "Minor Concrete."
B. Reinforcement
C. Joint Material
1. Bearing Pads
2. Joint Cover
D. Galvanizing
E. Inspection Elements
F. Soil Reinforcement
1. Soil reinforcement shall conform to the details shown on the contract plans,
the approved working drawings, the preapproved proprietary system
details, and these special provisions.
2. W11 and W20 steel wire shall conform to the requirements in ASTM
Designation: A 82/A 82M. The welded wire mat shall conform to the
requirements in ASTM Designation: A 185/A 185M. D11 and D20
deformed steel wire may be substituted for W11 and W20 steel wire,
respectively. The welded wire mat utilizing deformed steel wire shall
conform to the requirements in ASTM Designation: A 496/A 496M and
ASTM Designation: A 497/A 497M.
4. The coupler at the wire mat connection shall be a seamless steel sleeve.
The coupler shall be applied over the button-head wires and swaged by
means of a hydraulic press. The coupler shall develop the minimum tensile
strength of the wire without exceeding a total slip of the wires of 3/16 inch.
6. Prior to the start of wall construction, the Contractor shall furnish test results
to the Engineer from tension and slip tests conducted on 6 proposed
button-head wire and coupler connections. Failure of any of the proposed
button-head wire and coupler connector samples to meet the slip and
tensile strength requirements herein shall require the connection be
redesigned by the Contractor.
8. During wall construction, the Contractor shall furnish test results to the
Engineer from tension and slip testing of 4 samples of production button-
head wire and coupler connections for each lot of 500 individual mat wire
connections incorporated into the work. Production testing shall consist of
testing each of the 4 sample connections for both slip and tensile
requirements herein. If 2 or more of the production samples fail to meet
slip or tensile test requirements, the entire lot represented by these
samples shall be rejected. If one of the production samples fails to meet
slip or tensile test requirements, an additional 4 samples shall be tested.
Should any of the additional samples fail to meet the slip or tensile
requirements, the entire lot represented by these samples shall be rejected.
9. Splicing of the welded wire mat along its length shall be by mechanical
coupler that shall develop the minimum tensile strength of the wire. The
mechanical coupler shall be approved by the Engineer.
10. Geogrid soil reinforcement roll identification, storage, and handling shall be
in accordance with ASTM Designation: D 4873, and as specified in the
preapproved proprietary details. The geogrid shall be shipped and stored
such that the material is not placed directly on the ground. The geogrid
shall be covered and protected at all times during shipment and storage
such that it is fully protected from UV radiation including sunlight, site
construction damage, precipitation, chemicals, flames including welding
sparks, temperatures less than 20 F or greater than 140 F, or other
conditions that may damage the physical property values of the geogrid.
The Contractor shall prevent foreign materials from coming into contact
with or affixing to the geogrid.
G. Reinforced Backfill:
1. Excavation and backfill shall conform to the details shown on the plans, the
provisions in Section 31 20 00.
2. Structure backfill for earth retaining structures with soil reinforcement shall
be free of organic material and debris and substantially free of shale or
other soft materials of poor durability. Structure backfill shall not contain
slag aggregate or recycled materials such as glass, shredded tires,
portland cement concrete rubble, asphaltic concrete rubble, or other
unsuitable material as determined by the Engineer.
d. Draining System
3. Structure backfill for earth retaining structures with soil reinforcement other
than geosynthetic shall conform to the following requirements or the
requirements of the proprietary wall system, if more restrictive:
Gradation Requirements
Sieve Size Percentage California Test
Passing
6" 100 202
3" 78-100 202
No. 4 ---- 202
No. 30 0-60 202
No. 200 0-15 202
Property Requirements
Test Requirement California Test
Sand Equivalent 12 minimum 217
Plasticity Index 6 maximum 204
Minimum 2000 ohm-cm 643
Resistivity
Chlorides < 250 ppm 422
Sulfates < 500 ppm 417
pH 5.5 to 10.0 643
Gradation Requirements
Sieve Size Percentage California Test
Passing
2" 100 202
No. 4 50-80 202
No. 40 0-30 202
No. 200 0-15 202
Property Requirements
Test Requirement California Test
Sand Equivalent 30 minimum 217
Plasticity Index 6 maximum 204
Durability Index 35 minimum 229
pH 4.5 to 9.0 643
5. Permeable material shall be used for the portion of the structure backfill for
earth retaining structures with soil reinforcement within the limits shown on
the plans. Permeable material shall be Class 1, Type B, conforming to the
provisions in the Caltrans Standard Specification, Section 68-1.025,
"Permeable Material."
Property Requirements
Test Requirement California Test
Minimum 2000 ohm-cm 643
Resistivity
Chlorides < 250 ppm 422
Sulfates < 500 ppm 417
pH 5.5 to 10.0 643
Property Requirements
Test Requirement California Test
pH 4.5 to 9.0 643
8. Water used for earthwork or dust control within 500 feet of earth retaining
structures with metallic soil reinforcement shall conform to the provisions
for water in the Caltrans Standard Specifications, Section 90-2.03, "Water."
9. The drainage system shall conform to the details shown on the plans and
these special provisions.
10. Corrugated steel pipe shall conform to the provisions in the Caltrans
Standard Specifications, Section 66, "Corrugated Metal Pipe.”
11. Perforated steel pipe underdrains and underdrain outlets and risers shall
conform to the provisions in the Caltrans Standard Specifications, Section
68-1, "Underdrains,"
12. The class of rock used for rock slope protection at drain pipe outlets shall
be No. 3 Backing and shall conform to the provisions in the Caltrans
Standard Specifications, Section 72-2, "Rock Slope Protection.”
13. Filter fabric shall conform to the provisions in the Caltrans Standard
Specifications, Section 88-1.02, "Filtration." Filter fabric shall be Class A.
14. Adhesive for bonding filter fabric to concrete panels shall be commercial
grade.
H. Miscellaneous
1. Resin bonded cork for horizontal joints shall conform to the requirements
in ASTM Designation: D 1752, Type II, with a compressive load of not less
than 100 psi.
2. Pipe for the pipe pin shall conform to the requirements in ASTM
Designation: A 53/A 53M, Standard weight, except the amount of the zinc
coating per square foot of actual surface shall average not less than 2.0
ounces and no individual specimen shall be less than 1.8 ounces.
PART 3 - EXECUTION
Earth retaining structures shall be constructed to the lines, grades, and details shown on
the plans, and shall conform to these special provisions.
3.01 EARTHWORK
A. The foundation for the structure shall be graded level for a width equal to the length
of soil reinforcement elements plus 12 inches or as shown on the contract plans.
The foundation material shall be compacted to a relative compaction of not less
than 95 percent. The Engineer shall approve the compacted foundation area prior
to commencement of wall construction.
C. Structure backfill material shall be placed and compacted simultaneously with the
erection of the facing panels. Placement and compaction shall be accomplished
without distortion of the soil reinforcement or displacement of facing panels.
Structure backfill at the front of the wall shall be completed prior to backfilling more
than 15 feet above the bottom of the lowermost face element.
D. Vertical and horizontal alignment tolerances of panels shall not exceed 3/4 inch
when measured along a 10-foot straightedge. The maximum allowable offset in
any panel joint shall not exceed 3/4 inch.
E. Structure backfill for earth retaining structures with soil reinforcement shall be
compacted to a relative compaction of not less than 95 percent.
G. Soil reinforcement shall be tensioned in the direction perpendicular to the wall face
with enough force to remove any slack in the connection or in the soil reinforcement
itself. Soil reinforcement shall be secured in place to prevent movement during
placement of additional soil reinforcement and structure backfill until the initial lift
of structure backfill is compacted.
I. Soil reinforcement shall be covered with structure backfill during the same work
shift that it is placed.
J. Placement and compaction of structure backfill shall begin one foot from the back
face of wall panels and progress towards the free end of the soil reinforcement.
Compaction equipment shall be operated parallel to the wall facing. The remaining
width of backfill behind the wall panels shall be placed and compacted after soil
reinforcement has been covered to a depth of 6 inches.
K. Sheepsfoot or grid-type rollers shall not be used for compacting material within the
limits of the soil reinforcement. Hand-held or hand-guided compacting equipment
shall be used to compact structure backfill material within 3 feet of the facing
panels.
M. Structure backfill material for earth retaining structures with geogrid soil
reinforcement shall be placed in lifts not to exceed 6 inches where hand-operated
compacting equipment is used and 8 inches where heavy compaction equipment
is used.
N. At each level of the soil reinforcement the structure backfill shall be constructed to
a plane 2 inches above the elevation of the soil reinforcement connection and shall
start 3 feet from the back of the face panel and extend for at least the remaining
length of soil reinforcement. This grading shall be complete before placing the
next layer of soil reinforcement.
O. Permeable material and filter fabric shall be placed along with structure backfill as
shown on the plans. Permeable material shall be placed in layers not exceeding
2 feet in thickness. Compaction of the permeable material for the drainage system
outside the limits of the soil reinforcement is not required, and equipment shall not
be operated directly on the permeable material or filter fabric. If a sloped layer of
permeable material is placed to facilitate the work or to satisfy safety
considerations, the vertical limits of permeable material shall remain unchanged
and the thickness of the layer of permeable material shall be measured normal to
the slope.
P. The Contractor shall grade the reinforced backfill to rapidly drain away from the
wall face at the end of each work shift. Berms or ditches shall be provided to direct
runoff away from the wall site. The Contractor shall not allow surface runoff from
adjacent areas to enter the wall construction site.
A. Filter fabric shall be placed at the locations and in conformance with the details
shown on the plans and these special provisions.
B. Immediately prior to placing filter fabric, the subgrade to receive the filter fabric
shall conform to the compaction and elevation tolerance specified for the material
involved and shall be free of loose or extraneous material and sharp objects that
may damage the filter fabric during installation.
C. Concrete panel surfaces to receive filter fabric shall be dry and thoroughly cleaned
of dust and deleterious materials.
D. Filter fabric shall be handled and placed in conformance with the manufacturer's
recommendations.
3.03 CONCRETE
A. Concrete for the leveling pads shall be placed at least 24 hours prior to erecting
face panels.
E. The top of face panels, assuming no leveling pad settlement, shall be covered by
the coping lip or concrete barrier slab lip at a minimum of 9 inches.
F. The top level of soil reinforcement shall be placed parallel to the top of the concrete
panel at a distance below the top of the wall as shown on the plans. The top level
of soil reinforcement shall also be (1) placed a minimum of 3 inches below the
bottom of the barrier slab lip or the bottom of the concrete gutter behind coping
and (2) placed a minimum of 5 inches below the top edge of the concrete panel.
4.01 MEASUREMENT
A. MSE Retaining Walls will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. MSE Retaining Walls furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. The contract price paid for MSE Retaining Walls at each location shown on the
plans shall include earthwork, leveling pad, coping, bearing pads, and drainage
systems, Caltrans concrete gutters, handrails, complete in place, as shown on the
plans, as specified in the Standard Specifications and these special provisions,
and as directed by the Engineer.
C. Full compensation for furnishing and testing sample mechanical connectors shall
be considered as included in the contract price paid per square foot for earth
retaining structure, and no separate payment will be made.
D. Full compensation for revisions to the drainage system, or other facilities made
necessary by the use of an alternative earth retaining system shall be considered
as included in the contract price paid per square foot for earth retaining structure,
and no separate payment will be made.
END OF SECTION 32 32 20
IRRIGATION SYSTEM
PART 1 - GENERAL
1.01 SUMMARY
A. The Contractor shall provide all work necessary to design, install and make
functional in place, all irrigation systems shown on the Submittal Drawings and/or
specified herein.
3. Protect all existing utilities and repair any damage to existing utilities with
matching new materials, at no increase in contract price.
5. Clean-up.
6. Final Inspection.
B. Related Specification Sections include but are not necessarily limited to:
2. Section 32 90 00 – Landscaping
1.02 SUBMITTALS
A. Before proceeding with any work, the Contractor shall carefully check and verify
all dimensions. Spacing of sprinkler heads and locations of valves and backflow
preventer shall be as indicated on the Contractor submittal.
B. Grading: Before starting work on the irrigation system, the Contractor shall inspect
the site and check all grades to satisfy that the work may proceed safely.
C. Water Supply: The sources of water supply shall be from the potable water
pipeline shown on the Submittal Drawings. Contractor to verify existing static
pressure as indicated on the plans prior to beginning irrigation construction.
Contractor to notify Engineer immediately should there be any discrepancy
between the required pressure and the actual pressure on site.
D. Permits and Fees: The Contractor shall apply for all necessary permits required
in the pursuit of his work as required by governing codes.
2. The Contractor shall dimension from two (2) permanent points of reference,
building corners, sidewalk, or road intersections, etc., the location of the
following items:
c. Gate valves
3. On or before the date of the final inspection, the Contractor shall deliver the
corrected and completed sepias to the Engineer. Delivery of the sepias will
not relieve the Contractor of the responsibility of furnishing required
information that may be omitted from the prints.
F. Controller Charts:
3. The chart shall show the area controlled by the automatic controller and
shall be the maximum size which the controller door will allow.
5. The chart shall be a black line or blue line print, and a different color shall
be used to indicate the area of coverage for each station.
1. Prepare and deliver to the Engineer within ten calendar days prior to
completion of construction, two hard cover binders with three rings
containing the following information.
c. Guarantee statement.
I. Equipment to be Furnished:
c. Two (2) quick coupler keys and matching hose swivels for each type
of quick coupling valve installed.
PART 2 - PRODUCTS
2.01 GENERAL
A. All material shall be new stock and best grade of its kind. It shall be as specified
unless otherwise specifically approved, in writing, by the Engineer. Materials not
named shall be subject to approval or rejection by the Engineer.
2.02 PIPING
A. Plastic Pipe:
1. Plastic pipe and fittings shall be virgin hi-impact poly-vinyl chloride Type 2
conforming to commercial standards of National Sanitation foundation.
2. All plastic pipe shall be continuously and permanently marked with the
following information: Manufacturer's name, kind of pipe, material size, IPS,
NSF approval and schedule and type.
B. Main Lines:
1. All piping and fittings under constant pressure between backflow preventer
and control valves, quick couplers and hose bibs shall be as indicated per
Approved Drawings.
2. All main line piping and fittings under tracks and up to 10 feet beyond
centerline of tracks shall be PVC Schedule 80.
C. Lateral Lines:
1. All piping and fittings under intermittent pressure, down stream of control
valves shall be rigid PVC 1120, Schedule 40, Type I, Grade I or II and shall
meet ASTM-D 1785-86 standards.
2.03 FITTINGS
1. Where indicated on the Submittal Drawings, use red brass screwed pipe
conforming to Federal Specification #WW-P-351
2.05 VALVES
B. Ball Valves:
2. Color code each wire with a different color for each valve station. Common
to be black.
A. Ball Valve: Use 10"x10-1/4" round box for all gate valves, Carson Industries #910-
12B with green bolt down cover or approved equal. Extension sleeve shall be
PVC-6" minimum size.
B. Remote Control Valve: Use 9-1/2"x16"x11" rectangular box for all electrical control
valves, Carson Industries 1419-12B with green bolt down cover or approved equal.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Excavations:
d. Control wires - Below main lines when installed with main line pipe,
18" minimum. Run in a Schedule 40 PVC pipe sleeve under paving.
(May share pipe sleeve with main line pipe.)
2. Wherever possible, the main and lateral line may occupy the same trench.
Main and lateral lines in the same trench must be spaced a minimum of 6"
horizontally apart.
B. Trenching:
C. Cathodic Protection:
2. Due to the nature of plastic pipe and fittings, the Contractor shall exercise
care in handling, loading, unloading and storage to avoid damage. The
pipe and fittings shall be stored under cover, and shall be transported in
vehicle with a bed long enough to allow the length of pipe to lie flat, so as
not be subject to undue bending or concentrated external load at any point.
Any pipe that has been dented or damaged shall be discarded until such
damage has been cut and pipe is rejoined with a coupling.
3. The bottom of the trench in which plastic pipe is installed shall be free from
rocks or other sharp edged objects.
4. Welded joint shall be given at least 15 minutes setup curing time before
moving or handling. Pipe shall be partially center loaded to prevent arching
and slipping under pressure. No water shall be permitted in pipe until a
period of at least 24 hours has elapsed for solvent weld setting and curing.
6. Long runs of PVC pipe shall be snaked in the trench to allow for contraction.
E. Backflow Preventer
F. Automatic Controller:
2. Electrical wiring shall be installed according to local code. The cost of this
electrical connection shall be a part of this Contract.
G. Controller Wire:
1. The control wire shall be buried alongside other pipe in trenches a minimum
of 18" deep and bundled and taped at 10' on center.
3. Control wire splices and connections shall be made with Pen Tite
connectors or approved equal.
I. Backfill of Trenches:
1. Trenches shall be backfilled with excavated dirt after pipe has been
installed. Backfill shall be placed in layers; the thickness of the layer shall
depend on the nature of the material and the method of compaction used.
2. Compaction shall be such that there will be no settling within the one-year
guarantee period. The Contractor shall not place detrimental subsoil in the
top 5" of backfill.
2. Test all pressure lines under hydrostatic pressure of 150 pounds per
square inch, and prove watertight.
4. All piping under paved areas shall be tested under hydrostatic pressure of
150 pounds per square inch, and proved watertight, prior to paving.
5. Sustain pressure in lines for not less than two (2) hours. If leaks develop,
replace joints and repeat test until entire system is proven watertight.
6. All hydrostatic tests shall be made only in the presence of the Engineer.
No pipe shall be backfilled until it has been inspected, tested and approved
in writing.
9. Upon completion of each phase of work, entire system shall be tested and
adjusted to meet site requirements.
K. Guarantee:
2. Should any trouble develop within the specified guarantee period which in
the opinion of the Engineer, is due to inferior or faulty material and/or
workmanship, the trouble shall be corrected, without delay, by the
Contractor to the satisfaction of, and at no expense to the Engineer, as part
of this Contract.
3. Any and all damage to rain water drains, water supply lines, gas lines
and/or other service lines shall be repaired and made good by the
Contractor at no extra cost to the Engineer.
4.01 MEASUREMENT
A. Irrigation System will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
END OF SECTION 32 80 00
LANDSCAPING
PART 1 - GENERAL
1.01 SUMMARY
A. Work Include:
Furnish all labor, materials and equipment for installing landscape planting complete
as directed and indicated, including but not limited to the following:
1. Site Preparation
6. Disposal of surplus material, excess dirt and debris off-site, and site clean.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
A. Provide Landscaping design and shop drawings, products data and samples in
accordance with Section 01 33 00, Submittal Procedures.
2. Submit delivery slips for all soil amendments including but not limited to
fertilizer, organic amendments and top mulch.
A. Protection: Use all means necessary to protect the materials of this Section
before, during and after installation.
A. Guarantee plant material, including flatted materials, but less than 15-gallon size,
for a period of three months, and plant material 15-gallon size and over for a period
of one year from the date of final acceptance of the Project, this date to be
established by the inspection and written acceptance at the conclusion of the
maintenance period.
B. Replace any plant materials that die-back and lose their form and size as originally
specified, even though they have taken root and are growing after the die-back.
C. Within ten days of written notice by the Authority, remove and replace guaranteed
plant materials which have failed to meet the requirements of the guarantee. Make
replacements to the same specifications as required for the original plants and
guarantee as specified for the original guaranteed material.
PART 2 - PRODUCTS
2.01 TREES
A. General: Quality of all plants shall conform to the State of California Grading Code
of Nursery Stock #1 Grade, and full sized. They shall be vigorous, of normal
growth, free of disease, insects and latent defects.
Pruning shall not be done prior to delivery except by the specific written direction of
the Engineer.
Plants shall be subject to inspection and approval or rejection at place of growth and
on the project site at any time before or during progress of work for size, variety,
conditions, latent defects or injuries. Rejected plants shall be removed from the
project site immediately.
C. Tree Stakes: Shall be 2" diameter x 10' long new lodge pole pine treated with
copper napthenate.
D. Tie: Shall be as detailed per plan, three (3) per double tree stake.
PART 3 - EXECUTION
3.01 INSPECTION
C. Inspections and written approvals by the Engineer will be required for the following
landscape parts of the work:
3. When trees are spotted for planting, but before planting, holes are
excavated.
D. Contractor or his authorized representative shall be on the site at the time of each
inspection.
3.02 INSTALLATION
2. At time of planting, the top two inches (2") of all areas to be planted shall
be free of stones, stumps, roots or other deleterious matter one inch (1")_
in diameter or larger and shall be free from all wire, plaster or similar objects
that would be a hindrance to planting or maintenance.
3. Deliver the fertilizer to the site in sealed bags with the manufacturer's
analysis printed on or attached to each bag. Do not apply fertilizer until the
total quantity needed for the entire job has been delivered to the site,
recorded and accepted by the SCRRA.
C. Planting:
1. Protect plants from sun, wind and rain at all times before planting.
2. Do not plant trees until construction work in the area has been completed,
final grades established, the planting areas properly graded and prepared
as herein specified, and the work accepted by the Engineer.
3. Set plants so that when settled they bear the same relation to the finish
grade as they bore to the natural grade in the container before being
planted.
D. Trees:
1. Planting - Stake plant locations and obtain approval from the Engineer
before excavating pits, making necessary adjustments as directed.
3. Backfill - Shall be 6 parts rock free on site soil, 4 parts nitrolized wood
shaving, and 15 lbs. of Gro-Power per cu. yd. of mix.
5. Agriform 21-gram planting tablets shall be placed 6-8" deep at the side of
root ball at the following rates:
6. For planting, a hole two (2) times the diameter and 6" deeper than the root
ball shall be dug for each plant. All materials resulting from excavation of
plant holes, other than the existing topsoil, shall be disposed of at the
Contractor's expense. Backfill shall be placed in the bottom of each hole
to a growing depth at which the plant, when planted, will be 1" above normal
growing depth. Backfill is half-way up the root ball, when the hole shall be
watered sufficiently to settle the backfill around the root ball. More backfill
shall be firmed sufficiently to force air pockets from each hole.
3.03 MAINTENANCE
A. Apply water, weed, fertilize, care for plants and perform the following plant
establishment work:
B. Maintain the entire project for a minimum period of 90 days or until acceptance of
Contract, whichever is later, commencing from the time all items of irrigation and
landscaping work have been completed to the satisfaction of the Engineer. Start
of plant establishment work shall begin only after written review by the Engineer.
Periods which the site is not adequately maintained and the Contractor has been
notified in writing as such will not be counted as maintenance days and the
maintenance period will be extended for a matching number of days.
C. During the entire maintenance period, keep all plants and planted areas well
watered and weed free at all times. Remove weeds and undesirable grasses.
Care for the entire project so that a neat and clean condition will be presented at
all times to the satisfaction of the Engineer.
E. The Contractor may be relieved from maintenance work when the maintenance
period or plant establishment work has been completed to the satisfaction of the
Engineer.
3.04 CLEAN-UP
A. Upon completion of planting work and before final acceptance, remove material,
equipment and debris resulting from this work. Broom clean paved areas and
leave the site in a neat condition and acceptable to the Engineer.
4.01 MEASUREMENT
4.02 PAYMENT
END OF SECTION 32 90 00
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
3. Seeding.
B. Related Specification Sections include but are not necessarily limited to:
3. Section 31 20 00 - Earthwork.
1.02 REFERENCES
A. Erosion Control Standards: "Standards and Specifications for Soil Erosion and
Sediment Control in Developing Areas" by the United Sates Department of
Agriculture (USDA), Soil Conservation Service, College Park, Maryland.
A. Certifications:
PART 2 - PRODUCTS
2.01 MATERIALS
A. General:
B. Certificates:
1. Material test reports or certifications for all seed mixtures and products
intended to be purchased and used for the Project shall be furnished to the
Engineer for approval prior to commencing Work under this Specification.
D. Pipe Riser and Barrel: 16 gage corrugated metal pipe (CMP) of size indicated.
Coating and fabrication shall be in accordance with Section 33 42 00.
E. Stone for Stone Filter: 2 inches graded gravel or crushed stone in accordance with
Section 32 11 00.
F. Commercial Fertilizer:
1. Contractor must furnish evidence that clearance has been obtained from
the County Agricultural Commissioner, as required by law, before straw
obtained from outside the county in which it is to be used is delivered to the
site of the work.
H. Mulch Fiber shall be produced from natural or recycled (pulp) fiber, such as wood
chips or similar wood materials or from newsprint, chipboard, corrugated
cardboard or combination of the processed materials, and shall be free of synthetic
or plastic materials.
1. Fiber shall not contain more than 7 percent ash as determined by ASTM
D586.
2. Fiber shall have a water-holding capacity by weight of not less than 100
percent.
3. Fiber shall be of such character that the material will disperse into a uniform
slurry when mixed with water.
4. Fiber shall be colored to contrast with the area on which the fiber is to be
applied and shall not stain concrete or painted surfaces.
I. Grass Seed:
2. When not specified in the Plans, Coastal Sage Scrub Mix shall be used per
the following table:
Pounds/ Purity /
Botanical Name Common Name
Acre Germination
Artemisia California California Sage Brush 4 50/15
Encelia California Bush Sunflower 3 60/40
Eschscholzia California California Poppy 2 75/98
Lotus Scoparius Deerweed 8 60/90
Eriogonum fasciculatum California Buckwheat 8 65/10
Lasthenia glabrata Goldfields 2 85/90
Lupinus Succulentus Arroyo Lupine 4 85/90
Eriophyllum confertiflorum Golden Yarrow 3 60/30
Salvia apiana White Sage 4 50/70
Sisyrinchium bellum Blue-Eyed Grass 1 75/95
Diplacus longiflorus Monkey Flower 2 55/2
Salvia mellifera Black Sage 4 50/70
Stipa pulchra Purple Needlegrass 2 70/60
Bromus arizonicus Cucamonga Brome 5 95/80
Melica california California Melic 3 90/60
Slurry Mix
Fiber 2000
Organic Soil Stabilant
140
(Tackifier)
3. Seed (per seed type) shall be a minimum of 50 percent Pure Live Seed
(PLS) content. PLS content is defined as the product of 1) the percentage
of tested purity and 2) the percentage of tested germination of the specified
seed (PLS content - % purity x % germination = 50%) unless otherwise
stated. The Engineer may reduce the PLS content if the specified minimum
is not available.
4. All legumes shall be inoculated with viable bacteria compatible for use with
that species of seed. Contractor must furnish written statement of
inoculation. The application rate for seed shall be the weight exclusive of
inoculating Materials.
6. Signed copies of vendor’s statement for the seed mixture shall be supplied
the Engineer for approval prior to using the seed.
b. Place of Origin.
c. Strain.
J. Stabilizing Emulsion:
1. Organic Soil Stabilant shall be registered with and licensed by the State of
California, Department of Food and Agriculture, as an “auxiliary soil
chemical.”
2. Shall be a concentrated liquid chemical that forms a plastic film upon drying
and allows water and air to penetrate.
K. Water shall be free of substances harmful to growth. Provide water from a source
approved prior to use.
1. General:
a. Plans shall specify if the erosion control blanket will have seeds
mixed with material and the type and rate of seeds to be placed in
the mat.
2. Straw Mat/Blanket:
3. Jute Matting:
c. Furnished in rolled strips about 150 feet long, average width about
48 inches, plus or minus one (1) inch.
4. Excelsior Blanket:
c. Encasing material shall be free from cuts, tears, or weak places and
shall have a life-span greater than 6 months.
2. Coir Logs shall be 100 percent durable coconut (coir) fiber uniformly
compacted with an outer netting.
N. Topsoil:
O. Tolerances:
P. Silt Fence:
1. Posts:
1) Be at least 4 FT long.
2) Be made of steel.
e. Posts for a temporary reinforced silt fence must be at least six (6)
feet in length for a Type 1 installation and five (5) feet in length for
a Type 2 installation.
Value
Property Test Woven Nonwoven
Grab breaking load, 1-inch grip, lb
min, in each direction ASTM D 4632 120 120
3. Fasteners:
Q. Inlet Protection:
b. Gravel for gravel-filled bags must be from 3/8 to 3/4 inch DIA and
must be clean and free of clay balls, organic matter, and other
deleterious materials.
2. Fiber Rolls:
3. Check Dams:
PART 3 - EXECUTION
3.01 PREPARATION
4. Machine compact all berms, dikes and embankments for basins and traps.
6. Install wattles and coir logs where indicated or as Engineer directs, staking
as required by the Plans
B. After rough grading, sow or hydroseed temporary grass cover over all exposed
earth areas not draining into sediment basin or trap.
D. Provide necessary swales and dikes to direct all water towards and into sediment
basins and traps.
F. Excavate sediment out of basins and traps when capacity has been reduced by 50
percent.
G. Topsoil and Fine Grade Slopes and Swales or other project areas:
A. Verify rough grading, finish grading and compaction are complete and accepted
by Engineer.
B. Eliminate basins, dikes, traps, and other features that may cause ponding water.
C. Loosen top surface to a depth of 2 inches, removing all stones and debris over 2
inches in any dimension.
E. Provide finished surface free of stones, sticks and other material 1 inch or more in
any dimension.
F. Fine grade all remaining earth areas, loosen top surface as preparation for seeding
and mulching.
G. Spread and mix mulch and fertilizer in accordance with these Specifications or as
required in the plans during top surface preparation for seeding and mulching.
H. Do not seed until prepared topsoil has been approved by the Engineer
3.04 SEEDING
A. General:
B. Hydro Seeding:
2. Proportion and seed mix may be changed by the Engineer to meet field
conditions.
5. The seed shall be the last item added to the slurry. Slurry shall be applied
within 30 minutes after seed has been added.
6. The slurry planted areas shall be kept moist during the germination period,
but puddling shall be avoided.
D. Hand Methods:
1. Use where above methods are not practical as determined by the Engineer.
2. Method must show ability to spread seeds evenly at rates required by these
Specifications or the Plans in the areas other methods not practical.
A. Prior to seeding and until placing the blanket, the area to be covered shall be
relatively free of all rocks or clods over 1 inch in diameter and all sticks or other
foreign material that will prevent the close contact of the blanket with the soil. The
area shall be smooth and free of ruts or other depressions.
C. The straw mat/blanket shall be placed within 24 hours after seeding operations
have been completed.
1. The blanket shall be laid out flat, even, and smooth without stretching or
crimping the material.
2. The blanket shall be applied with the length running parallel to the flow of
water.
4. Staples shall be spaced not more than three feet apart in 3 rows for each
strip, with a row along each edge and one row alternately spaced in the
middle. All ends of the mesh shall be secured by staples spaced six inches
apart across the width.
5. Immediately after the straw mat/blanket has been placed and stapled, the
area covered shall be sprinkled and rolled with a light roller of sufficient
weight to press the blanket into the surface of the soil.
E. Silt Fence:
1. Construct a temporary silt fence with silt fence fabric, posts, and fasteners
assembled at the job site or with prefabricated silt fence.
2. If prefabricated silt fence is used, attach the fabric to the posts by inserting
the posts into the sewn pockets. If assembled at the job site:
a. Fasten the fabric to the posts with staples or nails if wood posts are
used.
b. Fasten the fabric to the posts with tie wires or locking plastic
fasteners if steel posts are used.
c. Space the fasteners not more than eight (8) inch apart.
3. Place temporary silt fence parallel with the slope contour. For any 50 feet
section of temporary silt fence, do not allow the base elevation of the fence
to vary by more than 1/3 of the height of the fence above the ground.
a. Place the bottom of the fabric in a six (6) inch deep trench.
b. Secure it with the posts placed on the downhill side of the fabric.
a. Join separate sections of the silt fence to form reaches not more
than 500 feet long. Each section must be a continuous run from
end-to-end or from an end to an opening, including joined panels.
b. Secure the end posts of each section by wrapping the tops of the
posts with at least 2 wraps of 16 gage tie wire.
6. You may install the silt fence by mechanically pushing the silt fence fabric
vertically into the soil. Mechanically installed fabric must not slip out of the
soil or allow sediment to pass under the fabric.
F. Inlet Protection:
2. For drainage inlet protection at drainage inlets in paved and unpaved areas:
3. If gravel-filled bags are used for Type 3A and Type 3B temporary drainage
inlet protection, place the gravel-filled bags end-to-end to eliminate gaps.
Stack the bags so that the upper row overlaps joints in the lower row.
Arrange the bags to create a spillway by removing 1 or more gravel-filled
bags from the upper layer.
4. Place fiber rolls over the erosion control blanket for Type 4A temporary
drainage inlet protection.
7. Install a sediment filter bag for Type 5 temporary drainage inlet protection
as follows:
G. Fiber Rolls:
1. Before installing fiber roll remove obstructions from the ground, including
rocks, clods, and debris greater than one (1) inch DIA.
2. Install fiber roll approximately parallel to the slope contour. For any 20 feet
section of fiber roll, prevent the fiber roll from varying more than five (5)
percent from level. Install fiber roll on slopes at the following spacing unless
shown otherwise:
a. Place in a furrow that is from two (2) to four (4) inch deep.
b. Fasten with wood stakes every 4 feet along the length of the fiber
roll.
c. Fasten the ends of the fiber roll by placing a stake 6 IN from the end
of the roll.
d. Drive the stakes into the soil so that the top of the stake is less than
two (2) inch above the top of the fiber roll.
b. Drive stakes into the soil until the notch is even with the top of the
fiber roll.
c. Lace the rope between stakes and over the fiber roll. Knot the rope
at each stake.
d. Tighten the fiber roll to the surface of the slope by driving the stakes
further into the soil.
5. Maintain fiber roll in a manner that provides sediment holding capacity and
reduces runoff velocities as follows:
a. Remove sediment from behind the fiber roll when sediment is 1/3
of fiber roll height above ground.
c. Repair or replace the fiber roll when they become split, torn, or
unraveled.
H. Check Dams:
a. Secure the fiber rolls with rope and notched wood stakes as shown.
b. Drive the stakes into the soil until the notch is even with the top of
the fiber roll.
c. Lace rope between the stakes and over the fiber roll. Knot the rope
at each stake.
d. Tighten by driving the stakes further into the soil and forcing the
fiber roll against the surface of the ditch or drainage line.
3.06 ACCEPTANCE
A. Upon completion of the soil erosion and sediment control obtain Engineer’s written
acceptance of the work.
B. Upon completion of the topsoil and finish grading, obtain Engineer’s written
acceptance of the work.
C. Upon completion of the seeding, obtain Engineer’s written acceptance of the work.
4.01 MEASUREMENT
A. Soil Erosion and Sediment Control will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
B. Topsoil and Finish Grading will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
C. Seeding will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
D. The required areas of soil erosion and sediment control topsoil and finish grading,
and seeding as measured by the Engineer and shown on the Contract Plans shall
be used for information purposes only.
4.02 PAYMENT
A. Soil Erosion and Sediment Control furnished and completed in accordance with
the Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
B. Topsoil and Finish Grading furnished and completed in accordance with the
Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
C. Seeding furnished and completed in accordance with the Contract Documents will
be paid for at the Contract Unit Price, as listed on the Schedule of Quantities and
Prices. This price shall include full compensation for furnishing all labor, Materials,
tools, equipment, supplies, supervision, and incidentals, and doing all work, as
shown on the Plans, and as specified in these Specifications, and as directed by
the Engineer.
D. Full compensation for temporarily placing topsoil along the top of the slopes and
later spreading the topsoil over the prepared slopes shall be considered as
included in the Contract price.
E. Full compensation for removing and disposing of rocks and debris from
embankments constructed as part of the work shall be considered as included in
the Contract prices and no additional compensation will be allowed therefore.
END OF SECTION 32 19 00
STEEL CASING
PART 1 - GENERAL
1.01 SUMMARY
A. The Work involves furnishing all labor, materials, transportation, and equipment
necessary and incidental to installing steel casing up to six (6) feet diameter.
B. Related Specification Sections include but are not necessarily limited to:
1. Section 31 20 00 - Earthwork.
4. Section 34 11 26 - Ballast.
5. Section 34 72 00 - Trackwork.
1.02 REFERENCES
1. The depth of cover from base of rail to top of casing shall be 5 feet – 6
inches minimum or equal to the outer diameter of the casing, whichever is
greater.
2. The depth of cover from the flow line of the right-of-way ditch to the top of
casing shall be at least four feet for non-flammable substances in the
carrier pipe and five feet for flammable or hazardous substances in the
carrier pipe.
3. Jacking and receiving pits shall be at least 25 feet clear from the nearest
track centerline.
1.04 SUBMITTALS
2) Water volume.
1. This plan shall identify methods to cut and remove rock, concrete or timber
encountered at the boring face and methods to temporarily bulkhead the
face.
PART 2 - PRODUCTS
A. The steel casing shall be new and conform to SCRRA Engineering Standard
ES5001 and ES5002.
B. Specified minimum yield strength (SMYS) of steel shall be at least 35,000 psi.
C. Casing under track shall be designed for Cooper E-80 loading in accordance with
AREMA.
PART 3 - EXECUTION
3.01 GENERAL
A. Casing and ancillary items shall be handled in such a manner as not to damage
the Material.
B. Casing shall not be dropped to or dragged over the ground, but shall be handled
with rolling slings on skids or with cranes.
3.03 EXCAVATION
A. Excavation for jacking and receiving pits shall be in accordance with Section 31 20
00 and Section 31 50 00.
A. The jacking and boring method consists of pushing the casing into the earth with
a boring auger rotating inside the casing, which removes the spoil.
B. The jacking and tunneling method consists of pushing the casing into the earth
with jacks and excavation being performed by worker(s) using handheld tools from
within the jacking shield at the head of the casing.
C. Neither Jacking and boring nor jacking and tunneling shall be used in sandy, loose,
or otherwise unstable soils or where boulders are anticipated.
E. The use of water or slurry under pressure (jetting) or puddling shall not be
permitted to facilitate boring, pushing, or jacking operations.
F. The annular space between the casing and the soil shall be grouted.
1. Such grout shall contain at least 8 sacks of cement per cubic yard of
material.
G. Should the operation be abandoned before completion, the annular space between
the casing and excavated soil shall be grouted as specified above.
2. Such grout shall contain at least 2 sacks of cement per cubic yard of
material.
H. The hole diameter resulting from bored or tunneled installations shall not exceed
the outside diameter of the casing by more than 1.5 inches for casings of less than
12 inches in outside diameter and by 2 inches for casings of greater than 12 inches
in outside diameter.
2. The Contractor is liable for all damage resulting from ground displacement.
3. Should the track displace, corrective action will be taken by SCRRA forces
or shall be taken by the Contractor as approved by the Authority.
4. SCRRA costs for such corrective action shall be deducted from the
payment due to the Contractor under this Contract.
L. For casings with drainage culvert carrier pipes, the annular space between the
casing and the carrier pipe shall be grouted.
1. Such grout shall contain at least 8 sacks of cement per cubic yard of
Material.
M. For casings with carrier pipes that are other than drain culvert pipes, the annular
space between the casing and carrier pipe at the casing ends shall be sealed with
a concrete bulkhead with a thickness equal to annular space or 6 IN whichever is
greater.
A. This method consists of utilizing specialized drilling equipment and boring a small
diameter pilot hole along the desired horizontal and vertical alignment, using a
mechanical cutting head with high-pressure bentonite slurry to remove the
cuttings.
1. Bore pits at either end of the Installation are not necessarily required with
this method.
2. The drill string is advanced with the bentonite slurry pumped through the
drill string to the cutting head and then forced back along the drill string,
carrying the cuttings back to the surface for removal.
3. After the cutting head reaches the far side of the crossing, it is removed
and a reamer (with a diameter wider than the cutting head) is attached to
the lead end of the drill string.
4. The casing is attached to the reamer and the casing is then pulled back
into its final position.
B. Methods that excavate the soil by means of jetting of fluid or slurry are not allowed.
E. Slurry use shall be kept to a minimum and shall only be used for head lubrication
or spoils return.
1. The Contractor must calculate anticipated slurry use and shall monitor
actual slurry use during the boring operation in order to determine the slurry
loss into the surrounding soil.
F. The bentonite slurry shall seal the annular space between the casing and the
excavated soil with a minimum return of 95 percent.
G. Bore stems or cutting tools that become immovable under the track shall be
abandoned in place.
H. Should the operation be abandoned before completion, the complete inside of the
casing shall be grouted.
1. Such grout shall contain at least 2 sacks of cement per cubic yard of
Material.
2. The Contractor is liable for all damage resulting from ground displacement.
3. Should the track displace, corrective action will be taken by SCRRA forces
or shall be taken by the Contractor as approved by the Authority.
4. The SCRRA costs for such corrective action shall be deducted from the
payment due to the Contractor under this contract.
A. Steel casing bulkhead as called out in the Contract Documents shall be installed
in locations as identified in the Contract Documents and as per the details as
shown in the Contract Documents.
4.01 MEASUREMENT
A. Steel casing will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Steel casing bulkhead is incidental to the steel casing work and no separate
measurement will be made.
4.02 PAYMENT
A. Steel casing furnished and completed in accordance with the Contract Documents
will be paid for at the Contract Unit Price, as listed on the Schedule of Quantities
and Prices. This price shall include full compensation for furnishing all labor,
Materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
END OF SECTION 33 05 23
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Culverts.
a. Headwalls
b. Flumes
c. End sections
a. Headwalls
c. Cleanouts
d. Connections
e. Risers
a. Concrete collars
c. Concrete Caps
B. Related Specification Sections include but are not necessarily limited to:
2. Section 31 20 00 - Earthwork.
1.02 REFERENCES
1. M274, Steel Sheet, Aluminum Coated (Type 2), for corrugated steel pipe.
1. A31, Standard Specifications for Steel, Rivets and Bars for Rivets,
Pressure Vessels.
3. A760, Corrugated Steel Pipe, Metallic Coated for Sewers and Drains.
6. B633, Coating.
10. C1784, Standard Specification for Polyvinyl Chloride (PVC) Plastic Pipe.
11. D2729, Standard Specification for Polyvinyl Chloride (PVC) Sewer Pipe
and Fittings.
12. D3350, Standard Specification for Polyethylene Plastics Pipe and Fittings
Material.
D. Standard Plans for Public Works Construction (SSPWC) “Green Book”, Current or
Latest Edition.
1.03 SUBMITTALS
A. General:
2. Schedules of work.
4. Details for culverts and drainage structures and joints including Shop
Drawings and installation procedures.
C. Certificates:
2. Certifications:
3. Test reports:
D. Miscellaneous Submittals:
A. The Contractor shall barricade open excavations and post with warning lights
those excavations occurring on property adjacent to or within public access areas
and along tracks in accordance with Section 31 50 00. Operate warning lights
during hours from dusk to dawn each day and as otherwise required. Warning
lights shall not shine into the eyes of locomotive engineers on oncoming trains.
B. The Contractor shall protect utilities, structures and facilities designated as protect
in place from damage caused by settlement, lateral movement, undermining,
washout, and other hazards created by excavation and backfill operations in
accordance with Section 31 50 00 and Division 01. Damage to utilities designed
to remain must be repaired by the Contractor to the satisfaction of the Authority in
accordance with these Specifications or replaced at no cost to the Authority.
A. The Contractor shall protect against erosion and uncontrolled run-off within and
adjacent to right-of-way in accordance with Division 01.
B. The Contractor shall obtain all permits for and legally dispose of all water from
water removal operations in accordance with Division 01.
1. Contractor shall maintain the construction site and those areas impacted
by construction in accordance with Division 01.
PART 2 - PRODUCTS
a. RAM-NEK.
b. BIDCO C-56.
c. Or equal.
2.02 MATERIALS
1. RCP shall not be used, unless approved by the Authority, when crossing
below tracks and within the typical track section with 2:1 side slopes. If
placed under the track, the pipe shall be able to withstand railroad loading.
2. Reinforced concrete culvert, storm drain and sewer pipe: RCP Joint
Sealer:
a. Rubber gasket: ASTM C361 when water tight joints indicated in the
Plans.
b. Joint sealing material per Article 2.01 above for other joints of
concrete pipe.
1. CMP and Structural Plate Pipe may be used in all culvert or storm drainage
applications.
2. CMP shall be either Class 1, annular rings with riveted seams or Class 2,
helical rings with lock seams or welded seams per the AREMA Manual
Chapter 1, Part 4, Section 4.3 Specifications for Prefabricated Corrugated
Steel Pipe and Pipe Arches for Culverts, Storm Drains, and Underdrains.
In addition to these requirements, CMP culverts shall meet the following:
2) CMP Class I culverts shall have all 14 gage pipe with at least
5/16 IN DIA rivets. CMP Class I culverts shall have all 12
gage and thicker pipe with at least 7/16” dia. rivets.
3. Sizes less than 1 foot diameter shall meet requirements of AASHTO M252,
Corrugated Polyethylene Drainage Pipe.
1. Smooth Steel Pipe may be used for all culvert or storm drainage
applications.
E. PVC Pipe:
1. PVC may be used for under drains and storm drainage applications. When
subjected to railroad live loading, Schedule 80 PVC pipe shall be used.
PART 3 - EXECUTION
3.01 PREPARATION
A. The site including the drainage facilities shall be prepared in accordance with
Section 31 11 00 and Section 31 11 50.
A. Pipe, fittings and supplementary items shall be handled in such a manner as not
to damage the Material. All dirt and trash shall be removed from the pipe prior to
installation. Damage to the pipe, pipe lining or coating, if any, shall be repaired to
the satisfaction of the Authority in accordance with these Specifications or replaced
at no additional cost to SCRRA.
B. Pipes or structural steel plate materials shall not be dropped to or dragged over
the ground, but shall be handled with rolling slings on skids or with cranes.
D. Distribute pipe and other Materials along the line of Work and outside the trench
as near as practical to the point of placement. Do not deposit site Materials on or
against pipe.
E. Protect pipe ends until the pipe is placed in its final position.
3.03 INSTALLATION
A. Foundation Preparation
5. The width of excavation and bedding backfill shall be the pipe diameter or
pipe-arch span in solid rock and boulders, and in other unsuitable material,
the width shall be three pipe diameters or pipe-arch spans for single pipes,
and for multiple pipes, this width shall be increased by the distances
between pipe or pipe-arch centers.
7. The Contractor must by diversion ditches, dikes, or other means, keep the
foundations free of water at all times after the work is started, and until the
embankment is placed over the pipe. Any channel work necessary to allow
free flow through the pipe shall be completed before the embankment is
placed. This work is incidental to installation of the culvert or drainage pipe.
B. Install Smooth Steel Pipe, if using jacking and boring method, in accordance with
Section 33 05 23.
1. General:
a. No pipe shall be laid until it has been inspected and approved. All
pipes shall be laid upgrade beginning at the lower end of the line.
Pipe shall be laid accurately to line and grade. Ensure that the pipe
has a full solid bearing along its entire length. When pipe has been
checked for line and grade, the body of the pipe shall be sufficiently
backfilled and compacted in accordance with Section 31 20 00 on
both sides to hold the pipe firmly in position.
b. All adjustments to line and grade of the pipe laid on earth foundation
shall be done by removal or filling of the bedding under the pipe and
not by blocking or wedging.
2. Placing CMP:
1) When the distance from base of rail to the top of pipe will be
less than the dimensions given in Table 1, corrugated pipes
must be field strutted by the Contractor using Contractor
supplied material.
TABLE 1
CMP Pipe Diameter - Inches Base of Tie to Top of Pipe - Feet
48 3.5
54 to 66, incl. 4.0
72 to 96, incl. 4.5
102 to 108, incl. 5.0
114 to 120, incl. 5.5
b. Where two or more structural plate pipes are used, they shall be a
minimum of 1/2 pipe diameter or one-third of pipe-arch span apart.
Where practicable, in the opinion of the Engineer, a space of 10 feet
may be provided between pipes to facilitate compacting fill material
around the pipe with heavy equipment.
1. General:
f. Where the distance from subgrade to top of pipe is less than 3 feet,
the excess material shall be left in place until the roadbed receives
its final finish. At this time the material over the pipe to a depth of 1
foot below subgrade elevation shall be compacted to the full amount
required by Section 31 20 00.
g. Care must be taken to prevent water form leaking through the fill or
along the side of the pipe. When granular materials have been used
for bedding or backfill, the ends of such material must be sealed
against infiltration. This can be done by using impervious
embankment material for 3 feet at both ends of the pipe.
F. Installation Finalization:
2. At the conclusion of the Work, the Contractor must thoroughly clean the
entire length of all the installed, extended or modified culvert by flushing
with water or other means to remove all dirt, stones, pieces of wood, or
other material, which may have entered the culvert during the construction
period. Debris cleaned from the lines shall be removed from the Worksite.
If there are any remaining obstructions after such cleaning, such
obstructions must be physically removed by the Contractor.
4.01 MEASUREMENT
A. Culvert Pipe will be measured by the type and size of the pipe, and the unit or
fraction thereof furnished and installed in accordance with the Contract Documents
and as measured by the Engineer. The quantities as contained on the Schedule
of Quantities and Prices, or approved Schedule of Values, as applicable, as
derived from the plans will be used as the basis for this measurement.
B. All material, work and services furnished for excavation and backfill, structural fill,
crushed aggregate bedding material, structural concrete, Concrete for connection
structures between existing and new culverts and headwalls and precast concrete
will be included in this Section and are considered incidental to work under this
Section and will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer.
4.02 PAYMENT
A. Culvert and drain pipe furnished and installed in accordance with the Contract
Documents will be paid for at the contract unit price for each type and size of pipe,
as listed on the Schedule of Quantities and Prices. This price shall be full
compensation for furnishing all labor, materials, tools, equipment, supplies,
supervision, and incidentals necessary for culvert and drain pipe described by the
Contract Documents.
B. Full compensation for excavation and backfill, structural fill, crushed aggregate
bedding material, structural concrete, Concrete for connection structures between
existing and new culverts and headwalls and precast concrete shall be considered
as included as listed on the Schedule of Quantities and Prices.
END OF SECTION 33 42 00
UNDERDRAINS
PART 1 - GENERAL
1.1 SUMMARY
A. The Work in this Section consists of furnishing all labor, materials and equipment
necessary and incidental to providing underdrains, and subsurface drainage
Materials behind foundations, piers, retaining walls and along track bed. The Work
includes connecting system to existing or new storm drains as indicated on the
Contract Plans.
B. Related Specification Sections include but are not necessarily limited to:
1. Section 31 20 00 - Earthwork.
1.2 REFERENCES
E. Standard Plans for public Works Construction (SSPWC) “Green Book”, 2012.
1.3 DEFINITIONS
A. The term “underdrain” pipe is in reference to any perforated plastic underdrain pipe
as indicated in the Contract Plans.
C. Trenching and Backfilling for the underdrain as shown on the Contract Plans or
other Referenced Standard.
1.5 SUBMITTALS
1. Submit Product Data, certifications and samples for each Material used in
this Section. Samples of permeable rock shall be no less than 150 lbs and
shall be accompanied with Supplier’s certified test data.
PART 2 - PRODUCTS
A. Outlets, risers and cleanouts shall be of the same materials as the perforated pipe
and shall be supplied from the same manufacturer. Riser cover shall be as detailed
on the Contract Drawing.
2.5 GEOTEXTILE
PART 3 - EXECUTION
3.1 PREPARATION
B. Subgrade for drainage installation shall be free of rock, rubble, debris, or stones
larger than 1.5 inches. If this condition is present, excavate an additional 4 inches,
and place 4 inches of sand bedding material at no additional cost to the Authority.
2. Fill trench bottom to the bottom of pipe grade with underdrain granular
backfill material to ensure complete and continuous support for the barrel
of the pipe.
B. Place the filter fabric as indicated. Place the long axis of the fabric parallel with
long axis of the pipe. Filter fabric sections shall be overlapped a minimum of 12
inches.
C. Place 6 inches of permeable rock on the filter fabric. Grade the rock to the line
and grade indicated for the perforated drainpipe.
D. Install aggregate filter material above the bottom of the trench and below the pipe
to the depths as indicated on the Contract Plans. The depth aggregate filter
material above and around the pipe shall also be as indicated on the Contract
plans.
E. Installation of ballast material as for bedding material should be per the limits as
shown in the Contract Plans.
F. Lay pipes in the upstream direction to the lines and grades shown, with the bell
pointing upgrade.
G. Place the perforated or slotted drain pipe with the perforations or slots facing down
in a semi-circular seat prepared in the permeable rock. Connect sections of pipe
in accordance with the manufacturer’s instructions.
H. Continue placing permeable rock in 4 inches layers under the sides and to the
spring line of the pipe. Tamp material to provide thorough compaction under and
on each side of the pipe. Successive layers of permeable rock may be placed in
8 inches layers and thoroughly compacted to the indicated depth shown on the
Contract Plans. Exercise caution not to damage the filter fabric. Torn or punctured
areas of filter fabric shall be repaired by placing a piece of fabric that is large
enough to cover the damaged area plus 12 inches of overlap on all sides.
I. Complete permeable rock backfill as indicated and close the filter fabric at the top
of this backfill with 12 inches lap.
A. After pipe is laid and joined, notify and obtain Engineer’s approval prior to
backfilling. Take up and re-lay or replace, any pipe found to be out of alignment,
unduly settled, or damaged.
4.1 MEASUREMENT
A. Underdrains will be measured by the type and size of the pipe, and the unit or
fraction thereof furnished and installed in accordance with the Contract Documents
and as measured by the Engineer. The quantities for each item included in the
Schedule of Quantities and Prices or approved Schedule of Values as derived from
the Contract Plans will be used as the basis for this measurement.
B. Underdrain connections are incidental to the items listed above and will not be
measured separately for payment.
D. Filter fabric including overlap, permeable rock and fill material are incidental to the
work and will not be measured separately for payment.
4.2 PAYMENT
B. Underdrain connections are incidental to the items listed above and will be
included in prices of the underdrain pipe listed above.
D. Filter fabric, including overlap, permeable rock and fill material are incidental to the
work and will not be a pay item.
END OF SECTION 33 46 00
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for the
Continuous Welded Rail (CWR) to be furnished in accordance with Contract
Documents or required by the Engineer.
1.02 REFERENCES
1.03 DEFINITIONS
A. Detail Fractures – A progressive fracture originating near the rail surface from a
shell or head check
B. Rail Wear – The change in shape of the cross-sectional area of the rail head due
to the passage of rail traffic and grinding
C. Shelling – A rail condition consisting of one or more horizontal separation that may
originate in the rail head and may crack out at the gage side of the rail. Shelling
normally originates towards the gage side of the rail head and extends
longitudinally
D. Spalling – A rail surface condition that is the direct result of micro-cracking, often
with material separating from the surface of the rail head.
1.04 SUBMITTALS
A. The CWR Vendor shall submit supporting information within 60 days of award
documenting the past successful performance in furnishing the materials included
in the Schedule of Quantities and Prices. Provide references and contact numbers
at the railroads where the CWR have been placed in service.
B. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing CWR to Class 1 Freight, passenger or commuter
railroads.
C. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality CWR included in the Schedule of Quantities and
Prices.
D. The Vendor shall submit certification that materials delivered to site are in
conformance with specifications. For CWR, include weld test results. Include all
material testing results and submittals stipulated in the AREMA Manual.
E. The Vendor shall submit procedure for transportation of CWR to site, unloading
and handling.
G. The Vendor shall submit drawings and specifications of the proposed equipment,
materials, methods and procedures to be used for the electric flash butt welding
process for joining of rail. Include layouts of the welding line showing locations of
welding components.
A. Vendor’s Quality Control Program (QCP) shall be in accordance with the AAR M-
1003 or SCRRA approved equivalent quality control program. Comply with
AREMA Portfolio of Trackwork Plans.
D. Material not meeting the requirements of this Specification shall not be used.
E. SCRRA shall have access to CWR Vendor’s plant during normal working hours
and all Project related procurement and production records for inspection any time
during the Contract period of performance.
A. The CWR Vendor shall load, transport, and deliver CWR in a manner which will
prevent damage to the CWR. Vendor shall submit to SCRRA the procedures and
equipment information for loading, unloading, handling, and storing rail.
B. SCRRA will review the Vendor's methods and procedures for unloading and
handling continuous welded rail.
C. The material will be supplied to the SCRRA in accordance with the delivery
requirements. Quantity of each supply will be as requested by the SCRRA release
document. The material when purchased is to be delivered to the Los Angeles
area at a place designated by the SCRRA. The delivery must be coordinated with
SCRRA prior to shipping and loading. Orders can be combined and shipped on
or before the delivery scheduled with approval by SCRRA. Delivery time and
minimum quantities shall be as follows:
D. Delivery delays due to Rail Train (carrier) unavailability are excusable when the
Vendor has made a best efforts attempt to schedule a carrier, and these best
efforts, at minimum included 14 days advance communication with at least three
carriers. Documentation of these best efforts and approval is required by SCRRA.
PART 2 - PRODUCTS
2.01 CWR
A. Rail shall be new 136 RE CWR Head Hardened rail conforming to AREMA Volume
1, Chapter 4, Section 2.1, Specifications for Steel Rails. The rail shall be controlled
cooled low alloy high strength rail, Grade HH (Head Hardened) or LH (Low Alloy
Head Hardened) and shall meet or exceed 370 HB (Brinell Hardness).
A. Rail and welds shall be ultrasonically tested as per AREMA Section 2.1 8.
B. Surface and internal hardness shall be determined as per AREMA Section 2.1.3.
D. For fabrication of CWR, flash butt production welds shall be tested by an inspection
agency approved by the SCRRA during the fabrication process using the dry
powder method of magnetic particle inspection (or ultrasonic method) in
accordance with ASTM E709 and the AREMA Manual of Railway Engineering,
Chapter 4.
2.04 MANUFACTURE
1. The steel for rails shall be made by purifying molten iron from the blast
furnace (plus any added scrap steel) using the Basic Oxygen Steelmaking
process, or by melting scrap steel using the Electric Arc Furnace
Steelmaking process. The resulting molten steel from either process shall
be cast into strands by a continuous casting process. Strands shall be cut
into blooms of an appropriate length for further processing and rolling.
B. Hydrogen Elimination:
1. The rail shall be free from shatter cracks and other inclusions caused by
hydrogen. Hydrogen elimination shall be accomplished by at least one of
the following processes:
2. Other processes (OP) for hydrogen and inclusion elimination in steel shall
be accepted in the production of steel rail, and be approved by SCRRA.
3. When controlled cooling of rails is used for elimination of hydrogen, all rails
shall be cooled on the hot beds or runways until full transformation is
accomplished and then charged immediately into insulated cooling
containers. In no case should the rail be charged into the containers at a
temperature below 725 degrees F. The temperature of the rails before
charging shall be determined at the head of the rail at least 12 inches from
the end of the rail.
5. If the above cooling requirement is not met, the rails may be considered
control-cooled, provided that the temperature at a location not less than 12
inches from the end of a rail at approximately the center of the middle tier
does not drop below 300 degrees F in less than 15 hours.
6. After removal or raising of the lid of the container, no rail shall be removed
until the temperature of the top layer of rails has fallen to 300 degrees F or
lower. The manufacturer shall maintain a complete record of the cooling
process for each container of rails.
A. Chemical Composition:
The chemical composition of a rail steel grade must be within the limits given in
Table 1 for standard chemistry rail steel. Rail steel with a high carbon content in
a range from 0.9 to 1.1 percent by weight and chemistry similar to that disclosed
in United States Patent No. 7,288,159 is also acceptable provided that rail rolled
this specification has been in successful use for more than five years by a Class I
railroad operating in North America.
Table 1: Product and Chemical Analysis Table for Standard Chemistry Rail Steel
B. Surface Hardness:
Rails furnished shall be high strength or high carbon pearlite. The minimum Brinell
hardness of the surface shall be within the limits found in Table 2.
A fully pearlitic microstructure shall be maintained in the head of the rail for all
ranges of rail chemistry and no un-tempered martensite may be present within the
rail at any point of the rail section.
C. Tensile Properties:
The tensile properties of rails shall be produced within the limits found in Table 3
for a particular grade of rail steel.
Note 1: Up to 5% of the order may be less than 10% elongation for high-
strength rail, but in no case may the elongation be less than 9%
A. Rolling:
The length of rails for welding into CWR strings shall be not less than 80 feet when
corrected to a temperature of 60 degrees F. Not more than 10 percent of standard
length rail of the total tonnage accepted from each individual rolling may be
comprised of shorter lengths corresponding to 78, 74, 70, 66, 60, or 39 feet.
Individual rails not welded into CWR strings as part of the purchase shall be
furnished to the length shown on the Schedule of Quantities and Prices. The
allowance for 10 percent shorter lengths will not apply to individual rails ordered to
a specific length.
B. Straightening:
C. Drilling:
Rails to be welded into CWR strings shall be furnished undrilled (blank). Individual
rails not welded into CWR strings shall be furnished to SCRRA undrilled but
chamfered and finished on both ends in accordance with SCRRA Engineering
Standard No. ES 2301.
A. Rails shall be marked to identify the length and grade with colored paint or other
identifying markings. Individual rails shall be paint-marked only one color
according to grade or length. High-strength rails shall be marked by either a metal
plate permanently attached to the neutral axis, hot stamped in the web, or rolled in
the brand. The marking shall give the manufacturer, type, and method of
treatment.
B. Heat treated rail shall be paint-marked orange. Alloy rail shall be paint-marked
aluminum color. Short rails (less than 80) feet) shall be paint-marked green. Rails
meeting the tolerances for Special Trackwork shall be paint-marked white. The
length of each rail shall be painted at the end of the rails in accordance with the
standard practices of the manufacturer.
C. Rails not meeting the requirements of this specification but acceptable under
another specification for use in low speed industry tracks shall be paint-marked
yellow. Industrial quality rails shall also be permanently identified by cutting
diagonally through every “RE” or other designation within the rolled branding of the
rail. Each designation brand shall be ground or milled diagonally from the top right-
hand corner to the bottom left-hand corner, a minimum of 1/4” in width and to within
0.010” of the parent rail web surface.
D. Rail Branding: Branding shall be rolled in raised characters on the side of the web
of each rail at a minimum of every 16 feet. The design of the letters and numerals
shall be determined by the manufacturer. The data and order of arrangement of
the branding shall be as shown in the following typical brand:
The method of Hydrogen Elimination shall be located in the brand when a Hydrogen
Elimination method other than Vacuum Treated (VT) is used.
E. Rail Stamping:
1. The web of each rail shall be hot stamped a minimum of 3 times per rail
(short rails must contain a minimum of one full stamp) on the side opposite
the brand, except that stamping shall not occur within 2 feet of either end
of rails.
3. The data shall be shown in the following typical stamping, except that
strand and bloom numbers may be joined or may be coded at the
manufacturer’s option. The height of the letters and numerals shall be 5/8
inch.
Stamping Markings
4. The 5/8 inch stamped characters shall have a flat or radius face (0.040 inch
to 0.060 inch wide) with bevels on each side so as not to produce
metallurgical stress risers. The letters and numbers shall be rotated to a 10
degree angle from vertical and shall have rounded corners. No sharp
corners are permitted. The stamping shall be between 0.020 inch and
0.060 inch in depth along the center of the web. The design shall be as
shown in Figure 1.
A. Chemistry Testing:
1. Steel from each heat must be tested to ensure that the chemistry of the
finished rail conforms to the limits shown in Table 1, or the limits for any
permitted alternative chemistry rail steel. Separate analyses shall be made
from test samples representing the front, middle (optional), and back of the
heat taken during pouring of the heat. Determination of the chemical
composition may be made chemically or spectrographically. Any portion of
the heat meeting the chemical analysis requirements of Table 1 (below)
may be applied.
a. Vacuum Degassing.
1. One longitudinal tension test specimen shall be taken from the gage corner
of the rail head, centered ½ inch from the gage side and ½ inch from the
running surface. The specimen shall be 0.5 inch diameter and shall be
tested per ASTM A370, “Standard Test Methods and Definitions for
Mechanical Testing of Steel Products.”
3. Except for high-strength rail, the test frequency shall be one test for each
heat for the first one hundred heats, one test for every fifth heat for the
second hundred heats and one test for every tenth heat thereafter for heats
furnished to the same manufacturing practice. In addition, a minimum of
one tensile test per order shall be furnished at the request of SCRRA, from
a heat supplied on the order. For high-strength rail of all steel grades, the
testing frequency shall be one test for each heat or 10,000 feet of rail,
whichever represents the smaller amount of rail.
C. Ultrasonic Testing:
1. Rails shall be ultrasonically tested for internal imperfections. The full length
of the rail shall be tested using in line ultrasonic testing equipment at the
rolling mill. The rail shall be free from rough surfaces, loose scale or foreign
matter which would interfere with the ultrasonic detection of defects.
Testing shall be done when the rail temperature is below 150 degrees F.
2. The calibration test rail shall be a full section rail of the same section as
that being tested. The test rail shall be long enough to allow a calibration
at the same rate of speed as the production rail. The size, shape, location
and orientation of calibration references to be placed in the test rail shall
be agreed upon by the purchaser and manufacturer. At least one reference
shall be put into the test rail to represent each search unit in the system.
3. The in-line testing system sensitivity level, using the calibration rail, shall
be adjusted to detect a minimum 1/16 inch diameter defect anywhere in the
sound path in the head, a minimum of 3/32 inch diameter in the web, and
longitudinal imperfections exceeding ½ inch length and greater than 1/16
inch depth occurring in the base. Any indication equal to or greater than
the above defect sizes when scanning the rail at the production speed shall
be cause for initial rejection. A record shall be made of each suspect rail.
This record shall be made available to SCRRA upon request.
4. The calibration rail shall be run through the ultrasonic testing equipment at
the start of each shift or at least once each 8 hour operating turn and
additionally at any section change or at any indication of equipment
malfunction. A record shall be maintained by the manufacturer of each time
the calibration test rail is run through the test system. This record shall be
made available to SCRRA upon request. In the event of a calibration
failure, all rails processed since the last successful calibration shall be
retested.
5. Rejected rails may be cut back to sound metal as indicated by the ultrasonic
testing. Rails shall be cut to one of the specified non-standard short
lengths. The cut shall be a minimum of 12 inches from any indication.
D. Brinell Hardness:
2. The test shall be conducted in accordance with the current version ASTM
E 10, “Standard Test Method for Brinell Hardness of Metallic Materials.”
The test shall be made on the side or top of the rail head after decarburized
material has been removed to permit an accurate determination of
hardness. Alternately, the test may be made on the prepared transverse
ground/milled sample no less than 3/8 inch inward from all rail surfaces.
3. If any test result fails to meet the specifications, two additional checks shall
be made on the same piece. If both checks meet the specified hardness,
the heat or heat treatment lot meets the hardness requirement. If either of
the additional checks fails, two additional rails in the heat or lot shall be
checked. Both of these checks must be satisfactory for the heat or lot to be
accepted. If any one of these two checks fails, individual rails may be tested
for acceptance.
4. If the results for off-line head hardened rails fail to meet the requirements
shown in Table 5 (below), the rails may be retreated at the option of the
manufacturer, and the retreated rails shall be re-tested.
1. The internal hardness of high-strength rail of any rail steel grade shall be
determined on a transverse specimen cut from the head and at least 6
inches from the end of the rail. The specimen shall be ground or milled so
that the transverse surfaces are parallel. The hardness test shall be
conducted in accordance with ASTM E-18, “Standard Test Methods for
Rockwell Hardness of Metallic Materials.” The results shall be reported in
Brinell using the conversions in Table 5.
2. The hardness shall be determined at intervals of not greater than 1/8 inch
along traverses 1, 2, and 3 and at positions 4 and 5 as shown in Figure 2.
Hardness gradient of head hardened rail along lines 1, 2, and 3 shall be
gradual towards the center of the rail, with no sharp drop or discontinuity.
Traverse 2 can extend into the web of the rail (X + 1.6 inch).
3. The hardness at a depth of 0.6 inch on lines 1, 2 and 3 and at points 4 and
5 of (depth of 3/8 inch) Figure 2 shall be 352 HB or higher for high strength
rail. For the low alloy head hardened rail steel grade (LH) the hardness at
a depth of 7/8 inch on lines 1, 2, and 3 shall be 341 HB or higher. The
testing frequency shall be one test per heat or 10,000 feet of rail, whichever
is the smaller amount of rail.
4. If any test specimen fails to meet the required hardness, two additional test
specimens shall be obtained from the same lot and tested. If both meet the
requirements, the lot shall be accepted. If one of the specimens fails to
meet the requirements, two additional rails from the lot shall be sampled
and tested. Both of these tests must be satisfactory for the lot to be
accepted. If one of the tests is unsatisfactory, individual rails may be
sampled and tested for acceptance. If the results for off-line head
hardened rail fail to meet the requirements for internal hard, the rails
represented by the test may be re-treated and re-tested.
a. A test piece representing a rail from each strand from the beginning
of each sequence and whenever a new ladle is begun shall be shall
be macroetched which is the point representative of the lowest level
in the tundish (i.e. the point of the lowest ferrostatic pressure.) One
additional sample from the end of each strand of the last heat in the
sequence shall also be tested. A new tundish is considered to be
the beginning of a new sequence.
b. SCRRA may, upon receipt, examine and test any rail from any part
of a heat at its option, and if the determines that the rail sample
selected in rejectable, the entire heat shall be reevaluated
according to Section 2.06, Part F, Paragraph D, below.
2. Sample Preparation
b. Etching time shall be between ten and twenty minutes. The solution
surface shall be at least one inch above the etched surface. Upon
removal from the bath, the sample shall be rinsed and brushed
under hot water and dried. The sample shall not be blotted dry. A
rust inhibitor may be applied to the etched face at the option of the
manufacturer.
The areas of cross section shall be defined as head, web, and base in
accordance with Figure 4-2-9 of Chapter 4 of the AREMA Manual for
Railway Engineering. A description of each of the rejectable conditions and
corresponding figure in Chapter 4 of the AREMA Manual for Railway
Engineering are given in Table 6.
AREMA Figure
Rejectable Condition
Number
4-2-9 Definition of rail cross sectional areas for macroetch evaluation
4-2-10 and 4-2-11 Hydrogen flakes
4-2-12 and 4-2-13 Pipe; any size.
4-2-14 and 4-2-15 Central web streaking extending into the head or base
4-2-16 and 4-2-17 Streaking greater than 2-1/2 inches in length
4-2-18 Scattered central web streaking from the web into the head and base.
Scattered segregation extending more than one inch into the head or
4-2-19
base.
4-2-20 Subsurface porosity
Inverse or negative segregation having a width greater than 3 inches
4-2-21
and extending more than ½ inches into the head or base
Streaking greater than 1/8 inches in the head from radial streaks,
4-2-22
radial cracks, halfway cracks, or hinged cracks
Other defects that could cause premature failure (i.e. slag, refractory,
4-2-23
etc.)
4-2-24 and 4-2-25 Segregation extending into the head or base
4-2-26 Segregation greater than 1/8 inches wide in the head or base.
4-2-27 Scattered central web segregation extending into the head and base.
4. Retesting
1. Sampling
Figure 3 – Sample “A” location in rail head – Shaded area denotes area to be
analyzed
H. Tolerances:
Rail shall be rolled to the standard section shown on the drawings or listed
in the Schedule of Quantities and Prices within the section tolerances given
in Table 5, and to the specified length within the tolerances given in Table
4. Gauges for checking basic rail dimensions shall conform to those
illustrated in Figure 4-2-28 through and including Figure 4-2-40 of
Chapter 4 of the AREMA Manual for Railway Engineering.
2. Rail Straightness
a. The uniform surface upsweep at the rail ends shall not exceed a
maximum ordinate of 0.020 inch in 3 feet and the 0.020 inch
maximum ordinate shall not occur at a point closer than 18 inches
from the rail end as illustrated in Figure 5. Surface down-sweep
and droop must not be accepted.
Figure 6a – Top View of Rail Lateral (Horizontal) Line Tolerance at Rail Ends
Figure 6b – Top View of Rail Lateral (Horizontal) Line Tolerance at Rail Ends
d. Rails shall be hot sawed, cold sawed, milled abrasive wheel cut, or
ground to length. Rail ends shall be square with a variation of not
more than 1/32 inch allowed. The method of finishing the ends of
rails shall not cause metallurgical or mechanical damage to the rail.
e. If the rail shows evidence of twist while being laid head up on the
final inspection bed, it will be checked by inserting a taper or feeler
gage between the base and the rail skid nearest the end. If the gap
exceeds 0.060 inch the rail will be rejected. Alternatively, a twist
gage may be used and if the rail exceeds 1.5 degrees in 80 feet the
rail will be rejected. Rejected rails may be subject to straightening.
a. Finished rail shall meet the requirements of a web saw cut test
conducted of a fully roller-straightened rail sample of a regular
production rail. The rail ends not affected by the roller straightening
process shall not be used for the test. For those production rails
that are not roller-straightened, the rail shall also meet the following
requirements of a web saw cut test.
b. The test sample shall be 24” in length and cut from a production
rail. The sample end face furthest from the end of the rail from which
the sample is cut shall be punch marked with two central, vertically
aligned sharp cone pointed marks, one on each side of the neutral
axis a sufficient distance apart such that the marks are not affected
or obliterated by the subsequent saw cut. The caliper measurement
shall be taken at a distance no more than 0.25” (6mm) from the rail
end at the vertical centerline of the rail. The caliper point locations
shall be marked and this measurement shall be recorded.
c. The initial vertical distance between the two punch marks shall be
measured with a calibrated vernier or digital caliper and recorded.
Alternatively, a calibrated vernier or digital caliper may be used to
measure the initial height of the de-burred end of the rail to be saw-
cut.
d. The web of the test sample shall then be saw cut on a straight line
along the neutral axis of the web for a distance (L) of 16”. If the rail
closes during the saw cut, sufficient material shall be removed from
the mouth of the saw cut to prevent the top portion of the rail from
touching the bottom portion of the rail. The sawing process shall
employ a procedure and sufficient precautions such that there is no
induced distortion or heating of the rail.
Any rail that does not meet the acceptance criteria of the primary saw cut
test, may be accepted if a steel wedge forced into the mouth of the saw
cut generates crack propagation and completed fracture through either the
base or head of the rail.
Alternately, any rail that does not meet the acceptance criteria in may be
accepted if two additional rails from the same week’s production are
secured, saw cut tested and pass the primary acceptance criteria.
4. Testing Frequency
PART 3 - EXECUTION
3.01 GENERAL
A. Flash butt welding and testing of rail shall conform to the current AREMA Manual,
Chapter 4, Part 2, Section, "Specification for Fabrication of Continuous Welded
Rail" unless otherwise specified herein.
C. Lengths of CWR strings delivered to site shall be not less than 1,200 feet unless
otherwise approved by SCRRA.
E. Rejected welds shall be cut out and rewelded with a minimum of 19'-6” plugs at
Vendor's expense.
F. Bolt holes for the end of CWR strings are acceptable and must be approved (size,
location and number) with the SCRRA prior to shipment.
3.02 EQUIPMENT
B. The Vendor shall maintain welding equipment in good working order at all times.
B. Any rail sections that cannot be straightened shall be cut back a sufficient distance
to achieve the specified tolerances.
C. If straightened rail does not meet specification tolerance in two passes through the
straightener, it will be cut out of the string.
A. Rails used for electric-flash butt welds shall have their ends saw-cut or abrasive
disc-cut clean and square by means of accepted equipment.
C. The head and base of the rail for a length of approximately six inches from welding
end shall have mill scale removed down to bright metal.
D. All burrs shall be removed from the area where the welding current carrying
electrodes contact on the head and base of the rail.
A. CWR strings shall be fabricated so that all of the branding appears on one side of
the string.
2. Vertical alignment shall provide for a flat running surface. Any difference
in height of the rails shall be in the base.
C. Horizontal alignment shall be done in such a manner that any difference in the
widths of heads of rails shall be divided equally on both sides of the head.
D. All electric flash butt welds shall be forged to point of refusal to further plastic
deformation and have a minimum upset of 0.5 inches with 0.625 inches as
standard.
E. The upset cylinder shall not bottom out during the upset portion of the weld cycle.
G. Quenching the weld metal shall not be permitted on standard rail. Quenching of
premium rail weld is permitted and shall be per the standard industry practice as
accepted by class I railroad.
B. All heavy grinding used in the finishing process shall be performed on the hot metal
immediately following welding, to prevent metallurgical damage.
C. Finishing shall eliminate cracks visible to the unaided eye. Notches created by
offset conditions shall be eliminated by grinding to blend variations.
E. All fins on the weld due to grinding drag shall be removed prior to final inspection.
A. Trimming and grinding of rail welds shall result in the weld being within the
tolerances set forth in the AREMA Manual, Chapter 4, Part 2, Section
"Specifications for Fabrication of Continuous Welded Rail."
1. The CWR string designation number and station location in the field.
2. The heat numbers of the first and last pieces of rail in the string.
3. The heat numbers on each side of any weld which has been cut out and
rewelded.
4. A small sketch or graph indicating the current flow during the production of
each weld.
A. Mark each completed string with the appropriate CWR string designation indicated
in the schedule of CWR strings.
B. As welding is completed on each CWR string, the string shall be transported from
the welding line by the Vendor to the track location or a suitable stockpile location.
C. The stockpile location shall be approved by SCRRA if it lies within the right-of-way.
B. Welds with surface cracks visible to the eye will not be accepted.
A. Flash butt production welds giving fault indication in magnetic particle inspection
during production shall be cut, rewelded and retested and shall not be left for field
welding.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Contractor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 10
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for Other
Track Materials (OTM) to be furnished in accordance with Contract Documents or
required by the Engineer.
B. OTM materials shall include rail fastening systems, screw spikes, track bolts, nuts,
spring washers, tie plates, tie plugs, rail anchors, standard toeless joint bars,
compromise joint bars, and insulated joints.
1.02 REFERENCES
3. AAR: Assembly and Test of Insulated Track Part 16, Signal Section
1.03 DEFINITIONS
A. Compromise Rail – A relatively short rail, the two ends of which are different
sections, corresponding with the sections of the rail to which they are to be joined
B. The word “Vendor” used in this Specification shall mean the Contractor.
D. Joint Bar – A steel member used in pairs for the purpose of joining rail ends
together, and holding them accurately, evenly and firmly in position
E. Insulated Joint – A rail joint designed to arrest the flow of electric current from rail
to rail by means of insulation placed so as to separate the rail ends and other metal
parts connecting them
F. OTM – A general term referring to all miscellaneous materials other than rail and
ties
G. Tie Plug – Rectangular sections of wood for filling unused spike holes in wood ties
H. Switch – A track structure to divert rolling stock from one track to another
1.04 SUBMITTALS
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
C. The Vendor shall submit OTM packaging, loading, shipping, and handling method.
D. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality OTM included in the Schedule of Quantities and
Prices.
E. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing OTM to Class 1 Freight, passenger or commuter
railroads.
F. The Vendor shall include installation instructions. The Vendor shall Include, at a
minimum, the Care and storage of materials; Date of glue manufacture; Glue shelf
life; Rail end preparation; Weather and temperature restrictions; Mixing and
application of glue; Installation of insulated joint bar and pin bolts; Curing
restrictions; Detection of glue bond failures
G. Submit Certificates of Compliance for all OTM. Include material qualification test
reports for materials, components, and assemblies.
A. Vendor’s Quality Control Program (QCP) shall be in accordance with the AAR M-
1003 or SCRRA approved equivalent quality control program. Comply with
AREMA Portfolio of Trackwork Plans.
A. The Vendor shall load, transport, and handle the material in a manner which will
prevent damage to the material.
B. The material will be supplied to the SCRRA in accordance with the delivery
requirements, FOB Destination. Quantity of each supply will be as requested by
the SCRRA release document. The material when purchased is to be delivered to
the Los Angeles area at a place designated by the SCRRA representative. A
complete Bill of Material for each order will be submitted with modes, dates,
contents, and destinations of shipments clearly indicated. A complete shipping list
with reference to blanket purchase agreement, if applicable, will accompany all
deliveries of materials.
C. All materials delivered will be colored coded and have bar coded control tags using
bar code # 128 system or as approved by SCRRA on all parts/hardware for easy
assembly by field personnel.
D. Steel tie plates shall be palletized, with each standard non-returnable pallet holding
not more than 6,000 pounds. Binding for the palletized tie plates shall be of
sufficient strength to facilitate multiple loading, unloading and handling with cranes
and/or forklifts.
PART 2 - PRODUCTS
2.01 GENERAL
A. Tie plates shall conform to AREMA Volume 1, Chapter 5, Section 1.1, Tie Plates -
“Specifications for Steel Tie Plates” and appropriate SCRRA Engineering
Standard.
B. Tie plate dimensions for resilient fastening systems for 5½” base shall conform to
SCRRA Engineering Standard ES2453, “Rolled Steel Tie Plate to Suit 5½” Base
AREMA Rail and Pandrol Rail Clips E2055”. Tie plate dimensions for resilient
fastening systems shall conform to SCRRA Engineering Standard ES2454,
“Rolled Steel Tie Plate to Suit 132 LB. RE – 141 LB. RE Rail and Pandrol Rail Clips
E2055”.
C. Tie plate dimensions for standard fastening systems for 5½” base shall conform to
SCRRA Engineering Standard ES2451, “Standard 13” Tie Plate for 5½” Base
Rail”. Tie plate dimensions for standard fastening systems for 6” base shall
conform to SCRRA Engineering Standard ES2452, “14” Tie Plate for 6” Base Rail”.
A. Cut spikes shall be new and conform to the requirements of the AREMA Manual,
Chapter 5, Part 2, Section 2.1, “Specifications for Soft-Steel Track Spikes”, and
SCRRA Engineering Standard ES2355.
B. Cut spikes shall be 5/8 inches by 6 11/16 inches and conform to all other
dimensions specified in the AREMA Manual, Chapter 5, Part 2, Section 2.2,
“Design of Cut Track Spike”.
C. Screw spikes shall be 15/16 inch by 6 inches straight shank screw spikes with a
minimum tensile strength of 73,000 psi. Head shall be hot forged and centered
relative to the shank in accordance with SCRRA Engineering Standards ES2355.
D. Screw spikes for grade crossing panels shall be “Evergrip” or equal and shall be
as per ES2355.
B. Material for rail anchors to be high carbon steel. Material to be heat treated to Rc
34-47.
C. Rail anchors shall be sized to conform to the rail section used. Rail anchors shall
have sufficient bearing area and depth to minimize the possibility of the anchor
damaging or becoming embedded in the tie.
D. Rail anchors shall conform to the AREMA Manual, Chapter 5, Part 7, Section 7.1,
“Specifications for Rail Anchors”. Rail Anchors shall be one-piece conforming to
the requirements of AREMA Manual and of standard weight.
A. Track bolts and nuts shall conform to the dimensions specified in the AREMA
Manual, Chapter 4, Part 3, Section 3.3, “Rail Drilling, Bar Punching, and Track
Bolts”. Track bolts, nuts and washers shall conform to the requirements of the
AREMA Manual, Chapter 4, Part 3, Section 3.5, Specifications for Heat-Treated
Carbon-Steel Track Bolts, and Carbon-Steel Nuts.
B. Spring Washers shall conform to the requirements of the AREMA Manual, Chapter
4, Part 3, Section 3.6, Specifications for Spring Washers.
A. Resilient fastening system for wood ties shall be a Pandrol rail fastening system
per relevant SCRRA Engineering Standards, “Pandrol Rail Clip – Type “e” 2055”,
consisting of elastic fastener ”E-Clip” galvanized, type elastic clips, screw spikes,
and elastic fastener tie plates or approved equal or as otherwise indicated in the
Contract Drawings. Pandrol “E-Clip” shall be galvanized as required per ES2362.
B. Resilient fastening system for concrete ties shall be a Pandrol Rail fastening
system per relevant SCRRA Engineering Standards consisting of “Fast-Clip” type
elastic fasteners pre-installed in the “off” position on concrete ties, or approved
equal, unless indicated otherwise on the Contract Drawings.
A. Joint bars shall conform to AREMA Volume 1, Chapter 4, Part 3, Section 3.2, “Joint
Bars and Assemblies”; Section 3.3, “Rail Drillings, Bar Punchings and Bolts”; and
Section 3.4, “Specifications for Quenched Carbon-Steel Joint Bars, Micro-alloyed
Joint Bars and Forged Compromise Joint Bars”.
B. Bar dimension and details shall conform to SCRRA ES2502, “Rail and Joint
Assembly for 136 lbs. RE Rail”.
C. Joint bars used to temporarily connect rails that will be field welded in the final
configuration shall be bolted with the rails ends drilled in the outer four holes only.
B. Other rail weight connections or those connections necessary for “Industry Track”
or “Other than main line” will be made using Compromise Bars.
D. Final configuration of the track shall utilize field welds to join transition rails
wherever applicable in mainline track.
E. Compromise joint bars may be used for interim phases of construction on mainline
track provided interim phase duration is expected to be six (6) months or less.
F. Temporary Compromise joint bars as noted above shall use track bolts in the outer
four holes only.
A. Bonded insulated rail joints shall conform to the current requirements of the
SCRRA Engineering Standards ES2504 and AREMA Manual, Chapter 4, Part 3,
Section 3.8, “Specifications for Bonded Insulation Rail Joints”.
C. Insulated rail joints shall be complete with bars, end posts, bushing, washers, pin
bolts, collars, washers and adhesives.
D. Straight bars shall be new and smooth and will be providing full face contact,
conforming to the applicable rail section, and fabricated from material which meets
or exceeds the mechanical properties and workmanship requirements of the
current AREMA Volume 1, Chapter 4, Part 3, Section 3.4, “Specifications for
Quenched Carbon-Steel Joint Bars, Micro-alloyed Joint Bars and Forged
Compromise Joint Bars”. The toe of the joint bar shall properly fit against the web
of the rail. When elastically fastened, the joint bar shall provide adequate
clearance to maintain electrical isolation.
E. Pin bolts shall be of ASTM A325 structural steel furnished with the appropriate
collar.
F. Flat circular shall be hardened steel washers in accordance with ASTM F436.
G. Bolt hole size shall be in accordance with the bonded insulated joint Vendor's
recommendation. If bolt hole diameter is larger than 1-3/16 inches, place ASTM
A325 hardened washers between the joint bars and the nut. Refer to SCRRA
ES2370 for details.
H. The bolt hole locations shall be as specified in AREMA, Chapter 4, Part 3, Section
3.3, Rail for a 36-inch joint bar. Insulated joint bar lengths for main track
installations shall be 36 inches.
2.12 DERAILS
A. Derails shall be as per SCRRA Engineering Standard ES2604. The sliding and
hinged derails shall be painted yellow.
A. During OTM fabrication, perform the tests and inspections specified in the AREMA
Specifications.
B. The bonded insulated rail joints shall meet electrical resistance test as specified in
AREMA Chapter 4, Section 3.8.7.3.
PART 3 - EXECUTION
3.01 GENERAL
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor at phone number 909-468-9729, 48 hours prior to the date of delivery.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Contractor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 15
SPECIAL TRACKWORK
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for the
Special Trackwork to be furnished in accordance with Contract Documents or
required by the Engineer.
B. Special Trackwork materials furnished under this IFB shall include rail, switches,
frogs, insulated joints, derails, compromise/transition rail, stick rail, and bumping
posts and individual turnout components to be used as replacement parts. All
materials furnished shall be entirely new materials.
C. Special Trackwork materials furnished under this IFB shall be utilized in the
“general railroad system of transportation” within the meaning of 49 CFR 213.1
(Track Safety Standards) and will be used in dense traffic mixed
passenger/commuter and freight railroad service.
1.02 REFERENCES
1.03 DEFINITIONS
A. Closure Rails – The rails between the parts of any Special Trackwork layout, such
as the rails between the switch and the frog in a turnout
B. The word “Vendor” used in this Specification shall mean the Contractor.
D. Frog – A track structure used at the intersection of two running rails to provide
support for wheels and passageways for the flanges, thus permitting wheels on
either rail to cross the other
E. Guard Rail – A rail or other structure laid parallel with the running rails of a track –
used to hold wheels in correct alignment to prevent their flanges from striking the
end of switch points of frog points
F. Point Rail – Switch rail or switch point – the tapered rail of a switch used to divert
traffic along either route of a turnout
H. Running Rail – The rail that carries a wheel as differentiated from a guard rail or
flange rail which carry no weight
I. Spring Frog – A frog having a movable wing rail which is normally held against the
point rail by springs thus making an unbroken sunning surface for wheels using
the track. The flanges of wheels on the other track force the movable wing rail
away from the point rail to provide a passageway
J. Stock Rail – A running rail against which the switch points operate
K. Switch – A track structure to divert rolling stock from one track to another
1.04 SUBMITTALS
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
C. The Vendor shall submit Special Trackwork packaging, loading, shipping, and
handling method.
D. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality Special Trackwork Materials included in the list of
Special Trackwork items as provided in the Schedule of Quantities and Prices.
E. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing Special Trackwork material to Class 1 Freight,
passenger or commuter railroads.
A. Vendor’s Quality Control Program (QCP) shall be in accordance with the AAR M-
1003 or SCRRA approved equivalent quality control program. Comply with
AREMA Portfolio of Trackwork Plans.
D. Insulated gauge plates and switch rods shall be tested in accordance with AAR
Manual, Part 116, Signal Section, Assembly and Test of Insulated Track Fittings.
A. The Vendor shall load, transport, and handle the material in a manner which will
prevent damage to the material.
B. Band all switch points and stock rails together in one package for each turnout unit.
C. Package all frog as a single unit per turnout, and identify to indicate the turnout
number.
E. The material will be supplied to the SCRRA in accordance with the delivery
requirements, FOB Destination. Quantity of each supply will be as requested by
the SCRRA release document. The material when purchased is to be delivered to
the Los Angeles area at a place designated by the SCRRA. A complete Bill of
Material for each order will be submitted with modes, dates, contents, and
destinations of shipments clearly indicated. A complete shipping list with reference
to blanket purchase agreement, if applicable, will accompany all deliveries of
materials.
F. All materials delivered will be colored coded and have bar coded control tags using
bar code # 128 system or as approved by SCRRA on all parts/hardware for easy
assembly by field personnel.
PART 2 - PRODUCTS
2.01 GENERAL
A. Use SCRRA Standard Specifications and Engineering Standards for all turnouts
and crossovers and related replacement and spare parts.
B. Rails, castings, forging, rolled shapes, washers, and fastening used in Special
Trackwork ordered to the Engineering Standards shall be produced in
conformance to these Specifications and AREMA Specifications for Special
Trackwork.
2.02 RAIL
A. All steel rail used in the manufacturing of switches, turnouts and crossovers shall
be new Low Alloy, Head Hardened, High Strength Grade HH or LH 136 RE (10-
inch radius) conforming to AREMA Chapter 4, Part 2, Section 2.1, “Specifications
for Steel Rail” and shall meet or exceed 370 HB or new BNSF Specification HH
370 Rail or an equivalent “Premium Type Head Hardened” Rail. If the Bidder is
providing rail from a BNSF or UP specification that meets or exceeds these
specifications and the AREMA standard – the Special Trackwork Manufacturer
shall supply a copy of the applicable UPRR or BNSF standard for the rail being
furnished.
2.03 SWITCHES
A. All switch point rails and stock rails shall be Samson type construction in
accordance with SCRRA Engineering Standards.
B. Switch rails shall be fully heat-treated per specifications for heat-treated rails for
Special Trackwork, Plan No. 100-92 Specifications in the AREMA Portfolio of
Trackwork Plans.
2.04 FROGS
B. Railbound Manganese (RBM) frogs with elastic fastening system shall conform to
SCRRA Engineering Standards or approved equal. Manganese castings shall be
3-shot explosion-hardened in accordance with AREMA Specifications. Heel of the
frog shall incorporate a 30-degree cut. Frog plates shall be with one inch round
holes except as otherwise indicated on the SCRRA Engineering Standards. Bolts
shall be 1-3/8-inch Grade 8 square head with 1/4 inch hardened flat washers and
hexagon security locknuts. Lubricate frog bolts and torque to 2,500-foot pounds.
D. Casting for frog inserts manganese steel shall be in accordance with AREMA
Specifications for Special Trackwork, Article M2.
E. Frog guard rails may be machined initially and subsequently heat treated to
achieve the requirements of high strength rail as specified n AREMA
Specifications.
F. Tie plates shall conform to AREMA Volume 1, Chapter 5, Section 1.1, Tie Plates -
“Specifications for Steel Tie Plates” and appropriate SCRRA Engineering
Standard.
A. Bonded insulated rail joints shall conform to the current requirements of the
SCRRA Engineering Standards ES2504 and AREMA Manual, Chapter 4, Part 3,
Section 3.8, “Specifications for Bonded Insulation Rail Joints”.
C. Insulated rail joints shall be complete with bars, end posts, bushing, washers, pin
bolts, collars, washers and adhesives.
D. Straight bars shall be new and smooth and will be providing full face contact,
conforming to the applicable rail section, and fabricated from material which meets
or exceeds the mechanical properties and workmanship requirements of the
current AREMA Volume 1, Chapter 4, Part 3, Section 3.4, “Specifications for
Quenched Carbon-Steel Joint Bars, Micro-alloyed Joint Bars and Forged
Compromise Joint Bars”. The toe of the joint bar shall properly fit against the web
of the rail. When elastically fastened, the joint bar shall provide adequate
clearance to maintain electrical isolation.
E. Pin bolts shall be of ASTM A325 structural steel furnished with the appropriate
collar.
F. Flat circular shall be hardened steel washers in accordance with ASTM F436.
G. Bolt hole size shall be in accordance with the bonded insulated joint Manufacturer's
recommendation. If bolt hole diameter is larger than 1-3/16 inches, place ASTM
A325 hardened washers between the joint bars and the nut.
H. The bolt hole locations shall be as specified in AREMA, Chapter 4, Part 3, Section
3.3, Rail Drillings, Bar Punchings and Bolts, for a 36-inch joint bar. Insulated joint
bar lengths for main track installations shall be 36 inches.
2.06 DERAILS
B. Bi-directional Sliding Derail 136RE shall be Hayes model HBXS or approved equal.
Derail package shall include all rods, hardware and wood switch timbers, low
profile switch stand, target and fasteners. Derail shall be compatible for use with
or without electric lock. Derail to be compatible with 136 lb. rail.
C. Switch Point Derail 136RE or Double Switch Point Derail with wood switch timbers
shall meet the requirements of SCRRA Engineering Standard drawing ES2601,
ES2602 and ES2604. 16’-6” switch points, Pandrol plates, and galvanized e-clip
fasteners with all rods, connection hardware, and target shall be included for use
with Union Switch and Signal M23E USS model machine. Derail to be compatible
with 136 lb. rail.
D. Rail Mounted Flop-over Derail shall be bi-directional with flag, 136RE or 115RE as
listed in the Schedule of Quantities and Prices, all hardware and mounting kit
included.
A. Furnish 80’-0” long rail with blank ends. All stick rail to comply with the
requirements in Section 2.02 Rail.
A. Hand throw switch stands shall be Racor 36-EH switch stand or approved equal
furnished with a 14-inch red target with reflective material such as Scotchlite or
equal on both sides.
B. Hand throw switch stand for crossovers shall be Racor 36-E switch stand, or
approved equal, furnished with a 40 1/2 inch straight handle providing maximum
clearance between tracks and an 8-inch red target with reflective material such as
Scotchlite or equal on both sides.
C. Hand throw switch stand for double point split switch derail shall be Racor 36-EH
switch stand, or approved equal, in accordance with SCRRA Engineering
Standards furnished with a 14-inch round “D” target with yellow reflective material
such as Scotchlite or equal on both sides.
A. Furnish wood switch ties as required for turnout complete packages. All wood ties
furnished with this IFB will be pre-plated and conform to the requirement in SCRRA
B. Furnish concrete switch ties as required for turnout complete packages. All
concrete ties furnished with this IFB will conform to the requirement in SCRRA
spec Section 34 11 33 and will need to conform to the dimensions as shown in the
standard drawings.
A. During Special Trackwork fabrication, perform the tests and inspections specified
in the AREMA Specifications.
B. Examine each forging and weld by the dry powder method of magnetic particle
inspection in accordance with ASTM E709.
C. Perform ultrasonic testing on all forging and welds in accordance with ASTM E164.
D. All frog points shall be Brinell hardness tested on the head and along the side
wearing surface in accordance with ASTM E10.
E. The bonded insulated rail joints shall meet electrical resistance test as specified in
AREMA Chapter 4, Section 3.8.7.3.
PART 3 - EXECUTION
3.01 GENERAL
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor, 48 hours prior to the date of delivery.
4.01 MEASUREMENT
4.02 PAYMENT
A. Special Trackwork supplied in accordance with the IFB will be paid for at the
contract unit price as listed in the Schedule of Quantities. This price shall be full
compensation for furnishing labor, materials, tools, equipment, supplies,
supervision, and incidentals necessary for Special Trackwork described by the
Contracts Documents.
END OF SECTION 34 11 23
BALLAST
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for
ballast to be furnished in accordance with Contract Documents or required by the
Engineer.
B. Ballast shall consist of crushed stone which is angular fragments resulting from
crushing by mechanical means the following types of rocks quarried from
undisturbed, consolidated deposits: granite and similar phanero-crystalline
igneous rocks, extrusive igneous rocks, or massive metamorphic quartzite or
similar rocks. No crushed gravel shall be allowed.
1.02 REFERENCES
2. C117: Standard Test Method for Materials Finer than 75-μm (No. 200)
Sieve in Mineral Aggregates by Washing.
5. C136: Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates.
6. C142: Standard Test Method for Clay Lumps and Friable Particles in
Aggregates.
10. D3042: Standard Specification for Type PSM Poly (Vinyl Chloride) (PVC)
Sewer Pipe and Fittings.
11. E11: Standard Specification for Wire Cloth and Sieves for Testing
Purposes.
1.03 DEFINITIONS
A. Fine Graded Aggregates – Mineral aggregates which will pass a No. 4 mesh
screen and be retained on No. 200 screen
B. The word “Vendor” used in this Specification shall mean the Contractor.
1.04 SUBMITTALS
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
C. Representative samples of ballast, of not less than 150 pounds for gradation and
other required tests shall be taken from each source of ballast and tested as
specified herein. Samples will be delivered to Authority within 20 days of award.
Each shipment of ballast shall be accompanied by a certification as specified.
D. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality ballast included in the list of ballast items as
provided in the Schedule of Quantities and Prices.
E. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing Special Trackwork material to Class 1 Freight,
passenger or commuter railroads.
B. The Vendor shall provide laboratory certification that ballast Material meets the
Specifications of this Section.
C. If the Vendor observes ballast material not suitable for work, or not in compliance
with this part, SCRRA must be notified within three (3) hours of discovery of
condition.
D. The product delivered shall be from the same source from which samples were
tested and found to conform to the Specification and shall be of the same type and
quality of that which was tested.
A. Prepared ballast shall be handled in such a manner that it is kept clean and free
from segregation, and when delivered, the ballast shall be clean and free from
rubbish or any substance, which might foul the ballast.
E. The material will be supplied in accordance with the delivery requirements, FOB
Destination. Quantity of each supply will be as requested by the SCRRA release
document. The material is to be delivered to the six-county Los Angeles area at a
place designated by the SCRRA representative. The delivery must be coordinated
with SCRRA representative prior to shipping and loading.
F. In the event of an emergency, the Vendor shall use its best efforts to provide 200
tons of products within 6 hours of notice, 400 tons within 24 hours’ notice, and 800
tons within 48 hours. The emergency status shall be determined by the Engineer.
The Vendor is entitled to a surcharge to the unit price for emergency deliveries. If
an emergency delivery occurs outside regular operating hours (The Vendor will be
required to advise Authority, in writing, of operating hours or changes thereof) the
Vendor will be entitled to a 10% surcharge to the unit price. Vendor must identify
on each invoice which delivery is subject to the surcharge and identify the Authority
representative who ordered the product under the emergency status.
G. Vendor shall be responsible for unloading ballast under the direction of the
Engineer.
PART 2 - PRODUCTS
2.01 GENERAL
A. Use SCRRA Engineering Standards ES2007 for all ballast and sub-ballast supply.
C. Walkway rock or yard ballast gradation shall conform to SCRRA ES2007-02 and
AREMA Volume 1, Chapter 1, Section 2.4.4, Table 1-2-2, Standard No. 5 ballast
unless otherwise noted.
Traprock -- 25 percent
Quartzite -- 30 percent
Note 1: Materials having gradations containing particles on the 1 inch sieve shall be tested by ASTM C 535.
Materials having gradations with 100% passing the 1 inch sieve shall be tested by ASTM C131. Use ASTM C 535 for
Ballast Standard Type 4A and ASTM C131 for Ballast Standard Type 5.
C. All particles of the ballast shall have been broken by the crusher and must have at
least two fractured surfaces.
D. The aggregate base shall consist entirely of crushed rock with a minimum of 75
percent of the material having at least two fractured faces. No reclaimed asphalt
or concrete (Crushed Miscellaneous Base) shall be included in this material.
A. Vendor’s testing laboratory shall take and perform gradation and other tests on
representative samples of ballast, of not less than 150 lbs, from each source of
ballast.
PART 3 - EXECUTION
3.01 GENERAL
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor at phone number 909-468-9729, 48 hours prior to the date of delivery.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Contractor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 16
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for
roadway and pathway aggregate base to be furnished in accordance with Contract
Documents or required by the Engineer.
1.02 REFERENCES
1.03 SUBMITTALS
A. Samples: As required by the Engineer samples of not less than 150 lbs. Samples
shall be furnished by the Vendor or may be obtained independently by the
Engineer's representative for testing to determine whether the material delivered
to the site is in compliance with the Specifications.
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
B. The Vendor shall provide laboratory certification that ballast Material meets the
Specifications of this Section.
C. If the Vendor observes material not suitable for work, or not in compliance with this
part, SCRRA must be notified within three (3) hours of discovery of condition.
D. The product delivered shall be from the same source from which samples were
tested and found to conform to the Specification and shall be of the same type and
quality of that which was tested.
A. Prepared sub-ballast and aggregate base shall be handled in such a manner that
it is kept clean and free from segregation, and when delivered, the sub-ballast and
aggregate base shall be clean and free from rubbish or any substance, which might
foul the ballast.
E. The material will be supplied to the SCRRA in accordance with the delivery
requirements, FOB Destination. The material when purchased is to be delivered
to the six-county Los Angeles area at a place designated by the SCRRA
representative. The delivery must be coordinated with SCRRA representative prior
to shipping and loading. Orders can be combined and shipped on or before the
delivery scheduled with approval by SCRRA. A complete Bill of Material for each
order will be submitted with modes, dates, contents, and destinations of shipments
clearly indicated. A complete shipping list with reference to blanket purchase
agreement, if applicable, will accompany all deliveries of materials.
F. Vendor shall be responsible for unloading sub-ballast and aggregate base under
the direction of Authority or authorized representative.
PART 2 - PRODUCTS
A. Sub-ballast shall conform to the gradation and quality requirements for SCRRA
ES2007-02 and Caltrans Specifications Section 26-1.02A, Class 2 Crushed
Aggregate Base, 3/4” Maximum. In addition, the aggregate shall consist entirely
of crushed rock with a minimum of 75 percent of the material having at least two
fractured faces. No reclaimed asphalt or concrete (Crushed Miscellaneous Base)
shall be included in this material.
PART 3 - EXECUTION
3.01 GENERAL
B. Placing, and spreading of sub-ballast and aggregate base shall meet the
requirements stated in Caltrans Standard Specifications, Section 26-1.03,
Construction.
D. Finished surface shall not vary from grade shown in plans by 0.05 foot.
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor, 48 hours prior to the date of delivery.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Vendor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 27
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for
production and inspection of mono-block, pretensioned, prestressed concrete ties
for standard gage track (4’ – 8 1/2”) to be furnished in accordance with the
specifications and SCRRA Engineering Standards ES2402, ES2403, ES2406 or
ES2407 as appropriate.
B. Work included in this Section encompasses work necessary for the manufacturing
and production of concrete crossties and guardrail concrete cross ties both with or
without neoprene pads.
C. Related Specification Sections include but are not necessarily limited to:
3. Section 34 72 00 - Trackwork.
1.02 REFERENCES
1. Manual for Railway Engineering, Volume 1, Chapter 30, Part 4.2.3 Duggan
Concrete Expansion Test.
5. C31, Standard Practice for Making and Curing Concrete Test Specimens
in the Field.
11. C191, Standard Test Methods for Time of Setting of Hydraulic Cement by
Vicat Needle.
12. C192, Standard Practice for Making and Curing Concrete Test Specimens
in the Laboratory.
15. C359, Standard Test Method for Early Stiffening of Hydraulic Cement
(Mortar Method).
16. C430, Standard Test Method for Fineness of Hydraulic Cement by the 45-
μm (No. 325) Sieve.
20. C618, Standard Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use in Concrete.
21. C666, Standard Test Method for Resistance of Concrete to Rapid Freezing
and Thawing.
22. C403, Standard Test Method for Time of Setting of Concrete Mixtures by
Penetration Resistance.
25. C1567, Standard Test Method for Determining the Potential Alkali-Silica
Reactivity of Combinations of Cementitious Materials and Aggregate
(Accelerated Mortar-Bar Method).
1. MNL 116, Manual for Quality Control for Plants and Production of Precast
and Prestressed Concrete Products.
1.03 DEFINITIONS
A. The word "Inspector" in this Specification shall mean the duly authorized
representative of SCRRA.
B. The word “Vendor” used in this Specification shall mean the Contractor.
E. The word "source" in this Specification shall mean a plant where a material or
component used in the concrete ties, is produced. For aggregates, the word
"source" shall mean the strata or quarry face from which the aggregate is obtained.
F. The word "bed" in this Specification shall mean a prestressing bed with forms
placed end to end. Each bed is only one form wide.
G. The word "form" in this Specification shall mean a battery form, one tie long, with
5 to 8 cavities in which ties are cast upside down.
H. The word "line" in this Specification shall mean a series of ties end to end on a
prestressing bed. Each line is only one tie wide.
I. The words "long line process" in this Specification shall mean ties being, made on
a bed with at least ten forms end to end and on which the prestressing wires are
tensioned between fixed abutments, independent of the forms, and prior to placing
concrete.
J. The words "outside testing laboratory" in this Specification shall mean a testing
laboratory, independent of the manufacturer, which conforms to ASTM E994 and
is approved by the Engineer.
1.04 SUBMITTALS
a. Certification that the proposed concrete tie and shoulder inserts will
satisfy all test requirements as specified herein.
2. Tests:
1) Cement.
2) Aggregates.
3) Water.
4) Concrete.
6) Fasteners.
7) Electrical Properties.
8) Tie Testing.
3. Design Analysis:
5) Cure time:
a. Forms and gages shall not be used until the Plans have been
approved by the Engineer.
1) Management organization.
3) Plant Standards.
7. Submit the Quality Control Program and the Production Program specified
under “Quality Assurance and Quality Control” herein.
b. If the manufacturer's existing plants are outside the USA, they shall
have been certified by the equivalent National Certification
Organization for that country.
2. The manufacturer shall show to the satisfaction of the Engineer that he has,
or can obtain, the necessary and proper equipment, tools, facilities and
means, and that he has the experience, ability and financial resources to
perform the work within the time specified and to the quantity standards
required.
3. Ties shall be manufactured by the long line process with 5 to 8 lines per
bed.
4. If the manufacturer produces the ties in a new plant, that plant shall be
certified under the PCI Plant Certification Program within 6 months from
the start of production.
5. The requirements of ACI 301 and PCI MNL 116 shall apply except where
other requirements are stated in these Specifications.
A. Concrete ties shall be shipped in open-top cars or flat bed truck trailers.
2. Ties shall be shipped in a horizontal position and braced with spacer blocks
in such a manner that the top surface or cast-in-place hardware does not
contact ties loaded above.
3. Ties shall not be loaded higher than the top of the cars and not more than
six layers deep.
1. When handling ties in the plant, yard or at the delivery site, ties must not
be dropped or otherwise damaged.
2. Ties must be stacked on firm level ground, not more than 10 ties high and
supported on dunnage at the rail seats only.
PART 2 - PRODUCTS
A. The manufacturer shall only use materials from sources approved by the Engineer.
1. For cement, the source of clinker and the source of the ground cement will
be approved by the Engineer.
2. All tests for cement and aggregate shall be completed in accordance with
this Specification before approval of materials is requested from the
Engineer.
B. Adequate time shall be allowed for the Engineer to approve new sources.
1. Trial concrete mixes shall be cast at least 90 days prior to approval being
requested.
C. For aggregates to be supplied from a new source that has not been previously
tested, a minimum period of 224 days shall be required for testing to ASTM C227
prior to approval being requested.
1. Alternatively, 70 days shall be allowed for the Osmotic Cell Test. SCRRA
will accept previous test results on these aggregates from a qualified
laboratory performing these tests as required to the standards of the
appropriate ASTM which has been supervised, signed and sealed by a
California Registered PE or Geologist.
2.02 CONCRETE
1. The test cylinders shall be made and stored as specified in ASTM C31.
C. Proportioning:
D. Temperature: The temperature of freshly mixed concrete shall not exceed 90° F.
E. Curing:
2. Concrete shall not be placed in forms whose temperature is less than 40°
F and the concrete temperature shall not be allowed to fall below 50 ° F
between casting, and transfer of prestress.
3. If heat curing is used, the forms may be preheated to avoid cooling of the
concrete after placing but the temperature of concrete shall not exceed 90
° F during the first three (3) hours and 105 ° F during the first four (4) hours
(ASTM C403).
4. The rate of temperature rise in the concrete shall not exceed 35° F per hour
and the maximum concrete temperature shall not exceed 158° F.
b. The heating method used shall be such that all ties in a bed are at
a similar temperature.
5. During curing, the temperature at the center of the rail seat cross section
of one tie in each bed shall be automatically recorded.
1. The first batch on any bed shall be tested in accordance with this
Specification and if this requires no adjustment to the mix, a further test
shall be made after approximately 25 cubic yard has been poured.
2. Slump:
3. Air Content: Air entrainment of the concrete shall comply with the following
table in areas that are subject to freeze/thaw conditions:
1. Compressive Strength:
c. The cylinders shall all be made from one batch of concrete and the
slump and air content shall also be measured on the same batch.
d. The cylinders shall be cured with the ties until transfer of prestress,
in such a way that the temperature of the cylinders is with +0˚ -15°
F of the temperature of the ties.
a. If either result is less than 4500 psi, curing shall be continued for at
least a further one (1) hour.
H. Durability:
1. One tie shall be selected at the start of production and thereafter every
three months, for air void content and durability factor tests by an outside
testing laboratory.
2. The air void content shall be measured in accordance with ASTM C457 on
the top, center and bottom of a cross section slice cut from the rail seat of
a tie.
a. The measured air void content shall be not less than 3.0 percent
and the air void spacing factor shall not exceed 0.008 inch.
I. Chloride:
2.03 CEMENT
2. The false set penetration, when tested in accordance with ASTM C359,
shall be not less than 50 mm at intermediate times and 40 mm after remix.
B. Separate random samples of cement shall be taken each day to represent the
cement used on each bed.
1. Each sample shall be not less than 1 gallon and shall be clearly identified
with the date and bed number.
2. Each sample shall be kept in air- tight container until the corresponding 28-
day cylinder tests have been carried out and results accepted by the
Engineer.
C. Not more than two sources of clinker or ground cement shall be used by the
manufacturer during any one-month.
1. Cement from each source shall be clearly identified and stored in separate
weather tight silos.
2. If two sources of cement are used on one bed, the tests in Paragraph 2.02E
herein shall be performed on the first batch of concrete made with each
cement and if no adjustment to either mix is required, testing shall continue
as single design as required in Paragraph 2.02E. herein Strength tests as
required in Paragraph 2.02.F.1 herein shall also be conducted on concrete
made with each type of cement.
D. Cement mill certificates shall be provided weekly by each supplier and shall include
the results of the following tests on cement delivered during that week.
E. At least once during every three months, a randomly chosen sample of cement
from each source used shall be analyzed for alkali content in accordance with
ASTM C114 by an outside testing laboratory.
2.04 AGGREGATES
A. Both fine and coarse aggregates shall meet the requirements of the AREMA
Specifications for Aggregates, Part 1, Section 1.3, Chapter 8 of the AREMA
Manual.
B. Aggregates shall be natural aggregates complying with ASTM C33 Class 4S. The
maximum combined coarse aggregate percentage wear shall not exceed
39 percent.
C. The manufacturer shall provide evidence that concrete containing aggregate from
the proposed source with a cement content and alkali burden similar to the job mix,
has a satisfactory service history of at least 5 years. This evidence shall include
structures requiring a Class 4S aggregate.
D. The maximum size of aggregate shall be ¾”. If the coarse or fine aggregate is
supplied in more than one size, each size shall be stored separately.
a. A separate test shall be conducted with each job cement and the
results shall conform with ASTM C33 at three and six months.
1) The flow rate at 30 days shall not exceed 1.5 mm per day.
Proceedings 6th International Conference on Alkalis in
Cement, Danish in Concrete Institute, Copenhagen, 1983.
2.05 WATER
A. Water in mixing concrete and washing aggregates shall be potable and free of
injurious amounts of oil, acid, alkali, inorganic matter, or other deleterious
substances, that may be harmful to concrete or steel as specified in
AASHTO T-26.
1. In addition, the mixing water, including that portion of the mixing water
contributed in the form of free moisture on the aggregates, shall not contain
a chloride ion content greater than 400 ppm.
2.06 ADMIXTURES
4. Water reducing admixtures shall only be used with the approval of the
Engineer. They shall conform to ASTM C494, Types A, B, D, or E.
5. Other mineral admixtures shall not be used, except for Class F Flyash as
noted below, unless mix and quality control program are specifically
approved by the Engineer.
6. Class F Flyash, if used, shall conform to ASTM C618. The properties shall
not exceed the following:
A. General:
2. The wires shall comply with ASTM A881 or stress relieved wire complying
with ASTM A421.
7. Tendons shall not be contaminated with mud, oil, grease, or chloride salts.
8. Loose rust shall be removed during stringing and tendons pitted due to
corrosion shall not be used.
B. Pretensioning:
1. During stringing, tendons shall not become contaminated with form release
agent.
2. Each tendon shall be individually tensioned with the same initial force of
between 5 percent and 20 percent of the final force using, a hydraulic jack.
C. Detensioning:
a. The forms shall be free to move and the stress in all tendons shall
be transferred at the same time and the same rate.
2. If any tendons break during, curing, all ties shall be load tested in Rail Seat
Positive in accordance with Paragraph entitled “Acceptance Load Testing”
in Article “Testing of Ties”, starting with the ties from the form adjacent to
the abutment where the tendon broke and moving towards the other
abutment, when a point on the bed is reached at which all ties from one
form pass the test, the remaining ties shall be accepted without further load
testing.
A. Rail fastening system shall be resilient, thread-less and adjustable in three steps
without dismantling the fastener. The three steps shall be:
C. Configure fasteners so that the rail clip can be installed or replaced in the field by
one person using standard readily available track tools. Clips shall also be capable
of being installed by commercially available automated equipment.
D. Configure fasteners so that when the rail clips are retracted, the rail may be lifted
vertically until it is completely free of the fastener without disturbing the horizontal
or vertical alignment of the fastener.
E. Fasteners shall have, on both sides of the rail base, a positive means of preventing
more than 1/8 IN total lateral movement of the rail base relative to the fastener in
case of failure or loosening of one or both rail clips. The positive means shall
extend at least 3/8 IN above the base of rail in the installed position.
F. Fasteners shall be Pandrol “Fastclip” or approved equal. Rail clips, insulators and
tie pads shall be pre-assembled on cross tie at manufacturer’s plant.
G. Rail Clips:
2. The minimum vertical hold down force for spring clips shall be 2,500 LBS
with total minimum force of 5,000 LBS per rail fastener assembly.
H. Insulators:
1. An insulator shall be used between the rail clip, shoulder insert and the rail
to position rail to the proper gauge, provide electrical insulation, reduce
abrasion, and transfer the rail loading to the rail clip and shoulder insert.
1. Provide rail seat pads compatible with the rail fastening system with a
shape which provides positive means of preventing movement of the pad
parallel to the rail. Pads must comply with SCRRA Engineering Standard
ES2363.
2. Alternate designs of rail seat pads shall be considered, provided they have
successful history of performance of at least three years service under
comparable service conditions.
J. Iron Shoulders:
1. Iron Shoulders shall be Pandrol cast shoulders for “fast clip” or approved
equal, sized for 136 lbs., 6” IN base rail dimension, with adaptive insulators,
pads, and clips
f. The shoulders and test specimens may not be reheated more than
once.
1) All fins shall be removed from the vertical faces of the head
of each shoulder.
2) Fins across the top of the head shall not exceed 1/32 inch
and below the head, fins shall not exceed 1/16 inch.
3. Iron shoulders shall be free of mud, oil, loose rust and other contamination
when cast into ties. They shall be rigidly secured in the forms during
casting and shall not move within the concrete when the securing device is
released.
4. Location within the ties shall comply with the tolerances on the tie Plans.
5. Ductile iron shoulders shall conform to the dimensions on the Plans issued
by the fastening clip suppliers.
K. Guard Rail Inserts: Inserts for guardrail concrete ties shall be as shown on SCRRA
Engineering Standards ES2406 or ES2407 or approved equal.
L. Neoprene Pads: Neoprene Pads cast into the bottom of the tie for use on bridge
decks in certain applications as indicated in the Contract Documents shall be as
shown on SCRRA Engineering Standards ES2403 or ES2407.
1. Alternative designs of concrete ties will be considered if they have the same
general profile, and length.
B. Dimensions:
1. General:
2. Cross Ties:
2. The minimum flexural performance requirements for the concrete ties shall
be as follows:
A. The concrete tie and elastic fastener shall provide longitudinal and lateral rail
restraint as specified in Section 4.6 and Section 4.7, Chapter 30 of the AREMA
Manual.
A. Each concrete tie, together with its elastic fastening, shall comply with Section 4.8,
Chapter 30 of the AREMA Manual.
A. Prior to approval of the concrete tie design, tests specified in Section 4.9, Chapter
30 of the AREMA Manual, unless otherwise modified by this Section, shall be
performed at testing facility approved by the Engineer and results provided to the
Engineer.
1. Surface Finishes.
3. Two ties which, in the opinion of the Inspector, show the required bottom
surface finish and two ties which in the opinion of the Inspector show the
maximum allowable rail seat defects shall be set aside as comparison
standards for acceptance of ties.
4. The bottom surface of each tie shall have a rough struck, leveled surface.
5. The surface of the rail seat shall have a smooth, formed finish not inferior
to the comparison standards.
b. The rail seat flatness shall not exceed a 1/32 inch difference across
any part of the rail seat.
1) When referring to voids and rail seat flatness in the rail seat
area, the rail seat will be defined as "area between adjacent
shoulders and edge of tie to edge of tie" and the area
adjacent to the shoulder and 3/8 IN beyond the face of the
front face of the shoulder.
6. All ties will require a lateral resistance pattern to be placed on the side of
the tie.
a. The Engineer will review for approval the design, but not provide
the design of this pattern.
b. The tie shall provide a minimum lateral in a single tie push test of
5,000 pounds.
c. The tested tie must be in track on a major heavy haul railroad with
adequate ballast depth.
7. Other formed surfaces shall be smooth and holes shall not exceed 1/4 inch
in depth and diameter.
a. Ties with a limited number of holes up to 3/8 inch diameter but not
exceeding 1/4 inch in depth will be accepted providing that holes
are filled with a mixture of 3 parts washed sand, 1 part cement and
1 part SBR latex measured by volume or other accepted material.
8. Holes in tie ends shall not exceed 3/8 inch diameter and 1/2 inch in depth
or 1/4 inch diameter and 1 inch in depth below the general surface level of
concrete.
11. Prestressing wire shall not protrude more than 1/8 IN beyond the tie end
and shall not have ragged ends, which would be hazardous in handling.
12. The surfaces where fastening components bear on the iron shoulders shall
be 100 percent free from concrete or other foreign materials.
c. Shoulder height.
g. Wire location.
2. A "Go and No Go" gage is the basis for acceptance and rejection. No
interpretation of a gage is acceptable.
4. When new forms, modified forms or repaired forms are used, the first tie
cast in each cavity shall be checked with Go and No Go gages and normal
measuring equipment to insure conformity with dimensional tolerances on
the tie Plans.
5. All ties selected for routine acceptance load testing shall be checked as
described in this Specification.
7. Wire pattern for all ties on both ends shall be visually inspected every day.
1. All acceptance load testing shall be carried out on the day that detensioning
is performed. Vendor must provide sufficient notice to the Engineer so as
to allow for SCRRA Inspectors to be present during acceptance load
testing.
2. Production Start-up Testing: From the first bed cast under any contract, all
the ties from one form, selected at random, shall be load tested as follows:
c. If the ties meet these test requirements, further beds may be cast.
d. If any tie fails to meet the test requirements, two further ties shall
be taken from the same line and, if either of these ties fails to meet
the test requirements, each tie in the line shall be individually tested,
excluding the bond development test.
1) One further bed shall then be cast and the test procedure
repeated.
3) If any tie fails to meet test requirements, two further ties shall
be taken from the same line.
b. All ties from one form, selected at random from each bed cast, shall
be load tested as follows:
c. Every sixth (6th) tie selected for test shall additionally be tested as
follows:
1) If either of these ties fails the test, each tie in the line shall
be tested.
e. One tie per day shall be selected at random from ties subject to Rail
Seat Positive test and additionally tested for bond development.
f. One tie per day shall be selected at random from ties subject to Rail
Seat Positive Test and additionally tested for Tie Center Negative
Moment.
1. The tie shall be supported in a hydraulic testing machine with loading points
so arranged that the load is applied at right angles to the base of the tie
midway between the supporting pads. Test configuration shall be in
accordance with Chapter 30 of the AREMA Manual.
2. A test load of 52 kips shall be applied at a rate not exceeding 10 kips per
minute and maintained for at least three minutes to permit proper
inspection. Both sides of the tie shall be inspected.
3. A tie will be considered to have failed the test if at the 52 kips test load, it
contains a structural crack when viewed under 5-power magnification. The
illumination at the surface shall be not less than 125 FT candles.
3. A test load of 29 kips shall be applied at a rate not exceeding 5 kips per
minute and maintained for at least three minutes to permit proper
inspection. Both sides of the tie shall be inspected.
2. Dial gages reading, to 0.001 inch shall be attached to the tie at the end
being tested, to measure any movement relative to the tie of the outermost
wire in each of the bottom corners of the tie.
3. A test load of 78 kips shall be applied at a rate not exceeding, 5 kips per
minute and maintained for a period of five minutes.
b. If during this test, a structural crack more than 3 inch long occurs,
the test tie shall be rejected after completion.
2. A test load of 12 kips shall be applied at a rate not to exceed 5 kips per
minute and maintained for at least 3 minutes to permit proper inspection.
Both sides of the tie should be inspected.
2. A test load of 8 kips shall be applied at a rate not to exceed 5 kips per
minute and maintained for at least three minutes to permit proper
inspection. Both sides of the tie shall be inspected.
I. Electrical Short:
2. If any tie fails this test, all ties from the same line shall be individually tested.
J. Test Reports:
f. Tie first structural crack loads, rail seat positive and rail seat
negative.
2. The manufacturer shall retain for a period of 10 years all test certificates
provided by suppliers and outside testing laboratories.
2.14 INSPECTION
A. Inspectors shall have access, during any and all working hours, to all parts of the
manufacturer’s plant involved in tie production and to those parts of suppliers
plants engaged in producing materials or components for use in the ties.
B. Inspectors shall access to the results of all tests carried out by the manufacturer,
suppliers and outside testing laboratories.
A. When handling ties in the plant or yard, they shall not be dropped or otherwise
damaged.
1. Ties shall be stacked on firm level ground, not more than 20 ties high and
supported on dunnage at the rail seats only.
2.16 IDENTIFICATION
A. Each tie shall be marked with indented or raised letters or numerals to identify the
manufacturer, SCAX designation, form designation and date/month/year of
manufacture as detailed on the SCRRA Engineering Standard Plans ES2402,
ES2403, ES2406 or ES2407 as appropriate.
PART 3 - EXECUTION
A. Quality Control:
3. The Engineer reserves the right to examine any equipment used for any
manufacturing process at any stage of tie production.
c) Mold Certification.
d) Document control.
p) Strength testing.
6. Production Program:
1) Plant layout.
5) Material handling.
7) Curing method.
9) Method of vibration.
13) Plan for handling ties from finished product to assigned rail
cars or alternate transportation arrangements.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Vendor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 33
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for the
Wood Railroad Ties to be furnished in accordance with Contract Documents or
required by the Engineer.
B. Work included in this Section encompasses work necessary for the manufacturing,
production and handling of wood switch ties, crossties, and grade crossing ties.
1.02 REFERENCES
C. RTA: Railway Tie Association – Specifications for Timber Crossties and Switch
Ties.
1.03 DEFINITIONS
A. Anti-Splitting Device – Any device applied to the end or near the end of a tie or
timber such as anti-splitting iron, dowel or nail plate to reduce its splitting.
B. The word “Vendor” used in this Specification shall mean the Contractor.
C. Boulton Drying Process – A process for drying wood by removing moisture from it
by heating in preservatives under sufficient intensity of vacuum to evaporate water
from the material at the temperature of the preservative used.
E. Empty Cell – A treatment in which the cell walls in the treated portion of the wood
remain coated with preservative, the cell being empty or only partially filled.
F. Hardwood – One group of trees (deciduous) which have broad leaves. The term
has no reference to the hardness of the wood.
G. Softwood – One of the group of trees (conifers) which have needle-like or scale-
like leaves. The term has no reference to the softness of the wood.
1.04 SUBMITTALS
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
C. The Vendor shall submit wood railroad ties packaging, loading, shipping, and
handling method.
D. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality wood railroad ties included in the Schedule of
Quantities and Prices.
E. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing wood railroad ties to Class 1 Freight, passenger
or commuter railroads.
A. Vendor’s Quality Control Program (QCP) shall be in accordance with the AAR M-
1003 or SCRRA approved equivalent quality control program.
C. Ties may be inspected by SCRRA, at suitable and convenient times and places
including points of manufacture, shipment, or destination.
D. SCRRA reserves the right to examine any equipment used for any process or
method of treatment at any stage of tie production.
E. Material not meeting the requirements of this Specification shall not be used in the
Work.
F. SCRRA shall have access to Manufacturer’s plant during normal working hours
and all Project related procurement and production records for inspection any time
during the Contract period of performance.
A. Tie shall be delivered to any point along the lines of the SCRRA rail track, as
specified in each shipping release. Ties in truckload quantities will be unloaded
upon two working day’s notice by the Vendor. All unloading operations will take
place in active railroad corridors. SCRRA will assist the Vendor in unloading the
ties and will provide necessary equipment for the unloading. SCRRA will provide
an Roadway Worker-In-Charge (RWIC) for on-track safety for the unloading of the
ties in the right-of-way. The RWIC will provide job briefing and safety protection to
assure the Vendor a safe work environment and all Vendor personnel will be
required to attend the job briefing.
B. Banding of ties by length or grade for shipment shall be done by applying bands in
a tight manner (2,500 pounds of tension) to prevent warping, splitting, and slipping
during storage or shipment. Two steel bands per bundle (T = 5,450 pounds,
1¼”x0.029” or better) shall be applied within one foot of each end of cross ties or
switch ties. Three bands shall be applied to bundles of switch ties. No more than
9 switch ties shall be bundled together. No more than 25 cross ties shall be
bundled together.
C. No steel cables, steel rods, chains, or wooden strips, or any other sticker material
shall be shipped in any bundle to SCRRA.
D. All rejects shall be marked with an “X” on the end. This is to preclude the accidental
shipment of less than grade ties to SCRRA. Treated ties not handled directly from
tram to car shall be carefully and neatly stored. Different size classifications shall
be kept separate, and all bundles or stacks shall be marked with SCRRA, grade
or length, and treatment date. Ties shall be stacked to ensure that tie straightness
is not impaired during temporary storage. Treated stringers shall be placed
underneath all stacks of treated ties. No loose windrows of SCRRA treated ties
shall be allowed. Shipments shall be made from the oldest stacks first. If any ties
become excessively bleached during storage, they shall be retreated or replaced
by the supplier. Yard drainage conditions shall provide rapid drainage of water
from beneath stacks of treated ties. Storage areas shall be kept free of grass and
weeds to aid free flow of air and to minimize the possibility of fire. The Vendor
shall be liable for all fire damage. A minimum 10 foot weed-free zone shall be
maintained around SCRRA stored inventory at all times. Care shall be exercised
in handling of SCRRA ties for storage or shipment to prevent damage.
E. Ties shall be stored to avoid contamination of water and soil by the ties.
F. Long-term tie storage shall not be located within 250 feet of an open road crossing
or residences.
G. Ties temporarily located within 250 feet of a public road crossing or residences
shall be covered by an impervious sheet material to control odor and vapor emitted
by the crossties by SCRRA.
PART 2 - PRODUCTS
2.01 GENERAL
A. Wood railroad ties shall be new and conform to SCRRA Engineering Standards.
A. The following hardwood species can be used for cross ties, switch ties and grade
crossing ties:
C. Oak and elm ties shall be of compact wood throughout the top fourth of the tie.
D. All cross ties shall be the full length specified; double end trimmed, and should
have full body and full face.
1. Ties with greater than 1” of wane within the 20” and 40” rail-bearing
sections, when measured from the center of the tie, are not acceptable.
E. Vendor shall provide a maximum of 50 percent of the ties from oak-hickory species
and the remaining 50 percent from mixed hardwoods from list of ties specified
under Attachment A, Part E, Section 1 through 4.
1. Oak ties must be air seasoned unless otherwise directed by SCRRA and
preapproved and specified in writing.
A. All wooden ties shall be made from sound, straight, live timber and shall be free
from any defects that may impair their strength or durability, such as bark, splits,
shakes, large or numerous holes or knots, pitch seams, pitch rings, slanting grain
or other imperfections.
B. All ties shall be well sawn on all four sides and cut square at the end to the full
dimensions specified.
1. All ties shall be straight and opposite faces shall be true and parallel, and
with all bark entirely removed.
a. Timber Cross Tie: When a straight line from a point on one end to
a corresponding point on the other end is no more than 1-1/2” from
surface at all points.
b. Timber Switch Ties: When straight line from a point on one end to
a corresponding point on the other end is no more than 2” from the
surface at all points.
D. A tie is not well sawn when its surfaces are cut with score marks more than ½”
deep, or when its surfaces are not even.
E. The top and bottom of a tie shall be considered parallel, if any difference in the
thickness at the sides or ends does not exceed ½”.
F. For proper seating of nail plates, tie ends must be flat and will be considered
square with a sloped end of up to ½”, which equals a 1 in 20 cant.
2. This application should enable the plate to hold both vertical and horizontal
splits.
6. All anti-split end plates shall have rounded corners and a smooth perimeter.
B. Embossed on all end plates will be “SCRRA” and manufacturer name followed by
the year of manufacture and Treating Plant. End plates will be installed with the
letters “SCRRA” upright with the tie oriented with heartwood down.
2.05 DIMENSIONS
A. All cross ties shall have a 7”x 9” cross-section and shall be double end trimmed,
unless otherwise ordered.
1. Ties will be ordered as 8’-6”or in one (1) foot increments from 9’-0” to 24’-
0”.
1. Ties with thickness and width more than ¼” thinner or narrower than
specified will be rejected. Ties over 1” longer shall be rejected.
2.06 PRESERVATIVE
1. The creosote and oil shall be thoroughly mixed in the working tank until the
mixture is of uniform composition. (Note: use of treatment with P-2, 7lbs /
cu ft is an approved equal).
B. The residuum oil shall be approved asphalt base petroleum residuum oil.
1. It shall be free from water and any foreign substance that might interfere
with its penetrating qualities.
2. The flash point of the residuum oil shall not be less than 210˚F as
determined in the Cleveland Open Cup.
3. The viscosity of the residuum oil shall be such that a blend of 50 percent
residuum oil and 50 percent creosote shall have a viscosity exceeding 50
seconds Saybolt Universal 180˚F.
4. BS&W shall not exceed one (1) percent and the creosote oil mixture shall
show no sludge formation upon standing. (Note: AWPA P4 is acceptable
as an approved equal for residuum oil).
B. Rejection of ties for holes and knots. All such holes and knots as defined shall be
allowed if they occur outside the sections of the tie between 20” and 40” from its
middle.
1. A “large hole” is any hole more than ½” in diameter and 3” in depth within
the rail bearing area, or more than 1” in diameter and 3” deep outside the
sections of the tie between the 20” and 40” rail bearing area measured from
the center of the tie.
3. A “large knot” within the rail bearing area is one whose average diameter
is more than 1/3 the width of the surface on which it appears. “Numerous
knots” are any number, which, in total, equal a large knot in damaging
effect. A cluster of knots will be judged as if it were a large knot in damaging
effect.
C. Ties with shake more than 1/3 the width of the tie, and nearer than 1” to any
surface, will be rejected.
D. Except in woods with interlocking grain, ties with a slant grain in excess of 1 in 15
will be rejected.
E. Ties with continuous checks whose depth in a fully seasoned and/or treated tie is
greater than ¼ the tie thickness and longer than ½ the length of tie will be rejected.
F. Any other imperfections that are within the limits of current AREMA and RTA
Specifications will be allowed.
2. A split more than ¼” wide and/or 9” long on the face on which it occurs in
a seasoned cross tie will be rejected.
H. Bark seam or pocket is a patch of bark partially or wholly enclosed in the wood.
1. Bark seams will be allowed outside the rail bearing area provided they are
not more than 2” below the surface, ¼” wide, and not more than 5” long.
I. Ties with heart – checks that go into the tie plate area will be rejected if the check
is more than a cumulative ½” wide or if the check causes the plate area to be
concave or convex.
J. Holes:
1. Ties having solid holes on any surface within the rail bearing areas greater
than ½” diameter and greater than 3” deep will be rejected.
2. Ties having solid holes on any surface outside the rail bearing areas
greater than 1” in diameter or greater than 3” deep will be rejected.
3. Stump pull will be graded the same as a split in the end of a tie.
4. A stump pull that goes into the interior of the tie more than 5” will be
rejected.
5. Numerous holes are defined as having any number equaling a large hole
in damaging effect. Such holes may be caused in manufacture or
otherwise.
PART 3 - EXECUTION
3.01 GENERAL
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor at phone number 909-468-9729, 48 hours prior to the date of delivery.
A. Treating plant shall be equipped with the thermometers and gauges necessary to
indicate and record accurately the condition of all stages of treatment, and all
equipment shall be maintained in acceptable, proper working condition.
B. All green ties should be checked periodically for moisture content prior to going in
the cylinder.
1. Twenty (20) borings per charge shall be taken from cross ties, so that the
moisture content level can be measured, to determine the amount of water
that is to be removed from the crossties.
3.05 BOULTONIZING
B. When boultonizing, the oils shall cover the material in the cylinder.
1. The temperature of the oil during the conditioning period shall not exceed
210˚F.
3. The intensity of the vacuum or the temperature of the oil, or both, shall be
adjusted so as to regulate the evaporation of the waters.
4. The conditioning shall continue until the materials are sufficiently heated
and enough water removed from the cylinder before an empty-cell process
is applied for pressure treatment.
A. Treatment shall be by the empty cell method with a creosote/coal tar solution or
creosote/petroleum (50percent-50 percent) solution in accordance with AWPA
Standard P-2, P-3, and P-4. The preservative solution shall be tested monthly
according to AWPA Standard A-1 with a copy of the results forwarded to the
SCRRA representative. In no case shall treatment be less than that required for
AWPA U1, UC4B.
1. The preservative shall be introduced until the cylinder is filled while the air
pressure is being maintained during the filling operation.
D. The temperature of the preservative during the entire pressure period shall not be
more than 210˚F but shall average at least 180˚F.
A. No charge shall contain less than 75 percent or more than 110 percent of the
quantity of preservative specified for the class of material except when the
character of the wood in any charge makes these requirements impracticable
despite treatment to refusal.
3.09 PENETRATION
A. Penetration of ties shall not be less than the following for at least 80 percent of the
pieces bored in each charge.
B. Penetration of ties shall be determined by boring not less than two (2) ties in each
tram in each charge or more than 20 ties per charge.
E. Any holes, which may be bored, shall be filled with tight fitting treated plugs.
A. In handling treated material, extreme care shall be used to avoid damage to the
edges of the timbers or breaking through the portions penetrated by the treatment
and exposing untreated wood.
B. The use of peaveys, timber dogs, picaroons, log hooks, or other pointed tools shall
be such as not to break through the treated portion of treated timber.
A. The storage yard for seasoning shall be in the open where the air current will
circulate freely; shall not be in a low humid situation if it can be avoided; shall have
good drainage; and shall be kept free from vegetation and debris, especially from
scrap wood already infected with decay.
B. Treated materials shall be stored in a similar manner to untreated, but must not be
piled in same area with untreated materials.
3.12 STACKING
B. Alternate: If necessary to retard evaporation of moisture from the ties, they may be
stacked parallel on edge, using cross ties as separators.
3.13 BARKING
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Contractor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 34
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for
Elastic Rail Fasteners to be furnished in accordance with Contract Documents or
required by the Engineer.
1.02 REFERENCES
2. ASTM A689 - Standard Specification for Carbon and Alloy Steel Bars for
Springs
4. ASTM E18 - 08b Standard Test Methods for Rockwell Hardness of Metallic
Materials
1. BS EN 10089 - Hot rolled steels for quenched and tempered springs, grade
56SiCr7
1.03 DEFINITIONS
A. The word “Vendor” used in this Specification shall mean the Contractor.
B. Closure Rails – The rails between the parts of any Elastic rail fasteners layout,
such as the rails between the switch and the frog in a turnout
1.04 SUBMITTALS
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
C. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality Elastic rail fasteners Materials included in the list
of Elastic rail fasteners items as provided in the Schedule of Quantities and Prices.
D. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing Elastic rail fasteners material to Class 1 Freight,
passenger or commuter railroads.
F. Qualifying Tests: The Vendor or supplier must submit the results of the following
initial qualifying tests for equivalent fasteners:
G. Fatigue Tests:
1. The Vendor or supplier must submit the results of the fatigue tests used to
determine final acceptance of the clips from each heat of steel.
H. Shepherd Fracture Grain Size Analysis: The Vendor must submit the results of
the Shepherd Fracture Grain Size analysis.
I. Samples:
1. The Vendor or supplier must submit samples of the raw material used in
the production of the clips for independent verification, by SCRRA, of the
chemical, physical, and mechanical properties steel used in the production
of the clips.
1. The Vendor or supplier must submit mill test reports for each heat of steel
used in the manufacture of the clips furnished on a given order.
A. Vendor’s Quality Control Program (QCP) shall be in accordance with the AAR M-
1003 or SCRRA approved equivalent quality control program.
E. Final fatigue testing of the clips may be performed in the facility of a manufacturer,
or a distributor, or an independent testing laboratory. However, all fatigue testing
must be performed within the coterminous United States and subject to witness by
representatives of SCRRA. Notice of testing must be provided to SCRRA a
minimum of three weeks prior to the tests. A representative of SCRRA will select
the samples to be tested.
A. The Vendor shall load, transport, and handle the material in a manner which will
prevent damage to the material.
B. The material will be supplied to the SCRRA in accordance with the delivery
requirements, FOB Destination. Quantity of each supply will be as requested by
the SCRRA release document. The material when purchased is to be delivered to
the Los Angeles area at a place designated by the SCRRA. A complete Bill of
Material for each order will be submitted with modes, dates, contents, and
destinations of shipments clearly indicated. A complete shipping list with reference
to blanket purchase agreement, if applicable, will accompany all deliveries of
materials.
PART 2 - PRODUCTS
2.01 DESIGN
A. Clips must be Pandrol® brand type e-2055 (e-2056 for left hand application) elastic
rail clips or an equivalent in shape, size, function, and performance as generally
described in United States Patent No. 4,413,777, and as shown on SCRRA
ES2361 and ES2362. The equivalence of any alternative design, including the
chemical and physical characteristics of the material, must be established through
qualification by successful performance the tests described in AREMA Manual for
Railway Engineering, Chapter 30, Part 2.6, Test 5A – Fastener Uplift, Test 5B –
Fastener Longitudinal Restraint, Test 5C – Fastener Repeated Load, Test 5D –
Fastener Lateral Load Restraint, and Test 5E – Fastener Assembly Rotation. For
the purpose of conducting Test 5A – Fastener Uplift, the load “P” must be not less
than 5500 pounds for each pair of fasteners.
B. 'Pandrol' Brand Rail Clips form part of a 'Pandrol' Brand Rail Fastening System
and hold the rail to the tie, baseplate or other track support.
C. A new qualification test must be performed for each change in dimension or shape
of the clip, or a change in the chemical, physical, and mechanical properties of the
raw material used in the manufacture of the clip.
D. In lieu of performing the acceptance tests SCRRA may, at its sole discretion, may
accept a clip offered as an equivalent to the specified clip upon evidence of
satisfactory in-track performance for 10 years or more on a North American main
line carrying 40 MGT or more each year.
E. The supplier shall have a minimum of five years’ experience in supplying rail clips
and other track materials.
A. The raw material must be a fine-grained chromium allow spring steel with a
composition closely approximating SAE/AISI Grade 5160, or ASTM A689, or BS
EN 10089. Modifications to the basic alloy by the Vendor of the steel are required
to achieve the physical, mechanical, and performance requirements of this
specification.
B. Shepherd fracture grain size of the raw material must be seven (7) or greater.
C. Finished clips must possess a Rockwell C surface hardness not less than 44 or
more than 48 when tested in accordance with ASTM E18.
D. All pair of finished rail clips must produce a minimum resistance load of 5500
pounds before separation of the rail from the rail seat when tested in accordance
with AREMA Manual for Railway Engineering, Chapter 30, Part 2.6, Test 5A
Fastener Uplift.
2.03 MANUFACTURE
A. Rail clips must be formed from a round bar stock made from a fine-grained
chromium allow spring steel. The steel must be quenched and tempered during
manufacture to achieve the physical and mechanical characteristics specified, and
meet the requirements of the qualification tests.
A. Five clips produced from each heat of raw steel material must be tested after
manufacture for fatigue failure. In performing the test, a single clip must be fixed
in the test machine and a 2750-pound load applied at the toe of the clip. The clip
must then be raised 1mm above the neutral (2750 pound load point) and relaxed
to a point 1 mm below the neutral (2750 pound load point) through three million
(3,000,000) cycles (one cycle = neutral to raised position to lowered position to
neutral position).
B. The Vendor may use a test procedure similar to that described in Chapter 30, Part
2.6, Test 5A, of the AREMA Manual for Railway Engineering, or the Vendor may
the test described in Appendix I of Australian Standard 1085.19, or the Vendor
may use another test procedure provided that the clip moves through a distance
of 2mm, under a load of 2750 pounds at the mid-point of the range of flexure.
C. From the 5 clips selected, if two clips in a row break, all clips manufactured from
the heat of steel tested must be rejected. If two clips in a row pass, all clips from
the heat of steel tested, may be accepted.
D. A failure is recorded when a tested clip exhibits a loss of elasticity, breaks, or the
neutral position load drops below 2750 pounds during the test.
E. Table below lists the possible test combinations and the action to be taken:
Table
Test Number and Results Action
1 2 3 4 5
Heat of Steel Passes All Clips from Heat
Pass Pass
Accepted No Further Tests Required
Heat of Steel Passes All Clips from Heat
Pass Fail Pass Pass
Accepted No Further Tests Required
Heat Fails All Clips from Heat Rejected No
Pass Fail Fail
Further tests permitted
Heat Fails All Clips from Heat Rejected No
Pass Fail Pass Fail Fail
Further tests permitted
Heat Fails All Clips from Heat Rejected No
Pass Fail Pass Fail Pass
Further tests permitted
Heat Fails All Clips from Heat Rejected No
Fail Fail
Further tests permitted
Heat of Steel Passes All Clips from Heat
Fail Pass Pass
Accepted No Further Tests Required
Heat of Steel Passes All Clips from Heat
Fail Pass Fail Pass Pass
Accepted No Further Tests Required
Heat Fails All Clips from Heat Rejected No
Fail Pass Fail Pass Fail
Further tests permitted
F. At the conclusion of the fatigue test above, the pair of clips that have passed the
fatigue test must prevent separation of the rail from the rail seat when a minimum
uplift load “P” of 5500 pounds in accordance with AREMA Manual for Railway
Engineering, Chapter 30, Part 2.6, Test 5A - Fastener Uplift.
G. The clips must not break when applied or removed with a 8 lb to 12 lb sledge
hammer provided that the clips are not over-driven.
2.05 TOLERANCES
A. The clips shall conform to the dimensions on SCRRA drawing and shall fit the
relevant standard 'Pandrol' inspection gauges and/or direct measuring fixture.
B. Alternatively, a Vendor may provide its standard dimensional tolerances and the
means used to measure each clip for conformance to the standard to SCRRA for
review approval.
2.06 INSPECTION
A. All clips must be inspected for visual defects, incomplete formation, damage, or
dimensional non-conformance.
A. A minimum of five clips from each heat of steel used for Vendor of the clips must
be tested. SCRRA may, at its expense, select additional clips from any order and
submit them to the fatigue test described in this specification. SCRRA will provide
the Vendor or supplier a minimum notice of three weeks in advance of the date on
which the test will be performed. The Vendor or supplier may, at its expense, send
a representative to witness the test.
B. The Vendor must replace without charge any unused portion of an order that does
not pass the fatigue test administered by SCRRA with clips that conform to the
requirements of this specification.
A. The clips must be free from burrs which may be considered harmful when handled
or affect efficient assembly of the clip. Marks caused by the forming tools shall be
smooth and free from sharp indentations.
B. All clips must be Hot Dipped Galvanized in accordance with ASTM A123.
A. Each clip must be stamped with a code indicating the date of manufacture, the
manufacturer, and the plant in which the clips have been made. A mark indicating
the heat of steel used must also be included if the above information is not
sufficient to trace the clip to a specific heat of steel.
B. Final fatigue testing of the clips may be performed in the facility of a Vendor, or a
distributor, or an independent testing laboratory. However, all fatigue testing must
be performed within the coterminous United States and subject to witness by
representatives of SCRRA. Notice of testing must be provided to SCRRA a
minimum of three weeks prior to the tests. A representative of SCRRA will select
the samples to be tested.
PART 3 - EXECUTION
3.01 GENERAL
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor at phone number 909-468-9729, 48 hours prior to the date of delivery.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 72 00, Trackwork or Section 34 72 20, Track Shifting, Relocation,
and Resurfacing and no separate measurement and payment will be made to the
Contractor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 36
PART 1 - GENERAL
1.01 SUMMARY
A. This Section specifies the material requirements and performance criteria for the
Precast Concrete Grade Crossing Panels to be furnished in accordance with
Contract Documents or required by the Engineer.
1.02 REFERENCES
10. D624: Standard Test Method for Tear Strength of Conventional Vulcanized
Rubber and Thermoplastic Elastomers
11. D2137: Standard test Methods for Rubber Property- Brittleness Points of
Flexible Polymers and Coated Fabrics
1.03 DEFINITIONS
A. The word “Vendor” used in this Specification shall mean the Contractor.
B. Field Side – End of tie plate designed to be located on the opposite side of the rail
from the centerline of track
C. Gage Side – End of tie plate designed to be located closest to the centerline of
track
D. OTM – A general term referring to all miscellaneous materials other than rail and
ties
1.04 SUBMITTALS
B. The Vendor shall submit certificate of compliance that the material delivered is in
compliance with the specification within 60 days of approval of payment.
C. The Vendor shall submit for SCRRA’s review and approval quality control and
quality assurance plans and related certifications such as ISO 9001, “six sigma” or
equivalent demonstrating that the Vendor has the processes, personnel and
systems to produce high quality precast concrete grade crossing panels included
in the Schedule of Quantities and Prices.
D. The Vendor shall submit data documenting past performance and projects within
the last ten (10) years furnishing precast concrete grade crossing panels material
to Class 1 Freight, passenger or commuter railroads.
F. Submit Certificates of Compliance for all precast concrete grade crossing panels.
Include material qualification test reports for materials, components, and
assemblies.
A. Vendor’s Quality Control Program (QCP) shall be in accordance with the AAR M-
1003 or SCRRA approved equivalent quality control program.
A. The Vendor shall load, transport, and handle the material in a manner which will
prevent damage to the material.
B. The material will be supplied to the SCRRA in accordance with the delivery
requirements, FOB Destination. Quantity of each supply will be as requested by
the SCRRA release document. The material when purchased is to be delivered to
the Southern California area at a place designated by the SCRRA. A complete
Bill of Material for each order will be submitted with modes, dates, contents, and
destinations of shipments clearly indicated. A complete shipping list with reference
to blanket purchase agreement, if applicable, will accompany all deliveries of
materials.
1.07 WARRANTY
A. The Vendor shall warranty the precast concrete grade crossing panels for a
minimum ten years against defects in materials and workmanship.
PART 2 - PRODUCTS
2.01 GENERAL
A. Precast concrete grade crossing panels shall be new and conform to SCRRA
Engineering Standards ES4201.
A. Precast concrete grade crossing panels shall be lag-down heavy duty panels.
B. Precast concrete grade crossing panels shall be designed for use on 10 feet wood
track ties and ballast track.
C. Precast concrete grade crossing panels shall have flangeways not less than 2½”
in width and be electrically isolated to prevent shunt currents.
D. Precast concrete grade crossing panels shall be sized such that when installed,
the top of the panels is at the top of rail elevation.
E. Panels shall be of the type which fastens to the timber ties utilizing a lagging screw
system which fastens from the top down. The lagging screws shall be
mechanically galvanized with zinc coating in a room temperature process, without
electricity and without heat.
F. Rubber flangeway filler shall be designed to match the precast concrete crossing
panels and rail fastening system.
G. Grade crossing surface systems, including any flangeway (gage and field side)
filler material components, must be electrically non-conductive so as not to
interfere with train control or crossing signals.
H. Each gage panel shall incorporate a 3” UHMW shunt break to assure electrical
isolation. End angle for gage panels shall have 3” minimum gap to improve shunt
resistance.
I. Concrete Crossing Panels shall be by Omega Industries or approved equal for use
on SCRRA.
2.03 CONCRETE
C. Maximum water/cement ration shall be 0.44. Slump shall not exceed three inches.
D. Concrete sealant shall be used to prevent cracks and ion migration. Sealant shall
be applied to fresh concrete as an aid in curing, hardening, water proofing, acid
proofing and oil proofing each panel.
B. Steel angles shall be ASTM grade 36. The exposed steel shall receive one primer
coat.
4. Hardness – 75
C. The pre-attached flangeway filler shall allow for the removal of panels for
maintenance without damaging the flangeway filler or any other components
designed to hold the panel together.
2.06 FINISHES
A. All recess and minor concrete spalls are to be filled and finished to the panel
dimensions using the proper bonding agent and repair material. Surface of the
repaired area is to match the color and texture of the surrounding area.
B. The driving surface is to have a light broom finish or as approved by SCRRA. The
addition of water to the concrete surface finish during casting is not permitted.
2.07 MARKING
A. Each precast concrete grade crossing panel shall be marked with concrete imprint
for size of rail, weight of panel, Manufacturer’s ID, month/day/year of manufacture
and crossing type. End of each panel will be stenciled painted with size of rail,
weight of panel and crossing type.
A. During precast concrete grade crossing panel fabrication, perform the tests and
inspections specified in these Specifications.
PART 3 - EXECUTION
3.01 GENERAL
3.02 SCHEDULE
A. The Vendor providing the materials shall contact SCRRA’s Material Management
Supervisor at phone number 909-468-9729, 48 hours prior to the date of delivery.
4.01 MEASUREMENT
A. Work of this Section is considered incidental to work associated with project item
in Section 34 71 50, Highway-Rail Grade Crossings and no separate measurement
and payment will be made to the Contractor for Work of this Section.
4.02 PAYMENT
A. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 11 40
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section includes, but is not limited to, general procedures,
requirements, and incidental to the planning, manufacturing, installation, removal,
relocation, modification, testing, placing in service, and documentation of as-built
conditions of the various signal systems.
B. General:
C. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
B. The following General Orders (G.O.) or the most current General Orders of the
State of California Public Utilities Commission (CPUC) shall apply:
C. The following parts of the Code of Federal Regulations, Title 49, Transportation,
shall apply:
D. California Manual on Uniform Traffic Control Devices (CA MUTCD), Part VIII,
Traffic Control for Railroad and Light Rail Transit Grade Crossings, shall apply.
A. Provide all materials and installation services required for a complete working
signal system, as described herein, and as shown on the Contract Plans,
including any equipment not designated as being relocated or designated as
Owner-furnished or in these specifications.
B. All materials and equipment for installation and for interconnection of the various
signaling systems shall be fabricated, furnished, and installed as indicated on the
Contract Plans and specified herein.
C. The Contract Plans represent a final design utilizing systems, components, and
materials that meet the Project Specifications. Contractor may provide
equivalent systems, components, and materials subject to the approval of the
Engineer. If equivalent systems, components and materials are provided, the
Contractor shall provide an alternate detailed final design as specified herein
under Design Submittals.
D. Provide systems that are compliant with applicable rules and regulations of CFR
49, parts 234 and 236, and CPUC GO 75D. Refer to Design Submittals herein
for Contractor’s responsibility to indicate any corrections or modifications to the
Contract Plan’s final design that the Contractor may determine are required to
conform to these rules and regulations.
E. Be present at all design meetings held with the Engineer by a signal engineer
qualified in the application and installation of the signaling equipment the
Contractor proposes for use on this project.
G. Provide continuous train control and highway grade crossing warning during all
phases of rail construction. The work of the Contractor must not present a delay
to train operations, cause an unsafe signaling condition, or reduce the
effectiveness or quality of the existing or new grade crossing warning systems.
The Contractor shall submit, for approval by the Resident Engineer, its proposed
plan for providing alternate methods of crossing warning whenever the existing
automatic crossing warning devices are deactivated, altered, or modified to
accommodate construction work. Alternate methods shall conform to CFR 49,
Part 234, and all local ordinances.
H. Provide rail bonding for all new, temporary and relocated turnouts as shown on
the Contract Plans or as required by the Engineer. Provide rail bonding, as
necessary, to maintain existing systems during construction of all projects related
work, including the work of other disciplines.
I. Protect existing signal cabling and, where necessary, relocate existing cabling to
prevent damage during track installation and surfacing. If the Contractor
damages existing cabling, the Contractor shall be responsible for all repairs,
testing and replacement, if necessary, to existing cabling. Provide all new
signals, new foundations, new cabling, and other new equipment as shown on
Contract Plans. The Contractor shall remove and reuse existing signaling
equipment as indicated on the Contract Plans and in these Specifications.
K. Perform and document all tests and inspections in accordance with CFR 49
regulations, the AREMA C&S Manual, the Metrolink Signal Maintenance
Manual, and these Specifications.
P. Remove, salvage, retire, relocate, furnish, and install project related devices as
indicated on the Contract Plans, as described within the Project Specifications,
and as required to complete the Work.
R. Refer to Division 31, Earthwork and 01 14 49, Coordination with Utilities, for
requirements in locating and protecting existing utilities. Details of signal cable
runs, conduit runs, and pull box installations including number, size, and type of
cable are shown in the Contract Plans. Conduit runs and pull box locations, as
shown, are the preferred locations. In case of conflict between the systems
design plans and other Contract Plans, the systems design plans take
precedence as to detail, and in the event of conflict as to placement of
equipment, the Engineer will determine the correct placement.
S. All underground signal cables shall be in conduit, except for the final wire
connections made to the track.
U. Provide construction signal support and coordination of all work with other
disciplines including, but not limited to, track installation and removal, bridge
construction or reconstruction, rail and track renewal within crossings, installation
or change of track switches, clearing and grubbing. Contractor shall coordinate
all work with other disciplines that may affect the safe operation of existing
crossings and track circuits to prevent train delays or inconvenience to the public.
A. As used in these Specifications, the fail-safe principle shall mean that whenever
an equipment failure, human error or failure to act, or adverse environmental
condition affects the specified operation of a system involved with the safety of
life or property, that system shall revert to a state known to be safe.
1. Closed Loops: Fail-safe circuits shall employ the closed loop principle
and shall protect against open circuits, shorts, or any combination thereof.
3. Vital Circuits: All line circuits, which energize a vital relay, shall be two-
wire, double-break circuits and shall be energized from an ungrounded
direct current (dc) power supply.
2. Relay (vital as defined by the AREMA C&S Manual): Open coil, shorted
coil, or high contact resistance.
F. Seismic Zone Location of Work Site: Seismic Zone 4 as defined in the Uniform
Building Code.
1.07 SUBMITTALS
A. Do not begin any work without the prior submittal to and approval by the
Resident Engineer of the relevant personnel, plans and procedures.
C. Submit to the Engineer for approval, proposed design changes, plans, test and
inspection procedures, data sheets of proposed material, installation details,
Shop Drawings, mechanical Drawings, proofs of compliance with applicable
standards, and any other pertinent data required to fully demonstrate the
Contractor's proposed plan for the manufacture, installation, testing, and
maintenance of the various signaling systems. The Contractor shall provide
submittals within 30 calendar days after receiving Notice to Proceed.
E. Submit a detailed test plan for all systems a minimum of 60 days in advance of
placing any system in service. These test plans shall reflect the latest revisions
and changes approved by the Resident Engineer and made because of field
checks and conditions. The Contractor shall not proceed with the cutover or in-
service testing until the Engineer approves the test plans. Plans shall include, but
are not limited to:
2. Plan for point protection and fouling when crossover or turnouts are
installed or removed.
F. Prepare and submit a Signaling Construction Phasing Plan for each location
where a signal system is to be modified, installed, or removed. The Plan, as a
minimum, shall contain the following:
H. After a location is placed in service and prior to final acceptance of the project,
the Contractor shall submit as-built documentation as follows:
1. Submit four copies of all as-built circuit plans and documents to the
Resident Engineer within 3 business days.
3. Civil Drawings which show the physical location of all signal apparatus
and conduits, both along the tracks and perpendicular to it, and heights of
all signal structures within 60 calendar days.
J. Ensure that equipment used in the testing of wayside signal and grade crossing
warning systems and components shall be properly calibrated. Test meters and
other test apparatus shall have been inspected by a recognized facility that
performs calibrations a minimum of 6 months prior to performing required tests. A
sticker, or other documentation, must be made available for inspection at the
request of the Resident Engineer.
1.08 DELIVERABLES
A. Submit manufacturers' warranties, instruction sheets, and part lists supplied with
materials to the Resident Engineer prior to final acceptance.
operating railroad in the type and level of signal installation and testing work as
required herein.
C. Signal construction and installation personnel shall work under the authority of
the Signal Engineer. The Contractor’s signaling construction forces shall work
under the authority of a Signal Engineer.
2. Signal Engineer shall be responsible for all work under his charge and
must have the authority to remove any personnel from the project who
are not performing the work in a satisfactory manner. The Signal
Engineer shall obtain, review, and maintain documentation of the required
minimum experience, a copy of the Electrician’s license(s), and a record
of wage rate paid for each Signal Electrician that performs Signal or
Crossing Warning System work prior to that Electrician starting any Signal
related work. This documentation shall be always available for review by
the Resident Engineer upon request.
D. The Signal Managers shall report to and work under the direct authority of the
Signal Engineer and shall supervise and direct the work of all signal construction
and installation personnel.
E. Signal Engineer shall direct and organize the performance of all tests on
signaling equipment and systems, under direction of the Engineer, prior to
releasing the systems for service. The Signal Engineer shall be responsible to
ensure that all applicable test documentation other than that documentation
provided by the Engineer, is completed prior to, or immediately after, in-service
testing is completed.
including CPUC and FRA regulations and procedures. This demonstration shall
be by interview of the proposed Signal Engineer by the Engineer prior to
commencement of any work that may affect the signal system. The work of this
project includes working within constrained work windows on a live railroad
consisting of freight trains, inter-city passenger trains, and Metrolink commuter
trains. Candidate shall have a similar level of experience. The Engineer's
decision concerning the candidate's qualifications will be final. Begin no
signaling related work prior to obtaining Engineer’s approval of the Signal
Engineer. In addition, obtain the Resident Engineer’s approval of each Signal
Engineer prior to beginning any work that may affect the signal system. Obtain
approval of additional Signal Engineers as required depending upon the level
and type of work being performed.
I. The Resident Engineer reserves the right to disqualify any Signal Engineer,
Signal Manager, or Signal Electrician at any time during the Work. This right is at
the sole discretion of the Resident Engineer and is not subject to protest or
appeal.
J The Signal Electricians shall have a minimum 1,000 hours of experience in the
wiring and installation of railroad signal and grade crossing warning system
circuits, components, control equipment and associated devices including their
primary and backup power supply systems. Signal Electricians shall perform the
wiring, labeling and connection/continuity/resistance testing, as appropriate, of all
railroad signal and grade crossing warning system circuits, components, control
equipment and associated devices including their primary and backup power
supply systems. All Signal Electricians shall be licensed: Journeyman or Inside
Electricians or an approved equal. Signal Electricians shall be paid at the
prevailing wage rate for the locality of the construction.
K. All Contractor field personnel shall receive safety training in accordance with
Section 01 43 23, Contractor Qualifications and Requirements, 01 35 23, SCRRA
Site Safety Requirements, and 01 56 37, Worksite Security Requirements.
1. Submit four copies of all as-built circuit plans and documents to the
Resident Engineer within 3 business days.
2. Civil Drawings which show the physical location of all signal apparatus
and conduits, both along the tracks and perpendicular to it, and heights of
all signal structures within 60 days.
C. Annotate the As-Built drawing sets to show all approved circuiting and wiring
changes made during installation and testing of the location prior to placing it in
service, and any approved changes made after placement in service. Clearly
identify all changes on the Drawings using the "Red In"/"Yellow Out" convention.
Changes shall be dated and initialed by the Contractor's responsible Signal
Engineer. Identify the date that the location was tested and placed in service in
the revision block of the Drawings.
D. In addition to the as-built Drawings provided to the Engineer, one set shall be
bound and shall be kept in the instrument enclosure at a location and manner
approved by the Engineer. As-built Drawings shall be clean and legible. The as-
built Drawings shall not be removed from the field location after the location is
placed in service without the prior written approval of the Engineer.
F. Each circuit that continues to another drawing shall be annotated with drawing
number and routing information for the continuation of the circuit.
G. The circuit Drawings shall show all individual circuits. Typical circuits will not be
accepted.
H. The location plans shall show all cables installed with the number of conductors,
the size of conductors, the type of cable, termination points of conductors, and
the circuit on each conductor. Separate cable plans shall be drawn if cable
information cannot be shown in a neat and organized manner on the location
plans.
C. Signal cutovers will require coordination between the Contractor, Metrolink, other
railroads, as applicable, to keep train delays to a minimum.
A. Submit the Bid Item List for signal bid items as required under Section 01 29 73,
Schedule of Values, and in accordance with the following additional
requirements:
1. Bid Item List for the signal bid items shall include all interface circuits and
staging necessary to place the location in service at each stage, all
acceptance testing and transportation of materials, all equipment rental,
all pretesting and removal of old equipment.
2. Organize Bid Item List for signal bid items to assign a value to each signal
location. A location is defined as a grade crossing warning system, a
hazard detector system, an intermediate signal location, or a control
point.
1.13 WARRANTY
A. Provide warranties for all equipment and material covering parts and labor for
two years from the date equipment or material is accepted by the Owner.
B. All warranties shall comply with the requirements of Section 01 78 36, Warranties
and Guarantees, unless otherwise specified herein.
PART 2 – PRODUCTS
Design and construct fusing of all DC power supplies and circuitry according to
the following requirements:
1. Circuit breakers and fuses shall be the correct side-band rating for circuit
current interruption and shall protect the electrical equipment and circuits
from short-term and long-term overloads.
5. All branch feeds for a circuit shall be from the same fuse to prevent fuse
cascading due to branch fusing carrying loads for other circuits.
2. The PC wiring shall be organized so that wires serving the same function
shall be connected to the same terminal of PC cards. PC cards containing
the same circuitry and programming, where applicable, shall be
interchangeable between subsystems.
1. There shall be not more than one type of card file for each size of PC
card. The card file plug boards shall be registered to agree with the
registry of the associated PC card. PC cards shall not project beyond the
front of the equipment rack when mounted in the card file.
2. Card files shall be installed in dust-proof cabinets and protected with dust
covers.
3. Insulated cable clamping devices shall be located on the back of the file
in such a way that wires terminating in the files shall be installed in a neat
and secure bundle, rigidly supported, and protected to prevent chafing of
insulation. Cabling provision on the file shall permit wires to enter or leave
the file from both the right and left sides. Such cabling shall not restrict
access to the card file when the rear covers of the card files are removed.
A. Factory finish signal equipment with the exception signal system parts which are
stipulated as field finished in AREMA C&S Manual, Part 1.5.10, and aluminum
alloy and galvanized metal components. If manufacturer typically provides
factory painted finish for aluminum alloy and galvanized components, include
such information in equipment submittals for Engineer’s acceptance.
B. Finishes shall comply with AREMA C&S Manual, Part 1.5.10, signal equipment
manufacturer’s standards, and provisions specified herein. It shall be understood
that where AREMA C&S Manual, Part 1.5.10, uses the word “should” that the
word “shall” shall be substituted except as accepted by the Engineer in writing.
1. Finish terminal boards and interior of shelters with white gloss fire
retardant paint.
3. For signal system parts which the AREMA C&S Manual stipulates as
shop primed and field finish, shop prime in accordance with requirements
specified in Section 09 90 00, Painting and Coating and 09 96 23, Graffiti
Resistant Coating.
4. For signal system parts which the AREMA C&S Manual stipulates to
receive shop prime and finish coats followed by field finish coat,
coordinate shop finish coat with field finish specified in Section 09 90 00,
Painting and Coating and 09 96 23, Graffiti Resistant Coating.
A. Field finish as specified in Section 09 90 00, Painting and Coating and 09 96 23,
Graffiti-Resistant Coating and AREMA C&S Manual, Part 1.5.10. Exterior
surfaces shall receive a heavy duty finish system.
PART 3 – EXECUTION
3.01 INSTALLATION
A. Contractor shall make all necessary modifications to the existing signal system,
protect or relocate existing cabling, signals, switches, and signal shelters; and
modify associated signal and highway grade crossing systems to ensure the
existing signal system operates as intended during construction and installation
of the new signal system. Protect signal and highway grade crossing systems to
ensure train operations are not interrupted and safety is maintained.
B. Contractor shall take no action which will violate any rule or regulation as
specified by CFR 49, the General Code of Operating Rules, timetable
instructions, general order, bulletin, or special instruction; which will reduce the
integrity of the signal system; or endanger railroad personnel, the public, or
employees.
D. Ensure that equipment within the instrument shelters and relay cases is securely
anchored or otherwise fastened in enclosure upon completion of enclosure
installation. Securing equipment shall not negate the requirements to maintain
isolation between ground systems as otherwise called for in these Specifications.
E. An updated, detailed set of the approved signal design Drawings shall be kept at
each field location for equipment as it is placed in-service as system changes are
made.
A. For signal system parts which AREMA C&S Manual, Part 1.5.10, stipulates as
shop primed and field painted, field finish as specified in Section 09 90 00,
Painting and Coating and 09 96 23, Graffiti-Resistant Coating and AREMA C&S
Manual, Part 1.5.10, including requirement to apply one field coat prior to field
assembly and one field coat following field assembly.
4.01 MEASUREMENT
B. All work and services included in Sections 34 42 10, Coordination with SCRRA
Procurement Contractor; 34 42 38, Interlocking Controls; 34 42 40, Solid State
Coded Track Circuits; and 34 42 56, Signal Grounding; will be included in this
Section and are considered incidental to work under this Section and will be
measured by the unit or fraction thereof furnished and completed in accordance
with the Contract Documents and as measured by the Engineer.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
1.02 SUBMITTALS
1.03 WARRANTY
A. Because the manufacturer’s warranty for materials begins when the material is
received, the Contractor shall supplement the manufacturer’s warranty for the
amount of time elapsed between its receipt of the material and the Owner’s final
acceptance, and as required under Section 01 78 36, Warranties and
Guarantees. The supplemental warranty shall include all costs to repair or
replace material which is damaged while in Contractor’s care or fails prematurely
and as required under Section 01 78 36, Warranties and Guarantees. Make
arrangements for and pay costs of such repairs performed by and replacements
provided from the original equipment manufacturer.
PART 2 - PRODUCTS
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 42 10
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for all cable and wire required for signal and
signal power system wiring to wayside shelters, crossing shelters, junction boxes,
factory wired mechanisms and other signal equipment.
B. Related Specification Sections include but are not necessarily limited to:
1. Section 31 20 00 – Earthwork
1.02 REFERENCES
A. Material and workmanship shall be of the highest quality, assuring durability for
minimum life expectancy of 40 years. Cables shall be suitable for use in the
environment to be encountered on a railroad signal system, and shall be certified
for continuous operation, in wet or dry locations, with no conductor failing in
continuity or with loss of insulation to cross or ground less than one mega ohm.
1.04 SUBMITTALS
B. Product Sample: The Contractor shall submit one (1) foot of sample cable when
requested by the Resident Engineer. Resident Engineer shall make request in
writing prior to approval, if deemed necessary, to ensure the product data submittal
meets the specification.
3. All signal wire and cable furnished under this Contract shall be provided as
new and shall not be installed under this Contract if the manufacture date of
the cable exceeds 24 months prior to the Notice-To-Proceed date.
A. Shipping, storage, and handling shall be in accordance with AREMA Signal Manual,
Part 10.4.1.
B. During storage and handling, prior to final conductor termination, cable ends shall
be sealed to prevent the entrance of moisture.
PART 2 – PRODUCTS
A. Individual cable make-up and conductor sizes shall be as shown on the Contract
Plans.
B. Internal wire and cable shall conform to AREMA C&S Manual, Part 10.3.14, and the
following requirements:
C. Internal wire and cable insulation shall conform to AREMA C&S Manual Part
10.3.24 and the following requirements:
A. General
B. Track Wire
2. Track wire shall meet the requirements of AREMA C&S Manual, Part
10.3.15.
1. Wire and cable used for signals, switches, and express cable shall be
Okonite (EP) Armored Underground Signal Cable manufactured by Okonite
Co. or approved equal.
3. Armored cable shall be furnished with a 10-mil flat bronze tape between the
conductors and the outer jacket, helically applied, and adequately
cushioned from the conductors.
4. Armored cable shall meet the requirements of AREMA C&S Manual, Part
10.3.17.
D. AC Power Cable
2. Cable shall meet the requirements of AREMA Signal Manual, Part 10.3.16.
E. Modem Cable
4. Modem cable shall meet the requirements of AREMA Signal Manual, Part
10.3.17 except as specified herein.
A. Coordinate with the Engineer for Engineer’s inspections and tests at point of
production. The Engineer shall have the right to make inspections and tests, as
necessary, to determine if the wire or cable meets the requirements of this
Specification. The Engineer shall have the right to reject wire or cable that is
defective in any respect.
B. Provide, at the point of production, apparatus and labor for the following tests:
PART 3 - EXECUTION
3.01 INSTALLATION
A. General:
1. The installation of wire and cable shall conform to AREMA C&S Manual
Parts 10.4.1, 10.4.30, except as specified herein.
2. All external cable runs shall be in conduit in accordance with the Metrolink
Engineering Standards, and as called for in the Contract Documents.
10. Seal cable entrance openings in equipment enclosures and junction boxes
with either compression type fitting or pliable sealing compound after the
cable is in place. Use sealing compound to seal the area around cable
where the cable emerges from the end of a conduit or pipe. Seal and plug
all spare conduits. Seal around conduits where conduits enter enclosures to
prevent entry of vermin and insects.
11. Wherever multiple conductor cables are terminated, carefully remove the
outer sheath of the cable to a minimum point of 3 inches from the cable
entrance. At the end of the cable sheath or covering, apply two layers of
Scotch 88 plastic electrical tape or approved equal.
12. Terminate all cable conductors in number sequence from top to bottom.
2. Upon written request from the Contractor and only under extreme
circumstances because of installation hardship will installation of conduit(s)
be allowed to a depth of less than 36 inches and is subject to the Resident
4. Whenever any signal cable is to pass under the hot-mix asphalt concrete
(HMAC) underlay installed on the project, provide and install cable(s) in
conduit(s) with pull boxes in accordance with the Metrolink Engineering
Standards.
8. The Contractor shall ensure that cable(s), track wire, and conduit(s) shall be
installed per Contract Plans and Section 31 20 00, Earthwork.
9. Cables shall not cross one another when they are pulled into a conduit or
pipe; the conductors shall not be pulled tight or kinked in conduit fittings or
boxes. All cables to be installed in a conduit or pipe shall be pulled and
installed simultaneously.
10. All cables, except final connection of flex wires to rail, shall be installed in a
conduit system as shown on the Contract Plans and as required within the
Metrolink Engineering Standards.
C. Special Protection: Provide appropriate special protection for cables in areas where
the cables are unavoidably exposed to hazardous conditions, such as vibration or
sharp corners on equipment. Replace any cable that is installed but subsequently
damaged prior to acceptance because of the Contractor's failure to provide such
special protection.
D. AC Power Cable
1. Provide and install AC power cable dedicated conduit from the service
meters to the signal shelters and between signal shelters.
E. CABLE PULLING
2. Do not use poly rope for any mechanical means of pulling cable. Poly rope
stretches when subjected to high tension and can create a hazard. Manual
pulling (by hand) using poly rope is allowed. When using a mechanical
means to complete a pull, a Samson rope or equivalent, flat line, shall be
used, as it does not stretch in the same way that poly rope does, and
presents less of a hazard.
5. Establish the direction of the pull based on safe pulling tensions, sidewall
bearing pressure calculations and minimum bending radius for a specific
cable to be installed. Do not exceed the minimum bending radius at any
time. Follow the manufacturer’s instructions for the safe pulling tension and
determine if the cable pull requires a basket grip or a pulling eye attached to
the conductor. Basket grips or pulling eyes shall be attached to the pulling
rope or cable by an appropriately sized swivel head. Rod each conduit with
an appropriate size brush and mandrel to ensure conduits are properly fitted
and they are clean and free of all dirt, stones, scale, water etc. For
installation in conduit, place cable guides wherever necessary to avoid
abrasion and/or damage to the cable e.g., when guiding the cable from the
reel to the conduit mouth or trench, when passing through or exiting
manholes, when exiting a conduit run. Cable guides shall be in the form of
large diameter, smooth-surfaced free turning sheaves or rollers. They shall
be designed to ensure that cable will not ride off the end of the roller or be
pinched into a sheave contour. Guide tubes or chutes shall be used
provided they have a smooth burr-free working surface, well flared
3.02 REPAIR
A. Test all installed external cable in accordance with the requirements of Section 34
42 58, Signal System Testing, and AREMA C&S Manual, Part 10.4.30.
4.01 MEASUREMENT
A. Cables will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or
approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Case and house wiring will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
A. Cables and Wires furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule
of Quantities and Prices. This price shall include full compensation for furnishing
all labor, materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Field Case and House Wiring furnished and completed in accordance with the
Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
C. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
D. The Contractor shall allow for 100 wiring changes, not shown on the Contract
Plans and requested by the Engineer, at no additional cost. A wiring change shall
consist of connecting or removing a wire. Thus, moving a wire from one contact
terminal to another contact terminal will consist of two wiring changes.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
B. Material and workmanship shall be of the highest quality, assuring durability for
minimum life expectancy of 40 years. All pull boxes, handholes, PVC conduits,
HDPE conduits, fittings, cement and other materials to be furnished shall be
suitable for use in the environment to be encountered on a railroad signal system.
Conduits shall be used in underground, encased or exposed applications in
accordance with National Electrical Code, Article 347.
2. Section 31 20 00 Earthwork
1.03 REFERENCES
C. The following General Orders (most current) of the State of California Public Utilities
Commission (CPUC) shall apply:
1.04 SUBMITTALS
C. The Contractor shall submit for review and approval its proposed plan for final
installation of conduits and pull boxes prior to constructing underground facilities.
The proposed plan shall be redlined onto Metrolink’s PTC Composite Map Plan and
Profile for the relevant project area, or another method approved by the Engineer.
The Contractor shall not use the signal duct bank plan in the Contract Drawings for
this purpose.
1.06 INSPECTION
A. The Commission shall have the right to make inspections and tests, as necessary,
to determine if the materials meet the requirements of the Specification. The
Resident Engineer shall have the right to reject material that is defective in any
respect.
A. Contractor shall immediately replace any conduit or pull box that is damaged at any
time, prior to final acceptance by the Resident Engineer without additional cost.
PART 2 – PRODUCTS
2.01 MATERIALS
G. PVC Cement
H. 4’-0” x 4’-0” x 4’-0” Concrete Pull Box with Bolt Down Steel Cover
A. Conduit shall be rated for use with 90 degree C Conductors, shall be UL listed, and
shall comply with National Electric Manufacturers Association (NEMA) Specification
TC-2 (conduit) and TC-3 (fittings).
B. Conduit and fitting shall carry a UL label and shall be identified by type and
manufacturer and shall be traceable to location of plant and date manufactured.
Labels shall be legible and permanent.
C. The conduit shall be made from polyvinyl chloride compound which includes inter
modifiers to improve weatherability and heat distortion.
D. Conduit shall be free from visible cracks, holes or foreign inclusions. The conduit
bore shall be smooth and free of blisters, nicks or other imperfections which could
damage cables or conductors.
A. Conduit shall be rated for use with 90 degree C Conductors, shall be UL listed, and
shall comply with ANSI Specification C80.1.
B. Conduit shall carry a UL label and shall be identified by type and manufacturer and
shall be traceable to location of plant and date manufactured. Labels shall be
legible and permanent.
C. Conduit shall be hot-dipped galvanized inside and out. Conduit shall be coated with
an organic layer to inhibit white rust and increase corrosion resistance.
D. Conduit shall be threaded on both ends, with a threaded coupler attached on one
end to allow joining of multiple conduits.
Conduit shall be high density polyethylene (HDPE) suitable for direct burial and plowing
installation with the ballast portion of the track structural section. Corrugated innerduct is
not acceptable.
A. HDPE conduit supplied shall comply with ASTM D2447, schedule 80, 2.375” O.D.,
black with an orange stripe in color, ribbed interior and smooth exterior. Ribbed
interior wall shall be lubricated to reduce friction when installing fiber cable.
B. Equivalent material shall meet the minimum requirements of SDR 11 – ASTM D303
or SIDR 9 – ASTM D2239
D. HDPE conduit shall be capped at both ends prevent any undesirable contaminates
from entering tubes.
B. HDPE mini duct conduit shall be supplied on reels of a minimum of 5000’ foot
lengths.
C. HDPE mini duct conduit shall be capped at both ends with air tight blank plugs to
prevent any undesirable contaminates from entering tubes.
D. HDPE mini duct conduit shall be 12/10-mm and shall be available in colors of blue,
orange, yellow and green.
E. HDPE mini duct shall be factory pressure tested per the manufacturer’s
recommendations. Mini duct shall hold 130 psi to ensure there are no leaks.
1. NTSB-PSS-73-1
5. API RP 1109
B. Tape shall be easily located with an industrial grade non-ferrous metal detector and
shall have highly visible colors to assist in location when digging.
CAUTION
METROLINK COMMUNICATIONS
CABLE BURIED BELOW
A. Contractor to provide medium-bodied, fast setting solvent cement that shall have a
strong, leak-tight seal.
B. Precast concrete vaults and access doors shall be designed for H-20 highway
vehicle loading.
D. The minimum inside dimensions measured just below the lid support shall be 4”"
wide x 48” long.
E. The depth of the vault, when measured from the top of the access doors, shall be
48”.
F. Covers shall be two individual galvanized diamond steel pieces with hex bolts to
fasten in place. Covers shall have a skid resistant surface and be equipped with
lifting eyes.
PART 3 - EXECUTION
3.01 INSTALLATION
A. General
1. The installation of conduit and pull boxes shall conform to the AREMA C& S
Manual, except as specified herein.
2. The installation of conduits, vaults, and pull boxes shall conform to the
requirements of the Metrolink Engineering Standards, or as required in the
Contract Documents.
4. The Contractor shall install conduits, vaults, and pull boxes according to the
approved plan for final installation of conduits and pull boxes. Deviation from
the approved final plan must be in writing from the Resident Engineer.
5. Total bend radius allowed for a single conduit run shall not exceed 360
degrees. A single conduit run is defined as the conduits extending between
pull boxes, vaults, or instrument enclosures without interruption. Bends
6. All vault openings and knockouts shall be sealed with mortar. All conduits
extending into the sides of vaults shall be cut flush with the pull box wall.
8. The Contractor shall maintain required CPUC walkways around pull boxes.
9. All pull boxes installed into dirt or parkway areas shall have a concrete cap
around the box.
10. Pull boxes shall not be installed in any part of a driveway, wheelchair ramp,
or other travelled way unless specified in the Contract Documents or
approved by the Resident Engineer.
11. Contractor shall protect all pull boxes from damage; damaged sections of
pull boxes shall be replaced with new at the Contractor’s expense.
13. Any work performed by the Contractor that impacts or involves any
commercial utility facility shall be performed by a contractor approved by the
commercial utility and shall be governed by the utility’s standards.
Contractor accepts all liabilities and responsibilities when undertaking
repairs, modifications and additions involving commercial utility ducts,
handholes and cables.
6. Once the Contractor has finished conduit installation, and prior to installing
cables or wires, the Contractor shall mandrel the conduits and install a pull
rope into each conduit.
4.01 MEASUREMENT
A. Conduit will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or
approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Pull Boxes will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Conduit or Pull Boxes furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule
of Quantities and Prices. This price shall include full compensation for furnishing
all labor, materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
1.03 REFERENCES
D. ASTM E-814 - Standard Test Method for Fire Tests of Penetration Fire Stop
Systems.
Services.
H. GR-20-CORE, Generic Requirements for Optical Fiber and Optical Fiber Cable
1.04 SUBMITTALS
B. The Contractor shall refer to Section 34 42 00, General Signal Requirements for
related and additional submittal requirements.
C. The Contractor shall submit complete technical information for all products
herein.
1. For the proposed fiber optic cable, the Contractor shall submit cable
manufacturer’s qualifications if proposing an equivalent product. The
Contractor shall include manufacturer’s ISO 9001 Certification Number.
D. The Contractor shall submit a list and quantity of spare equipment as detailed
herein. Contractor is responsible for delivery of spare equipment to the SCRRA
facility in Pomona, CA.
E. Prior to ordering any signal fiber optic cable, the Contractor shall submit a Fiber
Cable Order Plan that includes a complete listing of cable types, cable
manufacturer(s), quantities, reel sizes and targeted location of installation within
the project. The plan shall be inclusive of cable slack within the subsystem and
shall include additional cable reels (amounting to 25% of total fiber cable
required) to address any damage and repair that arises during construction.
F. The Contractor shall submit Optical Link Calculations for all network links (signal
and crossing) prior to procurement of SFP optics.
G. Prior to signal fiber cable installation, the Contractor shall submit a Cable
Installation Plan. The plan shall include a written cable installation procedure
and supporting butterfly vault diagrams. This procedure shall be prepared based
on Contractor’s review of the conduit plans, survey of conduit and pull box
locations in the field and shall include a cabling plan and installation information
for each cable pull. The installation plan shall include butterfly vault diagrams for
each pull box with detail for slack quantity, location of cable within the duct
bank/vault, GPS coordinates of the vault and cable labeling. The installation plan
shall include a spreadsheet of all cable labels proposed at each location (inside
pull boxes and instrument enclosures). The installation plan shall include proper
procedures for feeding cable into conduit to maintain proper bend radii, and to
minimize friction. A cut sheet shall be submitted for the wire pulling lubricant.
H. The Contractor shall submit a Signal Fiber Cable Test Procedure. Both TIA-560-
C.0 Tier 1 (attenuation, link length and polarity) and TIA-560-C.0 Tier 2 (OTDR)
testing are required for final acceptance. The cable link type is backbone and
shall be tested at 1310nm and 1550nm wavelengths bi-directionally.
1. Included in the test procedure shall be test results summary sheet that
contains the following information:
b. Fiber number
2. The test results summary will set the parameters for acceptance testing
prior to making measurements in the field. This will facilitate the
Contractor to understand the minimum acceptance criteria to allow for
cleaning, retest measurements in the field during one mobilization. Test
reports shall be submitted to the Engineer after installation and prior to
placing cable in service.
I. The Contractor shall submit a Signal Fiber Network Test Procedure. Minimum
test requirements are detailed herein.
J. The Contractor shall submit a Crossing Fiber Network Test Procedure. Minimum
test requirements are detailed herein.
K. The Contractor shall submit a proposed RSL910 switch typical configuration file
for the signal and crossing networks. The Contractor shall hold four (4)
configuration development meetings at two (2) hours each with Metrolink to
determine the final switch configurations.
L. The Contractor shall submit a Signal Fiber Network Training Plan for approval.
Minimum training requirements are detailed herein.
3. Technical Data: The Contractor shall provide full technical data that
demonstrates compliance with the requirements of these Specifications
for each specified cable type the Contractor plans to provide.
4. Point of Origin: The cable shall be made in the United States of America.
2. Contractor shall have tools to inspect and clean the fiber optic connectors
every time a fiber connector is exposed to air:
1. Safety:
a. Never look directly into the end of a fiber that may be carrying
laser light. Laser light can be invisible (undetectable by the eye)
and can cause permanent eye damage.
b. Cleaved or broken glass fibers are sharp and can pierce the skin
easily, causing injury. Utilize tweezers to pick up cleave or broken
pieces of glass fibers and then on a loop of tape kept for disposal.
2. Packing:
e. Length of Cable.
f. Gross weight.
h. Date of manufacture.
j. The reel shall contain an arrow showing the direction in which the
drum should be rolled to gain access to the cable.
7. Cable ends shall be resealed promptly when a length is cut from the reel.
Cable reels shall be properly handled by following the manufacturer’s fork
lift handling illustration that comes with the reel.
10. Storage and Protection: Drums shall be stored with flanges upright.
Cable on drums with batten in place will be stored indoors.
PART 2 - PRODUCTS
1. One 24 strand signal fiber optic armored cable shall run continuously
along the right of way as designated within the main conduit duct bank.
This cable, defined as “FS24-1” on the Contract Drawings shall be
referenced as “Signal Fiber Main” throughout the system. This cable
shall be spliced in fiber pull boxes to lateral cables to enter the instrument
enclosures.
2. One 24 strand signal loopback fiber optic armored cable shall run
continuously along the right of way as designated within the main conduit
duct bank. This cable defined as “FS24-2” on the Contract Drawings
shall be referenced as “Signal Fiber Loopback” throughout the system.
This cable purpose is for redundancy. This FS24-2 cable shall be spliced
only at reel-to-reel ends or spliced to lateral cables at the project ends for
termination/OTDR purposes.
a. The blue buffer tube, fibers 1-12, shall be designated for signal
applications.
4. One 24 strand fiber optic armored cable shall be used for lateral access
to instrument enclosures, splicing to FS24-1. These lateral access
cables shall be defined as “FS24LS” (lateral cable for signal application)
or “FS24LX” (lateral cable for crossing application).
a. The blue buffer tube, fibers 1-12, shall be designated for railroad
west adjacent locations.
B. The signal fiber optic armored cable shall be loose tube, gel-free, single jacket,
single armored and contain 24 fiber optic strands. The signal fiber optic armored
cable shall be Corning Altos Lite model number 024EUC-T4101D20 or approved
equivalent. The cable shall be an accepted product of the United States
Department of Agriculture Rural Utilities Service (RUS) 7 CFR 1755.900 (PE-90).
1. Optical fibers shall be placed inside a loose buffer tube. The nominal
outer diameter of the loose buffer tube shall be 2.5mm. The buffer tube
shall be polyethylene.
2. Each buffer tube shall contain 12 fibers. Buffer tubes shall be resistant to
external forces and shall be meet the buffer tube cold bend and shrink
back requirements of 7 CFR 1755.900.
3. The fiber shall not adhere to the inside of the buffer tube.
6. Fillers may be included in the cable core to lend symmetry to the cable
cross section where needed. Fillers shall be placed so that they do not
interrupt the consecutive positioning of the buffer tubes. Fillers shall be
nominally 2.5mm in outer diameter.
8. Each buffer tube shall be gel-free. Each buffer tube shall contain water
blocking material embedded in the inside wall of the buffer tube for water
blocking protection. The water blocking material shall be non-nutritive to
fungus, electrically non-conductive, and homogenous. It shall also be
free from dirt or foreign matter. This material will preclude the need for
other water blocking materials such a gels, yarns, foams or tapes.
9. The optical fibers shall not require cleaning before placement into a splice
tray.
10. Buffer tubes shall be stranded around the dielectric central member using
the reverse oscillation, or “S-Z”, stranding process.
11. Water swellable yarn(s) shall be applied longitudinally along the central
member during stranding. Water blocking elements shall be applied
uniformly throughout the buffer tube.
12. Two polyester yarn binders shall be applied contra helically with sufficient
tension to secure the buffer tube layer to the dielectric central member
without crushing the buffer tubes. The binders shall be non-hygroscopic,
non-wicking, and dielectric with low shrinkage. A water swellable tape
shall be applied longitudinally around the outside of the stranded
tubes/fillers. A water swellable tape shall be non-nutritive to fungus,
electrically non-conductive, and homogenous. It shall also be free from
dirt and foreign matter.
13. Two ripcords shall be under the steel armor for easy sheath removal.
15. An armor layer shall be applied directly over the cable core and water
swellable tape. The armor shall be a corrugated steel tape, plastic-
17. The jacket or sheath shall be free of holes, splits and blisters.
18. The cable jacket shall contain no metal elements and shall be of a
consistent thickness.
19. The maximum pulling tension shall be 2700 N (600 lbf) during installation
and 890 N (200lbf) installed.
20. The minimum bend radius shall be 15 times the cable outside diameter
while under tension and 10 times the cable outside diameter installed.
21. The shipping, storage, and operating temperature range of the cable
shall be -40 degrees C to +70 degrees C. The installation temperature
range of the cable shall be -30 degrees C to +70 degrees C.
D. Cable Identification
1. The cable jacket shall be marked with the manufacturer’s name, date of
manufacture, fiber count, fiber type, flame rating, listing symbol, and
sequential length markings every two feet. The marking shall be in
contrasting color to the cable jacket.
compressive load of 220 N/cm (125 lbf/in) applied uniformly over the
length of the sample. The 220 N/cm (125 lbf/in) load shall be applied at a
rate of 2.5 mm (0.1 in) per minute. The load shall be maintained for a
period of 1 minute. The load shall then be decreased to 110 N/cm (63
lbf/in). Alternatively, it is acceptable to remove the 220 N/cm (125 lbf/in)
load entirely and apply the 110 N/cm (63 lbf/in) load within five minutes at
a rate of 2.5 mm (0.1 in) per minute. The 110 N/cm (63 lbf/in) load shall
be maintained for a period of 10 minutes. Attenuation measurements
shall be performed before release of the 110 N/cm (63 lbf/in) load. The
change in attenuation shall not exceed 0.15 dB at 1550 nm for single-
mode fiber.
A. All armored fiber optic cable shall be bonded and grounded for the safe and
effective dissipation of unwanted electrical current and to promote personnel and
site safety in accordance with NEC Articles 770.93 and 770.100. The armored
fiber optic cable shall utilize the kits at point of access within the fiber splice
enclosure within the pull box, and within the fiber distribution panel within
instrument enclosures. These points shall be tied to the instrument enclosure
ground buss.
B. The hardware grounding kit utilized within fiber splice enclosure shall be Corning
HDWR-GRND-KIT or approved equivalent. Grounding shall use green #6 AWG
stranded copper.
C. The hardware grounding kit for the fiber distribution panel shall be Corning FDC-
CABLE-GRND or approved equivalent.
A. The fiber splice enclosure utilized in pull boxes for the signal fiber and the signal
loopback fiber shall be Coyote Pup Closure, 8006661, by Preformed Line
Products or approved equivalent.
B. The fiber splice tray shall be compatible with the Coyote Pup Closure, 80806033,
by Preformed Products or approved equivalent. The splice tray shall support 12
fusion splices.
D. At all times, a separate fiber splice enclosure shall be used for each cable type
when splices are required. Cable types subject to this criterion include: signal
fiber main, signal fiber loopback, and communications fiber.
3. Suitable for loose tube fiber and below grade installation applications
B. At all times, a separate FDP shall be used within the instrument enclosure for
each cable application when terminations are required. Cable applications
subject to this criterion include lateral fiber cables for signal (FS24LS), lateral
fiber cables for crossing (FS24LX), and communication fiber cables.
1. Wall mountable.
D. The fiber distribution panel shall utilize splice cassette Corning CCH-CS12-3C-
P00RE or approved equivalent.
2.05 OPTICAL FIBER PATCH CORDS FOR SIGNAL AND CROSSING NETWORKS
A. Patch cords shall be utilized to connect the FDP to the Ethernet Switch or to
bypass a location by making an FDP to FDP connection. This may be required
at various stages of commissioning.
5. All patch cords shall be factory made and tested. Connectors shall not
be field assembled.
1. A distinct ring network shall include all locations that utilize a signal
application.
2. A distinct ring network shall include all locations that utilize a crossing
application.
1. Fully managed with Ethernet over Very high bit rate Digital Subscriber
Line 2 (EoVDSL2) capabilities.
3. The switch shall be equipped with six (6) copper Fast Ethernet ports
(10/100Base-Tx); two (2) Gigabit Ethernet Small Form-factor Pluggable
(SFP) uplink ports (1000Base-Lx); and two (2) EoVDSL2 ports with
terminal blocks.
12. RS232 port (Universal Serial Bus or USB Type-B and serial).
C. The Ethernet switch shall utilize single mode SFP optics. The Contractor shall
determine optics at each location by performing fiber link calculations that
provide a minimum of 6dB system margin. As determined by the fiber link
calculations and system margin criteria, the SFP transceivers shall be selectable
from:
A. The Contactor shall deliver to SCRRA the following optical test and repair
equipment to support the signal fiber network.
c. Cleaning kits
f. OTDR module
g. OLTS module
h. Integrated Wi-Fi
i. AC charger
j. Statement of calibration
C. Fusion Splicer
b. The fusion splicer shall utilize a core alignment with 300 power
X/Y magnification.
A. The Contractor shall deliver to SCRRA the following spare equipment to support
the signal fiber network.
PART 3 - EXECUTION
3.01 INSTALLATION
3. Contractor shall be responsible for verifying the required cable length for
each cable run prior to installation. Plans may be used for defining
locations and estimating cable lengths. However, no Plans shall be used
to determine final lengths and cuts. Actual lengths shall be determined
by the Contractor making on-site inspections and measurements.
4. Cable pulling locations shall be selected to protect the cable on the reel
and in slack loops. The Contractor shall be responsible for protecting
cable after working hours where cable installation is not completed during
a single shift.
5. Any damage to the SCRRA signal fiber cable shall be reported to the
Resident Engineer immediately, whether prior to installation, during
installation, during other construction, or during test or observation after
installation. Cable damage due to Contractor negligence shall be
replaced and repaired by the Contractor at no additional cost to SCRRA.
9. The Contractor shall not exceed the cable's minimum bend radius for
cable under any condition, including but not limited to, under tension or
long-term installation/storage.
11. All cable entrance openings in equipment enclosures, houses, rooms and
junction boxes shall be sealed with either a compression type fitting or
pliable sealing compound after the cable is in place. Sealing compounds
for rooms, houses, walls, or other partitions shall be fire retardant per
ASTM E814. Sealing compound shall be used to seal the area around
cable where the cable emerges from the end of a conduit, pipe, or duct
bank. All spare conduits shall be sealed.
1. All pull boxes that contain the signal fiber cable and signal loopback fiber
cable shall be each coiled to provide a service loop (slack) of 150 feet.
2. In areas where the signal fiber cable or signal loopback fiber cable utilize
a fiber splice enclosure, the service loop (slack) shall provide 75 feet of
slack to support each side/direction of the fiber splice enclosure.
3. The signal and crossing lateral cable shall provide a service loop (slack)
of 75 feet.
2. All fiber cables shall be clearly labeled for identification at the point
leaving the FSE and before entering the duct bank conduit. Refer to
labeling requirements herein for additional detail.
3. All fiber optic splices shall be fusion splices with a splicer equipped with
Local Injection and Detection (LID). The loss across each spliced fiber
shall be less than or equal to 0.10dB. Utilize proper fiber cleaning
procedures.
4. Clean shells and end plates to remove sand, dirt and other foreign
substances.
5. Lubricate the neoprene gasket in the shells with a uniform thin layer to
assure assembly and reentry.
7. Using the air valve, complete a flash test with a soap and water solution
to a maximum of 10 PSI to determine that the enclosure is properly
sealed. Confirm the pressure with a pressure gauge. Apply the
soap/water solution to all sealed surfaces of the enclosure. Visually
inspect that bubbles are not present, which indicate that the enclosure is
not properly sealed. At the end of the flash test, release the pressure
and reinstall the valve cap.
8. Mount the FSE to the pull box vertical wall to keep the enclosure off the
ground.
2. All fiber cables shall be clearly labeled for identification at the point
entering the FDP and before leaving the signal enclosure conduit. Refer
to labeling requirements herein for details.
3. Additional labels shall be applied to the FDP outside main door with
identification of “SIGNAL” or “CROSSING” in large font, reflecting the
FDP application. Labels shall also be placed on the panel door indicating
FDP Card Letter and the adjacent railroad west or railroad east location
within the network. An example of this convention for the Signal FDP at
location CP Stuart is “A: 7TH Street” and “B: Church Street”.
4. The central strength member of the cable shall be attached to the FDP
for strain relief. The outer jacket of the cable shall be attached to the
FDP with a cable clamp.
5. All fiber optic splices shall be fusion splices with a splicer equipped with
Local Injection and Detection (LID). The loss across each spliced fiber
shall be less than or equal to 0.10dB. Utilize proper fiber cleaning
procedures.
6. Utilize blank adapter panels to prevent dust entry for any unused slots.
4. Connect the failsafe alarm relay to the ElectrologIXS VLC. Utilize the
normally open wiring.
A. Install cable identification tags at both ends of each cable, at the entrance and
the exit of each pull box, housing, or fiber splice enclosure. All labels shall be
machine printed.
B. All signal fiber optic cable labels shall utilize an orange colored 2” x 3.5” self-
laminating fiber optic cable tag made of rigid PVC material and a polyester self-
sealing cover. The orange tag shall be resistance to moisture and grease. The
orange tag shall have slotted holes to accept the ties for a secure mounting
application. The orange tag shall be pre-printed “Caution Fiber Optic Cable”.
C. On the orange tag, under the cover, a white color industrial vinyl tape shall be
applied. The vinyl tape shall use a permanent acrylic adhesive and contain a
topcoat for thermal transfer printing. The following labels shall be printed on the
vinyl tape in accordance with the Contract Drawings:
1. Label “T1”
SG200
2. Label “T2”
SGL200
3. Label “T3”
CP<CP Milepost>-FDPSIGNAL
c. Example: SGV66.45-FSE-FS24-SG202-LS /
CP66.45-FDPSIGNAL
4. Label “T4”
CP<CP Milepost>-FDPXING
c. Example: SGV66.45-FSE-FS24-SG202-LX /
CP66.45-FDPXING
5. Label “T5”
SGV<Vault Milepost>-FSE-1
c. Example: CP66.45-FDPS-FS24-SG202-LS /
SGV66.45-FSE-1
6. Label “T6”
SGV<Vault Milepost>-FSE-2
c. Example: CP66.45-FDPX-FS24-SG202-LX /
SGV66.45-FSE-2
D. The fiber installation plan shall include a spreadsheet of all cable labels
proposed at each location (inside pull boxes and instrument enclosures) for
Engineer approval.
A. All cables shall be OTDR tested at 1310 nm and 1550 nm for single mode
operating wavelengths for anomalies and to ensure uniformity of cable
attenuation and connection insertion loss.
B. All dark fibers shall be OTDR tested. Dark fiber that is not terminated at an FDP
or spliced through but instead left coiled within the splice tray or splice case shall
be bare fiber OTDR tested. SCRRA shall have a complete test record of all fiber
installed, whether it is used in the design or not.
C. OTDR tests shall be performed utilizing a pulse suppressor such that the FDP
termination shall be shown.
E. A launch cable shall be installed between the OTDR and first link connection. A
receive cable shall be installed after the last link connection.
G. Test limits
1. Site/link identification
5. Cable type and value of the “index of refraction” used for length
calculations.
6. Date and time the test results were saved in the memory of the tester.
7. Brand name, model, serial number and calibration data of the tester.
8. Insertion loss measured at each wavelength, the test limit calculated for
the corresponding wavelength and the margin (difference between the
measured attenuation and the test limit value).
A. Contractor shall present to the Resident Engineer for approval a Signal Fiber
Network Test Plan showing the tests to be made, format and layout of test forms
and reports, and the limiting values to be used, at least 60 days in advance of
the testing.
2. Each node and link of the Gigabit Ethernet Signal Network ring shall be
tested for connectivity, throughput and redundancy are part of the larger
network. This testing shall include but not be limited to the following:
c. Record the optical link software values of all SFPs and produce a
spreadsheet comparing the link values to the link margin. Provide
explanation for any discrepancies.
in good health.
2. Each node and link of the Gigabit Ethernet Crossing Network ring shall
be tested for connectivity, throughput and redundancy are part of the
larger network. This testing shall include but not be limited to the
following:
c. Record the optical link software values of all SFPs and produce a
spreadsheet comparing the link values to the link margin. Provide
explanation for any discrepancies.
D. Contractor shall become familiar with and comply with SCRRA safety rules as to
safe operation of construction equipment and trains and the protection of
personnel. All safety precautions shall be observed, and any required safety
procedures shall be followed.
E. The Contractor shall provide all calibrated instruments, materials and labor
required for tests specified.
A. The contractor shall provide a comprehensive training program for the signal
fiber network including the following:
B. Training plan
1. The Contractor shall submit a training plan that outlines the proposed
training. Coordination and flexibility with SCRRA availability shall be
required.
d. Each training class shall include paper handouts and all materials
on a thumb drive for each student.
4.01 MEASUREMENT
A. Signal Fiber Network will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
A. Signal Fiber Network furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule
of Quantities and Prices. This price shall include full compensation for furnishing
all labor, materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This section includes requirements for installing, testing, and documenting vital
microprocessor based interlocking controller racks, custom local control panels
(CLCP), and ATCS compliant data radio that provides the functionality shown on
the Contract Plans and described here in.
C. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1. Part 236 - Rules, Standards, and Instructions for Railroad Signal System.
1.03 SUBMITTALS
C. Submit five (5) copies of all test reports and verification of tests in accordance with
the approved testing plan.
D. Submit five (5) copies of Shop Drawings for each CLCP faceplate design being
provided for approval of the Resident Engineer.
F. Rack testing of the application software. Rack testing shall mean the software
has been thoroughly tested and all possible conditions simulated using the same
type of Interlocking Control equipment and executive software being provided
under this contract.
A. Install, configure, and test the interlocking controller and custom local control
panel (CLCP) to conform to the requirements of CFR 49, Part 236, AREMA C&S
Manual Parts 2.2.10 and 8.1.2 and the manufacturer’s instructions.
C. All Interlocking Controls furnished under this Work shall be equipped with a PTC
Wayside Interface Unit (WIU) and be compatible with the existing Metrolink PTC
network. Interlocking Controls shall not require any additional interfacing
equipment beyond what Metrolink currently uses.
A. Package plug in modules for shipment separately from their card cage units using
ESD safe packaging. Protect each item from damage or loss during handling and
shipment.
B. Clearly identify each controller unit, LCP, and their associated components on the
packing crate, referencing its intended location.
1.06 WARRANTY
A. Provide warranty from defects for two (2) years from the first date of final
acceptance.
PART 2 - PRODUCTS
2.01 MATERIALS
3. The vital lamp driver module provided to operate wayside signal lamps
shall be capable of directly driving a minimum of 16 each 10 VDC, 18 watt
or 25 watt lamps through isolated lamp driver outputs for on, off, and
flashing. Flashing shall be at a nominal rate of 55 flashes per minute.
Controller shall provide tumble - down indications based upon light out
detection using both hot and cold filament checking.
5. Plug connectors shall be keyed for each module type to ensure only the
proper module can be connected.
6. The interlocking controller shall have the capacity to directly connect, via a
cable, to a chassis that will generate and receive Electro Code 4 and
Electro Code 5 track codes without use of relay interfacing.
7. The interlocking controller must be capable passing vital data, via a serial
connection, to existing VHLC units utilized on SCRRA properties.
8. The software associated with assuring the vitality of the system shall be an
inherent part of the basic controller system and shall not be accessible
for modification by the user. Changes to the application logic installed in
the system shall not require re-verification of the software associated with
assuring system vitality. The application logic shall be protected so that it
is user modifiable by authorized personnel only.
10. The interlocking controller shall provide event recording. The event
recording shall be designed so that the correct time is maintained when
the vital logic and/or code system equipment is reset or powered down.
The event recording equipment shall have sufficient storage capacity to
store a minimum of seventy-two (72) hours of events, without overwrite, at
11. The interlocking controller shall provide mitigation for "processor failure"
via a fall back relay.
12. The interlocking controller shall interface with the solid-state track circuit
detailed in Section 34 42 40, Solid -State Coded Track Circuits.
13. The failure of an output shall not cause loss of functions not associated
with those of the failed module.
14. The interlocking controller shall operate from a standard 12 VDC signal
battery supply. Any special power supply filtering devices required for
reliable operation shall be provided as part of the system.
1. Local Control Panel (LCP) shall be a Custom Local Control Panel (CLCP).
CLCP and shall be furnished as shown on the Contract Drawings.
3. The LCP shall be located on the equipment rack and shall permit
convenient use. The faceplate track, switch, and signal layout shall
conform to the Contract Drawings.
8. The LCP control board shall have the ability to communicate via RS-232,
RS-485, 2000 Vrms isolated Current Loop and Ethernet, with support for
Ansaldo PEER protocol and Alstom LCP protocol.
9. The LCP shall operate from a standard 12 VDC signal battery supply. Any
special power supply filtering devices required for reliable operation shall
be integrated as part of the system and be compliant with AREMA
Wayside Class C requirements.
10. Contractor shall program and/or configure the LCP to provide manual
control, allow CTC control, or function as indication only.
11. The local control panel board shall be capable of being configured via a
USB port.
12. The local control panel board shall provide 128 physical inputs and 128
physical outputs, unless otherwise specified on the Contract Drawings.
PART 3 - EXECUTION
3.01 PREPARATION
A. The Engineer shall furnish the application logic programs 90 days prior to
performing in-service tests. The Contractor’s Signal Engineer shall rack test the
application logic at the SCRRA office in Pomona, CA. The Engineer shall observe
the testing and shall make any modifications required to ensure the integrity and
functionality desired.
B. All time spent by the Contractor’s Signal Engineer in rack testing or making
modifications to the programs shall be at no additional cost to SCRRA. SCRRA
shall not be responsible for any work delays that may result from software
modifications made during final in-service testing and commissioning by the
Contractor.
3.03 INSTALLATION
B. Load all programmable and configurable modules with application software and
perform any configuration necessary.
C. Conduct a complete breakdown and operating test on the units prior to shipment.
A. Conduct tests as specified in AREMA C&S Manual Parts 2.4.1 and 7.4.1 to
ensure proper operation of the signal and grade crossing warning systems.
B. Conduct tests to ensure that the signal system conforms to CFR 49, Part 236.
C. Install and perform applicable tests in accordance with 34 42 58, Signal System
Testing, to ensure that the interlocking controller software and LCP has been
installed and made operational as part of the operating signal system. Verification
of such tests shall be provided to the Resident Engineer.
E. Testing, including pre-testing, shall include operating all switch machines and
lighting all signals. The use of lamp simulators in lieu of, or in parallel with, signal
lamps will not be allowed in pre-testing. An exception may be authorized by the
Resident Engineer where a signal or switch machine is in service and will be
reconfigured for final cutover or cannot be installed or wired until final cutover.
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
1.02 REFERENCES
1. Part 236 - Rules, Standards, and Instructions for Railroad Signal System
1.03 SUBMITTALS
C. The Contractor shall submit to the Resident Engineer five (5) printed copies of
all test reports and certify that all applicable tests have been made in
accordance with Section 34 42 58, Signal Systems Testing.
application program changes. These changes include both vital application and
Positive Train Control (PTC) Map file changes.
E. Rack test the application software. Rack testing shall mean that the software
has been thoroughly tested and all possible conditions simulated using the
same type of Solid-State Coded Track Circuits equipment and executive
software being provided under this contract.
A. Install, configure, and test the solid-state track circuit equipment in accordance with
all applicable requirements of CFR 49, Part 236,AREMA C&S Manual, Part 8.1.2
and the manufacturer’s instructions.
C. All Solid-State Coded Track Circuits furnished under this Work shall be
equipped with a PTC Wayside Interface Unit (WIU) and be compatible with the
existing Metrolink PTC network. Solid-State Coded Track Circuits shall not
require any additional interfacing equipment beyond what Metrolink currently
uses.
A. Package plug in modules for shipment separately from their card cage units
using ESD safe packaging. Protect each item from damage or loss during
handling and shipment.
B. Clearly identify each controller unit and their associated components on the
packing crate, referencing its intended location.
1.06 WARRANTY
A. Provide warranty from defects for two (2) years from the first date of final
acceptance.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Electronic track circuits shall be compatible with highway grade crossing constant
warning devices. Utilization of bi-directional, uni-directional, and auxiliary crossing
control functions shall be provided per Contract Plans and manufacturer's
specifications. Track filters shall be installed in track leads, as shown on the
Contract Plans.
C. Track circuit shall function to provide continuous train detection throughout the
length of the circuit whenever a shunt of 0.06 ohms is applied to the rails, including
applicable fouled turnouts.
I. The coded track circuit unit shall have available a minimum of six (6) discrete
code rates for vital signaling indication in addition to a code rate used for train
detection. An additional code rate shall be available for reversal of the code
transmission/reception signal orientation. Track circuit shall have two (2) codes
used to convey non-vital block information. Electrocode IV code rates are
presently used on Metrolink with Alternating Code 5. Coded Track Circuit must
be able to communicate on the rails with existing Electrocode without requiring
any interface equipment.
J. Event recorder modules for electronic track circuits shall be provided as shown
on the Contract Plans.
K. Electronic coded track circuits shall conform to the requirements of the AREMA
Signal Manual, Section 8.1.2, where these instructions and requisites are
applicable and do not conflict with these Specifications.
PART 3 - EXECUTION
3.01 PREPARATION
A. The Engineer shall furnish the application logic programs 90 days prior to
performing in-service tests. The Contractor’s Signal Engineer shall rack test the
application logic at the SCRRA office in Pomona, CA. The Engineer shall
observe the testing and shall make any modifications required to ensure the
integrity and functionality desired.
B. All time spent by the Contractor’s Signal Engineer in rack testing or making
modifications to the programs shall be at no additional cost to SCRRA. SCRRA
shall not be responsible for any work delays that may result from software
modifications made during final in-service testing and commissioning by the
Contractor.
3.03 INSTALLATION
A. Install solid-state coded track circuits at locations indicated on the Contract Plans.
B. Install the solid-state track circuit equipment in signal instrument shelters or cases
as shown on Contract Plans.
C. The solid-state track circuit equipment layouts shall provide for easy access to test
points, indicators, and adjustments.
A. Conduct tests as specified in AREMA C&S Manual Parts 2.4.1, 3.3.1, and 7.4.1 to
ensure proper operation of the signal and grade crossing systems.
B. Conduct tests to ensure that the signal system conforms to CFR 49, Part 236.
C. Install and perform applicable tests in accordance with 34 42 58, Signal System
Testing, to ensure that the Solid-State Coded Track Circuits software has been
installed and made operational as part of the operating signal system.
Verification of such tests shall be provided to the Resident Engineer.
E. Testing, including pre-testing, shall include operating all switches and lighting all
signals. The use of lamp simulators in lieu of, or in parallel with, signal lamps will
A. Work of this Section is considered incidental to work under other payment items
and no separate measurement and payment will be made to the Contractor for
Work of this Section. Work of this section shall include furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. The work of this Section shall include disassembling, relocating and installing
existing or new signals.
B. Signal layouts, as specified herein, shall consist of foundations, signal heads and all
structures including cantilevers, bridges, ground mounted masts, ladders, platforms,
and all mounting hardware required to construct signals.
C. Contractor shall furnish and install signals as shown on the Contract Plans at
existing and new signal locations.
D. Related Specification Sections include but are not necessarily limited to:
2. Section 31 20 00 – Earthwork
1.02 REFERENCES
A. Custom Signal Foundation Structures: Provide for the foundation structure type
selection and its design. The design of the signal foundation’s structure and
stability shall be in accordance with the AASHTO LTS-4. Design calculations
shall be prepared by a licensed California professional civil engineer with a
minimum of 5 years experience in the design of similar foundation structures.
B. Signal aspect shall be distinct and unmistakable when viewed from a height of 7
to 12 feet above top of rail at a distance of 1,000 feet. Nominal sighting distance
shall be 2,000 feet. Where unobstructed sighting distance for a standard signal
arrangement is less than 2,000 feet, supply and install color light LED signal and
adjust the signal head for the maximum sighting range possible. Provide the
Engineer written notification of any sighting problems or obstructions of signals..
1.04 SUBMITTALS
A. Submit Shop Drawings for each type of signal unit and each type of signal layout
to the Engineer for approval. Show all ladders, masts, bases, arms, signal heads
and required mounting hardware. Show location and method of mounting the
signals to the structure.
C. Submit Installation Procedure for approval by the Engineer. The procedure shall
include a detailed description of installation activity and sufficient detail to allow
the Engineer to determine the validity of the installation procedure.
A. Signals, structures, and related hardware shall meet the requirements of AREMA
C&S Manual, Section 7, and applicable portions of Manual Part 3.2.5 where they do
not conflict with any requirements specified herein.
B. Inspect each signal layout after it has been installed in the field. This inspection
shall conform to the Contractor's Installation Procedure as accepted by the
Engineer.
C. L.E.D. signal lamp units shall meet the requirements of the AREMA C&S Manual
Part 7.1.5.
D. Foundations shall meet all requirements of AREMA C&S Manual Parts 14.1.1
through 14.4.41, where requirements of the AREMA Specifications do not conflict
with any requirements specified herein.
E. The Engineer reserves the right to make inspections and tests, as necessary, to
determine if the equipment meets the requirements of this Specification.
A. Package LED’s separately from the signal in which they will be used during
shipment.
B. Contractor shall ensure that all wayside signal assemblies and signal lamp units are
safely stored and protected from damage during storage, handling and transporting.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Furnish LED color light signals, as indicated in the Contract Documents. Signals
shall be in accordance with the Metrolink Engineering Standards.
B. Color light signal units shall be capable of displaying three aspects: green, yellow
and red as shown on SCRRA ES8525-01.
D. Furnish mounting brackets for marker light assemblies, ladders, junction boxes,
housings, backgrounds, hoods and any other nuts, bolts, and associated hardware.
E. Furnish foundations for signal masts, signal cantilevers and signal bridges, as
applicable, in accordance withthe Metrolink Engineering Standards.
2.02 SIGNALS
C. Signal LEDs shall be GE Lighting Solutions RM4 Series 96 LED Wayside Color
Light units, or approved equal.
D. Signal LEDs shall function with 12 VDC relay logic or directly from lamp driver
modules within an ElectrologIXS, Vital Harmon Logic Controller, Electrocode 4,
or Electrocode 5 controller. The LEDs shall be capable of light-out detection
checks performed by solid state equipment.
A. Mast assemblies for ground mounting shall conform to the Contract Plans and
the Metrolink Engineering Standards.
A. Refer to the Contract Drawings for signal bridge and signal cantilever
requirements.
B. The junction box shall have two terminals with insulated test links, as specified in
Section 34 42 60, Signal Systems Miscellaneous Products, for each cable
conductor. Provide ten (10) percent spare terminals.
C. Cable entry to the junction box shall be direct from the signal structure. External
conduit construction is not acceptable. Provide an opening approximately four by
six inches near the base of the signal structure under each junction box location
to allow access for cable sealing at the foundation. Provide bolt-on access plate
which will cover the opening under normal conditions.
D. Locate junction box either at the base of a main support mast or on a main
support mast at a height of between 3 and 5 feet above the finished grade level
at the base.
E. The method of routing cables from the junction box to each signal mounted on
the structure shall be to route the cables within the tubular members of the
structure to the greatest extent possible. Pull cables entirely through the
structure members, mast, and signal mounting brackets, unless otherwise
approved by the Engineer. To facilitate this, provide appropriate pull box
locations as needed, located a maximum of 5 feet from each signal. Edges shall
be smooth and rounded to accommodate cable installation. Provide a means to
prevent entry of rodents and insects at the bases of the vertical masts without
cable entrances.
1. Use galvanized rigid steel conduit where wire is to be run external to the
structural members, except as noted.
2. Use flexible armored conduit to make the connection from the pull box to
the individual signal heads.
3. Use 5C #10 signal color coded cable for mast and jct. box wiring, type TC
Okonite 202-10-35-05 or an approved equal.
B. Construct galvanized steel foundations of steel angle and plate welded together.
Foundations shall be constructed of 2-1/2 inch by 2-1/2 inch by 1/4-inch steel
angle and 1/4 inch steel plate.
PART 3 - EXECUTION
A. Contractor shall install signal layouts in locations as indicated on the Contract Plans
and as shown on the accepted Shop Drawings. No part of any signal layout shall
conflict with Metrolink Engineering Standards, Code of Federal Regulations, Part
49, or CPUC rules and regulations.
B. Locate signals centered between insulated joint, except where physically not
possible. In such instances, submit a recommendation to the Engineer for approval.
C. Center line of signal mast shall be 15 feet 0 inches from centerline of track unless a
deviation from this is approved by the Engineer, as shown on the Contract Plans or
required to meet CPUC clearance requirements.
D. Install signal units level and plumb on their foundations. Leveling nuts shall be used
as shown on the Metrolink Engineering Standards.
K. The underground cable shall be dressed, pot headed, tagged, and terminated in the
signal junction box in accordance with Metrolink Engineering Standard 8210. The
conductor size of the underground cables shall be at least as large as that shown in
the Contract Plans.
L. Wiring from the junction box base to the signal heads shall be minimum No. 10
AWG copper stranded wire or larger as shown on the Contract Plans.
M. Install identification tags on each wire. These tags shall bear the nomenclature
shown on the accepted Shop Drawings.
N. Set lamp voltage between 8.8 volts and 9.2 volts measured at the signal lamp.
B. Refer to Section 31 20 00, Earthwork, for requirements for locating and protecting
existing utilities. Advise the Engineer immediately if any utility or cable interferes
with the foundation work. After locating an interference, allow 72 hours for the
Engineer to relocate or mitigate the interference.
C. Prior to placing steel foundations in the excavations, place and compact a crushed
stone base in accordance with Section 31 20 00, Earthwork.
D. When placing foundations, exercise care and ensure that anchor bolts are not bent
or threads damaged. Protect anchor bolt threads, washers, and nuts by applying
friction tape or other accepted method satisfactory to the Engineer, until the unit to
be supported is installed.
E. After backfilling foundations, ensure that the foundation is plumb and level. Where
galvanized steel foundations are installed, top of final grade shall be no more than
24 inches below top of foundation.
F. Install foundations to the lines, grades and dimensions required. Mounting bolts
shall be of sufficient length to accommodate use of leveling nuts between the base
of the equipment to be supported and the top of the foundation.
3.04 PAINTING
A. Make tests for proper operation and setting of lamp operating voltages in
accordance with Section 34 42 58, Signal System Testing.
4.01 MEASUREMENT
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 42 42
PART 1 - GENERAL
1.01 SUMMARY
1.02 REFERENCES
1.03 SUBMITTALS
A. Submit installation drawings showing the tie straps and the mounting details of the
switch circuit controller, including the connections to the track switch points and
switch stand being used for the Work.
A. Prior to installation, coat all parts of the Electric Switch Lock Layout that are not
painted or made of non-corroding material with approved grease to prevent
corrosion. Appropriately plug or cap unused threaded outlets.
B. During storage, lubricate and maintain Electric Switch Lock and switch circuit
controller layouts on a regular time program until installation. The Resident
Engineer shall have the right to monitor the Contractor’s compliance with this
maintenance required from time to time.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Furnish new Low Style Electric Lock Operating Mechanisms and layouts, such as G
& B Specialties Model 854 or Alstom Model 9B.
B. Furnish new High Style Electric Lock Mechanisms and layouts, such as Alstom
Model 9B or US&S Model SL6A.
C. Rods and Hardware. Each Low Style Electric Switch Lock shall securely lock the
switch hand throw lever in the normal position only. Provide a single color LED with
the assembly to indicate switch lock release. Each High Style Electric Lock shall
have a separate lock rod attached to the vertical front rod.
D. Junction Boxes. Each Electric Switch Lock layout shall be installed with an
individual pedestal mounted junction box. These junction boxes shall be as
specified in Section 34 42 60, Signal Systems Miscellaneous Products.
E. Electrical Fittings. All conduit, connectors, and electrical fittings, as required for
each electrical lock layout.
F. Switch Circuit Controller and Rod. Switch circuit controller layouts shall be installed
as specified in Section 34 42 50, Switch Circuit Controller
G. Stranded Wire. Furnish insulated No. 10 AWG stranded wire between the
pedestal-mounted junction box and the switch circuit controller. Insulated wire shall
be in accordance with Section 34 42 16, Signal Wires and Cables.
2.02 SECURITY
1. A switch padlock to restrict entry into the operating handle location of the
Electric Switch Lock.
2. Signal padlocks to restrict entry into the Electric Switch Lock operating
mechanism, the circuit controller, and the junction box.
A. Perform Contractor’s acceptance test of each Electric Switch Lock layout prior to
transporting the Electric Switch Lock layout.
PART 3 - EXECUTION
3.01 GENERAL
A. The circuits for Electric Switch Lock layouts shall be shown on the Contract
Drawings.
B. Mount and adjust the complete switch circuit controller layout as specified herein
and as indicated on the Contract Drawings.
3.02 INSTALLATION
A. Install two 16-foot long timber ties or concrete ties for mounting the Electric Switch
Lock where Alstom Model 9B or US&S Style SL-6A Electric Locks are used and
furnished by the Contractor, as shown on the Contract Drawings.
B. Mount Electric Switch Lock and switch circuit controller on new and existing timber
or concrete ties in conformance to Metrolink Engineering Standards.
C. Dap and drill timber ties to meet requirements of these Specifications. Limit of
cutting or dapping shall not exceed 2 inches.
D. Secure the Electric Switch Lock and switch circuit controller to the switch ties, by
3/4 inch by 10 1/2 inch bolts.
E. Remove any ballast necessary for the installation of the Electric Switch Lock layout
and replace and tamp the ballast after the installation has been completed. Spread
excess ballast evenly between ties in the vicinity of the switch and lock movement
layout.
F. Make a preliminary adjustment of the Electric Switch Lock and switch circuit
controller layout at the time of installation, and a final adjustment when placing it in
service, which shall result in the adjusting nuts being centered on the threads plus
or minus 30 percent of the thread length. Make final adjustment at the time of
functional test. Make final adjustments in conformance with the requirements of
AREMA C&S Manual, Parts 12.5.5 and 2.4.1.
G. Underground cable terminating in the Electric Switch Lock and switch circuit
controller junction boxes shall be dressed and pot headed as specified in Section
34 42 16, Signal Wires and Cables. Fan the individual conductors in a neat
workmanlike manner, properly tagged and terminated. Wiring between switch
junction box and Electric Switch Lock and switch circuit controller shall be No. 10
AWG insulated stranded flex wire. These wires shall also be tagged and
terminated. Install the wires between the Electric Switch Lock and switch circuit
controller mechanisms in an approved flexible conduit with a minimum length of 10
inches and a maximum length of 21 inches. Fasten this flexible conduit to the
switch junction box and switch mechanism with appropriate connectors.
H. After installation, properly lubricate and maintain Electric Switch Lock and switch
circuit controller layouts on a regular timed program until accepted by the Resident
Engineer.
I. Exercise care and ensure that the Electric Switch Lock and switch circuit
controllers, including switch tie plates, are thoroughly lubricated at all lubricating
points, that all machined surfaces susceptible to rusting, both external and internal,
are thoroughly coated with grease as acceptable to the Resident Engineer, and that
threaded portions of switch rods and nuts are similarly coated and protected.
J. Lubricate the switch tie plates with graphite lubricant, as acceptable to the Resident
Engineer. Thoroughly steam clean the plates to remove all oil or grease prior to
application of the graphite. Periodically renew the protective coating until such time
as Metrolink assumes responsibility for maintenance of the equipment.
K. Connect electric switch lock rod and switch circuit controller rods to the normally
closed switch point.
L. Any switch assembly which is connected to the open point side, or which has a
reverse switch indication shall be equipped with an insulated front rod in
accordance with Metrolink Engineering Standard 8650.
3.03 SECURITY
3.04 TOUCH-UP
A. Touch-up finish of all equipment described in this Section in accordance with the
AREMA C&S Manual, Part 1.5.10. Touch up shall match factory finish.
A. Inspect each Electric Switch Lock after it has been installed and correct any
deficiencies noted. Conduct this inspection in conformance with the requirements
of the Contractor’s Installation Procedure as accepted by the Resident Engineer.
B. Conduct the final operational tests of Electric Switch Lock Layouts and switch
circuit controllers as described in Section 34 42 58, Signal System Testing.
4.01 MEASUREMENT
A. Electric Switch Lock Layout will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
A. Electric Switch Lock Layout furnished and completed in accordance with the
Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for relays. Unless indicated as relocated on the
Contract Plans, relays shall be Contractor furnished and relays of each type shall
be uniform in design and contact assembly.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
A. Contractor shall provide acceptance testing and documentation for each relay when
it is transported from the warehouse to the job site.
C. Complete Test Report Form provided by the Engineer for each vital relay installed
under this Contract. Use typewritten characters to fill in all information requested on
the form.
A. Vital relays shall meet the requirements of AREMA C&S Manual Part 6.2.1, where
they do not conflict with any requirements specified herein. Vital Relays shall be of
the type and quality as designated in the Metrolink Engineering Standards 8110
and 8120.
C. Provide relay specifications including drop away, pick up and working values, any
A. Ship vital relays separately from the wired racks in which they are to be used.
Package relays individually; each in a sturdy corrugated cardboard carton with
the part number of the relay printed on the outside of the carton. Store relays in
a protected area until tested and installed.
B. Ensure that all vital relays are safely stored and protected from damage during
storage, handling and transporting.
A. The Contractor shall furnish one (1) e-post wrench for opening and closing the relay
test terminals with each shelter where relays are installed. E-post wrench must be
in each shelter for final acceptance.
B. The Contractor shall furnish two (2) insertion/extraction tools for each type of
contact at each shelter where relays are installed. Insertion/extraction tools must be
in each shelter for final acceptance.
1.07 WARRANTY
A. The Contractor shall provide warranty from defects arising from defective parts and
workmanship for 2 years from the first date of final acceptance.
PART 2 – PRODUCTS
2.01 GENERAL
A. General:
5. Design biased neutral vital relays so that gravity alone will prevent the
armature from picking up if the permanent magnet is de-energized or if no
current is applied to the coil, due to interruption of the normal magnetic
circuit.
8. Arc suppression for vital relays shall be built into the relay or into its
plugboard.
9. Equip vital plug-in relays, except for vital time-element relays and special
application relays, with front current testing facilities. Where shown on the
Contract Plans, provide facilities to enable the testing of voltage from the
front of the relay, without having to remove the relay or remove adjacent
relays.
10. Equip vital relays with a registration plate to prevent relays of the wrong
style, contact arrangement, or operating characteristics, from being inserted
into the plug board.
A. Vital switch operating relays used for control of switch-and-lock movement shall
meet the same requirements as specified for vital biased neutral relays except that
2.04 IDENTIFICATION
A. Facilities shall be included for mounting an approved typed or printed relay nametag
for each relay, either on the relay cover or on the relay cabinet front plate, as
applicable. The nametag shall be easily replaceable but shall not come off during
normal service.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Ensure that the relay operating characteristics have not been altered during
shipping.
B. Ensure that all AC and DC power buses are open while installing relays. Do not
reconnect buses until all relays have been installed.
C. Install and wire the relays as shown on the Contract Plans. Contractor shall refer to
Metrolink Engineering Standards 8110 and 8120 for relay tab and coil wiring
information.
A. All DC vital relays shall be tested and inspected in accordance with AREMA C&S
Manual Part 6.4.1.
4.01 MEASUREMENT
A. Relays will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or
approved schedule of values, as applicable, as derived from the Plans will be
4.02 PAYMENT
A. Relays furnished and completed in accordance with the Contract Documents will
be paid for at the Contract Unit Price, as listed on the Schedule of Quantities and
Prices. This price shall include full compensation for furnishing all labor,
materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for new factory-wired signal equipment houses
and relocating existing signal equipment houses. The Contractor shall be
responsible for supplying new house(s).
B. Installation and field modification of the new factory-wired signal equipment houses
by the Contractor to meet the requirements of the Contract Plans shall meet or
exceed the requirements of this Section.
D. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
B. Submit load calculations, indicating sizes of load center panel, voltage drops, and
all other 240/120 Vac equipment.
D. Submit four (4) copies of Shop Drawings showing the proposed size and
equipment layout including rack, air conditioner, lighting, convenience outlet
arrangement, and exhaust fan mounting and location.
E. Submit four (4) copies of Shop Plans of each instrument and entrance rack,
showing the arrangement and description of the mounted equipment and wiring,
if different from those shown on Contract Plans.
B. Each house will be inspected after it has been installed and the Contractor shall
correct any deficiencies. This inspection will be conducted in conformance with
the requirements of the Contractor's accepted Installation Inspection Procedure.
E. Each house and case will be inspected after they have been installed and the
Contractor shall correct any deficiencies. This inspection will be conducted in
conformance with the requirements of the Contractor's accepted Inspection and
Acceptance Procedure.
F. Resident Engineer reserves the right to make inspections and tests at the facility
where the wiring services are to be performed to determine if the equipment and
workmanship meets the requirements of this Specification.
A. Properly fasten and brace equipment shipped within houses and cases to prevent
damage during transit. Replace any equipment damaged during transit or prior to
in-service operation at no cost to the Owner.
B. Package all vital relays, batteries, and electronic plug-in modules in separate
containers for shipment and do not install until the house is set at its final location.
PART 2 – PRODUCTS
A. Furnish and install factory-wired signal equipment houses, as described herein and
as shown on the Contract Plans. These houses shall be complete with all the
equipment shown on the Contract Plans. Wiring shall conform to the requirements
of the AREMA C&S Manual, NEMA Standard ICS-70, or National Electrical Code
(NEC), as applicable.
C. Signal equipment houses shall be the size and layout shown on the Contract Plans.
F. The entire structure shall be powder coated on the outside with TGIC Polyester
Powder (or equal polyester powder) with a nominal thickness of four mils, but no
less than three mils at any point on the surface of the enclosure in accordance with
AREMA C&S Manual Part 1.5.10. The exterior color shall be light gray.
G. The instrument enclosures shall be complete with moveable shelves, wire chase,
and backboard.
H. The signal equipment houses shall provide access to underground and aerial cable
entrance behind the main terminal rack. The top and sides shall be lined with
temperature insulating material and constructed to prevent sweating. Provide
ventilation openings as required for the size of the house proposed. No ventilation
opening shall be made in the roof of the house. Provide lift rings to facilitate the
movement of the house.
I. Provide ventilation openings in each door. The exterior of the ventilation openings
shall be hooded to minimize the entrance of precipitation. Equip the interior of
ventilation opening with sliding plate to allow the adjustment of airflow and with a
replaceable dust filter. The doors shall be hinged and gasketed so that they will
provide a dustproof and weatherproof seal. Provide doors with exterior and interior
handles, (interior handles not required on cases) welded to a three-point locking
device to ensure that the door cannot be locked until it is in the fully closed position.
Provide doors with a two-position retaining device to secure the door when open.
J. House access doors shall be equipped with an additional locking mechanism such
as the Master Lock 770 Hidden Shackle Padlock Hasp, or approved equal.
K. Door openings shall be 32 inches wide by 86 inches tall unless otherwise specified
on the Contract Plans.
L. Provide thermostatically controlled exhaust fans, operated from 120 Vac and fused
separately, in each house, as shown on the Contract Plans. The thermostat that
activates the fan control shall be adjustable and operate in the range of 70 degrees
to 130 degrees Fahrenheit. Locate fans relative to the fresh air inlets to draw air
over the equipment and size to renew the air within the house every 3 minutes.
Exhaust fans shall have removable dust filters. Dust filters shall be either
replaceable or cleanable.
M. Hinges shall be separate castings, securely fastened to the house and door. The
hinges shall be equipped with bronze hinge pins, shall be lubricated by the
manufacturer before the case is shipped, and shall have grease fittings for future
lubrication.
N. Furnish signal equipment houses with interior lighting and duplex 120 VAC power
receptacles. Signal equipment houses and cases with double tube LED fluorescent
lights, energy efficient, as required to provide complete illumination for all passages
and sides, and operated from a switch conveniently placed near each entrance
door. Furnish convenience outlets as part of each switch.
O. House lighting and receptacle loads shall be fed from a ground fault interrupt circuit
breaker used exclusively for these loads. Signaling logic and signal appliance
power loads shall be fed from separate circuit breakers. The signal logic power and
signal appliance power shall be ungrounded. The Contractor shall size circuit
breakers and wiring.
P. Furnish Signal Equipment Houses complete with a 120/240 Vac power distribution
panel, circuit protective devices, and all appurtenances necessary to supply the AC
power required at each site.
Q. All access points in the enclosure shall be sealed for weather protection and against
entry of rodents and insects. All interior and exterior seams shall be caulked with
RTV silicone.
R. Enclosure foundations shall be the inner wall type and adjustable from the outside
of the enclosure. The range of adjustment shall be from 36-inches to 52-inches in
1/2-inch increments. Foundations shall be galvanized steel, a minimum of 60-
inches long, include all hardware, and a 12-inch x 12-inch x 1/4-inch footing pad. All
galvanizing shall conform to the AREMA Signal Manual, Part 15.3.1
S. Permanent vendor name plate, or equivalent, complete with vendor name, address,
model number, serial number, and date of manufacture or equivalent shall be
located on front the of house above the main entrance door.
A. Case shall have welded construction throughout. Welds shall be 1-1/2 inch
minimum in length with spacing not to exceed 6-inches where panels meet floor
and roof. Spacing on panel welds shall not exceed 18-inches.
B. Interior surfaces including top, sides, and shelves shall be finished with primer coat
and two (2) coats of white latex enamel paint.
D. Key slot channels shall be provided on each side and extend to the full inside
heights of the case. Keyhole spacing shall be 2-1/2 inch centers. Key slot
channels shall be flush with insulation.
E. Sides, top, and doors shall include 1-inch of fiberglass faced polyisocyanurate
insulation. Floor shall include 1/8-inch bi-directional pyramat rubber matting.
F. Permanent vendor name plate, or equivalent, complete with vendor name, address,
model number, serial number, and date of manufacture or equivalent shall be
located on front of the case.
G. Cases shall be equipped with a minimum of two (2) lifting/tie down lugs located at
roofline on each side.
H. Cases shall include four- (4) knockouts with cover plates and gaskets on sides ‘A’
and ‘C’ in the upper corners. Internal insulation at entry locations shall be precut for
ease of removal and equipment installation.
I. All access points in the case shall be sealed for weather protection and against
entry of rodents and insects. All interior and exterior seams shall be caulked with
RTV silicone.
K. Exterior surfaces, including bottom of floor, shall be powder coated with TGIC
polyester, color light gray, nominal thickness of 4 mils but not less than 3 mils thick.
M. Shelving shall be adjustable vertically in 2-1/2 inch increments and conform to the
Contract Plans.
N. Shelves shall be 12-inches wide and covered with 1/8-inch bi-directional pyramat
rubber matting. The shelf length will be determined by case size or as shown on the
Contract Plans.
O. All exposed edges on shelving, including rear edge, shall have a 1-inch facing
constructed of 14-gauge sheet metal, designed for this purpose. Facing shall be
aluminum or steel with rust preventive paint or plating. Facing shall be attached
with screws and be free of burrs or sharp edges.
P. Surface area of backboards and shelves shall be free of protrusions such as bolt
heads. The bottom of the backboards shall be cut level as shown on the Contract
Plans.
Q. The width of the backboard shall be determined by the size of the case or as shown
on the Contract Plans.
R. Door gasket shall be compressed 1/2-inch free height when door is closed and
locked. The gasket shall be coated with an approved lubricant to prevent sticking.
S. Three bolt on hinges, separate castings, with bronze hinge pins and lubrication
(3/16-inch zerk), fittings shall be installed with an anti-theft arrangement.
U. Heavy-duty three point locking system shall be furnished with each door. Latch and
locking system shall operate smoothly through complete opening and closing cycle.
The door handle must accept a large bail padlock. (Polar Hardware brand #7011) or
approved equivalent.
V. Case access doors shall be equipped with an additional locking mechanism such
as the Master Lock 770 Hidden Shackle Padlock Hasp, or approved equal.
W. Doors shall be provided with rods to hold door open at 90 degrees and near 180
degrees. Door insulation shall be covered by an interior sheeting to protect the
insulation and to add rigidity to door.
X. Louvers shall be provided in doors with adjustable cover plates for winter and
summer usage. The door shall accommodate an adjustable air intake sized to
accept a 1-inch x 10-inch x 20-inch replaceable filter.
Y. A drip channel (or roof design) shall be incorporated into the design to direct water
away from opening. Y.
Z. Case shall include six (6), 4-5/8” knockouts in the floor behind the backboard with
cover plates. Four (4) cable risers 36 inches long, complete with male adapters,
lock nuts, and bushings shall be included. The knockouts shall be equally spaced
behind the backboard.
A. All vendor installed electrical products shall be UL listed. All electrical work shall
conform to the National Electrical Code (NEC) standards and accepted practices.
B. Conduit and device box sizes shall conform to NEC Article 370.
C. The typical Breaker box shall be Square ‘D’ 100 AMP; Model QO12M100. The
breaker box shall be furnished with the following breakers, one- (1) QO120 GFI,
one- (1) QO230, one- (1) QO130, and seven- (7) QO120.
D. Bushings shall be installed on all conduits entering or leaving the breaker or device
boxes. An SDSA-1175 surge arrestor shall be mounted on the top of the breaker
box.
E. The breaker box ground buss shall be bonded to the breaker box and the nearest
keyway using an ERICO ‘VS’ welded connection designed for this purpose. The
neutral buss shall not be bonded during manufacture. The field shall bond the
neutral at the remote (main) disconnect when used.
F. The neutral bonding screw shall be packaged and shipped in the breaker box for
installation in the field if necessary.
G. All conduits shall be installed above the wire chase and secured to enclosure
structure. Flex conduit shall not be used except when used as a drop or attached to
equipment that maybe removed. All circuits must be routed in separate conduits.
The fluorescent lamp fixtures shall not be used for a junction box, raceway or
conduit for any circuit other than the one intended for lamp operation.
H. One (1) separate 20 AMP plug circuit shall be provided on the ‘A’ and ‘C’ walls as
shown on the Contract Plans. The end plugs shall be 8-inches from the ‘D’ wall and
18-inches from the ‘B’ wall the remaining plug(s) shall be centered between them.
I. Separate 20 AMP circuits (equipment power drops) shall be provided on the ‘A’ and
‘C’ walls. The junction boxes shall be located, above the wire chase, as shown on
the Contract Plans. The wires from the panel shall be terminated (wire nut and
taped) in the junction box. One–(1) piece of aluminum flexible conduit, 48-inches
long shall be supplied for each junction box and installed by the wiring shop. The
conduit shall be coiled up and shipped along with other house material.
K. General color code and wire specifications for all AC wiring are as follows. All wiring
shall be THHN or THWN solid copper or as required by the NEC.
L. The service entrance shall be a 2-inch EMT conduit, entering the bottom of the
breaker box. The conduit shall extend through the floor. Sufficient length shall be
left to allow easy coupling. The open end shall be capped and protected while in
transit.
M. One (1) 36-inch piece of 2-inch EMT conduit shall be included along with a
compression coupling. The conduit and coupling shall be secured and shipped
inside the enclosure.
N. A single or 3-way light circuit shall be provided based on house size and door
arrangement. One (1) 115/120V-20 AMP duplex receptacle shall be mounted with
each light switch, near the main enclosure entrance (D and/or B-wall). The fan
thermostat control unit shall be mounted to the light switch/duplex receptacle handy
box on ‘D’ wall.
O. A minimum of two (2) double tube, 4-foot LED energy efficient fluorescent fixtures,
and tube guards shall be installed in each enclosure. The actual quantity and
location of lights shall be based on the enclosure size or as shown on the Contract
Plans.
P. An air conditioner, sized for the structure, shall be supplied and located as shown
on the Contract Drawings. A 20 AMP circuit, with a single 20-amp receptacle,
configured for air conditioner unit provided shall be provided. All air conditioners
shall be commercial grade, 220/240Vac rated units with a minimum BTUh rating
of 12,000. Air conditioners shall be provided with a minimum warranty period of
five (5) years. Contractor shall furnish Kenmore Elite Model #76125, or approved
equal.
Q. Bushings shall be installed on all conduits entering or leaving the breaker or device
boxes. An SDSA-1175 surge arrestor shall be mounted on the top of the breaker
box.
A. All vendor installed electrical products shall be UL listed. All electrical work shall
conform to the National Electrical Code (NEC) standards and accepted practices.
B. The breaker box for cases shall typically be a Square ‘D’ 100 AMP; Model QO6-
12L100S mounted as shown on the Contract Drawings. Circuit breakers supplied
with the case shall be Square ‘D’ QO series as follows, one- (1) QO120 GFI, two-
(2) QO120.
C. Conduit and device box sizes shall conform to NEC Article 370.
D. Bushings shall be installed on all conduits entering or leaving the breaker or device
boxes. An SDSA-1175 surge arrestor shall be mounted on the top of the breaker
box.
E. The breaker box ground buss shall be bonded to the breaker box and the enclosure
frame using an ERICO ‘VS’ welded connection designed for this purpose. The
neutral buss shall not be bonded during manufacture. The field shall bond the
neutral at the remote (main) disconnect when used.
F. The neutral bonding screw shall be packaged and shipped in the breaker box for
installation in the field if necessary.
G. General color code and wire specifications for all AC wiring are as follows. All wiring
shall be THHN or THWN solid copper or as required by the NEC.
H. The service entrance shall be a 2-inch EMT conduit, entering the bottom of the
breaker box. The conduit shall extend through the floor. Sufficient length shall be
left to allow easy coupling. The open end shall be capped and protected while in
transit.
I. One (1) 36-inch piece of 2-inch EMT conduit shall be included along with a
compression coupling. The conduit and coupling shall be secured and shipped
inside the case.
K. 6-9 cases shall include one (1) switched incandescent light circuit. The fixture shall
be complete with 100 watt equivalent lamp and metal lamp guard.
L. A GFI protected duplex plug and light switch shall be mounted inside on the end (C)
wall as shown on the Contract Plans. The light with metal guard shall be mounted in
the front at the top-center of the case.
M. 6-9 case shall be equipped with an exhaust fan to afford proper air circulation
throughout the interior of the case.
A. General:
2. Mount all equipment in such a manner that a seismic event within the
parameters of Section 34 42 00, General Signal Requirements, will not cause
damage or excessive motion.
B. Relay Plugboards:
3. Equip the plugboards for vital relays with a registration plate to prevent
relays of the wrong type, contact arrangement, or operating characteristics
from being inserted.
2.06 IDENTIFICATION
A. Stencil a white identification number at the top of the front and rear frames of each
rack or panel.
B. There shall be an identifying nameplate for each relay, or other instrument mounted
on the rack or panel.
C. Equip the back and front of the relay plugboards with a tag, as specified in Section
34 42 60, Signal Systems Miscellaneous Products. This tag shall indicate the
nomenclature of the relay.
D. Identify terminals and both ends of all wires with a wraparound tag printed with the
circuit nomenclatures and terminal designations as shown on the Contract Plans
and as specified in Section 34 42 60, Signal Systems Miscellaneous Products.
E. Wire and cable conductor identification tags for terminal board mounting shall be as
specified in Section 34 42 60, Signal Systems Miscellaneous Products.
A. Cable entrance terminal boards shall be 3/4-inch Type AB exterior (five ply)
plywood, mounted on a rack and painted white with a fire retarding paint.
B. Cable entrance terminal boards shall be located as shown on the Contract Plans.
C. Multiple-unit terminal blocks for wire and cable conductors shall be in accordance
with AREMA C&S Drawing 14.1.6. Furnish each binding post with two binding nuts,
one clamp nut, and three washers.
D. Provide Siemens or equal test links on all terminal pairs where conductors enter
houses.
E. Equip binding posts and exposed terminals of other apparatus for circuits
exceeding 50 volts or greater (ac or dc) with insulating nuts and sleeves.
2.09 GROUNDING
A. House shall be fitted with four 48-inch long No. 2 ground wires cadwelded to floor
frame of the house at each corner. Cadwelding shall take place prior to powder
coating the structure. The pigtails shall be coiled and secured in a manner that
prevents damage during construction and while in transit. Cases shall have two 48-
inch long No. 2 ground wires cadwelded to floor frame of the house at each end.
A. Wiring shall be in accordance with Section 34 42 16, Signal Wires and Cables.
B. Minimum wire conductor sizes shall be as shown on the Contract Plans unless
otherwise approved by the Engineer.
C. Adhering to minimum wire size specifications does not relieve the Contractor’s
responsibility of using wire sized large enough to safely and effectively provide power
to the circuit it serves.
D. Solderless terminals for stranded wire shall be in accordance with Section 34 42 60,
Signal Systems Miscellaneous Products.
E. Solid terminal connectors shall be used for all short terminal jumpers.
F. All WAGO connections, except No. 6 battery connections, shall use vinyl insulated pin
terminal connections such as Thomas and Betts Pin Terminal, part number 14RB-
47PT, or approved equal.
A. All instrument enclosures shall be furnished complete with a layer of rigid insulation
on the walls, doors, and ceiling. Instrument houses shall have a minimum 2-inch
thick layer of rigid closed cell foam insulation rated R13. Instrument cases shall have
a minimum 1/2-inch thick layer of rigid closed cell foam insulation rated R3.3.
Insulation shall be suitable for residential installation.
B. The interior including the ceiling, walls, terminal boards, and shelves shall be finished
with a primer and two coats of white latex enamel paint.
D. Apply typical legend for control point houses, highway grade crossing houses and
cases as indicated on the Metrolink Engineering Standards. Consult with
manufacturer of house prior to paint application.
A. Equipment racks shall be the manufacturer's standard for the type of equipment
furnished and shall be sized according to the Contract Plans.
B. Equipment racks shall include all necessary supports for wire and equipment.
A. Wiring Raceway (Wire Routing): Internal case wiring shall be contained within
surface-mounted plastic raceway. Raceway shall be of a polycarbonate, low smoke
type with a solid snap-on cover and flexible sidewalls. The sidewalls shall be of
"finger" type construction allowing for insertion and removal of wire runs with
terminations attached. The manufacturer shall determine sizes. Fill capacity shall
not exceed 60 percent.
Contract Plans. The capacity rating shall be in accordance with the Contractor's load
calculations and the Contract Plans.
A. All houses shall be equipped with telescoping foundations as described in Part 2.01
Q of this Section complete with galvanized bolts, washers, nuts, and associated
hardware. Galvanizing shall conform to Section 34 42 60, Signal Systems
Miscellaneous Products, and AREMA C&S Manual, Part 15.3.1.
B. Galvanized steel foundations for cases shall be constructed of steel angle and plate
welded together. Foundations shall be constructed of 2-1/2 inch by 2-1/2 inch by
1/4-inch steel angle and 1/4-inch steel plate.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Mount houses and cases level and plumb and secure thereon with the hardware
provided. Do not use shims, spacers, or other filler devices to level and plumb
houses or cases.
B. Install cable entrance pipes through the cable knockout holes provided in the floor of
the house behind the terminal board(s) as shown on Contract Plans. Fill pipes with a
substance designed for the purpose that prevents entrance of debris, rodents, and
other pests.
E. Install relays on the relay plugboards corresponding to the relay nomenclature and
identification plate, and securely fasten in place with the hardware provided by the
relay manufacturer.
F. Place batteries on rubber matting on the floor of the shelter or bottom shelf of the
case. Coat battery posts with approved grease and securely fasten battery connec-
tors to the battery posts. Strap batteries or otherwise secure using a method
approved by the manufacturer so that they will not tip or move in the event of an
earthquake.
G. Mark each grade crossing warning device case or shelter with the street name,
milepost location, emergency response number, and DOT inventory number per
Metrolink Engineering Standard 8270.
H. Install pullboxes and conduits. Provide slotted pullbox covers to accommodate the
cable chute at new house locations. Place the house so the chute aligns with the
slotted cover.
I. Make any modifications to the cable chute required to fit the pullbox and
accommodate the cable installation. If it is necessary to cut the cable chute, ensure
no rough edges, sharp edges, burrs, or other surfaces exist which have the potential
to injure the cable.
3.02 AC POWER
A. Wall mount load center as shown on the Contract Plans. Mounting height from floor,
wire terminations, and clearances shall be in accordance with the NEC.
A. Test the functioning of the equipment contained within the instrument house in
accordance with the requirements of Section 34 42 58, Signal System Testing, CFR
Title 49, Parts 234 and 236, and AREMA C&S Manual Part 2.4.1.
4.01 MEASUREMENT
4.02 PAYMENT
C. Work of this Section shall include the cost of furnishing and installing foundations
for the house, ground rods and grounding, including the cost of excavation,
shoring where necessary, potholing, fill and any other equipment necessary to
install a foundation and a ground system including any mounting hardware.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This section includes requirements for dual control switch and lock movement for
each interlocked track switch at new, relocated and replaced switch locations as
shown on the Contract Drawings.
1.02 REFERENCES
1.03 SUBMITTALS
A. Submit installation drawings showing the tie straps and the mounting details of
the switch and lock movement, including the connections to the track switch
points and target.
D. Submit temporary point protection plans to the Resident Engineer for review and
approval.
A. Power switch and Lock Movements shall meet the recommendations of AREMA
C&S Manual Part 12.2.1, where they do not conflict with any requirements
specified herein.
B. The Contractor shall coordinate the installation of Power Switch and Lock
Movements with the track panel procurement and installation to ensure
compatibility between the track panel and the switch machine. Incompatibility
deriving from orientation, rod connections, or switch machine mounting is the
responsibility of the Contractor and shall be corrected at no expense to the
Owner.
C. Switch machine orientation (left or right hand) shall be the same configuration as
provided by the manufacturer. The Contractor is prohibited from changing this
orientation without written authority from the Resident Engineer.
A. Protect Switch and Lock Movements and their component layout parts against
damage during handling and shipment.
B. During storage, properly lubricate and maintain switch and lock movement
layouts on a regular timed program.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Install all new and complete dual control Power Switch and Lock Movement
layouts, including the switch targets where applicable. Power Switch and Lock
Movement shall lock the switch points in power and hand operation. Power
Switch and Lock Movement shall be 110VDC such as the Hitachi Rail STS
(formerly Ansaldo STS USA) M23A configuration. The gear ratio shall be 360:1.
C. Provide and install an insulated front rod per Metrolink Engineering Standards as
part of the power switch layout.
E. Switch targets shall be provided and installed by the Contractor within power
switch machines where freight operations will be using the switch as a hand
throw during construction of the project. Switch targets shall be removed when
the power switch machine is placed into service.
2.02 SECURITY
B. At power switches under construction and not to be used by the Freight Carrier,
the Contractor shall place the power switch and lock movement in an inoperative
mode (all power removed from machine and hand throw lever padlocked in hand
position) and switch points secured using a padlock able switch point clamp with
Contractor provided padlock. All locks shall be Contractor provided.
C. Furnish padlocks, except for switches requiring Freight Carrier access, until all
systems have been accepted. At final acceptance, the Contractor will remove
their padlocks and SCRRA maintenance will furnish replacement padlocks.
A. Test each switch and lock movement before shipping it to the job site. Conduct
this acceptance testing in accordance with the Contractor's Acceptance Test
Procedure for switch and lock movements. Submit a copy of documentation of
acceptance testing to the Engineer prior to shipping.
PART 3 - EXECUTION
3.01 GENERAL
A. Mount and adjust the complete Switch and Lock Movement layout as specified
herein and as indicated on the Contract Drawings.
B. Wire control and indication circuits for power-operated switches as shown on the
Contract Drawings.
3.02 INSTALLATION
A. Prior to installation, coat all parts of the switch and lock movement that are not
painted, or made of non-corroding material with an approved grease to prevent
corrosion. Suitably plug or cap unused threaded outlets.
B. Where existing concrete ties are not used, install two 14 foot long timber ties for
mounting the switch mechanisms as shown on the Contract Drawings. If a helper
assembly is required, one of the switch mounting ties shall be 16 foot long.
C. Prior to mounting the switch mechanism on either concrete or timber ties, align
the switch headblock ties at right angles to the straight stock rail, and space the
ties in accordance with the Metrolink Engineering Standards, and condition the
switch points to move without binding.
D. Provide and install all required components needed including, but not limited to,
bolts, ties, gauge plates, universal plates, rods, switch point rollers and the
Power Switch and Lock Movements at the locations shown on the Contract
Drawings to produce a complete power switch installation.
1. Secure power switch and lock movement to the switch ties using
galvanized or cadmium plated bolts of the proper diameter. Bolts are
required to have a six sided or square head and a head bolt lock must be
used on the underside of the wood tie. All thread threaded rod is
unacceptable.
E. Install the Switch and Lock Movements at the locations shown on the Contract
Drawings.
1. Secure Switch and Lock Movement to the switch ties using (8) eight 7/8-
inch bolts.
F. Remove any ballast necessary for the installation of each switch and lock
movement layout and replace and tamp ballast after the installation has been
completed. Spread excess ballast evenly between ties in the vicinity of the
Switch and Lock Movement layout. Remove ballast from between ties to allow
unrestricted movement of switch rods.
G. Make a preliminary adjustment of switch and lock layout at the time of installation
and a final adjustment when placing it in service, which shall result in the
adjusting nuts being centered on the threads plus or minus 30 percent of the
thread length. Make final adjustment at the time of the functional test. Make final
adjustments in conformance with the requirements of AREMA C&S Manual Parts
12.2.1 and 2.4.1, and the Metrolink Signal Maintenance Manual.
H. Do not apply power to the motor until the switch machine has been fully
lubricated, thrown, and adjusted in hand throw. There shall be no rubbing or
binding of switch rods or points on gauge plates, rails or ties. Follow
manufacturer’s adjustment and installation procedure.
I. During storage and after installation, properly lubricate and maintain switch and
lock movement layouts on a regular timed program until accepted by the
Engineer.
J. Exercise care and ensure that the switches, including switch tie plates, are
thoroughly lubricated at all lubricating points, that all machined surfaces
susceptible to rusting, both external and internal, are thoroughly coated with
grease, as acceptable to the Engineer, and that threaded portions of switch rods
and nuts are similarly coated and protected.
K. Lubricate the switch tie plates with graphite lubricant, as acceptable to the
Engineer. Thoroughly steam clean the plates to remove all oil or grease prior to
application of the graphite. Periodically renew the protective coating until such
time as the Owner assumes responsibility for maintenance of the equipment.
3.03 SECURITY
3.04 TOUCH-UP
A. Touch-up the finish of equipment described in this Section in accordance with the
AREMA C&S Manual, Part 1.5.10. Color shall match factory finish.
A. Inspect each switch and lock movement after it has been installed and correct
any deficiencies noted. Conduct this inspection in conformance with the
requirements of the Contractor's Installation Inspection Procedure as accepted
by the Engineer.
4.01 MEASUREMENT
A. Power Switch and Lock Movement furnished and completed in accordance with
the Contract Documents will be paid for at the Contract Unit Price, as listed on
the Schedule of Quantities and Prices. This price shall include full compensation
for furnishing all labor, materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, shall be determined from
the actual count in units as designated in the schedule of Quantities and Prices.
4.02 PAYMENT
A. Power Switch and Lock Movement furnished and completed in accordance with
the Contract Documents will be paid for at the Contract Unit Price, as listed on
the Schedule of Quantities and Prices. This price shall include full compensation
for furnishing all labor, materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
B. Switch Circuit Controller and layout shall be all new and include the controller
unit, junction box, point lug, detector rod, shims, all required bolts, nuts, washers,
pins, grease fittings, cotter keys, vent elbows, plates, adjusting brackets, and all
hardware to mechanically couple the switch circuit controller to the track switch
points, as a stand-alone unit or in conjunction with an electric switch lock.
1.02 GENERAL
A. Switch Circuit Controller layouts shall include the controller unit, junction box,
point lug, detector rod, shims, all required bolts, nuts, washers, pins, grease
fittings, cotter keys, plates, adjusting brackets, and all hardware to mechanically
couple the switch circuit controller to the track switch points and mount it on the
ties.
1.03 REFERENCES
1.04 SUBMITTALS
A. Submit installation drawings showing the tie straps and the mounting details of
the switch circuit controller, including the connections to the track switch points.
D. Submit temporary point protection plans to the Resident Engineer for review and
approval.
A. Protect switch circuit controllers and their component layout parts against
damage during handling and shipment.
B. During storage, properly lubricate and maintain switch circuit controller layouts on
a regular timed program.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Furnish Switch Circuit Controller layout complete with rod, lug, and associated
hardware as designated as required for a fully functional system.
B. The Contractor provided Switch Circuit Controller and layout shall be Model U-5
with return spring, ventilators and wire outlet as manufactured by Hitachi Rail STS
(formerly Ansaldo STS USA) or approved equal. Switch Circuit Controller provided
by Contractor shall be complete with offset crank, operating rod, switch point lug
and associated hardware.
D. Furnish Insulated Vertical No. 1 Rod with Basket in accordance with Metrolink
Engineering Standard 8660.
2.02 GENERAL
A. Stranded wire: Furnish insulated No. 10 AWG stranded wire between the
pedestal-mounted junction box and the switch circuit controller. Insulated wire
shall be in accordance with Section 34 42 16, Signal Wires and Cables.
2.03 SECURITY
B. At new switches under construction that are not to be used by a freight farrier,
the Contractor shall ensure that the switch points are secured using a padlock
able switch point clamp with Contractor provided padlock. All locks shall be
Contractor provided.
A. Test each switch circuit controller before transporting it to the job site. Conduct
this acceptance testing in accordance with the Contractor's Acceptance Test
Procedure for Switch Circuit Controllers.
PART 3 - EXECUTION
3.01 GENERAL
A. Mount and adjust the complete switch circuit controller layout as specified herein
and as indicated on the Contract Drawings and in accordance with the Metrolink
Engineering Standards.
B. Circuits for switch circuit controllers shall be as shown on the Contract Drawings.
3.02 INSTALLATION
A. Prior to installation, coat all parts of the Switch Circuit Controller that are not
painted, or made of non-corroding material, with an approved grease to prevent
corrosion. Suitably plug or cap unused threaded outlets.
B. Install one 10-foot long timber tie or concrete tie for mounting the controllers as
shown on the Contract Drawings
D. Dap and drill timber ties to meet the requirements of these Specifications. Limit
of cutting or dapping shall not exceed 2 inches.
E. Secure the Switch Circuit Controller to the wood switch ties, by 3/4 inch by 10 1/2
inch bolts. Secure switch circuit controller to the switch tie using galvanized or
cadmium plated bolts. Bolts are required to have a six sided or square head and
a head bolt lock must be used on the underside of the wood tie. All thread
threaded rod is unacceptable.
F. Remove any ballast necessary for the installation of each hand throw switch
layout and replace and tamp the ballast after the installation has been completed.
Spread excess ballast evenly between ties in the vicinity of the Switch Circuit
Controller layout.
H. Underground cable terminating in the controller junction box shall be dressed and
pot headed as specified in Section 34 42 16, Signal Wires and Cables. Fan the
individual conductors in a neat workmanlike manner, properly tagged and
terminated. Wiring between switch junction box and switch circuit controller shall
be No. 10 AWG insulated stranded flex wire. These wires shall also be tagged
and terminated. Install the wires between the controller junction box and the
controller mechanism in an approved flexible conduit with a minimum length of
10 inches and a maximum length of 21 inches. Fasten this flexible conduit to the
switch junction box and switch mechanism with appropriate connectors.
I. After installation, properly lubricate and maintain Switch Circuit Controller layouts
on a regular timed program until accepted by the Engineer.
J. Exercise care and ensure that the controllers, including switch tie plates, are
thoroughly lubricated at all lubricating points, that all machined surfaces
susceptible to rusting, both external and internal, are thoroughly coated with
grease, as acceptable to the Engineer, and that threaded portions of switch rods
and nuts are similarly coated and protected.
K. Lubricate the switch tie plates with graphite lubricant, as acceptable to the
Engineer. Thoroughly steam cleaned the plates to remove all oil or grease prior
to application of the graphite. Periodically renew the protective coating until such
time as the Owner assumes responsibility for maintenance of the equipment.
L. Connect switch circuit controller rods to the normally closed switch point. In
cases where the switch circuit controller is being used with a sliding derail with
wheel crowder (hand-throw derail application), connect switch circuit controller to
the lug provided with the derail.
M. Any switch assembly which is connected to the open point side, or which has a
reverse switch indication, shall be equipped with an insulated front rod.
3.03 SECURITY
3.04 TOUCH-UP
A. Touch-up the finish of all equipment described in this Section in accordance with
the AREMA C&S Manual, Part 1.5.10. Touch-up shall match factory finish.
A. Inspect each Switch Circuit Controller after it has been installed and correct any
deficiencies noted. Conduct this inspection in conformance with the
requirements of the Contractor's Installation Inspection Procedure as accepted
by the Engineer.
4.01 MEASUREMENT
A. Switch Circuit Controller will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
A. Calculate the loads based upon the equipment proposed. Size all batteries to
provide a minimum 48-hours standby capacity for all systems based on normal
operating conditions. Verify the ampere-hour capacity shown on the Contract
Plans is adequate to provide a minimum of 48 hours standby capacity.
B. Size batteries which provide power for crossing warning devices, such as gates
and flashing lights, to provide 12 hours of continuous operation with the gate
arms in the horizontal position and all lights flashing.
1.04 SUBMITTALS
PART 2 - PRODUCTS
A. Exide ELM IRONCLAD Single Wet Cell low maintenance Lead Acid Batteries
conforming to AREMA C & S manual parts 9.1.4 and 9.1.30 such as:
1. Model HF-Max Battery Charger equipped with four (4) 12VDC, 20 amp
modules part no. 12-4-310-10-D.
2. Model HF-Max Industrial Switch Mode Battery Charger and Supply part no.
BBX0410DAGIX00.
D. VMI Battery Charger – shall be all new and as manufactured by Quality Marine,
or approved equal.
B. Battery charging equipment shall be designed to deliver rated outputs with input
voltage of 100 Vac to 130 Vac at 60 Hz, single phase, two wire input.
H. Battery Cells shall be square tubular type design, flooded lead acid. Individual
battery cells shall have handles incorporated into their design to facilitate lifting.
I. Batteries shall not release any gas, fumes, or any toxic substances when
operated under normal conditions or when charged or discharged at a maximum
recommended rate. Each battery cell shall be equipped with a dual action
bayonet type flame-arresting vent plug, having an integral electrolyte level gage.
A. Furnish all mounting hardware, terminals, and terminators, and similar items for
mounting chargers and batteries in wayside cases and signal instrument shelters.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Install batteries and battery charging systems as shown on the Contract Plans.
3.02 TESTS
B. Test batteries and battery chargers in accordance with the manufacturer's and the
Metrolink Signal Maintenance Manual’s instructions.
4.01 MEASUREMENT
4.02 PAYMENT
END OF SECTION 34 42 52
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for rail bonds, fouling bonds, frog bonds, track
circuit connections, and all other material required for bonding of track circuit joints,
track frog and switch bonding, and track circuit connections.
A. Rail Bonding and track connections shall be in accordance with the Metrolink
Engineering Standards.
B. Rail track joints shall be bonded with welded railhead bonds per the Metrolink
Engineering Standards.
C. Track switch, frog fouling bonds, and track connections shall be stranded bonds.
D. Crimped sleeves shall not be used for any fouling or frog bonding unless allowed
by the Engineer.
1.03 SUBMITTALS
PART 2 – PRODUCTS
2.01 MATERIALS
A. Rail Head Bonds: Railhead bonds shall be 3/16-inch in diameter with steel
terminals welded to the conductors. They shall have a nominal length of 6 1/2
inches.
B. Web Bonds: Web Bonds shall be 3/16-inch, 12-inch long welded to the web.
C. Track Circuit Rail Connectors: Track circuit connectors shall be 3/16-inch stranded
bronze conductor, 1-inch tap for welded connection on one end and compression
sleeve on the other end for a direct crimp type connection to the track wire and
shall have a nominal length of 4 inches. Use no crimped connections on fouling
wires or frog bonding unless authorized by the Engineer.
D. Bond Strand: Bond strand for fouling wires shall be 3/16-inch single strand with
4/16-inch black PVC insulation.
E. Acceptable Manufacturers:
PART 3 - EXECUTION
A. Install welded bonds at all non-insulated rail joints within the limits of this Contract
that are not equipped with a bond.
B. Grind clean with a vitrified grinding wheel the surfaces of the rails where the bond
is to be applied. After grinding, clean surface with an approved non-toxic solvent
to remove all traces of grease and dirt. After the surface has been ground and
cleaned, weld the bond wire to the rail in a manner that will ensure a thorough
mechanical and electrical connection.
C. Before beginning work on these bonds, weld in the field, under conditions like
those of the regular installation, not less than three complete bond connections,
and as many more as the Engineer considers necessary to determine that the
welds are being made satisfactorily. Such welds shall be subject to inspection and
testing by the Engineer, and acceptance as to the method and quality of
workmanship will depend on the results of these inspections and tests.
D. Ensure that each bond connection is thoroughly welded to the rail. The Engineer
reserves the right to require a test of each weld by hammer and striker, or in any
other manner, which in the opinion of the Engineer is reasonable.
E. Remove any welded bond installed by the Contractor that is found to be defective
prior to acceptance and install a new bond.
A. The plug end of the track circuit connector shall be as specified herein, at a
maximum distance of 3 inches from the end of the insulated joint. When there are
multiple track connections to be applied at an insulated joint the wayside signal
track connection shall be the nearest connection to the insulated joint with crossing
detection circuits next and crossing shunts lastly installed in this order. The
Contractor shall ensure that the insulating quality of the materials used to protect
the splice meets FRA 234.241 requirements. The use of compression sleeves for
track circuit connections is only acceptable when making a bond strand connection
to underground cable inside of the trackside concrete pull box.
B. Strip back underground cable a sufficient distance for the exposed conductor to be
fully inserted into the compression sleeve. Then compress sleeve with the type of
compression tool designed for that purpose.
D. Install all track circuit connections. Remove any found to be defective prior to
acceptance and install a new track circuit connection.
E. Provide and install bond strand retainer clips made of Electroplated Spring Steel
on the rail base to hold terminated bond strand in place as specified in the
Metrolink Engineering Standards and as recommended by the manufacturer.
F. Provide and secure the bond strand along the tie by use of PVC cable keeper for
wood ties or “Snap-On” Style Stainless Steel Concrete Tie Clips for concrete ties.
3.03 TESTING
A. Shunt test all track circuits for continuity of circuit and ensure main line track circuit
is de-energized with 0.06-ohm shunt at any point within the track block. Hardwire
shunt usage for inspection and certification of wayside track circuits and constant
warning devices is unacceptable.
4.01 MEASUREMENT
A. Rail Bonding will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for a grounding system for the equipment
shelter and all other wayside equipment apparatus.
1.02 REFERENCES
1.03 SUBMITTALS
A. Submit drawings showing the design and detail of the proposed grounding system
for the signal and power equipment proposed to be furnished and installed.
B. Submit catalog cuts or drawings showing the type of components to be used for the
proposed grounding system(s).
C. Submit Installation and Test Procedure proposed for all equipment grounding.
A. Materials and equipment furnished and installed under this Section shall conform to
all applicable State and local ordinances pertaining to electrical power installations
and the National Electrical Code (NEC)
PART 2 – PRODUCTS
2.01 GENERAL
B. Ground rod clamps shall be made of a cast bronze clamp body, with non-ferrous
set-screws in accordance with AREMA C&S Manual Part 11.3.4.
C. Internal ground wire, from the equipment to the ground bus, shall be insulated No. 6
AWG standard copper wire in accordance with AREMA C&S Manual Part 11.4.1.
Insulated ground wire shall be colored green.
D. Provide a grounding bus of nickel-plated hard drawn pure copper in the equipment
shelters sized appropriately for the connections involved.
E. Bare Ground Wire: Soft drawn copper, Class A or Class B stranded, shall meet the
requirements of ASTM B8. Sizing of ground wire shall be in accordance with the
NEC, except where sizes specified herein or shown on the Contract Plans are
larger than those required by NEC; UL listed, Label A for lightning protection
conductors. Grounding cable shall be continuous without joints or splices
throughout its length.
2.02 MATERIALS
PART 3 - EXECUTION
3.01 INSTALLATION
A. General
3. Do not ground connection(s) to the track rails; do not use the neutral
conductors of the ac power supply.
5. Ground wire/cable runs shall be as short and straight as possible and shall
not be interrupted by any device, termination or splice.
1. At equipment shelters, drive four ground rods into the ground, one near
each corner of a structure. At equipment cases, drive two ground rods into
the ground, at opposite corners of the structure. The ground rods shall be a
minimum of 6 feet apart and shall be driven below ground level. Dig a 12
inch deep trench between the ground rods. Electrically connect each of the
ground rods connected to the others, using a No. 2 AWG bare stranded
copper cable, welded using Cadweld or an equivalent thermal process.
Coat Cadweld connections with epoxy resin. Place the ground wires in the
bottom of the trench. Backfill trench, returning the soils removed during
construction of the trench.
4. Properly ground equipment that has conductors that leave the shelter.
A. Ground Resistance Testing: Verify that resistance between ground buses and
absolute earth, as measured by the “Fall-Of Potential” method, does not exceed 15
ohms without benefit of chemical treatment or other artificial means.
B. Test Reports: Provide test reports to the Engineer upon completion of ground tests
that completely describe ground resistance test procedures and test results. Test
reports shall be signed by a technician and witnessed by a representative of the
Engineer.
C. Prior to final acceptance by the Engineer, arrange to have the new ac power
service inspected by state and local jurisdictional authority(s) as required.
A. Work of this Section is considered incidental to work under other payment items and
no separate measurement and payment will be made to the Contractor for Work of
this Section. Work of this section shall include furnishing all labor, materials, tools,
equipment, supplies, supervision, and incidentals, and doing all work, as shown on
the Plans, and as specified in these Specifications, and as directed by the Engineer.
B. Full compensation for all ground rods and grounding systems shall be considered as
included in the contract prices paid for the various items of work involved, such as
case and house installation, signal installation and AC meter service installation and
no additional payment will be made therefore.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for tests and inspections to demonstrate that
systems, subsystems, assemblies, subassemblies, and components supplied and
installed under this Contract comply with these Specifications and with all applicable
regulatory and Owner requirements.
1.02 REFERENCES
A. It shall be understood where this Section states “as authorized by the SCRRA
Signal Manager or SCRRA Signal Engineer” or “submit to the SCRRA Signal
Manager or SCRRA Signal Engineer” such authorization or submittal shall be
through the Resident Engineer or Project Manager.
B. Tests and inspections shall be made both during the progress of this Contract and
after completing installation of equipment and shall consist of factory tests of
contractor furnished equipment, circuit breakdown tests, wiring verification tests,
continuity tests, resistance tests, voltage and current tests, applicable locking tests,
operating tests, simulation tests, and other electrical and mechanical tests and
inspections.
C. The work shall include all tests required to ensure proper and safe operation of all
systems and subsystems, and to prove the adequacy and acceptability of the total
installation specified herein. Tests to be performed shall cause each system and
subsystem to be sequenced through its required operations, including imposition of
simulated conditions to prove that the installation complies with all specified fail-safe
requirements.
D. Each Contractor furnished component and unit of the wayside signal and highway
grade crossing system shall have an inspection performed at its point of
manufacture and evidence of this inspection and acceptability shall be indicated on
the item where practicable.
F. Work shall include costs of the Contractor's personnel and any special equipment
and assistance required to conduct all tests with complete documentation.
G. Supply test equipment of proper type, capacity, range, and accuracy to perform
required tests and inspections.
H. Test equipment used shall be in good working order and properly calibrated within 6
months of the date of the tests. This equipment shall display a sticker, indicating its
calibration date and the agency that performed the calibration.
I. If the system does not meet requirements, make necessary corrections and
retesting. Complete all tests and inspections prior to performing final in-service
tests.
J. Work shall include all necessary disconnecting and reconnecting to perform the
specified tests.
L. Field tests shall be coordinated with the Engineer. As many tests and inspections
as possible shall be completed prior to the final cutover to avoid train delay,
inconvenience to the travel public, and cost to the Owner. Place systems in-
service in phases where possible, thus reducing the actual cutover period.
M. Tests shall ensure conformance with CFR 49, Parts 234 and 236, and shall be
recorded on forms provided by the Engineer and signed by the Contractor’s
Signal Engineer directing each test and inspection.
N. Tests and inspections shall conform to the Metrolink Signal Maintenance Manual.
Owner will provide three (3) copies of this Manual at the Pre-Construction
meeting. Refer to Section 01 31 00, Project Management and Coordination,
Contract Meetings. Request guidance from the Engineer where the test and
O. Testing, including pre-testing, shall include operating all switch machines and
lighting all signals. The use of lamp simulators in lieu of, or in parallel with signal
lamps will not be allowed in pre-testing. An exception may be authorized by the
Resident Engineer where a signal or switch machine is in service and will be
reconfigured for final cutover or cannot be installed or wired until final cutover.
R. Notify the Engineer in writing at least 48 hours prior to each field test. No part of the
signal system shall be placed in service without an authorized representative of the
Engineer being present and witnessing the in-service tests.
1.04 SUBMITTALS
A. Submit the following pre-test information to the Resident Engineer for acceptance:
3. Identify any test or operation that may disrupt or disarrange the existing
signal circuits or systems. Include description of proposed safety provisions
and back-up contingency plans.
B. Submit the following in-service testing information to the Engineer for acceptance:
D. Record the results of each test, as herein specified, and submit copies of the field
test reports to the Engineer immediately at the completion of the cut-over testing.
Prepare final type-written test reports as indicated herein and submit to the
Engineer within five (5) days after the completion of each test. Final type-written
test reports shall include complete details of the test results and corrections, or
adjustments performed, or which remain to be completed. The type-written test
reports shall be signed and dated by the Contractor’s Signal Engineer. Furnish
certified test results for tests performed by any subcontractors when such tests are
required within these Specifications.
E. Where required in this Section, submit test results on completed SCRRA test record
forms.
F. Submit test reports for any additional tests required by the Contractor to ensure the
safe operation of the system to the Engineer.
G. Upon completion of all tests, submit a letter certifying that all tests necessary to
comply with all current regulatory requirements of these Specifications have been
performed at listed locations.
A. The Work and testing shall comply with the following standards and regulatory
requirements: AREMA Communications and Signals Manual, Part 2.4.1. and CFR,
Title 49, Parts 234 and 236.
PART 2 – PRODUCTS
A. Test instruments and equipment necessary to conduct the tests specified herein
shall be available, ready for use not less than one week in advance of test need.
“Ready for use” shall mean properly matched for test parameters, properly
calibrated, and sufficiently supplied with leads, probes, adapters, stands, and
similar items necessary to conduct the test in a completely professional manner.
A. Temporary or interim test related materials, special tools, connections, jumpers, and
similar items shall be furnished and available not less than one week in advance of
the test need.
A. All wiring and equipment shall be checked to verify conformance to the Contract
Plans and the Specifications.
B. Each control point, intermediate signal, grade crossing warning system shelter or
any other signal equipment shelter shall be tested to verify that it functions properly
before it is shipped to the field for installation. These tests shall involve connecting
all control systems (excluding signals, switches, and similar equipment) that make
up a control point, intermediate signal, grade crossing warning system shelter, or
any other signal equipment shelter; applying power; and then exercising each
function of the system and verify proper result.
PART 3 - EXECUTION
1. Condition precedent for in-service testing and cut-over will be the completion of
pre-testing and the Resident Engineer’s acceptance of the results. Complete
pre-testing and submit the results to the Engineer not less than one (1) week
prior to the proposed cut-over date.
B. The field tests performed shall cause each installed system and subsystem to be
sequenced through its required operations, including the imposition of simulated
conditions, to demonstrate that the installation complies with all specified fail-safe
design requirements and operational functions.
E. When tests require specific meter or test instrument readings, the preprinted data
sheet shall show the allowable range of values, for each part of the test. The test
report shall also contain a check off system for each action and a blank space
adjacent to the expected value in which to record the test readings.
F. All test reports shall be dated and signed by the Contractor’s Signal Engineer on the
day the test is performed. Space also shall be provided for the signature of the
witnessing inspector.
G. The report shall show the specific test instruments used on each test, with
instruments identified by name, type, serial number, calibration date, and calibration
due date.
H. Should an error be discovered during field testing due to field wiring and
connections that do not agree with the accepted circuit plans, the Contractor may
correct such errors without prior acceptance of the Engineer. The Contractor shall
notify the Engineer of the corrections as soon as practical.
I. The Engineer will make all final determinations as to whether only a part, or the
whole test, shall be rerun when any specific field test does not meet the
requirements specified for the test.
F. Operating tests.
G. All applicable tests prescribed by AREMA C&S Manual Part 2.4.1, where the
AREMA inspections and tests do not conflict with the requirements of these
Specifications
H. All applicable tests as required to ensure systems comply with CFR 49, Parts 234
and 236.
B. Grounds:
2. All low voltage DC circuits shall be tested for grounds in accordance with
the Metrolink Signal Maintenance Manual.
3. Contractor shall record test results on the appropriate SCRRA form and
submit this completed form to the Engineer to obtain acceptance of this test
requirement.
C. Insulation Resistance:
2. All insulation tests shall be performed after the equipment and cables are
installed and completely terminated in the field.
3. Contractor shall record test results on the appropriate SCRRA form and
submit this completed form to the Engineer to obtain acceptance of this test
requirement.
D. Vital Relays:
1. All DC vital relays shall be tested for pick-up and drop-away values. These
values shall be in accordance with field requirement values stated in Table
641-1 of AREMA C&S manual, Part 6.4.1.
2. Contractor shall perform all tests in accordance with the Metrolink Signal
Maintenance Manual. Results shall be recorded on the appropriate SCRRA
test form.
3. These tests shall be performed at the shelter locations after the shelter has
been set. Test result forms shall be submitted to the Resident Engineer.
E. Energy Distribution: Energy-Off Tests: With all power to the signal instrument
shelter or wayside case off, the following checks and tests shall be performed.
These tests shall include:
3. Comparing wire gages with those called for on the Contract Plans. All
discrepancies in wire sizes shall be replaced with the proper size wire.
5. Verify proper system voltage for each power supply, AC and DC.
1. All circuits shall be tested in their entirety for the correct operation of, and
response to, each contact on each circuit element, such as relays and
contactors. Where parallel paths exist, the tests shall validate each path,
and circuits shall be opened when required to ensure the proper test has
been made.
2. Adjust throw bar so that proper tension is placed on switch points in both
directions.
3. Manually operate switch machine normal and adjust lock rods and point
detector rods to allow switch machine to lock up with no obstruction.
Repeat above for switch machine in reverse position.
4. Turn on switch machine power, call switch machine normal and observe in
field that switch machine corresponds to position called, and observe in
wayside instrument shelter that proper switch correspondence relay is
energized.
5. With switch machine called normal, check gaps on circuit controller contacts
to see that they meet equipment specifications. Operate machine reverse
and repeat.
6. Break down each contact in switch circuit controller and observe that proper
switch correspondence relay drops. Repeat this procedure for both
positions of the switch.
7. Place ammeter in series with motor control energy and adjust clutch such
that it causes overload relay to pick up in less than ten seconds with
1/4-inch obstruction in switch point. Record current reading. Repeat for
opposite position.
8. Place switch and lock movement in "hand" operation and observe switch
mechanism cannot be operated by power. Place back in "motor" and verify
that switch mechanism can be powered from wayside instrument shelter.
9. Operate switch, then shunt detector track circuit and observe that switch
machine is stopped in middle of stroke and not allowed to complete
movement. Remove shunt and verify switch completes movement.
10. Contractor shall record test results on the appropriate SCRRA form and
submit this completed form the Engineer to obtain acceptance of this test
requirement.
H. Signal Layouts: Tests shall be performed on all signal layouts. These tests shall
include the following:
2. Apply energy to signal lighting circuits and adjust all lamp voltages to 10
percent less than the lamp rating.
4. Check that light-out feature, where used, complies with FRA Rule 236.23(f).
I. Line Circuits: The purpose of this test procedure shall be to verify the integrity of
line circuits between wayside instrument locations. These tests shall include the
following:
1. All nomenclature shall be verified and line circuits tested for continuity.
2. Each repeater relay shall be tested to determine that it follows the primary
relay’s operation.
3. Each line circuit will have a breakdown test performed between wayside
instrument locations. Breakdown of the line circuit shall begin at the
origination point of the circuit. The positive side of the circuit shall be opened
to ensure appropriate relay or input is de-energized in the other instrument
shelter. Close circuit and verify that the proper relay returns to its normal
position. Repeat for the negative side of the circuit. If circuit breaks through
relays within the instrument shelter where circuit originates, drop each relay
one at a time, which breaks the circuit to verify that the appropriate relay or
input is de-energized in the other instrument shelter. Restore relay and
verify that the proper relay and/or input returns to its normal position in the
other shelter. Each relay and/or input shall be tested to ensure that it follows
all the proper breaks in the signal shelters.
b. Lining of routes.
2. Contractor shall record test results on the appropriate SCRRA form and
submit this completed form to the Engineer to obtain acceptance of this test
requirement.
M. Track Circuits:
1. Each track circuit shall be tested for shunting sensitivity and polarity in
accordance with the AREMA C&S Manual, Part 8.6.1.
N. Insulated joints:
1. Each insulated joint installed by the Contractor shall be tested with one of
the following insulated joint testers, the Harmon 1501A1JC, S&C Model 324
Track Circuit Short Finder, or accepted equal, and shall measure no less
than 100 ohms across the joint.
1. A detailed list of the tests and complete test procedures shall be provided by
the Engineer to establish safe and proper operation of interlockings. The
Contractor shall provide the necessary personnel and equipment, along with
support functions, as part of the signal test crew. The test sequence shall be
designed to test each function for correct performance, in accordance with
these Specifications and the Contract Drawings. Furthermore, the test
sequence shall include simulated unusual conditions to determine that the
interlocking circuits will respond in a safe and desirable way.
a. Time locking.
b. Route locking.
d. Indication locking.
a. Loss of shunt.
b. Time locking.
4.01 MEASUREMENT
A. Signal System Testing will be measured by the unit or fraction thereof furnished
and completed in accordance with the Contract Documents and as measured by
the Engineer. The quantities as contained on the Schedule of Quantities and
Prices, or approved schedule of values, as applicable, as derived from the Plans
will be used as the basis for this measurement.
4.02 PAYMENT
A. Signal System Testing furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule
of Quantities and Prices. This price shall include full compensation for furnishing
all labor, materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Work of this Section shall include the cost of all associated equipment, including
meters, meggers, relay test units, shunt cords, communications equipment and
testing.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. This Section includes requirements for miscellaneous components and products for
signal systems that the Contractor shall provide and install. All materials provided
by the Contractor shall be new, unless designated on the railroad plans or approved
by the Resident Engineer.
1.02 REFERENCES
1.03 SUBMITTALS
PART 2 - PRODUCTS
2.01 GENERAL
A. All electrical components shall be rated to operate at power, voltage, current, and
temperature levels exceeding by 20 percent those which the components will be
subject to in service, unless otherwise specified herein.
A. Circuit breakers and fuses shall be of suitable capacity to protect the various pieces
of signal apparatus from the effects of short circuits or overloads. All circuit
breakers and fuses required for the equipment and systems shall be in accordance
with these Specifications.
B. Circuit fuses shall be non-renewable, and shall be of the fiber-case, time lag, fusion
type.
C. The circuit breakers and fuses shall be the correct size and rating for circuit current
interruption and shall protect the electrical equipment and circuits from short-term
and long-term overloads.
D. All circuit breakers and fuses shall be centrally located on the power distribution
panel and power racks.
E. Fuse clips shall be constructed so that they shall retain their resilience under all
installation and service conditions, to ensure a positive contact between the clips
and the fuse.
2.03 DIODES
A. Diodes to be furnished under this Contract shall carry a JEDEC number or shall be
available from more than one manufacturer and shall be used within the published
Specifications for such number. All diodes shall be silicon type, unless otherwise
accepted by the Engineer.
2.04 RESISTORS
A. Resistors, other than those required for electronic circuits, shall be in accordance
with AREMA C&S Manual Part 14.2.15.
2.05 REACTORS
A. Reactors, other than those required for electronic circuits, shall be in accordance
with AREMA C&S Manual Part 14.2.20.
A. Signal system terminal binding posts shall be in accordance with the applicable
requirements of AREMA C&S Manual Part 14.1.10.
B. Terminal binding posts for interface with plug-coupled wires to rack mounted
electronic equipment shall be in accordance with the AREMA C&S Manual, Part
14.1.2.
A. All terminal posts, located on terminal boards in the wayside cases and signal
instrument shelters, used to terminate 50V, or greater, ac or dc circuits, shall be
provided with a protective insulator.
B. The type of insulator shall be individual for each terminal post and shall be fire-
resistant.
A. Solderless terminals shall be in accordance with the AREMA C&S Manual, Part
14.1.1, unless otherwise specified herein.
C. Stranded copper wire shall be fitted with an approved type of terminal at all points
where the wires are to be terminated on terminal binding posts.
terminating wires larger than No. 14 AWG to a maximum diameter over the
insulation of 0.40 inch.
4. An AMP pre-insulated; diamond grip ring nylon insulated wire terminal shall
be used for terminating other stranded wires, No. 20 and No. 18 AWG,
having maximum diameter of 0.125 inch. AMP Catalog No. 320554, or an
approved equal, shall be furnished for No. 8 studs and AMP Catalog No.
320571, or an approved equal, shall be furnished for 1/4-inch studs.
E. Terminals shall be for attaching to the ends of the conductor in such a manner that
the flexibility of the conductor will not be destroyed and the possibility of breakage at
the terminal will be reduced to a minimum.
F. Terminals shall be for attaching to the wire with a tool made by the manufacturer of
the terminal and recommended by the manufacturer for the terminals being
furnished.
G. The tool shall be equipped with a ratchet device to ensure proper indentation of the
terminal, which will not release until proper indentation is complete.
A. Except as otherwise specified in this Section, permanently identify with a tag both
ends of each cable, each cable wire, and all single wires that terminate in the
junction boxes, switch mechanisms, signal instrument shelters, on equipment racks,
relay bases, shelter, and any equipment of the signal system outside of such
locations. Install tags so that they may be read with minimum disturbance of the
tags. Each conductor of the cable shall be rung out and identified before applying
the tag. Tagging shall follow the three-line convention with the termination in the first
line, nomenclature in the second line, and termination of the other end of the wire in
the third line. This three-line convention shall be in accordance with the Metrolink
Engineering Standard 8150.
B. Tags for wire and cable identification and for identification of transformers, resistors,
reactors and other components shall meet the following requirements and shall be
subject to Engineer’s acceptance:
d. After lettering, both the face and backside of the tag shall be
covered with a clear plastic coating, "vinylite", or an approved equal.
2.14 HARDWARE
A. Mounting hardware exposed to the elements and used for signal equipment, cases,
conduit, hangers, brackets, clamps, and the like, shall be hot-dip galvanized in
accordance with AREMA C&S Manual Part 15.3.1, except as otherwise accepted
by the Engineer.
B. Galvanizing:
1. The hot-dip process of galvanizing shall be used. All parts shall be picked
so that all scale and adhering impurities are removed. The zinc coating
shall be of commercially pure zinc and shall be continuous and thorough. It
shall not scale, blister, or be removable by any of the processes of handling
or installation. The finished surface shall be free from fine line cracks,
holes, or other indications of faulty galvanizing. It shall be smooth and free
from adhering flux and other impurities. The edges and ends of parts shall
be free from lumps and globules. Parts shall be coated with at least two
ounces of zinc per square foot of galvanized surface, after all bending,
cutting, drilling, and final fabrication.
C. Cadmium Plating:
2.15 CONDUIT
A. Flexible Conduit
1. Conduit for track circuit leads, switch-and-lock movements, and electric lock
layouts shall be Liquid-Tite flexible conduit or an approved equal. The
conduit shall be clamped at both ends with stainless steel clamps. Clamps
are not required for track wire risers.
B. Fittings
2.16 PADLOCKS
C. Switch padlocks for the freight carrier’s use will be SCRRA furnished. Provide all
other padlocks to provide security of signal and electrical equipment until such time
as the equipment is placed in-service and approved through final acceptance.
D. Provide signal equipment padlocks until such time as the project is found to be
acceptable and the Owner relieves the Contractor of maintenance responsibility.
The Contractor and Owner or SCRRA will schedule a lock change out program
directly related to the final acceptance of the project. The schedule shall be
coordinated through the Resident Engineer. Present a list of equipment locks to be
changed out by equipment and locations and the total number of locks that will be
required to secure all the signal equipment.
A. Sealing compound for use in sealing cable entrances shall be in accordance with
AREMA C&S Manual Part 15.2.15.
A. Cable entrance pipes for wayside signal shelters shall be 4-inch PVC, Schedule 40,
and 3 feet 6 inches long and extend 18 inches below the final grade.
B. Cable entrance for wayside signals shall be 4 inch Liquid-Tite flexible conduit or an
approved equal. Entrance pipe shall extend 18 inches below finished grade around
signal.
C. Cable entrance pipes are not required where a cable chute directly enters a pullbox.
A. All junction boxes shall be provided with gaskets to prevent the entrance of
moisture and dust, in accordance with AREMA C&S Manual Part 15.2.10.
B. Junction boxes shall be provided to terminate underground cables at all switch and
lock movements and all switch circuit controllers.
2.20 LUBRICATION
A. Lubrication for switch tie plates for all switch and lock movement layouts installed by
the Contractor shall be an accepted graphite lubricant, similar to Dixon's Graphite
"Railroad 60".
A. Provide and install overlay track circuits EPIC III manufactured by Alstom, or an
approved equal.
A. Power off strobe light and miscellaneous materials shall be packaged and shipped
with each shelter to be installed as shown on the Contract Plans. Power off strobe
light and miscellaneous materials shall be installed in the field by the installation
contractor.
B. Each shelter requiring a power off strobe light and Miscellaneous materials will
include the following:
1. 1 ea. Power Off Indication Light – S&C Distribution Company p/n 120-10, or
an approved equal.
2. 1 ea. Power Off Indication Light protective cage, metallic and powder
coated to match exterior surface of instrument enclosure.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Material and apparatus specified herein shall be installed in accordance with the
details of respective Sections of these Specifications, Metrolink Engineering
Standards, manufacturer's recommendations, and in accordance with the Contract
Drawings.
4.01 MEASUREMENT
4.02 PAYMENT
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
B. Provide all interface with, and in conformance to the standards of the Local Power
Company (LPC), to obtain the commercial metered power service at the locations
shown on the Contract Plans and as required by the Engineer.
C. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
A. Submit Meter Service Plans, indicating mounting pole, meter base, breaker box,
and grounding.
B. Submit Peak load calculation for each meter location. Submit load calculation
within 90 days of Notice to Proceed.
C. Submit letter certifying that the installation of the meter service has been approved
by the local electrical inspector.
D. Submit a copy of each service order to the Resident Engineer for approval and to
verify that each meter service planned falls within the Owners property.
B. Materials and equipment furnished and installed under this Section shall conform to
all applicable State and local ordinances pertaining to electrical power installations,
and the National Electrical Code (NEC).
PART 2 – PRODUCTS
2.01 MATERIALS
A. Circuit Breakers
1. Circuit breakers shall be sized by the Contractor for the projected loads.
Circuit breakers for 120 Vac power shall be 2-pole rated for 240 Vac.
Panels shall contain 25 percent spare circuit breaker space.
2. One double pole circuit breaker shall be provided for future use, in addition
to the 25 percent space circuit breaker space, specified herein.
C. Ground Rods and Ground Rod Clamps: Ground rods and ground rod clamps shall
meet the requirements of Section 34 42 56, Signal Grounding, and those of the
LPC.
E. Meter Pedestals and Bases: Shall provide and install meter pedestals and bases
which meet the requirements of LPC.
PART 3 - EXECUTION
3.01 GENERAL
A. Make the necessary arrangements with LPC and pay all fees in connection with
having the new meter service hooked up at least one month prior to placing signal
system in service.
B. Arrange to obtain the service connection from LPC. Pay LPC charges for this
service connection.
C. Where the Contract Documents specify that the Owner will coordinate with the LPC,
Contractor shall be responsible for installation and coordination with the LPC.
3.02 COORDINATION
A. Coordinate the connection and interface of new cables and equipment with LPC
in accordance with its standards.
B. Shall be responsible for Local Power Company monthly charges from all new
meters installed until SCRRA accepts full and final maintenance of the project.
When final acceptance has been granted, the Contractor shall coordinate with
SCRRA and the Local Power Company to transfer all new meter address to
SCRRA at:
3.03 INSTALLATION
A. The installation of the various equipment and materials for the signal power
distribution system that are specified herein shall be in accordance with LPC’s
requirements and the NEC.
B. The requirements included within this Section shall cover all incidental installation
work necessary to affect an integrated, tested, and operable signal power system
for the Work as shown on the Contract Plans.
C. Arrange utility power service at all equipment shelter locations requiring such
services. Connections to equipment shelters from meter may be by underground or
aerial connection. Where aerial connection is used, maximum aerial length
between meter and shelter shall not exceed 125 feet without the Engineer’s prior
acceptance.
D. The Contractor, in cooperation with the Engineer, shall meet as necessary with LPC
representatives to negotiate for the upgrade, relocation, or addition of required
power services needed to complete system operation.
3.04 GROUNDING
A. Simulated load tests, in accordance with approved signal power system test
procedure, shall be satisfactorily completed prior to final connection of signal
facilities at each equipment location.
B. Prior to final acceptance by the Engineer, obtain inspection of the new AC power
service by state and local jurisdictional authority(s), as required.
4.01 MEASUREMENT
A. Service Meters will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
1.02 REFERENCES
A. Furnish and install new train detection equipment, wideband shunts, narrowband
shunts, tuned joint couplers, dummy loads, shunt housings, insulated joints, and
track connections for designated crossings.
C. Provide rail bonding for new or modified rail joints or turnouts, as shown on the
Contract Drawings. Provide rail bonding, as necessary, to maintain existing
systems during construction.
D. Protect existing signaling cabling and, where necessary, relocate existing cabling
to prevent damage to the cabling during track installation, profiling, or grade
crossing work.
E. Record the final as-built conditions of the crossing warning system for each
crossing.
F. Perform and document all tests and inspections in accordance with CFR 49
regulations and these specifications.
1.04 SUBMITTALS
B. Detailed Work Plan: The following work plan shall be coordinated with and
integrated with submittals made under Section 01 14 00, Work Restrictions.
Submit a detailed work plan, for approval and coordination by the Engineer, prior
to making the changeover from the existing crossing warning system to the new
crossing warning system. The Contractor's proposed plan shall detail the
amount of time the warning system will be out-of-service and the substitute
warning which will be provided to allow normal railroad operations to be
C. Submit for approval of the Engineer a procedure plan for conducting quality
assurance, component integrity, circuit continuity, circuit breakdown, and system
operation tests.
A. Package printed circuit cards separate from the constant warning time (CWT)
units and all other electronic components with removable cards for shipment to
the field. Protect each CWT unit and printed circuit card from damage or loss
during handling and shipment.
PART 2 – PRODUCTS
A. Furnish materials and equipment for installation and for interconnection of the
highway crossing warning as indicated on the Contract Drawings and specified
herein. Materials and equipment shall be the products of manufacturers
regularly engaged in the production of such material and equipment and shall be
the manufacturer's latest design. Signaling materials and equipment shall be of
a type and model that are in standard operation on major railway systems.
C. Furnish trackside equipment, such as tuned joint couplers, narrow band shunts,
and wideband shunts, as shown on the Contract Drawings. Furnish equipment
shelters, predictors, track filters, chokes, and other equipment as shown on the
Contract Drawings and as required for complete installation.
D. Refer to Section 01 64 00, SCRRA Furnished Material and Equipment, for lists of
Owner-furnished equipment. Conduct and document acceptance testing of all
components prior to transporting them from Owner-designated storage location.
A. Design fusing and furnish fuses and printed circuit cards, connectors, and files in
accordance with Section 34 42 00, General Signaling Requirements.
A. Furnish and install constant warning time (CWT) type crossing train detection
equipment, terminating shunts, surge panels, and arresters for the crossing
configurations shown on the Contract Drawings.
B. Furnish and install each CWT unit complete with the basic complement of
printed circuit cards and additional circuit card(s) for functions such as upstream
detection, downstream detection, preemption initiation, event recording, and all
other materials necessary to complete the Work, as shown on the Contract
Drawings.
D. Each highway-rail crossing unit shall consist of a primary grade crossing CWT
controller and a redundant standby grade crossing CWT controller. Provide an
automatic transfer unit to transfer the approach control function from the primary
CWT controller to the standby CWT controller in event of the failure of the
primary unit and back to the primary unit if the standby unit were to fail. House
the automatic transfer unit in the same cabinet as the CWT normal and standby
controller.
E. Furnish and install constant warning time controller capable of detecting train
movements on two separate track sections. Design CWT unit to allow selection
of a different frequency for each track.
F. Constant warning time crossing train detection equipment shall be Alstom XP4,
Siemens GCP 4000, or GCP 5000 as shown on the Contract Drawings, or
Approved Equal. Termination shunts shall be the CWT manufacturer’s
recommended type shunt for the frequency and application used. Furnish multi-
frequency selectable termination shunts.
G. Furnish and install termination shunts, adjustable inductors, filters, code isolation
units, and the like, as recommended by the CWT controller equipment
manufacturer, as shown on the Contract Drawings.
J. Furnish and install an internal data recorder with the CWT unit capable of
recording train speed, warning time, time and date, adjacent and auxiliary
crossing detection times, and equipment errors. The recorder shall be capable of
furnishing a report with only warning time, train speed, and time and date
information and a separate report that includes error data.
K. Furnish and install a separate solid state data recorder and crossing monitor
capable of remote interrogation. The Micro-Aide CWR-72B Data Recorder as
shown on the Contract Drawings or an approved equal, shall be used.
L. Furnish and install a data recorder antenna and associated cables on each
shelter as shown on the Contract Drawings.
B. The crossing gate warning device assembly shall conform to the requirements of
CPUC GO No. 75D; CFR, Title 49, Part 234; and the relevant sub-parts of the
AREMA C&S Manual Part 3.2.
C. The gate mechanism housing shall be cast aluminum for mounting on a 5-inch
diameter 16 feet aluminum pole and furnished complete with mounting brackets,
counter-weight assembly, and counter-weights. Provide either single sided
counter-weight brackets or double-sided counter-weight brackets as
recommended by the manufacturer. Fit gate arm bracket with a breakaway arm
adapter as shown in the AREMA C&S Manual, Part 3.2.21.
E. Furnish gate arms lengths required per the Metrolink Engineering Standards and
site conditions. Arms shall be of the aluminum with fiberglass extensions and
fiberglass tip type. Gate arm lamps shall be LED conforming to the AREMA C&S
Manual, Part 3.2.40. Provide high intensity lamps when shown on the Contract
Drawings.
F. Provide gate arm wind guards conforming to AREMA C&S Manual Part 3.2.22
with each gate assembly.
G. Provide flashing light crossing signal units as shown on the Contract Drawings.
Light units shall have 12-inch roundels with LED’s and be complete with steel
backgrounds, steel hoods, junction box, and cross-arm brackets.
H. Provide a crossing warning bell conforming to the AREMA C&S Manual, Part
3.2.60 with each gate assembly, except that the bell shall be mounted on the
cantilever structure when a cantilever is shown.
I. Railroad crossing signs, multiple track signs, and the like, shall be extruded
aluminum, reflex-reflective sheet type as recommended in the AREMA C&S
Manual Parts, 3.2.70 and 3.2.75, respectively. Provide signs complete with all
hardware for mounting on 5-inch mast or on a cantilever mast. All highway-rail
crossings shall conform to CPUC signage requirements.
J. Exit Gates will default to the vertical position when energy is removed. At a grade
crossing, the entrance gates and the exit gates should be provided by the same
manufacturer. The Western Cullen Hayes (WCH) Model 3593 E and the WCH
Model 3597 EXIT gate mechanisms or approved equals are acceptable.
connect with another Exit gate controller of the same manufacturer. The Alstom
ElectrologIXS, Alstom XP4, Siemens Solid State Crossing Controller IV
(SSCCIV), or approved equal shall be used.
2.05 FOUNDATIONS
C. Provide precast concrete foundations complete with anchor bolts, nuts, and
washers in accordance with the AREMA C&S Manual, Part 14.4.
D. All galvanized steel foundations to be furnished and installed shall conform with
Section 34 42 60, Signal Systems Miscellaneous Products, and AREMA C&S
Manual, Part 15.3.1.
E. Galvanized steel foundations shall be constructed of steel angle and plate welded
together. Foundations shall be constructed of 2-1/2 inch by 2-1/2 inch by 1/4-inch
steel angle and 1/4-inch steel plate.
F. Bolts, nuts, and washers shall be galvanized. Nuts and threads shall be in
accordance with AREMA Specifications for Bolts, Nuts, and Threads, C&S
Manual, Part 14.6.20. Plain washers shall be in accordance with AREMA
Specifications for Plain and Spring Lock Washers, C&S Manual, Part 14.6.21.
Steel shall be in accordance with AREMA Specifications for Various Types of
Steel, C&S Manual, Part 15.1.4, Section 1. Bolts shall be of sufficient length to
provide for leveling of the device.
2.06 HARDWARE
2.07 CONDUIT
PART 3 - EXECUTION
3.01 GENERAL
A. Install and adjust equipment and materials in accordance with the appropriate
requirements and recommendations of the equipment manufacturer, in
conformance with the recommendations of the applicable parts of the AREMA
C&S Manual; as required by CFR 49, Parts 234 and 236; applicable CPUC
regulations; or as otherwise specified herein.
B. Where existing grade crossing warning system shelters and gate assemblies are
indicated to be relocated, remove, protect, transport, store, disassemble, re-
configure where necessary, reassemble and reinstall as shown in the Contract
Drawings and as required within the Metrolink Engineering Standards.
A. Install new, or maintain existing, and test rail bonding for electrical continuity as
required for continuous train detection within the approach limits of the
crossings.
B. Double bond frog assemblies, switch points, and rail joints as specified in
Section 34 42 54, Rail Bonding, with the type of bonds specified in Section 34 42
54, Rail Bonding.
C. Make signal connection to rails using weld type track circuit connectors per
Metrolink Engineering Standards.
A. Install, connect, and test new equipment and cabling to the greatest extent
practicable without disruption of the existing highway-rail crossing or signal
systems.
A. Install and adjust all track circuits in accordance with the requirements of
AREMA C&S Manual, Parts 8.6.1, CFR 49, Parts 234 and 236, and as specified
herein.
B. Make all track circuit rail connections using weld type connectors.
C. Adjust each track circuit for a detection sensitivity of 0.06 ohm throughout the
length of the track circuit, including within the shunt fouling limits of turnouts.
D. Record voltage and current measurements at both feed and receive ends of
each track circuit in a format approved by the Engineer.
A. Install grade crossing warning equipment in conformance with CFR, Title 49 Part
234; CPUC G.O. 75D; approved submittals; and as shown on the Contract
Drawings.
B. The final voltage adjustment and alignment of the flashing light units and final
balancing of the gate arms shall be made at the time of the functional test. Final
adjustments and alignments shall be made in conformance with the
requirements of the AREMA C&S Manual, Parts 3.3.1 and 3.3.5 and CFR 49
Part 234.
C. Provide new cabling between the wayside gate/flasher and the crossing control
shelter except where the Contract Drawings specifically specify the re-use of the
existing cabling.
D. Furnish and install pedestrian gates in accordance with the Contract Drawings
and installation instructions furnished by the Engineer.
3.07 FOUNDATIONS
B. Install each foundation in accordance with the approved installation detail for
each type of foundation and as specified herein. The absence of a specific task
listing herein does not relieve the Contractor of the responsibility for providing a
complete and functional installation. The installation tasks that must be
completed by the Contractor are included herein.
sufficient length to accommodate use of leveling nuts between the base of the
mechanism and the top of the foundation.
E. When placing foundations, ensure that anchor bolts have not been bent and that
the threads are undamaged. Protect anchor bolt thread, washers, and nuts by
applying friction tape, or other method approved by the Engineer, until such time
as the wayside equipment is installed. Bring damaged anchor bolts to the
immediate attention of the Engineer. Do not use damaged anchor bolts.
Remove and replace damaged anchor bolts and completely or partially remove
and replace foundation as determined by the Engineer.
3.08 CONDUIT
C. Bore or jack conduit under the existing trackbed at any traverse, except that
conduit may be placed under the track prior to the track renewal.
B. Removed equipment and materials not designated for reuse or salvage shall
become the property of the Contractor and disposed of. Refer to Section 31 11
00, Site Clearing, for disposal requirements.
B. Prepare test procedures and perform and document tests on the highway-rail
crossing components and systems as follows:
C. Make measurements at each piece of wayside equipment and record on the as-
built record drawings verifying that the equipment is located where shown on the
Contract Drawings and as approved by the Engineer. Verify, by measurement,
that the equipment does not violate the train dynamic clearance envelope.
E. Disconnect and ground associated signal equipment not under test. Disconnect
or unplug electronic devices or signal equipment prior to any testing.
G. Submit test data and results to the Engineer's information and approval within 24
hours of placing the apparatus or system in operation.
4.01 MEASUREMENT
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
C. Preformed inductive loops and radar equipment shall be measured by the unit or
fraction thereof furnished, assembled, and completed in accordance with the
Contract Documents and as measured by the Engineer. The quantities as
contained on the Schedule of Quantities and Prices, or approved schedule of
values, as applicable, as derived from the Plans will be used as the basis for this
measurement.
D. Narrow Band Shunts, Wideband Shunts and Tuned Joint Couplers (NBS, WBS
& TJC’s) will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
D. Narrow Band Shunts, Wideband Shunts and Tuned Joint Couplers (NBS, WBS
& TJC’s) furnished and completed in accordance with the Contract Documents
will be paid for at the Contract Unit Price, as listed on the Schedule of Quantities
and Prices. This price shall include full compensation for furnishing all labor,
Materials, tools, equipment, supplies, supervision, and incidentals, and doing all
work, as shown on the Plans, and as specified in these Specifications, and as
directed by the Engineer.
E. The Narrow Band Shunts, Wideband Shunts and Tuned Joint Couplers (NBS,
WBS & TJC’s) shall include the cost of related enclosures, track wires and
exothermic track connections and all associated equipment, conduits, mounting
hardware, trenching and filling, adjustments and testing as shown on the Plans,
and as specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section shall include providing detailed design, furnishing and
installing a complete Dragging Equipment Detector as specified herein and as
shown on the Contract Drawings.
1.03 SUBMITTALS
A. Submit shop drawings for Dragging Equipment Detector System to the Engineer for
approval. Shop drawings, at a minimum, shall show location and method of
installation for the instrument enclosure and track mounted detector
appurtenances.
A. Signal bungalow and any equipment therein shall be shipped, stored and handled
as specified in Section 34 42 46, Signal Equipment Houses.
PART 2 – PRODUCTS
2.01 MATERIALS
A. The Dragging Equipment Detector system shall utilize mechanical paddle detectors
like the Alstom Self Restoring Paddle that can be interconnected and output a
female voice or an approved equivalent system.
B. Defect Detectors shall conform to all applicable parts in Section 5 “Defect Detector
Systems” of the AREMA C&S Manual.
G. The standby power and charging system shall be sized to provide 48 hours of
continuous operation in the event of an AC power failure and conform to the
requirements of Section 34 42 52, Rectifiers, Batteries and Battery Charging
Equipment.
PART 3 - EXECUTION
3.01 INSTALLATION
3.02 TESTS
4.01 MEASUREMENT
B. Batteries and Chargers will not be measured and shall be considered incidental
to the installation of the Dragging Equipment Detector Systems.
C. Grading and site preparation required for the installation of Dragging Equipment
Detector will not be measured and shall be considered incidental to the
installation of the Dragging Equipment Detector Systems.
4.02 PAYMENT
C. No separate payment shall be made for any grading or site preparation required
for the installation of Dragging Equipment Detector and shall be considered
incidental to the installation of the Dragging Equipment Detector Systems.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. The Section includes the requirements for furnishing and installing wayside
signal assemblies.
C. Contractor shall furnish and install signals as specified herein and as shown on the
Contract Drawings.
D. Related Specification Sections include but are not necessarily limited to:
2. Section 31 20 00 – Earthwork
1.02 REFERENCES
A. Wayside signal assemblies shall meet the requirements of AREMA C&S Manual
part 7 and applicable portions of Manual Part 3.2.5, where requirements of the
AREMA Specifications do not conflict with requirements specified herein.
B. Inspect each signal assembly after it has been installed in the field. This inspection
shall conform to the Contractor’s Installation Procedure as accepted by the
Engineer.
C. L.E.D. Lamp Units shall meet the requirements of AREMA C&S Manual Part 7.1.5.
D. Signal aspect shall be distinct and unmistakable when viewed from a height of 7 to
12 feet above top of rail at a distance of 1,000 feet. Nominal sighting distance shall
be 2000 feet. Where unobstructed sighting distance for a standard signal
arrangement is less than 2000 feet, provide to the Resident Engineer written
notifications of sighting problems and locations.
E. Foundations shall meet all requirements of AREMA Signal Manual Part 14.1.1
through 14.4.41 inclusive, where requirements of the AREMA Specifications do not
conflict with requirements specified herein.
F. Resident Engineer reserves the right to make inspections and tests, as necessary,
to determine if the equipment meets the requirements of these Specifications.
1.04 SUBMITTALS
A. Contractor shall submit shop drawings for each type of signal unit and each type of
signal layout to the Resident Engineer for approval. Show all ladders, masts,
bases, arms and required mounting hardware. Show location and method of
mounting the signals to the structure.
A. Ship lamp units separately from the signal head in which they will be used.
B. Contractor shall ensure that all wayside signal assemblies and signal lamp units are
safely stored and protected from damage during storage, handling and transporting.
1.06 WARRANTY
A. Contractor shall provide warranty from defects arising from defective parts,
workmanship, and lightning damage for 2 years from the first date of service.
PART 2 – PRODUCTS
2.01 MATERIALS
A. Contractor shall furnish color-light signal heads as specified herein, and as shown
on Metrolink Engineering Standard 8525
A. Signal head shall be furnished with L.E.D. lamp units, blank out cover plates (if
applicable), hoods, background, mounting brackets, and U-bolts to fit 5-inch mast
assemblies that Contractor proposes to furnish.
B. Signal head shall include mounting bracket for 5-inch mast and stainless steel
fasteners.
C. Color-light signal units shall be capable of displaying three aspects: green, yellow
and red as shown on Metrolink Engineering Standard 8525
E. Signal head shall be designed to allow removal of lamp units from the rear.
G. Signal access covers (doors) shall be provided with a means of securing in closed
position.
C. Each ground signal assembly must be fully compliant with the latest OSHA and
CAL-OSHA fall protection requirements in effect at the advertisement of this
Contract. Where a conflict exists between the requirements, the most stringent
shall apply.
A. Signal masts shall be predrilled for the placement of signal unit(s) by the
manufacturer at the factory. Nominal signal mast height is between 21’-0” and
21’7”. A 5-inch cap for top of mast shall also be provided with each mast unit.
C. Signal mast shall be fitted with one (1) 48-inch long No. 2 ground wire cad-welded
to the mast as shown on Metrolink Engineering Standards 8500 and 8505. The
pigtail shall be coiled and secured in a manner that prevents during construction
and while in transit.
C. Ladder platform cages shall extend a minimum of 42 inches above the top of
landing.
2.07 FOUNDATIONS
B. Furnish galvanized steel foundations complete with galvanized bolts, washers, nuts
and associated hardware. Galvanizing shall conform to Specifications Section 34
42 60, Signal Systems Miscellaneous Products, and AREMA Signal Manual, Part
15.3.1.
C. Construct galvanized steel foundations of steel angle and plate welded together.
Foundations shall be constructed of 2 1/2 inch by 2 1/2 inch by 1/4 inch steel angle
and 1/4 inch steel plate.
PART 3 - EXECUTION
A. Contractor shall furnish and install signal layouts in locations as indicated on the
Contract Drawings and as shown on the accepted shop drawings. No part of any
signal layout shall conflict with Metrolink Engineering Standards, Code of Federal
Regulations, Part 49, nor installed within the clearance envelope as defined in
CPUC G.O. 26-D.
B. Locate signals centered between insulated joint, except where physically not
possible. In such instances, submit a recommendation to the Resident Engineer for
approval.
C. Center line of signal mast shall be 15 feet 0 inches from centerline of track unless a
deviation from this is approved by the Resident Engineer, as shown on the Contract
Drawings or required to meet CPUC clearance requirements.
D. Install signal unit level and plumb on their foundations. Leveling nuts shall be used
as shown on Metrolink Engineering Standards.
K. The underground cable shall be dressed, pot-headed, tagged and terminated in the
signal junction box as specified in Section 34 42 60, Signal Systems Miscellaneous
Products. The number of conductors and conductor size of the underground cables
shall be as shown in the contract drawings.
L. Wiring from the junction box base to the signal heads shall be No. 10 AWG copper
stranded wire as shown on the Contract Drawings.
M. Install identification tags on each wire. These tags shall bear the nomenclature
shown on the accepted Shop Drawings.
N. Set lamp voltage between 8.8 volts and 9.2 volts measured at the signal lamp.
A. The junction box shall have two terminals with insulated test links for each cable
conductor, as specified in Section 34 42 60, Signal Systems Miscellaneous
Products.
B. Junction box placement and cable entry to the junction box shall be as shown on
Metrolink Engineering Standards 8500 and 8505.
C. The method of routing #10 flex wire from the junction box to each signal mounted
on the structure shall be to route the wire within the tubular members of the
structure. Pull wires entirely through the structure members, mast and signal
mounting brackets, unless otherwise approved by the Resident Engineer.
D. Provide pull boxes located a maximum of 5 feet from each signal. Edges shall be
smooth and rounded to accommodate cable installation.
B. Refer to Section 01 14 49, Coordination with Utilities, for requirements for locating
and protecting existing utilities. Advise the Resident Engineer immediately if any
utility or cable interferes with foundation work. After locating interference, allow 72
hours for the Resident Engineer to relocate or mitigate the interference.
C. Prior to placing steel foundations in the excavations, place and compact a crushed
stone base in accordance with Section 31 20 00, Earthwork.
D. When placing foundations, exercise care and ensure that anchor bolts are not bent,
or threads damaged. Protect anchor bolt threads, washers, and nuts by applying
friction tape or other accepted method satisfactory to the Resident Engineer, until
the unit to be supported is installed.
E. After back filling excavation, the Contractor shall ensure that the foundation is
plumb and level. Where ground signal foundations are installed, the top of the
foundation shall be no higher than the nearest rail and no lower than the top of
nearest tie. Under no circumstance shall the top of the foundation be more than 24
inches above final grade.
G. The Contractor shall provide a means to prevent entry of rodents and insects at the
bases of the vertical masts.
3.04 PAINTING
A. Make tests for proper operation and setting of lamp operating voltages in
accordance with Section 34 42 58, Signal Systems Testing.
4.01 MEASUREMENT
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
1.02 REFERENCES
1. Part 236: Rules, Standards, and Instructions for Railroad Signal System.
1.03 SUBMITTALS
1.06 WARRANTY
A. Provide warranty from defects arising from improper handling for 2 years from
the first date of service.
PART 2 - PRODUCTS
2.01 MATERIALS
B. PTC Radio
1. The PTC Radio shall be an ITC 220 Wayside Radio (Part Number
133980) manufactured by CalAmp or approved equivalent.
2. The PTC Radio shall be capable of operating between 217.6 and 222.0
MHz.
C. Surge Protection
1. PTC related surge protection shall be the 12R ICP (Part Number 1101-
624) manufactured by Transtector Systems or approved equivalent.
D. GPS/Cell Antenna
1. The GPS/Cell Antenna shall be the Mobile Mark GPS Antenna (Part
Number V5501-A) distributed by ARMS, Inc. or approved equivalent.
2. The GPS/Cell Antenna shall be composed of one GPS and two Cellular
Antennas.
3. The GPS/Cell Antenna shall mount to the signal shelter with the Antenna
Mount Kit (1.25” Pipe GPS with Bracket) manufactured by PTMW, Inc. or
approved equivalent.
E. PTC Antenna
1. The PTC Antenna shall be the Yagi Directional Antenna (Part Number
SY206-SF11SNM-U) manufactured by Sinclair or approved equivalent.
2. The PTC Antenna shall have a frequency range between 217 and 225
MHz and a nominal gain of 9.5 dBd.
1. The PTC Antenna Tower shall be the 60 foot Tilt-Down Tower (Part
Number SQT60MXHD) manufactured by Western Towers or approved
equivalent.
G. Polyphasers
2. The PTC Polyphaser shall be the 50-700 MHz Arrestor (Part Number IS-
B50HN-C1) manufactured by PolyPhaser or approved equivalent.
3. The Cell Polyphaser shall be the .700 – 2.7 GHz DSXL Arrestor (Part
Number DSXL) manufactured by PolyPhaser or approved equivalent.
H. Category 5 Cable
1. Cellular
2. PTC
a. PTC coax cable shall be the 1/2" Superflex Corrugated coax cable
(Part Number FSJ4-50B) and the 7/8” HELIAX Corrugated coax
cable (Part Number AVA5-50) manufactured by Andrew or
approved equivalent.
3. GPS
PART 3 - EXECUTION
3.01 INSTALLATION
C. All outdoor connectors, splices, antennas and ground kits shall be weather
sealed.
3.02 TESTING
B. All PTC Wayside Radios shall be tested by the Contractor for function and
performance.
3. Tests shall include interoperable tests for track areas where more than
one railroad operate. This shall include database verification and
operations testing for each railroad.
4.01 MEASUREMENT
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section includes, but is not limited to, general procedures and
requirements and incidental to the review, planning, manufacturing, assembly,
installation, removal, relocation, modification, testing, commissioning, and
documentation of as-built conditions of the various Railroad Communication
Systems.
1.03 REFERENCES
C. The following General Orders (GO) or the most current General Orders of the State
of California Public Utilities Commission (CPUC) shall apply:
E. The following parts of the Code of Federal Regulations, Title 49, Transportation,
shall apply:
A. Reference ES9005 for high level overview of the SCRRA Communication System.
C. All materials and equipment for installation and for interconnection of the various
communications systems shall be fabricated, furnished, and installed as indicated
on the Contract Plans and specified herein.
D. The Contract Plans represent a final design utilizing systems, components, and
materials that meet the Contract Specifications. Contractor may provide
equivalent systems, components, and materials subject to the approval of the
Engineer. If equivalent systems, components, and materials are provided, the
Contractor shall provide an alternate detailed final design as specified herein under
Design Submittals.
1.06 SUBMITTALS
A. All submittals required herein apply to all communications work shown within the
Contract Plans. Refer to the specific communications subsystem specification for
additional submittal requirements that are specific to the subsystem.
B. No related work can begin without the prior submittal and Engineer approval of the
personnel, material, plans and procedures.
C. Submit resume(s) of the Communications Engineer(s) who will oversee the related
work.
D. Submit resume of all personnel who will perform splicing as a Fiber Splice
Technician(s).
G. Submit a complete Network Device List for all Local Area Network (LAN) devices
that will be added or removed by the project 30 days prior to scheduled installation.
I. Submit a Test and Commissioning Plan for all communications systems that will
be impacted by the project 30 days prior to the scheduled installation.
B. The communications systems represented in the Contract Plans are broad and the
experience of a single Communications Engineer may not encompass all systems.
When this occurs, the Contractor shall submit more than one candidate to
collectively demonstrate experience in all systems being constructed. In this case
each Engineer shall coordinate under a designated Lead Engineer.
C. Detailed Qualifications
1. Networks
2. RF (Radio Frequency)
D. Submittal Requirements
A. The Fiber Splice Technician(s) shall be engaged in the fiber cable inspection,
installation, splicing, testing and commissioning and shall be qualified and have
had experience in the type and level of work as required herein and by the Contract
Plans. Once accepted, any replacement of these key employees shall be subject
to the approval of the Engineer.
B. Detailed Qualifications
C. Submittal Requirements
A. The lead Communications Engineer shall generate a master Bill of Materials for
the communications systems.
a. Equipment Description
b. Manufacturer
d. Total Quantity
e. Installation location
f. Quantity by location
A. The lead Communications Engineer shall generate a Network Device List for the
communications systems. This will serve as the basis for obtaining IP address
assignments from SCRRA and other pertinent configuration information.
3. Blank columns within the spreadsheet shall contain the following minimum
information:
a. IP Address
b. Network Mask
c. Gateway
1. Construction Phase
C. Should the construction phasing change during the project in a way that impacts
the communications systems, that Contractor shall submit an updated
Communications Construction Sequencing Plan.
B. Depending on the scope of the communications work, all phases of testing may
not be applicable. The lead Communications Engineer shall evaluate the testing
required in context with the communications work defined in the Contract Plans.
1. Factory Inspection
2. Rack Testing
D. The Inspection, Test and Commissioning Plan shall contain the following:
1. Summary Narrative
2. Summary Table
1) Communications Shelter
1) Factory Inspection
2) Rack Testing
A. The lead Communications Engineer shall prepare a Training Plan that outlines the
Contractor’s overall approach to training and schedule.
B. Depending on the scope of the communications work, a Training Plan may not be
required. The lead Communications Engineer shall evaluate the training required
in context with the communications work defined in the Contract Plans.
D. Training Requirements:
5. Each training class shall include paper handouts and all materials provided
on a USB flash drive for each student.
a. Course Objective
b. Course Outline
c. Technical Theory
f. SCRRA Application
A. After a location is placed in service and prior to final acceptance of the project, the
Contractor shall submit the following as-built documentation within 3 business
days:
1. Drawing annotations
2. Configuration files
B. Annotate the As-Built drawing sets to show all approved circuiting and wiring
changes made during installation and testing of the location prior to placing it in
service, and any approved changes made after placement in service. Clearly
identify all changes on the Drawings using the "Red In"/"Yellow Out" convention.
Changes shall be dated and initialed by the Contractor's Communications
Engineer.
A. Submit the Bid Item List for communications bid items as required under Section
01 29 73, Schedule of Values, and in accordance with the following additional
requirements:
1. Bid Item List for the communications bid items shall include all interface
circuits and staging necessary to place the location in service at each
stage, all acceptance testing and transportation of materials, all equipment
rental, all pretesting and removal of old equipment.
2. Organize Bid Item List for communications bid items to assign a value to
each communications location. A location is defined as a grade crossing
warning system, an intermediate signal location, a Control Point, or a
communications shelter.
1.16 WARRANTY
A. Provide warranties for all equipment and material covering parts and labor for two
years from the date equipment or material is "placed in service".
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
4.01 MEASUREMENT
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 44 00
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section describes the technical requirements for products and
miscellaneous components to be provided, installed, and tested to support the
organization of communications subsystems.
B. This Section also describes requirements for labeling all communications cable, wire
and equipment installed.
1.03 REFERENCES
1.04 SUBMITTALS
A. Submit cut sheets for all proposed products that meet the specifications of this
Section.
C. Submit labeling for all Inside Plant cable and wire installed within the
communications shelter or enclosure.
1. Equipment
B. Labeling Convention
3. “/” is the separator used after the originating end detail and means “TO”.
5. An example is “R101-FDP-A-1.2/R101-JUMBO-1-1”
6. Refer to ES9530-02.
1. Beginning from the right side of the communications shelter (when facing
from the entrance door) and moving towards the left side, racks shall be
assigned numbers starting with “101”, “102”, “103”, etc. If there is space
designated for future racks to be installed, their assigned number shall be
reserved.
20. Any equipment not defined within this list shall be assigned an abbreviation
not exceeding 6 characters. The abbreviation shall be recognizable as the
equipment described.
1. This field is used when the equipment from which the cable originates from
or is destined for is modular. To determine card or slot numbers, the
equipment silkscreen identifiers shall be used. If there are no silkscreen
identifiers, the equipment manual shall define the card or slot number
assignments.
F. Port Number
1. This field is used when the equipment from which the cable originates from
or is destined for is modular. To determine card or slot numbers, the
equipment silkscreen identifiers shall be used. If there are no silkscreen
identifiers, the equipment manual shall define the card or slot number
assignments.
1. Labeling shall conform with the Fiber Route Diagram information for each
Subdivision, which provides cable segment and site codes.
2. In every pull box that contains the Backbone Cable, the following
convention shall be used:
3. When a fiber cable lateral is in a pull box, the following convention shall be
used:
b. An example is “SGV56.11-FSE-FS72-SG100-L1/CP56.1-FDP”
b. An example is “CP56.1-FDP-FS72-SG100-L1/SGV56.11-FSE-1”
5. Cable Segment ID
b. The location site code shall utilize a milepost to the tenth of a mile
(MM.M) and the Site Type.
a. The pull box site code (V) shall utilize a milepost to the nearest
hundredth of a mile (MM.MM) of the pull box location and the
Subdivision (XX). If there is more than one vault at the milepost
location, vaults shall be labeled A, B, C, etc, working from Railroad
West to Railroad East.
b. An example is “VHF_BASE-LDF4-50A/220-4N-20FT”
PART 2 - PRODUCTS
A. Labels shall be a minimum of 0.75 inch in height and 1.5 inches wide.
B. Label material
1. Shall be UL listed.
C. Label printers
A. Labels shall be suitable for the environmental conditions in which they are applied
(such as moisture, heat, or ultraviolet light).
3. Under the cover of the yellow label, a white vinyl label meeting the
requirements of inside plant label material and printing shall be applied.
A. Zip ties
2. Shall be self-locking.
2. Shall be self-gripping.
3. Shall have color coded wire strips that assist in wire sorting.
4. Shall have jumper troughs sized to meet the cable minimum bend radius.
B. Protector Modules
3. Shall contain fingers to separate and organize patch cords for adds, drops
and modifications.
2.07 EXECUTION
2.08 INSTALLATION
1. Labeling shall be applied to all equipment, cables and wires installed by the
Contractor.
3. Character size shall not be less than 1/8th inch in height, and not exceed 3
rows.
5. At conduit entrance openings, labels shall be placed not less than 6 inches
from the opening.
3. Punch down one single wire on each terminating clip. Do not punch down
more than one wire per post.
3.01 MEASUREMENT
3.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 44 05
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section describes the technical requirements for products and
miscellaneous components to be provided, installed and tested to support the
housing of communications subsystems.
B. After the shelter is installed at its final location, the Contractor shall install all
equipment racks, wall mounted cable termination protections and other
communications equipment where shown on the Plans.
a. This shelter type will house SCRRA and an identified third party.
1.03 REFERENCES
A. ASCE 7-05, 7-10 – Minimum Design Loads for Buildings and Other Structures
C. ASTM A615 Grade 60– Standard Specification for Deformed and Plain Carbon-
Steel Bars for Concrete Reinforcement
D. ASTM A1064 – Standard Specification for Carbon-Steel Wire and Welded Wire
Reinforcement, Plain and Deformed for Concrete
F. ASTM F3125 – Standard Specification for High Strength Structural Bolts and
Assemblies, Steel and Alloy Steel, Heat Treated, Inch Dimensions 120ksi and 150
ksi Minimum tensile Strength and Metric Dimensions 830 MPa and 1040 MPa
Minimum Tensile Strength
1.04 SUBMITTALS
A. Submit Geotechnical Report for the area where the shelter will be installed.
B. Submit Fabrication Drawings produced by the shelter manufacturer that show the
following information:
3. Roof Plans – roof slope, cast in bolt pattern for antenna tripod mount,
dimensions and bill of materials.
7. Electrical Panel – schedule for each panel, single line diagram and alarm
wiring.
PART 2 - PRODUCTS
A. Structural
5) Be bullet resistant
b. Roof shall:
c. Wind design shall use a Basic Wind Speed of 110 mph, Exposure
Category C.
2) Design Category F
3) Occupancy Category IV
3. Floor
B. Architectual
1. Exterior
3. Flooring
b. Shall use 12” x 12” Static Dissipative Tiles (SDT) with 1/8-inch
thickness. Tile color shall be Ashgray.
1. Void(s) shall be placed in the floor of the shelter for entrance conduits as
indicated in the Plans.
2. Waveguide window shall be placed in line with the interior cable ladder and
support 4 cable entrance ports. Ports shall be 4-inch in diameter.
E. Electrical
1. Each tenant within the shelter shall be supplied with a minimum 100A 24
space integrated load center and Transient Voltage Surge Suppressor
(TVSS) Type 2.
2. The SCRRA tenant side shall incorporate and manual transfer switch and
external 30A (NEMA L14-30R) Ground Fault Circuit Interrupter (GFI)
receptacle.
7. A 240VAC, 30A circuit and fusible disconnect shall be provided for each
HVAC unit.
G. Alarms
a. Intrusion Detection
b. Smoke Detection
c. Power failure
d. High/Low temperature
e. AC failure
f. Humidity
g. Ionization
h. HVAC lockout
H. Lighting
1. Interior lighting shall be LED with acrylic lens cover. Light levels shall be
adequate for reading.
3. Emergency lighting shall include green illuminated exit sign, dual flood
lights and battery backup of 90 minutes.
4. Interior light switches shall be provided adjacent to the door(s) for both
interior and exterior lighting.
I. Cable Ladder
1. Cable ladder shall be 18” wide with 1 ½” stringer, yellow Zinc with hardware
to anchor into concrete.
J. Grounding
K. Additional Items
1. A plywood board, minimum 4’ tall and ¾” thick, shall serve as the Main
Distribution Frame (MDF) for each tenant. The board shall be painted
white.
A. Each shelter shall be provided with address signage on the side of the exterior
door for identification.
1. The sign shall have a white reflective background with 3 inch black
lettering.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Foundation
2. Ensure foundation design includes voids to allow for entrance conduits into
the shelter floor as shown in the Plans. Entrance conduits shall be placed
near the vertical cable ladder and the MDF board.
B. General
C. HVAC
1. Dual HVAC units shall be wired together to cycle (alternate) on-off during
normal operation, or all one unit to operate should the other unit fail.
D. Grounding
4.01 MEASUREMENT
4.02 PAYMENT
B. Work of this section shall include furnishing all factory acceptance testing,
transportation, storage, assembly, delivery, permits and incidentals as shown on
the Plans, and as specified in these Specifications, and as directed by the
Engineer.
END OF SECTION 34 44 10
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section describes the technical requirements for products and
supporting components for communications wire and cable to be furnished,
installed, terminated and tested to support communications data transmission.
B. Requirements for various cabling utilized by SCRRA including fiber optic, coaxial,
waveguide, and twisted pair are detailed herein.
1.03 REFERENCES
C. ASTM E-814 - Standard Test Method for Fire Tests of Penetration Fire Stop
Systems.
1.04 SUBMITTALS
A. Submit cut sheets for all proposed products that meet the specifications of this
Section.
B. Submit installation and maintenance manuals for all cable and supporting
equipment furnished.
C. Prior to ordering any backhaul fiber optic cable, submit a fiber cable order plan that
includes a complete listing of cable types, cable manufacturers, quantities, reel
sizes and targeted location of installation within the project. The reel sizes shall
include the required cable slack within the systems. An additional reel shall be
ordered to account for 25% of total cable. This reel shall serve as a guardband
and if not required by the contractor shall be submitted to SCRRA as spare
material.
D. For backhaul fiber optic cable, a detailed cable installation plan shall be submitted.
The installation plan shall designate pull points,
1) 1310nm
2) 1550nm
1) 850nm
2) 1300nm
PART 2 - PRODUCTS
a. Loose tube cable of 250 um coated fiber suitable for duct, aerial and
direct bury applications.
i. Optical fiber
3) 1310nm
4) 1550nm
2. Single mode patch cables shall utilize fiber that is compatible with the
backhaul cables.
1. SCRRA standard multimode fiber optic station cable shall meet the
following characteristics.
a. Loose tube cable of 250 um coated fiber suitable for duct, aerial and
direct bury applications.
c. Optical fiber
4) 850nm
5) 1300nm
2. Multimode patch cables shall use fiber that is compatible with the station
cables.
3. All panel cards shall have pigtails that are factory tested and fusion spliced
to the backhaul or station fiber cable.
4. Fiber cassette use is permissible only when all fibers are terminated within
a cable.
5. Fiber cassette use is not permissible if certain fiber strands within the cable
are designated to be fusion spliced (west to east) within the signal or
communications enclosure. These fibers cannot be physically spliced
within the same cassette.
a. Support 2 times the fiber strand count. For 72 strand fiber, fiber
optic termination shall support 144 terminations.
2. Splice trays shall be sized to seat and store the maximum number of
possible splices.
a. Category 3, up to 10Mbps
1) 16MHz bandwidth
1) 24 AWG
2) 100MHz bandwidth
c. Category 6, up to 1000Mbps
1) 23 AWG
2) 250Mhz bandwidth
3. RS-422 cable
a. Sheilded
b. 22 AWG
2. Be a minimum of 16 AWG
3. Unsheilded
2.05 WAVEGUIDE
1. Have attenuation and power information for the frequency of the radio
application.
PART 3 - EXECUTION
3.01 INSTALLATION
A. General
1. Visually inspect all equipment for possible damage upon receipt and prior
to installation. Do not install any damaged equipment.
1. Use the proper eye protection when working on fiber optic cable. Never
look directly into the end of any optical fiber unless certain that no light is
present in the fiber.
2. Optical fiber is sensitive to dust and dirt. Maintain the highest standards of
cleanliness when working with fiber. Always keep dust caps on connectors,
mating adapters, patch panels, or test equipment. Use lint free wips and
pure reagent grade isopropyl alcohol to clean connectors.
3. Conduct on-reel testing to verify the cable was not damaged during
shipping.
4. Prior to installation, survey the conduit and pull box locations in the field for
creation of the pull plan. The pull plan shall include a copy of the
manufacturer’s installation recommendations.
5. Swivel pulling eyes shall be used to attach the pulling rope to prevent cable
twisting during the pull.
7. When laying loops of fiber on a surface during a pull, use figure eight loops
to prevent twisting the cable.
10. Any metallic hardware used in fiber optic cable systems (such as the armor)
shall be grounded.
11. During OTDR testing, set the test pulse as short as possible for the range
needed to reach the end of the cable for best resolution.
1. Support cabling to prevent undue stress from its own weight. The cable
shall be free of tension at both ends, as well as over the entire length of the
run.
D. Waveguide
2. Use a hoist line that supports the total weight of the waveguide. Use a
pulley high enough on the tower to allow the waveguide to be raised
sufficiently to make the antenna connection. A winch is recommended for
hoisting.
4. The top and bottom of the waveguide shall be grounded to the tower. The
antenna input connection shall not serve as top ground. Ground the
waveguide at the point where it enters the enclosure.
b. Insertion loss
c. VSWR
E. Coaxial Cable
1. The top and bottom of the coaxial cable shall be grounded to the tower.
Ground the coaxial cable at the point where it enters the enclosure.
b. Insertion loss
c. VSWR
4.01 MEASUREMENT
A. Communications Wire and Cable will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
A. Communications Wire and Cable furnished and completed in accordance with the
Contract Documents will be paid for at the Contract Unit Price, as listed on the
Schedule of Quantities and Prices. This price shall include full compensation for
furnishing all labor, Materials, tools, equipment, supplies, supervision, and
incidentals, and doing all work, as shown on the Plans, and as specified in these
Specifications, and as directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 44 20
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section describes the technical requirements for products and
supporting components to be furnished, installed and tested to support, extend or
modify the Customer Information System (CIS).
B. Requirements for various systems, methods and cabling utilized by SCRRA for
Public Address, Real Time Messaging, Schedule Information, Ticket Vending and
Emergency Management at Passenger Stations are detailed herein. The Pomona
DOC is the SCRRA Operations Center.
1.03 REFERENCES
1.04 SUBMITTALS
A. Submit cut sheets for all proposed products that meet the specifications of this
Section.
D. Public Address
a. Audio Controller
b. Audio Processor
PART 2 - PRODUCTS
3. Support redundant fans for cooling. The switch shall be able to operate if
one of the fans fail.
b. 802.1Q VLAN
c. 802.1p QoS
d. 802.1w RSTP
g. 802.3af PoE
h. 802.3at PoE+
a. Web Browser
b. Telnet
c. SNMP
1. Support configurable inputs and outputs (I/O) via a minimum of 4 card slots.
1) AES3 standard
1) AES3 standard
a. Crossovers
b. Compressors
c. Gates
d. Duckers
e. Expanders
f. Limiters
g. Gain blocks
h. Graphic Equalizers
i. Filters
j. Metering points
k. Delays
l. Mixers
m. Tone Generators
n. Source Selectors
5. Have 8mm pitch pixels, 1600 pixels per square foot. The failure of a single
pixel shall not cause failure of any other pixel in the display.
12. Have front service access using a tamper resistant key entry system.
13. Support alphanumeric text in character sizes that meet ADA requirements.
14. Support presentation modes of steady, horizontal scroll, vertical scroll and
flash.
16. Use a protocol compatible with SCRRA’s LED signage head end control
software.
2. Be a 49-inch display.
10. Be fanless.
2. Contain a sunshield.
PART 3 - EXECUTION
3.01 INSTALLATION
A. General
1. Visually inspect all equipment for possible damage upon receipt and prior
to installation. Do not install any damaged equipment.
3. All equipment chassis shall be grounded to the main ground within the
enclosure. Use a separate ground cable for each equipment instance. If
equipment is grounded to the rack, verify that the rack is connected to the
main ground. Do not assume that an existing rack is correctly grounded.
4. Mount equipment with clearance to allow for proper ventilation and air flow.
1. All device IP assigned under the CIS subnet shall be connected to the CIS
Ethernet switch.
3. All patch cables shall be installed neatly using vertical or horizontal cable
management.
E. Audio Amplifier
1. When powering a fully configurate Public Address system, always turn the
amplifiers on last and off first.
2. Configure the amplifier for 70V output mode, Dual mode, High Z.
1. Install Ambient Noise Sensor on platform pole or canopy near area where
trains stop. House in an electrical outlet box with 2-inch minimum depth.
2. Run a 2-conductor shielded mic cable from the Audio Signal Processor to
the area where the sensor will be installed. Enable phantom power at the
Audio Signal Processor.
1. Power for the monitor enclosure shall be provided from the station electrical
distribution panel.
I. Testing
1) Verify all signs can display test messages from local laptop.
d. TVM
2. Coordinate with the CIS help desk to perform testing with the head end
systems located at the Pomona MOC/DOC.
1) Verify all signs can display remove messages from the head
end system.
d. TVM
4.01 MEASUREMENT
4.02 PAYMENT
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 44 50
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section describes the technical requirements for products and
supporting components to be furnished, installed and tested to support, extend or
modify the Wide Area Network (WAN).
1.03 REFERENCES
N. ITU G.694.1 – Spectral grids for WDM applications: DWDM frequency grid
1.04 SUBMITTALS
A. Submit cut sheets for all proposed products that meet the specifications of this
Section.
C. The Plans have been prepared using Vendor specific equipment. Should the
Contractor propose equivalent systems and they are approved by the Engineer,
the Contractor shall update all Plans where the equipment is used at no additional
cost.
1. Submit Optical Link Budget calculations for all new and existing WAN
nodes impacted by the project.
a. Station
b. Control Point
c. Intermediate
E. Microwave WAN
1. Submit Optical Link Budget calculations for all new and existing WAN
nodes impacted by the project.
PART 2 - PRODUCTS
1) Mesh
2) Ring
3) Point to Point
1) 802.1Q VLAN
2) 802.1p QoS
3) 802.1w RSTP
6) Port Mirroring
7) IGMP Snooping
1) 4U chassis
2) 2U chassis
1) AC 115/230V
1) VLAN
2) SNMP
3) Serial Console
4) Telnet
1) Single Mode
a) 100Base-FX
(2) 1310nm
b) 1000Base-LX
2) Multimode
a) 100Base-FX
(1) 2km
(2) 1310nm
b) 1000Base-SX
a) 1000Base-LX
4) Copper
a) 1000Base-T
A. The Train Control Microwave Radio equipment shall be Aviat Eclipse IRU 600,
Alcatel Lucent 9500 MPR, as indicated on the Drawings, or Engineer approved
equivalent.
a. 802.1Q VLAN
b. 802.1p QoS
2. Support Bridge Protocol Data Unit (BPDU), RSTP, and path costs to
eliminate Ethernet loops, while supporting path redundancy. It shall be
possible to close Ethernet rings using alternate media such as fiber.
10. Support Adaptive Coding and Modulation (ACM) steps of QPSK, 16 QAM,
64 QAM, and 256 QAM. Modulation switching shall be error-free.
11. Support co-channel dual polarized (CCDP) link operation with cross
channel interference cancellation (XPIC).
12. Support Automatic Transmit Power Control (ATPC) for all frequency bands.
13. Support link aggregation on two or more co-path Ethernet links using Layer
1 or Layer 2.
b. Engineering (read/write)
18. Support operation from -48 VDC power supply and be 19-inch rack
mountable.
b. Alarm inputs for TTL interfaces. (2V high and 0.8V low)
a. 6 GHz (L6/U6)
b. 11 GHz
3. Be of compact design and 19-inch rack mountable for colocation with its
baseband unit.
5. Support stackable transceivers, with one installed for 1+0 operation and
two for 1+1 or 2+0 operation.
8. Have low power and high power RFU options. The high-power option shall
use the best energy efficiency.
2. Shall support a craft tool to provide a means to source and save software
upgrades and download software to the platform. Craft tool shall support
the following options:
b. Transfer only.
A. The Security Data Network (SDN) DWDM switch equipment shall be Ciena Service
Delivery Switch (SDS) 3942, Ciena 5160 Service Aggregation Switch (SAS) as
indicated on the Drawings, or Engineer approved equivalent.
4. Support the following transport options for CE 2.0 compliant MEF Ethernet
Services:
a. G.8032 rings
b. 802.1Q VLANs
d. IP/MPLS
e. MPLS-TP
6. Support Network Node Interface (NNI) and User Network Interface (UNI)
connections via the SFP ports.
8. Capable of Zero Touch Provisioning (ZTP) and will auto configure a new
switch once connected to the network and powered up.
11. Support a quick reset (reboot) and a hard reset (factory defaults).
3. Support the following transport options for CE 2.0 compliant MEF Ethernet
Services:
a. G.8032 rings
b. 802.1Q VLANs
d. IP/MPLS
e. MPLS-TP
5. Support Network Node Interface (NNI) and User Network Interface (UNI)
connections via the SFP ports.
7. Capable of Zero Touch Provisioning (ZTP) and will auto configure a new
switch once connected to the network and powered up.
10. Support a quick reset (reboot) and a hard reset (factory defaults).
2. Be FirstNet Ready
7. Support GPS.
PART 3 - EXECUTION
3.01 INSTALLATION
A. General
1. Visually inspect all equipment for possible damage upon receipt and prior
to installation. Do not install any damaged equipment.
3. All equipment chassis shall be grounded to the main ground within the
enclosure. Use a separate ground cable for each equipment instance. If
equipment is grounded to the rack, verify that the rack is connected to the
main ground. Do not assume that an existing rack is correctly grounded.
4. Mount equipment with clearance to allow for proper ventilation and air flow.
1. Enter the factory measured insertion loss data labeled on the ACU.
2. The ACU shall be retuned if the frequency is changed outside its specified
pass band. ACUs shall be returned to the manufacturer for retuning.
4. For NEBS compliance, the fan air filter and power line filters shall be
installed.
1. Ensure that the installed SFP optic matches the capability of the port and
that the SFP optic is supported by the system.
1. Prior to installation, confirm the device has the latest version of firmware
that supports the device.
2. Mount the device out of reach. The surface of the device may become too
hot to safely touch.
3. The SIM card shall be provisioned by the cellular carrier SCRRA has
selected for each location.
F. Testing
2. Microwave
a. Bit Error Rate (BER) test shall be performed for each link for a
minimum time of 24 hours.
3. Optical Ethernet
4.01 MEASUREMENT
A. Wide Area Network will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Wide Area Network furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 44 70
PART 1 - GENERAL
1.01 SUMMARY
A. The work in this Section describes the technical requirements for products and
supporting components to be furnished, installed and tested to support, extend or
modify the Data Radio Network.
1. 34 42 60 Miscellaneous Materials
1.03 REFERENCES
1.04 SUBMITTALS
A. Submit cut sheets for all proposed products that meet the specifications of this
Section.
C. The Plans have been prepared using Vendor specific equipment. Should the
Contractor propose equivalent systems and they are approved by the Engineer,
the Contractor shall update all Plans where the equipment is used at no additional
cost.
1. Submit simulated Predicted Area of Coverage and Line of Sight plots for
each Control Point from the 2 closest ATCS bases to establish the
expected test results.
E. Ethernet Radio
2. Submit simulated Line of Sight plots showing the link budget for each link
shown in the Drawings.
PART 2 - PRODUCTS
9) Have Audio Response of +1, -3dB from 6dB per octave pre-
emphasis
a) Event log
b) Log Capture
A. The Train Control Ethernet Radio equipment shall be Afar AR-9010E or Engineer
approved equivalent.
1. Use Direct Sequence Spread Spectrum and operate in the unlicensed ISM
band at 900MHz.
a. Point to Point
b. Point to Multipoint
a. Telnet
b. SNMP
a. DES
b. Triple-DES
c. AES-128
d. ASE-256
11. Route packets to reduce the minimum number of hops through a learning
algorithm.
PART 3 - EXECUTION
3.01 INSTALLATION
A. General
1. Visually inspect all equipment for possible damage upon receipt and prior
to installation. Do not install any damaged equipment.
3. All equipment chassis shall be grounded to the main ground within the
enclosure. Use a separate ground cable for each equipment instance. If
equipment is grounded to the rack, verify that the rack is connected to the
main ground. Do not assume that an existing rack is correctly grounded.
4. Mount equipment with clearance to allow for proper ventilation and air flow.
1. All transmission lines shall be grounded with coax grounding kits at the top
of the tower near the antenna, at the bottom of the tower and prior to coax
entry into the shelter.
3. The transmit and receive antenna RF connections shall be made using two
separate N-type connectors.
4. Upon power up, view the front bezel LEDs for the general status and
condition of the radio.
C. Ethernet Radio
1. Verify that line of sight exists for each link. Report any obstructions to the
Engineer.
2. Perform an initial check of the radio using 2 units before field installation.
This will confirm the radios are working properly so other factors (RSSI,
interference) can be addressed in the field.
5. Use anti oxidizing paste to apply to the ground lug blade, exposed cable,
grounding point surface, as well as the thread of the screw to secure the
lug.
6. Install a surge suppressor module at the point where the CAT5E cable
enters the enclosure to protect equipment against surges.
11. Configure the access radio with a WAN connection to the be hub. The
subscriber radios will automatically join the network.
12. Directional antennas may need to be used if there is interference from other
equipment. Use the radio to perform a spectrum analysis.
13. Do not exceed the Maximum Output Power required by the FCC as follows:
14. Once the deployment is complete, record the configuration of each radio
installed.
4.01 MEASUREMENT
A. Data Radio Network will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
4.02 PAYMENT
A. Data Radio Network furnished and completed in accordance with the Contract
Documents will be paid for at the Contract Unit Price, as listed on the Schedule of
Quantities and Prices. This price shall include full compensation for furnishing all
labor, Materials, tools, equipment, supplies, supervision, and incidentals, and
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Work of this section shall include furnishing all acceptance testing, transportation,
storage, assembly, delivery and incidentals as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 44 95
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
4. Section 34 11 16 – Ballast.
7. Section 34 72 00 - Trackwork.
1.02 REFERENCES
1. D3776 Standard Test Methods for Mass per Unit Area (Weight) of Fabric.
2. D4632, Standard Test Method for Grab Breaking Load and Elongation of
Geotextiles.
F. WATCH: Work Area Traffic Control Handbook, Latest Edition, WATCH BOOK,
APWA Southern California Chapter.
G. Federal Railroad Administration (FRA): 49 CFR Part 213, Track Safety Standards.
I. Materials not meeting the requirements of this Specification shall not be used in
the Work.
1.03 SUBMITTALS
A. General
C. Certificates:
1. Material Test Reports for products purchased and used in the Project.
2) Structural calculations.
E. Miscellaneous Submittals:
1. Submit quality control test results for testing performed for precast concrete
panels and other material. Testing shall be performed by a certified test
laboratory hired by the Contactor or fabricator and approved by the
Engineer.
A. Employ a skilled foreman for the Installation of grade crossings, having no less
than 3 years experience in installation of the type of grade crossing panels used.
B. Track work shall be performed under the supervision of an FRA Part 213 Track
Safety Qualified Foreman in accordance with requirements of Section 34 72 00.
C. The Engineer, will review test reports in accordance with the Specifications as
applicable for the material item and may require additional testing to confirm
requirements with the Specifications.
1. Warning lights shall be set so they do not shine into the eyes of locomotive
engineers in on-coming trains.
A. The Contractor must protect against erosion and uncontrolled run-off within and
adjacent to right-of-way in accordance with the Project’s Storm Water Pollution
Prevention Plan (SWPPP) and the approved NPDES Permit in accordance with
Division 01 requirements.
B. The Contractor must obtain all required permits for dewatering and legally dispose
of water from dewatering operations in accordance with Division 01 requirements.
C. Contractor must provide for site cleanliness, sweeping and dust control in
accordance with Division 01 requirements.
A. Furnish any required excavation drawings or traffic control plans to Engineer for
review and approval by SCRRA and jurisdictional authorities.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Precast Concrete highway-rail grade crossing Panels shall be new and conform to
Section 34 11 40:
B. Wood Ties: Ties shall be new 10 feet long and conform to Section 34 11 34.
D. Rail: Rail size shall be 136# CWR and shall conform to Section 34 72 00.
E. Rail Fastening: Rail fastenings shall be new and shall conform to Section 34 72
00.
F. Geotextile:
1. Geotextile filter fabric used for grade crossings shall be nonwoven fabric.
The filaments shall be polypropylene, polyester, or polyethylene. The
filaments must be dimensionally stable (i.e., filaments must maintain their
relative position with respect to each other) and resistant to delaminating.
The filaments must be free from any chemical treatment or coating that
might significantly reduce porosity and permeability. Nonwoven fabric may
be needle-punched, heat-bonded, resin-bonded, or combinations thereof.
Test
Property Requirement
Method
ASTM
Minimum Weight (oz./sq. yd.) 3.5
D3776
ASTM Minimum Wet Grab Tensile Strength
100
D4632 (lbs.)
ASTM Minimum Grab Elongation at Break
20
D4632 (%)
ASTM
Apparent Opening Size(US Sieve) 30
D4751
G. Asphalt Concrete:
2. Asphalt concrete for roadway shall conform to Section 32 12 00, Hot Mix
Asphalt Concrete. Asphalt concrete for roadway approach paving shall
conform to Section 32 12 00, Hot-Mix Asphalt Concrete and the Greenbook
Section 203 – Bituminous Materials as noted in SCRRA Engineering
Standards ES4201 for permanent crossings or ES4302 for temporary
crossings or Agency requirements as specified in the Plans or Project
Special Provisions.
H. Cast-in-Place Concrete
J. Signal Conduit:
PART 3 - EXECUTION
3.01 GENERAL
C. Remove and salvage existing grade crossing panels or other crossing appliances
as required in the Plans in accordance with Section 31 11 50.
C. Cut lines for asphalt and concrete shall be straight and neat in accordance with
Section 31 11 50 and any damage to facilities to remain shall be repaired to the
approval of the Engineer at no additional cost to SCRRA.
A. Hot Mix Asphalt (HMA) pavement for crossing underlayment shall be placed as
indicated in the Contract Documents, according to Section 32 12 00 and as shown
in SCRRA Engineering Standards ES4201.
B. Hot Mix Asphalt (HMA) pavement end ramps shall be provided at all concrete
grade crossing panel installations in accordance with SCRRA Engineering
Standards ES4201 if the preapproved crossing panel is used. End ramps shall be
per the manufacturer’s recommendation if a substitute is approved, but shall not
be less than 3 feet in length.
A. Place new sidewalks, curbs, gutters and other roadway items as shown in the
Contract Documents, inclduing the identified standards of the public agency
identified in the Contract Documents responsible for the roadway and SCRRA
Engineering Standards ES4001 through ES4021.
C. Private, Pedestrian and Bicycle Railroad Grade Crossing Sign, when called for,
shall be installed in accordance with SCRRA Engineering Standards ES4311.
A. Install precast concrete grade crossing panels to the position and location shown
in the Contract Documents in accordance with manufacturer’s recommendations,
the approved procedures and SCRRA Engineering Standards ES4201.
B. Contractor must clean dirt and debris from the flangeways before releasing the
crossing for the passage of trains.
3.07 BALLAST
A. Place and spread ballast in accordance with the details indicated on the Contract
Documents, SCRRA Engineering Standards ES4201 and Section 34 72 00.
3.08 TIES
B. Tops of all ties within the crossing limits shall lie in the same plane. Any tie with
an irregular surface dimension shall be adzed or replaced.
B. Rail joints or thermite welds are not permitted within the limits of the grade crossing
trackwork unless approved by the Engineer.
C. Rail joints consisting of field welds are permitted at the ends of rail strings placed
for crossings. Welds shall conform to Section 34 72 30.
D. Contractor must use a dynamic stabilizer after initial tamping and surfacing
followed by a second surfacing pass in accordance with Section 34 72 20, prior to
the final installation of the grade crossing panels.
E. Every attempt needs to be made to close the roadway for the crossing construction
so that the entire crossing can be completed continuously. If the roadway cannot
be closed, extra efforts shall be utilized to ensure track surface profile is maintained
during and after construction, including but not limited to an extra dynamic
stabilizer pass.
A. Compaction testing for subgrade, trench backfill and sub-ballast shall conform to
Section 31 20 00.
C. Contractor must coordinate with and provide 24 hours advance notice of crossing
work to SCRRA Signal Inspectors and verify that testing of all crossing signal work
has been completed and accepted by SCRRA prior to opening crossing to
vehicular traffic.
4.01 MEASUREMENT
B. All material, work and services included in Sections 34 11 10, Continuous Welded
Rail (CWR); 34 11 15, Other Track Materials (OTM); 34 11 16, Ballast; 34 11 27,
Sub-Ballast and Aggregate Base; 34 11 34, Wood Railroad Ties; 34 11 36, Elastic
Rail Fasteners; and 34 11 40, Precast Concrete Grade Crossing Panels will be
included in this Section and are considered incidental to work under this Section
and will be measured by the unit or fraction thereof furnished and completed in
accordance with the Contract Documents and as measured by the Engineer.
C. No separate measurement and payment will be made to the Contractor for removal
of concrete panels.
4.02 PAYMENT
B. This price shall be full compensation for furnishing all labor, materials, tools,
equipment, fees, supplies, supervision, and incidentals within the limits of highway-
rail grade crossing work in accordance with SCRRA Engineering Standards
ES4201 necessary for any highway-rail grade crossings described by the Contract
Documents.
END OF SECTION 34 71 50
TRACKWORK
PART 1 - GENERAL
1.01 SUMMARY
A. This Section consists of the Contractor, unless otherwise indicated, furnishing all
labor, materials, equipment, tools, and incidentals necessary to remove, repair,
modify, rehabilitate, or construct trackwork, turnouts, crossings and crossovers.
1. Work includes ballast, walkways, ties, rail, fastening systems, other track
material (OTM), turnouts and other special trackwork.
B. Related Specification Sections include but are not necessarily limited to:
6. Section 34 11 16 - Ballast.
1.02 REFERENCES
B. FRA: 49 CFR Part 213, Track Safety Standards, most current and addenda,
Federal Railroad Administration.
1.03 SUBMITTALS
2. Shop Drawings:
a. Submit Shop Drawing and product data for trackwork items not
specifically defined by engineering standards.
10. Procedure: Submit procedure and field welding material technical data for
field welding rail.
13. Procedure: Plan for the coordinating and scheduling of a signal track
support crew to protect and maintain the operating signal system.
A. Quality Assurance:
A. Ties shall be lifted and supported during storage, transportation, and placing in
such a manner as to prevent damage.
B. Rail shall be unloaded and distributed in a manner that prevents damage to ties,
rails and structures. Do not bump or strike rail.
PART 2 - PRODUCTS
1. Track surfacing equipment must have all tamping tools in good repair and
working order.
C. Equipment shall be compatible with and shall be operated within the clearances
indicated in SCRRA Engineering Standards.
E. All construction loads borne by equipment shall be applied between gage lines of
running rails on each track unless approved by the Engineer.
G. Ballast Stabilizer for compacting ballast in crib and shoulder areas shall be
approved by the Engineer.
B. Track gages, track levels, and other tools shall conform to the AREMA Volume 1,
Chapter 5, Part 6, "Specifications and Plans for Tools."
1. Substitution of tools other than AREMA standard will be permitted only with
approval of the Engineer.
E. Track levels and gages shall be checked for accuracy at the start of every work
shift and at any time the tool is dropped or struck.
2.03 SUB-BALLAST
2.05 TIES
1. Cross ties and switch ties shall be of the lengths detailed on the Contract
Documents or the designated SCRRA Engineering Standard.
2.06 RAIL
2.08 TURNOUTS
B. Turnouts shall be as indicated on the Contract Plans, fabricated with all new
Material, and in conformance with SCRRA Engineering Standards.
2.10 LUBRICANTS
PART 3 - EXECUTION
2. Track must have ballast section full to top of ties, have joints fully bolted or
welded, have all anchors or elastic fasteners applied, and the rail shall be
fully de-stressed.
B. Bottom of rail, fastener assemblies, and all bearing surfaces shall be broom
cleaned before laying rail.
C. The low rail (inside rail of curves) on all superelevated tracks shall be designated
as the profile rail.
D. Install track, OTM, turnouts, derails and road crossings in accordance with the
Contract Plans, SCRRA Engineering Standards, SCRRA Track Maintenance
Manual and California Public Utilities Commission requirements.
3.02 SUB-BALLAST
1. Use of wood ties or concrete cross ties shall be designated on the Contract
Plans for use in track construction as indicated.
1. Place wood Crossties on 19-1/2” centers for mainline track, except through
grade crossings.
2. Space cross ties for grade crossings in accordance with the applicable
SCRRA Engineering Standard.
4. Obtain approval for any deviation in crossties spacing from the Engineer
prior to Installation of spikes or hold down devices.
5. Place wood ties with heartwood face down and square to the rail, except
as otherwise shown on the Contract Plans.
7. Do not drive nails or spikes other than those called for into wood ties.
D. Place concrete Crossties as shown in the Contract Plans and SCRRA Engineering
Standards.
E. Transition ties shall be installed where concrete ties abut timber track in
accordance with SCRRA Track Maintenance Manual and SCRRA ES2351-03.
F. Bridge decks with less than 12 inches of ballast under the tie will require use of a
concrete tie with embedded neoprene pad (SCRRA ES2403 or ES2407). When
calculating the depth of ballast under the tie, include any HMA underlayment as a
part of the ballast depth for determining the requirement for use of the concrete tie
with embedded neoprene pad. Bridge decks with 12 inches or more of ballast
under the ties will utilize standard concrete ties (SCRRA ES2402 or ES2406).
A. Plates shall be positioned so that the rail will cant inward towards track centerline
and the plate shall be centered on tie and applied as to obtain full proper bearing
on both the tie and rail.
B. Resilient fastening system shall be used for all new construction. Standard
fastening system shall be used only for maintenance of the existing track
constructed with cut spikes.
D. Spiking for standard cut spike fastening systems shall be performed using new cut
spikes unless otherwise indicated in the Contract Plans and as follows:
2. Spikes shall be started vertically, square to the base of rail and driven
straight.
3. Shank of rail-holding spikes shall have full bearing against base of rail.
5. Bent spikes shall be removed and replaced with a new spike as approved
by the Engineer.
E. Holes for the screw spikes shall be pre-drilled and applied perpendicular to the
plane of the base of the tie plate.
1. Sufficient torque shall be applied to bring the bearing face of the screw
spike into flush bearing contact with the tie plate so no gap exists.
2. Not more than 2 each cut spikes per plate may be used to hold the elastic
fastening system plates until the screw spikes are installed.
A. Rail anchors shall be installed per SCRRA ES2351-01 through ES2351-04 and
SCRRA Track Maintenance Manual, as applicable.
1. In applying rail anchors, they shall be set with full bearing against the side
of the tie.
A. Installation, laying, raising, lining, tamping and dressing of track over ballast shall
be performed as follows:
1. Ballast shall only be installed over sub-ballast, which has been prepared in
accordance with Section 34 11 27 and approved by the Engineer.
2. Place base ballast in lifts not more than 6 inches in thickness before
compaction.
a. Layers shall extend beyond the edge of the ties as shown on the
Contract Plans before compaction.
a. Each lift of ballast within the initial layer shall be uniformly spread
and compacted with not less than four passes of either a self-
propelled, pneumatic-tired roller or vibratory compactor.
9. The track shall be raised, aligned and tamped to within the specified
tolerances.
10. Ballast shall be thoroughly tamped within a space from 15 inches inside
either rail to the ends of the ties.
b. Tamping is not permitted at the center of the tie except within limits
of turnouts and crossings where the center of the ties shall be
tamped unless prevented by trackwork components.
12. Two tamping tools shall always be used opposite each other on the same
tie.
16. Where new track joins existing track, the existing track shall be surfaced
for a minimum distance of 500 feet on mainline or siding tracks, or 200 feet
on industrial tracks, from the point of connection.
17. After the track has been raised to its final elevation and super-elevation,
ballast consolidation of all tracks shall be performed before the track is
placed in service.
18. When raising track, a spot board or other approved device shall be used to
maintain grade, and a level shall be used to keep track to proper cross-
level.
19. In addition to the other requirements specified herein, all newly constructed
mainline and mainline siding tracks, upon completion of final surfacing
operations, shall be mechanically stabilized using a Ballast Stabilizer as
specified in Division 01.
A. Installation of frog plates, switch plates, and plates under the closure rails shall
conform to SCRRA Engineering Standards and AREMA trackwork standards.
B. Following the installation of turnouts on the initial layer of ballast, the turnouts shall
be lifted, aligned and supported prior to placement of final ballast.
1. The turnout shall then be raised and the ballast tamped under both sides
of each tie for the full length of the tie.
2. Tamp ballast thoroughly throughout the length of all ties in the turnout or
other special trackwork.
3. Final top of ballast shall conform to the ballast section as indicated except
in cribs wherein switch operating rods, locking rods or connecting rods are
located and between point of switch and heel of switch where the crib
ballast shall be 3 IN below the base of the rail.
D. When installing the various components of the turnout, particular attention shall be
given to the following:
2. Verify that bolts, nuts, cotter pins, and other fastenings are in place, in good
condition, and properly tightened.
3. Verify that switch points are properly aligned and fit tightly against rail when
switch is thrown in either position.
4. Verify that connecting rod and switch rod bolts are equipped with cotter
pins properly applied.
6. Examine the rod and fastenings that connect the switch point to the switch
stand to see that they are in place and in good condition.
F. Switch stands shall be so installed as to hold the switch point tightly against the
stock rail when stand is in normal position, per the manufacturer’s instructions.
1. Switch rods shall be adjusted to hold the opposite point tightly against the
rail when stand is in reverse position.
2. Switch stands, for both switches and derails, shall be mounted on two
headblock ties. Headblock ties shall conform to the requirements of
SCRRA ES8740.
G. Switch stands shall be kept securely fastened to the head block ties, use approved
screw spike fasteners.
1. The head block ties shall be set square with the track and kept firmly
tamped.
2. Correct any walkway deficiencies adjacent to the head block ties that would
impact SCRRA employee or operating personnel access to the operating
levers or controls for the switch stand.
H. Switch stand target colors shall conform to SCRRA ES2610 for Derail Switch
Target or to SCRRA ES2703 for Standard Switch Target.
1. No switch point shall be installed in the main track unless it has the proper
signal system point protection in place and tested.
3. All rail bonding and fouling circuit protection must be intact at all times on
all signaled switches.
3.10 DRILLING
A. Rail ends for bolted joints shall be drilled in accordance with SCRRA Track
Maintenance Manual, 5.2.3.
C. Holes shall be located with the proper size rail-drilling template and marked with a
center punch prior to drilling.
A. Rail shall be cut with rail saw to a tolerance of 1/32” from square.
A. At all rail end locations not eliminated by field welding, rail ends shall be field end
hardened in accordance with the AREMA Manual, Volume 1, Chapter 4, Section
2.1.17.1, “Supplementary Requirements” including all insulated joints.
B. ANCHORING CWR
C. HEATING RAIL
Heating rail shall be as per procedures shown in Section 9.6.3.5 of SCRRA Track
Maintenance Manual.
D. THERMAL ADJUSTMENT
E. RECORDKEEPING
2. Deviation from established gage and cross- level shall not exceed 1/8”, and
profile grade and horizontal alignment variation shall not exceed 1/8”
measured at the center of a 62 feet chord.
B. Provide vertical and horizontal control stakes every 50 feet on curves and every
100 feet on tangents.
C. Tangent track shall be level and superelevation and runoff spirals shall be provided
on all curves in conformance with SCRRA ES2201 through ES2204 unless
otherwise indicated in the Contract Plans.
D. Contractor must not cut rail strings except as required to fit rail to turnouts,
crossings or limits of work.
A. Rail welding shall be in accordance with the approved procedure and Section 34
72 30, Field Welding Rail.
3.16 WALKWAYS
A. CPUC walkways shall be provided within track work limits in accordance with the
Contract Plans, SCRRA ES2105 and ES2109, SCRRA Track Maintenance
Manual, and CPUC General Order No. 118.
A. Each insulated joint installed by the Contractor must be tested with an insulated
joint tester, either the Harmon 1501A1JC or equal approved by the Engineer.
1. Test shall measure no less than 100 ohms across the joint.
2. Test results shall be uniquely identified with a specific joint and submitted
to the Engineer in Compliance Record.
B. The rail ends at each insulated joint shall be beveled and hardened in accordance
with the manufacturer’s procedures as approved by the Engineer.
1. Contractor must comply with rail end hardening and beveling requirements
specified in this Section.
1. For all bridge spans where exposed structural steel is present above the
top of rail.
3. Where entire structure is over 800 feet in length and at least one span
crosses over a waterway that normally contains water which is at least 15
feet deep.
B. Inner Guard Rails shall extend 50 feet beyond the span or spans to be protected
as required above. SCRRA ES2302 and ES2304 indicate details for construction
of Inner Guard Rails. Inner Guard Rails require use of special Concrete Ties as
shown in ES2406 and ES2407.
4.01 MEASUREMENT
A. Trackwork will be measured by the unit or fraction thereof furnished and completed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
schedule of values, as applicable, as derived from the Plans will be used as the
basis for this measurement.
B. All material, work and services included in Sections 34 11 10, Continuous Welded
Rail (CWR); 34 11 15, Other Track Materials (OTM); 34 11 23, Special Trackwork;
34 11 16, Ballast; 34 11 27, Sub-Ballast and Aggregate Base; 34 11 33, Concrete
Railroad Ties; 34 11 34, Wood Railroad Ties; 34 11 36, Elastic Rail Fasteners; 34
11 40, Precast Concrete Grade Crossing Panels; and 34 72 30, Field Welding Rail
will be included in this Section and are considered incidental to work under this
Section and will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer.
4.02 PAYMENT
2. All work must be complete prior to payment being made, including but not
limited to welding, distressing, final surfacing, and completion of punch list
items related to track work.
END OF SECTION 34 72 00
PART 1 - GENERAL
1.01 SUMMARY
B. Section 34 72 00 will govern track construction work associated with this Section.
C. Related Specification Sections include but are not necessarily limited to:
6. Section 34 11 26 - Ballast.
1.02 REFERENCES
A. Full compliance with applicable rules, regulations, and General Orders of California
Public Utilities Commission is required. Representatives of that State agency will
inspect railroad related work for compliance with General Orders.
D. FRA:
1. 49 CFR Part 213, Track Safety Standards, most current and addenda,
Federal Railroad Administration
2. 49 CFR Part 214, Railroad Workplace Safety, most current and addenda,
Federal Railroad Administration
1. Engineering Standards.
A. Perform all track shifting, relocation and resurfacing work as shown on the Contract
Plans, and in accordance with this Section.
4. Track shifting shall include all work to shift existing track more than 1 foot
and less than 10 feet and providing Ballast per Section 34 11 26,
resurfacing and regulating track in its new location.
5. Track relocation shall include all work to relocate existing track a distance
greater than 10 feet including installation of Ballast per Section 34 11 16,
resurfacing and regulating track in its new location.
7. Rough and final surfacing of the entire track section shall be performed as
required to provide minimal profile smoothing and adjustment. This
surfacing may include providing and placing Ballast per Section 34 11 16,
tamping, stabilizing and regulating ballast.
B. The Contractor, as with any Work within the SCRRA Right of Way, must submit a
SSWP for each track segment that requires shifting, relocating, or resurfacing the
active track in accordance with Division 01, Coordination with SCRRA.
1.04 SUBMITTALS
A. Quality Assurance:
B. The Contractor must coordinate all phases of the Work to prevent undue
interference with the SCRRA daily operations, or with other phases of the Project,
whether performed by SCRRA forces or another contractor’s forces.
PART 2 - PRODUCTS
2.01 GENERAL
D. Material must be new, except as otherwise indicated herein, and meet the
requirements stated herein and of the AREMA and SCRRA Standards.
PART 3 - EXECUTION
3.01 GENERAL
A. Contractor personnel and equipment shall meet the requirements set forth in
Division 01.
B. Contractor must exercise care in his progression of work under this Contract to
avoid and prevent damage to the track being shifted, relocated, or resurfaced,
adjacent tracks, and structures and facilities, such as existing pavements,
pavement bases, drainage structures, light poles, fire hydrants, signal facilities
(track wires, bootlegs, signal masts, guy wires, signals, cables, conduits) utilities,
signage and buildings. Contractor must repair or replace damaged structures or
facilities to satisfaction of the owner at no cost to SCRRA, except that SCRRA will
repair and test signal facilities at the Contractor’s sole expense. The Contractor
must be responsible to coordinate his work with SCRRA to arrange for the timely
and orderly removals or relocations of this signal equipment and facilities. Failure
of the Contractor to provide reasonable and adequate coordination for timely
removal and relocation of signal facilities will not allow for an extension of time or
provide grounds for extra cost to SCRRA.
C. Contractor must perform Work under this Section in accordance with these
Specifications and consistent with track resurfacing standard industry practice.
D. Contractor must periodically review the supply of materials, labor and equipment
to ensure a uniform flow of work. Contractor must keep the Engineer informed
regarding material shortages or developing problems that require corrective action.
E. Shifted, relocated, and resurfaced track shall meet the following tolerances as well
as the standards for FRA 49CFR213 class 5 track.
F. Elastic clips, rail anchors, and spikes shall be loosened prior to shifting track to
prevent skewed ties. Rail, fasteners, or crossties damaged during track shifting
must be replaced by the Contractor at Contractor’s expense. Rail anchors are not
to be slid longitudinally along the base of the rail. They must be removed prior to
shifting track and reapplied in the correct location after track is shifted to its final
location.
A. Contractor must perform shifting and resurfacing within the stated project limit
station areas as specified to bring the line and surface into compliance within the
track geometry tolerances specified.
B. Contractor must resurface the track to zero crosslevel on tangent track and to the
proper crosslevel elevation, with spirals, for the curves as shown on Contract
Documents.
C. Ballast shall be spread and track raised in a series of lifts. No single lift shall be
higher than 2 inches except in crossings and turnouts. In raising the track, jacks
or equipment shall be regulated to avoid bending of angle bars or straining of joints.
When jacks are used they shall be simultaneously used and properly spaced at
not more than quarter points of the rail to avoid breaks or bends in the rail when
the track is raised. Both rails shall be raised simultaneously and to proper
crosslevel by utilizing automatic tampers or standard track level boards with each
set of track raising jacks. Each tie shall be tamped from 15 inches inside the rail
to the end of the tie. Tamping shall not be permitted at the middle of a tie. Both
ends of a tie shall be tamped simultaneously and tamping inside and outside the
rail shall be done at the same time.
D. Ties that become loose during track raise shall be placed in proper position, tie-
plates properly placed, holes plugged with “Tight Spike” or approved tie plugs and
spiked before tamping. During each track raise, track shall be uniformly tamped.
E. After ballasting is completed and the track is resurfaced and lined, according to the
tolerances, ballast shall be mechanically stabilized using a dynamic track stabilizer
and ballast shall be trimmed neatly and surplus material shall be spread evenly
along the ballast shoulder.
G. Contractor must perform the necessary operations to ensure that all ties are at
right angles to the track as practical with standard railroad procedures. Cribs
between ties shall be fully ballasted and dressed.
H. Contractor must perform two tamping squeezes per tie up to two (2) inches of raise
with one additional insertion and squeeze for each additional one (1) inch of raise.
Joint ties shall be given one additional squeeze more than other ties. The
Contractor must not cause a center-bound track condition.
I. In locations where squeeze tampers cannot fill and compact ballast, such as but
not limited at frogs, guard rails, switch portions of turnouts and headblocks,
mechanically tamp with approved hand-held air tools or other power tamping tools.
Hand tamping shall be done simultaneously from both sides of the tie.
J. On curves, the high rail shall be used as the line rail and the low rail shall be used
as the grade rail.
K. When surfacing turnouts, the straight side of the turnout shall be used as the line
rail.
L. After ballast regulating in turnouts, cribs for switch points, switch rods, and
guardrails shall be pocketed 3 inches and cleared of ballast to permit free operation
of the switch and signal rods.
M. After the ballast is regulated, dressed and consolidated using a track stabilizer,
Contractor must ensure that track bolts and rail anchors, or elastic track fasteners
are tight and in proper alignment.
N. For track resurfacing the total track raise will be the minimum amount necessary
to smooth the track profile. It shall be the responsibility of the Contractor to provide
smooth transitions that meet the required surfacing tolerances as listed above to
grade crossings and turnouts, using the ballast stockpiled near the worksite. In
addition, the Contractor must maintain vertical overhead clearances under
structures by limiting the amount of track raise. Adjustment of turnouts and
connecting tracks to match profile and alignment adjustments on adjacent track
must be provided by Contractor at no additional expense.
O. Any temporary surfacing runoffs made to accommodate interim rail traffic prior to
completion of track surfacing must meet FRA Track Class 5 Standards.
3.03 WALKWAYS
4.01 MEASUREMENT
A. Track shifting will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement. Surfacing, stabilizing and de-stressing of
shifted track is incidental to this item and will not be measured.
B. Track Relocation will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement. Surfacing, stabilizing and de-stressing of
shifted track is incidental to this item and will not be measured.
C. Track Surfacing will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement. Surfacing, stabilizing and de-stressing of
shifted track is incidental to this item and will not be measured.
D. All material, work and services included in Sections Other Track Materials (OTM);
34 11 16, Ballast; 34 11 17, and Sub-Ballast and Aggregate Base; will be included
in this Section and are considered incidental to work under this Section and will be
measured by the unit or fraction thereof furnished and completed in accordance
with the Contract Documents and as measured by the Engineer.
E. Work of shifting, relocating and resurfacing existing track will include furnishing all
labor, materials, tools, equipment, supplies, supervision, installation of Contractor
provided ballast and walkway rock, laser aligned tamping, resurfacing, regulating,
stabilizing and de-stressing to SCRRA standard cross section and any other
incidental work necessary for shifting, relocating and resurfacing existing track as
described in the Contract Documents.
4.02 PAYMENT
END OF SECTION 34 72 20
PART 1 - GENERAL
1.01 SUMMARY
B. The Contractor must make assessment as to the number of welds, including the
method of welding for each weld, to be performed under this Contract.
C. Related Specification Sections include but are not necessarily limited to:
3. Section 34 72 00 - Trackwork.
1.02 REFERENCES
C. FRA: 49 CFR Part 213, Track Safety Standards, most current and addenda,
Federal Railroad Administration.
1.03 SUBMITTALS
d. Method used for cutting and cleaning to parent metal of the rail
ends.
g. Method used for grinding and contouring rail removing weld upset
following the welding process.
e. Method used for preheating the rail ends including time and
temperature.
PART 2 - PRODUCTS
2.01 MATERIALS
A. For electric flash butt welding, materials, equipment and process shall be as
provided by Holland L.P. or other approved equivalent.
PART 3 - EXECUTION
3.01 GENERAL
A. Electric flash butt welding, methods and procedures shall comply with the AREMA
Manual, Volume 1, Chapter 4, Section 2.3, Specifications for the Quality
Assurance of Electric-Flash Butt Welding of Rail.
B. Thermite welding, methods and procedures shall comply with the AREMA Manual,
Volume 1, Chapter 4, Section 2.5 Specification for the Quality Assurance of
Thermite Welding Rail, with the welding kit manufacturer's recommendations, and
as specified herein.
C. Rail ends for thermite welding shall be prepared in accordance with the
recommendations of the welding kit manufacturer.
D. For thermite welding, the rail ends shall be preheated prior to welding to a sufficient
temperature and for sufficient time to ensure full fusion of the weld metal to the rail
ends without cracking of the rail or weld.
2. Within 6 inches of a Cadweld or copper bond wire (If this type of bond
exists, remove any presence of copper by grinding. The rail ends must be
inspected and cleaned after grinding is complete).
5. On both ends of a rail plug simultaneously unless the rail is 15 feet or longer
on tangent track and 24 feet long or longer on curved track.
I. Thermite welds shall be located in cribs between ties. The edge of the weld must
be no closer than 3 inches from the edge of the nearest tie.
J. Electric Flash Butt welds with the base of the rail smoothly ground may be located
anywhere.
4. Weather, air and rail temperature for destress welds (welds made to close
up rail).
5. Track condition, anchorage and rail stress for destress welds, or the word
“FREE” for free end welds.
B. Rail shall be permanently marked on the web of rail in legible characters at least
1-1/2 inches high at each field weld with the above information in accordance with
Section 5.16, Marking Thermite Welds of the SCRRA Track Maintenance Manual.
If an existing destress weld is located within 400 feet of a new destress weld, lines
shall be marked through the old weld’s marking and an arrow marked indicating
the direction towards the new destressed weld.
A. A straight edge 36 inches in length, applied to finished welded joint area shall be
used to check for the following maximum variations (measurements shall be taken
with a 6 inches steel taper gauge):
1. Rail Head:
c. Vertical Crown: 0.40 inches ofr Thermite and 0.60 inches for In-
Track.
2. Rail Base:
A. Sharp edges and burrs shall be removed, including chimneys from thermite welds.
Top of base of rail shall be ground smooth at chimney locations.
B. Weld joints shall be smooth on top and sides of head and straight in line. No over
grinding is permitted. Web of rail at thermite welds shall not be ground. All mold
residues shall be removed from the weld area and properly discarded.
C. Finishing of welds shall be sufficient to allow testing using the Ultrasonic test
method as described below. Welds rejected because of insufficient or
unsatisfactory finishing of welds shall be refinished, repaired, or replaced at the
Contractor’s expense until the weld meets the testing criteria.
A. Fabricate CWR strings so that the branding of all individual rail section appears on
the field side of installed track.
B. Rail welds must be tested by the Contractor through the use of an SCRRA
approved testing agency using the Ultrasonic testing method in accordance with
ASTM E164 Technique 4 for use with thick weldments.
C. Each completed weld shall have full penetration and complete fusion and be
entirely free of cracks. Total area of internal defects such as porosity and slag
inclusions shall not exceed 0.060 sq in and the largest single porosity or slag defect
permitted shall not exceed 1/8 inches dia.
2. Pit holes that show in web and base of weld after finish grinding. Pit holes
in head not exceeding 1/4 inches in depth may, if approved by the
Engineer, be repaired by gas welding.
3. Over-grinding of weld.
E. Welded joints not meeting these Specifications and tolerances will be replaced at
no additional cost to the Authority. The defective weld shall be cut out, and a new
section of rail of a length described in Article 3.06 herein shall be inserted, welded
into place as described in this Section, and retested.
3.06 CUTTING IN SHORT SECTION RAIL AND THERMITE WELDING THE ENDS
A. A short section of rail shall be cut in the CWR, when required by the Engineer, for
the following reasons:
3. To destress rail.
B. The short section of rail to be cut in shall be at least 19 feet-6 inches long on
tangents and curves less than 2 degrees; and 30 feet long on curves 2 degrees or
greater and rail to be cut in shall be of the same weight, size, section, and class of
rail being replaced or joined.
C. Before cutting out rail in CWR and inadvertently losing all thermal control, prevent
remaining CWR from further movement by applying full box anchors for at least
200 feet each way from the proposed cut. After cutting CWR, a rail expander/puller
or other means shall be used to prevent rail movement until a weld or temporary
joint is installed.
D. The ends of the short rail section and the CWR shall be saw cut.
G. When repairing a defective rail or weld, the new rail shall be the same length as
rail being replaced, or as required to achieve thermal adjustment.
Work of this Section is considered incidental to work under other payment items and no
separate measurement and payment will be made to the Contractor for Work of this
Section. Work of this section shall include furnishing all labor, materials, tools, equipment,
supplies, supervision, and incidentals necessary for Field Welding Rail as described by
the Contract Documents.
END OF SECTION 34 72 30
PART 1 - GENERAL
A. Work Included: The work of this Section includes the furnishing and installation of
a Track Collector Pan System at locations shown on the Contract Drawings.
1.02 CERTIFICATION
A. Except as otherwise specified, the Contractor shall submit for each of the materials
furnished, certification by each manufacturer or producer that the material is in
compliance with these specifications.
1.03 SUBMITTALS
PART 2 - PRODUCTS
2.02 MATERIALS
A. The Track Collector Pan System shall be constructed from a series of pre-formed
HDPE panels. The total assembly of panels shall form a 12-foot wide (cross track
direction) and 90 feet long (down track direction) drip pan. Each 30-foot length of
pan assembly shall consist of three panels: two are field side panels, with one gage
panel between rails. Refer to diagrams at the end of this section.
B. Physical Specifications:
A. Collector pans shall be fabricated from molds that provide a continuous, monolithic
pan section.
PART 3 - EXECUTION
A. Panels shall be stored on level, dry ground evenly supported every four feet using
wood shoring.
3.02 INSTALLATION
A. Unless otherwise specified, collector pans shall be installed in accordance with the
manufacturer's installation instructions.
4.01 MEASUREMENT
A. Track Collector Pan System work shall be measured by the unit or fraction thereof
furnished and placed in accordance with the Contract Documents and as
measured by the Engineer. The quantities contained on the Schedule of Quantities
and Prices, or approved Schedule of Values as derived from the plans, will be used
as the basis for this measurement.
4.02 PAYMENT
A. Track Collector Pan System work completed in accordance with the Contract
Documents will be paid for at the Contract Unit price, as listed in the Schedule of
Quantities and Prices. This price shall be full compensation for furnishing all labor,
materials, and equipment to install track collector pans as recommended by the
manufacturer including but not limited to center pans, side pans, end pans, and all
other work necessary and incidental to construction of the track collector pan
system.
END OF SECTION 34 72 40
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
b. Slope riprap.
3. Section 31 20 00 - Earthwork.
1.02 REFERENCES
A. Reference Standards:
1.03 SUBMITTALS
A. Shop Drawings:
3. Certifications.
4. Test reports.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Stone:
1. Durable broken quarry run stone Apparent Specific Gravity minimum 2.50
ASTM C127.
6. Breadth and thickness of any stone: Not less than one-third of its length.
7. Ensure that dirt and fines accumulated from interledge layers or from
blasting or handling operation is less than 2 percent by weight.
a. Riprap shall be angular (not rounded), each rock having its greatest
dimension not greater than 3 times its least dimension. Elongated
rocks shall be hand adjusted to a vertical verses horizontal position.
d. Riprap and grout colors may be limited by local flood control districts
or other regulatory entities. Contractor is responsible for
ascertaining and complying with any such requirements.
B. Geotextile:
C. Sand Cushion:
D. Grout:
1. Concrete for the grout shall be an approved batch meeting the following
requirements:
E. Synthetic Fiber-Reinforcing:
2. Physical characteristics:
d. Acceptable manufacturers:
1) Fibermesh.
C. Source Tests:
2. In event suitable test reports or a service record that is satisfactory are not
available, as in case of newly operated sources, subject material to tests
necessary to determine its acceptability for use.
a. Specific gravity.
a. Specific gravity.
2. Control tests:
PART 3 - EXECUTION
3.01 PREPARATION
B. Bring areas that are below allowable minus tolerance limit to grade by filling with
material similar to adjacent material.
D. Do not place any stone material on prepared base prior to inspection by Engineer.
3.02 PLACING
A. Ungrouted Riprap:
9. Ensure a final tolerance of within 3 inches from indicated slope and grade
lines.
B. Grouted Riprap:
1. The Contractor must notify the SCRRA a minimum of two working days of
his intent to perform any grouting activities prior to placement of any grout
to allow scheduling of inspection activities. Grout operation shall not
proceed without the approval of the SCRRA.
2. Contractor must clean with a water blast operation faces and edges of any
existing to-remain structural elements such as wingwalls or abutments to
which the grouted riprap will come in contact.
5. Contractor must keep riprap, boulders and concrete walls that are to
receive grout wet at all times prior to injecting grout.
7. The voids at the surface of the riprap will not be grouted. The depth of
grout measured from the prepared subgrade bed shall be 18 inches.
Operator shall be able to stop the flow of grout when required, and will
place grout in the voids and not on the surface of the riprap.
8. A "pencil" vibrator will be used to make sure all voids are filled between and
under the riprap. The intent is to fill all voids from the subgrade level around
the riprap for a minimum depth of 18 inches. In all cases, grout must
penetrate to the subgrade of the riprap. The pencil vibrator may be used to
smooth the appearance of the surface, but the Contractor must use a wood
float to smooth and grade the grout to drain. When placing grout, it shall
be placed between the riprap and against earth, rock, or concrete
excavated sidewalls.
9. Contractor must clean and wash any spillage before the grout sets. The
visible surfaces of the riprap will be free of grout to provide a clean natural
appearance.
4.01 MEASUREMENT
A. Ungrouted Riprap:
B. Grouted Riprap:
4.02 PAYMENT
A. Ungrouted Riprap:
2. The contract price paid unit of ungrouted riprap for each classification shall
include compensation to the Contractor for furnishing riprap, all labor,
materials, equipment and any other incidentals to place riprap complete-in-
place, including haul from the suppliers source, necessary stockpiling at
the job site, reloading for placement, placement, overestimates of
salvageable boulders, disposing of any rejected riprap, excavation and
removal of material, over-excavation for construction, backfilling, and any
other miscellaneous items and work shown or reasonable implied on the
Plans, in the Specifications for this work, and elsewhere in the Contract
Documents.
3. Geotextile and sand base and other associated materials and incidentals
and installation thereof shall be considered part of the riprap and full
compensation therefore shall be considered as included in the contract unit
price paid for ungrouted riprap.
B. Grouted Riprap:
2. The contract price paid per unit of grouted riprap for each classification
shall include compensation to the Contractor for furnishing riprap, all labor,
materials, equipment and any other incidentals to place riprap complete-in-
place, including haul from the suppliers source, necessary stockpiling at
the job site, reloading for placement, placement, overestimates of
salvageable boulders, disposing of any rejected riprap, excavation and
removal of material, over-excavation for construction, backfilling, and any
other miscellaneous items and work shown or reasonable implied on the
Plans, in the Specifications for this work, and elsewhere in the Contract
Documents.
3. Geotextile and sand base and other associated materials and incidentals
and installation thereof shall be considered part of the riprap and full
compensation therefore shall be considered as included in the contract unit
price paid for grouted riprap.
END OF SECTION 34 80 11
PILING
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Description:
1. Piles:
C. Related Specifications Sections include but are not necessarily limited to:
5. Section 31 20 00 - Earthwork.
1.02 REFERENCES
2. A252, Standard Specification for Welded and Seamless Steel Pipe Piles.
1.03 DEFINITIONS
1.04 SUBMITTALS
A. Shop Drawings:
B. The Contractor shall provide to the Engineer a description of all pile driving
equipment to be employed in the work, prior to commencement of pile installation.
This shall include details including weights of pile hammer, power plant, leads, pile
cushion, cap block and helmet.
C. The Contractor shall visit the site and review the Geotechnical Report and test
borings prior to selecting the pile driving hammer.
E. The Contractor shall perform and submit the results of wave equation analysis for
proposed installation equipment and piling material.
3. The results of the wave equation analysis shall demonstrate that the pile
stresses are higher at the top of the pile compared to the tip, that the piles
can achieve the required penetration into the hard strata without damaging
the pile, and that an excessive number of blows per foot are not needed to
achieve the required penetration and capacities.
4. The recommended pile driving criteria for the driving of piles (chart with
bearing as a function of ram fall and blow count) shall be submitted for
review.
G. Pile reports shall be submitted by the Contractor to the Engineer within 3 days of
completion of driving. The pile record shall be completed per Article 3.11 of these
specifications.
A. Qualifications:
A. Do not begin pile installation until the earthwork in the area where piles are to be
driven has been completed, to the extent possible, as shown in the Contract
Documents.
B. Jetting or predrilling of piling will not be permitted unless shown on the plans.
C. The use of followers shall only be permissible if driving pile through the existing
bridge deck.
1. If followers are used, their use shall be incorporated into the Contractor’s
wave equation analysis.
D. All work shall comply with these Specifications, the AREMA Manual for Railway
Engineering, and the SCRAA standards.
PART 2 - PRODUCTS
A. Submit pile manufacturer information to the Engineer for review and approval prior
to ordering and fabricating material.
2.02 MATERIALS
A. Timber Piles:
1. Timber piles shall be in accordance with Chapter 7, Part I, Article 1.9 of the
AREMA Manual for Railway Engineering for first-class piles with a
minimum tip circumference of 25 inches.
3. The method of storing and handling timber piles shall be such as to avoid
damage to the piles. Piles shall be handled with hemp or synthetic fiber
slings or wire rope encased in rubber hose, taking care to avoid dropping,
bruising, breaking or penetrating the outer fibers.
B. Steel Piles:
1. Steel Bearing Piles: Steel bearing piles shall be of the section shown on
the plans and shall be structural steel, containing no less than 0.2 percent
copper, conforming to ASTM A572, Grade 50, or ASTM A588. Piles shall
not be painted before driving.
2. Steel Sheet Piles: Steel sheet piles shall be of the section and length
shown on the plans and shall conform to ASTM A328 unless otherwise
shown on the plans.
1. Steel pipe piles shall be of the outside diameter and wall thickness shown
on the plans and shall conform to ASTM A252, Grade 2 or 3 for piles less
than 14 inches in diameter and shall conform to ASTM A252 Grade 3 for
piles 14 inches and greater in diameter unless other material is specified
on the plans. Piles shall have an end treatment as shown on the plans.
Piles shall not be painted before driving.
2. All concrete materials and reinforcing steel and their preparation and
placement, used in filling steel pipe piles, shall be in accordance with
Section 03 31 00 and Section 03 21 00. All concrete shall have a minimum
compressive strength equal to that shown on the plans.
A. Precast:
1. Precast concrete piles shall be of the type, size and length shown on the
plans.
2. All concrete materials and steel reinforcing and their preparation and
placement shall be in accordance with Section 03 31 00 and Section 03 21
00. All concrete shall have a minimum compressive strength equal to that
shown on the plans.
B. Prestressed:
1. Prestressed concrete piles shall meet the requirements, and shall be of the
type, size, and length shown on the plans, manufactured in accordance
with Section 03 31 00 and Section 03 21 00.
1. The method of storing and handling piles shall be such as to minimize the
danger of fracture by impact or undue bending stresses. Unless otherwise
A. The driven compressive capacity of piles shall be equal or greater than the
allowable working compressive load capacity, if provided and as stated on the
Contract Plans.
2.05 FABRICATION
A. Ends of piles to be machine cut and square making an angle of 90 degrees with
the longitudinal axis of the pile.
B. Tolerances:
PART 3 - EXECUTION
3.01 INSPECTION
A. Complete necessary excavation and furnish lines and levels as required to install
piles at their indicated locations.
A. Driving Equipment:
3. Pile drivers shall be equipped with leads which are constructed in such a
manner as to afford freedom of movement of the hammer and to provide
adequate support of the pile during driving. The longitudinal axis of the
leads and hammer shall coincide with the longitudinal axis of the pile.
Except where piles are driven through water, the leads shall be long
enough so that a follower will not be necessary. Where a follower is
required for driving piles underwater, one pile in each group of ten shall be
long enough to permit driving without a follower. This pile shall be used as
a test pile for proper correlation of the follower-driven piles bearing
capacity. This pile shall be paid for as a permanent pile and not as a "test
pile."
B. Driving Tolerances:
1. Piles for bent construction shall be driven with a degree of accuracy that
will permit framing into bents with a minimum of pulling or jacking. Under
ordinary conditions, pipe piles, after driving and before framing, shall not
vary from the vertical or from the required batter by more than 1/8 inches
per foot of pile above finished ground, except that under ordinary
conditions, the maximum deviation of the top of the pile from the plan
location shall be 2 inches in the direction of the structure centerline and 4
inches in the direction along the centerline of the bend.
2. Foundation piles shall be driven to the vertical or batter line shown on the
plans and the top of the completed pile shall not be more than 4 inches in
any direction from the position shown on the plans. The center of gravity
of the completed pile group shall not vary by more than 3 inches from the
center of gravity determined from plan location.
1. A steel driving head suitable for the type and size of piles being driven shall
be used. Steel bearing piles and steel sheet piles shall be driven with a
driving head compatible with the specific pile shape driven.
2. For concrete piles, a cushion block shall be provided between the driving
head and the top of the pile. Wood cushion blocks, wire rope mat, belting,
or other suitable material shall be used, subject to the approval of the
Engineer, to prevent damage to the pile. Cushion blocks shall be changed
as necessary to maintain an effective cushion.
E. Pile Penetration:
2. When test piles are required by the contract, the pile lengths and
penetration required will be established by the Engineer on the basis of the
test pile data. These lengths and elevation of pile tips shall supersede
requirements shown on the plans.
F. Pilot Holes:
1. If piles cannot be driven to the required penetration and the material is not
suitable for jetting, the Engineer may permit pilot holes to be drilled to
facilitate driving. The Engineer will designate the diameter and depth of
the drilled hole. Ordinarily, a drill diameter of 12 inches will be satisfactory
for timber piles and typically a drill diameter 4 inches less than the diagonal
of square piles, 2 inches less than the diagonal of octagonal piles, and 1
inch less than the diameter of round piles will be satisfactory for steel pipe
and concrete piles.
2. Where pilot holes are required in granular material which cannot be sealed
off by ordinary "mudding" drilling methods, a casing pipe of sufficient
diameter shall be placed around the boring device. The casing shall be of
sufficient length to extend through the loose materials and shall be held in
position until the pilot hole is completed and the pile placed ready for
driving.
3. If the hard material extends below the desired penetration, the drilling shall
be stopped 1 foot above that level and the pile driven the remaining
distance if it is possible to do so without damaging the pile. If the pile does
not completely fill the pilot hole, the space between the pile and the wall of
the hole shall be filled with dry granular material prior to driving as directed
by the Engineer.
G. Jetting:
1. If piles cannot be driven to the required penetration and the material is not
suitable for pilot holes, the Engineer may permit jetting to facilitate drilling.
3. Jetting shall be stopped a minimum of 2 feet above the desired tip elevation
and the final penetration obtained by driving without jetting. In silty soils it
is possible that jetting may loosen the soil around piles already driven. If
such a condition is considered possible, piles shall be redriven after all
jetting within 25 feet has been completed.
1. The use of explosives for drilling of pilot holes will not be permitted.
I. Bearing Capacity:
1. All piles shall be driven to the allowable working compressive load specified
on the plans, in the special provisions, or by the Engineer. The bearing
values shall be determined using the following formula unless otherwise
shown on the plans:
3𝑒𝐸 𝑊𝑟 + 𝑛2𝑊
𝑃= x
𝑠 + 𝑐 𝑊𝑟 + 𝑊𝑝
3. If, for some unavoidable reason, driving must be interrupted before final
penetration is reached, the penetration per blow to determine bearing
capacity shall not be measured until 12 inches of penetration or refusal has
been obtained after driving has been resumed.
1. Piles shall not be driven within 150 feet of concrete that was placed within
the previous 24 hours. If piling are driven within 150 feet of concrete that
has not attained its specified 28-day strength, the following distances,
based on the concrete strength and pile hammer rated energy, shall be
maintained between the concrete and the nearest pile.
A. The furnished length of test piles shall be a minimum of 10 feet longer than the
estimated length of the permanent piles shown on the plans or as directed by the
Engineer.
B. Wherever possible, test piles shall be driven in a location as shown on the plans.
If not so used in the permanent structure, test piles shall be cut off at least 3 feet
below final grate or extracted as directed by the Engineer. Extraction of test piles
shall be considered incidental to the test pile item, and no separate compensation
will be made for this work.
D. Equipment used for driving test piles shall be adequate for handling the lengths
provided without splicing. The hammer and all accessories used shall be the same
make and model as that to be used in driving the permanent piles.
E. Driving of a test pile shall continue until a penetration and bearing capacity is
obtained as indicated by these specifications. Typically, test piles shall be driven
to not less than 125 percent of the ultimate pile capacity required for permanent
piles in the bridge structure.
A. Pile Preparation:
1. When the furnished length is much longer than the required length, the
Engineer may permit shortening the tip end before driving so as to have
the desired diameter at the cut-off.
B. Cut-offs:
2. Piles which are to support steel or timber caps shall be brought into final
position and held while cut-off is made. Any chains or jacks used in
positioning the piles shall be arranged so that the surface of the pile below
cut-off will not be damaged. Cut-off shall be made with a saw to a true
plane and to the exact elevation shown on the plans so that the cap will
bear on the entire cross section of each pile in the bent. No shims will be
permitted between the pile and the cap. Piles must show a solid head at
the plane of cutting, and after cut-off, the pile caps shall be protected with
preservative, fabric, and plastic cement as specified on the contract
documents.
1. Any pile surface below cut-off that has been scuffed, torn or otherwise
damaged shall be treated in accordance with the requirements of the
applicable plans.
1. The length of steel bearing piles and steel sheet piles shown on the plans
may be built up in sections either before or during driving operations. The
sections, unless otherwise shown on the plans, shall be of identical cross-
section. Pile splices shall be made by full penetration butt welding the
entire cross-section or as otherwise shown on the plans. All welding shall
be in accordance with AWS D1.5. Care shall be taken to properly align the
sections connected so that the axis of the pile will be straight. Pile splices
above a point 15 feet below finished ground line shall be reinforced as
shown on the plans, unless otherwise directed by the Engineer. Field
splices shall be avoided for lengths under 60 feet. No more than two (2)
splices will be permitted on each pile.
B. Cut-Offs:
1. Piles shall be cut off, with a cutting torch, or by other acceptable methods,
to the elevation shown on the plans. Where caps are required, piles shall
be brought into final position and held while cut off is made and the end
surface of the piles shall be made as smooth as practicable with maximum
gap of 1/8 inches between pile and pile cap.
1. The length of a steel pipe pile may be built up in sections either before or
during the driving operation. The minimum length of a section measured
between welded splices shall be 5 feet, and between drive splices shall be
30 feet. Only one welded splice and no drive splices will be permitted in
that portion of the pile exposed above ground line or normal water line.
Drive splices shall be 15 feet below the ground line, unless directed by the
Engineer.
B. Cut-Offs:
1. Piles shall be cut off, with a cutting torch, or by other acceptable methods,
to the elevation shown on the plans or established by the Engineer. Where
caps are required, piles shall be brought into final position and held while
cut off is made and the end surface of the piles shall be made as smooth
as practicable with maximum gap of 1/8 inches between pile and pile cap.
C. Placement of Concrete:
1. After all driving, splicing, and positioning of pile is completed, the pile shall
be free from buckles, splits, distortions, water or other foreign matter. The
Contractor shall provide equipment, lighting, and facilities necessary for the
proper inspection of the piles. Any damaged, improperly driven, or
otherwise defective pile shall be removed and replaced at the Contractor's
expense.
2. The tops of piles shall be kept covered after driving until the concrete is
placed. No concrete shall be placed in the piles in any unit until the driving
of all piles in that unit has been completed. No concrete shall be placed
until the Engineer has inspected the completed pile and reinforcing steel,
when required, and given his approval to proceed. Unit is defined as a pier,
bent or abutment.
A. Splices:
1. Splices for precast and prestressed concrete piles will not be permitted.
B. Build-ups:
1. Build-ups shall be made in accordance with the details shown on the plans.
The concrete used for the build-up shall be of the same quality as that used
originally in the pile. Just prior to placing the concrete, the top of the pile
shall be coated with an epoxy bonding compound approved by the
Engineer.
C. Cut-Offs:
3.09 OBSTRUCTIONS
A. Should any obstruction including but not limited to boulders, rocks, rubble, fill,
existing foundations or timbers be encountered which prevent driving of pile to its
required tip elevation or final driving resistance, threaten pile damage or cause pile
to drift from required location horizontally or vertically, cease driving and take
corrective action as directed by Engineer.
B. Each pile to be free from defects and damage due to construction, fabrication,
delivery, installation or other causes.
C. Damaged piles include but not necessarily limited to piles bent, buckled, cracked,
with fabrication tolerances beyond those indicated, or with any other defect as
determined by the Engineer that would weaken the pile.
A. Provide Engineer with a copy of a pile report for all driven pile providing the
following information:
3. Weather.
6. Pile type.
7. Batter.
9. Description of piles that were rejected (pile number, location, reason for
rejection).
16. Hammer blow count and ram fall for each foot along full length of pile.
4.01 MEASUREMENT
A. Piles
1. General:
a. Piles delivered of the various kinds, sizes, types, and weights will
be measured by the lineal foot, except steel sheet piles will be
measured by the square foot, of acceptable pile delivered at the site
of work and furnished in accordance with the lengths specified on
the plans.
b. Piles driven of the various kinds, sizes, types, and weights will be
measured to the nearest 1/10 lineal foot of net length of pile in place,
except steel sheet piles will be measured by the square foot of
acceptable pile in place, after all cut-offs and build-ups have been
made.
2. Timber Piles:
3. Steel Piles: Cut-off portions of piles will not be measured for payment.
B. Test Piles
1. Test piles of the various kinds, sizes, types and weights, when the piles do
not become a part of the permanent structure, will be measured by the
lineal foot of pile in the leads and driven in accordance with these
specifications and in the location specified on the plans or by the Engineer.
When test piles becomes a part of the permanent structure, they will be
measured by the lineal foot of acceptable pile in place after all cut-offs and
build-ups have been made in accordance with the provisions of Paragraph
1.07.A covering the various kinds of piles.
4.02 PAYMENT
A. Piles
1. Piles Delivered:
a. Piles delivered will be paid for at the contract unit price per lineal
foot or square foot, as designated in Article 4.01, of the various
kinds, sizes, types, and weights.
1) The contract unit price shall include full compensation for all
work and costs involved for furnishing the piles, unless
otherwise specified; unloading, storing, and transporting the
piles. This price shall not include compensation for concrete
or reinforcing steel in steel pipe piles which will be paid for
under Section 34 80 41 and Section 34 80 42.
2. Piles Driven:
a. Piles driven will be paid for at the contract unit price per lineal foot
or square foot, as designated in Article 4.01, of the various kinds,
sizes, types, and weights.
3. Timber Piles:
a. The contract price per lineal foot of acceptable timber pile shall also
include full compensation for preparing the piles, disposing of the
pile heads, treating the pile tops as specified in Paragraph 3.05.B.
B. Test Piles
1. Test piles will be paid for at the contract unit price per lineal foot of test pile
of the various kinds, sizes, types, and weights.
a. The contract unit price shall include full compensation for furnishing
the piles, unless otherwise specified; unloading, storing, and
transporting the piles; and for furnishing all labor, materials, tools,
equipment, jetting, pilot holes, and incidentals necessary to drive
the piles and complete the work. Payment will be made for splices
authorized by the Engineer at the rate specified in Paragraph
4.02.A.4.
1. Payment for reinforced pile tips on steel bearing piles, if required, shall be
made at the contract unit price per each.
a. The contract unit price shall include full compensation for furnishing
all material, labor and equipment required to install the tips.
Payment will be made only for reinforced tips required as shown on
the plans or as requested by the Engineer.
CONTRACTOR ___________________________________________
FOREMAN _______________________________________________ GROUND ELEVATION ___________________________
OBSERVER ______________________________________________ PILE TIP ELEVATION ____________________________
CUTOFF ELEVATION ____________________________
HAMMER TYPE/SIZE _____________________________________ PILE TYPE/SIZE _________________________________
CAP/HELMET/CUSION ____________________________________ LENGTH _______________________________________
RAM WEIGHT ____________________________________________ BATTER ________________________________________
THROTTLE SETTING _____________________________________
REMARKS: ______________________________________________________________________________________________________
_________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________
_________________________________________________________________________________________________________________
TIME OF START ____________________________________ TIME OF STOP _________________________________
END OF SECTION 34 80 21
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
C. CIDH Pile construction shall be in accordance with the most current edition of The
American Railway Engineering and Maintenance-of-Way Association (AREMA)
Manual of Railway Engineering, Chapter 8: Concrete Structures and Foundations,
Part 24: Drilled Shaft Foundations.
1.02 REFERENCES
A. ADSC West Coast Chapter, Standard CIDH Pile Anomaly Mitigation Plan “A” and
Plan “B”.
2. A53, Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-
Coated, Welded and Seamless.
3. A252, Standard Specification for welded and Seamless Steal Pipe Piles.
5. A929, Standard Specification for Steel Sheet, Metallic Coated by the Hot-
Dip Process for Corrugated Steel Pipe.
6. C203, Standard Test Method for Breaking Load and Flexural Properties of
Block-Type Thermal Insulation.
1.03 SUBMITTALS
A. See Division 01 for requirements for the mechanics and administration of the
submittal process.
C. Shop Drawings of all reinforcing and accessories required for the CIDH Piles.
E. Test Reports:
1. Copies of concrete strength tests for concrete placed in the CIDH Piles.
A. Qualifications:
1. Contractor Qualifications:
c. The CIDH pile work shall be performed under the supervision of the
Contractor’s superintendent, who shall be fully knowledgeable and
experienced in construction of CIDH pile foundations of similar size
and geotechnical conditions as those shown on the plans.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Slurry:
1. Only mineral or polymer slurries shall be used in the drilling process unless
other drilling fluids are approved in writing by the Engineer.
2. The percentage and specific gravity of the material used to make the
suspension shall be sufficient to maintain the stability of the excavation and
to allow proper concrete placement.
4. All tests specified below shall be performed when the slurry temperature is
above 40˚ F.
c. The Contractor must draw sample sets from the slurry tanks and
test the samples for conformance with the specified material
properties prior to introduction into the shaft excavation.
6. The Contractor must sample and test all slurry in the presence of the
Engineer, unless otherwise directed.
a. The date, time, names of the persons sampling and testing the
slurry, and the results of the tests shall be recorded.
Mineral slurries
(bentonite/attopulgite)
a. No end bearing 85 maximum
b. With end bearing 70 maximum
Polymer slurry
a. No end bearing 64 maximum
b. With end bearing 64 maximum
(bentonite/attopulgite)
Mineral slurries
(bentonite/attopulgite)
a. No end bearing 4 maximum
b. With end bearing 20 maximum
Polymer slurry
a. No end bearing 1 maximum
c. The Contractor must wait 30 minutes, after the last drilling and
scouring, to allow contaminants to settle out before taking and
testing a sample set of slurry.
B. Concrete:
3. The concrete for construction of drilled shafts shall have a slump of 8 inches
±1.5 inches.
4. Concrete admixtures:
C. Reinforcing Steel:
E. Expanded Polystyrene:
PART 3 - EXECUTION
A. The CIDH Pile shall be within 3 inches of plan position at the top of shaft.
B. The vertical alignment of pile excavation shall not vary from the plan alignment by
more than 1/4 inches/feet.
C. Full depth reinforcing steel cages shall be set at no less than 6 inches above the
bottom of the excavated shaft prior to placement of concrete.
D. After all the concrete is placed, the top of the reinforcing steel cage shall be no
more than six (6) Inch above and no more than 2-3/4 inches below plan position.
E. The top elevation of the shaft may have a tolerance of up to +1 inches or -3 inches
from the plan top of pile elevation.
1. Sufficient reinforcement bar splice length for splices above the shaft shall
be attained.
F. Excavation equipment and methods shall be designed so that the completed shaft
excavation will have a planar bottom.
G. CIDH Pile excavations and completed shafts not constructed within the required
tolerances are unacceptable.
H. The elevations, dimensions, and depth of the CIDH Piles shall be as specified on
the Plans.
3.02 INSTALLATION
A. The installation of the CIDH pile must be done in a continuous operation with no
unplanned interruptions. If an unplanned interruption cannot be avoided, the
engineer shall be notified immediately and the contractor must submit remedial
measures for approval.
1. The Contractor must submit a signed statement that they have inspected
the project site and all the subsurface information made available in the
contract documents.
2. No later than 1 month prior to constructing CIDH Piles, the Contractor must
submit a CIDH Pile installation plan for review by the Engineer.
a) Driller.
3. The Engineer will evaluate the CIDH pile installation plan for conformance
with the Contract Documents.
a. Within 14 calendar days after receipt of the plan, the Engineer will
notify the Contractor of additional information required and changes
necessary to meet the Contract requirements.
4. A pre-drilling conference will be required for this work prior to the start of
pile excavation. The Engineer and SCRRA will set up the conference.
C. Pile Excavation:
2. Construction Method:
2) Wet Method:
3) Casing Method:
a. Rock drilling tools such as augers with fitted rock teeth, core barrel,
buckets with significant down crowding, or roller bits combined with
extra drilling pressure by a hydraulic or percussion system are used
for the rock drilling excavation.
4. The Contractor shall anticipate and make available at the job site all
equipment necessary and essential to penetrate soft and hard rock during
the construction of the drilled shafts.
5. CIDH piles shall be installed in such a manner that no voids shall exist
between the overburden and the casings.
6. The drilling sequence shall be such that for every pile drilled, at least two
piles are skipped. The piles adjacent to the freshly poured pile may only
be drilled a minimum of 24 hours after placement of concrete.
7. The Contractor must extend CIDH pile tip elevations if the Engineer
determines that the material encountered during excavation or present at
tip elevation is unsuitable and/or differs from that anticipated in the design
of the CIDH pile.
8. After the pile excavation has been completed, the Contractor shall
immediately proceed with shaft construction.
9. Safety:
a. The Contractor shall not permit any worker to enter the CIDH pile
excavation for any reason unless; a suitable casing has been
installed, the water level has been lowered and stabilized below the
level to be occupied, and an adequate safety equipment and
procedures have been provided to the personnel entering the
excavation which includes OSHA certification for confined-entry-
space.
a. For each CIDH pile construction, the Contractor must provide the
Engineer with an excavation record including but not limited to the
following: the location; dimensions; verticality; description of the
materials encountered at all elevations; drilling time in each of the
various strata; elevation of the water table during excavation;
description of any change in excavated material; elevation of top
and bottom of the finished pile; depth to the steel casing; condition
of the bottom of the excavation and deviation from plan location.
1. The procedure and methods to install and seal the steel casings shall not
produce stresses in excess of 25 percent over the design allowable for the
type of steel used.
b. The casing shall not be more than one inch out of round before and
after installation.
4. After installation but prior to excavation of the rock socket, the casings shall
be inspected for location, alignment and condition.
1. The Contractor shall determine the elevation of the top of the rock and at
the bottom of the casing at each drilled shaft location.
2. Prior to excavation of the rock socket, the Contractor shall seat the casing
in the sound rock for a minimum depth of 1 foot and attempt to dewater the
shaft.
c. The Contractor will not be required to carry the casing more than
an additional 3 feet (a total of 4 feet) into the sound rock. The casing
may be advanced four feet into the sound rock during initial
placement.
d. The preliminary tip elevations of the casings are shown in the plans
based on available borings.
a. Excavation shall be along the axis of the shaft and over breakage
at the rock surface shall be avoided so as not to destroy the seal of
the bottom of the steel casing.
F. Final Cleaning:
1. If a slurry cake builds up on the sidewalls of the drill hole, the Contractor
shall remove it prior to concrete placement at no additional cost.
2. The Contractor must clean the base of each pile so that a minimum of 50
percent of the base will have less than ½” of sediment at the time of
concrete placement.
4. For slurry piles, the Contractor must use an air lift to clean the bottom of
the pile.
a. After a wait period equal to the time to set the reinforcing steel cage
and concrete placement setup, the Contractor shall measure the
amount of sediment in the bottom of the pile.
1. The Contractor must provide suitable means of access and lighting facilities
for the Engineer to check locations, dimensions, and alignment of the
casings, inspect conditions of the casings, and inspect and determine that
the rock sockets are satisfactory.
3. If the shaft cannot be dewatered, the Contractor must provide a method for
visual inspection to confirm that the shaft is in an acceptable condition and
that rock socket cleanliness requirements are met.
2. The reinforcing steel in the pile shall be tied and supported so that the
reinforcing steel will remain within allowable tolerances given in this
Specification Section.
3. The elevation of the top of the steel cage shall be checked before and after
the concrete is placed.
4. At no time shall the reinforcing cage be allowed to rest at the bottom of the
drill hole.
I. Concrete Placement:
b. The tremie shall not be less than 10 in dia., and there shall be no
aluminum parts in contact with concrete.
d. The tremie shall have sufficient mass that it will rest on the pile
bottom before start of concrete placement.
h. The flow of the concrete shall be continuous and the concrete in the
tremie shall maintain a positive pressure differential at all times to
prevent introduction of air pockets or contaminants into the
concrete.
4. The elapsed time from the beginning of concrete placement in the pile to
the completion of the placement shall not exceed 3 hours.
a. All admixtures, when approved for use, shall be adjusted for the
conditions encountered on the job so the concrete remains in a
workable plastic state throughout the 3 hours placement limit.
J. The concrete in the rock socket shall be, if at all possible, placed in the dry.
1. The Contractor will be required to make a diligent effort to dewater the rock
socket.
2. If, after making such effort, it is determined by the Engineer that it is not
possible to dewater the socket sufficiently to allow the concrete to be
placed in the dry; the Contractor, with the Engineer's written approval, shall
proceed with the placement of the concrete under water.
K. The casing segment above the top elevation of the drilled shaft shall be left empty.
A. Provide means and opportunity for the Engineer to inspect the operation during
the withdrawal of casing and placing of concrete.
1. Maintain head of concrete to exceed the anticipated outside soil and water
pressure above the bottom of the casing at all times during casing
withdrawal.
C. Check concrete level prior to, during, and after withdrawing casing to confirm that
separation of shaft concrete has not occurred.
3. Do not withdraw casing after concrete has attained initial set as determined
by the Engineer.
A. Inspection of Pile:
1. For piles that have been dewatered, or constructed in the “Dry”, the
Contractor shall provide a method for visual inspection to confirm that the
pile is acceptable.
b. Each inspection pipe shall be capped at the bottom and shall extend
from 3 FT above the pile cutoff down to the bottom of the reinforcing
cage. A temporary top cap or similar means shall be provided to
keep the pipes clean before testing. If pile cutoff is below the
ground surface or working platform, inspection pipes shall be
extended to 3 FT above the ground surface or working platform.
Approved covers or railings shall be provided and inspection pipes
shall be located as necessary to minimize exposure of testing
personnel to potential falling hazards.
e. When any changes are made to the tip of CIDH concrete piling, the
Contractor shall also extend the inspection pipes to the bottom of
the reinforcing cage.
f. Inspection pipes shall be placed radially around the pile, inside the
outermost spiral or hoop reinforcement and no more than 1 IN clear
of the outermost spiral or hoop reinforcement.
5. For each inspection pipe that does not pass the 1-1/4 IN DIA cylinder, the
Contractor shall core a nominal 2 inch diameter hole through the concrete
for the entire length of the pile. Cored holes shall be located as close as
possible to the inspection pipes they are replacing and shall be no more
than 5 IN clear from the reinforcement.
a. Coring shall not damage the pile reinforcement. Cored holes shall
be made with a double wall core barrel system utilizing a split tube
type inner barrel. Coring with a solid type inner barrel will not be
allowed. Coring methods and equipment shall provide intact cores
for the entire length of the pile. The coring operation shall be logged
by an Engineering Geologist or Civil Engineer licensed in the State
of California and experienced in core logging. Coring logs shall be
in conformance with the Caltrans "Soil and Rock Logging,
Classification, and Presentation Manual." Coring logs shall include
Core Recovery (REC), Rock Quality Designation (RQD), locations
of breaks, and complete descriptions of inclusions and voids
encountered during coring, and shall be delivered to the Engineer
upon completion. Concrete cores shall be preserved, identified with
the exact location the core was recovered from within the pile, and
delivered to the Engineer upon completion. The Engineer will
evaluate the portion of the pile represented by the cored hole based
on the submitted core logs.
8. The Engineer may elect to require additional tests to further evaluate a pile.
These tests may include cross-hole sonic logging (CSL) and other means
of inspection selected by the Engineer. When the Engineer elects to
require additional tests to further evaluate anomalies for a rejected pile, no
time requirement exists for performing these tests. The Contractor may
progress with the mitigation plan process without waiting for these
supplemental results.
9. Inspection pipes and cored holes shall be dewatered and filled with grout
after notification by the Engineer that the pile is acceptable. Inspection
pipes and holes shall be filled using grout tubes that extend to the bottom
of the pipe or hole or into the grout already placed.
10. If the Engineer determines that a pile does not meet the requirements of
the specifications and California Test 233, Part 5C, then that pile will be
rejected and all depositing of concrete under slurry or concrete placed
using temporary casing for the purpose of controlling groundwater shall be
suspended until written changes to the methods of pile construction are
approved in writing by the Engineer.
1. The Engineer will determine whether the rejected pile requires mitigation
due to structural, geotechnical, or corrosion concerns. The Engineer will
consider the estimated size and location of the anomaly and potential
effects upon the design. The Engineer will provide the conclusions of this
analysis to the Contractor for development of a mitigation plan, if required.
The Contractor shall allow 35 days for the Engineer to determine whether
the pile requires mitigation and provide information to the Contractor. Day
1 of the 35 days shall be the 1st day after results of acceptance testing
have been provided to the Engineer. If additional information is submitted
to the Engineer that modifies the size, shape, or nature of the anomaly, the
Contractor shall allow 15 additional days for the subsequent analysis.
2) The Engineer has determined that the rejected pile does not
require mitigation due to structural, geotechnical, or
corrosion concerns, and the Contractor elects to repair the
pile using the most recent version of the "ADSC Standard
Mitigation Plan 'B' - Grouting Repair" without exception or
modification.
D. The most recent version of the "ADSC Standard Mitigation Plan" is available at:
http://www.dot.ca.gov/hq/esc/geotech/ft/adscmitplan.htm
3. All provisions for CIDH concrete piling shall apply to replacement piles.
4. The Contractor shall allow the Engineer 20 days to review the mitigation
plan after a complete submittal has been received.
5. When repairs are performed, the Contractor shall submit a mitigation report
to the Engineer within 10 days of completion of the repair. This report shall
state exactly what repair work was performed and quantify the success of
the repairs relative to the submitted mitigation plan. The mitigation report
shall be stamped and signed by an engineer that is licensed as a Civil
Engineer by the State of California. The mitigation report shall show the
assigned contract number, full name of the structure as shown on the
contract plans, and the Contractor (and subcontractor if applicable) name
on each sheet. The Engineer will be the sole judge as to whether a
mitigation proposal is acceptable, the mitigation efforts are successful, and
to whether additional repairs, removal and replacement, or construction of
a supplemental foundation is required.
3.05 CLEANING
2. All slurry and water, displaced during final cleaning and concrete
placement, shall be collected and properly disposed off site.
4. All excavated material, slurry, water, and other matter shall be controlled
by the Contractor so that at no time it enters or encroaches upon the
adjacent travel lanes, railroad and water ways.
4.01 MEASUREMENT
A. CIDH Piles will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. The length of each CIDH Piles to be paid for shall be the length, measured along
the longest side, from the tip elevation shown on the plans, or the tip elevation
ordered by the Engineer for the diameter of the pile shown on the plans, to the
plane of the pile cut-off. No reduction in the length for payment will be made for
any CIDH pile where the tip elevation is revised in conjunction with a request by
the Contractor to increase the pile diameter.
4.02 PAYMENT
A. CIDH Piles will be paid the contract unit price, as listed in the Schedule of
Quantities and Prices.
B. The contract unit price shall include full compensation for all equipment, labor and
materials necessary to satisfactorily construct the shafts; including drilling and
excavation of shaft and rock socket, furnishing, installing and removing temporary
casing, furnishing and placing concrete, confirmation boring and lab testing,
reporting boring logs and lab test results, CSL (steel pipe) or gamma-gamma (PVC
pipe) non-destructive testing and reporting, shaft inspection, disposal of excavated
materials and water, and all other materials.
C. Full compensation for furnishing all reinforcing steel in piles and pile extensions,
including reinforcement required to extend beyond the pile or extension as shown
on the Plans, shall be considered as included in the Contract price per unit for
furnishing piling of the type or class shown in the Schedule of Quantities and
Prices, and no additional compensation will be allowed therefor.
END OF SECTION 34 80 22
PART 1 - GENERAL
1.01 SUMMARY
B. Related Specification Sections include but are not necessarily limited to:
3. Section 31 20 00 - Earthwork.
1.02 REFERENCES
2. D3212, Standard Specification for Joints for Drain and Sewer Plastic Pipes
Using Flexible Elastomeric Seals.
6. F949, Poly (Vinyl Chloride) (PVC) Corrugated Sewer Pipe with a Smooth
Interior and Fittings.
1.04 SUBMITTALS
A. See Division 01 for requirements for the mechanics and administration of the
submittal process.
B. Samples:
1. Materials:
C. Certificates:
1. Materials:
b. Certifications are required for drain pipe, drain tile, fittings and filter
fabric.
1. Inspect materials delivered to site for damage; unload, and store with
minimum handling.
3. The inside of pipes and fittings shall be free of dirt and debris.
4. Install plastic pipe within 6 months from the date of manufacture unless
otherwise approved.
B. Handling:
PART 2 - PRODUCTS
2.01 MATERIALS
A. Plastic Pipe: Plastic pipe shall contain ultraviolet inhibitor to provide protection
from exposure to direct sunlight.
B. Polyvinyl Chloride (PVC) Pipe: ASTM F758, Type PS 46, ASTM D3034, or ASTM
F949 with a minimum pipe stiffness of 46 psi.
1. Use ASTM F405 for pipes 3 to 6 inches in diameter inclusive, ASTM F667
for pipes 8 to 24 inches in diameter.
D. Pipe Perforations:
1) Circular holes shall be cleanly cut not more than 3/8 inches
or less than 3/16 inches in diameter and arranged in rows
parallel to the longitudinal axis of the pipe.
2) Width of slots shall not exceed 1/8 inches nor be less than
1/32 inches.
E. Fittings:
H. Filter Fabric:
3. Resistant to the chemical actions of the soil and water and non-
biodegradable.
4. Fabric to prevent the migration of soil particles into the subdrain while
allowing the free flow of water from the subsoil to the subdrain pipe.
1. Geocomposite wall drain shall consist of a manufactured core not less than
0.25 inches thick nor more than 2 inches thick with one or both sides
covered with a layer of filter fabric.
a. The drain shall produce a flow rate of at least 2.0 gal per minute per
foot of width at a hydraulic gradient of 1.0 and a minimum externally
applied pressure of 3,500 psf.
2. Filter Fabric for the geocomposite drain shall conform to the provisions for
Filter Fabric in this Specification.
PART 3 - EXECUTION
3.01 INSTALLATION
B. Bedding:
2. Each section shall rest firmly upon the bedding, through the entire length,
with recesses formed for bell joints.
3. Except for recesses for bell joints, the bedding shall fully support the lower
quadrant of the pipe.
C. Pipe Laying:
1. Lay drain lines to true grades and alignment with a continuous fall in the
direction of flow.
4. When drain lines are left open for connection to discharge lines, the open
ends shall be temporarily closed and the location marked with wooden
stakes.
6. Any length that has had its grade or joints disturbed shall be removed and
relaid at no additional cost to the SCRRA.
D. Jointing:
1. Perforated pipe:
c. Covered joints shall have one thickness of the cover material placed
over the joint.
d. Material shall overlap the joint not less than 4 inches on each side
and cover the tile for not less than the upper half or more than the
upper two-thirds of the circumference of the tile.
3. PVC pipe:
E. Outlet Lines:
1. The outlet end of drain lines connecting with an open gutter or outfall shall
be covered with a removable wire basket of 16-mesh copper or bronze wire
cloth fastened with brass or wire straps.
3.02 BACKFILLING
A. After joints and connections have been inspected and approved, place the
specified pervious backfill material a minimum width of 6 inches on each side of
the pipe and 12 inches above the top of the pipe.
3.03 TESTS
A. Pipe Tests:
1. Strength tests of pipe shall conform to field service test requirements of the
ASTM Specification or AASHTO Specification covering the product (See
paragraph 2.1. in this Specification Section).
4.01 MEASUREMENT
4.02 PAYMENT
A. Subdrainage system for will be paid at the Contract lump sum price.
1. The contract lump sum price paid for subdrainage system for Railroad
Bridges, Retaining Walls, Concrete Masonry Wall, Concrete Retaining
Wall, and Platforms shall include full compensation for furnishing all labor,
materials, tools, equipment and incidentals, and for doing all work involved
in constructing the subdrainage system, complete in place, as shown on
the Drawings, as specified in this Specification Section, and as directed by
the Engineer.
END OF SECTION 34 80 23
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Description:
1. This work shall consist of shaft excavation, backfilling shaft with lean
concrete backfill, installing steel piling, installing steel brackets and steel
support angles, installing precast concrete headwall and wingwall panels,
connecting the culvert pipe to the headwall with end anchors, and
backfilling the headwall and wingwall panels.
C. Related Specification Sections include but are not necessarily limited to:
4. Section 31 20 00 – Earthwork.
1.02 REFERENCES
2. A193, Standard Specification for Alloy-Steel and Stainless Steel Bolting for
High Temperature or High Pressure Service and Other Special Purpose
Applications.
3. A194, Standard Specification for Carbon Steel, Alloy Steel, and Stainless
Steel Nuts for Bolts for High Pressure or High Temperature Service, or
Both.
1.03 SUBMITTALS
A. Shop Drawings:
3. Shop drawings for the precast concrete headwall and wingwall panels, in
accordance with Section 34 80 43.
b. Mix design for lean concrete backfill and socket concrete backfill.
c. End anchors.
d. Epoxy adhesive.
e. Grout.
B. The Contractor shall provide to the Engineer a description of the augercast pile
headwall and wingwall installation equipment to be employed in the work and
sequence of installation, prior to commencement of the work.
D. The Contractor shall provide details of the method(s) to be used to ensure shaft
stability (i.e., prevention of caving, bottom heave, etc. using temporary casing,
slurry, or other means, or if soils are self-supporting) during excavation and
concrete placement. If temporary casings are proposed, casing dimensions and
detailed procedures for casing installation and removal shall be provided. If slurry
is proposed, detailed procedures for mixing, using, maintaining, and disposing of
the slurry shall be provided.
F. The Contractor shall provide details of soldier pile placement including internal
support bracing and centralization methods.
G. The Contractor shall provide details of lean concrete backfill or socket concrete
backfill placement including proposed operational procedures for pumping and/or
tremie methods.
H. The Contractor shall provide its plan for shoring or sloping earth behind the
augercast pile headwall and wingwall as necessary for construction in
accordance with Section 31 50 00.
A. Qualifications:
PART 2 - PRODUCTS
2.01 MATERIALS
A. Steel Piles:
1. Steel piles for the augercast pile headwall and wingwall shall be of the
section shown on the Contract Documents, containing no less than 0.2
percent copper, conforming to ASTM A572, Grade 50. Piles shall not be
painted before installation.
B. Miscellaneous Steel:
1. Miscellaneous steel for use in the augercast pile headwall and wingwall
shall be of the section shown on the Contract Documents, conforming to
ASTM A36, including but not limited to the steel support brackets.
Miscellaneous steel shall be painted as noted herein.
1. Materials for the precast concrete headwall and wingwall panels shall meet
the requirements of Section 34 80 43 and Engineering Standard 6320.
1. Materials for corrugated metal pipe (CMP) culvert shall meet the
requirements of Section 33 42 00.
G. End Anchors:
1. Threaded rods shall be galvanized and meet ASTM A193 Grade B7.
2. Connecting nuts shall be galvanized and meet ASTM A194 Grade 2H.
H. Epoxy Adhesive:
I. Grout:
J. Handrailing:
2.02 FABRICATION
A. Steel Piles:
2. Tolerances:
1. Fabrication of the corrugated metal pipe (CMP) culvert shall meet the
requirements of Section 33 42 00.
E. Handrailing:
PART 3 - EXECUTION
3.01 PREPARATION
A. Shaft Excavation:
B. Backfilling Shaft:
4. If a pile socket is required, the excavated shaft shall be backfill with socket
concrete backfill, as shown in the Engineering Standard 6320 and the
Contract Documents.
C. Installing Pile:
1. The steel piles shall be immediately lowered into the shafts after lean
concrete backfill or socket concrete is placed and secured in position.
Concrete cover over the steel pile shall be 2 inches minimum.
2. The steel piles shall be placed so that the centerline of the pile at the top is
within 1/2 inch of the Plan location. The steel pile shall be plumb, to within
0.3 percent of the length based on the total length of the pile.
2. Each steel support bracket shall be field-painted, after welding to the steel
pile. Field-paint with one coat of Carboline Carboguard 890 VOC (or
approved equal), applied to a dry film thickness of 8 mils, corresponding to
a wet film thickness of 10 mils.
1. The precast concrete headwall panels shall be installed from the top of the
steel pile proceeding downward. The headwall panel shall make direct
contact with the soil. When and where headwall panel is not in full contact
with the soil being retained, either the headwall panel shall be wedged back
to create contact or the void shall be filled with a free-draining material, as
approved by the Engineer.
2. When utilizing headwall panels in fill situations, the backfill layers shall be
placed in accordance with Section 31 20 00.
1. Connect culvert into the precast concrete headwall panel opening with end
anchors and grout in accordance with Engineering Standard 6320 and the
Contract Documents.
2. Using pre-drilled holes in the CMP culvert as a template, drill holes into
precast concrete headwall panel and clean in accordance with epoxy
adhesive manufacturer instructions.
3. Each end anchor shall be placed within 1/4" of the specified location prior
to setting and bonding with epoxy adhesive, with nut tightened.
4. Fill annular space between headwall and CMP culvert with grout.
1. The precast concrete wingwall panels shall be installed from the top of the
steel pile proceeding downward. The wingwall panels shall make direct
contact with the soil. When and where wingwall panel is not in full contact
with the soil being retained, either the wingwall panel shall be wedged back
to create contact or the void shall be filled with a free-draining material, as
approved by the Engineer.
2. When utilizing wingwall panels in fill situations, the backfill layers shall be
placed in accordance with Section 31 20 00.
H. Installing Handrailing:
4.01 MEASUREMENT
A. Steel Piling will be measured by the linear foot as specified in the Contract
Documents.
B. Shaft construction will be measured by the linear foot of shaft excavated and only
that portion filled with lean concrete or socket concrete, as defined in the
Contract Documents, within the specified shaft diameter.
C. End Anchor will be measured by each unit installed in accordance with the
Contract Documents.
4.02 PAYMENT
A. Steel Piling shall be paid per linear foot, which includes fabricating the pile
assemblies, field splicing and field trimming the steel piles, welding attachments
to the steel piles and painting the exposed portions of the steel piles and
attachments.
B. Shafts shall be paid per linear foot, which includes shaft excavation, rock
socketing if needed, temporary casing if used, slurry if used, dewatering if
needed, lean concrete backfill, socket concrete backfill, and installing the steel
pile as detailed in the Contract Documents.
C. End Anchor shall be paid per each unit, which shall include full compensation for
furnishing labor, drilling, materials, threaded rods, nuts, epoxy adhesive, grout
between headwall and culvert, tools, equipment, supplies, supervision and
incidentals as detailed in the Contract Documents.
END OF SECTION
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
3. Section 31 20 00 - Earthwork.
1.02 REFERENCES
1.03 DEFINITIONS
A. Installer or Applicator:
1.04 SUBMITTALS
A. Shop Drawings:
a. Elbows.
b. Couplings.
c. Lap details.
d. End treatments.
PART 2 - PRODUCTS
1. Deck Drains:
2.02 MATERIALS
A. Deck Drain:
1. Corrugated steel pipe for deck drains shall be galvanized steel pipes with
1-1/2” x 1/4” corrugation manufactured from galvanized steel coils
conforming to applicable requirements of ASTM A929 and manufactured
in accordance with the applicable requirements of ASTM A760.
B. Drainage Piping:
B. The acceptance of any material by the inspector shall not be a bar to their
subsequent rejection if found defective.
1. Rejected material must be promptly removed from the job and replaced
with acceptable material.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Deck Drain:
1. Install corrugated steel pipe deck drain system as shown in the Drawings
and in accordance with ASTM A798.
c. Grade trench bottom and excavate for pipe bell and lay pipe on
trench bottom.
e. Except for first two (2) joints, before making final connections of
joints, install two (2) full sections of pipe with earth tamped along
side of pipe or final with bedding material placed.
g. Seal open end of line with watertight plug if pipe laying stopped.
4.01 MEASUREMENT
A. Bridge Deck Drainage system will be measured by the unit or fraction thereof
furnished and completed in accordance with the Contract Documents and as
measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the plans will be used as the basis for this measurement.
4.02 PAYMENT
A. Bridge Deck Drainage system will be paid at the contract lump sum price.
1. The contract unit price paid for drainage system shall include full
compensation for furnishing all labor, materials, tools, equipment and
incidentals, and for doing all work involved in constructing the drainage
system, complete in place, as shown on the Drawings, as specified in this
Specification Section, and as directed by the Engineer.
2. Half-round perforated corrugated steel drain pipe, steel pipe, bottom pans,
non-perforated round corrugated steel drain pipes, all connections and
closures, joints, elbows, cleanouts and outlet hardware, concrete drainage
swale or gutter, utility excavation and backfill and other associated material
and incidentals and installation thereof will be considered part of the
drainage system and full compensation therefore will be considered as
included in the contract unit price paid for drainage system.
END OF SECTION 34 80 31
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Waterproofing membrane.
2. Membrane protection.
3. Flashing.
B. Related Specification Sections include but are not necessarily limited to:
3. Section 34 11 26 - Ballast.
1.02 REFERENCES
A. Referenced Standards:
1.03 DEFINITIONS
A. Installer or Applicator:
1.04 SUBMITTALS
A. Shop Drawings:
4. Waterproofing layout:
1) Splice locations.
2) Edge details.
3) Joint details.
b. Membrane protection:
a) Edge details.
b) Joint details.
6. Ponded water test report with results and all remedial measures taken as
a result of a failing test.
A. Qualifications:
2. Installer shall have a minimum of five (5) years experience in the installation
of products specified.
3. Installer shall have completed a minimum of three (3) projects in the last
three (3) years on similar bridges.
1.06 WARRANTY
PART 2 - PRODUCTS
1. Waterproofing membrane:
2. Membrane protection:
a. Asphalt planks:
1) Elsro, Inc.
b. Asphaltic panels:
3. Bonding adhesive:
2.02 MATERIALS
B. Membrane Protection:
D. Cement:
F. Anti-bonding Paper:
1. Tough paper with a weight not less than 5 lbs per 100 sf.
H. Steel Flashing, Flashing Anchors and Armor Plate: In accordance with Section 34
80 52.
B. Acceptance of any material by the inspector shall not be a bar to its subsequent
rejection if found defective.
1. Promptly remove rejected material from the job and replaced with
acceptable material.
C. Do not use any material until it has been accepted by the Engineer.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Waterproofing Membrane:
2. Membrane sheets:
d. Allow adhesive to dry so as to not stick to a dry finger touch and all
solvent is evaporated.
e. Unroll the membrane and press firmly and uniformly in place, using
care to avoid trapping of air.
f. Repeat the same procedure for the remaining half of the membrane
sheets.
3. Splices:
b. Clean all seam, lap and splice areas with heptane, hexane, toluene,
trichloroethylene or white gasoline, using a clean cloth, mop or
similar synthetic cleaning device.
d. After cement is allowed to dry until it will not stick to a dry finger
touch, apply butyl gum tape to cemented area of membrane, press
firmly into place, obtain full contact.
B. Membrane Protection:
1. Asphaltic panels:
2. Asphalt planks:
c. Adhesive: Apply at a rate of not less than 1 gal per 100 sf.
d. Fill any voids between the panels with a material compatible to both
the membrane and the panel.
C. Steel Flashing:
D. Waterproofing Protection:
1. Supervise installation.
B. Ponded water testing: On bridges with entire deck waterproofed with membrane
waterproofing:
4.01 MEASUREMENT
4.02 PAYMENT
B. Adhesive, asphalt planks or sheets, steel sheeting, steel flashing, bolts and
connectors for flashing, armor plates, adhesive anchors, butyl rubber or EPDM
waterproofing membrane and other associated materials and incidentals and
installation thereof shall be considered part of the waterproofing and full
compensation therefore shall be considered as included in the contract unit price
paid for waterproofing.
END OF SECTION 34 80 32
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1. Hot mix asphalt (HMA) for track underlayment, bridge decks, and bridge
approaches.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1.03 SUBMITTALS
A. Shop Drawings:
1.04 DELIVERABLES
PART 2 - PRODUCTS
2.01 MATERIALS
A. Asphalts:
3. Liquid asphalt for the prime coat shall be of the grade designated by the
contract item or specified in the special provisions.
4. Asphaltic emulsion for the tack coat shall be of the grade designated by the
Engineer.
B. Aggregate:
D. Prime Coat:
E. Tack Coat:
PART 3 - EXECUTION
3.01 PREPARATION
A. When placing HMA for track underlay, prepare subgrade in accordance with
Section 31 20 00.
D. Spreading of HMA shall not be permitted when the mixing temperature of HMA is
below 250˚ F.
E. HMA shall only be placed when the atmospheric temperature is above 50˚ F.
4. Fill wide joints and cracks with asphaltic concrete/sand mix material and
compact.
3.02 SPREADING
1. When laying HMA for track underlay and the use of a mechanical spreader
or a grader is impractical, the Contractor must submit a request for the use
of alternate equipment to the Engineer for review.
B. HMA for bridge and bridge approaches shall conform to the following thickness
requirements:
2. The traffic surface shall be permitted to be placed in one 4 inches thick lift.
C. The prime coat shall be applied at a rate of 0.25 gal/sq yd and shall be in
conformance with the Caltrans Standard Specifications, Section 39.
D. The tack coat shall be applied in one application at a rate of 0.02 gal to 0.10 gal/sq
yd of surface covered and shall be in conformance with the Caltrans Standard
Specifications, Section 39.
E. Following application of the tack coat, the HMA shall be spread in conformance
with the Caltrans Standard Specifications, Section 39.
1. Successive lifts may be laid upon previously laid lifts as soon as the
previous lift has cooled sufficiently to show no displacement under
equipment or loaded material delivery trucks.
3.03 COMPACTION
A. Rollers:
a. Rear group wheels shall not follow the tracks of forward group
wheels.
d. The total maximum load per axle, whether single axle or a group of
axles in the same alignment, shall be 22,400 lbs.
B. Rolling:
3. Make initial rolling, using tandem type rollers, parallel to the center line of
the paved surface beginning at the edges of the paved surface and working
toward the center, overlapping on successive trips by one-half the rear
wheel roller.
4. First make final roll longitudinally with the paved surface and then
diagonally or at right angles.
5. Test after the mixture has been rolled with approved straight edge and
surface testing machine laid parallel to the centerline of the paved surface.
4.01 MEASUREMENT
A. Prime Coat and Tack Coat will not be measured for payment. Costs associated
with the prime or tack coats will be considered as incidental to the Hot Mix Asphalt
Pavement.
B. Hot Mix Asphalt Pavement will be measured by the unit or fraction thereof Installed
in accordance with the Contract Documents and as measured by the Engineer.
The quantities as contained on the Schedule of Quantities and Prices, or approved
Schedule of Values as derived from the Contract Drawings will be used as the
basis for this measurement. Separate measurements will be made for each
specified thickness of asphaltic concrete Material as included on the approved
Schedule of Values.
4.02 PAYMENT
END OF SECTION 34 80 33
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specifications Sections include but are not necessarily limited to:
1.02 REFERENCES
8. C618, Standard Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use in Concrete.
10. C1260, Standard Test Method for Potential Alkali Reactivity of Aggregates
(Mortar-Bar Method).
11. D412, Standard Test Methods for Vulcanized Rubber and Thermoplastic
Elastomers—Tension.
14. D2240, Standard Test Method for Rubber Property - Durometer Hardness.
15. D4711, Standard Test Method for Sulfonic and Sulfuric Acids in
Alkylbenzene Sulfonic Acids.
1. A5.1, Specification for Carbon Steel Electrodes for Shielded Metal Arc
Welding.
2. A5.5, Specification for Low-Alloy Steel Electrodes for Shielded Metal Arc
Welding.
1.03 SUBMITTALS
A. Shop Drawings:
3. Shop Drawings and erection plans for precast units, their connections and
supports showing:
A. Qualifications:
PART 2 - PRODUCTS
2. Bearing pads:
2.02 MATERIALS
2. Compression:
3. Shear Modulus (G): 230 ±30 psi Based on tests conducted according to
70˚ to 80˚ F under uniform compressive stresses of 500, 1000 and 1500
psi and at an applied horizontal shear plus slip strain of 50 percent. This
value is applicable to both concrete-to-concrete and steel-to-concrete
surfaces. G is constant in all directions parallel to the bearing plane.
5. Elongation:
c. Heat Aging (per ASTM D573) 70 hrs @ 212˚ F in forced air oven
Elongation, % Change: —25 percent max. 6.
D. Cement:
1. ASTM C33 with coarse aggregate meeting the gradation for size 67 as
stated in ASTM C33.
F. Admixtures:
3. Air entraining admixtures shall conform to ASTM C260 and shall be used
to produce 7 percent ±1 percent entrained air in the concrete after all
admixtures have been incorporated.
4. Water reducing admixtures shall be used only with the approval of the
Engineer and shall conform to ASTM C949, Types A, B, D, or E.
6. The use of calcium chloride or any admixture containing chloride ions will
not be permitted.
G. Flyash:
H. Water:
1. Potable, clean.
I. Maximum total chloride ion content contributed from all ingredients of concrete
including water, aggregates, cement and admixtures measured as a weight
percent of cement to not exceed 0.06 for prestressed concrete and 0.10 for all
other precast concrete.
J. Prestressing Strands:
L. Headed Studs:
1. ASTM A108.
1. ASTM A496.
N. Electrodes:
1. E70 series conforming to AWS A5.1 or AWS A5.5 for welding steel shapes
and plates.
O. Grout:
1. Grout shall consist of one part Type III Portland Cement to three parts of
fine aggregate, by weight, mixed with a gaging solution made of one part
Sika Set to five parts by volume.
2. The following mix proportions will yield one cubic foot of grout:
a. 35 lbs cement.
d. 1 qt Sika Set.
2.03 MIXES
B. Do not begin fabrication of units until concrete mix design(s) have been approved
by Engineer.
2.04 FABRICATION
A. Do not fabricate units until Shop Drawings and Mix Design(s) have been approved
by Engineer and returned to Contractor and support locations have been field
verified by Contractor.
C. Cast all members in smooth rigid forms which will provide straight, true members
of uniform thickness and uniform color and finish.
D. Use sand cement grout mixture to fill all air pockets and voids, and to repair
chipped edges.
E. Finish all repairs smooth and to match adjacent surface texture and color.
F. Incorporate embedded plates, angles, lifting devices, and other inserts into
members at time of manufacture.
H. Weld steel shapes and plates per AWS D1.1 and reinforcing steel per AWS D1.4.
a. Reinforce as indicated.
a. Reinforce as indicated.
a. Reinforce as indicated.
a. Reinforce as indicated.
A. Units shall be stored in such a way as to permit the Inspector's access to all sides
at all times, and the Fabricator's access for shipment without additional moving.
B. Transportation of prestressed units shall not be undertaken until the full 28 day
concrete strength has been achieved, or by order of the Engineer.
C. Units shall be handled such that the points of the support and direction of the
reactions with respect to the unit are approximately the same during transportation
and storage as when the unit is in its final position.
1. Care shall be taken during storage, hoisting, and handling of the precast
units to prevent cracking or damage.
D. Units shall be stored above ground on skids or other supports to keep items free
of dirt and other foreign debris.
C. The SCRRA must be allowed to inspect all Contract work at his own discretion.
PART 3 - EXECUTION
3.01 PREPARATION
1. Check bearing surfaces to determine that they are level and uniform.
B. Do not place design live load on structure until supports have reached their 28 day
required compressive strengths.
3.02 ERECTION
C. Use only erection equipment adequate for placing units at lines and elevations
indicated on Plans.
D. Weld steel shapes and plates per AWS D1.1 and reinforcing steel per AWS D1.4.
E. Coat adjoining surfaces of wingwalls and end caps with grout prior to wingwall
installation.
F. After all precast units are erected and all precast unit connections have been
made, coat all exposed surfaces of the connections as indicated on Plans.
A. Causes for rejection of units include, but are not necessarily limited to the following:
1. Cracked units.
4. Voids or air pockets which, in opinion of Engineer, are too numerous or too
large.
4.01 MEASUREMENT
A. Precast and prestressed concrete members will be measured by the unit or fraction
thereof furnished and completed in accordance with the Contract Documents and
as measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
B. Connection rods and associated hardware and other materials, bearing pads and
embedded steel items shall be considered part of the member and full
compensation therefore shall be considered as included in the contract unit price
paid for furnishing and erecting the precast and prestressed unit in-place.
END OF SECTION 34 80 43
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
1. 303, Code of Standard Practice for Steel Buildings and Bridges dated
March, 2005.
3. A53, Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-
Coated, Welded and Seamless.
4. A153, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
5. A307, Standard Specifications for Carbon Steel Bolts and Studs, 60,000
psi Tensile Strength.
12. F1554, Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi
Yield Strength.
1. A5.1, Specification for Carbon Steel Electrodes for Shielded Metal Arc
Welding.
2. A5.5, Specification for Low-Alloy Steel Electrodes for Shielded Metal Arc
Welding.
4. A5.18, Specification for Carbon Steel Electrodes and Rods for Gas
Shielded Arc Welding.
6. A5.28, Specification for Low-Alloy Steel Electrodes and Rods for Gas
Shielded Arc Welding.
1.03 SUBMITTALS
A. Shop Drawings:
b. Complete Shop Drawings for all of the work showing clearly all
pieces, sizes, dimensions, details, connections materials and shop
coatings.
4. Certifications:
5. Test reports:
c. Testing agency inspection and test reports for structural steel work
in the shop and in the field.
A. Qualifications:
1. Steel fabricator:
2. Steel erector:
A. Handle and store steel members above ground on skids or other supports.
1. Keep free of dirt and other foreign material and protect against corrosion.
1.06 DEFINITION
A. Code: AISC 303, Code of Standard Practice for Steel Buildings and Bridges.
C. Galvanizing: Hot-dipped galvanizing per ASTM A153 with minimum coating of 2.0
oz of zinc per square foot of metal (average of specimens) unless noted otherwise
or dictated by standard.
PART 2 - PRODUCTS
1. High-strength bolts:
c. Nucor Fasteners.
2.02 MATERIALS
E. High-Strength Bolts, Nuts and Washers, ASTM A325 with ASTM A563 nuts:
1. High-strength bolts:
c. Type to match.
3. Gas metal arc: AWS A5.18, E70S-X or E70U-1 or AWS A5.28, ER805-XX,
E80C-XXX.
2.03 FABRICATION
D. Field Connections: Provide bolts for all field connections except where shown
otherwise on the Plans.
2. If structural steel details shown on design Plans are not compatible with
selected erection procedures, submit proposed modifications for review.
E. Cut, drill, or punch holes in accordance with AREMA Section 15.3.2.6 and AREMA
Section 15.3.2.7.
H. Flame cut bevels for welds, provided such cutting is done automatically.
1. Leave free of burrs and slag by grinding or planing the cut edges.
I. Grind smooth all rough welds and sharp steel edges shall be ground to
approximately 1/8” radius.
1. ASTM A6: When material received from the mill does not satisfy ASTM A6
tolerances for camber, profile, flatness or sweep, the Contractor is
permitted to perform corrective work by the use of controlled heating, and
mechanical straightening, subject to the limitations of the AISC
Specification.
2. Fabrication tolerance:
a. Member length:
b. Member straightness:
e. Finished members shall be free from twists, bends and open joints.
2.04 WELDING
A. Comply with AREMA Chapter 15, AWS Code, and other requirements indicated
herein, for all welding, techniques of welding employed, appearance and quality of
welds, and methods used to correct defective work.
B. Test and qualify welders, welding operators and tackers in compliance with AWS
Code for position and type of welding to which they will be assigned.
3. Comply with Section 3 of AWS Code for assembly and surface preparation.
F. Where groove welds have back-up plates, make first three (3) passes with 1/8”
round electrodes.
1. Do not shear.
H. Grind flush web fillets at webs notched to receive backup plates for flange groove
welds.
I. Low Hydrogen Electrodes: Dry and store electrodes in compliance with AWS
Code.
1. Testing:
1. Inspect shop and field welding in accordance with AREMA Section 15.3.5.5
including the following non-destructive testing:
C. All spans shall be shop-assembled and piece marked. During assembly and
reaming, all bolts shall be placed in holes as work progresses to assure proper fit.
Spans may be disassembled prior to shipping.
PART 3 - EXECUTION
3.01 GENERAL
3. Until all elements of the permanent structure and lateral bracing system are
complete, provide temporary bracing designed, furnished, and installed by
the Contractor for the partially complete structure.
B. Adequate temporary bracing to provide safety, stability and to resist all loads to
which the partially complete structure may be subjected, including wind,
construction activities, and operation of equipment is the responsibility of the
Contractor.
2. Use temporary guys, bracing, shoring, and other work to prevent injury or
damage to adjacent work or construction from stresses due to erection
procedures and operation of erection equipment, construction loads, and
wind.
D. Field Measurement:
E. Check the elevations of all finished pier caps and the location and alignment of all
anchor bolts and bolt holes before starting erection.
3.02 ERECTION
B. Welding:
D. Clean stored material of all foreign matter accumulated during erection period.
F. Anchor Bolts:
a. If anchor bolts are to be grouted into the holes prior to the placement
of the span, location tolerance of the anchor bolts shall be 1/8”.
a. If anchor bolts are to be grouted into the holes prior to the placement
of the span, location tolerance of the anchor bolts shall be 1/8”.
I. Prior to making field connections to existing structural steel, remove completely all
paint from existing steel which will be in contact with new steel and new welds.
K. Provide beveled washers to give full bearing to bolt head or nut where bolts are to
be used on surfaces having slopes greater than 1 in 20 with a plane normal to bolt
axis.
L. After bolts are tightened, upset threads of A307 unfinished bolts and anchor bolts
to prevent nuts from backing off.
M. After erection, grind smooth all sharp surface irregularities resulting from field
cutting or welding; power tool clean welds, bolts, washers and abrasions to shop
coat removing all rust and foreign matter.
A. After erection, clean all steel of mud or other foreign materials, and repair any
damage.
4.01 MEASUREMENT
A. Structural Steel will be measured by the unit or fraction thereof furnished and
completed in accordance with the Contract Documents and as measured by the
Engineer. The quantities as contained on the Schedule of Quantities and Prices,
or approved schedule of values, as applicable, as derived from the Plans will be
used as the basis for this measurement.
B. Structural steel for use in bridge structures will be measured by the unit computed
by the Engineer from the nominal weight and dimensions shown on the Plans.
1. The weight of rolled shapes and structural plates will be computed on the
basis of their nominal weight and dimensions, without deductions for copes,
cuts, and holes.
4.02 PAYMENT
B. Structural steel for use in bridge structures will be paid for furnishing structural
steel and erecting structural steel complete in-place.
1. The contract price paid for structural steel shall include full compensation
for furnishing all labor, materials, tools, equipment and incidentals, and for
all work involved in constructing, furnishing, transporting, handling, and
erecting units in-place as shown on the Plans, as specified in these
Specifications and as directed by the Engineer.
2. The contract price paid structural steel shall include, but shall not be limited
to, furnishing all bolts, nuts and washers, stud connectors, welding
materials, bearing plates and pads, or other materials required for the
erection and connection or splicing of the structural steel, finishing the
structural steel as required by these Specifications and the Plans, and
conforming to the qualification and testing requirements associated with
member fabrication.
3. The contract price paid for structural steel shall include, but shall not be
limited to, connecting and splicing the structural steel, installing stud
connectors, installing bearing plates and pads, furnishing and applying
caulk, sealants and fillers, furnishing and placing mortar or grout for
masonry or bearing plates and anchor bolts, checking bolt tension, and
conforming to qualification and testing requirements associated with
member erection, connection or splicing.
4. The contract price paid for structural steel shall include, but shall not be
limited to, full compensation for furnishing all labor, materials, tools,
equipment, and incidentals, and for doing all the work involved in cleaning
and applying paint and protective coatings (non-metallic) and metallic
coatings to structural steel as shown on the Plans, and as specified in these
Specifications and as specified by the Engineer.
END OF SECTION 34 80 51
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
3. A53, Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-
Coated, Welded and Seamless.
5. A153, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
7. A307, Standard Specification for Carbon Steel Bolts and Studs, 60,000 PSI
Tensile Strength.
12. A668, Standard Specification for Steel Forgings, Carbon and Alloy, for
General Industrial Use.
13. A780, Standard Practice for Repair of Damaged and Uncoated Areas of
Hot-Dip Galvanized Coatings.
18. F1554, Standard Specification for Anchor Bolts, Steel, 36, 55, and 105-ksi
Yield Strength.
D. Military Specifications:
1. MIL-N-25027, Nut, Self Locking, Heavy hex, (Non-Metallic Insert) 250º and
450º F, UNJC-3B, ¼” Through 2-1/2” Nominal Diameters, Nickel-Copper
Alloy.
1.03 DEFINITIONS
A. Installer or Applicator:
C. Galvanizing: Hot-dip galvanizing per ASTM A123 or ASTM A153 with minimum
coating of 2.0 oz of zinc per square foot of metal (average of specimens) unless
noted otherwise or dictated by standard.
1.04 SUBMITTALS
A. Shop Drawings:
B. Miscellaneous Submittals:
A. Qualifications:
B. Store above ground on skids or other supports to keep items free of dirt and other
foreign debris and to protect against corrosion.
PART 2 - PRODUCTS
a. Hilti Inc.
c. Simpson Strongtie.
a. Hilti Inc.
c. Simpson Strongtie.
a. ZRC Products.
2.02 MATERIALS
A. Steel:
1. Structural:
b. Plates and other rolled sections not specified above: ASTM A36.
3. Structural tubing:
a. ASTM A588.
b. Provide one (1) spring lock washer and two (2) plain washers with
all bolts.
B. Stainless Steel:
c. Strip, plate and flat bars: ASTM A666, Type 304 or 316, Grade A.
a. Strip, plate and flat bar for welded connections, ASTM A666, Type
304L.
3. Welding electrodes: In accordance with AWS for metal alloy being welded.
C. Washers: Same material and alloy as found in accompanying bolts and nuts.
1. Type 304 or 316 stainless steel with two (2) matching nuts and matching
washer.
2. Machine bolts with two (2) matching nuts and matching washer.
F. Deformed Anchors Rods: ASTM F1554, Grade 36 with a minimum yield strength
of 36,000 psi and a minimum tensile strength of 58,000 psi.
G. Saddle Clips:
H. Steel:
I. Steel Hardware: Galvanized in accordance with ASTM A153 or ASTM B695 when
required to be galvanized.
1. High zinc dust content paint for regalvanizing welds and abrasions.
2. Dried film shall contain not less than 93 percent zinc dust by weight.
B. Steel Grating:
1. Bearing bars:
2. Cross bars:
b. Maximum 4 IN OC spacing.
4. Removable grating sections: Not wider than 3 feet and not more than
100 lbs unless shown otherwise on Plans.
5. Finish:
a. Galvanized.
2.04 FABRICATION
B. Form materials to shapes indicated with straight lines, true angles, and smooth
curves.
1. Punch or drill for field connections and for attachment of work by other
trades.
2. Weld structural steel in accordance with AWS D1.1 using Series E70
electrodes conforming to AWS A5.1.
F. Tolerances:
1. Rolling:
a. ASTM A6.
b. When material received from the mill does not satisfy ASTM A6
tolerances for camber, profile, flatness, or sweep, the Contractor is
permitted to perform corrective work by the use of controlled
heating and mechanical straightening, subject to the limitations of
the AISC Specifications.
2. Fabrication tolerance:
a. Member length:
2) Framed members:
b. Member straightness:
d. Finished members shall be free from twists, bends and open joints.
G. Fabricate grating, checkered plate, and accessories using galvanized steel unless
shown otherwise on Plans.
A. Surface Preparation:
1. Inspect shop and field welding in accordance with AWS Code, Section 6
including the following non-destructive testing:
1. During assembly and reaming, all bolts shall be placed in holes as work
progresses to assure proper fit.
PART 3 - EXECUTION
3.01 PREPARATION
A. Provide items to be built into other construction in time to allow their installation.
1. If such items are not provided in time for installation, cut in and install.
3.02 INSTALLATION
B. Adequate temporary bracing to provide safety, stability and to resist all loads to
which the partially complete structure may be subjected, including construction
activities and operation of equipment is the responsibility of the Contractor.
3. Use temporary guys, bracing, shoring, and other work to prevent injury or
damage to adjacent work or construction from stresses due to erection
procedures and operation of erection equipment, construction loads, and
wind.
D. Field Measurement:
E. Check the elevations of all finished pier caps and the location and alignment of all
anchor bolts and bolt holes before starting erection.
G. Welding:
I. Clean stored material of all foreign matter accumulated during erection period.
L. Remove all burrs and radius all sharp edges and corners of miscellaneous plates,
angles, framing system elements, etc.
N. Install and tighten ASTM A325 high-strength bolts in accordance with the AISC
Manual of Steel Construction.
a. Provide the hardened washer under the element (nut or bolt head)
turned in tightening.
O. After bolts are tightened, upset threads of ASTM A307 unfinished bolts or anchor
bolts to prevent nuts from backing off.
P. Secure metal to wood with lag screws of adequate size with appropriate washers.
Q. Do not field splice fabricated items unless said items exceed standard shipping
length or change of direction requires splicing.
S. Anchor such that work will not be distorted nor fasteners overstressed from
expansion and contraction.
3.03 CLEANING
4.01 MEASUREMENT
A. Metal fabrications for use in bridge structures will be measured by the unit or
fraction thereof furnished and completed in accordance with the Contract
Documents and as measured by the Engineer. The quantities as contained on the
Schedule of Quantities and Prices, or approved schedule of values, as applicable,
as derived from the Plans will be used as the basis for this measurement.
4.02 PAYMENT
doing all work, as shown on the Plans, and as specified in these Specifications,
and as directed by the Engineer.
B. Metal fabrications for use in bridge structures will be paid at the Contract Unit Price
for furnishing metal fabrications and erecting metal fabrications complete in-place.
1. The contract price paid for metal fabrications shall include full
compensation for furnishing all labor, materials, tools, equipment and
incidentals, and for all work involved in constructing, furnishing,
transporting, handling, and erecting units in-place as shown on the Plans,
as specified in these Specifications and as directed by the Engineer.
2. The contract price paid for metal fabrications shall include, but shall not be
limited to, furnishing all bolts, nuts and washers, stud connectors, welding
materials, or other materials required for the erection and connection or
splicing of the metal fabrications, finishing the metal fabrications as
required by these Specifications and the Plans, and conforming to the
qualification and testing requirements associated with member fabrication.
3. The contract price paid for metal fabrications shall include, but shall not be
limited to, connecting and splicing the metal fabrications, installing stud
connectors, furnishing and applying caulk, sealants and fillers, furnishing
and placing mortar or grout for masonry or bearing plates and anchor bolts,
checking bolt tension, and conforming to qualification and testing
requirements associated with member erection, connection or splicing.
4. The contract price paid for metal fabrications shall include, but shall not be
limited to, full compensation for furnishing all labor, materials, tools,
equipment, and incidentals, and for doing all the work involved in cleaning
and applying paint and protective coatings (non-metallic) and metallic
coatings to metal fabrications as shown on the Plans, and as specified in
these Specifications and as specified by the Engineer.
END OF SECTION 34 80 52
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
1.02 REFERENCES
2. A53, Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-
Coated, Welded and Seamless.
4. A153, Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
5. A307, Standard Specification for Carbon Steel Bolts and Studs, 60 000 PSI
Tensile Strength.
11. A1023, Standard Specification for Stranded Carbon Steel Wire Ropes for
General Purpose.
1.03 DEFINITIONS
B. Galvanizing: Hot-dip galvanizing per ASTM A123 or ASTM A153 with minimum
coating of 2.0 oz of zinc per square foot of metal (average of specimens) unless
noted otherwise or dictated by standard.
1.04 SUBMITTALS
A. Shop Drawings:
B. Miscellaneous Submittals:
3. Certification that railings have been designed and fabricated to meet the
loading requirements specified.
B. Store railings on skids, keep free of dirt and other foreign matter which will damage
railings or finish and protect from corrosion.
PART 2 - PRODUCTS
a. ZRC Products.
2.02 MATERIALS
2. Provide one (1) spring lock washer and two (2) plain washers with all bolts.
I. Steel Hardware: Galvanized in accordance with ASTM A153 or ASTM B695 when
required to be galvanized.
1. High zinc dust content paint for regalvanizing welds and abrasions.
2. Dried film shall contain not less than 95 percent zinc dust by weight.
L. Temporary Handrails:
2.03 FABRICATION
A. General:
2. For fabrication of items which will be exposed to view, use only materials
which are smooth and free of surface blemishes including pitting, seam
marks, roller marks, rolled trade names and roughness.
3. Form exposed work with smooth, short radius bends, accurate angles and
straight edges.
8. The ends of handrails shall not overhand terminal posts except where such
overhang does not constitute a projection hazard.
2. All exposed welds to be ground and buffed smooth and flush to match and
blend with adjoining surfaces.
D. Install weeps to drain moisture from hollow sections of railing at exterior locations
and in high humidity areas.
E. Expansion Joints:
3. Provide minimum 0.10 inches of expansion joint for each 20 feet length of
top rail for each 25˚ F differential between installation temperature and
maximum design temperature.
PART 3 - EXECUTION
3.01 PREPARATION
B. The top edge height of the top rail shall be 42 inches ±3 inches above the
walking/working surface.
C. At least two midrails shall be provided, evenly spaced between the walking/working
surface and the top rail.
3.03 INSTALLATION
B. Set work accurately in location, alignment and elevation; plumb, level, and true.
C. Align railings prior to securing in place to assure proper matching at butting and
expansion joints and correct alignment throughout their length.
1. Anchor handrail to concrete with ¾” heavy hex ASTM A307 bolt with
washer and heavy weight elastic locknut.
F. Anchor railings to metal structure with minimum 5/8” high strength steel bolts, nuts
and washers.
4.01 MEASUREMENT
A. Steel handrails for use in bridge structures will be measured by the unit or fraction
thereof furnished and completed in accordance with the Contract Documents and
as measured by the Engineer. The quantities as contained on the Schedule of
Quantities and Prices, or approved schedule of values, as applicable, as derived
from the Plans will be used as the basis for this measurement.
B. Steel handrails for use in bridge structures will be measured from end to end along
the face of the railing, including end and intermediate posts, and with no
deductions for gaps in railing for lighting and sign supports. The measurement
shall be made along the face of the rail elements without allowance for overlap at
rail splices.
4.02 PAYMENT
A. Steel handrails for use in bridge structures furnished and completed in accordance
with the Contract Documents will be paid for at the Contract Unit Price, as listed
on the Schedule of Quantities and Prices. This price shall include full
compensation for furnishing all labor, Materials, tools, equipment, supplies,
supervision, and incidentals, and doing all work, as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
B. Steel handrails for use in bridge structures will be paid at the Contract Unit Price
for furnishing steel handrails and erecting steel handrails complete in-place.
1. The contract price paid for steel handrails shall include, but shall not be
limited to, furnishing all bolts, nuts and washers, welding materials, or other
materials required for the erection and connection or splicing of the steel
handrails, finishing the steel handrails as required by these Specifications
and the Plans, and conforming to the qualification and testing requirements
associated with member fabrication.
2. The contract price paid for steel handrails shall include, but shall not be
limited to, connecting and splicing the steel handrails, installing end
treatments, anchor assemblies, and return and end caps, furnishing and
placing mortar or grout anchor bolts, checking bolt tension, and conforming
to qualification and testing requirements associated with member erection,
connection or splicing.
3. The contract price paid for steel handrails shall include, but shall not be
limited to, full compensation for furnishing all labor, materials, tools,
equipment, and incidentals, and for doing all the work involved in cleaning
and applying paint and protective coatings (non-metallic) and metallic
coatings to steel handrails as shown on the Plans, and as specified in these
Specifications and as specified by the Engineer.
END OF SECTION 34 80 53
PART 1 - GENERAL
1.01 SUMMARY
A. Section Includes:
2. Any other coating, thinner, accelerator, inhibitor, and any other material,
specified or required as part of a complete System specified in this
Specification Section.
B. Related Specification Sections include but are not necessarily limited to:
1.02 REFERENCES
A. Reference Standards:
b. SP 1, Solvent Cleaning.
B. Miscellaneous:
C. Deviation from specified mil thickness or product type is not allowed without written
authorization of Engineer.
1.03 DEFINITIONS
A. Installer or Applicator:
C. Corrosive Environment: Immersion in, or not more than 6 inches above, or subject
to condensation, spillage or splash of a corrosive material such as water,
wastewater, or chemical solution; or exposure to corrosive, caustic or acidic agent,
chemicals, chemical fumes, chemical mixture, or solutions with pH range of 5 to 9.
D. Highly Corrosive Environment: Immersion in, or not more than 6 inches above, or
subject to condensation, spillage or splash of a highly corrosive material such as
water, wastewater, or chemical solution; or exposure to highly corrosive, caustic
or acidic agent, chemicals, chemical fumes, chemical mixture, or solutions with pH
range below five (5) or above nine (9).
G. Immersion Surface:
2. Surface of any pipe, valve, or any other component of the piping system
subject to condensation including the pipe support system.
I. Surface Hidden from View: Surfaces such as those within pipe chases and
surfaces under overhanging walkways if over 5 feet above adjacent walking
surfaces
1.04 SUBMITTALS
A. Shop Drawings:
B. Samples:
C. Miscellaneous Submittals:
A. Qualifications:
4. Warning labels.
PART 2 - PRODUCTS
a. Tnemec.
b. Tiger DrylaC.
c. Sherwin Williams.
d. Diamond Vogel/Perdium.
e. International.
2. Graffiti-resistant coating:
a. Pro SoLo.
2.02 MATERIALS
1. P = prime coat.
2. F1, F2 . . . Fn = first finish coat, second finish coat . . . . nth finish coat, color
as selected by Engineer.
3. If two (2) finish coats of same material are required, Contractor may, at his
option and by written approval from paint manufacturer, apply one (1) coat
equal to mil thickness of two (2) coats specified.
1. Products of other listed manufacturers are acceptable for use providing the
product is of the same generic resin, requires comparable surface
preparation, has comparable application requirements, meets the same
VOC levels or better, provides the same finish and color options and will
withstand the atmospheric conditions of the location where it is to be
applied.
a. Prime coat:
b. Finish coat(s):
1) Interior:
2) Exterior:
a. Prime coat:
b. Finish coat(s):
1) Interior:
2) Exterior:
a. Prime coat:
b. Finish coat(s):
1) Interior:
2) Exterior:
a. Prime coat:
b. Finish coat(s):
1) Interior:
2) Exterior:
a. Prime coat:
b. Finish coat(s):
1) Interior:
2) Exterior:
a. Prime coat:
a. Prime coat:
a. Prime coat:
b. Finish coat:
1) Exterior:
a. Prime coat:
b. Finish coat(s):
1) Exterior:
a. Prime coat:
a. Prime coat:
12. HPIC SYSTEM #12 - Waterborne Acrylic Emulsion Prime and Top Coats.
a. Prime coat:
b. Finish coat:
1) Exterior:
a. Patching/filling coat:
b. Finish coat:
1) Interior:
14. HPIC SYSTEM #14 - Waterborne Vinyl Acrylic Primer with Water-base
Acrylic-Emulsion Top Coat.
a. Prime coat(s):
b. Finish coat(s):
a. Prime coat:
b. Slip resistance:
c. Finish coat:
16. HPIC SYSTEM #16 - Polyamine Novolac Epoxy Primer with Polyamine
Novolac Epoxy Top Coat.
a. Prime coat:
b. Finish coat:
a. Filler/surfacer coat:
b. Prime coat:
c. Finish coat:
18. SYSTEM #18 - Touch-up of galvanized surfaces not requiring a top coat.
a. Finish coat:
PART 3 - EXECUTION
1. Conduit, device boxes, junction boxes and covers, pull boxes and covers
and supports when attached to a surface required to be painted or to a
prefinished surface.
3. Structural steel.
A. General: Do not paint items listed in this Article unless specifically noted in the
Contract Documents to be painted.
B. Items with Approved Factory Finish: These items may require repair of damaged
painted areas or painting of welded connections.
C. Electrical Equipment:
D. When not in a corrosive or highly corrosive area, do not paint the following hidden
surfaces:
2. Conduit.
E. Other Items:
6. Metal soffit.
A. Concrete:
C. Steel:
1. Structural:
a. Exposed portion of pile plate, piling between the pile plates and
concrete collars or ground line, angle bracing and any other non-
galvanized exposed steel: SYSTEM #19.
1. Not for coating galvanized steel and products with approved factory
finishes.
E. Galvanized Metals:
1. Field touch-up where top coat is required: SYSTEM #2, prime and first
finish coat only.
G. Electrical Conduit:
I. Aluminum colored pipe thread touch-up, and aluminum colored finish where top
coat is not required: SYSTEM #11.
3.04 PREPARATION
A. General:
1. Verify that atmosphere in area where painting is to take place is within paint
manufacturer's acceptable temperature, humidity and sun exposure limits.
3. Remove all dust, grease, oil, compounds, dirt and other foreign matter
which would prevent bonding of coating to surface.
B. Protection:
C. Prepare and paint before assembly all surfaces which are inaccessible after
assembly.
D. Ferrous Metal:
a. Chip or grind off flux, spatter, slag or other laminations left from
welding.
5. All interior and exterior structural steel not included in corrosive, highly
corrosive or immersion service surfaces:
E. Hollow Metal:
F. Galvanized Metal:
G. Concrete:
2. Verify that concrete surfaces have been cleaned and that voids have been
patched in accordance with Specification Section 34 80 41 or Section 34
80 43.
4. Profile depth of blasted surface: Not less than 1 mil or greater than 2 mils
unless required otherwise by coating manufacturer.
5. Provide compressed air for blasting that is free of water and oil.
7. Protect nameplates and other items that may be damaged from blasting.
3.05 APPLICATION
A. General:
1. Thin, mix and apply coatings by brush, roller, or spray in accordance with
manufacturer's installation instructions.
3. Immediately after surface has been inspected apply structural steel and
miscellaneous steel prime coat in the factory.
8. Work each application of material into corners, crevices, joints, and other
difficult to work areas.
10. Smooth out runs or sags immediately, or remove and recoat entire surface.
12. Allow coated surfaces to cure prior to allowing traffic or other work to
proceed.
13. When coating rough surfaces which cannot be backrolled sufficiently, hand
brush coating to work into all recesses.
14. Backroll concrete and masonry surfaces with a roller if paint coatings are
spray applied.
6. Brush or spray bolts, welds, edges and difficult access areas with primer
prior to primer application over entire surface.
2. Touch up damaged finish coats using same application method and same
material specified for finish coat.
A. All accessible concrete, masonry, and porous surfaces from finish grade to 10 feet
above finish grade shall be painted with clear graffiti-resistant coating.
B. Surface Preparation:
C. Coating Preparations:
D. Application:
1. Test coating on each type of substrate for compatibility and desired results
before proceeding further.
2. Apply coating only under conditions that will ensure finishes free from
blemishes and defects.
a. Date, starting time, end time, and all breaks taken by painters.
1) Sky condition.
c. Air temperature.
d. Relative humidity.
1) Sky conditions.
D. Measure coating dry film thickness in accordance with SSPC PA 2 using Mikrotest
gage calibrated against NBS "Certified Coating Thickness Calibration Standards."
F. Measure substrate humidity with humidity gage specifically designed for such.
3.08 CLEANING
4.01 MEASUREMENT
Work of this Section is considered incidental to work under other payment items and no
separate measurement and payment will be made to the Contractor for Work of this
Section. Work of this section shall include furnishing all labor, materials, tools, equipment,
supplies, supervision, and incidentals, and doing all work, as shown on the Plans, and as
specified in these Specifications, and as directed by the Engineer.
END OF SECTION 34 80 61